government of himachal pradesh...himachal pradesh government has taken up an ambitious road...
TRANSCRIPT
E1540v 8
GOVERNMENT OF HIMACHAL PRADESH
PUBLIC WORKS DEPARTMENT
HIMACHAL PRADESH ROAD AND OTHERINFRASTRUCTURE DEVELOPMENT CORPORATION
(HPRIDC)
HIMACHAL PRADESH STATE ROADS PROJECT (HPSRP)
Contract No: HPSRP/WB/UG/4/ICB
Name of the Contract
WIDENING AND STRENGTHENING OFUNA-BARSAR-BHOTA-BHAM LA-KALKHAR ROAD
SECTION JAHU-KALKHAR
Environmental Management PlanVOL-2
FROM KM (90+000) TO KM (108+000)
fTHE LOUIS BERGER GROUP, INC.L 2300 N Street, NW Washington, D.C. 20037, USA
B Tel.: 202 331 777; Fax: 202 293 0787
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
TABLE OF CONTENTS
INTRODUCTION ................................. .................................................... 6
1.1 PROJECT BACKGROUND .......................................................... 6
1.2 FEASIBILITY STUDIES AND ALTERNATIVES ............................................ 7
1.2.1 FEAsIBLrry STUDIES ....................................... 7
1.2.2 ALTERNATIVES CONSIDERED ................................................................... .......... ... 7
1.3 DESIGN PROPOSALS ................................................ 8............
1.3.1.1 Proposed Cross Section Schedule ............................................... 8
1.3.1.2 Realignment Locations................................ .......... ........... 8
1.3.1.3 Retaining Wall Locations .................................................................. 9
1.3.1.4 Road Side Drainage ....................................................... 10
1.3.1.5 Rain Shelter & Bus Bay ..................................................... 111.3.1.6 Major Intersections ...................................................... . 11
1.3.1.7 Minor Intersections /Access Roads: ......................................................... 11
1.3.2 PROP SEDIMPROVEMENTSOFTHEPROJECTROAD.................................................................................................................19
1.4 ENVIRONMENTAL ASSESSMENT ................................................... 19
1.5 SCOPE AND OBJECTIVES ........................................................ 19
1.5.1 ENVIRONMENTAL mGATION AND ENHANCEMENT MEASURES.................................................... 20
1.6 CLEARANCES REQUIRED FOR THE PROJECT .................................... ..... 20
TABLE 1.11: ENVIRONMENTAL APPROVALS AND CLEARANCES REQUIRED PRIOR TO CONSTRUCTION PHASE .......... 20
2 BASELINE DATA AND SUMMARY OF IMPACTS ........................................... 23
2.1 PHYSICAL ENVIRONMENT .......................................................................... 25
2.1.1 AiR EN ROMENT ................................................................................ 25
2.1.2 NOSE ENVIRONMEN..............................................................................252.1.3 WATER ENRONMENT .............................................................................25
2.1.4 GEOLOGY AND MATERIAL SOURCES ..................................................................... 25
2.2 BIo E NV IR O N M E N T ............................................................................... 26
2.2.1 FLORA........................................................................................26
2.2.2 FAUNA.......................................................................................26
2.3 SOCIO CULTURAL ENVIRONMENT ................................................... 26
2.3.1 RESELEMENT AND REHABIUTATON .................................................................................................. 27
2.3.2 CULTURAL PROPER ES ............................................................................ 27
2.3.2.1 Temples and shrines...................................................... 272.3.2.2 Archaeological structures................................................... 27
2.4 SAFETY AND HEALTH ASPECTS OF THE PROJECT ..................................... 27
2.4.1 ROAD SAFETY IN DESIGN......................................................................................................................................................... .27
2.4.2 HEALTH AND SAFElY MEASURES FOR WORKERS AND LABOURS ................................................... 7
2.4.3 TRAFFiC SAFElY PLANS ............................................................................ 27
2.4.4 HANDLNG OF ExPLOSVES ........................................................................... 28
2.4.5 HANDUNG OF PETROLEUM PRODucT S (POL) ..................................................28
3 MITIGATION MEASURES ............................................................ 29
4 ENVIRONMENTAL ENHANCEMENT MEASURES ........................................... 46
4.1 DISPLAY OF TOURIST LEVEL INFORMATION .......................................... 46
4.2 INTEGRATION OF VALLEY VIEW LOCATIONS .......................................... 46
4.3 ENHANCEMENT OF SAFETY FEATURES IN THE DESIGN (BUS BAYS, RAIN SHELTER AND PARKINGAREAS) ......................................................................... 46
4.3.1 SAFEIYENHANCEMENT-BULAYBYS ................................................................... 46
4.3.2 ENHANCEMENT OF RAIN SHELTERI BUS SHELTERS/BUS WAITING SHEDS ...........................47
4.3.3 ENHANCEMENT TO PARKING FACILITIES -TRUCK TAXI CARS AND BUS PARKING FACILITIES ................47
4.4 ENHANCEMENT OF CULTURAL PROPERTIES .......................................... 47
4.4.1 ARCHAEOLOGICAL STRUCTURES/CULTURAL PROPERlY AND MONUMENS ............................................ 47
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
4.5 COMMUNITY SPACE ............................................................. 47
4.5.1 PLANTING ALONG THE OXBOW LAND (LEFT OVER PORTION OF THE EXISTING ROAD) .................... 47
4.5.2 DEVELOPMENT OF REALIGNMENTS AND BRIDGE RELOCATION AREAS ............................. 47
5 MONITORING PROGRAMME .......................................................... 49
5.1 PERFORMANCE INDICATORS ........................................................................ 49
5.2 MONITORING PLAN FOR ENVIRONMENTAL CONDITIONS .................................................... 51
5.3 REPORTING SYSTEM .............................................................................. 53
6 INSTITUTIONAL ARRANGEMENTS ...................................................... 56
6.1 INTEGRATION OF EMP WITHIN THE PROJECT ........................................................... 58
7 TRAINING AND CAPACITYBUILDING PLAN .............................................. 59
8 ENVIRONMENTAL BUDGETARY PROVISIONS ............................................ 62
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDICES
APPENDIX 1: DETAIL OF THE TREES AFFECTED DUE TO PROPOSED PROJECT ROADS .............. 66APPENDIX 2: SUMMARY OF THE COMMUNITY PROPERTIES AFFECTED ........................... 69APPENDIX 3: LIST OF CULTURAL PROPERTIES AFFECTED .................................................................. 70APPENDIX 4: LOCATIONS OF BORROW AREAS FOR EARTH WORK ............................. 71APPENDIX 5: DETAILS OF THE SOURCE OF AGGREGATES AND LEAD DISTANCE ................... 72APPENDIX 6: SELECTION AND MANAGEMENT OF CONSTRUCTION CAMP ......................... 73APPENDIX 7: SILT TRAP ............................................................................................. 75APPENDIX 8: OIL INTERCEPTOR ........................................................................... 76APPENDIX 9: NOISE BARRIERS ......................................................... 77APPENDIX 10: LIST OF PERSONAL PROTECTIVE EQUIPMENT .............................................................. 78APPENDIX 11: LIST OF TRAFFIC SAFETY EQUIPMENT (GUIDELINE) ............................. 79APPENDIX 12: TREE PLANTATION STRATEGY .............................................. 80APPENDIX 13: NATIONAL STANDARD OF AIR, NOISE AND WATER ........................................................ 84APPENDIX 14: FORMATS FOR ENVIRONMENTAL MONITORING ............................................................. 86APPENDIX 15: EXAMPLES OF SOME GOOD PRACTICE IN TRAFFIC CONTROL & SAFETY DURINGCONSTRUCTION ........................................................................... 97
APPENDIX 16: GENERAL GUIDELINES FOR CONTRACTOR'S .................................... 99APPENDIX 17: GUIDELINES FOR THE PREPARATION OF CONTRACTORS ........................ 102APPENDIX 19: LIST OF ENHANCEMENT SITES ............................................. 108APPENDIX 20: SIGN/INFORMATION BOARDS FOR TOURISM ENHANCEMENT ...................... 109APPENDIX-21: MITIGATION & ENHANCEMENT DRAWINGS ................................... 112APPENDIX 22: LIST OF OXBOW LAND AND OTHER LEFT OVER LAND ........................... 113APPENDIX 23: POLICY GUIDELINES .................................................... 114
T -.. D- 0- - -1- * T. A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
LIST OF TABLES
S No. Tables
Table: 1.1 Details of Proposed Phase I, Batch 1 project Roads
Table: 1.2 Baseline details of the project corridor
Table: 1.3 Altematives consideredTable: 1.4 Economic Intemal Return (EIRR) and Net Present Value (NPV)
for the altematives considered
Table: 1.5 Proposed Cross Section
Table: 1.6 Realignment Locations
Table: 1.7 Brief Summary on Requirement of Retaining Wall
Table: 1.8 Proposed Covered Drain Locations with Side Walk
Table: 1.9 Rain shelter and Bus lay by locations
Table: 1.10 Major Intersections Along Jahu-Kalkhar Road Section
Table: 1.11 Environmental approvals and clearances required prior to constructon phase
Table: 1.12 Clearances required for the project
Table: 2.1 Summary of Environmental impact issues
Table 3.1 Environmental Management Action Plan (EMAP)
Table: 3.2 Details of Forest immediately adjacent /in PIA of the Jahu-Kalkhar Road.
Table: 5.1 Performance Indicators and Monitoring plan
Table: 5.2 Environmental monitoring for Air, water, noise and Soil
Table: 5.3 Reporting System
Table: 5.4 Summary Details of Reporting Formats
Table: 7.1 Environmental Management training programmes
Table: 8.1 Bill of Quantities Bill no 11- Environmental mitigation works
Bill of quantities for non civil works (forestry, tree plantation and environmental
Table:8.2 monitoring)
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
1 INTRODUCTION
1.1 PROJECT BACKGROUND
Himachal Pradesh Government has taken up an ambitious road development plan for the over all economic development of theState. In this context, GOI has approached World Bank for loan assistance to support the project. After all studies including theStrategic Option Study, Feasibility study and detailed engineering the World Bank has in principle agreed to support the projectprovided all WB loan conditional ties are fulfilled. The final approval of the loan is expected to take place in the mid 2007. TheSOS studies were confined to the restricted carriageway width, and /or pavement conditions which result in capacity constraintsfor the high volumes of traffic carried by the roads, and also the connectivity of the roads. Following this, the feasibility anddetailed engineering studies were taken up during the early part of 2006. Based on population distribution and other locationrelated criteria's, Government of Himachal Pradesh (GOHP) has identified 413km of project roads well in advance to meet therequirement of the State to implement the project in a phased manner.
The document in hand is the EMP for the contract of 18 km of the Batch 1 roads out of the 413 km of phase 1 roads identifiedearlier. All studies including feasibility studies, detailed engineering studies, environmental and social impact managementstudies have been completed. This document represents the Environmental Management Plan (EMP) prepared for the ContractNo 4 with the Contract identification no: HPSRPNWB/UG/4/ICB, to be implemented by the Contractor in association with the PWDand the appointed supervision consultant's for the smooth and effective implementation of the project. The appointment of theConstruction Supervision Consultants (CSC) will be according to the ICB contract implementation requirements and the countrylaws and the WB policies and guidelines. A location map of the project road is provided in the Figure 1l1and are to be completedby the March- April 2007.
FIGURE 1.1: LOCATION MAP OF THE PROJECT ROAD
or
4n KTable 1.1 provides the details of the 250 kms of Phase I, Batch 1 roads.
Table-.1:DetaisoftheP Phaw e, BatchI *ecRoads
2 Una- Aghar- Barsar 45.000 SH-32 5.53 Barsar-Jahu 45.000 SH-32 3 .54 Jahu-Kalkhar** 1.8.000 SH-32 3.55 Theog-Kothkhai-Hatkoti-Rohroo 80.684 SH-28 6.6 and 3.5** This document relates to this project road
As described earlier this Environmental Management Plan (EMP) relates to Contract package No: HPSRPIWB/UG/4/ICB,project road Jahu-Kalkhar is a part of the Una-Barsar-Jahu-Nerchowk road. It has a length of 18 kms.
DESCRIPTION OF THE PROJECT ROAD. Jahu-Kalkhar
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
This secton -Jahu-Kalkhar- is the part of the project road- Una- Aghar- Barsar- Jahu -Kalkhar*- Mandi, which starts at Jahu town
in an intersecton with Una-Amb road and ends at Nerchowk located at a road junction along National Highway (NH-20) well
connected to Mandi town 10 km away. This secton facilitates to materialise the link of two important towns of the HP viz., Una
and Mandi. The link between Mandi and Nerchowk is already there along the National Highway (NH 20). This road passes
through extensive forest areas.This section does not pass through any Notified eco-sensitive areas and the land requirement for widening is also minimal.
Therefore this project does not require environmental clearance (EC) form the Ministry of environment and Forest (MOEF),
Government of India. Nevertheless for the purpose of the analysis and for the documentation the general standards of MOEF
apply to this document also. This includes analysis of a 20 km corridor with the PIA of 10 km on either side of the centre line of
the project road.ROW available along this section varies between 11 m to 12 m. Most of this section is single lane with carriage way width less
than 3.5 m and the remaining length is of narrow 2-lane to intermediate lane width. Overall road condition is from fair to poor
condibon. At km 92 the crusher is located at left hand of side of road.
1.2 FEASIBILITY STUDIES AND ALTERNATIVES
1.2.1 FEASIBILITY STUDIES
The feasibility study has been carried out for the road network of 1675km of roads (43 road links) identified/suggested by the
earlier Strategic Option studies (SOS). The feasibility study has come out with a list of high priority roads based on the
engineering and economic aspects prepared using the HDM model. The Economic Internal Rate of Return (EIRR) has been
calculated using the model for each of the project roads. EIRR computed for the Jahu-Kalkhar (Una-Barsar-Nerchowk) project
road is 47 % and NPV cost is INR 8079 million. (?) The roads, which have a rate of return 12 % and above have been
considered, qualified for the up-gradation. The EIRR does not include a comprehensive environmental and social screening and
scoping analysis. Therefore prioritisation based on these issues has been carried out by the environmental and social screening
and scoping studies as a part of the feasibility studies. Specific details are provided in the table 1.2 baseline details of the project
corridor.
Table 1.2: Baseline details of the project corridor
2.4 Jahu to Bhamla Hilly Single Lane 2.000
2.5 Jahu-Kalkhar Bhamla to Hilly Single Lane 16.00
Kalkhar
1.2.2 ALTERNATIVES CONSIDERED
As far as the contract package is concerned the widening options were very limited as the entire corridor pass through mountain
systems surrounded by forest in most of the Project influenced areas. Widening towards valley side is almost impossible except
the alternatve option of having expensive viaducts. Because of the same reason, the viaducts initially considered in the project
were later dropped from further considerafion.
The project improvement alternatives are provided in Table 1.3.
Table 1.3: Alternatives considered
Project Alternative A Base Case (do-nothing/ do-minimum)
Project Alternative B Improvement Upgrading to Two Lane Standards (including investment on bridges)
Project Alternative C Improvement Upgrading to Two Lane Standards (excluding investment on bridges)
Project Alternative D Widening and Strengthening to Four Lane Standards
Project Alternative E Overlay of Existing Road
Table 1.4: Economic Internal Return (EIRR) and Net Present Value (NPV) for the alternatives considered
Jahu-KalkharAlternate B 47 8079
-7
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
The Alternative considered for Jahu-Kalkhar is B. The economic return is 47% and the Net Present Value is 8079 million rupees.
1.3 DESIGN PROPOSALS1.3.1.1 Proposed Cross Section Schedule
Subsequent to the completion of the alignment design, the cross sections were firmed up. In total, about 14 cross secdons havebeen formulated. While formulating these cross sections, the various variants that would represent the perspectives of existingpavement width, land use, geography and geology of along the project road was kept in mind. Details of use of various crosssection along the project road are furnished in cross section schedule in Drawing Volume. This cross section will have to bereviewed during the executon and necessary adjustments will be carried out as necessary. From the table it is clear that about1.9 km in the beginning is divided carriageway, out of the remaining length about 64 % of the length the Type 4 or Type 6 xsecdons were proposed. The full description of the design is given in the final design report.
Table 1.5: Proposed Cross Sections for Una- Nerchowk
1 10.52 2.33 9.24 40.4
5 16 35.27 18.5
9 2.3310 1.9Total 121.33
1.3.1 .2 Realignment Locations
Realignment Locatons: Generally the realignments were carried out very ever it is imperative that the geometric improvementwould not result in any loss of property or the approaches to the new bridges. Initially the consultants were proposed about 35 to40 locadons out of which only 9 locatons were retained keeping in view of constraints mentioned above. The final realignmentsamount for a length of 2.39 km. The following are the locations where the alignment was deviated from the exisdng road:
Table 1.6: Realignment Locations Jahu-Kalkhar
1 90.14 90.78 0.642 92.70 93.20 0.503 96.60 96.70 0.104 97.70 97.80 0.105 98.70 98.85 0.156 103.36 103.44 0.087 103.50 104.00 0.508 104.30 104.50 0.209 104.90 105.02 0.12
Total 2.39
r Nlli RPrnft .triXrTClP r TC A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
1.3.1 .3 Retaining Wall Locations
Based on the designed alignment and on the basis of the topographic surveys results, the location where the normal fill slopes
cannot be used due to the topographic conditons, consultants have adopted the retaining wall. Stone Masonry with Plum
concrete was used for the construction of retaining wall. Detailed schedule of the retaining wall, which is established from the
superimposition of existing cross sections with design cross sections, is provided in Drawing Volume. The table 1.7 illustrates
brief summary on the basis of incidence of length requiring the protecton structures.
Table 1.7: Brief Summaries on Requirement of Retaining Wall
Schedule of Retaining Walls
S. No. Design Chainage Average LengthStart End Height (m) (m)
1 92.790 92.830 10.05 40
2 92.790 92.830 8.34 40
3 94.240 94.340 3.22 100
4 94.420 94.500 2.71 80
5 94.700 94.800 4.21 100
6 94.860 94.900 1.33 40
7 95.340 95.400 1.00 60
8 95.440 95.460 1.90 20
9 95.780 95.800 1.00 20
10 95.860 95.880 1.63 20
11 96.080 96.09 1.28 10
12 96.480 96.520 1.03 40
13 97.780 97.800 3.48 20
14 98.860 98.900 1.00 40
15 99.000 99.040 1.70 40
16 99.140 99.15 1.00 10
17 99.300 99.31 1.48 10
18 99.340 99.360 1.01 20
19 99.620 99.660 1.34 40
20 99.780 99.800 2.15 20
21 100.020 100.03 1.00 10
22 100.960 100.97 4.61 10
23 101.060 101.100 1.18 40
24 101.200 101.220 1.06 20
25 101.300 101.320 1.00 20
26 101.500 101.520 1.13 20
27 101.580 101.600 3.94 20
28 101.780 101.79 1.00 10
29 101.900 101.920 1.00 20
30 102.010 102.02 1.00 10
31 102.060 102.080 1.00 20
32 102.220 102.260 2.34 40
33 102.440 102.460 1.30 20
34 102.620 102.640 2.31 20
35 102.880 102.940 1.00 60
36 102.980 103.000 1.54 20
37 103.080 103.100 2.75 20
38 103.140 103.180 1.74 40
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
39 103.360 103.37 6.35 1040 103.460 103.480 1.43 2041 103.560 103.580 1.28 2042 103.640 103.680 2.44 4043 103,720 103.760 3.08 4044 103,980 104.020 1.12 4045 104.220 104.300 1.67 8046 104.600 104.620 1.08 2047 104.700 104.71 2.86 1048 105.700 105.71 1.00 1049 105.740 105.75 2.50 1050 105.780 105.840 2.30 6051 106.060 106.070 3.94 1052 106.100 106.110 1.00 1053 106.300 106.310 1.00 1054 106.360 106.420 1.84 6055 106.580 106.590 2.96 1056 106.660 106.720 2.99 6057 106.860 106.870 3.11 1058 106.920 106.980 1.00 6059 107.120 107.130 2.12 1060 107.840 107.850 1.90 1061 108.060 108.080 2.41 2062 108.260 108.270 1.17 1063 108.440 108.460 1.68 2064 108.600 108.680 1.97 8065 108.67 108.71 5.50 4066 108.73 108.77 6.50 40
Length (m) 4580
1.3.1.4 Road Side Drainage
The road side drainage is ensured by adopfing one of the three forms. These are decided keeping in view the land use along thecorridors, economical aspects with respect to the over all project cost. The three types of drain that are being provided under heproject are:
Trapezoidal Drain: This drain section is used in plain and or flat areas where the embankment heights are shallow. This drain isnormally unlined and would require regular maintenance by means of cleaning regularly.
V-Shaped Drain: This drain is provided normally in the cut slopes located in hilly and rolling terrain, this drain is lined in nature.Predominant lengths in hilly areas are provided with this type.
Covered Drain: Locations in built up areas, and those with pedestrian movement covered drain with sidewalk is being proposed.In the locations where the drains out lets are not available, covered footpath with sidewalk is proposed. In total 1 location alongthe 18 km long road covered drain of 1.50 km length is being provided. As per the requirement it is provided on one side or bothsides of the cross section.
Table 1.8: Proposed Covered Drain Locations with Side Walk
1 91.00 I 92.50 1.50Total 1.50
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
1.3.1.5 Rain Shelter & Bus Bay
Based on the details of the existing bus shelter locations and the basis of consultations carried out by both social and
environmental teams, consultants have prepared detailed schedule for the rain shelter & bus bay. An attempt was made to
provide the bus shelter on either side; of the centre line so that weaving of the vehicles using the bus shelter would not impinge
on the free and safe movement of the traffic. However, due to restriction in site condition either due to heavily built-up or
topography there are instances where this facility is provided only on one side. It may happen at locations there may not be
enough space to build the Rain Shelter due to available width and the permanent structures in such cases only bus bay is
provided. A detailed schedule is provided in the Drawing Volume. The brief summary of the facility is provided in Table 1.9.
Table 1.9: Rain shelter and bus bay locations
93.29 RHS
94.79 LHS98.69 RHS
100.69 RHSTotal 4
1.3.1.6 Major Intersections
Consultants have surveyed the major intersections along the project road section. In order to assess the requirements for type of
improvement, turning movement surveys were carried at important junction locations. From the analysis of the turning movement
survey none of the junctions would require grade separation or traffic signals for controlling traffic. However, consultants have
developed the layout for all the major intersections in accordance with the IRC guidelines. There are 12 major intersections out of
which two of three of them are with National Highways, remaining are with State and District Roads. The major intersection at
Bhambla with Joginder nagar Ghumarwin will be designed as part of the design for Joginder nagar Ghumarwin Road. The details
of major intersections along the project road are as given under, the lay out plans for each of them are provided in Drawing
Volume.
Table 1.10 Major intersections along Jahu-Kalkhar road section
NO Intersection
1.3.1.7 Minor Intersections /Access Roads:
In addition to the above the consultants have surveyed the cross roads that abut the project road as part of the topographic
survey. These roads will have to be improved to establish the connectivity to the project road after the upgrading and
improvement works is completed. Various treatments to these minor intersections or access have been formulated. Depending
on the configuration and category of road the access treatments were suggested and are fumished in the Drawing Volume. The
brief summary of the access treatment along the road are provided in table no 1.11
Table 1.11 Brief summary of access treatment along the roads
11 |3 3 |1 |7 11ll
11
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
There are fourteen typical design cross sections as shown in Figures 1.2 to 1.15. These cross sections are
FIGURES 1.2 TO 1.15: TYPES OF DESIGN CROSS SECTIONS (TYPE I TO TYPE 14)
TYPE 1
-- -L I
TPE2
n.Tar TTC A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
IAN
*w
10X Ur W IN W -+ D W
t-,l,~~~- - - - - -E- -a- -,tSF
TYPE 3
05001 -LOOEII U many
TYPE3
1YPE5
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
1500
# I
DCDUNww.
I1000 \3500 13
150050~
X~~~ -ll, -e ---- -- --
a I;^o,,,M-.
TYPEa4c 6E5r e //
N01E- AU DWENWINS ME IM N= DIU EIDSSOlE NlK1D WALL
BC
GSBM
01w"*
SUGM IN FILL0\350035 0 1000 150w
NOTE- ALL DUENSDI ARE IN MM UNLESS OTHERtWIS "00 TYPE
Jr JT I= =1 NR
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
# "
MO
CUTC
Do
IOD \30
N g 00 350 r 310 - lOwl
-on
- -- 1 - -- - sX 3
1 1 2rz
--
NOTYPE AL DIDWAEI MULS nM BW Y
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
P.CC THICK I
BCD8M
1000 3500 3600 1000 FiRFED ROCKFACEROW 3500
TOEWALL
TYPEIO
1500 "
5T# I \
DBM
J TYPE 11
SUBGR. X -IN FILL
- -14 0 O - - 3N - - - -.. . . . .
----- ------
TYPE 11
I nl)iQ Rer, T Cr lsr. I\PT TQ A
|§ | {
20
} E ! 2
-t
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
.4- _X
T-l T T1E1
T AlMCs T2 TliI-r TSC'
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
1.3.2 PROPOSED IMPROVEMENTS OF THE PROJECT ROAD
Less than 10% of the State roads are double laned, only 50% of the road length has drainage and valley side safety measures.
Depending on the present condition of the selected roads, different levels of improvement up gradation measures will be
required for different road stretches. The improvement works will mainly consists of
* Cutting of hill ward side for widening* Raising the formation level where ever required
* Upgrading/ improving road geometric* Widening to two-lane/ intermediate lane from existing intermediate-lane/ single-lane widths
* Pavement strengthening, and* Improving cross drainage* Stabilization of the hill slope as far as possible by breast walls, retaining walls and or bio engineering techniques
* Road stretches crossing urban areas may also require alternative new alignments or realignments, or provision for
drains, sidewalks and parking along existing road.
* Construction of bridges and their approach roads
* River training works* Pedestrian Guard rails and safety barriers
* Replacement of culverts and construction of new culverts:
* The replacement / rehabilitating of culverts will accommodate two full lanes for the full formation width.
. Realignments* Construction of viaducts
A total of 2.39 km of realignments has been considered in the project (Table 1.6) to improve safety. Including this 2.93 km of
realignment there are 9 locations (Appendix- 22) where in the project road widening has shifted to either Right hand side or Left
hand side leaving oxbow land (left over land portions) in all these locations. Several environmental enhancement proposals have
been recommended at these locations.* Road safety measures, Rain shelters (bus waiting shed) and Parking Area
* Vehicle parking areas may be provided wherever there is a space available away from junctions and pedestrian
crossings. Wherever possible, the provisions of bus lay bys have been included in the design.
* Implementation of a Resettlement Action Plan (RAP)
This is prepared as a separately bound volume. The RAP has elaborate implementation arrangements including the services of
NGOs.
1.4 ENVIRONMENTAL ASSESSMENT
The Environmental and social screening Reports (ESR) has confirmed the environmental sensitivity more specifically ecological
sensitivity of the project road under consideration. The study has established the boundaries of the further studies required
(scoping) based on the proximity to ecologically sensitive and environmental sensitive areas. Accordingly Jahu-Kalkhar project
road considered in this report (Vol 2 -EMP) and a separately bound Vol 1 EA (EIA = EA+EMP, where EA and EMP are separate
volumes) for widening and up-gradation doesn't require GOI environmental clearance. The Project has to obtain State level
clearance from the State Pollution Control Board (PCB). Because of the World Bank's categorization as Category A projects, EIA
is also required to meet the WBs safe guard policies.
