good design is not enough 20 cm subgrade strength · good design is not enough ... 1961 the aasho...

12
2013 IJPC Paper 160-2 © Copyright 2013 IJPC International Journal of Pavements Conference, São Paulo, Brazil Page 1 PAVEMENT DESIGN OR PAVEMENT MANAGEMENT? GOOD DESIGN IS NOT ENOUGH Waheed Uddin Director, Center for Advanced Infrastructure Technology (CAIT), the University of Mississippi, USA Ralph Haas Professor Emeritus, University of Waterloo, Waterloo, Ontario, Canada N2L 3G1 W. Ronald Hudson * * DeWitt C. Green Professor Emeritus, University of Texas, Senior Consultant, AgileAssets, Inc. 3001 Bee Caves Road, Austin, Texas 78746, USA [email protected] ABSTRACT: Design is only one of many factors in providing good, economical pavement performance, albeit an important starting place. Engineers keep seeking the elusive, perfect mechanistic pavement design method as the “Total Solution,” to providing good pavements as evidenced by the US $15 million spent on the Mechanistic - Empirical Pavement Design Guide (MEPDG) and more money needed for calibration in the USA. No matter how good the design method, perfect results are not possible because of variability in materials, testing, construction, the environment, traffic, etc. What is worse, almost all variability observed in the field after design is on the negative side, providing less performance than expected. The paper puts these efforts into perspective for conference attendees and readers and redefines good Pavement Management principles as the desired long term solution which can also accommodate new directions like sustainability, climate effects, related new materials, and other new factors as they arise. KEY WORDS: Pavement design, management, performance, design life, rehabilitation, maintenance 1. INTRODUCTION Since the first Roman roads were built over 2,300 years ago, design of pavement thickness and material selection has been of primary concern. In 1935, Mr. O. J. Porter of the California Highway Department codified the thickness design of pavements in the California Bearing Ratio (CBR) method [1]. During World War II, Mr. Porter joined the US Corp of Engineers as a Colonel and adapted his CBR method for the design of airfield pavements. Many people think the CBR method contributed as much as anything to winning the World War II since nearly all forward airfields were designed using this CBR method. Figure 1. The basics of the CBR method CBR Design Chart Pavement Thickness Subgrade Strength Increasing loads 20 cm 40 cm

Upload: buicong

Post on 21-Jun-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 1

PAVEMENT DESIGN OR PAVEMENT MANAGEMENT?

GOOD DESIGN IS NOT ENOUGH

Waheed Uddin

Director, Center for Advanced Infrastructure Technology (CAIT), the University of Mississippi, USA

Ralph Haas

Professor Emeritus, University of Waterloo, Waterloo, Ontario, Canada N2L 3G1

W. Ronald Hudson *

* DeWitt C. Green Professor Emeritus, University of Texas, Senior Consultant, AgileAssets, Inc.

3001 Bee Caves Road, Austin, Texas 78746, USA [email protected]

ABSTRACT: Design is only one of many factors in providing good, economical pavement performance, albeit

an important starting place. Engineers keep seeking the elusive, perfect mechanistic pavement design method as

the “Total Solution,” to providing good pavements as evidenced by the US $15 million spent on the Mechanistic

- Empirical Pavement Design Guide (MEPDG) and more money needed for calibration in the USA. No matter

how good the design method, perfect results are not possible because of variability in materials, testing,

construction, the environment, traffic, etc. What is worse, almost all variability observed in the field after design

is on the negative side, providing less performance than expected. The paper puts these efforts into perspective

for conference attendees and readers and redefines good Pavement Management principles as the desired long

term solution which can also accommodate new directions like sustainability, climate effects, related new

materials, and other new factors as they arise.

KEY WORDS: Pavement design, management, performance, design life, rehabilitation, maintenance

1. INTRODUCTION

Since the first Roman roads were built over 2,300 years ago, design of pavement thickness and material selection

has been of primary concern. In 1935, Mr. O. J. Porter of the California Highway Department codified the

thickness design of pavements in the California Bearing Ratio (CBR) method [1]. During World War II, Mr.

