gloucester township board of e - nj clean energy...nov-11 50,082 $7,065 dec-11 68,140 $9,271 totals...
TRANSCRIPT
GLOUCESTER TOWNSHIP BOARD OF EDUCATION
LORING FLEMMING ELEMENTARY SCHOOL
135 LITTLE GLOUCESTER ROAD
BLACKWOOD, NJ 08012
FACILITY ENERGY REPORT
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 1 of 31
TABLE OF CONTENTS
I. HISTORIC ENERGY CONSUMPTION/COST ................................................................. 2
II. FACILITY DESCRIPTION ................................................................................................ 8
III. MAJOR EQUIPMENT LIST ............................................................................................ 10
IV. ENERGY CONSERVATION MEASURES ..................................................................... 11
V. ADDITIONAL RECOMMENDATIONS ......................................................................... 31
Appendix A – ECM Cost & Savings Breakdown
Appendix B – New Jersey Smart Start® Program Incentives
Appendix C – Portfolio Manager “Statement of Energy Performance”
Appendix D – Major Equipment List
Appendix E – Investment Grade Lighting Audit
Appendix F – Renewable / Distributed Energy Measures Calculations
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 2 of 31
I. HISTORIC ENERGY CONSUMPTION/COST The energy usage for the facility has been tabulated and plotted in graph form as depicted within this section. Each energy source has been identified and monthly consumption and cost noted per the information provided by the Owner. Electric Utility Provider: Public Service Electric & Gas Electric Utility Rate Structure: Large Power & Lighting Service (LPLS) Third Party Supplier: South Jersey Energy Co. Natural Gas Utility Provider: South Jersey Gas Utility Rate Structure: Firm Transportation Third Party Supplier: Hess The electric usage profile represents the actual electrical usage for the facility. The electric utility measures consumption in kilowatt-hours (KWH) and maximum demand in kilowatts (KW). One KWH usage is equivalent to 1000 watts running for one hour. One KW of electric demand is equivalent to 1000 watts running at any given time. The basic usage charges are shown as generation service and delivery charges along with several non-utility generation charges. Rates used in this report reflect the historical data received for the facility. The gas usage profile within each facility report shows the actual natural gas energy usage for the facility. The gas utility measures consumption in cubic feet x 100 (CCF), and converts the quantity into Therms of energy. One Therm is equivalent to 100,000 BTUs of energy.
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 3 of 31
Table 1 Electricity Billing Data
Utility Provider: PSE&GRate: LPLS
Meter No: 778010763 / UnmeteredAccount # 42 010 665 09 / 69 371 929 08
Third Party Utility Provider: South Jersey Energy CoTPS Meter / Acct No: -
MONTH OF USE CONSUMPTION KWH TOTAL BILL
Jan-11 124,459 $18,499
Feb-11 60,835 $8,992
Mar-11 54,175 $8,086
Apr-11 46,481 $7,083
May-11 56,737 $8,107
Jun-11 71,585 $12,323
Jul-11 63,590 $10,011
Aug-11 56,749 $9,059
Sep-11 83,571 $13,973
Oct-11 57,235 $8,319
Nov-11 50,082 $7,065
Dec-11 68,140 $9,271
Totals 793,639 293 Max $120,786
AVERAGE DEMAND 200.6 KW average
AVERAGE RATE $0.152 $/kWh
160
164
282
164
150
293
278
167
142
244
ELECTRIC USAGE SUMMARY
DEMAND KW
186
178
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 4 of 31
Fig
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 5 of 31
ure 1 Electricity Usage Profile
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 6 of 31
Table 4 Natural Gas Billing Data
Utility Provider: South Jersey GasRate: Firm Transportation
Meter No: 422463Account Number 2 05 34 0108 0 4
Third Party Utility Provider: HESSTPS Account No:
MONTH OF USECONSUMPTION
(THERMS)TOTAL BILL
Jan-11 8,951 $9,605
Feb-11 6,026 $6,463
Mar-11 4,201 $4,514
Apr-11 3,093 $3,331
May-11 282 $317
Jun-11 226 $140
Jul-11 85 $114
Aug-11 66 $90
Sep-11 205 $230
Oct-11 665 $669
Nov-11 2,194 $2,206
Dec-11 3,853 $3,875
TOTALS 29,849 $31,553
AVERAGE RATE: $1.06 $/THERM
446596/447057
NATURAL GAS USAGE SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 7 of 31
Figure 2
Natura
l Gas
Usage
Profile
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 8 of 31
II. FACILITY DESCRIPTION
The Loring Flemming Elementary School is located on 135 Little Gloucester Road in Blackwood, New Jersey. The 75,150 SF school was built in 1976 with an addition in 1988. The building is a single story facility comprised of classrooms, multi-purpose room, cafeteria, kitchen, media center, mechanical room and offices.
Occupancy Profile
The typical hours of operation for the Middle School are Monday through Friday between 9:00 am and 3:30 pm. Loring Flemming Elementary School employs approximately 61 people, with student enrollment estimated at 700.
Building Envelope
Exterior walls for the Elementary School are split face masonry with a concrete block construction. The windows throughout the school are in good condition and appear to be maintained. Typical windows are double pane, operable, ¼” coated glass with aluminum frames. The roof is a flat built up roofing.
HVAC Systems
The newest wing of the Loring Flemming School is conditioned by self-contained direct expansion unit ventilators with hot water coils for heating.
The older sections of the school are mostly conditioned by a 2-pipe system of unit ventilators with 1 set of coils which require a changeover each season for heating or cooling use. There are two Trane chillers located in the courtyard which supply the chilled water to the system.
The remainder of the classrooms on the interior of the building and are conditioned by a variety of packaged rooftop units. There are four Trane packaged cooling only 3 ton units serving the older wing interior classrooms. Two 10 ton York packaged heating and air conditioning units with 180 MBH heating input conditioning the multi-purpose room and cafeteria. Several other small tonnage split systems provide cooling for indoor air handling units within the ceilings of certain interior classrooms.
Heating Hot Water is generated by a single boiler plant fitted with three Weil McLain cast iron sectional boilers. Two of the boilers are older Model 88 series and the last boiler is a newer Model 88 series. These boilers are natural gas fired rated at 1,358 MBH, 810 MBH and 1,413 MBH respectively, and are all fit with Power Flame Burners. Heating water is circulated to four sets of zone pumps within a different mechanical pumping room. The primary circulating pumps from the boiler room to the pump room are two, one horsepower Armstrong pumps. The four zone pumps are all Armstrong pumps rated as follows: Pumps 5 & 6 are 10 horsepower at 276 GPM and 76 feet of head; Pumps 7 & 8 are 3 horsepower at 106 GPM and 63 feet of head; Pumps 9 & 10 are 2 horsepower at 207 GPM and 20 feet of head; Pumps 11 & 12 are 1 horsepower at 82 GPM and 20 feet of head.
Exhaust System
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 9 of 31
Air is exhausted from the toilet rooms through the roof exhausters. The kitchen is outfitted with two exhaust hoods each connected to a dedicated roof exhaust fan with on/off control.
HVAC System Controls
The building has pneumatic thermostats and control valves in the unit ventilators. Supplemental cooling systems are controlled by individual thermostat. Control for the heating and cooling season
Domestic Hot Water
Domestic hot water is provided by a single Bradford and White 250 MBH gas fired heater with an integrated 100 gallon storage tank. Domestic hot water is circulated via a small horsepower pump.
Lighting
Refer to the Investment Grade lighting Audit Appendix for a detailed list of the lighting throughout the facility and estimated operating hours per space.
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 10 of 31
III. MAJOR EQUIPMENT LIST
The equipment list contains major energy consuming equipment that through implementation of energy conservation measures could yield substantial energy savings. The list shows the major equipment in the facility and all pertinent information utilized in energy savings calculations. An approximate age was assigned to the equipment in some cases if a manufactures date was not shown on the equipment’s nameplate. The ASHRAE service life for the equipment along with the remaining useful life is also shown in the Appendix.
Refer to the Major Equipment List Appendix for this facility.
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 11 of 31
IV. ENERGY CONSERVATION MEASURES Energy Conservation Measures are developed specifically for this facility. The energy savings and calculations are highly dependent on the information received from the site survey and interviews with operations personnel. The assumptions and calculations should be reviewed by the owner to ensure accurate representation of this facility. The following ECMs were analyzed:
Table 1 ECM Financial Summary
ECM #1 General Lighting Upgrades $16,661 $8,377 2.0 654.2%
ECM #2Multi-Purpose Room
Upgrade$5,400 $877 6.2 143.7%
ECM #3 Lighting Controls Upgrade $21,865 $3,109 7.0 113.3%
ECM #4NEMA Premium Motor
Replacements$14,150 $4,377 3.2 518.7%
ECM #5Condensing Boiler
Replacements$121,832 $2,974 41.0 -39.0%
ECM #6 Rooftop Unit Replacement $33,540 $2,270 14.8 1.5%
ECM #7 DDC Controls Upgrade $282,000 $8,951 31.5 -52.4%
REM #1 117.5 KW PV System $716,530 $49,248 14.5 3.1%
Notes:
ECM NO.
DESCRIPTIONSIMPLE
PAYBACK (Yrs)
SIMPLE LIFETIME
ROI
ENERGY CONSERVATION MEASURES (ECM's)
NET INSTALLATION
COSTA
RENEWABLE ENERGY MEASURES (REM's)
ECM NO.
DESCRIPTIONNET
INSTALLATION COST
ANNUAL
SAVINGSB
ANNUAL SAVINGS
SIMPLE PAYBACK
(Yrs)
SIMPLE LIFETIME
ROI
A. Cost takes into consideration applicable NJ Smart StartTM incentives.B. Savings takes into consideration applicable maintenance savings.
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 12 of 31
Table 2 ECM Energy Summary
ECM #1 General Lighting Upgrades 21.9 55,111 0
ECM #2Multi-Purpose Room
Upgrade2 5,772 0
ECM #3 Lighting Controls Upgrade 0.0 20,455 0
ECM #4NEMA Premium Motor
Replacements9.7 28,798 0
ECM #5Condensing Boiler
Replacements0.0 0 2,806
ECM #6 Rooftop Unit Replacement 7.5 14,933 0
ECM #7 DDC Controls Upgrade 0.0 41,476 2,496
REM #1 117.5 KW PV System 117.5 143,544 0
ENERGY CONSERVATION MEASURES (ECM's)
ELECTRIC DEMAND
(KW)
ELECTRIC CONSUMPTION
(KWH)
ECM NO.
DESCRIPTION
ANNUAL UTILITY REDUCTION
ECM NO.
DESCRIPTION
ANNUAL UTILITY REDUCTION
RENEWABLE ENERGY MEASURES (REM's)
NATURAL GAS (THERMS)
ELECTRIC DEMAND
(KW)
NATURAL GAS (THERMS)
ELECTRIC CONSUMPTION
(KWH)
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 13 of 31
Table 3 Facility Project Summary
Design / Construction Extras is shown as an additional cost for the facility project summary. This cost is included to estimate the costs associated with construction management fees for a larger combined project.