1.5 SCOPE AND OBJECTIVES
The project aims to achieve high standard with required cost effectiveness, coupled with necessary environmental management
standards for achieving sustainable development in the State. Therefore the objectives of the project can be stated as to alleviate
the current unsafe and congested conditions of the project roads connecting the villages and towns with one another and to the
NH network for the benefit of the road users at large. To achieve the environmental management standards, contract wise EMPs
are being prepared for sub projects. Jahu-Kalkhar project road having a length of 18 kms has been taken as a single Contract
package for International Competitive Bidding. This has been prepared and incorporated in the bidding/contract documents. The
EMP has been prepared as per the requirements of World Bank OP 4.01- Annex C. The entire project with all the sub projects is
categorized as Category A by the World Bank, where as the sub projects has been individually classified as Category A and
category B by the GOls latest gazette notification of September 14 this year (2006).
'A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
1.5.1 ENVIRONMENTAL MITIGATION AND ENHANCEMENT MEASURES
Mitigation measures have been devised in such a way that the Contractor would be able to locate the location and chainage ofthe mitigafion measures accurately. All studies relating to the project has finally come out with an implementable environmentalmitigation & enhancement plans. This plan has been recommended for feasible and cost-effective measures to avoid, prevent orreduce significant negative impacts to acceptable levels. Apart from mitigation of the potential adverse impacts on theenvironmental components, the EMP identified opportunities that exist for the enhancement of the environmental quality alongthe corridor. This also includes the enhancement of specific enhancement of cultural properties along the corridor; some roaduser facilities such as bus lay bys and waiting sheds (part of civil work) and parking areas. EMP included management andredevelopment of destabilized slopes especially by including a pilot slope stabilization initiative viz., bioengineering. In order toimplement the Environmental management plan Contractor need to prepare specific plans for the following;
* Debris (Muck) disposal plan (Includes collection, transportation haul roads and disposal)* Construction phase Water management plan
Management plan for Construction camps, Labour camps,Management plan for plant sites (WMM Plan, Hot mix, Crushers etc)Accidents, safety and Traffic Management plan.
* This should include how the contractor wanted to execute the excavab'on of the hill ward side for widening and howdoes it links to the debris disposal plan. Contractor need to specify the timings/effectiveness wanted to remove theexcavated material. What is the method of storing the material and the location of intending material storage place.This EMP provides guidelines for the preparaton of all such plans.
EMP includes detailed specifications, bill of quantities (BOQ), execution drawings and contracting procedures for execution ofthe environmental mifigaton and enhancement measures suggested. This is separately considered for pre-construction,construcUon and operational stages of the project. Since the project is to be implemented under ICB contracting, higheststandards of project planning, Project Management and project implementab'on are to maintain. Therefore the Contractor needsto resort to international good practices not only in the implementation of EMP but also in all construction activites. The successof the project management is directly linked to the effective implementation of the EMP measures. All miUgation measures,avoidance measures and environmental enhancement measures recommended are to be implemented in a bmely and phasedmanner. Proper understanding of all environmental management measures especially the EMAP is a pre-requisite for all thoseworking from the Contractor's side.
The institutional arrangements required at the PWD, Contractors and the CSC (supervision consultants) have been definedproperly for the smooth implementation of the project components. A positive attitude from the project management and theindividual professional or staffs are always a pre-requisite for success of the EMP implementafion.
The EMP specifies the environmental supervision, monitoring and auditing requirements. The monitoring programme specifyparameters, reference standards, monitoring method, frequency, duration, locabion, reporting responsibilities, and what otherinputs (e.g., training) are necessary. The EMAP on the other hand provides an action plan showing the mitigation measures timeof implementaton, who will implement, at what location and who will supervise etc. This is provided for pre-construction,construction and post construction stages. The EMP listed all mandatory government clearance conditions, and the status ofprocuring clearances.
1.6 CLEARANCES REQUIRED FOR THE PROJECT
The project road considered in this contract package will not have to obtain National Environmental clearance as it does not falls inthe ecologically sensitive area. The PIA (7 km X 7 km) has very less forest cover especially protected forests. Table 1.11 andTable 1.12 are the clearance requirement during the preconstruction and construction phases
TABLE 1.11: ENVIRONMENTAL APPROVALS AND CLEARANCES REQUIRED PRIOR TO CONSTRUCTION PHASE
Frest Yes for the Yes Frsclane, approval Approval as per OP No Noforest land fo odsd ree cutting 4.01,4.04,requirements an adrqirements
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Wildlife Yes Yes Clearance required Approval as per OP No No4.01,4.04
Environme Yes Yes No Approval as per OP No No
nt EIA/EMP 4.01required
Air/water/n No Yes, No Approval as per OP No No
oise Accordin 4.01
related g towater
noise &Air Act
Water No Yes No Approval as per OP Drinking water Yes
(impacts 4.01 resources/Water
as well as for construction,
construction
requirements)
Debris No Yes No Approval as per OP For
disposal 4.01 disposalsites
Land Yes Yes For Forest land Approval under OP No Yes
acquisiton (RAP required) 4.20 4.11 and 4.30 (e.g.
s and parking
rehabilitati areas)
on
Table 1.12: Clearances required for the project
1 Forestry clearance for cutting of trees Forestry department HPRIDC
2 Consent to Establish and Consent to HP- State Pollution Control Board Contractor
Operate
3 Permission to establish the HP-SPCB Contractor
construction camp, labour camp,WMM plant, Hot Mix plants,
4 Permission to establish Crushers, etc HP-SPCB and Industrial department Contractor(Basically permission from MiningGeology),
5 Permission for Withdrawal of Ground Irrigation department Contractor
water6 Permission for withdrawal of Surface Irrigation department Contractor
water7 Explosive licence for rock blasting for Forest department and explosive Contractor
widening towards hill ward side department at Chandigarh
8 Permission for Employing labour Labour department Contractor
9 PUC certificates for vehicles and Road transport Department Contractormachinery
10 License for setting up of diesel pumps Department of explosives and ContractorForest department
11 Registration of workers Executing agency for Building and Contractorother construction workers act
12 NOC for the overall activities HP-SPCB Contractor
91
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
13 Cnrlldba C rslnbatn onesutdeants etCnrcorocks in the forest areas14 Insurance coverage to all workers Public Works DepartmenV Contractor
Consultants
ILmniq Rerm-r f.-- In CA I TC A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
2 BASELINE DATA AND SUMMARY OF IMPACTS
The baseline environmental aspects and the project impacts during the various phases of the implementation are
provided. The table 2.1 provides a summary of the project impacts.
Table 2.1: Summa of Environmental impact issues:
Fauna NWildlife Waiting for the BIA studies that is Waiting for the BIA studies Waiting for the BIA studies
being undertaken nowFlora Do Do Do
Other Bio Do Do Do
diversity issuesTree removal 533 Trees will be impacted. Since A tree plantation programme has been After planting check its
the widening is mostly confined to prepared to implement. survival rate.the existing ROW, This is largelyunavoidable.
Erosion Identification of erodible soils and Slope protection measures identified Maintenance of all drainage
erosion prone areas. Treatment of and incorporated in the design and channels, and removal of all
embankment slopes, and treatment BOQ. And implementation of pilot bio possible erosion prone areas.
of stream inlets and outlets and pilot engineering measures at few pilot Addressing of the concerns
bio engineering measures locations. raised by the localcommunities
Debris disposal Debris disposal has been given A debris disposal plan will be prepared The disposed areas need to
adequate importance to the level it by the Contractor. be maintained by
requires. A number of disposal strengthening the vegetation
locations (2) has been identified in The excavated material during the hill over the disposed site. This
consultation with the local ward side widening would be safety required avoiding massive
communities. Guidelines for the stored, transported and disposed of erosion of the disposed
preparation of the Debris disposal the in identified debris disposal areas. materials especially when
plan prepared. located near the streams andrivers.
Cultural and 2 cultural properties will be Provide enhancement measures Other than the safety
Archaeological impacted. Local community according to the Cultural property monitoring no other action
sites and consultations, alignment changes to rehabilitation programme. would be required
properties minimize the impacts.
Demolition of All such unstable areas will be An effective sequencing of the
Retaining wall rehabilitated especially those in the construction work would be required
breast wall etc vicinity of the residential buildingsclose toStructuresespecially housesAir pollution Widening of the road with improved Siting of secondary work areas away Traffic emission control as
surface. from sensitive receptors. Along the per the legal requirements.
Smooth flow of traffic construction corriDors contractor shallresort to best practices to reduce air Regular air sampling andpollution. compare with the bench
marks established during theEIA preparation
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Nos plution Use best eqimet *and machineis MVonito noie leelsBaseline data monitored and for construction. Follow all procedures periodically to understand therecorded as a benchmark. as per the company norms. Use PPE deviation from the benchProvide noise barriers for sensitive wherever necessary. Siting of marksreceptors secondary work areas away from
sensitive receptors.
Water the use of potable water for dustsuppression should be reviewedregularly. Water sprinkling.
Site facilibes Contract Documents provide the Supervision consultants approve and No action requiredEnvironmental requirements check facilibes
Land The land requirement has been During implementabon the planned Need to monitor ribbonrequirements considerably reduced by proper requirements will be reviewed and developments. All newplanning to match the requirements implemented to the actual construction shall bewith in the ROW with minimum land requirement. Reinstate work areas on sufficiently way from theacquisition, realignments and completion of works project road edge.bypasses
Displacement of Minimized the displacement by RAP implementation to involve an Monitor and evaluate (M&E)PAPs proper planning in selectng the final NGO to ensure that the policies are the effectiveness of RAPalignment. Compensation provisions adhered to implementationas per the GOHP approved R&Rpolicy for the project
Road safety Design has incorporated all safety Implement a road safety, accidents Monitor and create a datameasures. and traffic management plan that has base for accidents along theProvide safety barriers at bridge been prepared and approved by the road with very specificapproaches, crash barriers at critical CSC details. As a follow up carrylocations, and included all safety out corrective measures toprovisions in the BOQ for lining and improve safety.signing
EA IEMP/ Prepared during this phase Shall use at this phase. Must keep one Shall review the effectivenessDocuments copy of the relevant Documents at this stagerequired at the including the Environmental clearancecontractors office Documents at the contractors project
site office under direct control of theProject Management
Aggregate and Use materials only from legitimate Use the excavated materials obtained No action requiredsand sources adhering to best practices. during widening as far as possible.Obtain all permissions andapprovals necessary. Conform to regulations
Borrow areas In addition to the excavated Open and close borrow areas No action requiredmaterials, Identified few more according to the borrow areaborrow areas for the Contractors management planuse
Land slide, land Construction scheduling has been Contractor needs to take extra care Maintain all road drainageslips, flash carried out by experienced during construction phase. Insurance through out the year.flooding and specialist. Detailed assessment of shall be extended to all labour forcedrainage bridges and culvert capacities. working at site to face any un
Replace under sized and damaged avoidable or accidental eventualities.bridges and culverts. Provide provide drainage during constructionadditional culverts and improve even for temporary diversions Keep all
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
0.
2.1 PHYSICAL ENVIRONMENT
The project road entirely within Mandi district and passes through hill ranges.
2.1.1 AIR ENVIRONMENT
Air quality is generally good. The dust prone areas require sprinkling of water for suppression of the dust. The Contractor will
partially inherit the problem from the previous Contractor unless other wise completed and stabilised. There are no polluting
industries in PIA or in the adjoining areas. The areas have thick vegetation for most of the length.
The air pollution during construction would be very high if not properly managed, particularly near the working zones,
construction plant sites and from the construction machinery and construction vehicles. The mitigation measures for the
avoidance and mitigation measures for controlling the air pollution are provided in table 3.1 Environmental management action
plan (EMAP). Due to an increase in the width of pavement and landscaping the dust levels created by traffic will decrease during
operational phase.
2.1.2 NOISE ENVIRONMENT
Ambient noise level is generally little of the order of 44 -59 dB (A). The natural sources of noise level are that of the prevailing
natural environment, natural forests and scattered settlements. The limited traffic plying along the project road also contributes to
the noise level.
The adverse impacts from the increase of noise during construction phase on the near by community will be reduced by several
construction phase mitigation plans. All possible mechanical and administrative controls will be practiced to reduce the adverse
impacts on the workers. In unavoidable situations personal protective equipments (PPE) will be provided to the workers based
on the nature of works.
Three numbers of sensitive receptors for the construction of noise barriers have been identified and the details are presented in
Appendix 9.0 and in design drawings in Appendix-21. These locations have been identified based on its proximity of the sensitive
receptors (schools and hospitals) to the road traffic and the absence of wall or the inadequate height of the existing walls.
Provision has been provided for additional barriers identified during construction phase. In all areas of identified noise barriers
public will be advised how the noise levels can be reduced by barriers such as solid walls and trees. The project does not
recommend expensive double glazed windows as an economically viable impact mitigation measure.
2.1.3 WATER ENVIRONMENT
The water environment is generally good. There is a slight increase of dissolved solids near kalkhar. All other water quality
parameters in this section is almost normal. The water quality of samples tested has been found good (Refer Vol 1 EA report).
Contractor needs to keep a copy of the Vol-1 EA and Vol-2 EMP in the contractor's site office. Other than the construction water
issue no major pollution points have been identified through out the length.. The construction vehicles are prohibited from
entering the riverbed for any purpose (including cleaning) other than any legitimate requirements. This is to avoid major pollution
points due to Petroleum oil and lubricants (POL).
The construction water requirement could be an issue during construction at certain stretches of the project road. As part of the
planning contractor is to prepare a contractors construction water management plan as per the guide lines provided in Appendix
16.
2.1.4 GEOLOGY AND MATERIAL SOURCES
Geologically the areas are not very stable and are seismically very active zone (zone IV and V) as per the Seismic zoning
classification of India. Slope stabilization measures are required to avoid major landslides. Land slips landslides mudflow and
other slope failures along the hill slopes are very common along the road. Details of the retaining wall locations have been
provide in Table 1.7 in section 1.3.1.3.
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
The material sources would be generally the materials obtained while widening (hill cuffing) the project road. Nevertheless as apre-requisite few quarries and borrow areas have been idenhfied and provided in Appendix- 4 and 5.
All borrow areas will be operated and redeveloped in accordance with the IRC 10:1961. MoRTH and applicable EMP clauses.Contractor may not require soils from borrow areas, as the hill ward side cuffing would be sufficient to meet the constructionrequirements. In case the Contractor find the qualities of the cut materials are not good for construction. Then other sources willhave to be explored. This is most unlikely as there would be many locations (in 18 km stretch) from which good quality materialsalso can be excavated. The soil found along the project road is shallow black brown and alluvial soils and other recently formedsoils.In addition to the above arrangements, Contractor will have to establish dedicated crushers units to generate adequate sand andaggregates so as to effectively utilise the excavated materials during widening.
2.2 BIO ENVIRONMENT
It has been identified that almost 60 -70 % of the PIA is Forest area. There are barren forest areas and dense green forest areas.
2.2.1 FLORAThe project location is in an area of highly diverse flora. There are many threatened plants in the endangered, criticallyendangered, threatened categories of flora in the region.
All forest patches that are abutting the project road are protected forests (PF). There are no Reserved Forests (RF) along thePIA. Details of some of the identified protected forests are provided in table 2.2
Table 2.2: Details of Forest immediately adjacent /in PIA of the Barsar-Bhota.
According to the latest notification on the re engineered environmental clearance process, this project falls in the Category B notrequiring an MOEF Clearance. More over the project also does not require Forest clearance as it requires more than 5 Ha ofForest land located immediately adjacent along the project road.
Contractor needs to maintain high vigil in all activities, including a control on the labour force so that there will not be any impactto the Forests. For all activities that involve forest area or forest produce must get written permission from the Forest departmentauthorities.
Project will require removing more than 533 trees from the side of the project road. hundreds of trees will be removed from theforest areas also. All this requires compensatory afforestation according to the Forest conservation Act. The forest departmentwill complete this task up on payment.
2.2.2 FAUNASimilarly the project location is in an area of highly diverse fauna. There are many threatened species of the endangered,critically endangered, threatened categories of fauna in the region. All consultations carried out with the local communities andthe forest officials do confirm the high faunal presence in the PIA.
Contractor shall not establish camps in the vicinity of forests within 500m distance. Contractor will have to vigorously implementthe Table 3.1 Environmental Management Action Plan (EMAP), which specifies the dos and don'ts in the Forest areas. In orderto address all flora, fauna and biodiversity related
2.3 SOCIO CULTURAL ENVIRONMENTThe socio economic environment has considered the land use changes, impact to drinking water sources, impact to land andproperties and impact to cultural properties. Project has integrated several mitigation, avoidance and enhancement plans relatingto socio economic aspects that include provision for parking areas, bus bays, rain shelters etc in to the engineering design toimprove the quality of life in these areas.
I niki Rproa- .r-- ln HdI TT1 A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
2.3.1 RESETTLEMENT AND REHABILITATION
A separate study has been carried out and a Resettlement Action Plan (RAP) prepared for land acquisition and resettlement of
people and properties. This is being taken up separately for implementation with the help of an NGO. The land acquisition
process has been started for the Jahu-Kalkhar project road with the section 4.1 notification in the month of October 2006.
2.3.2 CULTURAL PROPERTIES
2.3.2.1 Temples and shrinesHimachal Pradesh is well known as Dev Bhoomi with numerous temples distributed through out the State. The project road
Jahu-kalkhar is also known for the number of temples along the project road. Nevertheless the number of directly and indirectly
impacted temples are only two. A cultural property rehabilitation plan will be in place after the design of all 413 kms of project
roads. Those that require shifting will be dealt with in the Resettlement Action Plan (RAP). Those that require enhancement are
included in the EMP.
2.3.2.2 Archaeological structuresThere are no archaeological structures coming in the PIA of the poject road
2.4 SAFETY AND HEALTH ASPECTS OF THE PROJECT
2.4.1 ROAD SAFETY IN DESIGN
Road safety is an important aspect of the modern design requirements. All possible road safety measures have been taken in to
consideration while designing the project. This includes provision for bus lay bys, parking areas, and also includes improved
lining and signing, guard rails at appropriate locations, pedestrian crossing facilities. Locations of all these features are provided
in the Volume of drawings. Near schools there would be raised footpath zebra crossing and a Standard road safety signage
relating to schools.
2.4.2 HEALTH AND SAFETY MEASURES FOR WORKERS AND LABOURS
Depending on the nature of work all workers shall be provided with adequate personal protective equipments. A list of personal
protective equipments (PPE) is provided in Appendix 10.
The project manager of the Construction contractor and the team leader of the CSC should wear the PPE as a role model so that
the safety culture will be transmitted to the lowest rank of the construction workers. This should be seen as an encouragement
for developing and inculcating a safety culture at all levels at work site.
First aid boxes with first aid leaf lets will be placed at all work places and at least four sets in each construction camps. A
selected group of workers will be trained to use the first aid so as to meet the emergencies at working zones and secondary work
sites. Arrangements with nearby health centres and local doctors will be made for treating injuries which need attention of
specialist doctors.
Contractor must ensure insurance to its workers covering through out the Construction contract period.
2.4.3 TRAFFIC SAFETY PLANS
During construction phase contractor is to prepare plans for the effective implementation of the traffic safety arrangements along
the construction zones. Contractor shall not open numerous construction fronts simultaneously. The number of opening fronts
should depend on the capability and capacity of the Contractor to effectively manage the work sites with his dedicated staff. Prior
to opening of new work fronts, after the completion of the work, the area should be safely closed in all respects with suitable
information or signboards.
The Contractor will have to prepare a 'Road safety, Accidents and Traffic management plan' with the guidelines provided in the
appendix 15. In this plan road safety are precautionary measures against accidents through out the length of the project road,
while accident plan is to take measures once an accident took place at work site and traffic management plan is the physical
managing of the traffic at critical work locations in accordance with the IRC guidelines on road safety at construction zones
(IRC:SP:55 2001). All safety precautions will be ensured during temporary and permanent works for the road construction and
details of the requirement are included in the volume of drawings, the specifications and Bills of quantities (BOQ). Based on
these, site-specific traffic management plan will be prepared and implemented by the Contractor and checked by theconstruction supervision consultants (CSC) during the construction stage.
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
2.4.4 HANDLING OF EXPLOSIVESConsiderable rock blastng would require along the project road, due to the presence of hard rocks, huge rock blocks etc on thehill ward side where the total widening would takes place. This need permission and licence from the department of explosives.
Further storing, transportation and its use require considerable safety requirements and arrangements. Therefore the Contractormust resort to all safety guidelines and best practices.
Near forest reserves Contractor shall use controlled/ silent blasting. Further a written permission will be required from the Forestdepartment especially from the wildlife wing.
2.4.5 HANDLING OF PETROLEUM PRODUCTS (POL)The use of petrol, oil and lubricants (POL) including bitumen and emulsions will be handled, stored and used in accordance withthe relevant rules, acts, and guidelines to avoid any impact to the environment and reduce the probability of the occurrence ofthe accidents. Wastes generated from the use of the petroleum products will also be disposed of safely as detailed in therelevant rules, regulations and guidelines. The rules and regulabons applicable for the handling of these products are listedbelow.
* Environmental protection Act, 1986* Petroleum act 1934* Petroleum rules, 2002
The Contractor has, not only the full responsibility for conforming to these rules and regulations but also to follow internabonallyaccepted best practices.
I - . . _ - rTlr T1i T
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
3 MITIGATION MEASURES
Table 3.1: ENVIRONMENTAL MANAGEMENT PLAN
No. Environmental Issue Management Measures Reference Responsibity
PRE-CONSTRUCTION STAGE
Pre-construction activities by Himachal Pradesh Road and other Infrastructure Development Corporation
The acquisition of land and private properties will be carried out in accordance with the RAP and entitlement framework HPRIDC, Revenue
P.1 Land Acquisition (If of the Project. LA Act 1984 and its Dept, Collaborating HPRIDCrequired) HPRIDC has to ascertain that acquisition of land in the post design phase are addressed and integrated into the EMP Amendments, Agencies
and relevant contract documents.
Clearance of Advance notice, as per RAP shall be given to the encroachers & squabters present in the Corridor of Impact, who need HPRIDC and
P.2 Encroachment/squ atters to be relocated. All R&R activities will be undertaken. Entitlements as per HPRIDC enttlement framework will be RAP documents RevenueAuthority HPRIDC
(change in land use) completed before construcbon starts.
Trees will be removed from the Corridor of Impact before the actual commencement of the work with the permission MoRTH 201.6. Contractor/ Agency
P.3 Tree Cubting from the state Forest Department. All unnecessary removal of trees shall be avoided. engaged by CSC and/ HPRIDC
Stacking, transport and storage of the wood will be done as per the relevant norms. HPRIDC
All efforts will be made to preserve trees including evaluation of minor design adjustments/afternatives (as applicable) to
save trees. Specific attention will be given for protecting giant trees, green tunnels and locally important trees
(religiously important etc.). Detail of the trees affected due to the proposed project road is given in (Appendix -1)
Tree cutting is to proceed only after all the legal requirements including attaining of In-principle and Formal Clearances
PA4 Preservation of Trees from the Forest Dept./DoEF/MoEF are completed and subsequently a written order is issued to the Contractor. Ap d'x1
P.4 PrsrainfParticular species declared as 'protected' by the State's Forest Dept. in the private land will be felled only after due ppendIX-
clearance from the Forest Dept. is obtained.In the event of design changes, additional assessments including the possibility to save trees shall be made.
Stacking, transport and storage of the wood will be done as per the relevant norms.Systematic corridor level documentabon for the trees cut and those saved will be maintained by the HPRIDC.
Relocation of Community All community utilities and properties i.e., hand pumps, open wells, water supply lines, sewer lines, telephone cables, RAP document HPRIDC other
P.5 Utilities and Common buildings and health centers will be not relocated before constructon starts in the project road. Details of the community & Agencies and / HPRIDC
Property Resources properties affected are provided in Appendix 2. Appendix 2 Contractor
Louis Berger Group, INC, USA 29
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue Management Measures Rfc ResponsIblIt
No. dcmn
All religious property resources such as shrines, temples and mosques within the project road will not be relocated.Cultural property rehabilitation plans including the list of cuftural properties affected are given in the (appendix-3).Relocation of affected If there is any relocation of the religious structures may happen then it will be identified in accordance with the choice ofP.6 Cultural and Religious the community. HPRIDC in consultation with local people will finalize those. Appendix-3 HPRIDC, Contractor CSC/HPRIDCProperties The entire process (i.e. selection of relocation sites and designs) will be under supervision of Environmental Specialistof CSC, during the construction stage by the Contractor. The relocation will be completed before the construction tartsin these sites.
Pre-construction activities by the Contractor/Environmental Specialist of CSC
P.7 Field Verification and Modification of the Contract Documents
The Environmental Specialist of CSC and the Contractor will carry out joint field verification to ascertain any Contractor/P.7.1 Joint Field Verification possibilities of saving trees, environmental and community resources, if these activities are to be taken up by the Environmental HPRIDCconstruction Contractor. Specialist of CSC
Assessment of ImpactsP.7.2 due to Changes/Revisions The Environmental Specialist of CSC will assess impacts and revise/modify the EMP and other required sections of the Contractor/ HPRIDC.7. /Additions in the Project project document/s in the event of changes/revisions (including addition or deletion) in the project's Scope of work. Envonmental oPRICWork
All construction plants will be sited sufficiently away from settlements and agricultural operations or any commercialestablishments. Such plants will be located at least 100 m away from the nearest dwelling preferably in the downwinddirection.The Contractor shall submit a detailed layout plan for all such sites and approval of Environmental Specialist of CSC MoRTH 111.1, Airshall be necessary prior to the establishment. Pollution ControlCrushers, hot-mix plants Arrangements to control dust pollution through provision of wind Screens, water spnnklers, and dust extraction systems Act, and Noise Contractor/P rushers, hix plants will have to be provided at all such sites.
Rules onmentor/P.7.3 and Batching Plants Specifications for crushers, hot mix plants and batching plants will comply with the requirements of the relevant Environmental HPRIDCLocation emission control legislations. Consent for the Establishment and Operation from HPPCB shall be obtained BOQ Bill No 11 Specialist of vCSCbefore establishment and operation respectively and a copy should be submitted to the CSC and HPRIDC. EnvironmentalWhere ever there are extremely water scarcity areas exists in such locations the Water sprinkling shall be restricted to mitigation worksone time in the moming. To balance this deficient information boards shall be erected at appropriate locations with amessage similar to Dust prone area take precautions'
All vehicles, equipment and machinery to be procured for constwuction will confirm to the relevant Bureau of IndiaOther Construction Standard (BIS) norms. The discharge standards promulgated under the Environment Protection Act, 1986 and Motor Air Pollution Control Contractor/P.7.4 Vehices, Euipmet andVehicles Act, 1988 shall be strictly adhered to, c,adNie Evrnetl HRDMachinery The silent/quiet equipment available in the market shall be used in the Project. Rules and Motor eCionmenalt HPRIDCThe Contractor shall maintain a record of PUC for all vehicles and machinery used during the contract period which Vehicle Act, 1988 Specialist of CSCshall be produced EO, HPRIDC/ PWD's verification whenever required.
Louis Berger Group, INC, USA 30
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue ManagementMeasures ponsibHlty
P.8 Identification and Selection of Material Sources
Finalizing soil borrow areas for borrowing earth and all logistic arrangements as well as compliance to environmentalrequirements, as applicable, will be the sole responsibility of the Contractor. (Appendix-4).The Contractor will not start borrowing earth from select borrow area until the formal agreement is signed betweenlandowner and Contractor and a copy is submitted to the CSC. Contractor/
P.8.1 Borrow Areas Locations finalized by the Contractor shall be reported to the Environmental Specialist of CSC and he will submit the Appendix 4 Environmental HPRIDCreport to HPRIDC.SpcaitoCCPlanning of haul roads for accessing borrows areas will be undertaken during this stage. The haul roads shall be routed Specialist of CSCto avoid agricultural areas as far as possible and will use the existing village roads wherever available.The environmental personnel of the CSC will be required to inspect every borrow area location prior to approval. TheCSC should include the Request for Inspection form for borrows area approval from the environmental angle.
