global pharmaceutical manufacturer - quality road & jurong sites – singapore
DESCRIPTION
Pharma Manufacturing & laboratoriesTRANSCRIPT
![Page 1: Global Pharmaceutical Manufacturer - Quality Road & Jurong sites – Singapore](https://reader036.vdocuments.site/reader036/viewer/2022081816/55875d39d8b42ae7788b46a9/html5/thumbnails/1.jpg)
EECO2 Case Study
Global Pharmaceutical Manufacturer - Quality Road & Jurong sites – Singapore
Pharma Manufacturing & laboratories
![Page 2: Global Pharmaceutical Manufacturer - Quality Road & Jurong sites – Singapore](https://reader036.vdocuments.site/reader036/viewer/2022081816/55875d39d8b42ae7788b46a9/html5/thumbnails/2.jpg)
EEC02 LimitedSuite 9, The GreenFountain Street, MacclesfieldCheshire, SK10 1JNTel: +44 (0) 1625 660 717 |Email: [email protected]
Benefits:
Delivering Global Energy Saving Solutions The core expertise & experience within EECO2 is not the usual Consultant format as we all come from a design & build background, commercially grounded and totally focused upon the identification & cost effective delivery of identified energy savings. Core Objective of all services:Use our acquired experience & knowledge to provide cost effective, energy & emission reduction solutions from initial opportunity identification through implementation & verification of savings delivered globally.
Project Benefits:
Energy savings delivered = 2.2m kWhr/pa Energy cost savings = S$347,000 Emissions reduction = 985 te CO2 Simple pay back = 1.3 years Further energy savings identified = 2.5m kWhr/pa
![Page 3: Global Pharmaceutical Manufacturer - Quality Road & Jurong sites – Singapore](https://reader036.vdocuments.site/reader036/viewer/2022081816/55875d39d8b42ae7788b46a9/html5/thumbnails/3.jpg)
EEC02 LimitedSuite 9, The GreenFountain Street, MacclesfieldCheshire, SK10 1JNTel: +44 (0) 1625 660 717 |Email: [email protected]
About the Project:
Facility: Pharma Manufacturing & laboratories Issue: Very high energy demand driven by original HVAC design & layout
Brief: Reduce energy demand without compromising on Compliance or Laboratory safety Solution:
Reduce existing air change rates Reduce existing fresh air volume Improve plant operational maintenance Optimise BMS system Recommended upgrading laboratory fume cupboards to VAV Recommended upgrade & control of warehousing Facilities
Conclusion:
EECO2 supported HVAC design review, project scoped out & managed local test & balance & BMS Contractors to complete project – project successfully completed also produced a prioritised Action Plan to implement further savings.
![Page 4: Global Pharmaceutical Manufacturer - Quality Road & Jurong sites – Singapore](https://reader036.vdocuments.site/reader036/viewer/2022081816/55875d39d8b42ae7788b46a9/html5/thumbnails/4.jpg)
Contact Details:
General Enquiries & SalesTel: +44 (0) 1625 660 717Email: [email protected]
Technical SupportTel: +44 (0) 1625 660 717Email: [email protected] EEC02 LimitedSuite 9, The GreenFountain Street, MacclesfieldCheshire, SK10 1JN
Connect with us:
Follow us on Linkedin
Like us on Facebook
Follow us on Twitter
Add us on Google Plus