Porter joined the US Corp of Engineers as a Colonel and adapted his CBR method for the design of airfield

pavements. Many people think the CBR method contributed as much as anything to winning the World War II

since nearly all forward airfields were designed using this CBR method.

Figure 1. The basics of the CBR method

CBR Design Chart

Pa

vem

ent

Th

ick

nes

s

Subgrade Strength

Increasing

loads

20 cm

40 cm

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 2

Figure 1 shows the basics of the CBR method which used three main variables, traffic loads, subgrade strength,

and total pavement thickness. The CBR method became the world’s pavement design method for all flexible

pavements until the early 1960s. The Westergaard equations served as the major design method for the worlds

Portland cement concrete pavements for 50 years until about 1962 and continued to be recommended by the

Portland Cement Concrete Association and others after that [1].

From 1958 – 1961 the AASHO Road Test, a $30 million designed experiment was conducted and showed

conclusively that the strength of base and subbase layers was important to the performance of pavements [2,3].

Such strength was not included as part of the CBR method. As a result of the Road Test, the first AASHO

Pavement Design Method was produced. Dr. Hudson, a co-author of this paper [3], had the benefit and pleasure

to serve at that Road Test and also helped prepare the design guides themselves. These improved design methods

based on sound empirical evidence from the AASHO Road Test were used to design many heavy duty

pavements worldwide, especially the US Interstate Highway System. Even using these improved methods, these

heavy duty pavements began to fail after 8-10 years, much earlier than the design predicted, particularly on the

US Interstate Highway System but also worldwide.

Defining failure and performance requires using a simple pavement quality versus age performance curve. The

preferred method of defining quality in the US at that time was the Present Serviceability Index (PSI) using a

scale from 0 to 5, where 0 was total failure and 5 was considered a perfect pavement. Categories in-between

were very poor, poor, fair, good, and very good. It was also necessary to define a minimum required level of

serviceability (failure) which varied from 1.0 to 2.5 based on the class of highway considered. In this paper PSI

will be used to define quality on this scale of 0 to 5 and a generic minimum serviceability or quality level will

define failure (usually 1.0 to 2.5). Canada had a similar index which ranged from 0 to 10, called the riding

comfort index but which operated in the same way with each category spanned two digits, 0 to 2 very poor, 2 to

4 poor, etc. Since the 1990’s, the IRI (International Roughness Index) and the PCI (Pavement Condition Index)

have been used in the United States. In this paper we will use PSI as a measure of quality on all our graphs and

figures, 5.0 is the Best and 0.0 is the Worst, because it is easier to understand.

Figure 2 shows the expected performance for a well designed heavy duty pavement using a 20 year design

period. Figure 3 shows the actual observed performance of many heavy duty pavements in the United States

during the 1950’s and many pavements around the world today. Field observations show early deterioration (the

’s) and the extrapolated dashed line shows the expected life is less than “designed.”

0

5

20

|

_Predicted performance

(Design Life)

Failure Minimum PSI

Serviceability

PS

I

(Ser

vic

eab

ilit

y)

Years 0

5

20

|

_

Actual Observed

Feedback

Current Predicted Life|

14 Years

PS

I

(Serv

icea

bil

ity)

Failure

Design Life

Figure 2. The expected performance for

heavy duty pavement Figure 3. The actual observed performance of

heavy duty pavement

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 3

50

25

15

10

5

ES

AL

s to

Fa

ilu

re, m

illi

on

20 22.5 25 27.5 30 cm

Surface Thickness, cm

0

50

25

15

10

5

1993 AASHTO Guide Designs for Clay/Silt Subgrade,

50 cm Subbase, 20 cm Base, Moderate Climate

ESALs to

Failure

5

million

10

million

15

million

25

million

50

million

Surface

Thickness

20 cm 22.5 cm 25 cm 27.5 cm 30 cm

2. DEVELOPMENT OF PAVEMENT MANAGEMENT SYSTEMS

In 1963-65 major research was funded by the National Cooperative Highway Research Program in the United

States involving all state DOTs to solve this premature failure problem [4]. Similar research was carried out by

Dr. Haas and his associates in Canada [5,6,7,8]. Both these studies showed that pavement design alone was not

adequate to produce required pavement performance. Although good design is certainly the first step in

providing desired performance. Design also requires accurate predictions of traffic loads and volumes, subgrade

strength, base material and surface strength, and as-constructed pavement thickness, as well as surface

smoothness. Failure to predict any and all of these factors accurately will result in early deterioration and failure.