Contractor will finalize the quarry for procurement of construction materials after assessment of theavailability of sufficient materials, quality and other logistic arrangements. MoRTH 111.3In case the Contractor decides to use quarries other than recommended by DPR consuftant, then the Contractor should Environmental
P.8.2 Quarry give substantiation. & Contractor Specialist of CSC and
Contractor will also work out haul road network and report to Environmental Specialist of CSC and CSC will inspect. Appendix 5 HPRIDC
and in turn report to HPRIDC before approval.
In view of the special situation in HP, Contractor shall prepare and implement the approved water management plan inaccordance with the Appendix 16 and BOQ No 11- Environmental mitgation worksThe Contractor will use ground /surface water as a source of water for the construction and may set up own bore wellfacility for construction work. Environmental
P.8.3 Arrangement for Contractor may take surface water from the Irrigation Canal with the written consent from the Irrigation Department. . Eci alConstruction Water To avoid disruption/disturbance to other water users, the Contractor will extract water from fixed locations and consult (Appendix -16) Contractor Specialist of CSC and
with Environmental Specialist of CSC before finalizing the locations. HPRIDC
The Contractor will provide a list of locations and type of sources from where water for construction will be extracted.The Contractor will need to comply with the requirements of the State Ground Water Department for the extraction andseek their approval for doing so and submit copies of the permission to CSC and HPRIDC.
The sand will be procured from Identified sand mines as far as possible. If the Contractor wanted to obtain from source All riverbeds
P.9 Sand other than listed in EMP, substantiation shall be provided. Appendix -5 is the details of the source aggregates and lead recommended forP. addistance. Appendix 5 sand extraction for
The Contractor should obtain copy of the Lease agreement of the supplier and submit to CSC before procuring the the project.sand.
The Contractor preferably will use unskilled labour drawn from local communities to give the maximum benefit to the Copy of Contract EnvironmentalL sRequiremen Document Contractor Specialist of CSC and
Louis Berger Group, INC, USA 3 1
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue Management Measures Reference Repnsibillty
No.
Siting of the construction camps will be as per the guidelines below and details of layout to be approved by CSCResident Engineer and environmental specialist.Construction Camp Construction camps will not be proposed within 500 m from the nearest settlements to avoid conflicts and stress over EnvironmentalP.1 1 Locations - the infrastructure facilities with the local community.Selection, Design and Location for stockyards for construction materals will be identified at least 300 m away from watercourses. (AppendixH6) Contractor Specialist of CSC andLay-out The sewage and solid waste for the camp will be designed, built and operated.
Contractor's camps shall be identified at least 2 km away from the Forest reserves. Appendix 6 and Appendix 18 Forestarea management plan.
The Contractor as per prevalent rules will carry out negotiations with the landowners for obtaining their consent forP.12 Temporary Land temporary use of lands for construction camp /construction/ borrow areas etc. . Eci al.12 uiem ent Temporary land arrangements shall not be from the forest reserves except under special permission circumstances Appendix 18 Contractor HPRIDCwhere it is un avoidable due to the vast forest reserves in the PIAPROrientation of The HPRIDC shall organize orientation sessions and regular training sessions during all stages of the Project. This shall EMP and other Contactor, CSC andP.13 Implementing Agency and include on-site training (general as well as in the specific context of a sub-project). These sessions shall involve all staff training plan HP RID C HPRIDCContractors of HPRIDC involved in the implementation of EMP, Environmental Specialists of CSC and Contractors. developed byCONSTRUCTION STAGE
Activities to be Carried Out by the Contractor
C.1 Site Clearance
If required Vegetation will be removed from the construction zone before commencement of construction. All works willbe carried out such that the damage or disruption to flora other than those identffied for cutting is minimum.Only ground cover/shrubs that impinge directly on the permanent works or necessary temporary works will be removedwith prior approval from the Environmental Expert of CSC. EnvironmentalC.1.1 Clearing and Grubbing The Contractor, under any circumstances will not cut or damage trees and forest reserves (refer Appendix 18). Trees MoRTH 201 Contractor Specialist of CSC,identified under the project will be cut only after receiving clearance from the Forest Dept./DoEF/MoEF (as applicable) HPRIDCand after the receipt of HPRIDC's written permission in this regard.
Vegetation only with girth size of over 30 cm will be considered as trees and shall be compensated, in the event ofHPRIDC's instruction to undertake tree cutting.
Louis Berger Group, INC, USA 32
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue Management Measures Reference ResponsibUltYNo. docuent
.. g- r C~VA. A .,', - - 1 1
Appendix 17 provides guidelines for the preparation of the contractors Debris disposal plan. This is mainly to deal withhuge quantity of excavation of the order of 30,000 m 3 towards the hill ward side for widening of the existing roads.Other debris generated due to the dismantling of the existing road will be suitably reused in the proposed construction,subject to the structure suitability of the materials and approval of the Resident Engineer and Environmental Expert ofCSC as follows:For filling and levelling of School grounds and proposed parking areas.The sub grade of the existing pavement shall be used as embankment fill material.The existing base and sub-base material shall be recycled as sub-base of the haul road or access roads.The existing bitumen surface may be utilized for the paving of cross roads, access roads and paving works inconstruction sites and campus, temporary traffic diversions, haulage routes etc.The Contractor will suitably dispose off unutilized debris materials either through filling up of borrows areas located in MoRTH 202 MoRTH Environmental
Disposal of Debris from wasteland or at pre-designated disposal locations, subject to the approval of the Environmental Expert of CSC. 202 SCo o Enin t ee d R CSC etC.1.2 dismantling structures and At locations identified for disposal of residual bituminous wastes, the disposal will be carried out over a 60 mm thick Spe17i Contractor dEninr of ent
road surface layer of rammed clay so as to eliminate the possibility of leaching of wastes into the ground water. The Contractor will (Appendix-i) 7)RiDCensure that the surface area of such disposal pits is covered with a layer of soil. (Appendix-21)All arrangements for transportation during construction including provision, maintenance, dismantling and clearingdebris, will be considered incidental to the work and will be planned and implemented by the Contractor as approvedand directed by the Environmental Expert of CSC.The pre-designed disposal locations will be a part of Comprehensive Solid Waste Management Plan to be prepared byContractor in consultation and with approval of Environmental Expert of CSC.Debris generated from pile driving or other construction activities shall be disposed such that it does not flow into thesurface water bodies or form mud puddles in the area.The Contractor shall identify dumping sites as per the Debris disposal plan prepared using the Guidelines provided inthe Appendix 17; . The identified locations will be reported to the Environmental Expert of CSC. These locations will bechecked on site and accordingly approved by Environmental Expert of CSC prior to any disposal of waste materials.
Louis Berger Group, INC, USA 33
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue Management Measures sibilityNo.
dcmn
The pre-identified disposal locations will be part of Comprehensive Waste Disposal Solid Waste Management Plan tobe prepared by the Contractor in consultation and with approval of Environmental Specialist of CSC. Location ofdisposal sites will be finalized prior to initiation of the works on any particular section of the road, if disposal isenvisaged.The Environmental Specialist of CSC will approve these disposal sites after conducting a joint inspection on the sitewith the Contractor.Contractor will ensure that any spoils or material unsuitable for embankment fill will not be disposed off near any water MoRTH 202.5Other Construction course or agricultural land, Apple Orchards and Natural Habitats like Grasslands. Such spoils from excavation can be MoRTH:301.11 EnvironmentalC.1 3 WOter DCIosti used to reclaim borrow pits and low-lying areas located in barren lands along the project road (if is so desired by the MAppndix17) Contractor Specialist of CSC,astes isposa owner/community and approved by the E. Specialist, CSC). (Appendix-21) HPRIDCNon-bituminous wastes will be dumped in borrow pits covered with a layer of the soil to ensue that borrow pit is restored (AppendIx-2)to original use. No new disposal site shall be created as part of the project, except with prior approval of theEnvironmental Specialist of CSC.All waste materials will be completely disposed and the site will be fully cleaned and certified by EnvironmentalSpecialist of CSC before handing over.The Contractor at its cost shall resolve any claim, arising out of waste disposal or any non- Compliance that may ariseon account of lack of action on his part.
The topsoil from all areas of cuffing and all areas to be permanently covered will be stripped to a specified depth of 150mm and stored in stockpiles. A portion of the temporarily acquired area and/or Right of Way will be earmarked forstoring topsoil. The locations for stock piling will be pre-identified in consultation and with approval of EnvironmentalSpecialist of CSC. The following precautionary measures will be taken to preserve them till they are used:(a) Stockpile will be designed such that the slope does not exceed 1:2 (vertical to horizontal), and height of the pile is MoRTH:301.3.2Str p tock d restricted to 2 m. To retain soil and to allow percolation of water, silt fencing will protect the edges of the pile. MoRTH:301 .. , EnvironmentalC.1.4 preservation of top soil (b) Stockpiles will not be surcharged or otherwise loaded and multiple handling will be kept to a minimum to ensure that MoRTH:305.3,3 Contractor Specialist of CSC,no compaction will occur. The stockpiles shall be covered with gunny bags or vegetation. MoRTH-305.3 9 HPRIDC(c) It will be ensured by the Contractor that the topsoil will not be unnecessarily trafficked either before stripping or .3..when in stockpiles.Such stockpiled topsoil will be utilized for -> Covering all disturbed areas including borrow areas, only in a case where there are to be rehabilitation> Dressing of slopes of road embankment > Agricultural fields of farmers acquired temporarily land.
The Contractor will provide safe and convenient passage for vehicles, pedestrians and livestock to and from roadsidesand property accesses connecting the project road, providing temporary connecting road. EnvironmentalC. 1.5 Accessibility The Contractor will also ensure that the existing accesses will not be undertaken without providing adequate provisions. Contractor Specialist of CSC,The Contractor will take care that the cross roads are constructed in such a sequence that construction work on the HPRIDCadjacent cross roads are taken up one after one so that traffic movement in any given area not get affected much.
Louis Berger Group, INC, USA 34
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue Management Measures Reference ResponsibityNo. document ________
____- -"'-,4 " -~iIL jii -STemporary diversions will be constructed with the approval of the Resident Engineer and Environmental Specialist ofCSC. Detailed Traffic Control Plans will be prepared by the Contractor and approved by Environmental Specialist andResident Engineer of CSC for approval, seven days prior to commencement of works on any section of road. The trafficcontrol plans shall contain details of temporary diversions, traffic safety arrangements for construction under traffic,details of traffic arrangement after cessation of work each day, safety measures for night time traffic and precaution for MoRTH: 112 and its Environmental
0.1.6 Planning for Traffic transportation of hazardous materials and arrangement of flagmen. Amendments Contractor Specialist and ResidentDiversions And Detours The Contractor will ensure that the diversion/detour is always maintained in running condition, particularly during the (Apndix 15 Engineer of CSC,EO,
monsoon to avoid disruption to traffic flow. pped- HPRIDC
The Contractor will also inform local community of changes to traffic routes, conditions and pedestrian accessarrangements with assistance from CSC and HPRIDC. The temporary traffic detours will be kept free of dust bysprinkling of water three times a day and as required under specific condHfions (depending on weather conditions,construction in the settlement areas and volume of traffic).
C.2 Procurement of Construction Material
No borrow area will be opened without permission of the Environmental Specialist of CSC. The location, shape and sizeof the designated borrow areas will be as approved by the Environmental Specialist of CSC and in accordance to theIRC recommended practice for borrow pits for road embankments (IRC 10: 1961). The borrowing operations will becarried out as specified in the guidelines for siting and operation of borrow areas.
Earth from Borrow Areas The unpaved surfaces used for the haulage of borrow materials, if passing through the settlement areas or habitations; MoRTH:305.2 EnvironmentalC.2.1 for Construction will be maintained dust free by the Contractor. Sprinkling of water will be carried out twice a day to control dust along (Appendix-4) Contractor Specialist of CSC,
such roads during their period of use. HPRIDCDuring dry seasons (winter and summer) frequency of water sprinkling will be increased in the settlement areas andEnvironmental Specialist of CSC will decide the sprnkling time depending on the local requirements.Contractor will rehabilitate the borrow areas as soon as borrowing of soil is over from a particular borrow area inaccordance with the approved borrow area Redevelopment Plan.
The Contractor shall obtain materials for quaries only after consent of the Department of Mining and DistrictAdministration. In view oft he special situation of excavation of the hill ward side, Contractor will get an opportunity to
C.2.3 Quarry Operations use the same material for road construction. This will require establishment of a number of crushers along the road MoRTH: 111.3 Contractor EnvionmentalCrushers sides. The crushers and all related activities shall be under taken as per the Appendix 23 Policy guide lines for Appendix 23 HSpecalist of CSC,
installation of stone crushers.
Contractor will maintain all roads (existing or built for the project), which are used for transporting constructionmaterials, equipment and machineries as precised. All vehicles delivering fine materials to the site will be covered to
Transporting Construction avoid spillage of materials. Environmental
C.2.4 Materials and Haul Road All existing roads used by vehicles of the Contractor or any of his subcontractor or suppliers of materials and similarly Contractor Specialist of CSC,
Management roads, which are part of the works, will be kept clear of all dustmud or other extraneous materials dropped by such HPRIDC
vehicles.Contractor will arrange for regular water sprinkling as necessary for dust suppression of all such roads and surfaces.
Louis Berger Group, INC, USA 35
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue Management Measures Referce ResponsibiltyNo. docurnent .
am M' .- --
Contractor need to implement the finally approved contractors Construction water management plan as per theguidelines provided in Appendix 16.Contractor will arrange adequate supply and storage of water for the whole construction period at his own costs. TheContractor will submit a list of source/s from where water will be used for the project to CSC and HPRIDC. (Appendix-16) Environmental ExpertC.2.5 Construction Water The Contractor will source the requirement of water preferentially by conjunctve use of Surface water and ground water (Appendix 21) Contractor of CSC, HPRIDCbut with prior permission from the Ground Water Board. A copy of the permission will be submitted to CSC and PPHPRIDC prior to initiation of construction.The Contractor will take all precaution to minimize the wastage of water in the construction process/ operation.
C.3 Construction Work
River Training and While working across or close to any perennial water bodies, Contractor will not obstruct/ prevent the flow of water. EnvironmentalC.3.1 Disruption to Other Users Construction over and close to the non-perennial streams shall be undertaken in the dry season. If construction work is MoRTH 304.3.2 Contractor Specialist of CSC,of Water expected to disrupt users of community water bodies, notice shall be served well in advance to the affected community. HPRIDCContractor will ensure that no construction materials like earth, stone, or appendage disposed off in a manner that blockDrainage and Flood the flow of water of any water course and cross drainage channels. MoRTH: 305.37 EnvironmentalC.3.2 Control Contractor will take all necessary measures to prevent any blockage to the water flow. In addition to the design MoRTH: 306 Contractor Specialist of CSC,requirements, the Contractor will take all required measures as directed by the Environmental Specialist of CSC to Refer Appendix 17 HPRIDCprevent temporary or permanent flooding of the site or any adjacent area.
The Contractor will not excavate beds of any stream/canals/ any other water body for borrowing earth for embankmentconstruction.Siltation of Water Bodies Contractor will construct silt fencing at the base of the embankment construction for the entire perimeter of any water MoRTH: 306 EnvironmentalC.3.3 and Degradation of Water body (including wells) adjacent to the project road and around the stockpiles at the construction sites including ancillaryQaiysites close to water bodies. The fencing will be provided prior to commencement of earthwork and continue ti the (Sitpencingxotrco Seilito CPRCDstabilization of the embankment slopes, on the particular sub-section of the road.
Contractor will ensure that construction materials containing fine particles are stored in an enclosure such thatsediment-laden water does not drain into nearby watercourse.
Louis Berger Group, INC, USA 36
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
No. Environmental Issue Management Measures Refcece Reponsib0ty
J.1 - --11-
The Contractor will construct slope protection works as per design, or as directed by the Environmental Specialist ofCSC to control soil erosion and sedimentation through use of Breast walls, Retaining Walls, Pilot Bioengineeringmethods, dykes, sedimentation chambers, basins, fibber mats, mulches, grasses, slope, drains and other devices.All temporary sedimentation, pollution control works and maintenance thereof will be deemed as incidental to the earthwork or other items of work and as such no separate payment will be made for them.Contractor will ensure the following aspects: MoRTH: 305.2.2.2 Environmental
C.3.4 Slope Protection and After construction of road embankment, the side slopes will be covered with grass and shrubs (refer Appendix 12) MoRTH: 306.2 Contractor Specialist of CSC,Control of Soil Erosion as per design specifications. & Appendix 12 HPRIDC
> Turfing works will be taken up as soon as possible provided the season is favourable for the establishment of grasssods. Other measures of slope stabilization will include mulching netting and seeding of batters and drainsimmediately on completion of earthworks
4 In borrow pits, the depth shall be so regulated that the sides of the excavation will have a slope not steeper than 1vertical to 2 horizontal, from the edge of the final section of the bank.
> Along sections abutting water bodies, pitching as per design specification will protect slopes.
C.4 Pollution
C.4.1 Water Pollution
The Contractor will take all precautionary measures to prevent entering of wastewater into streams, water bodies orC.4.1.1 Water Pollution from the irrigation system during construction. Contractor will avoid construction works close to the streams or water MoRTH 111.4 MoRTH: Contractor Specialist of CSC
.4. Construction Wastes bodies during monsoon. 111.1 HPRIDCContractor shall not wash his vehicles in river water and shall not enter river bed for that purpose.
The Contractor will ensure that all construction vehicle parking locations, fueVlIubricants storage sites, vehicle,machinery and equipment maintenance and refuelling sites will be located at least 500 m away from nvers andirrigation canal/ponds.The Contractor will submit all locations and layout plans of such sites prior to their establishment and will be MoRTH: 111.4approved by the Environmental Specialist of CSC. MoRTH: 111.1Contractor will ensure that all vehicle/machinery and equipment operation, maintenance and refuelling will be carried (Oil Interceptors) Environmental
C.4.1 .2 Water Pollution from Fuel out in such a fashion that spillage of fuels and lubricants does not contaminate the ground. Wastewater from vehicle Petroleum Act and Cttr Sp eIt af CSCand Lubricants parking, fuel storage areas, workshops, wash down and refuelling areas will be treated in an oil interceptor before Rules Conractor peciaIs oC
discharging into on land or into surface water bodies or into other treatment system. MoEF/CPCBIn all, fuel storage and refuelling areas, if located on agricultural land or areas supporting vegetation, the top soil will Notificationsbe stripped, stockpiled and returned after cessation of such storage. (Appendix-8)Contractor will arrange for collection, storing and disposal of oily wastes to the pre-identified disposal sites (list to besubmitted to CSC and HPRIDC) and approved by the Environmental Specialist of CSC. All spills and collectedpetroleum wastes will be disposed off in accordance with Petroleum Rules and PCB guidelines.
C.4.2 Air Pollution
Louis Berger Group, INC, USA 37
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue Management Measures Reference ResponsibDity
N. document.The Contractor will take every precaution to reduGe the level of dust from construction plants, construction sites
involving earthwork by sprinkling of water, encapsulation of dust source.Due to the acute water scarcity in certain areas, Contractor should limit water sprinkling only to one time in the earlymoming hours and for that matter to balance the action Contractor should erect waming boards on dust nuisance to MoRTH: 111.1the road users.
MoRTH: 111.5 EnvironmentalC.4.2.1 Dust Pollution The Contractor will procure the construction plants and machinery, which will conform to the pollution control norms MoRTH: 111.9 Contractor Specialist of CSC, EO,specified by the MoEF/CPCB/HPCB. MoRTH: 111.10 HPRIDC through theThe concentration of suspended particulate matter at a distance of 40m from a construction plant located in a cluster Contract Agreement Engineerof industries should be less than 500 pg. The environmental monitoring is to be conducted as per the monitoring (Appendix-13)plan.
Alternatively, only crushers licensed by the HPCB shall be used. The Environmental Specialist, EO, and HPRIDCthrough the Engineer shall submit required certificates and consents.
Emission from Contractor will ensure that all vehicles, equipment and machinery used for construction are regularly maintained and EnvironmentalC.4.2.2 Construction Vehicles, confirm that pollution emission levels comply with the relevant requirements of CPCB and/ Motor Vehicles Rules. Contractor Specialist of CSC,Equipment and The Contractor will submit PUC certificates for all vehicles/ equipment/machinery used for the Project. HPRIDCMachineries
C.4.3 Noise Pollution
The Contractor will confirm the following:> All Constructon plants and equipment used in construction shall strictly conform to the MoEF/CPCB noise standards.> All vehicles and equipment used in constructon will be fitted with exhaust silencers.> Servicing of all constructon vehicles and machinery will be done regularly and during routine servicing operations, theeffectiveness of exhaust silencers will be checked and if found defective will be replaced.P The equipment available in the market should be procured, if the Contractor plans to purchase new equipment. For the old Noise Rules Publishedequipment, necessary or possible alterations must be carried out to reduce the noise levels to the possible extent. by MoEFN Maintenance of vehicles, equipment and machinery shall be regular and up to the safisfaction of the Environmental Appendix 9Noise Pollution: Noise Specialist of CSC to keep noise levels at the minimum.
EnvironmentalC.4.3.1 from Vehicles, Plants and At the construction sites within 150 m of the nearest habitation, noisy construction work such as crushing, operation & Contractor Specialist of CSC, EO,Equipments of DG sets, use of high noise generation equipment will be stopped during the night time between 10.00 pm to 6.00 HPRIDCam. Appendix-i3Working hours of the construction activities will be restricted around educational institutes/heafth centers Appendix 21(silence zones) up to a distance of 100 m from the sensitive receptors i.e., School, health centers and hospitals.
Contractor will provide noise barriers to the suggested locations of select Schools. List of locations for noise barriersis given in (Appendix-9).Noise monitoring shall be carried out at the locations specified in Table 5.2 by the HPRIDC and the Engineer throughthe approved monitoring agency.
C.5 Safety
Louis Berger Group, INC, USA 38
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
No. Environmental Issue Management Measures Referc Responsibility
Contractor will provide:> Protective footwear, proteectve goggles and nose masks to the workers employed in asphalt works, concrete
works, crusher etc.P Welder's protective eye-shields to workers who are engaged in welding works> Earplugs to workers exposed to loud noise, and workers working in crushing or compaction> The Contractor will comply with all regulations regarding safe scaffolding, ladders, working platforms, gangway,
stairwells, excavations, trenches and safe means of entry and egress. Environmental
Personal Safety The Contractor will comply with all the precautions as required for ensuring the safety of the workmen as per the Eci alC.5.1 Measures for Labour International Labour Organization (ILO) Convention No. 62 as far as those are applicable to this contract. Appendix-il Contractor Specialist of CSC,
The Contractor will make sure that during the construction work all relevant provisions of Building and otherConstruction Workers (regulation of Employment and Conditions of Services) Act, 1996 are adhered to.
The Contractor will not employ any person below the age of 14 years for any work and no woman will be employed onthe work of painting with products containing lead in any form
The Contractor will take all necessary measures for the safety of traffic during constructon and provide, erect andmaintain such barricades, including signs, markings, flags, lights and flagmen as proposed in the Traffic Control MoRTH: 112.4Plan/Drawings and as required by the Environmental Expert of CSC for the information and protection of traffic MoRTH: 112.1 IRC: Environmental
C.5.2 Traffic and Safety approaching or passing through the section of any existing cross roads. SP: 55 Contractor Specialist of CSC,
The Contractor will ensure that all signs, barricades, pavement markings are provided as per the MoRTH specifications. Appendix-11 HPRIDCBefore taking up of constructon on any section of the existing lanes of the highway, a Traffic Control Plan will bedevised and implemented to the satisfacton of the Environmental Expert of CSC.
The Contractor will take all required precautions to prevent danger from electrical equipment and
ensure that -
> No material will be so stacked or placed as to cause danger or inconvenience to any person or the
Risk from Electrical public. Environmental
C.5.3 Equipment(s) P All necessary fencing and lights will be provided to protect the public in construction zones. Contractor Expert of SC, PIU
All machines to be used in the construction will conform to the relevant Indian Standards (IS) codes, will
be free from patent defect, will be kept in good working order, will be regularly inspected and properly
maintained as per IS provision and to the satisfaction of the Environmental Expert of SC.
Louis Berger Group, INC, USA 39
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue Management Measures Repnsillity
C54 Risk from Electrical All necessary fencing and lights will be provided to protect the public in construction zones.CotaorSeilsofSC.5. Equipment(s) All machines to be used in the construction will conform to the relevant Indian Standards (IS) codes, will be free from Contractor Specialist of CSC,patent defect, will be kept in good working order, will be regularly inspected and properly maintained as per IS provisionand to the satisfaction of the Environmental Expert of CSC.
The Contractor will take all reasonable precautions to prevent danger to the workers and public from fire, flood etc. Contract Agreementresulting due to construction activities. and Buldig and EnvironmentalC.5.5 Risk Force Measure The Contractor will make required arrangements so that in case of any mishap all necessary steps can be taken for ather Construction Contractor Specialist of CSC,prompt first aid treatment. Construction Safety Plan prepared by the Contractor will identify necessary actions in the WorkCos Act 199o HPRIDCevent of an emergency.
The Contractor will arrange for -A readily available first aid unit including an adequate supply of sterilized dressing materials and appliances as per the Contract EnvironmentalC.5.6 First Aid Factories Rules in every work zone. c Contractor Specialist of CSC,Availability of suitable transport at all times to take injured or sick person(s) to the nearest hospital. requireme HPRIDCEquipment and trained nursing staff at constructon camp.
The Contractor will provide, erect and maintain informatory/safety signs, hoardings written in English and local language MoRTH: 8010.5.7 Informatory Signs and (Hindi), wherever required or as suggested by the Environmental Specialist of CSC. MoRTH: 802 EnvironmentalC.5.7 Hoardings After construction Information boards shall be erected for the tourism enhancement. These boards should be of & Contractor Specialistof CSC,intemational standards. The locations identified for such type of activities are provided in Appendix 20 Appendix 20 HPRIDCAppendix 21
C.6 Flora and Fauna: PlantationlPreservationl Conservation Measures
The Contractor will do turfing on embankment slopes, plantation of shrubs as specified in the Contract.The compensatory forestation will be carried out by the State Forest Department.
C.61 Road side Plantation Minimum 80 percent survival rate of the saplings will be acceptable otherwise the Contractor/ Forest Department will Appendix-12 Environmental. Strategy replace dead plants at his own cost. Appendix 21 Contractor Specialist of CSC,The Environmental Specialist of CSC will inspect regularly the survival rate of the trees planted by the Contractor in HPRIDCaccordance with the plantation strategy suggested.
Louis Berger Group, INC, USA 40
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
No. Environmental Issue Management Measures Reference ResponstbflltyN. .,o-ument-
The Contractor will take reasonable precaution to prevent his workmen or any other persons from removing anddamaging any flora (plantvegetation) and fauna (animal) including fishing in any water body and huntng of any animal.If any wild animal is found near the construction site at any point of time, the Contractor will immediately upon discovery Environmental
Flora and Chance found thereof acquaint the Environmental Specialist of CSC and carry out the instructions for dealing with the same.C.6.2 Fauna The Environmental Specialist of CSC will report to the near by forest office (range office or divisional office) and will Appendix 21 Contractor HPRIDC
take appropriate steps/ measures, if required in consultation with the forest officials.