General Lighting Upgrades $8,377 $26,201 $9,540 $16,661 2.0
Multi-Purpose Room Upgrade
$877 $7,400 $2,000 $5,400 6.2
Lighting Controls Upgrade $3,109 $23,850 $1,985 $21,865 7.0
NEMA Premium Motor Replacements
$4,377 $14,910 $760 $14,150 3.2
Condensing Boiler Replacements
$2,974 $126,207 $4,375 $121,832 41.0
Rooftop Unit Replacement $2,270 $35,000 $1,460 $33,540 14.8
DDC Controls Upgrade $8,951 $282,000 $0 $282,000 31.5
Design / Construction Extras (15%)
$0 $77,335 $0 $77,335
Total Project $30,936 $592,904 $20,120 $572,784 19
SIMPLE PAYBACK
ENERGY CONSERVATION
MEASURES
ANNUAL ENERGY
SAVINGS ($)
PROJECT COST ($)
SMART START
INCENTIVES
CUSTOMER COST
ENERGY SAVINGS IMPROVEMENT PROGRAM - POTENTIAL PROJECT
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 14 of 31
ECM #1: Lighting Upgrade – General Description: The majority of the interior lighting throughout Loring Flemming Elementary School is provided with fluorescent fixtures with older generation, 700 series and 741/ECO 32W T8 lamps and electronic ballasts. Although these T8 lamps are considered fairly efficient, further energy savings can be achieved by replacing the existing T8 lamps with new generation, 800 series 28W T8 lamps without compromising light output. CE recommends, re-lamping all of the fixtures with 28W T8 lamps and in some cases removing a lamp from the fixture due to excessive foot candle levels in specific areas. This ECM includes re-lamping of the existing fluorescent fixtures with 800 series, 28W T8 lamps. The ECM also includes retrofit of all older fluorescent fixtures with T8 or T5 fluorescent fixtures with electronic ballasts in the building. The new, energy efficient T8 fixtures will provide adequate lighting and will save on electrical costs due to better performance of the lamp and ballasts. The ECM also includes replacement of any incandescent lamps with compact fluorescent lamps. Compact fluorescent lamps (CFL’s) were designed to be direct replacements for the standard incandescent lamps which are common to table lamps, spot lights, hi-hats, bathroom vanity lighting, etc. The light output of the CFL has been designed to resemble the incandescent lamp. The color rendering index (CRI) of the CFL is much higher than standard fluorescent lighting, and therefore provides a much “truer” light. The CFL is available in a myriad of shapes and sizes depending on the specific application. Typical replacements are: a 13-Watt CFL for a 60-Watt incandescent lamp, an 18-Watt CFL for a 75-Watt incandescent lamp, and a 26-Watt CFL for a 100-Watt incandescent lamp. The CFL is also available for a number of “brightness colors” that is indicated by the Kelvin rating. A 2700K CFL is the “warmest” color available and is closest in color to the incandescent lamp. CFL’s are also available in 3000K, 3500K, and 4100K. The 4100K would be the “brightest” or “coolest” output. A CFL can be chosen to screw right into your existing fixtures, or hardwired into your existing fixtures. Where the existing fixture is controlled by a dimmer switch, the CFL bulb must be compatible with a dimmer switch. In some locations the bulb replacement will need to be tested to make sure the larger base of the CFL will fit into the existing fixture. The energy usage of an incandescent compared to a compact fluorescent approximately 3 to 4 times greater. In addition to the energy savings, compact fluorescent fixtures burn-hours are 8 to 15 times longer than incandescent fixtures ranging from 6,000 to 15,000 burn-hours compared to incandescent fixtures ranging from 750 to 1000 burn-hours. However, the maintenance savings due to reduced lamp replacement is offset by the higher cost of the CFL’s compared to the incandescent lamps. Energy Savings Calculations: The Investment Grade Lighting Audit Appendix outlines the hours of operation, proposed retrofits, costs, savings, and payback periods for each set of fixtures in the each building.
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 15 of 31
Energy Savings Summary:
Installation Cost ($): $26,201
NJ Smart Start Equipment Incentive ($): $9,540
Net Installation Cost ($): $16,661
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $8,377
Total Yearly Savings ($/Yr): $8,377
Estimated ECM Lifetime (Yr): 15
Simple Payback 2.0
Simple Lifetime ROI 654.2%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $125,653
Internal Rate of Return (IRR) 50%
Net Present Value (NPV) $83,341.23
ECM #1 - ENERGY SAVINGS SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 16 of 31
ECM #2: Lighting Upgrade –Multi-Purpose Room Description: The multi-purpose room at Loring Flemming Elementary School is currently lit via 400 watt Metal Halide HID fixtures. The space would be better served with a more efficient, fluorescent lighting system. CE recommends upgrading the lighting to an energy-efficient T5 high output system that includes new six lamp 54 watt high output fixtures. This measure replaces all the HID, 400 watt HID MH fixtures with a well-designed T5 high output (HO) system. T5 High output fixtures with reflectors and wire guards will be required in order to meet the mandated 50 foot-candle average within the spaces. Energy Savings Calculations: A detailed Investment Grade Lighting Audit can be found in Investment Grade Lighting Audit Appendix that outlines the proposed retrofits, costs, savings, and payback periods. Energy Savings Summary:
Installation Cost ($): $7,400
NJ Smart Start Equipment Incentive ($): $2,000
Net Installation Cost ($): $5,400
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $877
Total Yearly Savings ($/Yr): $877
Estimated ECM Lifetime (Yr): 15
Simple Payback 6.2
Simple Lifetime ROI 143.7%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $13,160
Internal Rate of Return (IRR) 14%
Net Present Value (NPV) $5,073.68
ECM #2 - ENERGY SAVINGS SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 17 of 31
ECM #3: Lighting Controls Upgrade – Occupancy Sensors Description: Some of the lights in the Loring Flemming Elementary School are left on unnecessarily. In many cases the lights are left on because of the inconvenience to manually switch lights off when a room is left or on when a room is first occupied. This is common in rooms that are occupied for only short periods and only a few times per day. In some instances lights are left on due to the misconception that it is better to keep the lights on rather than to continuously switch lights on and off. Although increased switching reduces lamp life, the energy savings outweigh the lamp replacement costs. The payback timeframe for when to turn the lights off is approximately two minutes. If the lights are expected to be off for at least a two minute interval, then it pays to shut them off.
Lighting controls come in many forms. Sometimes an additional switch is adequate to provide reduced lighting levels when full light output is not needed. Occupancy sensors detect motion and will switch the lights on when the room is occupied. Occupancy sensors can either be mounted in place of a current wall switch, or on the ceiling to cover large areas. The U.S. Department of Energy sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the “Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways,” document posted for public use April 2005. The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the report:
Occupancy Sensors for Lighting Control 20% - 28% energy savings.
Savings resulting from the implementation of this ECM for energy management controls are estimated to be 20% of the total light energy controlled by occupancy sensors (The majority of the savings is expected to be after school hours when rooms are left with lights on) This ECM includes installation of ceiling or switch mount sensors for individual offices, classrooms, large bathrooms, and Media Centers. Sensors shall be manufactured by Sensorswitch, Watt Stopper or equivalent. The Investment Grade Lighting Audit Appendix of this report includes the summary of lighting controls implemented in this ECM and outlines the proposed controls, costs, savings, and payback periods. The calculations adjust the lighting power usage by the applicable percent savings for each area that includes lighting controls. Energy Savings Calculations:
kWh/YrEnergyLightControlledSavings%SavingsEnergy
kWh
$CostElecAvekWhSavingsEnergySavings.
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 18 of 31
Rebates and Incentives:
From the NJ Smart Start® Program Incentives Appendix, the installation of a lighting control device warrants the following incentive: SmartStartIncentive
#Wallmountsensors $20persensor#Ceilingmountsensors $35persensor
Energy Savings Summary:
Installation Cost ($): $23,850
NJ Smart Start Equipment Incentive ($): $1,985
Net Installation Cost ($): $21,865
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $3,109
Total Yearly Savings ($/Yr): $3,109
Estimated ECM Lifetime (Yr): 15
Simple Payback 7.0
Simple Lifetime ROI 113.3%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $46,636
Internal Rate of Return (IRR) 11%
Net Present Value (NPV) $15,251.19
ECM #3 - ENERGY SAVINGS SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 19 of 31
ECM #4: Install NEMA Premium® Efficiency Motors Description: The improved efficiency of the NEMA Premium® efficient motors is primarily due to better designs with use of better materials to reduce losses. Surprisingly, the electricity used to power a motor represents 95 % of its total lifetime operating cost. Because many motors operate continuously 24 hours a day, even small increases in efficiency can yield substantial energy and dollar savings. The electric motors driving the hot and cold water pumps are candidates for replacing with premium efficiency motors. These standard efficiency motors run considerable amount of time over a year. This energy conservation measure replaces existing inefficient electric motors with NEMA Premium® efficiency motors. NEMA Premium® is the most efficient motor designation in the marketplace today.
Energy Savings Calculations:
Electricusage, kWhHP LF 0.746 HoursofOperation
MotorEfficiency
where, HP MotorNameplateHorsepowerRating
EQMTID
FUNCTIONMOTOR
HPHOURS OF
OPERATIONEXISTING
EFFICIENCY
NEMA PREMIUM
EFFICIENCYP-1 Boiler Circ Pump 1 3,732 77.0% 87.5%P-2 Boiler Circ Pump 1 3,732 77.0% 87.5%P-3 Cold Water Suppl 5 2,745 85.5% 8850.0%P-4 Cold Water Suppl 5 2,745 85.5% 8850.0%P-5 Hot Water Pump 10 3,732 86.5% 92.4%P-6 Hot Water Pump 10 3,732 86.5% 92.4%P-7 Hot Water Pump 3 3,732 81.5% 89.5%P-8 Hot Water Pump 3 3,732 81.5% 89.5%P-9 Hot Water Pump 2 3,732 81.5% 86.5%P-10 Hot Water Pump 2 3,732 81.5% 86.5%P-11 Hot Water Pump 1 3,732 77.0% 87.5%P-12 Hot Water Pump 1 3,732 85.5% 87.5%
IMPLEMENTATION SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 20 of 31
LF LoadFactor MotorEfficiency MotorNameplateEfficiency
ProposedExisting UsageElectricUsageElectrickWhSavings,UsageElectric
ElectricUsageSavings, kWh ElectricUsage ElectricUsage
Electriccostsavings ElectricUsageSavings ElectricRate$
kWh
The calculations were carried out and the results are tabulated in the table below:
Equipment Cost and Incentives
Below is a summary of SmartStart Building® incentives for premium efficiency motors:
EQMTID
MOTOR HP
LOAD FACTOR
EXISTING EFFICIENCY
NEMA PREMIUM
EFFICIENCY
POWER SAVINGS
kW
ENERGY SAVINGS
kWH
COST SAVINGS
P-1 1 90% 77.0% 87.5% 0.10 393 $60P-2 1 90% 77.0% 87.5% 0.10 393 $60P-3 5 90% 85.5% 8850.0% 3.89 10,731 $1,631P-4 5 90% 85.5% 8850.0% 3.89 10,731 $1,631P-5 10 90% 86.5% 92.4% 0.50 1,860 $283P-6 10 90% 86.5% 92.4% 0.50 1,860 $283P-7 3 90% 81.5% 89.5% 0.22 829 $126P-8 3 90% 81.5% 89.5% 0.22 829 $126P-9 2 90% 81.5% 86.5% 0.10 357 $54P-10 2 90% 81.5% 86.5% 0.10 357 $54P-11 1 90% 77.0% 87.5% 0.10 393 $60P-12 1 90% 85.5% 87.5% 0.02 67 $10
TOTAL 9.7 28,798 $4,377
PREMIUM EFFICIENCY MOTOR CALCULATIONS
HORSE POWER
NJ SMART START
INCENTIVE5 $60
7.5 $9010 $10015 $11520 $12525 $130
30 $15040 $180
INCENTIVES
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 21 of 31
The following table outlines the summary of motor replacement costs and incentives:
Energy Savings Summary:
EQMTID
MOTOR POWER
HP
INSTALLED COST
SMART START
INCENTIVENET COST
TOTAL SAVINGS
SIMPLE PAYBACK
P-1 1 $708 $50 $658 $60 11.0P-2 1 $708 $50 $658 $60 11.0P-3 5 $1,562 $60 $1,502 $1,631 0.9P-4 5 $1,562 $60 $1,502 $1,631 0.9P-5 10 $2,560 $100 $2,460 $283 8.7P-6 10 $2,560 $100 $2,460 $283 8.7P-7 3 $1,049 $60 $989 $126 7.9P-8 3 $1,049 $60 $989 $126 7.9P-9 2 $868 $60 $808 $54 14.9P-10 2 $868 $60 $808 $54 14.9P-11 1 $708 $50 $658 $60 11.0P-12 1 $708 $50 $658 $10 64.3
TOTAL Totals: $14,910 $760 $14,150 $4,377 3.2
MOTOR REPLACEMENT SUMMARY
Installation Cost ($): $14,910
NJ Smart Start Equipment Incentive ($): $760
Net Installation Cost ($): $14,150
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $4,377
Total Yearly Savings ($/Yr): $4,377
Estimated ECM Lifetime (Yr): 20
Simple Payback 3.2
Simple Lifetime ROI 518.7%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $87,540
Internal Rate of Return (IRR) 31%
Net Present Value (NPV) $50,968.71
ECM #4 - ENERGY SAVINGS SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 22 of 31
ECM #5: Condensing Boiler Installation Description: The existing boiler plant consists of three cast iron boilers which are used as the primary source of heat for Loring Flemming Elementary School. The two existing boilers are approaching their life expectancy of a typical cast iron boiler and could be considered for replacement. With the increased efficiency of the condensing boilers, the savings can be substantial. New condensing boilers could substantially improve the operating efficiency of the heating system of the building. Condensing boiler’s peak efficiency tops out at 99% depending on return water temperature. Due to the operating conditions of the building, the annual average operating efficiency of the proposed condensing boiler is expected to be 88%. The existing boiler’s efficiency is approximately 75%, which makes the condensing boilers an 13% increase in efficiency. This ECM is based on variable supply water temperature adjusted based on outdoor temperature. This ECM includes installation of two condensing gas fired boilers to replace the existing Weil McLain cast iron boilers. The basis for this ECM is Aerco condensing boiler; model numbers BMK – 1.0 & 1.5. The boiler installation is based on a one for one replacement based on capacity of the existing boiler. Energy Savings Calculations: Baseline Hot Water Gas Use: 4,885 Therms Baseline Rooftop Gas Use: 5,373 Therms Existing Heating Natural Gas: 29,849 Therms – 4,885 Domestic HW – 5,373 Rooftops = 18,995 Therms
Therm
BTUHeatValueFuelEffHeatingThermsGasNatExistingquiredHeatBldg %.Re
Therm
BTUValueHeatFuelEffHeating
BTUquiredHeatBldgUsageGasHeatingoposed
%.
