Good Construction Practices – Part I This report is solely for the internal use. No part of it may be circulated, quoted, or reproduced for distribution outside the company organization without prior written approval from ACC Limited. This material was used during an oral presentation; it is not a complete record of the discussion.

Upload: vanquynh

Post on 06-Feb-2018

219 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Good Construction Practices – Part I

This report is solely for the internal use. No part of it may be circulated, quoted, or reproduced for distribution outside the company organization without prior written

approval from ACC Limited. This material was used during an oral presentation; it is not a complete record of the discussion.

Page 2: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

� Cost Estimation and budgeting� Layout planning, drawing preparation & approval� Excavation, foundation, plinth beam or brickwall up to plinth, DPC, compound wall

� Brick wall up to roof, lintels & Chajjas and openings for doors/ windows, septic tankShuttering for slab, reinforcement fixing, concreting

Construction Sequence of a House

2

ACC Limited 26.06.2010Good construction practices

� Shuttering for slab, reinforcement fixing, concreting� Electrical conduit, Plastering work, floor concreting & roof water proofing, water supply & sanitary pipe fixing

� Floor tiles, painting, electrical wiring, fittings in bath/kitchen, door & window shutters, electrical fittings

� Plinth protection, final painting, check list, billing

Page 3: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Estimation of Material Requirements

� For M-20 grades of concrete of 1 cu. m.

� Cement 6.5-7.5 bags, Sand- 0.4m3 , CA- 0.83m3 , water 21-22 litre

� For 100sq.m (1076 sq. ft.) Slab of 4” thk-

� Cement 79 bags, Sand- 4.2m3 , CA- 8.3m3 ,

3

ACC Limited 26.06.2010Good construction practices

� For plaster of 100 sq. m.

Cement Sand

� 1:4 ( 12mm thk) 12 bags 1.6m3

� 1:4 ( 20mm thk) 20 bags 2.6m3

� 1:6 ( 12mm thk) 9 bags 1.8m3

� 1:6 ( 20mm thk) 12 bags 3.0m3

� For brick works of 1 cu. M.- 500 bricks are required.

Page 4: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

� Formwork should be watertight so that there is no loss of cement paste through it.

� Properly leveled centering will minimize the cost of finishing� Supports should be provided to slab and beam at sufficient

distance.� Apply a mixture of Greece and diesel before using.

Centering (FORMWORK)

4

ACC Limited 26.06.2010Good construction practices

Page 5: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Formwork

5

ACC Limited 26.06.2010Good construction practices

Page 6: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Why cover blocks?

6

ACC Limited 26.06.2010Good construction practices

Page 7: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Do not use of Aggregates as Cover Blocks

7

ACC Limited 26.06.2010Good construction practices

Page 8: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

8

ACC Limited 26.06.2010Good construction practices

Page 9: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Cover Blocks for Durability

9

ACC Limited 26.06.2010Good construction practices

Page 10: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Cover Blocks

� Use Proper Cover Blocks

� As per IS, cover should be

� 40mm for columns� 25 mm for columns of minimumdimension of 200 mm or under

� 50 mm for Footing

10

ACC Limited 26.06.2010Good construction practices

� 50 mm for Footing� 30mm for moderate exposure� 20mm for mild exposure ( 15mmif bars of 12mm dia are used)

Page 11: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Control Slump

11

ACC Limited 26.06.2010Good construction practices

Page 12: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

� Avoid Manual concrete mixing.

� Keep a close watch on water quantity while mixing

� Minimum mixing time should be 2 mins.

� Use Admixtures only if required.

� Admixture dosage should be optimum. Do not add more/less quantity.

Concrete Mixing

12

ACC Limited 26.06.2010Good construction practices

� Admixture should be first added in water and then can be mixed with other ingredients.

� Mortal Plasticizer should be used only for Mortar and concrete plasticizer for concrete.

� Use good quality Water proofing chemical which should be chloride free.

� For RCC minimum grade of concrete should be M 20

Page 13: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Add Water

by

Measurement

Water

13

ACC Limited 26.06.2010Good construction practices

at

Construction

Site

Page 14: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

14

ACC Limited 26.06.2010Good construction practices

Page 15: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Avoid

Segregation

&

Segregation & Bleeding

15

ACC Limited 26.06.2010Good construction practices

bleeding

of

concrete

Page 16: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Segregation

16

ACC Limited 26.06.2010Good construction practices

Page 17: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

17

ACC Limited 26.06.2010Good construction practices

Page 18: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

� Concrete should be poured from more than 1 m height to avoid segregation.

� Walking rails should be provided on slabs before concrete placement so that R/F will not get disturbed/damaged.

Placing of Concrete

18

ACC Limited 26.06.2010Good construction practices

height to avoid segregation.

Page 19: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

� Compaction means removing air from concrete

� It will reduce the voids

� Lesser the voids, stronger the concrete.

Compaction

19

ACC Limited 26.06.2010Good construction practices

the concrete.

� Proper compaction will ensure Water tightness

� For manual compaction of slab use Wooden float and 16 mm bar

Page 20: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

Compaction

20

ACC Limited 26.06.2010Good construction practices

Page 21: Good Construction Practices –Part I - ACC Helpacchelp.in/pdf/best-practices/Good-Construction-practices-1.pdf · Good Construction Practices –Part I This report is solely for

21

ACC Limited 26.06.2010Good construction practices