All fossils, coins, articles of value of antiquity, structures and other remains or archaeological interestdiscovered on the site shall be the property of the Government and shall be dealt with as per provisions of the relevantlegislation.The Contractor will take reasonable precautions to prevent his workmen or any other persons from removing and
Chance Found damaging any such article or thing. He will, immediately upon discovery thereof and before removal acquaint the . EnvironmentalC.6.3 Archaeological Property Environmental Specialist of CSC of such discovery and carry out the CSC's instructions for dealing with the same, Appendix 19 Contractor Specialist of CSC,
waiting which all work shall be stopped. HPRIDCThe CSC will seek direction from the Archaeological Survey of India (ASI) before instructing the Contractor torecommence the work in the site.The Archaeological structures identified along the road sides should be protected/ preserved or enhanced as per thelaw.
C.7 Labour Camp Management
Contractor will follow all relevant provisions of the Building and the other Constructon Workers (Regulation ofEmployment and Conditions of Service) Act, 1996 for construction and maintenance of labour camp.The location, layout and basic facility provision of each labour camp will be submitted to CSC and HPRIDC prior to their Environmental
C.7.1 Accommodation construction. Contract Agreement Contractor Specialist of CSC,The Construction will commence only upon the written approval of the Environmental Specialist of CSC. HPRIDCThe Contractor will maintain necessary living accommodation and ancillary facilities in functional and hygienic mannerand as approved by the CSC.
Louis Berger Group, INC, USA 41
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
No. Environmental Issue Management Measures dbilit
The Contractor will construct and maintain all labour accommodation in such a fashion that uncontaminated water islavailable for drinking, cooking and washing.The Contractor will also provide potable water facilities within the precincts of every workplace in an accessible place,as per standards set by the Building and other Construcbon Workers (Regulation of Employment and Conditions ofService) Act, 1996.The Contractor will also guarantee the following:
a) Supply of sufficient quantity of Potable water (as per IS) in every workplace/labour camp(Site at suitable andeasily accessible places and regular maintenance of such facilities.C.7.2 Potable Water b) If any water storage tank is provided that will be kept such that the bottom of the tank at least 1 meter above Contract Agreeme Contractor Specialist of CSC,C72 PtbeWtrthe surrounding ground level. I:150191HPRIDCc) If water is drawn from any existing well, which is within 30meters proximity of any toilet, drain or other sourceof pollution, the well will be disinfected before water is used for drinking.
d) All such wells will be entirely covered and provided with a trap door, which will be dust proof and waterproof.e) A reliable pump will be fitted to each covered well, The trap door will be kept locked and opened only forcleaning or inspection, which will be done at least once in a month.f) Testing of water will be done every month as per parameters prescribed in IS 10500-1991.
Environmental Specialist of CSC will be required to inspect the labour camp once in a week to ensure the compliance ofthe EMP.
The Contractor will ensure that -> The sewage system for the camp are designed, built and operated in such a fashion that no health hazardsoccurs and no pollution to the air, ground water or adjacent water courses take placeS d Se>eSeparate toilets/bathrooms, wherever required, Screened from those from men (marked in vernacular) are to EnvironmentalC.7.3 Sanitaon an ewage be provided for women MoRTH: 114.14 Contractor Specialist of CSC,Y > Adequate water supply is to be provided in all toilets and urinals HPRIDC> Night soil can be disposed of with the help of local municipal extractor or disposed of by putting layer of it atthe bottom of a permanent tank prepared for the purpose and covered with 15 cm. layer of waste or refuseand then covered with a layer of earth for a fortnight.
The Contractor will provide garbage bins in the camps and ensure that these are regularly emptied and disposed off inC.7.4 Waste Disposal a hygienic manner as per the Appendix 21Comprehensive Solid Waste Management Plan approved by the Environmental Specialist of CSC.
C.8 Contractor's Demobilization
Louis Berger Group, INC, USA 42
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
S. Environmental Issue Management Measures Reference ResponsibilityNo. EvrnetlIse MngmnMesrsdocument_________ _________
_L_and ^ - 4
The HPRIDC will undertake seasonal monitoring of air, water, noise and soil quality through an approved moniorng Environmental
C.8.1 Environmental Conditions agency. The parameters to be monitored, frequency and duration of monitoring as well as the locations to be monitored Appendix 13 Contractor Specialist of CSC and
will be as per the Monitoring Plan prepared. National Standard of Air, Noise and Water given in Appendix-13. HPRIDC, NHAI
Continuous Communit The Environmental Specialist of CSC will have continuous interactions with local people around the project area to Environmental Environmental
C.8.2 .a.tctin y ensure that the construction activibes are not causing undue inconvenience to the locals residing in the vicinity of project Specialist of CSC H andPartcipation site under construction due to noise, dust or disposal of debris etc. HPRIDC, NHAI
Contractor will prepare site restoration plans, which will be approved by the Environmental Specialist of CSC. Theclean-up and restoration operatons are to be implemented by the Contractor prior to demobilization. The Contractor willclear all temporary structures; dispose all garbage, night soils and POL (Petroleum, Oil and Lubricants) wastes as per
- OComprehensive Waste Management Plan and as approved by CSC.
0.8.3 Restoration and All disposal pits or trenches will be filled in and effectively sealed off. Residual topsoil, if any will be distributed on EnvironmentalRehabilittion adjoining/ proximate barren land or areas identified by the Contractor and approved by the Environmental Specialist of Contractor HPRIDC
CSC in a layer of thickness of 75 mm-150 mm.All construction zones and facilities including culverts, road-side areas, camps, Hot Mix plant sites, Crushers, batchingplant sites and any other area used/affected due to the project operations will be left clean and tidy, at the Contractorsexpense, to the entire satisfaction to the Environmental Specialist of CSC.
The HPRIDC will undertake seasonal monitoring of air, water, noise and soil quality through an approved montoring Environmental
C.8.1 Environmental Conditions agency. The parameters to be monitored, frequency and duration of monitoring as well as the locations to be monitored Appendix 13 Contractor Specialist of CSC and
will be as per the Monitoring Plan prepared. National Standard of Air, Noise and Water given in Appendix-13. HPRIDC, NHAI
. . The Environmental Specialist of CSC will have continuous interactions with local people around the project area to Environmental Environmental
C.8.2 cipation ensure that the construction activities are not causing undue inconvenience to the locals residing in the vicinity of Specialist of S Specialist of CSC andartcipaton project site under constructon due to noise, dust or disposal of debris etc. HPRIDC, NHAI
Louis Berger Group, INC, USA 43
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
NS. Environmental Issue Management Measures Referne ResponsiboityNo ..S......... document
Contractor will prepare site restorabon plans, which will be approved by the Environmental Specialist of CSC. Theclean-up and restoration operabons are to be implemented by the Contractor pror to demobilization. The Contractor willclear all temporary structures; dispose all garbage, night soils and POL (Petroleum, Oil and Lubricants) wastes as perClean-up Operations, Comprehensive Waste Management Plan and as approved by CSC.C.8.3 Restoration and All disposal pits or trenches will be filled in and effectively sealed off. Residual topsoil, if any will be distributed on EnvironmentalRehabilitation adjoining/ proximate barren land or areas identified by the Contractor and approved by the Environmental Specialist of Contractor Specialist of CSC,CSC in a layer of thickness of 75 mm-150 mm.
HPRIDCAll construction zones and facilities including culverts, road-side areas, camps, Hot Mix plant sftes, Crushers, batchingplant sites and any other area used/affected due to the project operations will be left clean and tidy, at the Contractor'sexpense, to the entire satisfaction to the Environmental Specialist of CSC.
C.9 Construction Activities by HPRIDC/PWD
The plantation at the following locations will be implemented by the HPRIDC through the State Forest Department;i) Roadside,ii) enhancement sites,
C.9.1 Tree Plantation iii) Forest land Appendix 21 Department HPRIDCiv) Community Forestaton.A forest area management plan is provided in Appendix 18. Appendix 19 is the list of various enhancements sitesincluded in the project.
Oxbow lands and other Development of the enhancement sites identified where PWD land is already available are provided in Appendix 22 isC.9.2 left over portions of the the list of recommended enhancement sites Appendix 22 State PWD HPRIDCexisting project road Appendix 19 is the list of various enhancements sites identified Apendix 2
Enhancement To ParkingFacilities -Truck, Taxi Typical designs required for parking areas are provided in the appendix-21 design drawings. In all busy junctions, it isC9.3 Cars And Bus Parking necessary to construct parking areas separately. Appendix 19 and 21Facilities Proposed parking areas are provided in the Appendix -19.
OPERATION STAGE
Louis Berger Group, INC, USA 44
Himachal State Roads Project Environmental Manage-ment plan (Jahu-Kalkhar Section)
SO. Environmental Issue Management Measures Responsibility
Activities to be Carried Out by the HPRIDC/ PWD
The HPRIDC will monitor the operational performance of the various mitigation/ enhancement measures carried out as
0.1 Monitoring Operabon a part of the project. E PICPD HRD/WPerformance The indicators selected for monitoring include the survival rate of trees; utility of enhancement provision made under the EA HPRIDC/PWD HPRIDC/PWD
project; status of rehabilitation of borrow areas; and effectiveness of noise barriers.
0.2 Maintenance of Drainage PWD will ensure that all drains (side drains, median drain and all cross drainages) are periodically cleared especially EA HPRIDC/PWD HPRIDC/PWDbefore monsoon season to facilitate the quick passage of rainwater and avoid flooding.
The periodic monitoring of the ambient air quality, noise level, water (both ground and surface water) quality, soil quality Pollution Monitorn0.3 Pollution Monitoring in the selected locations as suggested in pollution monitoring plan through the HPCB or its approved monioring EA Agency HPRIDC/PWD
agency.
Soil Erosion and Visual monitoring and inspection of soil erosion at borrow areas, quarries (if closed and rehabilitated), embankments0.4. Monitoring of Borrow and other places expected to be affected, will be carded out once in every three months as suggested in monitoring EA HPRIDC/PWD HPRIDC/PWD
Areas plan.
Changes in Land Use Necessary hoardings will be erected indicating the availability of ROW and legal charges for encroachment of RoW. HPRIDC/PWD, HPRIDC/PWDD0.5 EA Revenue
Pattern Budgetary provisions are to be made to control the ribbon development along project road. Department and HPRIDC/PWD
0.6 Removal of Dead Animals Dead animals lying on the road should be removed and buried away from the nearby residences. EA Local Authorities HPRIDC/ PWD
Public awareness on However the public will be advised to construct the noise barriers such as walls, double glazed windows and tree0.7 Noise levels and Health plantation between the roads and their property The public awareness is necessary regarding the human health through HPRIDC HPRIDC
Affects the news papers and consultations and distribution of pamphlets during the operation stage.
Louis Berger Group, INC, USA 45
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
4 ENVIRONMENTAL ENHANCEMENT MEASURES
The various environmental enhancement measures considered include* Provision for additional parking areas /Oxbow land development* Rest area development (Development and Improvement of Oxbow land)* Bus bays or bus lay bys* Bus waiting sheds locally known as 'Rain shelters'* Cultural property enhancement
* Development of scenic spots along the project roads (tourism plus safety)* Improvement to drinking water sources
Further a number of environmental enhancement measures in addition to the impact mitigation and avoidance measures would also be cardedout as a part of the project. This include,
* Enhancement tree planting along the oxbow lands (2 ..760 km including realignmentlocations) and the other left over portions of the original PWD land provided in appendix12.
* Cultural property enhancement as a part of the cultural property rehabilitation plan(Appendix-3).
* Public amenities such as bus lay bys (all new facility enhancement), rain shelters (in additionto the compensatory rain shelters for lost ones), comfort stations (toilets) at parking areasand at rain shelters (Appednix-20 Design drawings for Environmental enhancement.
* Information boards for the tourist, pilgrimage and other important structures of importance
4.1 DISPLAY OF TOURIST LEVEL INFORMATIONThis relates to the information boards with regards to the tourism and pilgrimage areas so that all these structures are properly integrated to theproject roads. This will be a positive step towards tourisms prospects of the State.
HP is a tourist area and clear display of the name of tourist locations including names of rivers the lengths and catchments areas would be avery positive step for encouraging tourism with investment from tourism as well as PWD. The PIA has no major tourist attractive locations.
Provision for tourist information/sign boards at the access roads is provided in Appendix 20. This is also included in the BOQ NO 11Environmental mitigation works.
Further in this project, many of the existing oxbow land Appendix -22 areas could be developed in to comfort stations depending up on thelocation.
4.2 INTEGRATION OF VALLEY VIEW LOCATIONSThere no valley view locations in this section..
4.3 ENHANCEMENT OF SAFETY FEATURES IN THE DESIGN (BUS BAYS, RAIN SHELTER ANDPARKING AREAS)
For health and safety of the road users, it is necessary to maximise the utilisation of the existing space. In this regards it will be possible toprovide bus bays, rain shelter and a number of parking areas (including breakdown yard) in all available spaces.
This includes all parking areas and all new bus lay bys, rain shelters, and cultural property enhancement.
4.3.1 SAFETY ENHANCEMENT -Bus LAY BYSBus lay bays have been provided in almost all areas of existing rain shelter locations for the project road depending up on the available space.A typical bus lay bys is provided in Appendix 21 design drawings. These measures will improve public convenience and safety and intended toallow free flow of traffic along the corridor.
~~~~~~YT ; Tz-..... TCTMIr A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Enforcement of all traffic safety measures is important at the bus bay locations. Right and left sections of bus bay shall not be facing to eachother at the same location. There should be pedestrian crossing facilities and proper signing of bus stops. Entry of other vehicles to the bus lay- bys must be prohibited. Taking all these aspects into consideration, bus lay - bys have been built into the designs as shown in Appendix -21and necessary provisions provided in the BOQ relating to Civil contract works.
4.3.2 ENHANCEMENT OF RAIN SHELTER/ BUS SHELTERS/BUS WAITING SHEDS
Due to the larger presence of pedestrians (in the built up areas) and rainfall conditions, rain shelters are required where ever it is presentlylocated. This is provided as an impact mitigation measures. In addition to this there are several others wherever the bus bays have beenprovided. During construction phase, the project authorities need to consult the local municipal and Panchayat authorities for finalizing theexact locations to avoid the conflict with the local interest (Any new area development plan) groups. There are provisions in the Project for thenecessary budget and included within the BOQ relating to civil construction Contract for implementation. It is also required to include the toiletfacilities in the design drawings to increase the usefulness of the rain shelter.
This aspect has been included in the BOQ bill no 11 titled Environmental mitigation works.
4.3.3 ENHANCEMENT TO PARKING FACILITIES -TRUCK, TAXI CARS AND BUS PARKING FACILITIES
Since this road is a link to the industrial area Una and Mehatpur and to Tourist area Mandi where in numerous trucks and Taxi operatethroughout the year. These trucks require parking areas and breakdown yards to avoid hindrance to the free flow of traffic.
Various studies carried out during the early preparation stage indicated the requirement of proper parking space. Therefore proper parkingareas and use is required as a part of good traffic management.
Typical designs required for parking areas are provided in the appendix-21 design drawings. In all busy junctions, it is necessary to constructparking areas separately.
Proposed parking areas are provided in the Appendix -19. There will be provision for separate parking space for these vehicles. This is atypical example. If such land kept unutilized could be encroached by individuals and could lead to huge loss for the local communities.Proposed Parking Area Design For TAXI is provided in the Appendix-1 9. Design drawings for Environmental management.
The space required will be of the order of 200 sq.m. This space should be secure and away from the existing available corridor. Raisedfootpaths will be required at these locations. The project will develop parking areas as shown in Appendix-19, provided land is alreadyavailable. Separate design for typical parking areas for cars, trucks etc are provided Appendix-21. Appendix-1 9 is the proposed parking areaswhere in no additional land acquisition would be required. All these area in the oxbow lands and other left over portions of the project roadROW.
4.4 ENHANCEMENT OF CULTURAL PROPERTIESA cultural property rehabilitation plan will be prepared utilizing the efforts of a cultural property specialist. This plan will have provisions forEnvironmental enhancement measures for the cultural properties that would be impacted as well as that are close to the highway. Those thatwill be impacted will be dealt with in the Resettlement Action Plan (RAP) and those that are close to the road would be dealt with in theEnvironmental Management Plan (EMP) for implementation by the Contractor.
4.4.1 ARCHAEOLOGICAL STRUCTURESICULTURAL PROPERTY AND MONUMENTS
No archaeological structures are there in the PIA
4.5 COMMUNITY SPACE
4.5.1 PLANTING ALONG THE OXBOW LAND (LEFT OVER PORTION OF THE EXISTING ROAD)
The tree planting explained in this section is different form the compensatory afforestation as per the tree planting strategy developedaccording to the Environmental Management Plan (EMP). Trees and shrubs need to be planted in all oxbow land areas available along theproject roads. To avoid any future encroachments no land shall be kept unutilised. Appendix-22 provides a list of oxbow land locationsavailable for various kind of development for the local communities.
Some of these locations could be useful for the development of the municipal solid waste disposal areas, while some other could be useful for
the development of comfort stations and rest areas. This part is provided in the remaining section of the document.
4.5.2 DEVELOPMENT OF REALIGNMENTS AND BRIDGE RELOCATION AREASAs a part of environmental management, it is necessary to develop the left over portion (oxbow land) of the (1) realignments and (2) new bridgealignments sections. These areas will be heavily planted and parking areas developed. Depending up on the space available, a full-scale restarea can also be developed in such locations. In almost all bridge sites, the environmental survey has identified solid waste disposal areas.
A 7
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
This should not be allowed to continue instead a certain area in the vicinity should be used to pile up the municipal waste. Local bodies shouldbe entrusted to dispose this safely on a weekly or monthly basis.
Municipal waste disposal for the 5 settlements identified along the project road is provided in BOQ.
I nuii Rpropr flrnm, 'rJ T T, A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
5 MONITORING PROGRAMME
The monitoring programme consists of performance indicators, reporting formats and necessary budgetary provisions. Out of this thebudgetary provisions are confidential and are not supposed to be part of the disclosure statement. Thebudgetary statements are provided in section 7.0 for the purpose of evaluation of the EMP.
The contractors monitoring plan should be in accordance with the baseline environmental monitoring, locations provided in the Environmental
impact assessment report.
The monitoring plan has the following objective* To ensure effective implementation of EMP* To comply with all applicable environmental, safety, labour and local legislation* To ensure that public opinions and obligations are taken in to account and respected to the required satisfaction level
* To modify the mitigation measures or implementing additional measures, if required
5.1 PERFORMANCE INDICATORS
Environmental components identified of a particular significance in affecting the environment at critical locations have been suggested as
performance indicators (PIS). For example near the construction site, a thick layer of dust over the near by vegetation/leaf is an indication that
the dust control measures are not effective. The performance indicators shall be evaluated under three heads as;
* Environmental condition indicators to determine efficacy of environmental management measures in control of air, noise, water and
soil pollution.* Environmental management indicators to determine compliance with the suggested environmental management measures
* Operational performance indicators have also been devised to determine efficacy and utility of the proposed mitigation measures
The performance indicators and monitoring plans prepared for the Jahu-Kalkhar section are presented in table 5.1. Details of the performance
indicative parameters for each of the component have to be identified and reported during all stages of the implementation.
Table 5.1: Performance Indicators and Monitoring plan
MP No. of Trees Planted (Total) Road side and other Post construction stage Forest Department and
* No. of Trees under Compensatory Afforestation plantation areas HPRIDC
* No. of Trees Planted along Road sides* No. of Trees planted at other locations (such as
camps, borrow areas, debris disposal sites andplant areas)
* No. of trees planted at enhancement sites
PI Survival Rate Trees Planted (Average) Road side and other Post construction stage Forest Department and
* Compensatory Afforestation plantation areas HPRIDC
* Road side Plantation* Other locations (such as camps, borrow areas,
debris disposal sites and plant areas)* Enhancement sites
MP * Area of Forest land Diverted (in hac.) Area treated with Post construction stage ContractorBioengineering
PI * Area treated with Bioenginernng interventions (inhac.)
PI * No. of Borrow Areas identified and verified Borrow Area and Pre Construction Contractor
* No. of sites for which Restoration Plans have Quarriesbeen prepared
* No. of Site Restored and Rehabilitated* No. of Sites handed over
* . ,, *.,,~, *,e:AO
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
PI * No. of Quarry Areas identified and vedified Borrow Area and Pre Construction Contractor* No. of sites Restoration Plans are required and Quarries
have been prepared* No. of Site Restored and Rehabilitated* No. of Sites handed over
cp Quantity of Debris and Spoils to be disposed off Disposal sites Construction Contractor* No. of locations finalised for Debrs disposal* Quantity of Debris and Spoils disposed off* No. of locations for which Rehabilitation works
have been completed
PI * No. of location/s identified for the Construction Construction Camps Pre Construction Contractorcamp and Construction Plant sites and Plant Sites
* No. of location/s approved* Lay-ouYs Approved* No. of sites for which Site Restoration and
Rehabilitation has been completed
PI * No. of Trees to be Cut Tree cutting Pre Construction HPRIDC* No. of Trees cut* % Progress on the tree removal
PI No. of Locations identified for temporary storage areas Storage of excavated Pre Construction Contractorfor storage of the excavated materials to be used in materials and Constructionembankment and sub grade
MP Statutory environmental monitoring as per the Environmental status at Construction Contractorconditions stipulated in the consents / permissions Construction Plant Sitesissued by PCB
MP Environmental parameter monitoring in accordance Air Quality Noise Construction and HPRIDC throughwith the frequency and duration of monitoring as well Quality Soil Operation external agency.as the locations as per the Monitoring Plan given in Quality WaterTable 5.2 Quality
MP Before the onset of monsoon all the debris/excavated Silting of Water bodies Construction Contractor and shouldmaterial shall be cleaned from the work sites and be supervised by thedisposed of at the pre-identified approved locations. Environmental
Specialist of CSC.PI Implementation of enhancement measures for Enhancements Construction Contractor
* Parking areas* Tourism* Cultural properties* Religious Properties* Other oxbow land development.
PI * No. of Training Sessions Organised for Training Imparted Construction and HPRIDCi. Departmental Staff Operational faceii. Contractors
iii. Combined* No. of People Trained
iv. Departmental Staffv. Contractors
PI Slope Protection Measures Work sites Construction Contractor* Length (by type)* No. of Locations
PI Drainage Work sites Construction Contractor* Length (by type)* No. of Locations
TnliC Rprapr 1.r-n M(' I 1 A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
PI Safety Provisions Work sites Construction Contractor
* Signage (by type and no.)* Guard Rails
______ * Guide RailsNumber of Chute Drains Provided Work sites Construction Contractor
PI Soil erosion prevention measures Work sites Construction Contractor
* Silt Fencing (No. of Locations and Length)* Stone Pitching (No. of locations and Quantity)* Any Other (Grass seeding etc.)
PI Utility Ducts Utility ducts Construction Contractor
* Length provided* No. of Locations
PI Water Sources Work sites Construction Contractor
* No. of Sources Protected* No. of Relocated
PI No. of HIV awareness sessions conducted Construction Stage HPRIDC
PI No. of safety awareness sessions conducted Construction Stage HPRIDC
MP No. of awareness sessions for educating the public Operation Stage HPRIDC
about road safety and other environmental aspects(such as waste dumping, preservation of enhancedsites, pollution and health impacts etc.)
5.2 MONITORING PLAN FOR ENVIRONMENTAL CONDITIONS
For each of the environmental condition indicators, the monitorng plan specifies the parameters to be monitored, location of the monitorng
sites, frequency and duration of monitoring. The monitoring plan also specifies the applicable standards, implementation and supervising
responsibilities. The monitoring plan and details of monitoring locations for environmental condition indicators of the project during the
construction and operation stage are presented in Table 5.2. The monitoring will be carried out by HPRIDC/PWD through the approved agency
and will be supervised by the Environmental Experts of the CSC and HPRIDC/PWD.
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Table 5.2: Environmental monitoring for Air, water, noise and SoilAttribute Timing Parametere Special guidance Standards Frequency Duratlon Location No of Implementation
SamplesAtr Constructio CO, NOx, High Volume sampler to be located Air (prevention and Once in every season 24 hors sampling Construction Plant Sites and 3 HPRIDC/PWDn SPM, RPM 50 m from the plant in the down wind control of pollution)rules for three seasons Work Zonesand S02 direction. Use method specified by CPCB,1994 (except monsoon
CPCB for Analysis season) per year foreach year ofconstruction
Operation Once in summer and Road side 1 HPRIDC/PWDwinter three years
Water Constructio Important Grab sample collected from source Indian standards for One in every season for Grab sampling Drinking water samples from 3 HPRIDC/PWDn Factors as and analyse as per standard methods inland surface waters all four seasons the labour camps and fromdecided by for examination (IS:2296,1982) and for hand pumps Surface waterthe drinking water from the water courses nearENV.Speciali (IS:10500-1991) the work sitesOperation st of the Surface water sources 1 HPRIDC/PWDCSC
Noise Constructio Noise Levels Equivalent noise levels using and MOEF Noise rules Once in every season Leq in dB(A) of day time Near the construction camps, As desired HPRIDC/PWDn on dB (A) integrated noise level meter kept at a 2000 during construction and night time working zones, sensitivescale distance of 15 m from edge of stage receptors and constructionpavement plant sitesOperation
Once every seasons for Sensitive receptors As desired HPRIDC/PWD5 year after completionof construction activitySoil 1 Constructio Monitoring of Sample of soil collectd to acidified Threshhold for each During the pre & post Grab sampling Construction Camp/plant 3 HPRIDC/PWDn Pb, SAR and and analysed using absorption contaminent set by IRIS monsoon season each sites and productiveOil and spectrumetre data base of USPEA year for the entire agricultural lands abuttingGrease unitil Stdards are construction period traffic detours and trafficavailable to use diversions and major
intersections.Operation Surface water sample 1 HPRIDC/PWD
Accidental spillage of hazardous and non hazardous substances need to be dealt with as special cases largely depends on the circumstances including state of the substance (liquid or Soilid) etc.
Louis Berger Group, INC, USA 52
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Monitoring shall be carried out at all locations used for collection of primary data in the study.
5.3 REPORTING SYSTEM
Reporting system for the suggested monitonng programme operates at two levels:* Reporting for environmental condition indicators and environmental management indicators* Reporting for operational performance indicators at the HPRIDC/PWD level.
Environmental monitoring involves regular checking of the environmental management issues detailed in the EMP and to ascertainwhether the mitigation measures are achieving their objectives, according to the EMP, with the progress of the works. It provides thenecessary feedback for Project management to keep the programme on schedule will still achieving the expected outcomes.
The Contractor, CSC and HPRIDC/PWD operate the reporting system for environmental conditions and environmental managementindicators. The reporting system is presented in Table 5.3. Reporting formats for Contractors and Construction Supervision consultantshave been prepared, which will form the basis of the implementation by the Contractor and monitoring by the CSC and HPRIDC/PWD.The list of reporting formats prepared for the Project is presented in Table 5.4 and Formats are presented in Appendix-14.
* The reporting system will start with the Construction Contractor who is the main executor of the implementation activities.The Contractor will report to the Construction Supervision Consultant, who in turn shall report to the HPRIDC/PWD. As acheck on that the Independent Environmental Review Consultant for EMP compliance will canyout the independent reviewof EMP compliance and submit a draft and final half yearly report to HPRIDC/PWD along with a note specifying the criticalissues and suggested actions to be take by the HPRIDC/ CSC/ Contractor.
* The Contractor will submit monthly and quarterly environmental compliance reports along with formal monthly and quarteriyreporting to the CSC.
* The CSC will submit separate quarterly environmental monitoring reports to HPRIDC/PWD in addition to submission of thesummary of the activities of the month in the formal monthly report including any deviations and corrective actions
* HPRIDC will be responsible for the preparation of the targets for identified non compliances in association with independentenvironmental reviewer for the EMP compliance.