RePr
ThermCostFuelAveThermsUsageGasHeatingCostEnergy
$
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 23 of 31
From the NJ Smart Start Appendix, the installation of new condensing boilers warrants the following incentive: $1.75 per MBH.
ECM INPUTS EXISTING PROPOSED SAVINGS
ECM INPUTSExisting Cast Iron
BoilersNew Condensing
Boilers
Existing Nat Gas (Therms) 18,995 0
Boiler Efficiency (%) 75% 88% 13%
Nat Gas Heat Value (BTU/Therm)
100,000 100,000
Equivalent Building Heat Usage (MMBTUs)
1,425 1,425
Gas Cost ($/Therm) 1.06 1.06
ECM RESULTS EXISTING PROPOSED SAVINGS
Natural Gas Usage (Therms) 18,995 16,189 2,806
Energy Cost ($) $20,135 $17,160 $2,974
COMMENTS:
CONDENSING BOILER CALCULATIONS
ENERGY SAVINGS CALCULATIONS
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 24 of 31
Energy Savings Summary:
Installation Cost ($): $126,207
NJ Smart Start Equipment Incentive ($): $4,375
Net Installation Cost ($): $121,832
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $2,974
Total Yearly Savings ($/Yr): $2,974
Estimated ECM Lifetime (Yr): 25
Simple Payback 41.0
Simple Lifetime ROI -39.0%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $74,361
Internal Rate of Return (IRR) -3%
Net Present Value (NPV) ($70,037.79)
ECM #5 - ENERGY SAVINGS SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 25 of 31
ECM #6: Replace Rooftop Units with High Efficiency Units
Description:
Cooling for the cafeteria and multi-purpose room of Loring Flemming Elementary School is served by two 10 ton packaged rooftop units.
These units are in average condition though the current units in operation are not high efficiency units. These units are approximately sixteen years old and have recently surpassed their ASHRAE service life of fifteen years.
These units can be replaced with new higher efficiency units. New packaged rooftop units provide higher full load and part load efficiencies due to advances in inverter motor technologies, heat exchangers and higher efficiency refrigerants such as R410A which would be used in place of R22 that is currently used in these units. This ECM includes one-for-one replacement of the older packaged rooftop units with new higher efficiency systems. It is recommended to fully evaluate the capacity needed for all new systems prior to moving forward with this ECM. A summary of the unit replacements for this ECM can be found in the table below:
The manufacturers used as the basis for the calculation is Trane. The unit pricing and install cost were estimated based on current rates quotes and labor rates. The payback may change based on actual unit pricing and install costs if the ECM is implemented. Energy Savings Calculations: Cooling Energy Savings: Seasonal energy consumption of the air conditioners at the cooling mode is calculated with the equation below:
EnergySavings, kWh CoolingCapacity,BTUHr
1SEER
1SEER
OperationHours
1000 WkWh
DemandSavings, kWEnergySavings kWhHoursofCooling
CoolingCostSavings EnergySavings, kWh CostofElectricity$
kWh
ECM INPUTS SERVICE FORNUMBER OF UNITS
COOLING CAPACITY,
BTU/HR
TOTAL CAPACITY,
TONSREPLACE UNIT WITH
RTU RTU - 1 , 2 2 120,000 20.0 Trane THC120
Total 2 240,000 20.0
IMPLEMENTATION SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 26 of 31
Project Cost, Incentives and Maintenance Savings From the NJ Smart Start® Program appendix, the rebate is $73 per ton. Summary of cost, savings and payback for this ECM is below.
Energy Savings Summary:
ECM INPUTS
COOLING CAPACITY,
BTU/Hr
ANNUAL COOLING
HOURS
EXISTING UNITS EER
SPLIT UNITS EER
# OF UNITS
ENERGY SAVINGS
kWh
DEMAND SAVINGS
kW
RTU 120,000 2,000 9 EER 12.5 EER 2 14,933 7.5
Total 2 14,933 7.5
ENERGY SAVINGS CALCULATIONS
ECM INPUTSINSTALLED
COST# OF
UNITSTOTAL COST
REBATES NET COSTENERGY SAVING
PAY BACK YEARS
RTU $35,000 2 $35,000 $1,460 $33,540 $2,270 14.8
Total $35,000 2 $35,000 $1,460 $33,540 $2,270 14.8
COST & SAVINGS SUMMARY
Installation Cost ($): $35,000
NJ Smart Start Equipment Incentive ($): $1,460
Net Installation Cost ($): $33,540
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $2,270
Total Yearly Savings ($/Yr): $2,270
Estimated ECM Lifetime (Yr): 15
Simple Payback 14.8
Simple Lifetime ROI 1.5%
Simple Lifetime Maintenance Savings 0
Simple Lifetime Savings $34,048
Internal Rate of Return (IRR) 0%
Net Present Value (NPV) ($6,442.48)
ECM #6 - ENERGY SAVINGS SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 27 of 31
ECM #7: Digital Energy Management System (DDC EMS) Description:
The unit ventilators are controlled locally via central pneumatic control systems. The remainder of the HVAC systems throughout the school is controlled via manual thermostats.
The unit ventilator fans throughout the spaces are manually enabled with the control valve and outside air damper controlled by a pneumatic thermostat. The unit ventilators are all 2-pipe systems and require a manual change-over to switch from heating and cooling mode. The window air conditioners are controlled manually via on board controls or remote controllers.
Concord Engineering recommends installing a DDC system throughout the school to control the entire HVAC systems including the unit ventilators in the classrooms, indoor air handling units, rooftop units and roof exhaust fans. The system will include new temperature sensors and new local thermostats with limited over-ride capability, a front end computer and main controller. The system will also include central controls for lighting. With the communication between the control devices and the front end computer interface, the facility manager will be able to take advantage of scheduling for occupied and unoccupied periods based on the actual occupancy of each space in the facility. Due to the fact that the building may have diverse hours of occupancy, including evening and weekend activities, having supervisory control over all of the equipment makes sense. The DDC system will also aid in the response time to service / maintenance issues when the facility is not under normal maintenance supervision, i.e. after-hours. The new DDC system has the potential to provide significant savings by controlling the HVAC systems as a whole and provide operating schedules and features such as space averaging, night set-back, temperature override control, etc. The U.S. Department of Energy sponsored a study to analyze energy savings achieved through various types of building system controls. The referenced savings is based on the “Advanced Sensors and Controls for Building Applications: Market Assessment and Potential R&D Pathways,” document posted for public use April 2005. The study has found that commercial buildings have the potential to achieve significant energy savings through the use of building controls. The average energy savings are as follows based on the referenced report:
Energy Management and Control System Savings: 5%-15%. Savings resulting from the implementation of this ECM for energy management controls are estimated to be 10% of the electricity and 10% for the fuel oil utility in this building.
The basis for the DDC system expansion is the Automated Logic Energy Management System or similar.
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 28 of 31
Energy Savings Calculations:
Energy savings for each utility is calculated with the equation below.
EnergySavings Utility CurrentEnergyConsumption EstimatedSavings,% Following table summarizes energy savings for this facility via implementation of an Energy Management System:
Demand savings due to implementation of this ECM is minimal.
ECM INPUTS EXISTING PROPOSED SAVINGS
ECM INPUTSExisting Controls w/ Local Thermostats
DDC Controls
Existing Nat Gas Usage (Therms)
24,964 -
Existing Electricity Usage (kWh)
414,763 -
Energy Savings, Nat Gas - 10%
Energy Savings, Electricity - 10%
Gas Cost ($/Therm) $1.06 $1.06
Electricity Cost ($/kWh) $0.152 $0.152
ECM RESULTS EXISTING PROPOSED SAVINGS
Nat Gas Usage (Therms) 24,964 22,468 2,496
Electricity Usage (kWh) 414,763 373,287 41,476
Nat Gas Cost ($) $26,462 $23,816 $2,646
Electricity Cost ($) $63,044 $56,740 $6,304
Energy Cost ($) $89,506 $80,555 $8,951
COMMENTS:
DDC ENERGY MANAGEMENT SYSYEM CALCULATIONS
ENERGY SAVINGS CALCULATIONS
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 29 of 31
The cost of a full DDC system with new field devices, controllers, computer, software, programming, etc. is approximately $3.75 per SF in accordance with recent Contractor pricing for systems of this magnitude. Savings from the implementation of this ECM will be from the reduced energy consumption currently used by the HVAC system by proper control of schedule and temperatures via the DDC system. Cost of complete DDC System = ($3.75/SF x 75,150 SF) = $282,000 Currently, there are no prequalified NJ SmartSmart Incentives for installation of the DDC system. Energy Savings Summary:
Installation Cost ($): $282,000
NJ Smart Start Equipment Incentive ($): $0
Net Installation Cost ($): $282,000
Maintenance Savings ($/Yr): $0
Energy Savings ($/Yr): $8,951
Total Yearly Savings ($/Yr): $8,951
Estimated ECM Lifetime (Yr): 15
Simple Payback 31.5
Simple Lifetime ROI -52.4%
Simple Lifetime Maintenance Savings $0
Simple Lifetime Savings $134,265
Internal Rate of Return (IRR) -8%
Net Present Value (NPV) ($175,143.54)
ECM #7 - ENERGY SAVINGS SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 30 of 31
REM #1: 117.5 kW Solar System Description: The Loring Flemming Elementary School has available roof space that could accommodate a significant amount of solar generation. Based on the available areas a 117.5 kilowatt solar array could be installed, assuming the existing roof structure is capable of supporting an array. The array will produce approximately 143,544 kilowatt-hours annually that will reduce the overall electric usage of the facility by 18.09%. Energy Savings Calculations: See Renewable / Distributed Energy Measures Calculations Appendix for detailed financial summary and proposed solar layout areas. Financial results in table below are based on 100% financing of the system over a fifteen year period. Energy Savings Summary:
System Size (KWDC): 117.50
Electric Generation (KWH/Yr): 143,544
Installation Cost ($): $716,530
SREC Revenue ($/Yr): $27,429
Energy Savings ($/Yr): $21,819
Total Yearly Savings ($/Yr): $49,248
ECM Analysis Period (Yr): 15
Simple Payback (Yrs): 14.5
Analysis Period Electric Savings ($): $405,804
Analysis Period SREC Revenue ($): $397,343
Net Present Value (NPV) ($219,152.05)
REM #1 - ENERGY SAVINGS SUMMARY
Gloucester Township BOE – Loring-Flemming Elementary School Energy Audit
Concord Engineering Group, Inc. 9C12010 August 2, 2012– FINAL Page 31 of 31
V. ADDITIONAL RECOMMENDATIONS The following recommendations include no cost/low cost measures, Operation & Maintenance (O&M) items, and water conservation measures with attractive paybacks. These measures are not eligible for the Smart Start Buildings incentives from the office of Clean Energy but save energy none the less.
