good neighbourly relations committee city of brossard - may 4, 2016

43
Good Neighbourly Relations Committee Meeting City of Brossard: May 4, 2016 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau

Upload: nouveau-champlain

Post on 09-Jan-2017

85 views

Category:

Engineering


3 download

TRANSCRIPT

Page 1: Good neighbourly relations committee City of Brossard - May 4, 2016

Good Neighbourly Relations Committee Meeting City of Brossard: May 4, 2016 New Champlain Bridge Corridor Project Centre communautaire Nathalie Croteau

Page 2: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

2

Committee Members

Residents Luis Oscar Corrales Ginette Dufresne Marc Gagné Nabil Halouani Jacques Picard Jaime Reis Marc Turcotte – Representative from a community organization Éric Jutras – Member of the business community Partners Dan Genest – The Signature on the Saint-Laurent team Benoît Fillion – City of Brossard Vincent Jarry – Infrastructure Canada

Page 3: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Scope:

• Based on similar initiatives in other large-scale projects, creation of the Good Neighbourly Relations Committee (hereafter the “Committee”) to favour exchanges between SSL and residents, merchants and community organizations

• The primary purpose of the Committee is to proactively share all information on: Work completed, underway and to come

Anticipated impacts

Associated mitigation measures

• The meetings shall serve to: Answer questions

Find possible solutions for the various issues that are raised

Engage in discussions in an open and transparent manner

3

Page 4: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

SSL’s commitment

SSL is committed to:

• Listening to Committee members, answering their questions and concerns, and providing them with accurate and up-to-date information throughout the project

• Making the required information available to residents, merchants and community organizations as well as making such information easily accessible on various platforms

• Searching for solutions to respond to the concerns raised

by the Committee

4

Page 5: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

1. Inform you about the work that has been completed, is under way and planned between now and October 2016

2. Present the proposal retained for the anti-noise walls on the South Shore

3. Answer questions, find possible solutions and discuss the issues

Aim of the meeting

5

Page 6: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Agenda

6

Series Item Duration Time

1. Opening 10 min. 7:00 to 7:10 pm

2.

Work completed, underway and to come • Eastern approach area • Hwy-10 area • Cable-stayed bridge area

30 min. 7:10 to 7:40 pm

3. Committee question period 10 min. 7:40 to 7:50 pm

4. Anti-noise walls 30 min. 7:50 to 8:20 pm 5. Committee question period 10 min. 8:20 to 8:30 pm

6. Varia 10 min. 8:30 to 8:40 pm

7. General public question period 30 min. 8:40 to 9:10 pm

8. Adjournment: next meeting and topic 5 min. 9:10 to 9:15 pm

Page 7: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work completed in the last months

Page 8: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Overview of completed work

8

• Pile caisson drilling and concreting in the East Approach: 61 out of 78 (78% complete)

• Start of work on footing forms in the East Approach

• Abutment started

• Relocation of water main and other utilities

Page 9: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

• Easy winter: solid progress for work in general in the East Approach

• Relocation of water main: excellent cooperation by the City of Brossard and the City of Longueuil

• Work site facilities basically completed: concerns with respect to access to the work site and motorist safety

• Very few complaints

Completed work: observations

9

Page 10: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Complaints handling (early June 2015 to April 29, 2016)

Topic

Sector

Brossard

Closed Open Total

Noise 4 - 4

Air quality 0 - 0

Traffic 1 - 1

Vibrations 1 - 1

Brightness 1 - 1

Other 6 1 7

Total 13 1 14

10

Page 11: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Main priorities for the coming months South Shore

Page 12: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

1 2 3

Location of areas City of Brossard

Gaétan Laberge and Wellington

12

Page 13: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Highway 10

• Soil management and earthworks

East Approach of the new Champlain Bridge

• Construction of footings and pier bases

• Construction of eastern abutment

• Start of installation of prefabricated segments of piers and pier caps

Cable-stayed bridge

• Construction of main pylon and rear span

South Shore Priorities: May to October 2016

13

Page 14: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Description of activity Approximate duration of work

Planned work period

Legend: Work and impacts

• Traffic and public transportation: • Proximity of residential areas: • Boating: • Bike paths:

Minor impact Medium impact

Major impact

Indication by level colour code

14

Page 15: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Key activities under way and to come East Approach

Design and planning underway so modifications are possible

Page 16: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Objective: Construction of East Approach of the new Champlain Bridge

Upcoming work:

• Completion of pile caissons

• Forming and concreting of footings and pier bases

• Construction of eastern abutment columns and pier caps

• Placement of prefabricated segments of piers and pier caps

Approach:

• Daytime work, to the extent possible, when the impacts (especially noise levels) are significant

• Nighttime work, to the extent possible, when the impacts on daytime traffic are too significant

East Approach area

16

Page 17: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Nov 2015

May 2016

Nov 2016

May 2017

Nov 2017

Nov 2018

May 2018

Construction of footings

Installation of piers and pier caps

Assembly of superstructure and deck

Finishing work

East Approach: Timetable

17

Feb 2016

Aug 2016

Feb 2017

Aug 2017

Feb 2018

Aug 2018

Page 18: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work and impacts: East Approach

