Effervescent Sachets Manufacturing Area – low relative humidity required

TRANSCRIPT

Page 1: Global Pharmaceutical Manufacturer – Buenos Aires – Argentina

EECO2 Case Study

Global Pharmaceutical Manufacturer– Buenos Aires – Argentina

Effervescent Sachets Manufacturing Area – low relative humidity required

Page 2: Global Pharmaceutical Manufacturer – Buenos Aires – Argentina

EEC02 LimitedSuite 9, The GreenFountain Street, MacclesfieldCheshire, SK10 1JNTel: +44 (0) 1625 660 717 |Email: [email protected]

Benefits:

Delivering Global Energy Saving Solutions The core expertise & experience within EECO2 is not the usual Consultant format as we all come from a design & build background, commercially grounded and totally focused upon the identification & cost effective delivery of identified energy savings. Core Objective of all services:Use our acquired experience & knowledge to provide cost effective, energy & emission reduction solutions from initial opportunity identification through implementation & verification of savings delivered globally.

Benefits:

Energy savings = 1.5m kWhr/pa Energy cost savings = £58,000 Emissions reduction = 686 te CO2 Simple pay back = 11 months

Page 3: Global Pharmaceutical Manufacturer – Buenos Aires – Argentina

EEC02 LimitedSuite 9, The GreenFountain Street, MacclesfieldCheshire, SK10 1JNTel: +44 (0) 1625 660 717 |Email: [email protected]

About the Project:

Facility: Effervescent Sachets Manufacturing Area – low relative humidity required Issue: Very high energy demand driven by original HVAC design & unable to meet Product critical conditions during summer months Brief: Reduce energy demand without compromising on product quality or ComplianceSolution: Solution: • Reduce existing air change rates  • Reduce existing fresh air volume • Install new VSD’s to the supply air fans • Replace the existing supply air diffusers to improve air distribution • Re-commission & balance the complete manufacturing areas HVAC system  • Supported upgrade of BMS system, installation of VSD’s • Maintenance upgrade of filtration & control valve replacement • Completed product risk assessments, Engineering Change Control documentation & all required Regulatory documentation covering the changes

Page 4: Global Pharmaceutical Manufacturer – Buenos Aires – Argentina

EEC02 LimitedSuite 9, The GreenFountain Street, MacclesfieldCheshire, SK10 1JNTel: +44 (0) 1625 660 717 |Email: [email protected]

Conclusion and Comments:

Conclusion:EECO2 supported HVAC design review, recommissioned HVAC system & supported BMS & HVAC upgrade also design of new supply air diffusers Site Director commented:The savings delivered during Phase 1 has exceeded our expectations & the quality Team have supported the risk based approach used to deliver the savings. We now move on to Phase 2 upgrade which is much more demanding but the confidence & structure knowledge we gained during phase 1 we help us deliver our target for 2011.

Page 5: Global Pharmaceutical Manufacturer – Buenos Aires – Argentina

Contact Details:

General Enquiries & SalesTel: +44 (0) 1625 660 717Email: [email protected]

Technical SupportTel: +44 (0) 1625 660 717Email: [email protected] EEC02 LimitedSuite 9, The GreenFountain Street, MacclesfieldCheshire, SK10 1JN

Connect with us:

Follow us on Linkedin

Like us on Facebook

Follow us on Twitter

Add us on Google Plus