A. Chemically clean the condenser and evaporator coils periodically to optimize efficiency. Poorly maintained heat transfer surfaces can reduce efficiency 5-10%.
B. Maintain all weather stripping on windows and doors.
C. Clean all light fixtures to maximize light output.
D. Provide more frequent air filter changes to decrease overall system power usage and maintain better IAQ.
E. Turn off computers when not in use. Ensure computers are not running in screen saver mode which saves the monitor screen not energy.
F. Ensure outside air dampers are functioning properly and only open during occupied mode.
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX A
APPENDIX A1 of 1
LIFETIME ENERGY SAVINGS
LIFETIME MAINTENANCE
SAVINGSLIFETIME ROI SIMPLE PAYBACK
INTERNAL RATE OF RETURN (IRR)
NET PRESENT VALUE (NPV)
MATERIAL LABORREBATES,
INCENTIVES
NET INSTALLATION
COSTENERGY MAINT. / SREC TOTAL (Yearly Saving * ECM Lifetime)
(Yearly Maint Svaing * ECM Lifetime)
(Lifetime Savings - Net Cost) / (Net Cost)
(Net cost / Yearly Savings)
($) ($) ($) ($) ($/Yr) ($/Yr) ($/Yr) (Yr) ($) ($) (%) (Yr) ($) ($)
ECM #1 General Lighting Upgrades $26,201 $0 $9,540 $16,661 $8,377 $0 $8,377 15 $125,653 $0 654.2% 2.0 50.16% $83,341.23
ECM #2 Multi-Purpose Room Upgrade $7,400 $0 $2,000 $5,400 $877 $0 $877 15 $13,160 $0 143.7% 6.2 13.96% $5,073.68
ECM #3 Lighting Controls Upgrade $19,800 $4,050 $1,985 $21,865 $3,109 $0 $3,109 15 $46,636 $0 113.3% 7.0 11.41% $15,251.19
ECM #4 NEMA Premium Motor Replacements $14,910 $0 $760 $14,150 $4,377 $0 $4,377 20 $87,540 $0 518.7% 3.2 30.79% $50,968.71
ECM #5 Condensing Boiler Replacements $29,410 $96,797 $4,375 $121,832 $2,974 $0 $2,974 25 $74,361 $0 -39.0% 41.0 -3.49% ($70,037.79)
ECM #6 Rooftop Unit Replacement $25,000 $10,000 $1,460 $33,540 $2,270 $0 $2,270 15 $34,048 $0 1.5% 14.8 0.19% ($6,442.48)
ECM #7 DDC Controls Upgrade $282,000 $0 $0 $282,000 $8,951 $0 $8,951 15 $134,265 $0 -52.4% 31.5 -8.11% ($175,143.54)
REM #1 117.5 KW PV System $716,530 $0 $0 $716,530 $21,819 $27,429 $49,248 15 $738,716 $411,436 3.1% 14.5 0.38% ($128,614.18)
Notes: 1) The variable Cn in the formulas for Internal Rate of Return and Net Present Value stands for the cash flow during each period.2) The variable DR in the NPV equation stands for Discount Rate3) For NPV and IRR calculations: From n=0 to N periods where N is the lifetime of ECM and Cn is the cash flow during each period .
REM RENEWABLE ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY
ECM COST & SAVINGS BREAKDOWN
CONCORD ENGINEERING GROUP
Gloucester Township BOE - Loring Flemming Elementary School
INSTALLATION COST YEARLY SAVINGS
ECM LIFETIMEDESCRIPTIONECM NO.
ECM ENERGY AND FINANCIAL COSTS AND SAVINGS SUMMARY
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX B
Appendix B Page 1 of 4
Concord Engineering Group, Inc. 520 BURNT MILL ROAD VOORHEES, NEW JERSEY 08043 PHONE: (856) 427-0200 FAX: (856) 427-6508
SmartStart Building Incentives The NJ SmartStart Buildings Program offers financial incentives on a wide variety of building system equipment. The incentives were developed to help offset the initial cost of energy-efficient equipment. The following tables show the current available incentives as of February 15, 2011:
Electric Chillers Water-Cooled Chillers $12 - $170 per ton
Air-Cooled Chillers $8 - $52 per ton
Energy Efficiency must comply with ASHRAE 90.1-2007
Gas Cooling Gas Absorption Chillers $185 - $400 per ton
Gas Engine-Driven Chillers Calculated through custom measure
path)
Desiccant Systems $1.00 per cfm – gas or electric
Electric Unitary HVAC Unitary AC and Split Systems $73 - $92 per ton
Air-to-Air Heat Pumps $73 - $92 per ton Water-Source Heat Pumps $81 per ton
Packaged Terminal AC & HP $65 per ton Central DX AC Systems $40- $72 per ton
Dual Enthalpy Economizer Controls $250 Occupancy Controlled Thermostat
(Hospitality & Institutional Facility) $75 per thermostat
Energy Efficiency must comply with ASHRAE 90.1-2007
Gas Heating
Gas Fired Boilers < 300 MBH $300 per unit
Gas Fired Boilers ≥ 300 - 1500 MBH $1.75 per MBH
Gas Fired Boilers ≥1500 - ≤ 4000 MBH $1.00 per MBH
Gas Fired Boilers > 4000 MBH (Calculated through Custom Measure
Path)
Gas Furnaces $300 - $400 per unit, AFUE ≥ 92%
Appendix B Page 2 of 4
Ground Source Heat Pumps
Closed Loop $450 per ton, EER ≥ 16 $600 per ton, EER ≥ 18 $750 per ton, EER ≥ 20
Energy Efficiency must comply with ASHRAE 90.1-2007
Variable Frequency Drives Variable Air Volume $65 - $155 per hp
Chilled-Water Pumps $60 per VFD rated hp
Compressors $5,250 to $12,500 per drive
Cooling Towers ≥ 10 hp $60 per VFD rated hp
Natural Gas Water Heating
Gas Water Heaters ≤ 50 gallons, 0.67 energy factor or better
$50 per unit
Gas-Fired Water Heaters > 50 gallons $1.00 - $2.00 per MBH
Gas-Fired Booster Water Heaters $17 - $35 per MBH
Gas Fired Tankless Water Heaters $300 per unit
Prescriptive Lighting Retro fit of T12 to T-5 or T-8 Lamps
w/Electronic Ballast in Existing Facilities
$10 per fixture (1-4 lamps)
Replacement of T12 with new T-5 or T-8 Lamps w/Electronic Ballast in
Existing Facilities $25 per fixture (1-4 lamps)
Replacement of incandescent with screw-in PAR 38 or PAR 30 (CFL)
bulb $7 per bulb
T-8 reduced Wattage (28w/25w 4’, 1-4 lamps)
Lamp & ballast replacement $10 per fixture
Hard-Wired Compact Fluorescent $25 - $30 per fixture
Metal Halide w/Pulse Start Including Parking Lot
$25 per fixture
T-5 and T-8 High Bay Fixtures $16 - $200 per fixture
HID ≥ 100w Retrofit with induction lamp, power coupler and generator
(must be 30% less watts/fixture than HID system)
$50 per fixture
HID ≥ 100w Replacement with new HID ≥ 100w
$70 per fixture
Appendix B Page 3 of 4
Prescriptive Lighting - LED
LED New Exit Sign Fixture Existing Facility < 75 kw Existing Facility > 75 kw
$20 per fixture $10 per fixture
LED Display Case Lighting $30 per display case
LED Shelf-Mtd. Display & Task Lights $15 per linear foot
LED Portable Desk Lamp $20 per fixture
LED Wall-wash Lights $30 per fixture
LED Recessed Down Lights $35 per fixture LED Outdoor Pole/Arm-Mounted Area
and Roadway Luminaries $175 per fixture
LED Outdoor Pole/Arm-Mounted Decorative Luminaries
$175 per fixture
LED Outdoor Wall-Mounted Area Luminaries
$100 per fixture
LED Parking Garage Luminaries $100 per fixture
LED Track or Mono-Point Directional Lighting Fixtures
$50 per fixture
LED High-Bay and Low-Bay Fixtures for Commercial & Industrial Bldgs.
$150 per fixture
LED High-Bay-Aisle Lighting $150 per fixture
LED Bollard Fixtures $50 per fixture
LED Linear Panels (2x2 Troffers only) $100 per fixture
LED Fuel Pump Canopy $100 per fixture
LED Refrigerator/Freezer case lighting replacement of fluorescent in medium
and low temperature display case
$42 per 5 foot $65 per 6 foot
Appendix B Page 4 of 4
Lighting Controls – Occupancy Sensors
Wall Mounted $20 per control Remote Mounted $35 per control
Daylight Dimmers $25 per fixture
Occupancy Controlled hi-low Fluorescent Controls
$25 per fixture controlled
Lighting Controls – HID or Fluorescent Hi-Bay Controls Occupancy hi-low $75 per fixture controlled Daylight Dimming $75 per fixture controlled
Daylight Dimming - office $50 per fixture controlled
Premium Motors Three-Phase Motors $45 - $700 per motor
Fractional HP Motors Electronic Communicated Motors (replacing shaded pole motors in
refrigerator/freezer cases)
$40 per electronic communicated motor
Other Equipment Incentives
Performance Lighting
$1.00 per watt per SF below program incentive threshold, currently 5% more energy efficient than ASHRAE 90.1-
2007 for New Construction and Complete Renovation
Custom Electric and Gas Equipment Incentives
not prescriptive
Custom Measures
$0.16 KWh and $1.60/Therm of 1st year savings, or a buy down to a 1 year
payback on estimated savings. Minimum required savings of 75,000 KWh or 1,500 Therms and a IRR of at
least 10%. Multi Measures Bonus 15%
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX C
OMB No. 2060-0347
STATEMENT OF ENERGY PERFORMANCE8-Loring Flemming Elementary School
Building ID: 3102177 For 12-month Period Ending: November 30, 20111
Date SEP becomes ineligible: N/A Date SEP Generated: July 03, 2012
Facility8-Loring Flemming Elementary School135 Little Gloucester RoadBlackwood, NJ 08012
Facility OwnerGloucester Township Public Schools17 Erial Road Blackwood, NJ 08012
Primary Contact for this FacilityJohn Bilodeau17 Erial Road Blackwood, NJ 08012
Year Built: 1988Gross Floor Area (ft2): 75,150
Energy Performance Rating2 (1-100) 50
Site Energy Use Summary3
Electricity - Grid Purchase(kBtu) 2,460,549 Natural Gas (kBtu)4 2,881,717 Total Energy (kBtu) 5,342,266
Energy Intensity4 Site (kBtu/ft2/yr) 71 Source (kBtu/ft2/yr) 150 Emissions (based on site energy use) Greenhouse Gas Emissions (MtCO2e/year) 502 Electric Distribution Utility Public Service Electric & Gas Co National Median Comparison National Median Site EUI 71 National Median Source EUI 150 % Difference from National Median Source EUI 0% Building Type K-12
School
Stamp of Certifying Professional
Based on the conditions observed at thetime of my visit to this building, I certify that
the information contained within thisstatement is accurate.