Looking at Figure 1, a design thickness of 20 cm is shown by the solid line, but because the actual traffic loads

were heavier that predicted, the actual thickness needed is shown dashed to be 40 cm. Similar examples could

be shown where the subgrade is weaker than predicted, etc. Therefore, when the thickness required is greater

than actually built, then the pavement will also fail early. In the case of the US interstate system, most early

failures were caused by errors in predicting traffic loads accurately or were due to inadequate thickness and

materials strength resulting from efforts to get the Interstate Highway System constructed as rapidly as possible.

Inability to predict heavy traffic loads was a problem worldwide during the 1960s where rapid expansion of the

world economy after World War II resulted in a greater demand for goods, but the use of railroads declined so

that more and more heavy loads used the world’s highways.

Table 1 illustrates the effect of axle loads on thickness required for a typical design case. A 25 cm thick surface

for weak subgrade will carry 15 million Equivalent Single Axle Loads (ESALs) but a 20 cm thick surface will

handle only 5 million ESALs to failure. What does this mean in terms of applied axle loads? The AASHO Road

Test [2,3] showed the relative effect of heavy axles (Figure 4). If the damage of a 8,165 kg (18,000 lb) axle is

taken as 1.0 then a 10,886 kg (24,000 lb) axle will cause three times as much damage (three times as many

ESALs) as the 8,165 kg axle. Thus as illustrated in Table 1, if the designer expected primarily 8,165 kg axles

then the thickness would need to be 20 cm surface. If the average trucks are actually loaded to 10,886 kg per

heavy axle then they will produce 15 million ESALs (three times as many) and require 25 cm surface. The 20

cm surface will likely fail in seven years instead of 20 years.

Table 1. Effect of ESALs on Surface Thickness Required

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 4

In some cases after WW II, inadequate construction due to poor quality control resulted in poor quality materials

and inadequate pavement thickness and rough surface construction which led to early failure. It only takes one

bad prediction error. This was true in both developed and developing countries. In North America and Europe

the primary causes of early failure were in most cases higher traffic volumes, heavier loads, and extreme weather

conditions, but poor construction quality in the pavement surface or low compaction and aggregate quality on

asphalt pavements also contributed. Bad construction methods on Portland cement concrete pavements,

particularly continuously reinforced concrete pavements, also produced early failure as did the use of reactive

aggregates which causes surface damage.

Figure 4. Relative effect of heavy axles

The authors have been called upon to inspect failed pavements in the US, Canada, Brazil, Argentina, as well as

in Africa. On most pavements we inspected, the in-place thicknesses were less than designed and paid for. The

asphalt concrete or Portland cement concrete was also of inferior quality in some cases with the asphalt content

or cement content being less than specified for construction. This was sometimes due to inadequate inspection

because of graft and pay-offs between the contractor and highway agency employees in some countries. In some

cases, vastly overloaded trucks were permitted to operate on the highway system and thus destroyed the

pavements prematurely. The AASHO Road Test [3] showed that a 13,608 kg (30,000 lb) axle does 10 times as

much damage to the pavement as a 8,165 kg (18,000 lb) axle. Yes, you read that correctly. Many engineers then

and now think the relationship between load and damage is linear. It is not. It is either logarithmic or a power

function as shown in Figure 4. In some cases this damage ratio is even made worse by the poor selection of

materials. In the 1970s Dr. Hudson was asked to inspect severe damage on cement treated bases in Brazil where

failure was due to heavy loads from greatly increased soybean production. There was strong pressure in those

days to use cement for road construction in Brazil because of the lack of available asphalt. These pavements

were a mixture of local soil and a very high cement content (near 10%) which caused them to crack due to

temperature change and fail in flexure under the heavy traffic loads thus causing major damage. The resulting

performance was much worse than predicted.