* Solutions for further effective implementation may also emerge as a result of the compliance monitoring reports.* Photographic records will be kept to provide useful environmental monitoring tools. All material source points, disposal
locations, plant locations, camp locations, crusher locations etc should be photographed and kept as a record to understand the land use
* A full record of construction activities will be kept as part of normal Contractmonitoring system. Reporting and Monitoring Systems for various stages of construction and related activities have beenproposed in Table 5.3 and 5.4 are to ensure timely and effective implementation of the EMP.
* The operation stage monitoring reports may be annual or biannual, provided the Project Environmental Completion Reportshows that the implementation was satisfactory.
This reporting will be as follows:>0 Reporting by the Contractor to the CSC
Reporting by SC to HPRIDC/PWDReporting by HPRIDC/PWD for the information of all interested parties
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Table 5.3: Reporting System
Construction Stage
Monitoring of Before start of work Regular Quarterly Quarterly Half yearlyConstruction site andconstruction camp
Pollution Monitoring As required As required Quarterly Quarterly After Monitoring Half yearly
Monitoring of Implementation Regular Quarterly Quarterly Half yearly YearlyEnhancements
Top Soil preservations Weekly Weekly Monthly Quarterly Half yearly Yearly
Borrow area/quarry Regular Weekly Monthly Quarterly Half yearly Yearlyarea/Debris Disposalarea
Tree cutting Weekly Weekly Monthly Quarterly Half yearly Yearly
Tree plantation Monthly Monthly Monthly Quarterly Half yearly Yearly
Operation Stage
Pollution Monitoring As per monitoring After monitoring Twice duringplan operation phase
Table 5.4: Summary Details of Reporting Formats
Identification of temporary Pre-Construction One Time One Time One Timestorage yards andManagement Plan
EMS1 Approval of Construction Pre-Construction One Time One Time One TimeCamp/ Plant site and itsManagement Plan .
EMS2 Approval of Borrow Pre-Construction General -One Time Regular QuarterlyManagement Plan(General and Specific redevelopmentSpecific) plan -one for each
borrow areaSolid Waste Management Plan Pre-Construction General -One Time Regular Quarterly(General and Specific) Specific plan -one for
each camp or plant siteDebris generated by the During Through out the Regular quarterlyhuillward side widening. cutting construction construction period duringof hill slopes widening
EMS3 Construction Camp and Plant Construction Monthly Regular QuarterlySite Management
I - n_,CZr- .lMTC' I TC A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
EMS4 Top Soil Management Construction Monthly Regular Quarterly
EMS 5 Pollution control and Construction Monthly Regular Quarterlyconstruction plantsPollution Monitoring Construction and Quarterly
Operation
EMS 6 Vehicles and Pollution Control Construction Monthly Regular Quarterly
EMS 7 Details of the DG sets and Construction Monthly Regular Quarterlypollution control
EMS 8 Details of Oil Storage Construction Monthly Regular Quarterly
EMS 9 Working at Water courses and Construction Monthly Regular QuarterlyPollution Control
EMS 10 Details of Water Extraction Construction Monthly Regular Quarterly
EMS 11 Details of Personal Protective Construction Monthly Regular QuarterlyEquipment
EMS 12 Status of Consent for Water Construction Half yearly Half yearly Half yearlyextraction
EMS 13 Deviations and Corrective Construction - Monthly QuarterlyActions
EMP14 Tree Plantation Construction and Quarterly QuarterlyOperation I
EMS 15 Plantation of Shrubs and grass Construction and As applicable As Applicable As applicableOperation
EMS 16 Implementation of Construction Monthly Regular QuarterlyEnhancement Measures forCultural Properties, parkingI areas and Incidental SpacesStatus Regarding Rehabilitation Operation Half yearlyof Borrow Areas
Noise barrier Construction Operation As applicable Quarterly Quarterly
Survival rate of plants Operation Quarterly Quarterly
Debris generated by the Durng Through out theEMS 17 hiilward side widening, cutting construction construction period during Regular quarterly
The Environmental Officer of CSC can make required changes in the Formats specified in Appendix 14 of EMP to ensure effectivereporting of environmental issues. Some of the formats should be included in the Request for Inspection such as Debris disposal areaapproval request. For making any required changes in the frequency of reporting and change in the contents of the report for effectiveand simple for implementation and monitoring, CSC should discuss the reporting formats with the Contractor and HPRIDC. This will notonly ensure that the environmental provisions are addressed but also link the satisfactory compliance to environmental proceduresprior to approval of the Interim Payment Certificate (IPC) by the Engineer. In the regular monthly meeting the environmental aspectsshould also be discussed and the staff responsible for the implementation of the environmental management from the Contractor,HPRIDC/PWD and CSC should also be present.
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
6 INSTITUTIONAL ARRANGEMENTS
Institutional arrangements are intended to achieve certain level of quality in the project during implementation of various projectcomponents by the Government of Himachal Pradesh (GOHP) as specified by the various conditions of loan agreement between theWordd Bank and the GOHP. These are basically to meet the Worid Bank safe guard policies that in turn will make sure that the countrylaws (Indian laws and regulations) are not violated during the pre construction, construction and Operational (defect liability period)stages of the project.
HPRIDC is headed by the Chief Engineer who will be responsible for the successful implementation of the Project. The Chief Engineeris also the Project Director in the HPRIDC set up for the implementation of the project. The Project director (PD) will be assisted byContract Management Unit (CMU), Environmental and Social Expert at the head office. The environmental officer at the HQ will be aconservator of Forest (CF) with 1 Assistant Engineer to coordinate the implementation of the Environmental management plan atHPRIDC head quarters. The environmental officer will be the head of the Environmental management Unit (EMU). The Environmentalsocial management Unit (ESMU)on the other hand will consists of EMU and social management unit (SMU). The SMU will be headedby a Social Development Officer (SDO). The Project Director will be heading the over all functioning of the Environmental and SocialManagement Unit (ESMU).
There CMUs located at Shimla will be in charge of the project implementation of this contract. Each CMU will have the following staff
1 Assistant Engineer for Environmental management1 Assistant Engineer for RAP implementation
>O 1 Assistant Engineer for Encumbrances>O 1 Assistant Engineer for Technical
The executive engineers (EEs) and supporting staff as employers representatives nominated for the project will be responsible for theimplementation of the Project under the division. At present HPRIDC is a small organization. Competent highway professionals can bedrawn from the large pool of efficient engineers of the Public Works Department. The Environmental and Social Expert of HPRIDC willlook after the environmental issues during the project preparation, implementation and operation with the assistance of theEnvironmental Specialist of the Project Design and Environmental Officer (EO) of the Construction Supervision Consultant. Thestructure is shown in Figure 6.1.
The Contract Supervision Consultants (CSC) has planned to have The following staff required as given below:
678 key professional staff months and 816 sub key professional staff months have been taken as per RFP & there are 6 Nos. ResidentEngineers, 6 Nos. Assistant Resident Engineers in addition to Team Leader ('Engineer')and following professionals:1) Pavement/material Specialist2) ProcuremenVContract management Specialist3) Structural/Bridge Engineer4) Senior material Engineer5) Highway/Pavement Engineers-6 Nos.6) Material Engineersx37) Bridge Engineersx48) Bio Engineer Specialist9) Senior Surveyor10) Geo Technical Specialist11) Survey/Field Engineers-12 Nos.12) Environmental Engineers-3 nos.13)Bio-Engg. Local Staff
14)Assistant Geo Technical engineer
The Environmental monitoring during the design and construction phase will be carred out by an Independent Environmental Reviewerwho has been appointed for this project. During the operation stage monitoring will be carried out by HPRIDC with the help of theenvironmental monitoring agencies approved by the State or Central Pollution Control Board.
T ai Tlrao GrrlrTXTt' IT T A r
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Dre .udr.
. . m ..7 -
Ernviruaueutk
= & a W \, CoX ft"#
- i -1E | | . .. .X lemetao of .............Eniomna Nb gmn Plan
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
6.1 INTEGRATION OF EMP WITHIN THE PROJECT
Table 3.1 is the Environmental Management Action Plan (EMAP), which describes the Environmental mitigation measures for projectimpact management.
Detailed environmental monitoring plans for air, noise, soil and water quality are presented in Table 5.2.
Tentative reporting formats for the reporting of the environmental aspects of the Contract are presented in the EMP in Appendix 14. EMPwill be reviewed by the Construction supervision Consultants (CSC) in discussion with the Contractor and HPRIDC/PWD within twomonths of mobilization of the Construction Contractor or before commencement of the works. The environmental measures suggested aspart of contract broadly falls into the following categories:
* Specific items shown in the volume of drawings, specifications and in the BOQ and summarized in this EMP.* Management measures that are stand-alone items and can be implemented by the Contractor
(as provision of oil interceptors, regulatory monitoring of environmental components etc)* Management measures that are to be taken up by the Contractor as part of permanent works in accordance with good
engineering practices* Enhancement measures directly related to the road development to improve public safety and convenience such as parking
areas, bus bays, bus waiting sheds etc all new and are part of road safety enhancement* Enhancement measures including measures indirectly related to the road construction
(enhancement of cultural properties, common property resources such as wastewater ponds etc).
The environmental management measures have been incorporated into the permanent and temporary work items. Separate provisionshave been made in the BOO for the items, which can be quantified separately. Other items that are specified but not priced separately inthe BOQ are to be included in the Contractors rates.
T1 2 _ rT1_T- 1 TZ A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
7 TRAINING AND CAPACITYBUILDING PLAN
It is a fact that the design consultants who prepared the Environmental Management plan (EMP) after detailed Environmental ImpactAssessment (EIA) has acquired considerable knowledge about the project, people as well as their resources. This need to be transferredto the concerned CSC officials/engineers. This does not show supremacy of the design consultants over the CSC but smooth transfer ofthe experience gained during various studies. This aspect was not respected and such training/workshop was hardly held. Consideringthis aspect and the over all requirement the following training programmes are being planned to various groups as provided in the Table-7.1.
Table 7.1: Environmental Management training programmes
1 Legal and policy requirements Engineers of the PWD World bank Completed in Junefrom all ranks safeguard polices 2006
and all Indian laws
2 Environmental screening and scoping SPCB and PWD Completed in Decfor World bank funded projects enqineers 2006
3 Environmental impact Assessment of PWD Engineers EA process and the March April 2007HP State roads project preparation of EMP
4 Forest /wildlife and Biodiversity issues PWD engineers Special studies doin HP state roads project required during the
EA process and itsrequirement.
5 Environmental management plan PWD Engineers and Implementation of dothe CSC Environmental
- management Plan
6 Public consultation community PWD Engineers Participatory doparticipation and Focus group process in the EA
discussions in HP State Roads Project preparation
7 Role of IT in the EA process PWD engineers InterneVGIS/comput doer/printer etc
b) Training plan
The project provision for training plan will be carried out as provided in the table no 7.2 and 7.3 . These training programmes are not partof the Contractors plan and estimates but will be a part of the project cost that includes intuitional strengthening, capacity building andtraining. Table 7.2 provides training modules. Total earmarked training cost is INR 5.0 million ( INR 50 lakhs). Except one trainingprogramme on bio engineering in Nepal and one in Malasia no other training programme has been envisaged outside the country.The basic objective of giving training to different Stakeholder is to enhance their capabilities for implementation of EnvironmentManagement and Monitorng Plan. It is recommended that training be given at least 4 times both offsite and on site
Before Start of Construction WorkDuring Construction* During Construction* During construction at site* Before de-mobilization of Contractor
)o After Construction before Start of Monitoring
Table 7.2 lists all the raining modules developed.
Table 7.2: Training ModuleS. No. Training Recipients |Mode of Training Environmental Aspects to be Training Conducting
l T i covered in training modules I AgencySESSION-I (BEFORE START OF CONSTRUCTION WORK )
Module-I Staff of HPRIDC, staff of CSC, PWD/ Lecture Sessions, Overview. Need and Value of CSCCMU engineers, Engineering Staff of Presentation and Environment Assessmentcontractor and collaborating discussionGovemment agencies
Module-Il Staff of HPRIDC, staff of CSC, PWD/ Lecture Sessions, Institutional Set Up CSCCMU engineers, Engineering Staff of Workshops & Role and Responsibility of Stake
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
SI. No. Training Recipients Mode of Training Environmental Aspects to be Training Conductingcovered in training modules Agency
contractor and collaborating Presentation Holders and ContractualGovemment agencies, obligations
Module-lIl Staff of HPRIDC involved in the project, Lecture Sessions, Overall generic Environment CSCstaff of CSC, PWD engineers involved Workshops & Issues, Regulations & Statuaryin construction, contractor, and Presentation requirements and Mitigationcollaborating Government agencies Measures
SESSION -11Module-IV Staff of HPRIDC, staff of CSC, PWD / Lectures; Project related Project related CSC
CMU engineers, Engineering Staff of Demonstration environmental issues andcontractor and other concerned sessions mitigation measuresagencies.
Module-V Staff of HPRIDC (Nodal Level), staff of Group Discussions Environmentally Sound CSCCSC, PWD / CMU engineers, and action plan for Construction Management &Engineering Staff of contractor. the project Environmentally, Sustainable
.operations of HighwaysModule-VI Staff of HPRIDC staff of CSC, PWD / Lectures; Group Supervision and Monitoring, CSC
CMU engineers, Engineering Staff of Discussions Reporting Formatscontractor.
Module for Training during ConstructionModule-I Staff of HPRIDC involved in the project, Lecture Sessions, Implementation of Environment CSC
staff of CSC, PWD engineers involved Presentation & Management Plan,in construction, contractor Workshops Environmental Friendly
Construction Methodology andWorkers Safety durngConstruction
Module-Il Staff of HPRIDC involved in the project, Lecture Sessions, Interactive discussion, Monitoring CSCstaff of CSC, PWD engineers involved Workshops & and Reporting Systemin construction, contractor Presentation
Module for Training during Cons truction at SiteModule-I PWD / CMU engineers, Staff of CSC, Lecture Sessions, Environmental Friendly CSC
All Staff of contractor Workshops & Construction Methodology andPresentation Workers Safety
Module-Il PWD / CMU engineers, Staff of CSC, Practical on Site Safety Practices CSCAll Staff of contractor.
Module for Training before Contrac or DemobilizationModule-I HPRIDC Staff, PWD/ CMU engineers, Lecture, Restoration of Site CSC
Staff of CSC, Engineering Staff of PresentationContractor. Sessions
Module-11 HPRIDC Staff, PWD/ CMU engineers, Lecture Sessions, Reporting Formats for CSCStaff of CSC, Engineering Staff of Presentation, RestorationContractor Workshop and
lesson leamedAfter Construction before Start of Monitoring
Module-I HPRIDC Staff, PWD/ CMU engineers Lecture Sessions, Environment Monitoring CSCPresentation and
WorkshopModule-Il HPRIDC Staff, PWD/ CMU engineers Lecture Sessions, Reporting Formats CSC
Presentation,Workshop
Table 7.3 CRASH COURSES ON FOCUSSED THEMES RELATING TO ENVIRONMENTAL MANAGEMENT
1 Indian institute of Remote sensing, Dehradun PWD Executive Engineers Geographic information Systems (GIS)2 National Environmental Engineering Research Junior Engineers Air, Water Noise Quality modelling
Institute (NERI) NagpurNational Remote Sensing Agency, Hyderabad Assistant Engineers Application of satellite imageries in road planning
3 Indian Institute of Ecology and Environment, Selected Engineers from all Himalayan EcologyNew Delhi levels
4 Forest Research Institute, Dehradun Environmental Engineers Training programme on environmentalmanagement relating to transport projects
5 Centre of Environmental Education, Selected Engineers from all Legal dimension of Environmental managementAhemadabad levels
6 Wadia Institute of Himalayan Geology Junior Engineers Himalayan Geology7 National Institute of Training for Highway Junior and Assistant Enginners Environmental Management in Transport
T 2-eTlono r.-, TlTTf I TC A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Engineers (NITHE), Noida Projects
8 Environment Protection Training and Research Junior Engineers Theoretical aspects of environmentalInstitute, Hyderabad management
9 Tata Energy Research Institute (TERI) Assistant Engineers Hydro Energy and ecological systems
10 Centre for Water Resources Development and Selected group of Enginners Water Resources Management in hilly terrain
Management, (CWRDM) Kozhikode, Kerala11 Centre for Earth Science Studies, Selected Group of Engineers Tectonic and Seismic forces in Himalayan
Thiruvananthapuram, Kerala Region
12 Kerala Forest Research Institute (KFRI) Senior Engineers Bio-diversity and forest ecosystemsTrichur,Kerala
13 Hind swaraj twust, Ahmed Nagar Pune Junior and Assistant Enginners Soil and water conservation
14 Visit to Nepal to see Bio engineering works Chief Engineers and Bio Engineering for slope stabilisation andimplemented along different roads Superintending Engineers landscaping works along road sides in the hilly
terrains.
15 Visit to Malasia for overseas experience on Selected middle level Both good and part of EnvironmentalRoad construction and Environmental Engineers management and modem construction practices.
Management
These training programmes are expected to impart in-depth knowledge from experienced professional working at geographically distant
locations. However these training programmes are only indicative and can be considered in coordination with the respective institutes. In
geographically distant areas of the Indian sub continent.
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
8 ENVIRONMENTAL BUDGETARY PROVISIONS
The budgetary provisions for the implementation of the environmental management plan of the Project are presented in Table 8.1 and canbe categorsed in to four types
* EMP works to be implemented by the Contractor as per the Civil Works BOQ* EMP works to be implemented by the Contractor as per the EMP BOQ (not included in civil works BOO)* EMP works to be implemented by specialist /or other agencies* Mandatory EMP works that area to be implemented other govemment departments/agencies as per regulatory requirements
8.1 Cost Estimates for Implementation of EMP
A. EMP works to be implemented as per Civil Works Bill of Quantities( BOQ)
SL NO Description Unit Quantity Rate (Rs)
A EMP works to be implemented as per Civil Works Bill of Quantities( BOQ)
Construction of Retaining Walls at 7 specified Debris1 Disposal Points, to the required dimensions and Refer: Bid document Part-1 Section Cost included under civil works
standard civil work specifications as shown in the 1 BOQ No 7 Item No 7.10Drawings Volume VI
Construction of Retaining Walls at unspecified(approximate 4 locations to be finalised in consultation
2 with private landowners, who are willing offer land for Refer Civil Works BOQ No 7 Item Cost included under civil worksdebris disposal points in retum for developed land. No 7.10Civil works to be executed as per standardspecifications as shown in the Drawings Volume VI
Development of Debris Disposal Points at all locations(both specified and unspecified) by compacting the top
3 60cm through backfilling with graded material including Refer Civil Works BOQ No 7 Item Cost included under civil worksearth in layers of 15cm and finished upto to natural No 7.16ground level as per standard specifications anddrawings shown in Drawings Volume VI
Regular Water Sprinkling (at least 2 to 3 times) a day Covered under Civil Works BOQ4 at all construction sites for dust suppression. The No-9 Item No 97 as incidental Costincludedundercivilworks
sprinkling of water shall be limited to duration and activities to civil worksactivities generating dust but spread over duration
Provision of informatory sign boards indicatingmajor/important rivers, tourist locations, silent zones,valley view locations, ecologically important areas, wild Covered under Civil Works BOQ No
5 life crossing points, monkey menace points along with 8 Item No 8.02 (road furniture Cost included under civil worksmessages/waming for road users. The specifications works)of sign boards shall conform to relevant IRCspecifications
Sub Total of Items under A, cost of which is already included under Civil Works BOQ
8.2 Works to be implemented as per EMP Bill of Quantities ( BOQ) to be executed by civil contractor (items under this head are notincluded in civil works BOQ),
B Works to be implemented as per EMP Bill of Quantities( BOQ) to be executed by civil contractor (items are not included in civil worksB BOQ),
1 Disposal of Excess Material (Part of EMAP) for an average lead km 23,562,000 2 47,124,000of 9 Km.
r;cn~~-..-, I,TMr I TQ A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Compaction of the disposed surface area using adequate2 quantity of water at the disposal location by road rollers and Sqm 1000 100 100,000
other machineres.
Preparation of 'Contractors Debris disposal Plan' in accordance3 with the EMP and the guidelines provided as in EMP appendix- No 1 10,000 10,000
17.
Construction Cement Concrete Plafform with stone masonrywall enclosure for municipal waste /garbage collection points
4 along project road at specified locations and as per standard No.s 2 25481 50962specifications of civil works and typical drawing-SRP/WB/UG/4/ICB/MW-1- given in Appendix of EMP -21
Re-development of oxbow lands suitable to parking insettlement areas along rural/non-urban /forest stretches at 1
5 selected locations as per standard specifications of civil works 56 200 11,200and specific drawing no- SRP/WB/UG/4/ICB/RA-1 given in nosAppendix 21 of EMP
Construction of silt trap to avoid silting of the water body at three8 locations as per the drawing provided in the Appendix -8 at m 250 1250 312,500
three locations as specified in the Appendix.
Sub Total of Items under B to be executed by civil contractor (items under this head are not included in 47,608,662civil works BOQ),
8.3 Works to be implemented as per EMP Bill of Quantities by Specialist /Other agencies (Notincluded in civil works BOQ)
C Works to be implemented as per EMP Bill of Quantities by Specialist /Other agencies (Not included in civil works BOQ)
Air quality monitoring during construction one location to3 monitor SPM, RPM, SO 2, NOx and CO for summer and Sample nos 12 7500 90 000
winter season- one locations, 4 times per year for 3 years, .each sampling shall cover 12 hours (7am to 7pm duration).
Water quality monitoring during construction phase at onelocation for which base line data was generated during the
4 EIA stage. Water Quality analysis to cover all standard Sample no.s 12 7500 90,000physical, chemical and biological parameters(excludingheavy metals and pesticides)- one locations/4 times per
year/3 years
Noise quality monitoring dunng construction phase at onelocations for which base line data was generated during
5 the EIA stage and one locations at which major work Sample no.s 12 500 60,000activities are executed (1 locations/4 times per year/3
years)
Soil quality monitorng during construction phase at fourlocations for which base line data was generated during
the EIA stage and 6 locations covering BMP, Construction6 camp sites, Workshop areas, and other oil/lubricants Sample no.s 12 3500 42,000
handling areas (1 locations/4 times per year/3 years).Paramaters shall include N, P, Oil & Grease, Heavy
Metals, C/N ratio, PH, Organic matter
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Bio engineering works to be implemented at 7 specifiedlocations as per bio-engineering design and drawings for
slope protection and erosion control as per detail7 estimates. Works area to be executed under the As per detail estimate prepared by bio- 3500000
supervision of bio engineer or any other trained person. engineerThese works needs to be carried out as per the Bio
engineering report and action plans.
Location specific measures for easy/safe passage of As per detailed estimate prepared by bio-8 wildlife at wildlife crossing conridors as determined through diversity specialist @4300/km 77,400
Bio Diversity Impact Assessment Report and Action Plan
Sub Total of Items under C to be executed by Specialist /Other agencies (Not included in civil 385940works BOQ)
8.4 Mandatory Works to be implemented by Other Government DepartmentAgencies as a regulatory requirement
D Mandatory Works to be implemented by Other Govemment DepartmenVAgencies as a regulatory requirement
Plantation works in and around debris disposal locations.1 The plantation program shall be prepared and implemented Ha 1 150000 150,000
and maintained for 3 year duration by Forest Department
Compensatory Tree Plantation Program as per the norms ofForest Department. The plantation program shall be
2 prepared, implemented and maintained for 3 year period by Per No 1599 600 959,400Forest Department (533 trees are to be felled and 1599saplings are to be planted at 1:3 ratio)
Planting of specific tree species like (1) silver Oak (2)Jagarinda along one oxbow land as a enhancement tree
3 planting as per the EMP Design drawings provided in Per No 200 56 11,100Appendix 21. The plantation program shall be prepared,implemented and maintained for 3 year period by ForestDepartment
Re-development of oxbow lands suitable for green beltalong rural/non-urban /forest stretches at Chainage 104+500
4 selected as per standard specifications of civil works and 7 No.s 44 200 6700specific drawing SRPlWB/UG/4/ICB/RA-1given in Appendix21 of EMP
Compensatory Afforestation for the forest land diverted forroad up-gradation works as per the Forest Conservation Act.
5 Compensatory Afforestation works will be taken by Forest Ha 0.5 150000 75,000Department in degraded forest lands as decided by thedepartment
Net Present value (NPV Cost) of the Forest land to be paid6 by the HPRIDC to the department of forests for the land Ha .5 800000 400,000
acquired
Sub Total of Items under D to be executed by Other Govemment Department/Agencies as a regulatory 1,602,200requirement
Total Cost Estimate for implementation of EMP works listed under A, B, C and D 53070262 53,070,262
T A-... r-TC' I T A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDICE
Himachal State Roads Project Environmental Management plan (Jahu-Kalkbar Section)
APPENDIX 1: DETAIL OF THE TREES AFFECTED DUE TO PROPOSEDPROJECT ROADS
Impacted Trees (Girthwise & Specieswise)
1 90-91 Bihul 2 1kalam 2Drek 1karal 1Toot 1
Jamun 2 2 1Sesham 1Tunni 3 3 1Ecalyptus 1 3kamal 1Shimbal 1
_ Banyan tree 1mango 4 6 2 2 1 4 6
2 91-92 Bihul 2AmIa 1kangu 1Pipal 1Papita 1Drek 2Toot 1 2Sarein 3Jamun 2Sesham 1 6 3Tunni 2KimbEcalyptus 1 - 2Japanese toot 1Slambda 1mango 1 3 2 1 2 1 2 1
3 92-93 Jaahu Bihul 1PipalEcalyptus 3 1mango 1 1 1 1 4 l
4 93-94 JaahuPipal= l.= =Toot 1 1 -Sesham 1Ecalyptus 18 19 2 2Banyan tree 1Bihul 2 - 11 1Pardesi =I1_= 1Drek 1karal 2 5Tyamal 1Sheer 1Japanese toot 3Poplar 1 1Sarein 1Jamun 3 9 1UmreaSesham 1Tunni 6 2 1Sikunda 1Ecalyptus 1 1Japanese toot 2 1kamal 2 1 - 5
r : T ) - {............ Tli r T TC t
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Slambda = 3 lChiul 2 2mango 1 2 1 1
5 95-96 Bihul 1jagarinda 1karal 1Bilpatra 2 =Toot __ _ _ _- 1
Jamun 1Pansla 1Sesham 2Tunni 2Ecalyptus 2 1Plah 1kamal - 1Shimbal 1Chiul 4 2mango 7 1
6 96-97 Bihul 1-Drek 1Toot 3 1Sarein 1Sesham 6 =Tunni 6Ecalyptus 3 2Bes 2Shimbal 3Chiul 6
7 97-98 Bhambla Bihul 4 1Nasuda = 1 =Drek 1karal 7Sesham 1 6Tunni 1Ecalyptus 3 1kamal 2Chiul 1
= mango 18 98-99 Bihul 2
Behada 10Fedu 1Jamun 2Sesham 5Tunni 1 1Ecalyptus 9 1Kheir 5kamal 2Umrea 1Slambda 2chiul 10mango -__ _ 2
9 99-100 Mango 3 1Behada 3Cheed 2Amda 1 -
T .Re 2>voPr ....C- .TkT\T T TQ A L
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
= = Sesham 4 = =Flia 1 _ _ _
Shimbal 1Slambda 3chiul 4
10 100-101 BilpatraCheed 3 2 3Cheed 3
11 101-102 Cheed 11Kheir 1Shimbal 1 -chiul 1
=mango 1=12 102-103 Dhalwan Sesham 1
Tunni 1Ecalyptus 1chiul 6 1mango 1 1
13 103-104 Bihul 1 1Pipal 1karal 5Cheed 1Sesham 1kamal 4Shimbal 1 1Slambda 14 1
= chiul 22 1 414 104-105 Bihul 1
Cheed 13Jamun 2Sesham 1
15 105-106 Cheed 1Sub Total 225 54 5 10 175 45 10 9
Total 533
I -; A--i Rr--r .rnrw T\ TQ AC {;
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 2: SUMMARY OF THE COMMUNITY PROPERTIES AFFECTEDLikel impacted drinkin water sources
1 92-93 Jaahu 2public water supply Public water supply 32 93-94 Jaahu Public water supply 13 94-95 Public water supply 14 102-103 Dhalwan Hand pump, public water supply 25 105-106 Water tank 1Public water supply 3 3 6Hand pump 1 IWater tank 1 1
Total 8
l A n.D -~.. A - -- TOA
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 3: LIST OF CULTURAL PROPERTIES AFFECTED
9 16- 17.A T aveA ;rn
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 4: LOCATIONS OF BORROW AREAS FOR EARTH WORK
MATERIAL SOURCES ALONG THE PROJECT ROAD
After Jahu toawards Ner chowk stone uarries are available.
