gilbert road...2011-2015 2015-2016 2016-2019 late spring 2019 2019 project schedule 202 university...
TRANSCRIPT
LRT4
39
4
About the ProjectThe Gilbert Road Extension will extend light rail on Main Street from Mesa Drive to Gilbert Road in Mesa. At Gilbert Road, there are significant transit connections and the ability to serve the growing transit demand in the East Valley. This extension will attract new riders and increase development opportunities in central Mesa.
PROJECT STATUS
NEXT STEPS
• Approximately 10,000 linear feet of utility lines (communications, water, electrical and waste water) have been installed.
• A community celebration was held in the spring to showcase local businesses.
• The Shop on Rewards program launched in the fall to encourage the community to shop local.
• Impacted business owners can learn more about Valley Metro construction business assistance programs by visiting valleymetro.org/community_outreach.
• A public meeting to update the community on the project art and urban design will take place in August 2017.
MILES STATIONS
2PARK-AND-RIDE/ TRANSIT CENTER
1
Underground utility work will be completed in late 2017. Construction will then begin on the roadway to make way for track installation. The extension is scheduled to open in late spring 2019.
1.9
T I T L E
T Y P E
GILBERT ROAD
LIGHT RAIL EXTENSION
FACT SHEET / Q2 2017valleymetro.org/gilbertroad
Michael BookCommunity Outreach Coordinator
/valleymetro
/valleymetroconstruction
Join the Gilbert Road Extension mailing list by contacting Michael Book.
PROJECT FACTS
LRT4
39
4
ROUTE MAP
FACT SHEET / Q2 2017valleymetro.org/gilbertroad
T I T L E
T Y P E
GILBERT ROAD
LIGHT RAIL EXTENSION
PLANNING DESIGN CONSTRUCTION COMPLETION
2011-2015 2016-20192015-2016 LATE SPRING 2019
2019
PROJECT SCHEDULE
202
University Dr
Cou
ntry
Clu
b D
r
Mes
a D
r
Cen
ter S
t
Stap
ley
Dr
Gilb
ert R
d
Lind
say
Rd
Alm
a Sc
hool
Rd
Syca
mor
e
Gre
enfie
ld R
d
Hig
ley
Rd
McKellips Rd
University Dr
Main St
Broadway Rd
Southern AveHar
ris
Dr
Hor
ne
Exte
nsio
n Rd
Superstition Springs
Sycamore/Main St
Gilbert
Rd/Main StMESA
20192019
Park-and-Ride
Transit Center
LEGEND
NValley Metro Rail
Gilbert Road Light Rail Extension
Note: Dates indicate anticipated calendar year openings
Michael BookCommunity Outreach Coordinator
/valleymetro
/valleymetroconstruction
BUDGET
Programmed Expended %Expended Forecast
Construction $120,915,024 $7,392,417 6% $120,915,024
Utilities $5,174,000 $371,814 7% $5,174,000
ROW $14,786,915 $574,517 4% $14,786,915
Public Art $732,189 $78,411 11% $732,189
Design/Management $25,562,383 $15,325,461 60% $25,562,383
Vehicles $16,858,710 $0 0% $16,858,710
TOTAL $184,029,221 $23,742,620 13% $184,029,221
Total budgeted $184,029,221* Excludes Transit Center/OPF Costs
Federal - CMAQ
Federal - STP
Mesa Local Match
City of Mesa TPANS
$9,270,271
$21,392,907
$107,130,157
$46,235,886
FUNDING ($M)