The NCHRP and Canadian studies cited above showed that planning, design, construction, maintenance, and

rehabilitation must all be considered in what has become known as Pavement Management and Pavement

Management Systems (PMS). PMS works for individual sections at the project level and also on a network of

several or many pavement sections. The project level pavement activities include design and are considered most

importantly in this paper.

Figure 5 depicts the project level management process which is the focus of this paper. The model of the

pavement structure shown upper left is only a small but important part of providing good pavements. It also

shows that the model outputs are deflection, stress and strain. These taken to a limit, produce distresses which

combine to define the performance. More detailed explanation can be obtained in Haas et al. [5] as can details of

network level pavement management which are beyond the scope of this paper. Figure 6 shows the PMS process

with more emphasis on field feedback data. The accumulated feedback for many pavements over several years

ΣD

am

age

10.0

1.0

Accumulated Axles

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 5

becomes the database which can be used to accurately revise the design and performance models and is a better

calibration method than the spot calibration being used for MEPDG. This is a better way to define true design.

Figure 5. Block diagram of project level pavement management system

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 6

Figure 6. Performance and cost models diagram

3. A REALISTIC LOOK AT DESIGN

3.1 Single Designs Pavement design engineers tend to think of the design of a pavement section as being uniform for the total

section length of perhaps four to ten kilometers or more. But there is variability along the length of any section

of road. Nevertheless, the designer often makes a single selection of materials and thicknesses which he/she calls

“the design.” Even if such a design is perfect we must then move to construction.

3.2 The Construction Process Construction quality must recognize the variability of materials and the statistics of quality control and quality

assurance (QC/QA) by using a normal distribution curve as shown in Figure 7. As an example, if the mean

thickness of the asphalt surface is 30 centimeters as shown in this normal distribution diagram [5], we know that

50% of the pavement constructed will be thinner than 30 cm the mean. We must set the design at a lower value,

at least one or two standard deviations (as a measure of error); thus the effective thickness in this case would be

about 25 centimeters. Even then 16% (using 1σ) or 6% (using 2σ) of the actual constructed pavement would be

thinner than 25 cm. If a 30 cm pavement is truly required, then the contractor would need to adjust and construct

at least a 35 cm mean thickness to produce the required 30 cm thickness 84-94% of the time.

INPUTS

•Traffic

•Materials

•Thickness

Models

Design Behavior Distress Performance

Costs

Safety

Traffic

Counts &

Weights

DeflectionCondition

Surveys

Roughness

PSI

Update

Models•Test Pits

•Lab Tests

•Count

•Weigh

•Classification

•Rainfall

•Temperature

RECORD

• Construction

• MaintenanceLONG-TERM

DATABASE

&

ANALYSIS

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 7

Figure 7. Normal distribution of thickness construction

Figure 8. Distorted distribution with contractor working for a maximum of 32 cm

In reality the contractor has no desire to build 84% of the pavement that he is to be paid for thicker than required.

He will therefore work against a construction maximum as shown in Figure 8. In this case, if he is seeking a 30

cm thickness, he would likely work against a 32 cm maximum. Therefore the resulting distribution is skewed

and as much as 75% of the thickness could be less than the desired 30 cm design. In this case, as shown in

Figure 8, an expected (realistic design) thickness of 25 centimeters would result; but even then 15-25% of the

pavement could be less than the effective 25 cm thick. If in fact a 30 cm pavement were required then the

contractor would need to work against a 37 cm control thickness for construction. Even when construction

inspection reveals these thin areas, in many cases the contractor will pay a penalty for the reduced thickness but

the resulting thicknesses will remain substandard and thus produce shorter pavement life which must be dealt

with in future years.

There are many ways that this substandard thickness pavement can be distributed along the length of the specific

pavement section but Figure 9 shows an example possible distribution where about 25% of the pavement

(hatched) is thinner than required and can fail earlier than predicted. How does “design” deal with this situation?

