good neighbourly relations committee city of brossard - may 4, 2016
TRANSCRIPT
Good Neighbourly Relations Committee Meeting City of Brossard: May 4, 2016 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau
New Champlain Bridge Corridor Project
2
Committee Members
Residents Luis Oscar Corrales Ginette Dufresne Marc Gagné Nabil Halouani Jacques Picard Jaime Reis Marc Turcotte – Representative from a community organization Éric Jutras – Member of the business community Partners Dan Genest – The Signature on the Saint-Laurent team Benoît Fillion – City of Brossard Vincent Jarry – Infrastructure Canada
New Champlain Bridge Corridor Project
Scope:
• Based on similar initiatives in other large-scale projects, creation of the Good Neighbourly Relations Committee (hereafter the “Committee”) to favour exchanges between SSL and residents, merchants and community organizations
• The primary purpose of the Committee is to proactively share all information on: Work completed, underway and to come
Anticipated impacts
Associated mitigation measures
• The meetings shall serve to: Answer questions
Find possible solutions for the various issues that are raised
Engage in discussions in an open and transparent manner
3
New Champlain Bridge Corridor Project
SSL’s commitment
SSL is committed to:
• Listening to Committee members, answering their questions and concerns, and providing them with accurate and up-to-date information throughout the project
• Making the required information available to residents, merchants and community organizations as well as making such information easily accessible on various platforms
• Searching for solutions to respond to the concerns raised
by the Committee
4
New Champlain Bridge Corridor Project
1. Inform you about the work that has been completed, is under way and planned between now and October 2016
2. Present the proposal retained for the anti-noise walls on the South Shore
3. Answer questions, find possible solutions and discuss the issues
Aim of the meeting
5
New Champlain Bridge Corridor Project
Agenda
6
Series Item Duration Time
1. Opening 10 min. 7:00 to 7:10 pm
2.
Work completed, underway and to come • Eastern approach area • Hwy-10 area • Cable-stayed bridge area
30 min. 7:10 to 7:40 pm
3. Committee question period 10 min. 7:40 to 7:50 pm
4. Anti-noise walls 30 min. 7:50 to 8:20 pm 5. Committee question period 10 min. 8:20 to 8:30 pm
6. Varia 10 min. 8:30 to 8:40 pm
7. General public question period 30 min. 8:40 to 9:10 pm
8. Adjournment: next meeting and topic 5 min. 9:10 to 9:15 pm
New Champlain Bridge Corridor Project
Work completed in the last months
New Champlain Bridge Corridor Project
Overview of completed work
8
• Pile caisson drilling and concreting in the East Approach: 61 out of 78 (78% complete)
• Start of work on footing forms in the East Approach
• Abutment started
• Relocation of water main and other utilities
New Champlain Bridge Corridor Project
• Easy winter: solid progress for work in general in the East Approach
• Relocation of water main: excellent cooperation by the City of Brossard and the City of Longueuil
• Work site facilities basically completed: concerns with respect to access to the work site and motorist safety
• Very few complaints
Completed work: observations
9
New Champlain Bridge Corridor Project
Complaints handling (early June 2015 to April 29, 2016)
Topic
Sector
Brossard
Closed Open Total
Noise 4 - 4
Air quality 0 - 0
Traffic 1 - 1
Vibrations 1 - 1
Brightness 1 - 1
Other 6 1 7
Total 13 1 14
10
New Champlain Bridge Corridor Project
Main priorities for the coming months South Shore
New Champlain Bridge Corridor Project
1 2 3
Location of areas City of Brossard
Gaétan Laberge and Wellington
12
New Champlain Bridge Corridor Project
Highway 10
• Soil management and earthworks
East Approach of the new Champlain Bridge
• Construction of footings and pier bases
• Construction of eastern abutment
• Start of installation of prefabricated segments of piers and pier caps
Cable-stayed bridge
• Construction of main pylon and rear span
South Shore Priorities: May to October 2016
13
New Champlain Bridge Corridor Project
Description of activity Approximate duration of work
Planned work period
Legend: Work and impacts
• Traffic and public transportation: • Proximity of residential areas: • Boating: • Bike paths:
Minor impact Medium impact
Major impact
Indication by level colour code
14
New Champlain Bridge Corridor Project
Key activities under way and to come East Approach
Design and planning underway so modifications are possible
New Champlain Bridge Corridor Project
Objective: Construction of East Approach of the new Champlain Bridge
Upcoming work:
• Completion of pile caissons
• Forming and concreting of footings and pier bases
• Construction of eastern abutment columns and pier caps
• Placement of prefabricated segments of piers and pier caps
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise levels) are significant
• Nighttime work, to the extent possible, when the impacts on daytime traffic are too significant
East Approach area
16
New Champlain Bridge Corridor Project
Nov 2015
May 2016
Nov 2016
May 2017
Nov 2017
Nov 2018
May 2018
Construction of footings
Installation of piers and pier caps
Assembly of superstructure and deck
Finishing work
East Approach: Timetable
17
Feb 2016
Aug 2016
Feb 2017
Aug 2017
Feb 2018
Aug 2018
New Champlain Bridge Corridor Project
Work and impacts: East Approach
Pile caisson drilling and concreting and cofferdam placement
Duration: five months Projected period: January to May 2016
18
40-metre navigational corridor