Meets Industry Standards5 for Indoor EnvironmentalConditions:Ventilation for Acceptable Indoor Air Quality N/A Acceptable Thermal Environmental Conditions N/A Adequate Illumination N/A
Certifying ProfessionalMichael Fischette520 South Burnt Mill Road Voorhees, NJ 08043
Notes: 1. Application for the ENERGY STAR must be submitted to EPA within 4 months of the Period Ending date. Award of the ENERGY STAR is not final until approval is received from EPA.2. The EPA Energy Performance Rating is based on total source energy. A rating of 75 is the minimum to be eligible for the ENERGY STAR.3. Values represent energy consumption, annualized to a 12-month period.4. Values represent energy intensity, annualized to a 12-month period.5. Based on Meeting ASHRAE Standard 62 for ventilation for acceptable indoor air quality, ASHRAE Standard 55 for thermal comfort, and IESNA Lighting Handbook for lighting quality.
The government estimates the average time needed to fill out this form is 6 hours (includes the time for entering energy data, Licensed Professional facility inspection, and notarizing the SEP) andwelcomes suggestions for reducing this level of effort. Send comments (referencing OMB control number) to the Director, Collection Strategies Division, U.S., EPA (2822T), 1200 Pennsylvania Ave.,NW, Washington, D.C. 20460.
EPA Form 5900-16
ENERGY STAR®
Data Checklistfor Commercial Buildings
In order for a building to qualify for the ENERGY STAR, a Professional Engineer (PE) or a Registered Architect (RA) must validate the accuracy of the data underlyingthe building's energy performance rating. This checklist is designed to provide an at-a-glance summary of a property's physical and operating characteristics, as well asits total energy consumption, to assist the PE or RA in double-checking the information that the building owner or operator has entered into Portfolio Manager.
Please complete and sign this checklist and include it with the stamped, signed Statement of Energy Performance.NOTE: You must check each box to indicate that each value is correct, OR include a note.
CRITERION VALUE AS ENTERED INPORTFOLIO MANAGER VERIFICATION QUESTIONS NOTES
Building Name 8-Loring FlemmingElementary School
Is this the official building name to be displayed inthe ENERGY STAR Registry of LabeledBuildings?
Type K-12 School Is this an accurate description of the space inquestion?
Location 135 Little Gloucester Road,
Blackwood, NJ 08012 Is this address accurate and complete? Correctweather normalization requires an accurate zipcode.
Single Structure Single Facility
Does this SEP represent a single structure? SEPscannot be submitted for multiple-buildingcampuses (with the exception of a hospital, k-12school, hotel and senior care facility) nor can theybe submitted as representing only a portion of abuilding.
Loring Flemming (K-12 School)
CRITERION VALUE AS ENTERED INPORTFOLIO MANAGER VERIFICATION QUESTIONS NOTES
Gross Floor Area 75,150 Sq. Ft.
Does this square footage include all supportingfunctions such as kitchens and break rooms usedby staff, storage areas, administrative areas,elevators, stairwells, atria, vent shafts, etc. Alsonote that existing atriums should only include thebase floor area that it occupies. Interstitial(plenum) space between floors should not beincluded in the total. Finally gross floor area is notthe same as leasable space. Leasable space is asubset of gross floor area.
Open Weekends? No
Is this building normally open at all on theweekends? This includes activities beyond thework conducted by maintenance, cleaning, andsecurity personnel. Weekend activity could includeany time when the space is used for classes,performances or other school or communityactivities. If the building is open on the weekend aspart of the standard schedule during one or moreseasons, the building should select ?yes? for openweekends. The ?yes? response should applywhether the building is open for one or both of theweekend days.
Number of PCs 150 Is this the number of personal computers in theK12 School?
Number of walk-inrefrigeration/freezer
units 2
Is this the total number of commercial walk-in typefreezers and coolers? These units are typicallyfound in storage and receiving areas.
Presence ofcooking facilities Yes
Does this school have a dedicated space in whichfood is prepared and served to students? If theschool has space in which food for students is onlykept warm and/or served to students, or has only agalley that is used by teachers and staff then theanswer is "no".
Percent Cooled 70 % Is this the percentage of the total floor space withinthe facility that is served by mechanical coolingequipment?
Percent Heated 100 % Is this the percentage of the total floor space withinthe facility that is served by mechanical heatingequipment?
Months 10(Optional) Is this school in operation for at least 8 months ofthe year?
Page 1 of 4
High School? No
Is this building a high school (teaching grades 10,11, and/or 12)? If the building teaches to highschool students at all, the user should check 'yes'to 'high school'. For example, if the school teachesto grades K-12 (elementary/middle and highschool), the user should check 'yes' to 'highschool'.
Page 2 of 4
ENERGY STAR®
Data Checklistfor Commercial Buildings
Energy ConsumptionPower Generation Plant or Distribution Utility: Public Service Electric & Gas Co
Fuel Type: Electricity
Meter: Electric #42 010 665 09 (kWh (thousand Watt-hours))Space(s): Entire Facility
Generation Method: Grid Purchase
Start Date End Date Energy Use (kWh (thousand Watt-hours))
10/25/2011 11/23/2011 49,560.00
09/26/2011 10/25/2011 56,760.00
08/25/2011 09/26/2011 83,160.00
07/27/2011 08/25/2011 56,400.00
06/26/2011 07/27/2011 63,240.00
05/26/2011 06/26/2011 71,280.00
04/27/2011 05/26/2011 56,400.00
03/28/2011 04/27/2011 46,080.00
02/25/2011 03/28/2011 53,760.00
01/26/2011 02/25/2011 60,360.00
Electric #42 010 665 09 Consumption (kWh (thousand Watt-hours)) 597,000.00
Electric #42 010 665 09 Consumption (kBtu (thousand Btu)) 2,036,964.00
Total Electricity (Grid Purchase) Consumption (kBtu (thousand Btu)) 2,036,964.00
Is this the total Electricity (Grid Purchase) consumption at this building including allElectricity meters?
Fuel Type: Natural Gas
Meter: Gas #2 05 34 0108 0 4 (therms)Space(s): Entire Facility
Start Date End Date Energy Use (therms)
10/25/2011 11/22/2011 2,193.80
09/23/2011 10/25/2011 665.30
08/23/2011 09/23/2011 205.10
07/26/2011 08/23/2011 66.40
06/24/2011 07/26/2011 85.10
05/24/2011 06/24/2011 226.50
04/26/2011 05/24/2011 282.40
03/25/2011 04/26/2011 3,093.30
02/23/2011 03/25/2011 4,201.50
01/26/2011 02/23/2011 6,026.50
12/23/2010 01/26/2011 8,950.80
Gas #2 05 34 0108 0 4 Consumption (therms) 25,996.70
Page 3 of 4
Gas #2 05 34 0108 0 4 Consumption (kBtu (thousand Btu)) 2,599,670.00
Total Natural Gas Consumption (kBtu (thousand Btu)) 2,599,670.00
Is this the total Natural Gas consumption at this building including all Natural Gas meters?
Additional FuelsDo the fuel consumption totals shown above represent the total energy use of this building?Please confirm there are no additional fuels (district energy, generator fuel oil) used in this facility.
On-Site Solar and Wind EnergyDo the fuel consumption totals shown above include all on-site solar and/or wind power located atyour facility? Please confirm that no on-site solar or wind installations have been omitted from thislist. All on-site systems must be reported.
Certifying Professional (When applying for the ENERGY STAR, the Certifying Professional must be the same PE or RA that signed and stamped the SEP.)
Name: _____________________________________________ Date: _____________
Signature: ______________________________________ Signature is required when applying for the ENERGY STAR.
Page 4 of 4
FOR YOUR RECORDS ONLY. DO NOT SUBMIT TO EPA.
Please keep this Facility Summary for your own records; do not submit it to EPA. Only the Statement of Energy Performance(SEP), Data Checklist and Letter of Agreement need to be submitted to EPA when applying for the ENERGY STAR.
Facility8-Loring Flemming Elementary School135 Little Gloucester RoadBlackwood, NJ 08012
Facility OwnerGloucester Township Public Schools17 Erial Road Blackwood, NJ 08012
Primary Contact for this FacilityJohn Bilodeau17 Erial Road Blackwood, NJ 08012
General Information8-Loring Flemming Elementary School
Gross Floor Area Excluding Parking: (ft2) 75,150 Year Built 1988 For 12-month Evaluation Period Ending Date: November 30, 2011
Facility Space Use SummaryLoring Flemming
Space Type K-12 School
Gross Floor Area (ft2) 75,150
Open Weekends? No
Number of PCs 150
Number of walk-in refrigeration/freezerunits 2
Presence of cooking facilities Yes
Percent Cooled 70
Percent Heated 100
Months o 10
High School? No
School District o N/A
Energy Performance ComparisonEvaluation Periods Comparisons
Performance Metrics Current(Ending Date 11/30/2011)
Baseline(Ending Date 11/30/2011) Rating of 75 Target National Median
Energy Performance Rating 50 50 75 N/A 50
Energy Intensity
Site (kBtu/ft2) 71 71 56 N/A 71
Source (kBtu/ft2) 150 150 118 N/A 150
Energy Cost
$/year N/A N/A N/A N/A N/A
$/ft2/year N/A N/A N/A N/A N/A
Greenhouse Gas Emissions
MtCO2e/year 502 502 395 N/A 505
kgCO2e/ft2/year 7 7 6 N/A 7
More than 50% of your building is defined as K-12 School. Please note that your rating accounts for all of the spaces listed. The National Median column presentsenergy performance data your building would have if your building had a median rating of 50. Notes:o - This attribute is optional.d - A default value has been supplied by Portfolio Manager.
20118-Loring Flemming Elementary School135 Little Gloucester RoadBlackwood, NJ 08012
Portfolio Manager Building ID: 3102177
The energy use of this building has been measured and compared to other similar buildings using theEnvironmental Protection Agency’s (EPA’s) Energy Performance Scale of 1–100, with 1 being the least energyefficient and 100 the most energy efficient. For more information, visit energystar.gov/benchmark.
This building’sscore
50
100
Most Efficient
This building uses 150 kBtu per square foot per year.*
*Based on source energy intensity for the 12 month period ending November 2011
Date of certification
Date Generated: 07/03/2012
Statement ofEnergy Performance
1
Least Efficient
50
Median
Buildings with a score of75 or higher may qualifyfor EPA’s ENERGY STAR.
I certify that the information contained within this statement is accurate and in accordance with U.S.Environmental Protection Agency’s measurement standards, found at energystar.gov
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX D
Appendix D
Page 1 of 8
AC UnitsTag
Unit Type Split System Rooftop Units Split System
Qty 1 2 1
Location Roof Roof Roof
Area Served Classroom 6 MPR/Café Music Room
Manufacturer 900+ YorkInternational Comfort
Products Corp.