The answer is, design cannot handle this situation. It must be dealt with by preventive maintenance and/or

corrective maintenance. Up to 25% of the example pavement can fail earlier than predicted by design and must

receive corrective maintenance or preventive maintenance early in the life. A similar early failure problem exists

σ σ

30 352520

84%

Thicker

Thickness, cm

Up to 16%

Thinner

3025 32

25%

Too Thin

75%

Thicker Meets

Specifications

Thickness, cm

Contractor’s

Target

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 8

for inadequate asphalt content, asphalt strength, concrete strength and other variables. The results are also

cumulative so there could be as much as 25 to 50% of the pavement constructed below the desired (designed)

value. It is unlikely that QA/QC practice can prevent this entire problem. The pavement management process

now moves from design and construction to the preventive maintenance or maintenance phase. Let us be clear,

you cannot deal with this problem with any “design” no matter how perfect the design may be.

Figure 9. Random distribution of poor pavement construction

The majority of the example project or section is well constructed and should perform nearly as designed if no

other unexpected variation occurs during the performance period as shown by the solid curve in Figure 2 and

Figure 10. The remaining 25%, shown crosshatched (in Figure 9), is weaker than designed and will deteriorate

earlier, shown by the dashed curve in Figure 3 and Figure 10. We may deal with this in two ways, (1) apply early

preventive maintenance to extend life as shown by the dashed curves in Figure 10 or, (2) as often happens for

lack of funds, wait longer until the pavements gets into fair or poor condition and then apply heavy maintenance

to extend the pavement life as shown in the dotted lines in Figure 10.

3.3 Effects of Traffic Loads and Environment during the Pavement’s Life

Even in the case of the well-constructed parts of the original 10 kilometer pavement section, extra traffic, worse

weather than expected, etc. can all produce more damage than predicted in the design. This problem is handled

in bridges by using a safety factor of 2.0 but this is not possible in pavements since the resulting pavement

thicknesses would be cost prohibitive. Thus pavement management becomes more important the longer the

pavements remain in service and when the accumulated damage becomes bad enough, even in the face of

applied maintenance, rehabilitation is required to renew the pavement surface and improve quality.

Adequate thickness (75% of total length)

Too Thin (25% of Total Length)

Too ThinOK

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 9

Figure 10. Early pavement failure with maintenance options

3.4 Rehabilitation

Continued deterioration of pavement quality for the original pavement section will show up in proper feedback

data on pavement condition, strength, traffic, etc. In such cases major rehabilitation or overlay will be required

as shown in Figure 11. The overlay can be applied with variable thickness as needed to bring the whole 10

kilometer section back to the required performance or design life. A new predicted design or performance life

can even be set for the overlaid pavement as shown, another benefit of pavement management not available in

design alone. In fact many pavements remain in service far beyond the 20 year design life usually prescribed.

Most of the world’s interstate and trunk road systems have remained in service since 1955-1965, thus total

service life is reaching 50 to 55 years not just 20 years. This pavement reality cannot be dealt with by design but

can be handled by Pavement Management.

Figure 11. Early failure with rehabilitation to extend pavement life

0

5

20

|

_

30

|

Preventive Maintenance

|

1510

|

Design

PS

I (S

ervic

eab

ilit

y)

Heavy Maintenance

or Rehabilitation

Actual

Failure

Minimum PSI

Years

0

5

20

|

_

30

|

Years

Minimum PSI

FailurePS

I (S

erv

icea

bil

ity

)

Rehabilitation

DesignActual

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 10

4. WHY SO MUCH FOCUS ON DESIGN?

In spite of the fact that pavement management was first developed in the early 70’s and that many countries and

all the states in the United States and provinces in Canada now require use of pavement management, many

pavement engineers still seek the "holy grail" of the “perfect design method.” The US alone has spent $20-30

million in the last 10 years to develop the Mechanistic-Empirical Pavement Design Guide, known as MEPDG,

and for its region-specific calibration efforts. To further illustrate the problem, the method started out to be the

Mechanistic Pavement Design Guide, but two years into the project, the project staff admitted the reality that no

mechanistic equations can predict pavement performance. They only predict stress, strain, and deflection

(Figures 5 and 6). Therefore, calibration and empirical adjustment is required. So the most complex design

methods are not purely mechanistic, even the Westergard equations used for Portland Cement Concrete (PCC)

for over 50 years, required practical empirical adjustments for the real world.