Pile caisson drilling and concreting and cofferdam placement

Duration: five months Projected period: January to May 2016

18

40-metre navigational corridor

Page 19: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work and impacts: East Approach

Forming and concreting of footings and pier bases Duration: six months

Projected period: April to September 2016

19

40-metre navigational corridor

Page 20: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work and impacts: East Approach

Construction of East Abutment Duration: seven months

Projected period: January to July 2016

20

Page 21: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work and impacts: East Approach

Placement of prefabricated segments of piers and pier caps

Duration: one year Projected period: August 2016 to August 2017

21

Page 22: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work and impacts: La

Riveraine bike path

22

Detour of La Riveraine bike path until summer 2019

DETOUR OF LA RIVERAINE BIKE PATH

Page 23: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work and impacts: East Approach work site exit

23

Worker parking

Daily flow of traffic • 20 heavy trucks •150 light vehicles

Page 24: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Key activities under way and to come Highway 10

Design and planning under way so modifications are possible

Page 25: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Highway 10 area

25

Objective: Area reserved for soil management for the work site and preparatory work for the reconfiguration of highway links

Upcoming work:

• Soil storage and earthworks at the eastern abutment

• Creation of a retaining basin for permanent drainage

• Installation of permanent anti-noise walls

Approach:

• Daytime work, to the extent possible, when the impacts (especially noise levels) are significant

• Night-time trucking from the West Approach to the East Approach

Page 26: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work and impacts: Highway 10

Soil management and creation of a retaining basin Duration: duration of project

Projected period: 2016 to 2019

26

Page 27: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work and impacts: Highway 10

Earthworks at the eastern abutment Duration: one year

Projected period: April 2016 to spring 2017

27

Page 28: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Key activities under way and to come Cable-stayed bridge

Design and planning underway so modifications are possible

Page 29: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Cable-stayed bridge: Timetable

29

2. Pylon foundations October 2015 to April 2016 1. Jetty

August to October 2015

6. Main span March 2017 to June 2018

3. Rear span November 2015 to March 2017

5. Upper pylon September 2016 to

June 2017

4. Lower pylon May to September 2016

Page 30: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Cable-stayed bridge: Overview

30

Page 31: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Work and impacts: Seaway dike bike path

31

Occasional closures starting this summer Final closure: fall 2016 or spring 2017 (TBC) to December 2018

Page 32: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Anticipated impacts

Page 33: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Anticipated impacts

• Road, bicycle and water traffic

• Noise

• Air quality

33

Page 34: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Traffic

• JCCBI blitz from May 6 to 9: complete closure of northbound Hwy-15 North

• Fall JCCBI blitz: four weekends in September and October

• Minimal impact over the next six months: shoulder closure and lane deviation

• Upcoming major disruptions: installation of

superstructure and deck above Highway 132 traffic lanes

34

Page 35: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Bike traffic

35

• Detour of La Riveraine bike path until summer 2019 • Closure of Seaway dike bike path between Champlain

Bridge and the St-Lambert locks starting in all 2016 or spring 2017 (TBC) until December 2018

Page 36: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Water traffic

36

Background

• Work site in water as well as a transport corridor for heavy parts between the Port of Montreal and the cable-stayed bridge area

• Navigational vigilance in the St. Lawrence

and in the Lesser La Prairie Basin

• Four one-day-long closures of the Lesser La Prairie Basin navigational corridor

Main mitigation measures • Communication • Waterway signs and marking • Patrolling and nautical surveillance • Equipment lighting

Page 37: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project 37

B1: Turenne area B2: Voltaire area B3: Tisserand area

Noise management Ar

ea Activity

Period J/S/N

Exposed sensitive

area

Ambient noise dBA

Criterion dBA

Estimatednoise dBA

Required measures

Pile caisson drilling and concreting and cofferdam

placement J B1 60 75 75 Monitoring

required

Forming and concreting of footings and pier bases J B1/B2 60/62 75 68/66 Not required

Construction of eastern abutment J B1/B2 60/62 75 62/66 Not required

Placement of prefabricated segments of piers and

pier caps J B1/B2 60/62 75 61/64 Not required

A10 Earthworks at the Eastern

Abutment

J B2 62 75 73 Monitoring required

Cabl

e-st

ayed

br

idge

Miscellaneous work J B1/B2 60/62 75 61/63 Not required

East

App

roac

h

Page 38: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project 38

Noise management

Noise-sensitive zones

Page 39: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Air quality management

Regulatory framework - Contractual environmental obligations - Clean Air Regulation (CAR)

Applicable MDDELCC standards

MDDELCC CAR

PMt PM2.5

120 ug/m3 30 ug/m3

39

Page 40: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

Next meetings

Page 41: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

• Good Neighbourly Relations Committee: September 21 or 28 (TBC) Topic: none projected

• No public information meeting is planned for the time being

Next meetings (for discussion)

41

Page 42: Good neighbourly relations committee City of Brossard - May 4, 2016

New Champlain Bridge Corridor Project

• Newsletter: sign up online

• Information sheets delivered to residents’ homes, if required, and notices in local newspapers

• Sign up / contact us: Website: www.newchamplain.ca Email: [email protected]