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 5: DETAILS OF THE SOURCE OF AGGREGATES AND LEAD DISTANCE
I -; i P- C- INTCO T NZ A .71
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 6: SELECTION AND MANAGEMENT OF CONSTRUCTION CAMP
* Water supply- Refers to water supply requirements at construction camps, construction,and also for the lost drinking water resources during resettlement and rehabilitation.
* Power plants- Refers to power plants required at camps, plants and at the constructionsites etc.
* Raw materials- Raw materials includes sand, wood, cement, rock, bricks etc are requiredfor constriction of camps, plants etc
• Construction camps - This include camps for managers, engineers, technicians, labourersetc.
• Housing- This refers to all housing requirement at plant sites, camps etc.
• Quarries- Refers to quarries for the construction works
* Blasting - Refers to any blasting requirement at quarries, approach roads, borrow areas etc.
* Access roads - required at camps, plant sites, borrow areas and quarry areas
* Hazardous materials - require at plant sites, quarries etc
* Waste (all kind of solid and liquid wastes) generated- wastes will be generated atconstruction zones, construction/labour camps, plant sites etc.
Construction Workers Camp: In all over India, road construction works are in peak stage. With several local/
regional/national and international contractors in place. The road construction work shows lack of seriousness towards this
issue. The Contractor usually does not provide legally and contractually required facilities for the unskilled labour, hired from
the local villages or are brought to the place of work from outside the State. The Contractor camps and other facilites are
set up in worst conditions even when the contract documents are clearly specifying the required standards. The associated
issues are as follows.
* Forest resources could be encroached up on in all possible ways by the labour force.Unauthorized tree felling to get fuel -wood even when alternative fuel is made available,Poaching of edible animals and birds of the locality in spite of prohibition,
* Poor sanitation arrangement and improper methods used for disposal of solid wastes andeffluent,
* Indigenous people getting invaded by imported construction labour - force, due to lack ofdiscipline,
* Transmission of communicable diseases to the local people by the construction workersdue to inappropriate health monitoring facilities, and
* Creating hazardous traffic flow at construction site due to lack of concern about the localneeds and provision for pedestrian.
Selection and Layout of Construction Camp
The construction camps for labour, accommodation, offices and construction plant sites shall be identified based on the
following guidelines. The construction site shall be located
* At a minimum distance of 1 km away from any major settlement or village.
* At a minimum distance of 300m of any major surface water course or body
If this is not possible the base camps should be located away from the settlements with the following precautions
1. The base camp should be enclosed with boundary wall.
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
2. Movement of the workers should be registered during the night time.
3. There should not be any disturbance to the local community.
4. Operation of the plant and machinery should be restricted to 6 am to 1Om
5. Care should be taken while starting and moving the heavy vehicles, there is a possibility that children of near
settlement may be playing with the machinery parked outside the camps.
Facilities at Workers Camps
During the construction stage of the Project the construction Contractor will construct and maintain necessary (temporary)
living accommodation and ancillary facilities for labour. It will be ensured that all the temporary accommodation will be
provided with uncontaminated water for drinking, cooking and washing. Adequate washing and bathing places shall be
provided, and kept in clean and drained condition. Construction camps will be sited away from vulnerable people and
adequate health care will be provided for the work force.
Sanitation Facilities: Construction camps shall be provided with sanitary latrines and urinals. Closed drainage systems
and the proper treatment systems according to the local conditions should be constructed for the proper flow and effective
treatment. The sewage system built for the camp will be operated properly to avoid health hazard, ground water and soil
pollution. Compost pits will be constructed for the disposal of the garbage and other biodegradable wastes generated from
the camps. Proper collection, transportation and disposal of the wastes will be ensured.
Shelter at Workplace: At such workplaces where the duration of the works will prevail for more than one month some
form of shelters will be provided for meals, resting, change of clothes and for keeping the tools of the work and personal
protective equipment. The height of shelter shall not be less than 3m from floor level to lowest part of the roof. Sheds shall
be kept clean and the space provided shall be on the basis of at least 1 m2 per head.
Canteen Facilities: A cooked food canteen on a moderate scale shall be provided for the benefit of workers wherever it is
considered necessary. All the wastes generated from the canteen will be treated/ disposed of as detailed in the other
sections of waste disposal.
Health Care Facilities: Health problems of the workers should be taken care of by providing basic health care facilities
through a health centre set up at the construction camps. The health centre will have at least a doctor (part time), nurses,
duty staff, medicines and minimum medical facilities to tackle first-aid requirements for minor accidental cases. Some
arrangements will be made with the nearest hospital to refer patients of major illnesses or critical cases.
Day Creche Facilities: At construction sites where women with very young children are employed, provision of a day
creche shall be provided. At construction sites where 20 or more women are ordinarily employed, a hut for children under
the age of 6 years shall be provided.
For ensuring the implementation of effective pollution control measures at the construction base camps andconstruction plant sites, redevelopment closure plans for the closure of these sites will be made part of the EnvironmentalManagement Plan of the construction Contract
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 7: SILT TRAP
b SLOTS lODrnmc/cSUppo* Mesh Anee Fram
GEOTEXTILE MESH
140 n or sinhlar A PP R O V E -
Note: Locations of silt traps will depend on Contractor's proposals for site facilities and work sites and should be provided inthe Contractor's proposals. This will be checked by the Supervising Consultant and monitored by HPRIDC
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 8: OIL INTERCEPTOR
INTERCEPTORINLET AIR COVER
BIAKE
OUTLET
SAMPLE POINT
FLOWREGULATORY 0&DEVICE ACCUMULATION
ACCUMULATION
T R - r,. TT1JC -- D T- A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 9: NOISE BARRIERS
1.0 TYPICAL DESIGNS FOR NOISE BARRIERS ARE ENCLOSED IN THE EMP DOCUMENT.Mitigation at the sensitive receptor locations may include posting of signs prohibiting the use of horns and, to the extentpossible, landscape planting to serve as green noise barriers. Effect of noise can be reduced considerably by the combinedeffect of sound insulating walls and green barriers. Nevertheless the putting of green barriers require at least 2-5m additionalspace between the solid barrier and the receptor. Principle of the designed barrier is also explained in the design sections.Proposed project mitigation actions are cost effective and implementable when compared to the generally recommendedexpensive double glazed windows.
2.0 SOUND INSULATING WALLS FOR SILENCE ZONESThe designs of these arrangements were proposed with a brick wall to act as a sound barrier. The hospitals, medicalcentres, schools and other educational institutions are affected by the traffic noise. A number of schools and a few hospitals(total 8 structures) have been identified adjacent to the road corridor.
3.0 GREEN BARRIERS FOR SILENCE ZONESThese are simply a thick layer of green plantation with small leaves acting as noise attenuates. These trees may be plantedjust 'inside" and adjacent to the wall. Contractors will be responsible for the implementation of the civil work. Treeplantations will be carried out by the forest department under the tree planting scheme of the project the implementationaspects are provided in the respective EMPs. In addition to the noise mitigation, the thick green barrier will also act as an airquality filter for traffic emission. A typical green barrier of 100 m length will have 300 trees in 4 ROWs.Noise mitigation techniques will be employed as may be warranted at each of the sensitive receptor sites tabulated in exhibit5.12. Definitive noise levels will be empirically determined at each site and selection of the mitigation technique will be madeon a site - specific basis in consultation with property owners. Co -ordination and implementation will be the responsibility ofthe Environmental Officer of the Construction Supervision consultants (CSC). Mitigation costs have been estimated as apart of the environmental costs of the project. Exhibit 9.5 provides the various sources of noise during construction phase.
Locations of Noise Barriers
t - - T 2 1- -A Ml t- I TCM A t
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 10: LIST OF PERSONAL PROTECTIVE EQUIPMENT
1 Eye Safety Glasses, Goggles
2 Face Face Shields
3 Nose Nose Masks
4 Head Helmets
5 Feet Safety Shoes
6 Hands and arms Gloves
7 Bodies Vests
8 Hearing Earplugs, Earmuffs
- P.rJ-CrW T TI A 72
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 11: LIST OF TRAFFIC SAFETY EQUIPMENT (GUIDELINE)
1 Barricading Type I/lI/ll 130 2600 m 10002 Men at Work 5 500 100 100003 Keep Left 11 500 220 100005 Go Slow 8 500 160 100006 Flaamen 10 - 10 100007 Narrow Signs 4 500 80 100008 Lantem (Amber Blinker) 4 500 80 100009 Traffic Control Lights 4 Sets 1000010 Cones 15 500 300 10000
Note:* Safety Jackets and helmets should be provided to all the workers/engineers working on the road.. Fixed mobile solid barricades must be placed between the workmen and traffic or pedestrian and
traffic.* All the Signs should be according to IRC: 67 and IRC: SP: 55: 2001.
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 12: TREE PLANTATION STRATEGY
1.0 INTRODUCTION
This is the most common impact of any road-widening project. If the location of the project road is in dry areas, the degree ofimpact is more than in a wet area where the trees can be planted and grown easily. In the case Himachal Pradeshconsiderable vegetabon exists in the PIA as forests of various categories. Except along the Mehatpur-Una-Amb road there ishardly any planted avenue plantation along the prioritised project roads of 41 3kms.
The scopes for tree planting along hill roads are rather poor. Nevertheless there are many isolated patches of unutlised landalong the project road. Two sketches are prepared for the possibility of roadside planation. These are provided in Figure 1.0and 2.0. Figure 1.0 a standard plantation scheme for two lane road in (Plains) with shoulders @ 200 plants per km length(Refer SOS, 2006)The figure 2.0 is a standard plantation scheme for two lane road (in hills) with shoulders @ 100 plants per km length.
The main areas where afforestation is proposed are along the road on both sides where ever adequate ROW is available. Ifthis not possible at least one side and the side slope should be adequately protected by adopting slope stability measures.
2.0 PURPOSE OF TREE PLANTATION
The objectives of planfing trees and shrubs at selected enhancement sites against the felled trees are the following* To reduce the impacts of air and dust pollution and act as a natural filter to traffic emissions* To provide shade for the traffic as well as the pedestrians
To reduce the impact of vehicular noise caused by vehiclesTo arrest soil erosion on slopesBeautficaton of sites by planting selective ornamental shrubs, landscaping andturfing with grassesPlanting trees on the roadsides is to produce a softer greener landscape.To raise social forestry in order to improve the
* To act as a natural filter to the traffic emissions.
3.0 IMPACTED TREES
3.1 PUBLIC OWNED TREES-These are trees within the legal ROW of project road with in the control of PWD.
All these trees with in the forest reserves are also termed as public trees. However the procedure for cutting of these trees isdifferent from the normal trees with in the PWD ROW.
Platform trees: There are number of Good fully-grown Trees with beautiful canopy along most of the roads. There are 3impacted Platform trees along this section.
3.2 PRIVATE OWNED TREES-The number of private owned trees to be acquired outside the right of way will be high compared to the public trees withinthe right of way. The private trees that will be affected during widening and improvement will be subjected to compensationat the appropriate market rates. In addition to this the project will plant two trees for every tree removed as a compensatorytree planting measure irrespective of the size, species etc.
The total no of impacted trees along the project road areTrees with in the Road Right of way 533 NosTrees with in the Forest land to be acquired-Nos ( data not available)
* Trees that are falling in private lands-Nos ( data not vailable)
Therefore 1066 Nos of trees will be required to be planted as a compensatory tree planting as per the Forest conservationact. The data not available are to be obtained from the Social impact survey and land verification.
I A - - .- D # \1 - I 1I- A O n
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
4.0 SELECTION OF TREES SPECIES
The selecton of the plants for greenery development is to be made as per the following criteria;
* Plants should be fast growing with dense canopy cover;* Preferably perennial and evergreen with large leaf area index;* Indigenous* Resistant to air pollutants involved, and* Should help to maintain the ecological and hydrological balance of the region
The most recommended trees for planting along the hill roadsides are provided in the following table. Species Selected forTree Plantation.
The plant species that are selected based on the climatic condition, soil characteristics and conditions of the area. The rowclosest to the main carriage way will be of shade plants. Similarly, subsequent rows will comprise of ornamental andflowering species. Mainly native deciduous species, which retain their foliage longest, with high crown forms, resistant tofungus and insects with rapid growth rate are selected for avenues. Lists of the species recommended as shade plants aregiven below:
4.1 TREES RECOMMENDED FOR PLANTING
Table 1.0: trees recommended for lanting
1 Peepul2 Shisham3 Baheda4 Jamun5 Arjun6 Poplar7 Japani Toot8 Neem9 Jakaranda10 Bottle brush11 Kikkar
4.2 RECOMMENDED SHADE TREES
Table 2.0: Shade Trees Recommended for Roadside Use
Local name botanical namePapal Ficus religiosaGulmohar Delonix regiaKikar Accacia nilotica
Mango Mangifera indicaNeem Azadirachta indica
Jamun Syzigium cumini
Arjun Termenelia arjuna
Papri Pongamia glabra
Shisam Dalbegia sissooBottle brush Callistemon sp
T A.; lZo-- Y. .. .......... T1 I T^! A ........ a
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
5.0 COMPENSATORY TREE PLANTATION PROGRAMME
All trees that are cut and removed will be accountable as per the forest laws and efforts will be maintained to plant doublethe number of trees according to this tree plantation strategy.
Total number of trees that will be cut and removed will be more than 1000 private trees in addition to trees located with inthe forest reserves. This will require compensatory planting of 2000 trees along the sides of the newly constructed projectroad or in other locations.
Indigenous species of trees recommended above are most suited for the tree plantations. In order to make it tourist friendlyand beautiful same types of trees would be planted in the same location so that for every kilometre the trees would changeto new species.
Since the area has dense forest secfions, a very detailed study is being under taken bio biodiversity expert unUil that study iscomplete the exact loss and the consequent mitigation measures cannot be determined.
6.0 TREE PLANTING DURING CONSTRUCTION
6.1 TREE PLANTING ALONG THE ROADSIDESTree plantation will be the responsibility of the Forest department. Necessary budget has been made for the tree plantationand provided in the EMP. The total no of trees to be planted will be double the number of trees that will be removed from theroadsides for the improvement of the project road. The Forest Department will be responsible for obtaining sites and plantingtrees to compensate for the required tree cutting.
6.2 TREE PLANTING ALONG OXBOW LANDSIn rural areas, it is an accepted fact that the improvement of roads will result in the formation of numerous 'oxbow lands' allalong the hillsides where in suitable curve improvements and realignment takes place. The Oxbow lands are the existingroads where the road realignments are proposed. This is similar to the OXBOW LAKES formed durng the evolution of rivershence the name for easier identification for environmental management. The importance of the proper management of theseoxbow lands is there for an unavoidable outcome of the project. There were many alternatives available for the highwayauthority. Tree planting all along these oxbow lands could be very useful for the environmental enhancement of the region.This will help positively for tourism industry. The Oxbow lands along the corridors are available as described in theEnvironmental Management Plan for individual corridors.
7.0 PROTECTION MEASURES
The protection measures are discussed in this section
7.1 BARBED WIRE FENCINGBarbed wire fencing around the plantation area will be provided to protect the plants. Angle iron will be fixed at a spacing of5 m. with 3-stand stretched barbed wire.
7.2 PRECAUTIONARY MEASURES:
Plantation will be made in the monsoon months (July -August)The height of the plants should not be less than 1 ft. and should be supplied inpolythene bags which are not to be removed until the moment of planting
All plants supplied must be planted within three days of removal from the nurseryArrangements must be made to water in case of insufficient rains after planting
* 2 kgs of compost / manure are suggested for each pit before plantation
7.2.1 SHRUBSPrior to planting it is suggested to remove all loose debris, fill up with good soil and level the area. To ensure better growthand survival of grasses and shrubs, the surface should have sufficient layer of good quality soil (up to 45 cms). Shrubswhich are suggested for the road side and open area spaces where available should be selected from the following andagreed with the Environmental Specialist of the Construction Supervising Consultants Environmental Specialist:
M -: f--- --- T\T I IC' A Q1
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Garna Caroissa spinarumKarir Caparis deciduaHins Capris zeylanica
Gandhala Murra yakoenigilMalla Zizypuhs nummulariaJhau Artemesia sppJindu Xanthium stumarium
Panwar Cassia toraJangli Mirch Capsicum fruitscens
Akk Ipomea gossypiolides
The Contractor will be responsible for planting of shrubs at enhancement sites and along bridge approaches duringconstruction phase.
7.2.2 TURFING WIH GRASSESThe Contractor will be responsible for turfing at enhancement sites and along bridge approaches during construction phase.
The cost for the turfing along the bridge approaches and high embankments are part of the Civil construction contract.
Grass lines are used to provide a strong surface cover at the slope but it also needs a well-prepared surface. If grass is tobe effective, then it must be allowed to establish properly on a slope which is not subject to undue stress from erosion andmass movement in its initial stages. To ensure this the following measures are suggested for the grass turfing.
* A cover of 25 grams of grass seed per square m. of surface will be prepared* Bed will be prepared in June. The seed sowing must be carried out before the onset of
monsoon so that they yield desired results. Till the onset of the monsoon, watering ofthe surface to be done by tankers with controlled flow sprinklers.
* After sowing, mulch of prepared and dried out herbs will be laid over the wholeseeded area in a thin layer so that the direct sunlight and transpiration loss may notaffect the grasses
* The grass species recommended for median are Khabbal, Dhaula, Palwan, Sariala andKahi.
Contractor will ensure that the condition of the site is good enough for the successful establishment of grasses and shrubs.They will also supervise all field operations like preparation of surface, sowing of grasses and quality of grass seeds used.
8.0 TREE PLANTATION COSTS
The plantation cost has been included in the bill of quantities (BOQ) under the non-civil contracts and provided in section 8.0of the Environmental management plan (EMP).
A tree - planting strategy is being developed which will meet all compensatory tree planting that will be cut during theimprovement of the roads including private trees. The cost provisions have been included in the EMP and BOQ.
9.0 MAINTENANCE OF TREES PLANTED
The trees planted once will be maintained at any cost for the full growth of at least for a period of three years.
A programme of compensatory afforestation has been proposed, not only to replace the trees, which must be cut toaccommodate road widening and improvements in geometric design, but also to upgrade the condition of adjacent areas.Trees will be re - planted at a rate of two for each one removed depending upon the location.Tree felling in other sites such as borrow areas- will be accommodated by the Contractor in the borrow area managementplan.
I D-A- .-. TnT. T T A A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 13: NATIONAL STANDARD OF AIR, NOISE AND WATER
A. NATIONAL AMBIENT AIR QUALITY STANDARDS
(SO2)Method Ultraviolet24 hours** 30 pg/rm3 120 pg/M3 80 pg/M3 Fluorescence
Oxides of Nitrogen Annual* 15 pg/m3 80 pg/rM3 60 pg/rM3 Jacob & Hochheiser Modified(NOX) method
24 hours** 30 pg/M3 120 pg/M 3 80 pg/M3 Gas phaseChemiluminescence
Suspended Annual* 70 pg/m3 360 pg/M3 140 pg/M3 High Volume SamplerParticulate Matter (Average flow rate not less(SPM) 24 hours' 100 pg/M 3 500 pg/Mr3 200 pg/M3 than 1.1 m3/minute)
Respirable Annual* 50 pg/M 3 120 pg/rM3 60 pg/m3 Respirable Particulate MatterParticulate Matter Sampler(RPM) Size < 24 hours 75 pg/M3 150 pg/M 3 100 pg/m3
Lead (Pb) Annual* 0.50 pg/M3 1.0 pg/M3 0.75 pg/M3 MS Method after
24 hours** 0.75 pg/m3 1.5 pg/M3 1.00 pg/M 3 sampling using EPM 2000
Carbon Monoxide 8 hours** 1.0 Mg/m3 5.0 mg/m 3 2.0 rng/m3 Non-dispersive infrared
(00) 1 hour 2.0 mg/m3 10.0 mg/m 3 4.0 mg/m3 Spectroscopy
* Annual arithmetic mean of minimum 104 measurements in a year taken twice a week 24 hourly at uniforminterval**24 hourly/8 hourly values should be met 98% of the time in a year. However, 2% of the time, it may exceed butnot on two consecutive days.Source: Central Pollution Control Board, 1997 Gazette Notification dated 4/94, Part II Sec 3 (ii)
B. WATER QUALITY STANDARDS
1 PH 6.5-8.5 6.5-8.5 pH meter2 BOD (3 days 27°C) 3.0 NS DO-Azide modification of
Wrinkler's method3 Temperature (C) NS NS Thermometer4 Dissolved oxygen 4 NS Azide Modification of Wrinkler's
method
5 Color (Hazen) 300 NS Visual Comparison method6 Fluorides (F) 1.5 1.0(1.5) SPANDS method7 Chlorides (Cl) 600 250(1000) Argentometric Titration8 Total Dissolved Solids 1500 500 (2000) Gravimetric Analysis9 Sulphates (S04) 400 200 (400) Barium Chloride method10 Iron (Fe) 50 0.3(1.0) Phenanthrolin method11 Oil and Grease 0.1 NS Partition - Gravimetric method12 Nitrates 50 45(100) Chromotropic acid
* -. :- n -_ TT I TC A QA
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
13 Chromium (Cr6+) 0.05 0.05 Atomic Absorpton14 Cadmium (Cd) 0.01 0.01 Atomic Absorption15 Lead(Pb) 0.1 0.05 Atomic Absorption16 Copper (Cu) 1.5 0.05 (1 5) Atomic Absorption17 Cyanide (CN) 0.05 0.05 Chloramine-T-method18 Selenium (Se) 0.05 0.01 Atomic Absorption19 Arsenic (As) 0.2 0.05 Atomic Absorption20 Phenols 0.005 0.001(0.002) Spectrophotometer21 Detergents 1.0 0.2(1.0) Spectrophotometer22 DDT Absent Absent Spectrophotometer23 Total Coliform 5000 NS Multiple Tube Fermentation
C. NATIONAL AMBIENT NOISE STANDARDS
A Industrial 75 70B Commercial 65 55C Residential 55 45D Silence Zone ** 50 40
Daytime shall mean from 6.00am to 10.00 pm and Night shall mean from 10.00 pm to 6.00 am Silence zone is defined asarea up to 100 meters around premises of hospitals, educational institutions and courts. Use of vehicles homs, loudspeakers and bursting of cracking are banned in these zones.
T --.. 1'-- -... TlOf- I TA AA
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 14: FORMATS FOR ENVIRONMENTAL MONITORING
EMS 1: CONSTRUCTION CAMP/ PLANT SITE MANAGEMENT PLAN
1 Name of the location
2 Nearest road chainage.
3 Name of the owner
4 Area involved
5 Arrangements with the owner (agreement with land owner, includingthe restoration aspects, should be attached as an Annexure)
6 Existing land use7 Photographs depicting the present condition of the construcfion camp
and access road.8 Land use of the area surrounding the borrow area including a map
9 Site layout plan of the construction camp
10 Establishment and maintenance of demarcated and labelled differentareas within the camp
11 Number of trees to be removed, if any, along with compensationmeasures
12 Proposed top soil management
13 Activifies planned in the construction camp
14 Machinery & equipment to be used on site
15 Labour camp facilities onsite
16 Health facilities
17 Site drainage provisions
18 Copy of the consents to establish and operate should be attached asan Annexure
19 Conditions laid down in the clearance / licenses and plans
20 Staff strength and details such as contractor staff vs sub contractors,women labour, migrant vs local labour and skilled & unskilled labour
21 Access road condition and proposed maintenance
22 Safety provision such as fire protection equipment and personalprotective measure.
23 Closure / completion plan Format EMS: 1A
T : } - - -- kr I -O A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
EMS 1A: CLOSURE PLAN CONSTRUCTION CAMP AND/ PLANT SITE
1 Name -idenfty of location2 Distance from the Project Road and side3 Name of the owner4 Details of the Land i. Survey Number ii. Boundaries iii. Other Revenue
Details
5 Details of settlements, sensitive areas, water bodies, wells and borewells with in 500 mPopulation in Numbers Name of the Village Distance from the constructioncampDetails of water bodies/ sensiEve areas/ wells/ bore wells
6 Physical DetailsNumber of Labour StabonedNumber of Dwellings Constructed Number of toilets provided Weredwellings demolishedWas the wastewater treatment facilities demolished and clearedWas the solid waste generated cleared and disposed of properly; if yesspecify the location and quantity.Whether any soil was contaminated with oils and waste oils wascleared and disposed safely, if yes specify the location and quantity.Was scrap generated while the construction removed, if yesspecify the details such as where, when, to whom and quantity.
7 Land Use before Establishment Proposed Use after complebon of works
EMS 2: BORROW AREA NO:
1 Name I identity of location2. Nearest project road Chainage3. Name of the owner
4. Area involved/capacity/quantity5. Type of material proposed to be taken6 Arrangement with the owner including restoration aspect.
7. Existing land use8. Land use of the area surrounding the proposed area9. A map of the area10. Number of trees to be removed, if any along with the compensation
measure
11. Top soil management if required12. Access road condition and proposed maintenance13 Photograph depicting the present condition of the proposed
area and access road
14. Closure / completion plan EMS2A
'.ThiR RerQerPfrGmnn INC IIA Q7
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
EMS 2A: CLOSURE PLAN FOR BORROW AREA
1 Name / identity of location
2 Nearest Project chainage, distance from the Project Road and side
3 Name of the owner
4 Details of the Land i. Survey Number ii. Boundariesiii. Other Revenue Details
5 Details of 5 settlements, sensitive areas, water bodies within 500 mPopulation in Number Name of the Village Distance from the borrow areaDetails of water bodies/ sensitive areas/ wells/ bore wells
6 Physical DetailsLength and width in metersDepth excavated in meters Quantity Excavated in cum Type of materialsexcavated
7 Land Use before Opening Proposed Use before opening Details ofsurroundings
8 Drawing showing the dimensions of the borrow areas, access roads and Appendix- 1features of surrounding
9 Number of trees removed (girth>300mm), if any along with thecompensation measure
10 Details of top soil Quantity excavated in cumWhere was it used
11 Initial access road condition and final access road condition
12 Photographs depicting the original condition, during the Appendix-2operation, top soil management, and after closure
13 Copy of the agreement with the Owner Details of the agreed Appendix-3
14 Land use after rehabilitation Details should be submitted if the final land
15 Satisfaction certificate from the owner Appendix-4
16 Details of the practical problems faced and solutions adopted, if any
EMS 3: CONSTRUCTION CAMP / PLANT AND ENVIRONMENTAL MANAGEMENT
1 Drainage System1 . Closed drainage
2 Disposal for Wastewater1. Kitchen wastewater2. Wastewater from water closets3. Wastewater from bathrooms4. Wastewater from the vehicular washings.