Model # 61-7-40A DM120N15N4AAA3 HAC030AKA1
Serial # 28805142472 NOD5851218 1011016563
Cooling Type DX, R-22 DX, R-22 DX, R-22
Cooling Capacity (Tons) 2 Tons 10 Tons 2.5 Ton
Cooling Efficiency (SEER/EER)
10 SEER 9 EER 10 SEER
Heating Type N/A Gas Fired HX N/A
Heating Input (MBH) N/A 180 MBH N/A
Efficiency N/A 80 N/A
Fuel N/A Natural Gas N/A
Approx Age 8 16 1
ASHRAE Service Life 15 15 15
Remaining Life 7 (1) 14
Comments
Note:
MAJOR EQUIPMENT LISTConcord Engineering Group
Loring Flemming Elementary School
"N/A" = Not Applicable. "-" = Info Not Available
Appendix D
Page 2 of 8
AC UnitsTag
Unit Type
Qty
Location
Area Served
Manufacturer
Model #
Serial #
Cooling Type
Cooling Capacity (Tons)
Cooling Efficiency (SEER/EER)
Heating Type
Heating Input (MBH)
Efficiency
Fuel
Approx Age
ASHRAE Service Life
Remaining Life
Comments
Note:
"N/A" = Not Applicable. "-" = Info Not Available
Rooftop Units Split System
4 1
Roof Roof
Inner Classrooms Older Wing
Classroom 5
TraneRheem-Ruud Weather
King
THC036A4R0A0YD10 13AJA30A01
3281008322 7654W480910088
DX, R-22 DX, R-22
3 Tons 2.5 Tons
12.5 SEER 13 SEER
N/A N/A
N/A N/A
N/A N/A
N/A N/A
9 4
15 15
6 11
Appendix D
Page 3 of 8
BoilersTag B-1 B-2 B-3
Unit Type Cast Iron Sectional Cast Iron Sectional Cast Iron Sectional
Qty 1 1 1
Location Boiler Room Boiler Room Boiler Room
Area Served Hot Water Loop Hot Water Loop Hot Water Loop
Manufacturer Weil McLain Weil Mclain Weil McLain
Model # WCRI-G-12 WCRI-G-12 WCR2-5-15
Serial # - - -
Input Capacity (Btu/Hr) 1,703 1,010 1,701
Rated Output Capacity (Btu/Hr)
1,358 810 1,413
Approx. Efficiency % 75.0% 75.0% 83.1%
Fuel Natural Gas Natural Gas Natural Gas
Approx Age 25 25 4
ASHRAE Service Life 35 35 35
Remaining Life 10 10 31
Comments
Note:
MAJOR EQUIPMENT LIST
Concord Engineering Group
Loring Flemming Elementary School
"N/A" = Not Applicable. "-" = Info Not Available
Appendix D
Page 4 of 8
Cooling TowerTag CH-1 CH-2
Unit Type Air Cooled Chiller Air Cooled Chiller
Qty 1 1
Location Outside Outside
Area Served Chilled Water Loop Chilled Water Loop
Manufacturer Trane Trane
Model # CGAA4001FALA No Tag
Serial # L6D717794 No Tag
Refrigerant - No Tag
Cooling Capacity (Tons) 40 Tons No Tag
Cooling Efficiency (KW/Ton)
- No Tag
Volts / Phase / Hz 460 No Tag
Fuel - No Tag
Chilled Water GPM / ΔT - No Tag
Condenser Water GPM / ΔT
- No Tag
Approx Age 18 18
ASHRAE Service Life 20 20
Remaining Life 2 2
Comments
Note:
MAJOR EQUIPMENT LISTConcord Engineering Group
Loring Flemming Elementary School
"N/A" = Not Applicable. "-" = Info Not Available
Appendix D
Page 5 of 8
Domestic Water HeatersTag
Unit TypeGas Fired Domestic Hot Water Heater
Qty 1
Location Boiler Room
Area Served Domestic Loop
Manufacturer Bradford White Corp.
Model # D100L2503NA
Serial # GF13536951
Size (Gallons) 100
Input Capacity (MBH/KW)
250
Recovery (Gal/Hr) 2428
Efficiency % 80%
Fuel Natural Gas
Approx Age 8
ASHRAE Service Life 12
Remaining Life 4
Comments
Note:
MAJOR EQUIPMENT LIST
Concord Engineering Group
Loring Flemming Elementary School
"N/A" = Not Applicable. "-" = Info Not Available
Appendix D
Page 6 of 8
PumpsTag P-7,8 P-5,6 P-9, 10
Unit TypeBase Mounted End
SuctionBase Mounted End
SuctionBase Mounted End
Suction
Qty 2 2 2
Location Pump Room Pump Room Pump Room
Area Served Hot Water Loop Hot Water Loop Hot Water Loop
Manufacturer Armstrong Pump Armstrong Pump Armstrong Pump
Model # 4080 4080 4030
Serial # 143512 - L43510
Horse Power 3 10 2
Flow 106 GPM @ 63 FTHD 276 GPM @ 76 FTHD 207 GPM @ 20 FTHD
Motor Info Marathon Electric Marathon Electric Marathon Electric
Electrical Power 208-230/460 208-230/460 208-230/460
RPM 1730 1745 1740
Motor Efficiency % 81.5% 86.5% 81.50%
Approx Age 20 20 20
ASHRAE Service Life 20 20 20
Remaining Life 0 0 0
Comments
Note:
MAJOR EQUIPMENT LISTConcord Engineering Group
Loring Flemming Elementary School
"N/A" = Not Applicable. "-" = Info Not Available
Appendix D
Page 7 of 8
PumpsTag
Unit Type
Qty
Location
Area Served
Manufacturer
Model #
Serial #
Horse Power
Flow
Motor Info
Electrical Power
RPM
Motor Efficiency %
Approx Age
ASHRAE Service Life
Remaining Life
Comments
Note:
"N/A" = Not Applicable. "-" = Info Not Available
P-11 P-12 P-3,4Base Mounted End
SuctionBase Mounted End
SuctionBase Mounted End
Suction
1 1 2
Pump Room Pump Room Pump Room
Hot Water Loop Hot Water Loop Cold Water Supply
Armstrong Pump Armstrong Pump Aurura Pump
- C072B 3-41A
143509 143508 75 10781-2
1 1 5
82 GPM @ 20FTHD 82 GPM @ 20 FTHD 112 GPM @ 86 FTHD
Marathon Electric US Electric Motor US Electric Motor
208-230/460 230/460 230
1730 1755 3480
77.0% 85.5% 85.5%
20 20 20
20 20 20
0 0 0
Appendix D
Page 8 of 8
PumpsTag
Unit Type
Qty
Location
Area Served
Manufacturer
Model #
Serial #
Horse Power
Flow
Motor Info
Electrical Power
RPM
Motor Efficiency %
Approx Age
ASHRAE Service Life
Remaining Life
Comments
Note:
"N/A" = Not Applicable. "-" = Info Not Available
P-1,2Base Mounted End
Suction
2
Pump Room
Boiler circulation Pumps
Armstrong pump
-
-
1
-
Marathon Electric
208-230/460
1730
77.0%
20
20
0
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX E
CEG Project #:
Facility Name:
Address:
City, State, Zip
Fixture Reference #
LocationAverage
Burn Hours
DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Work Description Equipment DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Energy Savings,
kW
Energy Savings,
kWh
Energy Savings, $
Control Ref #
Controls DescriptionQty of
Controls
Hour Reduction
%
Energy Savings,
kWh
Energy Savings, $
35 Classroom 1 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
35 Classroom 2 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
9 Closet 1/2 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 33 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 25 0.01 8 $1 0 No New Controls 1 0.0% 0 $0
9 Closet 2/3 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 33 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 25 0.01 8 $1 0 No New Controls 0 0.0% 0 $0
35 Classroom 3 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
35 Classroom 4 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
9 Closet 3/4 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 33 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 25 0.01 8 $1 0 No New Controls 0 0.0% 0 $0
36 Hallway for CR1-4 30001-Lamp 4 Foot T12
Magnetic Cove Lighting1 44 6 0.26 792 Re-ballast & re-lamp
Sylvania Ballast QHE1x32T8/UNV-ISL-SC
Sylvania LampFO28/841/SS/ECO
1 25 6 0.15 450 0.11 342 $52 0 No New Controls 0 0.0% 0 $0
7 Hallway for CR1-4 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 6 0.33 990 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 6 0.29 882 0.04 108 $16 0 No New Controls 0 0.0% 0 $0
35 Kindergarten 1 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
9 Kindergarten 1 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 2 0.11 286 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 2 0.08 218 0.03 68 $10 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 44 $7
37 Kindergarten 1 Toilet 12002-Lamp T8 F17 4100K
2x2 Surface Mount Prismatic Lens
2 55 1 0.06 66 Existing to Remain 0 2 55 0 0.06 66 0.00 0 $0 0 No New Controls 0 0.0% 0 $0
25Kindergarten 1
Storage600
2-Lamp T8 F032 4100k 1x4 Surface Mount No Lens
2 55 3 0.17 99 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 3 0.13 76 0.04 23 $4 0 No New Controls 0 0.0% 0 $0
35 Kindergarten 2 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
9 Kindergarten 2 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 143 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 109 0.01 34 $5 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 22 $3
37 Kindergarten 2 Toilet 12002-Lamp T8 F17 4100K
2x2 Surface Mount Prismatic Lens
2 55 1 0.06 66 Existing to Remain 0 2 55 0 0.06 66 0.00 0 $0 0 No New Controls 0 0.0% 0 $0
35 Kindergarten 3 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
9 Kindergarten 3 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 143 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 109 0.01 34 $5 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 22 $3
37 Kindergarten 3 Toilet 12002-Lamp T8 F17 4100K
2x2 Surface Mount Prismatic Lens
2 55 1 0.06 66 Existing to Remain 0 2 55 0 0.06 66 0.00 0 $0 0 No New Controls 0 0.0% 0 $0
35 Kindergarten 4 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
Retrofit Energy SavingsExisting Fixtures Proposed Fixtures Retrofit
9C12010
Loring Flemming Elementary
135 Little Gloucester RD
Blackwood, NJ 08012
Proposed Lighting Controls
Appendix E - Lighting Audit - Loring Glemming Elementary School.xlsx Page 1
Fixture Reference #
LocationAverage
Burn Hours
DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Work Description Equipment DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Energy Savings,
kW
Energy Savings,
kWh
Energy Savings, $
Control Ref #
Controls DescriptionQty of
Controls
Hour Reduction
%
Energy Savings,
kWh
Energy Savings, $
Retrofit Energy SavingsExisting Fixtures Proposed Fixtures Retrofit Proposed Lighting Controls
38 Kindergarten 4 26001-Lamp 4 foot T8 F032 4100k Surface Mount
Prismatic Lens1 30 2 0.06 156 Re-lamp
Sylvania LampFO28/841/SS/ECO
1 25 2 0.05 130 0.01 26 $4 4Dual Technology
Occupancy Sensor - Remote Mnt.