New Champlain Bridge Corridor Project
Work and impacts: East Approach
Forming and concreting of footings and pier bases Duration: six months
Projected period: April to September 2016
19
40-metre navigational corridor
New Champlain Bridge Corridor Project
Work and impacts: East Approach
Construction of East Abutment Duration: seven months
Projected period: January to July 2016
20
New Champlain Bridge Corridor Project
Work and impacts: East Approach
Placement of prefabricated segments of piers and pier caps
Duration: one year Projected period: August 2016 to August 2017
21
New Champlain Bridge Corridor Project
Work and impacts: La
Riveraine bike path
22
Detour of La Riveraine bike path until summer 2019
DETOUR OF LA RIVERAINE BIKE PATH
New Champlain Bridge Corridor Project
Work and impacts: East Approach work site exit
23
Worker parking
Daily flow of traffic • 20 heavy trucks •150 light vehicles
New Champlain Bridge Corridor Project
Key activities under way and to come Highway 10
Design and planning under way so modifications are possible
New Champlain Bridge Corridor Project
Highway 10 area
25
Objective: Area reserved for soil management for the work site and preparatory work for the reconfiguration of highway links
Upcoming work:
• Soil storage and earthworks at the eastern abutment
• Creation of a retaining basin for permanent drainage
• Installation of permanent anti-noise walls
Approach:
• Daytime work, to the extent possible, when the impacts (especially noise levels) are significant
• Night-time trucking from the West Approach to the East Approach
New Champlain Bridge Corridor Project
Work and impacts: Highway 10
Soil management and creation of a retaining basin Duration: duration of project
Projected period: 2016 to 2019
26
New Champlain Bridge Corridor Project
Work and impacts: Highway 10
Earthworks at the eastern abutment Duration: one year
Projected period: April 2016 to spring 2017
27
New Champlain Bridge Corridor Project
Key activities under way and to come Cable-stayed bridge
Design and planning underway so modifications are possible
New Champlain Bridge Corridor Project
Cable-stayed bridge: Timetable
29
2. Pylon foundations October 2015 to April 2016 1. Jetty
August to October 2015
6. Main span March 2017 to June 2018
3. Rear span November 2015 to March 2017
5. Upper pylon September 2016 to
June 2017
4. Lower pylon May to September 2016
New Champlain Bridge Corridor Project
Cable-stayed bridge: Overview
30
New Champlain Bridge Corridor Project
Work and impacts: Seaway dike bike path
31
Occasional closures starting this summer Final closure: fall 2016 or spring 2017 (TBC) to December 2018
New Champlain Bridge Corridor Project
Anticipated impacts
New Champlain Bridge Corridor Project
Anticipated impacts
• Road, bicycle and water traffic
• Noise
• Air quality
33
New Champlain Bridge Corridor Project
Traffic
• JCCBI blitz from May 6 to 9: complete closure of northbound Hwy-15 North
• Fall JCCBI blitz: four weekends in September and October
• Minimal impact over the next six months: shoulder closure and lane deviation
• Upcoming major disruptions: installation of
superstructure and deck above Highway 132 traffic lanes
34
New Champlain Bridge Corridor Project
Bike traffic
35
• Detour of La Riveraine bike path until summer 2019 • Closure of Seaway dike bike path between Champlain
Bridge and the St-Lambert locks starting in all 2016 or spring 2017 (TBC) until December 2018
New Champlain Bridge Corridor Project
Water traffic
36
Background
• Work site in water as well as a transport corridor for heavy parts between the Port of Montreal and the cable-stayed bridge area
• Navigational vigilance in the St. Lawrence
and in the Lesser La Prairie Basin
• Four one-day-long closures of the Lesser La Prairie Basin navigational corridor
Main mitigation measures • Communication • Waterway signs and marking • Patrolling and nautical surveillance • Equipment lighting
New Champlain Bridge Corridor Project 37
B1: Turenne area B2: Voltaire area B3: Tisserand area
Noise management Ar
ea Activity
Period J/S/N
Exposed sensitive
area
Ambient noise dBA
Criterion dBA
Estimatednoise dBA
Required measures
Pile caisson drilling and concreting and cofferdam
placement J B1 60 75 75 Monitoring
required
Forming and concreting of footings and pier bases J B1/B2 60/62 75 68/66 Not required
Construction of eastern abutment J B1/B2 60/62 75 62/66 Not required
Placement of prefabricated segments of piers and
pier caps J B1/B2 60/62 75 61/64 Not required
A10 Earthworks at the Eastern
Abutment
J B2 62 75 73 Monitoring required
Cabl
e-st
ayed
br
idge
Miscellaneous work J B1/B2 60/62 75 61/63 Not required
East
App
roac
h
New Champlain Bridge Corridor Project 38
Noise management
Noise-sensitive zones
New Champlain Bridge Corridor Project
Air quality management
Regulatory framework - Contractual environmental obligations - Clean Air Regulation (CAR)
Applicable MDDELCC standards
MDDELCC CAR
PMt PM2.5
120 ug/m3 30 ug/m3
39
New Champlain Bridge Corridor Project
Next meetings
New Champlain Bridge Corridor Project
• Good Neighbourly Relations Committee: September 21 or 28 (TBC) Topic: none projected
• No public information meeting is planned for the time being
Next meetings (for discussion)
41
New Champlain Bridge Corridor Project
• Newsletter: sign up online
• Information sheets delivered to residents’ homes, if required, and notices in local newspapers
• Sign up / contact us: Website: www.newchamplain.ca Email: [email protected]
Phone us at: (514) 876-1020 Twitter: @NOUV_CHAMPLAIN
Communication
42
New Champlain Bridge Corridor Project