3 Collection and Disposal of Solid Waste1. Waste from the office2. Waste from the kitchen3. Waste from sweeping
4 Drinking Water facilitySource with quantityNo of bore wells with capacityLocation of the well and bore wellAny treatment facility No of overheads tanks Test results of the Drinkingwater
T A;O -vn rr- - TXT(-TP TC A A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
5 First Aid Facility
6 Roads in Camp SiteType of roadDust suppression practicing or not, if the roads are not tarred. Condition ofthe road.
7 Fuel Storage1. Impervious Base2. Spills and Wastewater will be collected in a sump3. Number of drums where wastes are collected.4. Number of drums disposed
8 Garbage & Night Soil1. Provision of Garbage Bins2. Separation of Polythene materials3. Records of solid waste removal from septic tanks
EMS 4: TOP SOIL MANAGEMENT
2
3
4
5
6
7
8
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
EMS 5: CONSTRUCTION PLANTS AND POLLUTION CONTROL
2
3
4
5
EMS 6: MACHINERY/ VEHICLES AND POLLUTION CONTROL
23 _ _I
EMS 7: DETAILS OF THE DG SETS WITH THE POLLUTION CONTROL EQUIPMENT
Camp -I
Camp-11 l l
I __ I _ __ I __
Crusher -I
[ I __ _I
Plant Site -I
Construction Works
; .- rTi- I CTX A nn
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
EMS 8: DETAILS OF OIL STORAGE
Diesel i
Engine Oils
Lubricants
EMS 9: WORKING AT WATER COURSE AND POLLUTION CONTROL MEASURES
EMS 10: DETAILS OF THE GROUND WATER EXTRACTION
2
87 ___T______ _____ ____
EMS 11l: PERSONAL PROTECTIVE EQUIPMENT
7 Safety Bhels __ _ _ _ __ _ _ _ _
8 Ear Plugs _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
9 Reflective Jackets __________
10 Gum Boots__ _ _ _ _ _ _ _ __ _ _ _ _ _
T3rT .- TPTDA^
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
EMS 12: STATUS OF CONSENTS AND PERMISSIONS
Hot Mix Plant---s
Crusher
Batching Plant
WMM Plant
Crusher at Dalla
Diesel Pump -l
Labour License
EMS 13: DEVIATIONS WITH CORRECTIVE ACTIONS
EMS 14: DETAILS OF TREE AND SHRUBS PLANTATION
EMS 15: PLANTATION OF SHRUBS AND GRASS
T Ai -1 ---a t MAA T1X- T TC A )
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
EMS 16: IMPLEMENTATION OF ENHANCEMENT MEASURES
EMS 17: DEBRIS DISPOSAL AREA NO
1. Name / identity of location
2. Nearest project road Chainage
3. Name of the owner
4. Area involved/capacity/quantity
5. Type of material proposed to be disposed off
6 Arrangement with the owner including restoration aspect.
7. Existing land use
8. Land use of the area surrounding the proposed area
9. A map of the area
10. Number of trees to be removed, if any along with thecompensation measure
11. Top soil management if required
12. Access road condition and proposed maintenance
13 Photograph depicting the present condition of theproposed area and access road
14 Lead distance
15 Length,height and type of of retaining wall constructed
T ' TW {~- T. T w1O>
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
16 Quantity of materal that can be stored
17 Date of Community meeting at local level
18 Details of the various approvals received
20 Compaction of the debris disposed off
21 No trees planted
22 No of shrubs planted at the location.
23 Closure / completion - meeting with the localbody/Panchayath pradhans
T { li T2ra r -{.r .-sr TXTI- T TQ A
IIIIIkdIidI ML~ I'ae oaus lrrojecr - Iznvironmentai Management plan (Jahu-Kalkhar Section)
APPENDIX 15: Examples of some good practice in traffic control & Safety during Construction
/, ,- C $
Fiue :Dveso o rafconhl o h ra wdh-sylft7
LouisBergr Grup, NC, SA 9
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Turn left Keep loft Road ClefUih direction of (The arrow mav bethe arrow may pointed downwdbe reversed for to the right lor'Utn right) 'keep right)
Tieltic conv
!;-, *1, ,l./" Minsnun I .25!. n
Lusie cklsur. i ws.
2001ti ma
I All sejnso slgo uhJ bUI E V . **reIlectorised
f-71 2 MUlt.*,Xuiiill tglii of c,,cu1v
I . .. be I miette l l.25 msetie%.4-.- )z lefelletl)
Figure 2
Louis Berger Group, INC, USA 96
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
\\ I \\
-AAp8
AX'"'\ \@A
AAXFigure 3: Sign layout for lane Closure (Drawn for driving on left)
Louis Berger Group, INC, USA 97
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Figuw. 5
X. -1
Figure 4
Louis Berger Group, INC, USA 98
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 16: GENERAL GUIDELINES FOR CONTRACTOR'S'CONSTRUCTION WATER MANAGEMENT PLAN'
1.0 INTRODUCTION
In Himachal Pradesh (HP) all roads are generally cutting across a number of perennial and non perennial rivers, streams,nallahs, Khuds tributaries etc. In hilly terrain, there are many stretches of roads which are dry during most part of the year(e.g. Theog-Chela section). Nevertheless the water requirement at the dry sections will be much more than the othersections. Besides the surface water sources there are numerous community drinking water sources along the project road.This includes springs, PWS, HPs, wells, Shallow tube wells etc.
The guidelines provided here are over and above the provisions include in the National Water Policy and State Water Policy.Therefore Contractor must refer to these two documents and if necessary consult the lrrigation department who preparedthe State policy.
2.0 WHY DO WE NEED A MANAGEMENT PLAN FOR MEETING THE WATER REQUIREMENT DURINGCONSTRUCTION?
The availability of water for construction is very limited and this is variable through out the section. The contractor may resortto take water from streams, rivers and other sources near by without the consent of all relevant officials and the localcommunities. There is every chance that the contractor's labor force (even without the knowledge of the Contractor) will tryto use and over use the existing community drinking water sources. In such cases community conflict could lead to stoppageof construction work and will hinder the progress of all activities. In the event of such occurrences there could be financialloss for the government and the people. More over the people hardship during construction will continue and worsen.
After all, a careful planning in this regard is going to save contractor's efforts and time. A well planned constructionprocedure will help the Contractor to finish the work in the scheduled date of completion.
3.0 QUANTITY OF WATER REQUIREMENT DURING CONSTRUCTION
During construction phase water will be required for the following,* Construction work along the road (e.g. for compaction)* In the plant site (e.g. Batch mixers, masonry works)* Water for drinking at plant sites, and at construction camps
If applies thump rule for the minimum requirement of water then 10,000 Ipd per running kilometer of work will be taken in toaccount.
4.0 CONVENTIONAL WATER SOURCES
The possible conventional source for the Contractor would be the followinga) Rivers (e.g. Beas)b) Reservoirs (e.g. Govind sagar)c) Streams, Nallahs, etcd) Deep bore wells etc
Other than this, there are non-conventional sources. These are the harvesting of;e) Rainwaterf) Snow waterg) Springs
(Refer:SRP/WB/UG/4/ICB/WM- 1)
nT
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
5.0 CONVENTIONAL WATER RESOURCES
5.1 RIVERS (E.G BEAS)Major rivers are the most conventional source of construction water that is feasible. Even then the Contractor needs toobtain all necessary permissions prior to the extraction of water. In this case the potential impact to water quality should beavoided. No vehicle wash shall be allowed in the river as it pollutes the river. The Petroleum, Oil and Lubricants (POL) canpollute the river water.
5.2 RESERVOIRS/DAMSContractor can use of reservoir water for construction. For example in the case of Una Nerchowk, possibility of use ofGovind Sagar reservoir shall be explored. All necessary written permission shall be obtained from all authorities that have astake in the dam water.
5.3 STREAMS AND NALLASIn the case of streams and nallas, Contractor constructs suitable water harvesting structure to harvest the stream water. Thedimension of the structure could be of the order of 5 m X 2m x 2m (20 m3)
For construcfion of this structure in the riverbed, Contractor should obtain written Permission from all concerneddepartments.
5.4 DEEP BORE WELLSThe scopes for deep bore wells are rather limited due to the Geomorphologic characteristics and the limited availability ofgroundwater
6.0 NON-CONVENTIONAL WATER RESOURCES
6.1 RAINWATERRain water-harvesting structures- a probable opbon. For construction water, in the scarcity/dry area, if required Contractorcan opt for harvesting of the rainwater. For that a water harvesting structure has to be constructed. Potential locafbons for aharvesting structure need to be identified in relations to the availability of water and water catchments area. This can beconstructed in the form of ponds with non-percolating tanks, which can be "kacha", tanks covering the Tarpaulins sheets atthe bottom. This is not a new concept. These are being used in many parts of the Himachal Pradesh. This will help theContractor to extract water for this purpose for the construcdon period.
6.2 SNOW WATERAlthough snow water is very unconventional, this could be very important source of construction water. Contractor will haveto look for suitable location to collect snow melt water during February-March April period. This is applicable on for theTheog- Rohru road..
The structure should be more or less similar to Rain water harvesting.
6.3 SPRINGSThe springs are concentrated discharge of Ground water appearing at the surface as continuous flow of water. These areabasically water table aquifer in the case of perennial springs. In the case of non - perennial springs this is the saturated soilwater the drains an area. Contractor should take permission from local communities as wells as from the Department for theuse of springs. This source is not recommended as a viable opfion along the project road. Nevertheless presence ofpotential springs out side the road ROW along the feeder roads could not be ruled out.
7.0 DOS AND DONTS FOR THE CONTRACTOR
There are a number of dos and Don'ts for the Contractor as provided below;> Contractor's vehicles shall not be allowed to wash in the river or stream. This is to avoid potential pollution from
POL residues.> Contractors shall not use water from the community drinking water sources such as;
T -i. A-,z, fl,,,rT TKIT rZ A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
* Public water supply schemes* Community spring water sources* Community hand pumps* Community bore wells /shallow tube wells* Location of or the streams from which the community take drinking water
) Contractor shall obtain all legal approvals and clearances from the concerned departments.
Contractor shall consult the local communities where the water source has been identified.
> If the source is a spring -check discharge, dependency in consultation with local communities.
> If the source is nallalkhad- discharge data for the past several years need to be analysed, whether source is
perennial, or non-perennial, any irrigation scheme is running over it or not, if IPH* department is using it, or local
people using it or not. NOC* from all concerned authorities will be required.
) If the source is a major river like Beas-, In addition to the local permissions, Contractor may require obtaining written
permission from the State level authorides at Shimla.> If the sources is groundwater (a Hand pump/bore well or open deep well)- then its chemical composition and water
related tests are required to be obtained from the competent authority and an NOC* obtained from the competent
authority is also required.* IPH = Irrigation and Public Health Department.* NOC=No objecton certificate.
8.0 POST CONSTRUCTION STAGEOnce the Contractor finishes his job, this can be handed over to the local panchayath or for local communities.
The two possible alternate uses of this structure would beLocal communities of this area can use the same to meet their water needs
This could be a water hole for the wild life of that particular area.If the water source is snow melt water all necessary planning shall be carried out prior to the snow melt period. This
could be end February to end March.In the case of snow melt water only local permission to establish the 'kacha Tanks' i.e. This is a cost effective
structure. A local NGO or community groups is to be introduced to execute such type of works. So that the
Contractor can obtain considerable quantity of water. In this case after the construction phase, same local groups will
inherit the structure and there by will continue to use this.If road passes through a plain water scarcity prone area and if no nearby water source has been identified,
transportation is uneconomic, then Contractor should go for underground water option. If it is feasible and will not
lead to a serious depletion of the source ground water.
1 Al
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 17: GUIDELINES FOR THE PREPARATION OF CONTRACTORS'DEBRIS DISPOSAL PLAN'
1.0 INTRODUCTIONThis is the most widely talked about impact of road widening in the State of Himachal Pradesh. Even the common man livingon the roads side is worried about the possibility of disposal of large amount of debris towards the valley side to hispremises. This could be apple orchards, other farming areas, his house etc. On an average 30,000 m3 per kilometre ofdebris would be generated. The maximum possible use for the road work would be 10-40 % depending on the kind ofmaterials that would be impacted. If not careful the massive soil erosion could take these loose materials in to the ArabianSea and to the Bay of Bengal (from Giri River and Pabbar River).
Hence the Contractor should plan for the disposal of muck in such a way so that it may not harm, or create any hindrance forthe implementation of the project. It's obvious that nearly a 10 million Cub.m of muck will be cut and removed during the hillaward side widening of Phase 1 roads. During the execution phase, Contractor should plan for its safe disposal according tothe geographical status of area.
A poor planning could lead to very poor engineering practces, community conflicts and the stoppage of the work etc thatcould incur huge losses to all concerned.
2.0 THE PROJECTThe Himachal State Roads Project (HSRP) is now planning to implement the phase 1 batch 1 roads. Altogether 250kms ofroads would be implemented in four ICB and one NCB contracts. Where ICB is the International competitive bidding andNCB is the national competitive biding process. The projects roads that are included in the batch 1 are the following;
Mehatpur-Una-AmbUna-Barsar-NerchowkTheog- Kharapatthar-Rohru
From the first road Mehatpur-Una-Amb road, no excess debris would be available. On the other hand this road wouldrequire considerable quantity of borrow and quarry materials. On the other hand there would be huge quantity of debrismaterials in both other two-project roads.
3.0 EXPECTED QUANTITIES OF DEBRIS GENERATEDAn analysis has been carried out to understand the quantum or the dimension of the issue. The expected quantified debrismaterials would be 1.68 million cubic meters for the Theog-Rohru and an estimated 2.268 million in the case of Una-Nerchowk. These quantities are quite large in terms of the space or area required for the disposal.
TABLE 1: AN ANALYSIS OF THE EXPECTED QUANTITY OF MATERIALS AVAILABLE
Theoa-Rohru | 80 | 70 | 56.000 | 30,000 1,680,000Una Nerchowk 126 60 75.600 30,000 2,268,000Total 206 130 131.600 Total 3,948,000
4.0 POSSIBLE USESThe excavated materials that can be used for the insitu construction purposes would be limited to as low as 10-20 %. This is mainly due tothe adequacy of the quality of the materials that would be generated. The expected possible use of the materials would be for thefollowing;
* Using it as the granular sub base (GSB)* Fill material to create embankments especially of the bridge approaches and realignment
I niiiQ R-Prn , P'J- CTr I TQ A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
4.1 ENVIRONMENTAL ENHANCEMENT USES
Other possible environmental enhancement uses could be
* To create proposed parking areas* To use the oxbow lands available on the road sides
Where in the oxbow lands are the left over portion of the project road while realigning/, bypassing or by one side widening (RHS or LHS).
In the above in situ uses the quantity of materials required to use in the oxbow lands and the parking areas would be substantially higher.
In this case, the project can maximise the project benefits to many fold. If this is not carried out as part of the project all the PWD land
would be degraded and would be encroached by private people. In the long run, it will be a huge loss for the GOHP and for the people of
HP.
More over overall the project would remain as 'incomplete forever. To make a complete road we must address all issues that would be
generated by the project.
5.0 POSSIBLE IMPACTS DUE TO THE EXCAVATED DEBRIS MATERIALS
If not disposed off properly what would be the expected scenario? This is described in the following sub sections 5.1 to 5.5.
5.1 OBSTRUCTION TO NATURAL WATERCOURSES
The materials if not disposed off properly would be taken by the running water to the lowest portion of the valleys creating huge
obstruction to free flow of natural stream water. If people are residing nearby that would affect their life by way of flooding or by spoiling
the premises.
5.2 SILTATION IN SURFACE WATER RESERVOIRS
Most of the materials would be ultimately taken down stream through rivers and ultimately depositing in to reservoirs leading to heavy
siltation. This in turn would reduce the reservoir capacity substantially within a very short span. This could incur huge losses to the
exchequer. Desiltation is also expensive and normally carried out after many years of operation of reservoirs in the natural circumstances.
5.3 SOIL EROSIONMassive soil erosion is the most direct impact of the debris excavation. The precipitation and the consequent run off would erode the loose
materals by way of suspension and solution. Once reached up to the mainstream courses even the big boulders would be transported
down due to the steep gradients available along the stream courses.
5.4 SPOILING OF AGRICULTURAL LAND
As a usual practice mainly due to poor planning and limited resources, the Contactor usually throw the matenals to the near by valley
areas. This would be taken down to the private agricultural areas. The farmer will incur huge losses and may even sue the Contractor. As
a result the project could be stopped indefinitely leading to losses.
5.5 DESTRUCTION OF AGRICULTURAL CROPS
Destruction of agricultural crops immediately down the hill will require crop compensation there by reducing the profit margin of the
Contractor.
6.0 IDENTIFIED DISPOSAL AREAS
The Contractor should also try to make use of all disposal areas identified during the project preparation stage. These are provided in the
table 2.0.
Table 2.0: Identified disposal areas
---Jahu-Kalkhar__ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _
Location Chainage Distance from Present landuse
the road
Dhalwan 102+340 2 km away School ground
from the road
Dhalwan 103+025 500 m away School groundfrom the road
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
if the road execution is approaching hill area , semi hill area and mountainous area, rocky area than at most important is tobe given screening i.e., to screen the debris into useful or non useful material. Useful means stones can be used asconstruction material and non useful can be used as development of the public, social and cultural properties as alreadywritten above. Such as parking places, school playground, bus bays, ground near any temple, Gurudwaras and masjids sothat people participation can be assured in well running of this international project. So it would be good if an NGO isintroduced to perform this task more efficiently.
6.1 PROPOSED TYPICAL DESIGNSThe proposed typical designs are provided in the Appendix-21 Design drawings. Most important characteristics of theidentified locatons are the requirement of retaining walls. The fill height has been fixed as two meter for it to be manageable.
7.0 DISPOSAL AREAS IDENTIFIED BY THE CONTRACTOR
In order to maximise the profits or at least to reduce the expenditure the Contractor usually resort to his own methods. Inthat process Contractor could find a number of more feasible areas.
8.0 DISPOSAL METHODS AND ITS LIMITATIONS
There are several constraints in the disposal of material in the identified locafions. These are* Disposal areas are uneven and irregular in shape in the hilly terrain* Most of the disposal areas would require construction of retaining walls* Disposal areas would require compaction* Disposal areas would require plantation* Would require consultation with all concerned* Would require written permission form all concerned* Would require to transport through difficult haul roads - may require maintenance* Need to transport safely with covered trucks using tarpaulin* No overloading and should be in small trucks or dumpers
8.1 LOCAL COMMUNITY GROUPSAt each identified debris disposal locatons, it is necessary to form local community groups. Entrust the duty of thesupervision and all other assistance to dumping process. Ultimately the disposed area should be compacted using roadrollers.
8.2 INFORMATION DISPLAY BOARDSThe capacity of the disposal locations, name of the location etc shall be written in an Information board at each identifieddisposal locations.
9.0 PROPOSED DESIGN
Contractor needs to plan the disposal in the following way.* Identify the disposal area* Need to photograph the present land use and condition of the area* Consult with all stake holders* Get written agreements from all concerned* Prepare a suitable design for the safe disposal* Construct all required structures (e.g. retaining wall)* Planting of fast growing poplar trees on the outer portion of the retaining wall in the form of a linear wall parallel tothe retaining wall* Estimate the quantities* Compact of the materials after disposal* Prepare a Contractors debris disposal plan with design drawings for each identified area
T ; A- - f---., n.rrT I IC A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
With regards to plan, there would be only one disposal plan with small changes for each location. Contractors need to get
approvals for specific design for each identified disposal area.
10.0 PENALTIES
The biodiversity workshop on December 14 at Shimia has suggested stringent penalties for dumping of materials in
locations other than the pre-identified locations. This need to be worked out to avoid clandestine disposal in the midnight
hours. There are several cases of dumping of material randomly in many locatons.
I W;
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 18: GUIDELINES FOR THE MANAGEMENT OF ROAD SECTION THROUGH FOREST AREAS1.0 INTRODUCTION
A Forest Area Management Plan for the impacted forest area is required for effective mitigation and enhancement measuresduring construction and operational phases of the project road. This will not allow any room for neglecting/avoiding of theimplement able measures. This will also define responsibilities of various institutions in this regard. Recently Word Bank(WB) has taken stringent measures for the environmental impact assessment and EMP requirements with the 10 Safe guardpolicies/Operational Policies. The project will trigger the World Bank Operational Policy OP 4.04 Natural Habitats. Thisrequirement is the basis of the preparation of this document. The document addressed the issues relating to the Forestareas in the PlAs as well as immediately adjacent to the project road. The measures have addressed the design,construction and operational phases on the project.A plan for considering a mini biosphere plan in the region has been informally available from the Forest department.Incorporation of effective mitigation measures is therefore necessary and important. This will be based on therecommendations of the ongoing biodiversity studies. All these clearances are expected by the April, 2007.
2.0 STATUS OF THE WORK RELATING TO THE UP-GRADATION
The actual construction work cannot be started until all environmental clearances are obtained from various agenciesincluding World Bank. The environmental clearance also includes forest clearance basically for the required land from forestreserves. Application for both clearances has been routed through two different agencies Viz., PCB and State ForestDepartment. A public hearing will be held in the affected districts and the various activities relating to this is to be initated.
3.0 FORESTS ALONG THIS CONTRACT
The PIA area of the project (Ten kilometre on either side) does not contain reserved forests. Also there are no wildlife areaswithin the PIA, therefore no special mitigation measures are required. The impacted forest sections are provided in table 1.0.This State Highway has a length of 18 km. The GOI need environmental clearance for those up-gradation roads passingthrough sensitive ecological resources, which include reserve forests as well.
Table 1.0: Details Of Forest Area PIA District
Protected ForestsSidhkot PF
1 53 A/14Gobarta PF 1
4.0 FOREST LAND ACQUISITION & FOREST CLEARANCE PROCESS
Prior to the preparation of the application, a joint site verification exercise was carried out with forest officials and the PWDlocal Engineers. Specific details of this investigation are not yet available.An application is to be prepared in the prescribed application form and submitted to the relevant DFOs in consultation withthe Nodal officer of Forest Department at Head quarters at Shimla. This application will be verified by the respective DFOs.
5.0 COMPENSATORY AFFORESTATION PROGRAMME
Compensatory a forestation will be carried out for land to be acquired against the loss of trees from the area to be acquiredfor road reserves. PWD will plant an area double to that of the land acquisition.
6.0 IMPACT MITIGATION AND ENHANCEMENT MEASURES
Louis Rerver 1r,ml-n TNr T TQ A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
This includes the legal requirement according to the (1) GOI forest laws and the (2) requirement according to the other laws.
The GOI requirements are provided in the section 4.1 and the other requirements are provided in section 4.2.
6.1 COMPENSATORY AFFORESTATION PROGRAMME
According to the afforestation programme PWD has agreed to plant an area double to that of the land area to be acquired.
This amount will be deposited with forest department.
In addition, a number of impact mitigation and enhancement measures are required for the Forest area that will be impacted.
The forest reserves adjacent to the project road do have high faunal value. For an approximate 10 Ha of forestland
acquisition the following measures are proposed.i) Considering this aspect, the project will provide demarcation of the forest boundary with the Project road by
providing barbed wire fencing through out the common boundary with forest reserves. This will be provided only
according to the recommendations of the ongoing Biodiversity Impact Assessment (BIA) studies.
ii) PWD is committed to compensate/plant trees according to the compensatory a forestation programme required
according to the Forest conservation Act 1980 as provided in paragraph 4.1
iii) Further, contractors are to set-up construction camps and plants (Hot mix, WMM plant etc) at least five km away
from the forest boundary. In this regard;
* Adequate training will be provided to contractors.
* The labour force will not allowed to enter forest reserves for the purpose of hunting, fuel wood collection, nuts
and fruit collection etc.* The debris and waste materials shall not be dumped inside /immediately out side forest areas and other
water sources.* Debris shall be disposed off according to the contractors debris disposal plan
* The source of construction water shall not be from the forest areas or immediately adjacent (within 2 km) to
the forest areas.* The construction work within the forest stretches should adhere to all international environmental standards
as laid out by the environmental management plan under the GOI/GOHP/WB rules and regulation.
During construction, the following measures will be taken in to consideration for effective implementation.
* No construction camps or other polluting plants within 0.5 kilometres of the forest reserves.
* No blasting shall be allowed during night time
* Blasting should be silent blasting along the forest reserves
* Blasting shall be confined to a particular time only. Best time would be 2-3 pm in day time.
* Hunting is strictly prohibited.* No cutting of trees from the forest reserves for any purpose relating to the construction work nor shall the
people associated with the project construction should enter the forest reserves other than any legal
requirements.* Contractor should erect appropriate sign boards during construction
* After construction, the CSC/HPRIDC should advice the locations for erecting the signboards including
advance signboards notifying the forest reserves.
* Immediately after construction fencing should be carried out parallel to the forest reserves.
* Any sign/indication of forest fires will be immediately notified to all concerned agencies
Immediately after construction, the contractors shall erect signboards and information boards close to the forest boundaries
according to the Environmental Management Plan (EMP) prepared for the link.
1 07
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 19: LIST OF ENHANCEMENT SITES1.0 ENHANCEMENT MEASURES
• Enhancement tree planting along the oxbow lands (2.760kms) and the other left over portions of theoriginal PWD land.* Cultural property enhancement as a part of the cultural property rehabilitation plan* Public amenities such as bus lay bys (all new), rain shelters (in addition to the compensatory rainshelters for lost ones), comfort stations (toilets) parking areas,* Information boards for the tourist, pilgrimage and other important structures of importance as
2.0 LIST OF ENHANCEMENT SITESA: PROPOSED PARKING AREAS (ENHANCEMENT)
1 90-91 Jahu 0.64
B: EXISTING PARKING AREAS MEHATPUR-UNA-AMB
I9 92-93 Jaahu Parking parking 22 102-103 Dhalwan Parking 1Total 3
3.0 SIGN/ANFORMATION BOARDS FOR TOURISM ENHANCMENT
C: IMPORTANT TOURIST PLACES IN THE PROJECT INFLUNECED AREA. (PIA)
No major Tourist Places
4.0 BORROW AREAS
This is also most unlikely that the corridor will require any borrow areas. However in the case of such an event where ina requirement of borrow areas then opening of new borrow areas could generate drainage issues and erosion andconsiderable loss of topsoil if adequate mitigation measures are not taken.
Louis Berger Chmi-n INr T TIA
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 20: SIGNIINFORMATION BOARDS FOR TOURISM ENHANCEMENT
- -No Major Tour
109
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
Appendix-21MITIGATION & ENHANCEMENT DRAWINGS:
Contract-4 Jahu-Kalkhar):
* 0+0- Reaignen enancmet Refe: SRPW BlTl/4/CBS/RA- I-- 104+6002 Proposed municipal Refer: SRP/WBIUG/4/ICB/MW- 1garbage collection point
(typical)*Dhalwan*Kalkhar
3 95-96 Information board at Refer:SRP/WB/UG/4/ICB/IB-1wildlife crossing-1
4 Debris disposal sites plan- Refer:SRP/WB/UG/4/ICB/DD-ldrawing
* Type-lI* Type-2
5 Water management plan Refer:SRP/WB/UG/4/ICB/WM-I6 Construction Camp Layout Refer:SRP/WB/UG/5/ICB/CC-17 Traffic management Plan Refer:SRP/WB/UG/4/ICB/TMS-1
& Construction Sequence Refer:SRP/WB/UG/4/ICB/TMS-lRefer: SRP/WB/UG/4/ICB/TMS- 18 General Type Drawings Refer:SRP/WB/UG/4/ICB/GN-1Refer: SRP/WB/UG/4/ICB/GN-2Refer:SRP/WB/UG/4/ICB/GN-3
Louis Berger Groun INC I IC A
- JAHU KALKHAR
XI
;o\ oreo ea/
A t ' PROPOSED PINE TREE
A PL4A500TION 0\ oCeC
PROPOSED PINE TREE A 7/ AFTER REMOVE EX. ROAD
PLANTATION 014m C/C SUFC
|IIALPEAEHROADAII
T .............w1....llTIELois rPI
-H-M-ACHAL PNRASRCUEDESH ROD AN |.. -RAT I TEoiBerger Group, Inc.,US Consultancy servces For Feasbility Of 1675 Km. PKOPOSED PLANTATION SRPCDVr%W
VDrPRP'IKPPO; S'RTIN DEVELOPMENT CORPORATION LTD. AndBKN^AM-E{
I" l**eD, Deaie En3Kn. edsngdaegurdhasesmn AT REJAUGNMENT
FAE RE77~PRV)fDrCRITNIOf43K.O od ne hs-I(aw/CA450T
0+0
JAUKAKA
CATCH DRAIN CONNECTED TO 00 1500 300 -j 300 [ 2000 | 300 VNEAR BY STORM WATER DRAIN - -
_ - :_ - _ _
300 So0
400 4 300
STONE MASONRY WALL I
2 CM 1:6 20 I
1200 MS DOOR I Iz10
WIT LCK400 DIA CIRCULAR OEIG
150mm MS/Cl GRATING GLLN FOR GARBAGE DR
GL -HO --
150 200- DRAIN CONECT TO IGi NEAR BY DISPOSAL POINT
300L r~ LI
PLA-300STONE MASONRY FOUNDATION L
ISTORM WATER DRAIN[9 -
- - - - - -- -- -- - --- -- - - - - PC 12:4SECTIONAL ELEVATION
TO THOG ~SECTION A-AROAD
TO ROHRU -
--------------------------- !