This illusive MEPDG mechanistic method for asphalt pavement design now includes over 300 input variables.

On its face this seems so absurd that it is hard to understand why anyone would try to develop a method with so

many variables since in the real world it has been difficult to get agencies to obtain good data for more than five

to ten variables much less 300. Furthermore the amount of time, and thus money, required to obtain this large

number of variables with any degree of accuracy is prohibitive. Calibration efforts by each state are being carried

out for only some variables [9]. This will lead users of the method to use many default values for design which

means that the detailed MEPDG method is not really being used anyway.

5. DESIGN METHODS DO NOT PREDICT PERFORMANCE

Another problem with mechanistic design methods is that they do not predict pavement smoothness or

performance. They predict stress, strain, or deformation (Figure 5). Everything else is empirical modification of

the theory. Only by obtaining regular (hopefully annually) feedback measurements of roughness, cracking, and

other distress can we know how to provide the performance required for pavements. Pavement management

automatically provides a historical way to predict, monitor, and maintain required pavement performance and

life-cycle for minimum costs through feedback.

6. TIME AND COST OF DETAILED DESIGN PROHIBITIVE

Even if the 300 MEPDG variables could be measured, the cost of obtaining and using those values on each

individual pavement section would be prohibitive. Even worse all of that time and money goes to waste because

the previously discussed actual values of construction, traffic, climate, etc. will change and as-built thicknesses

and strength almost always vary from the design value. Your authors remain amazed at this pursuit of the

“perfect design, holy grail” when reality and research have shown time and again that pavements must be

managed in the face of real world conditions and required performance in the field. Pavement management is a

more realistic answer.

7. EFFECT OF ENGINEERING EDUCATION

Perhaps one of the most important contributors to this Design mentality is the design culture in university civil

engineering curricula. The average civil engineering curricula worldwide contains 15-20 course units in design;

steel design, concrete design, bridge design, waterworks design, sewage treatment design, etc. Usually there are

no courses at all on maintenance and rehabilitation. In some universities, there is a three unit course in asset

management but this cannot offset the weight of 15 - 20 units of “design courses” in the mind of the average

student. This level of design education encourages the quest for better mechanistic design of pavements who

some people already consider the poor cousin in civil engineering. Bridge design and structural design are held

up as icons for engineers. A parallel contributing factor is that work on analytical and mathematical

improvements in design fits better into master’s theses or a PhD dissertation than does the messy use of field

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 11

data and the empirical problems of pavement maintenance, rehabilitation, and management. The three authors of

this paper have a total of 105 years in teaching at the university level. We are to some degree contributors to this

design mentality. However, all of us since the mid-1970s have strongly developed and supported pavement

management and asset management systems as a necessary supplement to design [10].

8. WE USUALLY HAVE MORE THAN ONE PAVEMENT SECTION TO MANAGE

What if you have a network of 10 pavement sections that need to be dealt with? Assume you design them but

you don’t’ have enough money to do all 10 at the desired design level. Do you then build the six most important

or spread the money over the network of all ten sections? Design cannot tell you but you can deal with this

problem with network level pavement management. In this case our example network was only 10 sections but

pavement management can also handle 100, 1000, 100,000 and more sections. You can learn more about

network PMS in Haas and Hudson [5].

In addition, pavement management systems can and do integrate with maintenance management systems [11]

including the preservation and rehabilitation cycles. This provides the beginning of an asset management system

as outlined in References [11,12,13,14]. Proper pavement management provides a lasting useable framework.

Furthermore, project-level pavement management and maintenance management integrate into network-level

pavement management to allocate funds among many pavement sections for the whole agency network to

maintain and maximize overall service; not for a few highly designed roads while the rest suffer deterioration.

9. RECOMMENDATIONS

We have shown that design alone cannot guarantee good pavements. What should the process actually look like?

We suggest the steps listed in Table 2 as part of pavement management. No design method, no matter how

complicated or well documented can accomplish these tasks. Only by managing pavements can you achieve the

goals of providing good serviceability at reasonable or minimum costs and of reducing user costs on these

pavements.