1 20.0% 26 $4
37 Kindergarten 4 Toilet 12002-Lamp T8 F17 4100K
2x2 Surface Mount Prismatic Lens
2 55 1 0.06 66 Existing to Remain 0 2 55 0 0.06 66 0.00 0 $0 0 No New Controls 0 0.0% 0 $0
25Kindergarten 4
Storage600
2-Lamp T8 F032 4100k 1x4 Surface Mount No Lens
2 55 4 0.22 132 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 4 0.17 101 0.05 31 $5 0 No New Controls 0 0.0% 0 $0
35 Classroom 5 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
35 Classroom 6 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
7 Classroom 6 Storage 600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 2 0.11 66 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 2 0.10 59 0.01 7 $1 0 No New Controls 0 0.0% 0 $0
35 Classroom 7 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
2 Classroom 6/7 Storage 6004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 1 0.11 65 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 1 0.08 50 0.02 14 $2 0 No New Controls 0 0.0% 0 $0
7 Classroom 7 Storage 600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 2 0.11 66 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 2 0.10 59 0.01 7 $1 0 No New Controls 0 0.0% 0 $0
35 Classroom 8 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
35 Classroom 9 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
35 Classroom 10 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
9 Coats 9/10 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 33 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 25 0.01 8 $1 0 No New Controls 0 0.0% 0 $0
35 Classroom 11 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
25 Storage 10/11 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 2 0.11 66 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
9 Coats 11/12 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 33 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 25 0.01 8 $1 0 No New Controls 0 0.0% 0 $0
35 Classroom 12 26003-Lamp T8 FO32 4100K
2x4 Surface Mount Prismatic Lens
3 83 16 1.33 3,453 Relamp, De-lamp center Lamp,
& Defeat SocketSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.66 1,706 $259 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
7 Hallway for CR 9-12 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 5 0.28 825 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 5 0.25 735 0.03 90 $14 0 No New Controls 0 0.0% 0 $0
36 Hallway for CR 9-12 30001-Lamp 4 Foot T12
Magnetic Cove Lighting1 44 6 0.26 792 Re-ballast & re-lamp
Sylvania Ballast QHE1x32T8/UNV-ISL-SC
Sylvania LampFO28/841/SS/ECO
1 25 6 0.15 450 0.11 342 $52 0 No New Controls 0 0.0% 0 $0
25 Main Office - Office 26002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 1 0.06 143 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 1 0.04 109 0.01 34 $5 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 22 $3
40Main Office - Work
Room2600
2-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens2 55 1 0.06 143 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 1 0.04 109 0.01 34 $5 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 22 $3
Appendix E - Lighting Audit - Loring Glemming Elementary School.xlsx Page 2
Fixture Reference #
LocationAverage
Burn Hours
DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Work Description Equipment DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Energy Savings,
kW
Energy Savings,
kWh
Energy Savings, $
Control Ref #
Controls DescriptionQty of
Controls
Hour Reduction
%
Energy Savings,
kWh
Energy Savings, $
Retrofit Energy SavingsExisting Fixtures Proposed Fixtures Retrofit Proposed Lighting Controls
41Main Office -
Restroom1200
2-Lamp T8 F17 4100K 2 Foor Side Wall Mount Prismatic Lens Vanity
Fixture
2 55 1 0.06 66 Existing to Remain 0 2 55 0 0.06 66 0.00 0 $0 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 13 $2
7 Main Office - Hallway 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 1 0.06 165 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 1 0.05 147 0.01 18 $3 0 No New Controls 0 0.0% 0 $0
7Main Office -
Principal2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 6 0.33 858 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 6 0.29 764 0.04 94 $14 5
Dual Technology Occupancy Sensor - Switch
Mnt.1 20.0% 153 $23
7Main Office -
Conference Room2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 5 0.28 715 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 5 0.25 637 0.03 78 $12 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 127 $19
7Main Office - Vice
Principal2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 4 0.22 572 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 4 0.20 510 0.02 62 $9 5
Dual Technology Occupancy Sensor - Switch
Mnt.1 20.0% 102 $15
40Main Office - File
Room2600
2-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens2 55 1 0.06 143 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 1 0.04 109 0.01 34 $5 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 22 $3
7Main Office - General
Office2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 11 0.61 1,573 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 11 0.54 1,401 0.07 172 $26 0 No New Controls 0 0.0% 0 $0
7 Front Corridor 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 5 0.28 825 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 5 0.25 735 0.03 90 $14 0 No New Controls 0 0.0% 0 $0
7 Main Lobby 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 5 0.28 825 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 5 0.25 735 0.03 90 $14 0 No New Controls 0 0.0% 0 $0
39 Main Lobby 3000High Hat 60 Watt
Incandescent1 60 4 0.24 720 Re-lamp
Energy Star Rated, Dimmable 13w CFL Lamp
1 13 4 0.05 156 0.19 564 $86 0 No New Controls 0 0.0% 0 $0
7 Nurse - Waiting 2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 2 0.11 286 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 2 0.10 255 0.01 31 $5 0 No New Controls 0 0.0% 0 $0
25 Nurse - Storage 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 1 0.06 33 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 1 0.04 25 0.01 8 $1 0 No New Controls 0 0.0% 0 $0
7 Nurse - Office 2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 8 0.44 1,144 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 8 0.39 1,019 0.05 125 $19 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 204 $31
42 Nurse - Rest Area 26002-Lamp T8 3 foot Direct/
Indirect 25 Watt Wall Mount
2 48 3 0.14 374 Existing to Remain 0 2 48 0 0.14 374 0.00 0 $0 0 No New Controls 0 0.0% 0 $0
41 Nurse - Toilet 1200
2-Lamp T8 F17 4100K 2 Foor Side Wall Mount Prismatic Lens Vanity
Fixture
2 55 2 0.11 132 Existing to Remain 0 2 55 0 0.11 132 0.00 0 $0 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 26 $4
7Nurse - Examination
Room2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 7 0.39 1,001 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 7 0.34 892 0.04 109 $17 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 178 $27
41Teacher Lounge Men
Toilet1200
2-Lamp T8 F17 4100K 2 Foor Side Wall Mount Prismatic Lens Vanity
Fixture
2 55 1 0.06 66 Existing to Remain 0 2 55 0 0.06 66 0.00 0 $0 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 13 $2
41Teacher Lounge Female Toilet
1200
2-Lamp T8 F17 4100K 2 Foor Side Wall Mount Prismatic Lens Vanity
Fixture
2 55 1 0.06 66 Existing to Remain 0 2 55 0 0.06 66 0.00 0 $0 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 13 $2
7 Teacher Lounge 2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 7 0.39 1,001 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 7 0.34 892 0.04 109 $17 4
Dual Technology Occupancy Sensor -
Remote Mnt.0.5 20.0% 178 $27
9 Teacher Lounge 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 143 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 109 0.01 34 $5 4
Dual Technology Occupancy Sensor -
Remote Mnt.0.5 20.0% 22 $3
7 Media Center 2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 17 0.94 2,431 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 17 0.83 2,166 0.10 265 $40 4
Dual Technology Occupancy Sensor -
Remote Mnt.0.3333 20.0% 433 $66
Appendix E - Lighting Audit - Loring Glemming Elementary School.xlsx Page 3
Fixture Reference #
LocationAverage
Burn Hours
DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Work Description Equipment DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Energy Savings,
kW
Energy Savings,
kWh
Energy Savings, $
Control Ref #
Controls DescriptionQty of
Controls
Hour Reduction
%
Energy Savings,
kWh
Energy Savings, $
Retrofit Energy SavingsExisting Fixtures Proposed Fixtures Retrofit Proposed Lighting Controls
33 Media Center 26002-Lamp T8 F032 4100k 1x4 Recessed Parabolic
Lens2 55 12 0.66 1,716 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 12 0.50 1,310 0.16 406 $62 4Dual Technology
Occupancy Sensor - Remote Mnt.
0.3333 20.0% 262 $40
34 Media Center 26004-Lamp T8 FO32 4100K 2x4 Recessed Parabolic
Lens4 108 16 1.73 4,493 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 16 1.34 3,494 0.38 998 $152 4Dual Technology
Occupancy Sensor - Remote Mnt.
0.3333 20.0% 699 $106
2 Audio Visual 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 4 0.43 1,123 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 4 0.34 874 0.10 250 $38 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 175 $27
2 Spec ed 1 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 4 0.43 1,123 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 4 0.34 874 0.10 250 $38 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 175 $27
2 Library Office 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 2 0.22 562 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 2 0.17 437 0.05 125 $19 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 87 $13
2 Book Storage 6004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 2 0.22 130 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 2 0.17 101 0.05 29 $4 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 20 $3
2 Spec ed 2 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 4 0.43 1,123 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 4 0.34 874 0.10 250 $38 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 175 $27
2 Spec ed 3 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 4 0.43 1,123 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 4 0.34 874 0.10 250 $38 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 175 $27
9 Girls Restroom 12002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 5 0.28 330 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 5 0.21 252 0.07 78 $12 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 50 $8
29 Girls Restroom 1200
2-Lamp T8 F032 4100k 1x4 Side Wall Mount Prismatic Lens Vanity
Fixture
2 55 2 0.11 132 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 2 0.08 101 0.03 31 $5 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 20 $3
25 Janitor Closet 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 2 0.11 66 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
2 Spec ed 4 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 4 0.43 1,123 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 4 0.34 874 0.10 250 $38 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 175 $27
2 Spec ed 5 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 4 0.43 1,123 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 4 0.34 874 0.10 250 $38 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 175 $27
25 Storage 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 2 0.11 66 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
9 Boys Restroom 12002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 4 0.22 264 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 4 0.17 202 0.05 62 $9 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 40 $6
32 Boys Restroom 12001-Lamp T8 F032 4100k Surface Mount No Lens
1 30 1 0.03 36 Re-lampSylvania Lamp
FO28/841/SS/ECO1 25 1 0.03 30 0.01 6 $1 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 6 $1
27 Classroom 13 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 14 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 15 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 16 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
7 Hallway for CR 13-16 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 6 0.33 990 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 6 0.29 882 0.04 108 $16 0 No New Controls 0 0.0% 0 $0
Appendix E - Lighting Audit - Loring Glemming Elementary School.xlsx Page 4
Fixture Reference #
LocationAverage
Burn Hours
DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Work Description Equipment DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Energy Savings,
kW
Energy Savings,
kWh
Energy Savings, $
Control Ref #
Controls DescriptionQty of
Controls
Hour Reduction
%
Energy Savings,
kWh
Energy Savings, $
Retrofit Energy SavingsExisting Fixtures Proposed Fixtures Retrofit Proposed Lighting Controls
27 Classroom 17 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 18 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 19 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 20 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 21 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 22 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 23 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
27 Classroom 24 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 16 0.88 2,288 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 16 0.67 1,747 0.21 541 $82 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 349 $53
7 Hallway for CR 17-24 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 10 0.55 1,650 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 10 0.49 1,470 0.06 180 $27 0 No New Controls 0 0.0% 0 $0
9 Classroom 25 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 26 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 27 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 28 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
2New Wing Boys
Restroom1200
4-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 2 0.22 259 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 2 0.17 202 0.05 58 $9 5Dual Technology
Occupancy Sensor - Switch Mnt.
0.5 20.0% 40 $6
7New Wing Boys
Restroom1200
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 1 0.06 66 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 1 0.05 59 0.01 7 $1 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 12 $2
2New Wing Gorls
Restroom1200
4-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 2 0.22 259 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 2 0.17 202 0.05 58 $9 5Dual Technology
Occupancy Sensor - Switch Mnt.
