Gold Ray Dam Interagency Technical Team Meeting. Agenda. NEPA Update Deconstruction Plans Hydraulic Modeling Next Steps. NEPA Update. EA Issues from Scoping Mtg. Upstream habitat (wetlands, fish, frogs, riparian areas) Well levels Downstream domestic water intakes Sediment quality - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/1.jpg)
Gold Ray Dam Interagency Technical Team Meeting
![Page 2: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/2.jpg)
NEPA UpdateDeconstruction PlansHydraulic ModelingNext Steps
Agenda
![Page 3: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/3.jpg)
Upstream habitat (wetlands, fish, frogs, riparian areas)
Well levels Downstream domestic water intakes Sediment quality Recreation Economic impacts (fishing and river guides) Alternatives – dam rehab and power
generation
NEPA Update
EA Issues from Scoping Mtg
![Page 4: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/4.jpg)
Section 1 – Introduction Section 2 – Purpose and Need and Alternatives
Purpose and need – complete No action Alternative 1 – Dam Removal
• Deconstruction plan• Restoration plan
Alternative 2 – Dam Rehabilitation• Dam, forebay walls, etc. (structural)• Fish Ladder• Fish Screening• Power generation – optional?
NEPA Update
EA Progress
![Page 5: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/5.jpg)
Section 3 – Affected Environment and Environmental Consequences
Section 4 - Preparers and Agencies Consulted Section 5 – Abbreviations/Acronyms Section 6 – References
NEPA Update
EA Progress
![Page 6: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/6.jpg)
Dam complex SHPO coordinationDetermination of eligibility (DOE) nearly complete Likely eligible for National RegisterRemoval likely “adverse effect” but mitigated
Archaeology SHPO coordination doneDOE underway – no shovel testing required
NEPA Update
Cultural Resources
![Page 7: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/7.jpg)
“Level 1” – based on records and site visit; no testing
Look for indicators for contamination Recommend testing locations in power
house and former transformer sites
NEPA Update
Environmental Site Assessment
![Page 8: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/8.jpg)
Biological Assessment Content largely completed Confirm the action area Incorporate demo/restoration plan
information
Project Approach
![Page 9: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/9.jpg)
Wetlands Report Submitting 2 wetland reports: Delineation
Report and Indirect Wetland Impact Report
Reports are drafted; waiting for 2 year event modeling to finalize maps
Project Approach
![Page 10: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/10.jpg)
Schedule Review draft EA and permit applications in
middle of January Draft EA – 30 day review and revision Goals:
Submit BA and permit applications in early February
EA out for public review in mid to late February
Project Approach
![Page 11: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/11.jpg)
Deconstruction Plan Multi-step plan with controlled
drawdown of reservoir Minimizes risk for County Ensures dam removal and fish
passage when complete
Project Approach
![Page 12: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/12.jpg)
1934 Log Crib Dam (PacifiCorp)
![Page 13: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/13.jpg)
1940 Log CribDam (PacifiCorp)
![Page 14: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/14.jpg)
1941 Gold Ray Dam Construction (PacifiCorp)
![Page 15: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/15.jpg)
1941 Gold Ray Dam Construction (PacifiCorp)
![Page 16: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/16.jpg)
November 14, 1941 (PacifiCorp)
![Page 17: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/17.jpg)
Project Approach
![Page 18: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/18.jpg)
Project Approach
![Page 19: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/19.jpg)
Fish Passage Plan
![Page 20: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/20.jpg)
Fish Passage Plan
![Page 21: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/21.jpg)
![Page 22: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/22.jpg)
Project Approach
![Page 23: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/23.jpg)
Project Approach
DATE
5/24
/10
5/31
/10
6/7/
106/
14/1
06/
21/1
06/
28/1
07/
5/10
7/12
/10
7/19
/10
7/26
/10
8/2/
108/
9/10
8/16
/10
8/23
/10
8/30
/10
9/6/
109/
13/1
09/
20/1
09/
27/1
010
/4/1
010
/11/
10
CONSTRUCTION (June 15 - August 31 in-water)Access site on south side / mobilize equipment
Construct south side cofferdamRemove southern portion of concrete dam
Divert river to south channel opened by dam removal (fish passage delay)Construct north side cofferdam
Remove northern portion of concrete damRestore river to permanent channel
Construct restoration portions of project (Kelly Slough/Tolo Slough/Bear Creek)Remove existing powerhouse and fish ladders
Deconstruction Schedule
![Page 24: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/24.jpg)
Restoration PlanProject Approach
![Page 25: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/25.jpg)
Hydraulic Modeling
![Page 26: Gold Ray Dam Interagency Technical Team Meeting](https://reader035.vdocuments.site/reader035/viewer/2022062422/5681371a550346895d9ea778/html5/thumbnails/26.jpg)
Next Steps Finalize deconstruction plan Run hydraulic modeling DRAFT NEPA Continue with public outreach