Table 2. Actual Steps Involved in Providing Good Pavement Performance

1 Design the pavement with reasonable input estimates and reasonable design methods.

2 Build the pavement with good construction methods and reasonable quality control.

3 Measure the feedback from the pavement including performance properties, roughness,

serviceability, distress at least annually.

4 Provide preventive maintenance when the pavement begins to deteriorate below the desired

performance curve.

5 Provide maintenance or major maintenance when needed to extend serviceability.

6 Rehabilitate the pavement when it becomes clear that the performance levels are dropping too

rapidly for maintenance to be economical.

7 Adjust the performance curves and prediction to the required level as needed.

8 Continue this cycle for as long as the highway needs to remain in service, usually 50 years or

more.

9 Work toward a complete asset management by adding a Maintenance Management System.

10. SUMMARY

This is a Pavement Asset Management Conference. If at all possible when you return to your agency, look at the

pavement related activities in your agency. Use the information herein to gain support among your design

2013 IJPC Paper 160-2

© Copyright 2013 IJPC − International Journal of Pavements Conference, São Paulo, Brazil Page 12

cohorts to put design into proper perspective as part of project level Pavement Management. Again, we are not

suggesting sloppy or inferior design. Rather produce a good but economical design and immediately follow-up

with the principles of pavement management discussed in Recommendations.

REFERENCES:

[1] Yoder, E.J. and M.W. Witczak. Principles of Pavement Design. 2nd

Ed., Wiley, New York, 1975.

[2] Carey, W.N. and P.E. Irick. The Pavement Serviceability-Performance Concept. HRB Bulletin 250,

Highway Research Board, 1960.

[3] Highway Research Board. The AASHO Road Test: Report 5-Pavement Research. HRB Special Report

61-E, Highway Research Board, 1962.

[4] Hudson, W.R., F.N. Finn, B.F. McCullough, K. Nair, and B.A. Vallerga. Systems Approach to Pavement

Design, Systems Formulation, Performance Definition and Materials Characterization. Final Report,

NCHRP Project 1-10, Materials Research and Development Inc., March 1968.

[5] Haas, Ralph and W.R. Hudson. Pavement Management Systems. McGraw-Hill, New York, 1978.

[6] Wilkins, E.B. Outline of a Proposed Management System for the CGRA Pavement Design and

Evaluation Committee. Proceedings, Canadian Good Roads Association, 1968.

[7] Hutchinson, B.G. and R.C.G. Haas. A Systems Analysis of the Highway Pavement Design Process.

Highway Research Record No. 239, Highway Research Board, 1968.

[8] Haas, R.C.G. and B.G. Hutchinson. A Management System for Highway Pavements. Proceedings,

Australian Road Research Board, 1970.

[9] Souliman, Mena I., Michael Mamlouk, Mohamed El-Basyouny, and Claudia E. Zapata. Calibration of the

AASHTO MEPDG for Designing Flexible Pavements in Arizona Conditions. IJP - International Journal

of Pavements, Vol. 9, No. 1-2-3, 2010, pp. 2-13.

[10] Uddin, W., W.R. Hudson, and Ralph Haas. Public Infrastructure Asset Management. McGraw Hill, New

York, 2013.

[11] Hudson, W.R., S.W. Hudson, Eric Perrone, and Charles Pilson. Improving PMS by Simultaneous

Integration of MMS. Proceedings, 8th International Conference on Managing Pavement Assets, Santiago,

Chile, November 15 – 19, 2011.

[12] Hudson, W.R., R. Haas, “Progress Assessment of PMS,” Keynote Presentation and Paper, 8th

International Conference on Managing Pavement Assets, Santiago, Chile, November 15 – 19, 2011.

[13] Haas, Ralph, W.R. Hudson, and L. Cowe-Falls. Evolution of and Future Challenges for Pavement

Management. Proceedings, 8th International Conference on Managing Pavement Assets, Santiago, Chile,

November 15 – 19, 2011.

[14] Rada, G.R. and W.R. Hudson. Balancing Accurate Pavement Management Data Collection and Software

Requirements. Proceedings, 8th International Conference on Managing Pavement Assets, Santiago, Chile,

November 15 – 19, 2011.