gmrr bridge #114 emergency irene repair

26
GMRR Bridge #114 Tropical Storm Irene Emergency Repairs Chester, Vermont ECI Rail Constructors, Inc. September 2011 www.eci-rail.com

Upload: eci-vt

Post on 12-Jul-2015

195 views

Category:

Education


0 download

TRANSCRIPT

Page 1: GMRR Bridge #114 Emergency Irene Repair

GMRR Bridge #114 Tropical Storm Irene Emergency Repairs

Chester, Vermont

ECI Rail Constructors, Inc. September 2011

www.eci-rail.com

Page 2: GMRR Bridge #114 Emergency Irene Repair

Tropical Storm Irene

Page 3: GMRR Bridge #114 Emergency Irene Repair

NWS Bulletin for Irene 5:00 PM on August 28, 2011

• RAINFALL...IRENE IS EXPECTED TO PRODUCE TOTAL RAINFALL ACCUMULATIONS OF 4 TO 6 INCHES...WITH ISOLATED MAXIMUM AMOUNTS OF 8 INCHES... FROM NORTHEASTERN NEW YORK STATE NORTHEASTWARD THROUGH THE NORTHERN PORTION OF NEW ENGLAND. THESE RAINS...COMBINED WITH HEAVY RAINS OVER THE PAST FEW WEEKS...COULD CAUSE WIDESPREAD FLOODING AND LIFE-THREATENING FLASH FLOODS.

Page 4: GMRR Bridge #114 Emergency Irene Repair

Initial ECI Site Visit Tuesday – August 31

Page 5: GMRR Bridge #114 Emergency Irene Repair

Mobilization & Access Construction Wed-Sat: Sept 1 to Sept 3

Page 6: GMRR Bridge #114 Emergency Irene Repair

Mobilize Cranemasters Saturday – September 3

Page 7: GMRR Bridge #114 Emergency Irene Repair

Setup Cranes Saturday – September 3

Page 8: GMRR Bridge #114 Emergency Irene Repair

Bridge Brought to Vertical & Secured Sunday – September 4

Page 9: GMRR Bridge #114 Emergency Irene Repair

Stabilize West Abutment Monday - September 5

Page 10: GMRR Bridge #114 Emergency Irene Repair

Install Pedestal at NW Bearing Tuesday – September 6

Page 11: GMRR Bridge #114 Emergency Irene Repair

Secure Work from Tropical Storm Lee Wednesday – September 7

Page 12: GMRR Bridge #114 Emergency Irene Repair

Test Borings at East Abutment Thursday – September 8

Page 13: GMRR Bridge #114 Emergency Irene Repair

Start Driving Pipe Piles Thursday – September 8

Page 14: GMRR Bridge #114 Emergency Irene Repair

Testing & Driving Pipe Piles Friday – September 9

Page 15: GMRR Bridge #114 Emergency Irene Repair

13.75-in-OD x 0.707-inch wall Pipe Pile Splicing – 2 hrs/joint

Page 16: GMRR Bridge #114 Emergency Irene Repair

Final Driving of Pipe Piles Saturday – September 10

Page 17: GMRR Bridge #114 Emergency Irene Repair

Shotcreting of West Abutment Sunday – September 10

Page 18: GMRR Bridge #114 Emergency Irene Repair

Sheet Pile Wall to Extend Damaged West Abut Sunday - September 10

Page 19: GMRR Bridge #114 Emergency Irene Repair

Temporary Bearing Pedestal Sunday - September 11

Page 20: GMRR Bridge #114 Emergency Irene Repair

Setting Bridge on Temporary Bearing Supports Sunday - September 11

Page 21: GMRR Bridge #114 Emergency Irene Repair

Pouring Concrete Backwall & Abut Extension Monday – September 11

Page 22: GMRR Bridge #114 Emergency Irene Repair

Final Welding & Bracing of Piles & Pedestal Tuesday – September 13

Page 23: GMRR Bridge #114 Emergency Irene Repair

Rebuilding Approach Embankment Tuesday – September 13

Page 24: GMRR Bridge #114 Emergency Irene Repair

West Approach Track Reconstruction Tuesday – September 13

Page 25: GMRR Bridge #114 Emergency Irene Repair

Team Photo Tuesday – September 13

Page 26: GMRR Bridge #114 Emergency Irene Repair

First Train Wednesday – September 14