GMedTech Design Project Presentation
Patrick LivingstoneEthan O’KaneMichael ConwayPadraig O’RaghallaighShay McGonigle
TREYresearch
MEET THE TEAM
PATRICK LIVINGSTONE
Project Manager
ETHAN O’KANE
MICHAEL CONWAY
PADRAIG O’RAGHALLAIGH
2
Mechanical Engineer
SHAY MCGONIGLE
Revit Technician Electrical & Plumbing Engineer
Energy Analyst
TREYresearch
The Design of a concept idea for a new GMedTech Building located on
the GMIT Dublin Rd. Campus:
• Project Plan
• Building Overview / Layout
• Revit
• Results
• Energy Analysis
• Conclusions
• Q&A’s
Introduction
3
TREYresearch
Project Plan
• Aims & Objectives
• Project Details
• MS Project
• Deliverables & Deadlines
• Roles & Responsibilities
4
TREYresearch
Project Plan
Aims & Objectives
• Create Project Plan
• Research
• Design Layout for building
• Report
• Project Poster
• Presentation
Project Details
• Location?
• Design
• Software used
• What must we do to reach our goals?
5
TREYresearch
Project Plan
MS Project
• Tracking
• Ability to distinguish Tasks.
• Financial management
• Gannt Chart
Weekly Meetings
• Meeting every Wednesday
• Weekly Progress
• Upcoming tasks to be completed
7
TREYresearch
Project Plan
Deliverables & Deadlines
• A new concept idea for a GMedTech Building
• A Revit model that illustrates the buildings services
• 22nd of May 2020 Project Hand Up
Roles & Responsibilities
• Project Manager
• Revit Technician
• Mechanical Engineer
• Electrical & Plumbing Engineer
• Energy Analyst
9
TREYresearch
• X4 Offices
• X1 Open plan Office
• X1 Clean room
• Male & Female Toilets
• Reception
10
Building Layout
TREYresearch
Why Choose Revit & What it can do
• Easy to use and a very accessible interface
• Provides 3-D modelling
• Well established BIM Software
• Calculate Areas, Airflows, frictional losses
• Advantages
• Disadvantages
16
TREYresearch
Results:
21
OccupancyFloor Area
[m2]
∆T ∆THeating
[W/m2]
Cooling
[W/m2]
Heating
[kW]
Cooling
[kW]
Ground Floor - [Totals] 100 790.93 Winter Summer Winter Summer 1140.00 1900.00 8.857 14.761
Reception 6 47.61 19 21 27 6.3 60 100 2.857 4.761
Male toilets 4 16.32 19 21 27 6.3 60 100 0.979 1.632
Female Toilets 4 16.32 19 21 27 6.3 60 100 0.979 1.632
Storage Room 1 11.48 15 15 23 12.3 60 100 0.689 1.148
Bathroom Hallway 2 13.80 19 21 27 6.3 60 100 0.828 1.380
Main Hallway 3 42.08 19 21 27 6.3 60 100 2.525 4.208
First Floor - [Totals] 46 360.43 480.00 800.00 21.626 36.043
Open Plan Office, hallway 20 191.71 21 22 29 5.3 60 100 11.502 19.171
Kitchen/Canteen (same as dwelling) 8 26.08 17 21 25 6.3 60 100 1.565 2.608
Managers Office 4 35.19 21 22 29 5.3 60 100 2.111 3.519
Office 1 1 14.96 21 22 29 5.3 60 100 0.898 1.496
Office 2 1 14.96 21 22 29 5.3 60 100 0.898 1.496
Office 3 1 14.96 21 22 29 5.3 60 100 0.898 1.496
Office 4 1 14.96 21 22 29 5.3 60 100 0.898 1.496
Meeting Room 1 10 47.61 21 22 29 5.3 60 100 2.857 4.761
Rest of Building - [Totals] 47 375.22 1158.38 869.51 30.482 50.804
Designed
Room Temp
Building Heating & Cooling Loads
OccupancyFloor Area
[m2]∆T ∆T
Heating
[W/m2]
Cooling
[W/m2]
Heating
[kW]
Cooling
[kW]
Gowning Room 8 26.92 23 23 31 4.3 813.71 36.01 21.91 3.04
Corridor 2 15.08 19 21 27 6.3 678.38 52.76 10.23 2.39
Airlock 1 3.57 19 19 27 8.3 678.38 69.51 2.42 0.74
Clean Room storage 1 14.79 19 19 27 8.3 678.38 69.51 10.03 3.08
Clean Room Material pass 2 9.86 19 19 27 8.3 678.38 69.51 6.69 2.06
Clean Room 20 138.34 19 19 27 8.3 678.38 69.51 93.85 28.85
Clean Areas - [Totals] 117 896.46 1440.00 2400.00 145.126 40.160
Designed
Room Temp
Clean Areas Heating & Cooling Loads
• ሶ𝑄 = ሶ𝑚𝐶𝑝∆𝑇
• 5 year extreme dry bulb temperatures.
• Considerable heating load for cleanroom areas.
• 2 AHU’s
TREYresearch
22
0.000 20.000 40.000 60.000 80.000 100.000 120.000 140.000 160.000 180.000 200.000
Ground Floor - [Totals]
Reception
Male toilets
Female Toilets
Storage Room
Bathroom Hallway
Main Hallway
Gowning Room
Corridor
Airlock
Clean Room storage
Clean Room Material pass
Clean Room
First Floor - [Totals]
Open Plan Office, hallway
Kitchen/Canteen (same as dwelling)
Managers Office
Office 1
Office 2
Office 3
Office 4
Meeting Room 1
Total
Heating & Cooling Loads
Cooling[kW]
Heating[kW]
TREYresearch
Cleanroom Supply and Extract
25
• Halton Vita VHH, HEPA diffuser.
• Used in hospitals and clean rooms.
• Flush to the ceiling.
• Ability to produce radial, swirl and low turbulence flow patterns.
• Antibacterial epoxy -polyester powder paint finish
TREYresearch
Lighting Ground Floor
28
Lighting Load legend with Lighting layout plan of the Ground Floor
TREYresearch
Lighting First Floor
29
Lighting Load legend with Lighting layout plan of the 1st Floor
TREYresearch
Lighting Fixtures
30
Cooper FailsafeClean Room
Cooper Corelitei2 Led
Cooper Troffer Metalux
TREYresearch
Conclusion:
• Successfully completed project
• MEP (Mechanical, Electrical & Plumping) services.
• High Standard of work.
• We would like to thank our project Sponsor and lecturer Willie Geraghty we greatly appreciated your involvement with our project.
33
TREYresearch
34
Thank You Any Questions?
Patrick Livingstone – [email protected]
Ethan O’Kane – [email protected]
Michael Conway – [email protected]
Padraig O’Raghallaigh – [email protected]
Shay McGonigle – [email protected]