0.5 20.0% 40 $6
7New Wing Gorls
Restroom1200
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 1 0.06 66 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 1 0.05 59 0.01 7 $1 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 12 $2
25 New Wing Janitor 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 2 0.11 66 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
27 New Wing Storage 1 6002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 2 0.11 66 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
27 New Wing Storage 2 6002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 2 0.11 66 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
7 New Wing Hallway 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 26 1.43 4,290 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 26 1.27 3,822 0.16 468 $71 0 No New Controls 0 0.0% 0 $0
Appendix E - Lighting Audit - Loring Glemming Elementary School.xlsx Page 5
Fixture Reference #
LocationAverage
Burn Hours
DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Work Description Equipment DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Energy Savings,
kW
Energy Savings,
kWh
Energy Savings, $
Control Ref #
Controls DescriptionQty of
Controls
Hour Reduction
%
Energy Savings,
kWh
Energy Savings, $
Retrofit Energy SavingsExisting Fixtures Proposed Fixtures Retrofit Proposed Lighting Controls
9 Classroom 29 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 30 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 31 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 32 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 33 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 34 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 35 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Classroom 36 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 20 1.10 2,860 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 20 0.84 2,184 0.26 676 $103 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 437 $66
9 Music 26002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 24 1.32 3,432 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 24 1.01 2,621 0.31 811 $123 4
Dual Technology Occupancy Sensor -
Remote Mnt.1 20.0% 524 $80
9 Boys Restroom 12002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 2 0.11 132 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 2 0.08 101 0.03 31 $5 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 20 $3
29 Boys Restroom 1200
2-Lamp T8 F032 4100k 1x4 Side Wall Mount Prismatic Lens Vanity
Fixture
2 55 1 0.06 66 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 50 0.01 16 $2 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 10 $2
7 Music/Art Hallway 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 7 0.39 1,155 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 7 0.34 1,029 0.04 126 $19 0 No New Controls 0 0.0% 0 $0
27 Art Room 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 18 0.99 2,574 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 18 0.76 1,966 0.23 608 $92 4
Dual Technology Occupancy Sensor -
Remote Mnt.0.33333 20.0% 393 $60
31 Art Room 26002-Lamp T8 F032 4100k
Direct/ Indirect Wall Mount2 55 4 0.22 572 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 4 0.17 437 0.05 135 $21 4Dual Technology
Occupancy Sensor - Remote Mnt.
0.33333 20.0% 87 $13
30 Art Room 26002-Lamp T8 F032 4100k 1x4 Recessed Prismatic
Lens2 55 6 0.33 858 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 6 0.25 655 0.08 203 $31 4Dual Technology
Occupancy Sensor - Remote Mnt.
0.33333 20.0% 131 $20
9 Girls Restroom 12002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 66 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 50 0.01 16 $2 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 10 $2
29 Girls Restroom 1200
2-Lamp T8 F032 4100k 1x4 Side Wall Mount Prismatic Lens Vanity
Fixture
2 55 1 0.06 66 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 50 0.01 16 $2 5
Dual Technology Occupancy Sensor - Switch
Mnt.0.5 20.0% 10 $2
25 Pump Room 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 7 0.39 231 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 7 0.29 176 0.09 55 $8 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 35 $5
25 Storage 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 4 0.22 132 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 4 0.17 101 0.05 31 $5 0 No New Controls 0 0.0% 0 $0
9 Storage 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 4 0.22 132 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 4 0.17 101 0.05 31 $5 0 No New Controls 0 0.0% 0 $0
9 Storage 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 2 0.11 66 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
Appendix E - Lighting Audit - Loring Glemming Elementary School.xlsx Page 6
Fixture Reference #
LocationAverage
Burn Hours
DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Work Description Equipment DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Energy Savings,
kW
Energy Savings,
kWh
Energy Savings, $
Control Ref #
Controls DescriptionQty of
Controls
Hour Reduction
%
Energy Savings,
kWh
Energy Savings, $
Retrofit Energy SavingsExisting Fixtures Proposed Fixtures Retrofit Proposed Lighting Controls
25 Mechanical Room 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 4 0.22 132 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 4 0.17 101 0.05 31 $5 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 20 $3
25 Outdoor Storage 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 2 0.11 66 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
25 MPR Storage 1 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 1 0.06 33 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 1 0.04 25 0.01 8 $1 0 No New Controls 0 0.0% 0 $0
25 MPR Storage 2 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 2 0.11 66 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
27 Stage 26002-Lamp T8 F032 4100k
1x4 Pendant Mount Prismatic Lens
2 55 6 0.33 858 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 6 0.25 655 0.08 203 $31 0 No New Controls 0 0.0% 0 $0
25 Stage Office 26002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 1 0.06 143 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 1 0.04 109 0.01 34 $5 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 22 $3
25 Stage Storage 6002-Lamp T8 F032 4100k
1x4 Surface Mount No Lens2 55 1 0.06 33 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 1 0.04 25 0.01 8 $1 0 No New Controls 0 0.0% 0 $0
9Kitchen Back Hall
Area2600
2-Lamp T8 FO32 4100K 1x4 Surface Mount
Prismatic Wrap2 55 4 0.22 572 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 4 0.17 437 0.05 135 $21 0 No New Controls 0 0.0% 0 $0
9 Kitchen Storage 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 2 0.11 66 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 2 0.08 50 0.03 16 $2 0 No New Controls 0 0.0% 0 $0
9 Kitchen Electric 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 33 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 25 0.01 8 $1 0 No New Controls 0 0.0% 0 $0
9 Kitchen Storage 6002-Lamp T8 FO32 4100K
1x4 Surface Mount Prismatic Wrap
2 55 1 0.06 33 Re-lampSylvania Lamp
FO28/841/SS/ECO2 42 1 0.04 25 0.01 8 $1 0 No New Controls 0 0.0% 0 $0
28 Kitchen Storage 6002 Lamp 17W CFL Ceiling
Mount Globe2 34 1 0.03 20 Existing to Remain 0 2 34 0 0.03 20 0.00 0 $0 0 No New Controls 0 0.0% 0 $0
2 Kitchen 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 12 1.30 3,370 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 12 1.01 2,621 0.29 749 $114 0 No New Controls 0 0.0% 0 $0
7 Kitchen 2600
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 6 0.33 858 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 6 0.29 764 0.04 94 $14 0 No New Controls 0 0.0% 0 $0
2 Dish Washing 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 3 0.32 842 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 3 0.25 655 0.07 187 $28 0 No New Controls 0 0.0% 0 $0
2 Kitchen Office 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 1 0.11 281 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 1 0.08 218 0.02 62 $9 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 44 $7
2 Cafeteria 26004-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens4 108 24 2.59 6,739 Re-lamp
Sylvania LampFO28/841/SS/ECO
4 84 24 2.02 5,242 0.58 1,498 $228 0 No New Controls 0 0.0% 0 $0
4 Teacher Dining 26003-Lamp T8 FO32 4100K 2x4 Recessed Prismatic
Lens3 83 6 0.50 1,295
Relamp, De-lamp center Lamp, & Defeat Socket
Sylvania LampFO28/841/SS/ECO
2 42 6 0.25 655 0.25 640 $97 4Dual Technology
Occupancy Sensor - Remote Mnt.
1 20.0% 131 $20
9Teacher Dining
Restroom1200
2-Lamp T8 FO32 4100K 1x4 Surface Mount
Prismatic Wrap2 55 1 0.06 66 Re-lamp
Sylvania LampFO28/841/SS/ECO
2 42 1 0.04 50 0.01 16 $2 5Dual Technology
Occupancy Sensor - Switch Mnt.
1 20.0% 10 $2
7 Back Lobby MPR 3000
2-Lamp T8 FBO32 4100K U Tube
2x2 Recessed Prismatic Lens
2 55 4 0.22 660 Re-lampSylvania Lamp
FBO30/841XP/6//SS/ECO2 49 4 0.20 588 0.02 72 $11 0 No New Controls 0 0.0% 0 $0
TOTAL 1,125 73.7 183,456 1,112 51.8 128,345 21.9 55,111 $8,377 81 20,455 $3,109
Appendix E - Lighting Audit - Loring Glemming Elementary School.xlsx Page 7
CEG Project #:
Facility Name:
Address:
City, State, Zip
Fixture Reference #
LocationAverage
Burn Hours
DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Work Description Equipment DescriptionLamps per
FixtureWatts per
FixtureQty of
FixturesTotal kW
Usage kWh/Yr
Energy Savings,
kW
Energy Savings,
kWh
Energy Savings, $
Control Ref #
Controls DescriptionQty of
Controls
Hour Reduction
%
Energy Savings,
kWh
Energy Savings, $
26 Multi-Purpose Room 2600 400W MH Pendant Mount 1 465 20 9.30 24,180 Re-ballast & re-lamp2x4 54w T5HO 6 Lamp
w/Prismatic Lens6 354 20 7.08 18,408 2.22 5,772 $877 0 No New Controls 0 0.0% 0 $0
TOTAL 20 9.3 24,180 20 7.1 18,408 2.2 5,772 $877 0 0 $0
Retrofit Energy Savings Proposed Lighting Controls
9C12010
Loring Flemming Elementary
135 Little Gloucester RD
Blackwood, NJ 08012
Existing Fixtures Proposed Fixtures Retrofit
Appendix E - Lighting Audit - Loring Glemming Elementary School.xlsx Page 8
Appendix Energy Audit
Concord Engineering Group, Inc.
APPENDIX F
Appendix FPage 1 of 2
Location Description
Area (Sq FT) Panel Qty
Panel Sq Ft
Panel Total Sq
FtTotal KWDC
Total Annual kWh
Total KWAC
Panel Weight
(41.9 lbs) W/SQFT
Loring-Flemming Elementary School
12250SHARP
NU-U235F2500 17.5 8,770 117.50 143,544 95.2 20,950 13.40
.= Proposed PV Layout
Notes:
1. Estimated kWH based on the National Renewable Energy Laboratory PVWatts Version 1 Calculator Program.
Appendix FPage 2 of 2
Project Name: LGEA Solar PV Project - Loring-Flemming Elementary School
Location: Blackwood, NjDescription: Photovoltaic System 100% Financing - 15 year
Simple Payback Analysis
Total Construction Cost $716,530Annual kWh Production 143,544
Annual Energy Cost Reduction $21,819Average Annual SREC Revenue $27,429
Simple Payback: Years
Life Cycle Cost AnalysisAnalysis Period (years): 15 Financing %: 100%
Discount Rate: 3% Maintenance Escalation Rate: 3.0%Average Energy Cost ($/kWh) $0.152 Energy Cost Escalation Rate: 3.0%
Financing Rate: 6.00% Average SREC Value ($/kWh) $0.191Period Additional Energy kWh Energy Cost Additional SREC Interest Loan Net Cash Cumulative
Cash Outlay Production Savings Maint Costs Revenue Expense Principal Flow Cash Flow0 $0 0 0 0 $0 0 0 0 01 $0 143,544 $21,819 $0 $35,886 $42,165 $30,393 ($14,853) ($14,853)2 $0 142,826 $22,473 $0 $35,707 $40,290 $32,267 ($14,378) ($29,231)3 $0 142,112 $23,147 $0 $35,528 $38,300 $34,258 ($13,882) ($43,114)4 $0 141,402 $23,842 $0 $35,350 $36,187 $36,371 ($13,366) ($56,479)5 $0 140,695 $24,557 $1,449 $35,174 $33,944 $38,614 ($14,276) ($70,756)6 $0 139,991 $25,294 $1,442 $27,998 $31,563 $40,995 ($20,708) ($91,463)7 $0 139,291 $26,053 $1,435 $27,858 $29,034 $43,524 ($20,082) ($111,545)8 $0 138,595 $26,834 $1,428 $27,719 $26,350 $46,208 ($19,432) ($130,977)9 $0 137,902 $27,639 $1,420 $27,580 $23,500 $49,058 ($18,759) ($149,736)10 $0 137,212 $28,468 $1,413 $20,582 $20,474 $52,084 ($24,921) ($174,657)11 $0 136,526 $29,322 $1,406 $20,479 $17,261 $55,297 ($24,163) ($198,820)12 $0 135,844 $30,202 $1,399 $20,377 $13,851 $58,707 ($23,378) ($222,198)13 $0 135,164 $31,108 $1,392 $20,275 $10,230 $62,328 ($22,567) ($244,765)14 $0 134,488 $32,041 $1,385 $13,449 $6,385 $66,172 ($28,453) ($273,218)15 $0 133,816 $33,003 $1,378 $13,382 $2,304 $70,254 ($27,552) ($300,770)
Totals: 2,079,408 $405,804 $15,548 $397,343 $371,838 $716,530 ($300,770) ($2,112,581)Net Present Value (NPV)
Photovoltaic System 100% Financing - 15 year
14.55
($219,152)