TYPICAL DETAILS OF MUNCIPAL GARBAGE
COLLECTION POINT
PROPOSED GARBAGE DUMPING &
COLLECTION POINT
TYPICAL LOCATION PLAN FORPROPOSED MUNCIPAL GARBAGE COLLECTION POINT
| AM- |1I-N PROTACT TITLE
HIMACHAL PRADESH ROAD AND l'. THE Louis Berger GroUp, lnc.,USA Consultancy SerAces For Feasibility Of 1675 Km. PROPOSED MUNCIPAL GARBAGE | r
OTHERINFRASTRUCTURE AAAKN ATA Eng,eA,, PlnFAD SCEAR, FCoAoA. And Detailed En4neering/Saleguard Assessment COLLECTION POINT lMW-i
A [ATF PRFP (K *PPADEVELOPMENTOCoRPORATIONLTD. | 5 AOf
413 Km. Of Roads Under Phase-I (Package-I) |JAHU-KALKHAR
INFORMATORYMESSAGE
INFORMATION SIGN BOARD
- -NA SIGN PROJECT:- TITLE.
HIMACHAL PRADESH ROAD AND -o.s *Us = THE Louis Berger Group, Inc.,USA Consultancy Services For Feasibility Of 1675 Kn. INFORMATORY SIGN BOARD s
OTHERINFRASTRUCTURE -By LJ - ngmuS Plumers M SeAESs n OoNu- And Detailed Engineerng/Safeguard Assessment IS-1
DEVELOPMENT CORPORATION LTD. Of 413 Km Of Roads Under Phase-I (Parg) JAHU - KALKHAR
DATE PREP. CHK PPROVE DLSCRI.ETON Of 413KmY Of R UDS -
Package-Ill
c CDUMPING SITE
QTY=9, 600 Cu m N
CC
LEGEND:- L 24o
DEBRIS DISPOSAL LOCATION Q7y20 000 Cfir
r I I r l l HIMACHAL PRADESH ROADOANO ti |" |ETHELOU;S B3erger Group Inc US/\ |Consuttancy Seace For Fesbijy Of 1675 Km. P ROJECTLAYOUT PLAN |wW,
| DATF |PREP |CIfK |APPROVED) |DSCRIPTION| EEOMNCROTO T.| (D Of 413 Kmn. Of Roads Under Phase- (Package-| (JHU TO NER CH0W)
Package-IllPackage-Ill
C11.76+000
110+000117+000
ULWAN PIOJ+0.
00
HIMACHAL PRADESH ROAD AND | | THE Louis Berger Group, Inc.USA Consultancy Services For Feasibilty Of 1675Km-. PROJECT LAYOUT PLAN S G
OTHERVINFRASTRUCTURE PP-RET LYUT TON)
DEVELOPMENT CORPORATION LTD., n ealdEgneigSfgadAssmn (WATER RESOURCE LOCATION)
=ATL PRPCThAPOU)DARITO
01413 Km. Of Roads Under Phase-I (Packrage-1 JAHU TO NER CHOWK
\ ~~- - - - - --- r - -- -- -- -CAMP BOUNDARY
CHAIN LINKl__ _ _ _ _ __ FENCING I
SKILLED LILABOURES IINSP IECT R'S CLINIC CRECHE
STORE 3m WIDE OFFICEBRICK PAVING IN I1:6 CEMENT
PLASTER
WEHICLE WASHING PAKNlOKR
CONSTRUCTION PLANTS TIET
l 7 METTLED ROAD 0D[30 AREA
-- -- -----J
ENTRY |
TYPICAL LAYOUT OF CONSTRUCTION CAMP
H lMAHAL PRADESH ROAD AND [ THE Louis BergeT Group, Inc.,USA Consultancy Services For Feasibilty Of 1675 K. TYPICAL LAYOUT OFDEEOTHERNFCRPSORUCTURN LTD. E- Uss p.,s. c~ns And Detailed Engineering/Safeguard Assessment CONSTRUCTION CAMP C-DEELPMN CORPORATIONELTD. F C M'A Of 413 Km. Of Roads Under Phase-I (Package-I)
Ee."N peonmttoedeald
STAGE - 3
TRARAFC COVVEMENTAREA
STAG -S.CW mSTAGE -4 bGo,bd and rras|r- r 2
C-tEWEC MOEMEN( AkE
ron hZ X-t-
TROAVE MOVEMENT AREA
r~Wt 5 1 875 ' 15 =,
E.camSTAGE -5
SdT I d r-a-dW SId
by rqk7 G aT CA S l.BTSIT. F
STAGE - 4|
f fJ TstFFC MrEMENT AREEat. Gpk) bGfi-.1 d M
|oe I Ceseb
bs MS
FCI-W by Ee
STAGE - I a5s r byr,. ENIr-
TFFIC FlVEMENT AREA
STAGE-TAG --- 5<
.. w VEC PAEAVES
Plan for Stage - 1, Stage -,2 & Stage - 5 T Reledoesed Baff* TeRpoty Re eeBareNOTE: (1) SHOULDER WIDTH 1.875 M FOR SINGLE LANE 81.5 M FOR NTERMEDIATE AND TWO LANE. Plan for Stage - 3 & Stage - 4
PROJECE. -IITLE,HIMACHAL PRADESH ROAD AND Ta OT , ,, THE Louis Berger Group, IncUSA Consultancy Services For Feasibility Of 1675 Km. TRAFFIC MANACEMFNTPIAN& SRPrWB AjGICBDEVELOPMENTCORPORATiONLTD hiECa I F ng-eT * Pi-neoeT * S-IsIEr * - And Detailed Engineering/Safeguard Assessment CONSTRUCTION SFQUENCF FOR TMS 1TF PKEP. CIRK. APPROVFD ON5LTD Of 413 Km. Of Roads Under Phase-I (Package-I)PROPOSEDRECONSTRUC1NTE PRERCIM.PROROSED DRECOFSTRUCTION
l SnH 8777Y5.5m , CW,a- CW/2 -SH *.87Y1 57m
STAGE - 0EXISTING X-SECTION
STAGE -4llnAPIiC MVEMENTAREA-
CONSTRUCTION OF DBM ON LEFT/RIGHT SIDESSA8751,sE,A -CW12--1-CW/2 .S1117Y5m ., TRAFFIC4MVEMENT REA
FPAVED S C.R2A.f d dLAp-od 8. dh*2 by E.
- -t --- - -.'f wvs-
STAGE -1 7dirOd.d by fHt agrD\DISMANTLING OF EXISTING SHOULDER ON RIGHT/LEFT SIDE STAGE - 5CONSTRUCTION OF AC/SDBC ON LEFT/RIGHT SIDE
FA RFFIC MOVEMENT AREA TFAFEIC MOVEMENT AREASIa.T8711.571 CWIA-------CW,a SR l.875I1.5..,
SAI.8D151, C W/Za CW/2l - SR187511.S
0AVEDSPA.
STAGE - 2BUILDING OF DISMANTLED HARD SHOULDER AS PERPROPOSED X-SECTION ON RIGHTtLEFT SIDE)
STAGE - 6COMPLETED LEFT X-SECTION WORKTIFIMOEET ARATO
BE SHIFTED ON RIGHT SIDE-SUriNASIm -CIVIl CWIA SETSAU5-
E-m875t15.S- t IO--.
PAV--SC -SAR 7.7..CW121CWdstrg g gd b b2 - l i o 24 1 1 .O m | 0.- VERDElaO E H.SVED
ExcaIvap e - ma.trM Iby ENh,
ASIA ft
EoodLpW EdsoFnlobed P. I . b. d Z ':5Ro b I d bgd b oin-W aAd byV
E Ep -
Rne5
U.bWdN.as,e 8.. 1 t-07 STAGE -3dd dby D. ERngh DISMANTLING OF LEFT/RIGHT SIDE
CARRIAGEWAY & SHOULDER STAGE - 7COMPLETED X-SECTION
I E e"CaM oy R Tmpy R.DnE Resed Sam a-D11&8AEESE C7I tgedk by 0E, C I Ow 5Sbags as diemed by ngieeI
u d iontea H FhgHoby EnEcmgea hga,..,
Flog Boy EoarIg C.nage"wy Flag Boy __Plan for Stage - 1, Stage - 2 & Stage -S
Tempoay RelleIsed B6nie, TemDpT,ay Retectcnaed Bsn7cfNOTE: (1) SHOULDER WIDTH 1.875 M FOR SINGLE LANE & t 5 M FOR INTERMEDIATE AND TwO LANE Platn fr Stage -3 8 Stage - 4(2) FINAL STAGE X-SECTION CONSISTS OF CW 3.7515.5 / 7.0 M 1 I M PAVED SHOULDER WITH 0.5 M VERGE ON EITHER SIDE.
HA LE SA -N TITLtHIMACHAL PRADESH ROAD AND - L -A.I THE Louis Berger G roup, Inc.,USA Consutancy Services For Feasibility Of 1675 Km. TYPICAL CROSS SECTION SRPN/B.G/JCBD EVELOPMENT CORPORATION LTD. RUCTUR E ngln- P Isa . P.S,I, Esoonl. And Detailed EngmneeringlSafeguard Assessment FOR TRAFFICE MANAGEMENT PLAN TMS 2
V DATE PREP CHK APPROVED D A
Of 413 Km. Of Roads Under Phase-I (Package-I) AND CONSTRUCTION SEQUENCE
=-~~~~~-ON Ml ------- -= Is 2'-SOEGE AWS. Cw,------W2 SI2.2S?SA
STAGE - 0
EXISTING X-SECTION STAGE - 4
COMPLETED LEFT X-SECTION WORK*- - TRAWElC MOVEMENT AREA TO BE SHIFTED ON RIGHT SIDE
-sH22AI3.7NV -cw,?------cw,2 AAJ2.s,3sJ,,
2 2WTRAFFc MOVMENT AREA
o.s5 vRGE . S" -cA w S-cw2 f VERGE
STAGE-- 1
TRFAFFc MOVEMENT AREA .Wor c- _Ar ^ C7S 2.2s/ 3 75 m-C I 2 2-CW I 2AT SH 2 25 1 .5 mSTAGE
5
|o.5r VE.re %D -CW/2 CW12 VE W VE.GE
STAGE-2 TRAPElC MOVEMENT AREA
--GS -STAGE
- 6
COMPLETED X-SECTIONSTAGE -3
CONSTRUCTION ON LEFT SIDE
- 30om m, m DASN by Eo k s -- 3m oA Db, OI- by E.0- RTenDO ary RefleolS0nsd Banew Temporary Refi0odAsed Barmer
Cones I Cemen/ begs as diected by EngineerrE.Isting Carriageway Comas / Cem0t bags as dimcte0d by Er Flgin Boy ED -Exsn3 CamE wwa Flag Boy
Co,rsljsdon RIN
Flag go3y ExSistin Camnageway FRag Boy .- l Ex arraeaPlan for Stage -1, Stage -2 & Stage -5 Tempary Ressed Barrier Tempraa ReIge-sed BarrSerNOTE: (1) SHOULDER WIDTH 1.875 M FOR SINGLE LANE & 1.5 M FOR INTERMEDLATE AND TWO LANE.
Plan for Stage - 3 & Stage - 4
SOE SION PROJECT- TnT.EHIMACHAL PRADESH ROAD AND R-Ral AAAO THE Louis Berger Group, Inc.,USA Consuhtancy Services For Feasibility Of 1675 Km. TRAFFIC MANAGEMENT PLAN SRPMRBBUGIICBOTHERINFRASTRUCTURE rehRS- AS EnerRA 1 - Pi-rAS - SAIRASS RO R-AnArt And Detailed Engineering/Safeguard Assessment & CONSTRUCTION SEQUENCE TMS3DEVELOPMENT CORPORATION LTD.
OrfAEOAA A AAAA 01413 Km. Of Roads Under Phase-I (Package-I) FOR RAISED SECTIONSTIE PRFP C(HK APPROVtD mESCKIPTION
ARROVEDrY A RlATO
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
FIGURE: TYPICAL LAYOUT OF PARTIAL Bus BAY IN URBAN AREA
BUS BAY I -lOom ND DOID LINT
ATH OUr0amA LONG AT O0cm INTERVAL.
CElEWAY
PEDESTRIAN CROSSING J100 WTDK SOLED LINE
HADTH SCALE 1:125LENGTH SCALE 1U250
ALL DOMENSIONS ARE IN mm UNLESS OTHERWSE SPECIFiED
FIGURE: TYPICAL PLANTATION SCHEME FOR Two LANE ROAD IN (PLAINS) WITH SHOULDERS
I I
Loi Bre Gru. INC. ...USA..8
-) -' *1*¶--- -, -
L ROAD SIDE ROW
OUTER ROW
Louis Berger Group, INC. USA
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
FIGURE: TYPICAL PLANTATION SCHEME FOR HILLS
PLANTATION SCHEME FOR HILLS
PAAPET WALL
'IN
-Y SIDE HILL 11
Tf~ I TA12
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 22: LIST OF OXBOW LAND AND OTHER LEFT OVER LAND
1 90+080 90+740 RHS 660m2 91+590 91+650 LHS 60m3 92+710 92+775 LHS 65m4 92+805 92+860 RHS 55m5 93+050 93+170 LHS 120m6 93+810 93+850 LHS 40m7 95+245 95+280 RHS 35m8 96+030 96+060 RHS 30m9 96+215 96+260 RHS 45m10 96+300 96+370 RHS 70m11 96+585 96+710 RHS 125m12 97+235 97+275 RHS 40m13 97+320 97+370 RHS 50m14 97+720 97+750 RHS 30m15 97+760 97+800 LHS 40m16 98+165 98+220 RHS 55m17 98+525 98+555 RHS 30m18 98+700 98+740 RHS 40m19 99+225 99+270 RHS 45m20 99+665 99+695 RHS 30m21 100+420 100+460 RHS 40m22 100+550 100+590 RHS 40m23 100+740 100+780 RHS 40m24 102+140 102+200 RHS 60m25 102+270 102+340 RHS 70m26 102+370 102+430 RHS 60m27 103+095 103+130 RHS 35m28 103+370 103+430 RHS 60m29 103+490 103+550 RHS 60m30 103+580 103+610 RHS 30m31 103+770 103+805 RHS 35m32 103+915 103+960 RHS 45m33 104+120 104+150 RHS 30m34 104+310 104+350 RHS 40m35 104+405 104+485 RHS 80m36 104+720 104+765 RHS 45m37 104+935 105+010 RHS 75m38 105+470 105+540 RHS 70m39 105+905 105+980 RHS 75m40 106+790 106+855 RHS 65m41 107+785 107+825 RHS 40m
Total 2.760 km
Louis Ber2er Groun INC I ISA
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
APPENDIX 23POLICY GUIDELINES FOR CONTROL OF LOCATION. INSTALLATION OR WORKING OF STONE
CRUSHERS AND THEIR REGISTRATION IN THE STATE OF HIMACHAL PRADESH.
GEOLOGICAL WINGDEPARTMENT OF INDUSTRIES
UDYOG BHAWAN, SHIMLA-1,
Taking into consideration the overriding principle of protection of ecology and environment, to ensure that not a single
stone crushing unit in the State causes any Pollution of any type and in consonance with the " River/Stream Bed Mining
Policy Guidelines for the State of Himachal Pradesh-2004" as notified on 28-2-2004, the State Government hereby makes
following Policy Guidelines for control of location, installation, workings of stone crushers and their registration thereof.
1.0 MINING LEASE MANDATORY FOR RUNNING A STONE CRUSHER.1.1 In order to ensure legal and regular supply of minor minerals, every owner of stone crusher, shall have a
valid mining lease for this purpose.1.2 In respect of River/Stream Bed Mining leases over larger area of ten hectare or above shall be given priority
for setting up of stone crushers.
For Hill Slope mining, lease area shall depend upon the size of crusher, availability of mineral and annual requirement of
mineral in relaton to scientific mining. In any case, the area shall not be less than 15 Bighas.
If the area is less than 15 Bighas and in no case less than 5 Bighas, the period of lease shall be determined, based on
reserves calculated and annual requirement as per the proposals given in the Working-cum-Environmental Management
Plan, which every lease holder shall have to prepare.
2.0 PROVISIONAL REGISTRATION OF STONE CRUSHER.2.1 No person shall install or run any stone crusher in any area within the State of Himachal Pradesh unless he obtains a
Provisional Registration from the Geological Wing, Department of Industries. For this an application in Form"A" shall be
submitted and it shall be accompanied by:-a) A fee of Rs. 2500/- (Two thousand and five hundred )only.b) Revenue record and site plan of the land on which the stone crusher is proposed to be installed, showing the
location of the stone crusher with reference to various siting parameters as notified by Govt. on dated 29-4-03. or
amended from time to time.(A stone crusher should have a minimum working area ranging from 2-5 Bighas, depending upon the size of the stone
crusher for raising machineryl plant and stacking of raw material/finished product in private land or in Govt. land after
completing codel formalities and obtaining land lease from the competent authority).c) In case of private land, consent of land owner where the stone crusher is to be installed.d) An application for mining lease from where the minor mineral shall be used as raw material for feeding/running the
stone crusher. This area should be within 5 Kms. radius of the stone crusher.
2.2 Based on these documents 'Provisional Registration' shall be issued by the Geological Wing, Department of Industries
which shall form base for obtaining pre-production clearance from other Government Departments.
2.3 After provisional registration and Joint Inspection, the consent to Establish from the Himachal Pradesh State
Environment Protection & Pollution Control Board (HPEP & PCB) should be obtained. The unit shall submit the Working-
cum-Environment Management Plan before the issuance of Consent to Operate (COP) by the State Board.
2.4 Himachal Pradesh State Electricity Board shall give electric connection to the crusher owner only after obtaining
Provisional Registration from the Geological Wing.
TNTC' I TV A 114
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
2.5 Already established stone crusher shall registered themselves within a period of 3 months from the date of issuance ofthese Policy Guidelines and for this registration they have to produce consent issued by Himachal Pradesh EnvironmentProtection & Pollution Control Board.
3.0 JOINT INSPECTION OF THE AREAS APPLIED FOR MINING LEASE AND FOR SETTING UP OF STONECRUSHER.
3.1 A) JOINT INSPECTION OF CRUSHER SITE.The site for sefting up the stone crusher shall be appraised and approved by a Joint Inspection Committee, consisting of thefollowing members( as per Notification of Deptt. of Science & Technology dated 29-4-03)
1. Sub-Divisional Officer(Civil) concerned Chairman.2. Divisional Forest Officer or his representative Member3. Representative of the State Environment Protection and Pollution Control Board. Member.4. Executive Engineer, PWD or his representative Member5. Executive Engineer, I&PH or his representative Member6. Representative of the Deptt. of Tourism Member7. Representive of HPSEB -Local SDO(E) Member8. Geologist or Mining Officer Member Secretary
(B) Joint inspection shall be conducted at least by four members viz. Chairman, representabive of H.P. State EnvironmentProtection & Pollution Control Board, D.F.O. or his representative and GeologisV Mining Officer on a prescribed checklist.Other members may issue separate NOC's as per the check list.
3.2 JOINT INSPECTION OF THE AREA APPLIED FOR MINING LEASE.a) The area applied for lease shall be inspected by a Committee consisting of the following members ( as per River/StreamBed Mining Policy Guidelines for the State of H.P. 2004: notified on 28-2-04).
1 Sub-Divisional Officer (Civil) concerned Chairman.2 Assistant Conservator of ForestRange Officer Member3 Representative of the State Environment Protection and Pollution Control Board. Member.4 Executive Engineer, PWD or his representative Member5 Executive Engineer, I&PH or his representative Member6 Representative of the Dept. of Tourism Member7 Mining Officer Member Secretary
(b) Joint Inspection shall be conducted by at least three members viz. Chairman, Assistant Conservator ForesVRangeOfficer and Mining Officer on the prescribed check list. Other members may issue separate NOC's as per the check list.
3.3 The grant of Mining lease and approval of stone crusher site by the Committee shall be the basis for issuance ofpermanent registration.
4.0 PERMANENT REGISTRATION.
(a) Based on the approval of sites for setting up of the stone crusher grant of mining lease and after obtainingconsent to operate from the Pollution Control Board. Permanent registration shall be issued to the owner ofthe stone crusher by the Geological Wing, Department of Industries, which shall be valid for a period of twoyears (Form-B).
(b) The Geological Wing, Department of Industries may renew the Registration for a further period or periods oftwo years subject to proper functioning of the stone crusher as per the provision of various Acts and Rulesand clearance of all dues including clearance from Pollution Control Board.
(c) In case the Geological Wing, Department of Industries is of the opinion that it is not expedient to grant apermanent registration taking into consideration the various factors as per the recommendabions of the JointInspection Committee, Geological Wing, Department of Industries may after giving an opportunity of beingheard and for reasons to be recorded in writing and communicated to the applicant, refuse to grant thepermanent registration.
I fuic 1or f--_ UTxr r TC- A
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
(d) In case of renewal of the registration, the owner of the Stone Crusher shall apply for the renewal at least six
month's before the expiry of the registration in 'Form-A'.(e) In case, the application for renewal submitted is not disposed off before the expiry of the period of
registration, it shall be deemed to have been extended by a further period till the Geological Wing,
Department of Industres passes order thereon.
5.0 OTHER CONDITIONS FOR RUNNING OF STONE CRUSHERS.
a) The owner of the stone crusher shall observe the provisions of;* The Air (Prevention and Control of Pollution ) Act, 1981 and rules framed there under.
* The Water (Preventon and Control of Pollution) Act 1974 and rules framed there under.
* The Environment(Protection) 1986 and rules framed there under.* The Noise Pollution (Regulation and Control) rules 2000.
b) No consent for expansion to a crusher shall be given by Pollution Control Board or electric connection by
H.P. SEB, without prior approval of Geological Wing, Department of Industries.c) Every stone crusher owner shall ensure that the emission standards as per the statute and as notified by the
Govt. on 29-4-03 are adhered to.d) Every stone crusher owner shall adopt pollution control measures as per Govt. notification dated 29-4-03 or
as amended from time to time.e) The Geological Wing, Department of Industries may impose any such further conditions as it may deem fit for
the protection of Environment and Ecology.f) The crusher owner shall submit a return by 10th of every month, giving details of total quantity of minerals
crushed, electricity consumed, power generated in case of captive power generated run crusher, fuelconsumption in case of diesel run crusher, number of labour employed and wages paid etc. .
g) The crusher owner shall allow the inspecting staff, access to the crusher and make available all recordsrelating to operation of the crusher and verification of source of legal supply of minor minerals and stocks.
6.0 CONDITIONS FOR MINING LEASES:a) As per strategy No. 9.6 of River/Stream Bed Mining Policy Guidelines and Rule 21 (4)(i) of H.P. Minor Mineral
(Concession) Revised Rules, 1971 (as amended on 10-6-04) every applicant shall submit Working-cum-EnvironmentManagement Plan for carrying out systematic and scientific mining.
b) Mining in river/stream beds shall be subject to general conditions as per Strategy No.9.5 of the River/Stream Bed
Mining Policy Guidelines in addition to any other site specific conditons as specified by the Joint Inspecton
Committee, as detailed below:-c) Mining in Hill slopes shall be subject to following general conditions:-
I. Environmental Considerations:* No mining shall be allowed within 100 metres of thickly forested area.* No mining shall be allowed in areas, which may cause aesthetic/visual degradation near any known
tourist spot.No mining shall be allowed where it is likely to disrupt water regime, IPH schemes roads, bridges etc.
No mining shall be allowed where danger to site of culture, religions, historical, archeological or scenic
importance is likely.No mining shall be allowed near habitation, where it is likely to cause noise and vibration problems, dueto blasting or operation of machinery.
* No mining shall be allowed where proper disposal of mine waste cannot be arranged.Conditions shall be imposed that the lease holder will take adequate steps to control and check soilerosion, debris flow etc. by raising various engineering structure.
II. Geological and Geomorphological considerations:* No mining shall be allowed where the slope angles are more than 45O from horizontal and in case of
mid slope mining, the foot wall should be of hard strata.* No mining lease shall be granted where the ore to overburden rabo is not economical i.e. 1:0.2 that is
the waste generation should not be more than 20%.• Proper appraisal of the deposit for its qualitative and quantitative assessment shall be made in the form
of Geological and topographical plans.
III. Technical Consideration:
- -116
Himachal State Roads Project Environmental Management plan (Jahu-Kalkhar Section)
* The area should not be highly jointed, fractured on consisting of weak planes.
* Relation of slope angle to angle of repose should be within mining parameters where 6x6 metre
benches by keeping overall angle of repose as 45o can be made.* No mining shall be allowed where subsidence of rocks is likely due to steep angle of slope.
* No overhangs shall be allowed to be formed during the course of mining.
* The gradient of approach roads shall be gentle with hill-ward slope, side drains and parapet walls.
Adequate number of waiting and crossing points shall be provided for safe plying of vehicles.
* No blasting shall be resorted to without taking proper licence under Explosive Act.
d) General Conditions:* Mining site shall only be handed over to the lease holder, after it is duly demarcated by permanent
boundary pillars and certified by concerned Mining Officer.* Junction at take off point of approach road with main road shall be developed with proper width and
geometrics required for safe movement of traffic by crusher owner at his own cost in consultation with
Executive Engineer, H.P. PWD.* No lease holder shall store/stack any material in the acquired width of PWD road without the specific
permission of the competent authority.* In addition to above the mining operation shall be subject to provisions of various Acts and Rules in
force.* Dumping of waste shall be done in earmarked places as per the Working Plans.
Table: Parameters for new stone crushers to be set up in future
i Minimum distance from NH/SH 150 mtrs
ii Minimum distance from Link roads/other DisH. Roads 75 mtrs.
iii Minimum distance from District Head-Quarters 1 .5 km
iv Minimum distance from Town/Notified Area Committee 1 km
v Minimum distance from Village Abadi deh 500 mtrs.
vi Minimum distance from Hospital/Education Institution 1 km
vii Minimum distance from Natural water Springs 500 mtrs.
viii Minimum distance from Notified parks 2 kms
ix Minimum distance from Sanctuaries 1 km
x Minimum distance from Bridge Sites 200 mtrs, Upstream
xi Minimum distance from Notified Lakes and Wetlands 300 mtrs.
1 7