geoff moret, u. idaho jean pan, mojn i&m ecologist research permits
TRANSCRIPT
Geoff Moret, U. Idaho Jean Pan, MOJN I&M Ecologist
Research Permits
Protocol # Parks Total # Permits*
Total # IAR submitted**
Streams & Lakes
1 1 (1 active) 4
SLS 6 4 (2 active) 6
Aridland Springs
5 5 (5 active) 9
IU 7 8*** 8
Current MOJN I&M Research Permits
2
*this includes all permits across all years**this includes all IARs that must be submitted by end of 2012 calendar year***expected number of permits in 2012
Permitting Issues (1)
• Scientific/research permits are issued to individuals rather than to the network• What happens if the permit holder/signer leaves
MOJN I&M (after several years in the case of a long-term permit)?
• Can permits be issued to MOJN I&M?
3
Permitting Issues (2)
• Permit holder must be in the field, so field crews must be named as co-investigators• It is not possible to name field crew if we apply for
permits several months in advance
4
Permitting Issues (3)
• Exact field site locations need to be provided as part of the permit• Some field sites may be visited but rejected for a
variety of factors, thus, the exact # of field sites needed may change
• the exact location of the field site may change (e.g., GPS variation, due to an obstruction)
5
Permitting Issues (4)
• Permits are issued for a fixed length of time, with variations from park to park• Ideally, we would prefer indefinite or long-term
permits (10 or 20 years)• Equipment associated with permit stipulated to be
removed at the expiration of the permit (e.g., permanent markers, monitors)
6
Permitting Issues (5)
• An Investigator Annual Report is Due for Each Permit in Each Park Each Year• Will be 12 per year for aquatic lead• Monitoring occurs on a rotation for some
protocols, so there may be a number of years where an IAR must be submitted where no monitoring is occurring
7
Permitting Issues (6)
• Turnaround time for permit issuance varies greatly, from days to several months
• Permit requirements for application varies greatly across parks
8
Water-Related Permits Time Table
• Nearly all water-related permits have been approved within 1 month of application
• Much faster, when needed (Thank you!)
• No permanent markers, sites in washes, named sites that CR staff have often visited
9
IU Permit Application Time TablePark 1st review of
potential field sites1
Research Permit Application submitted2
Permit Issued
Permit Caveats Notes
DEVA 12/20/11 1/10/12 2/28/12 3 permanent markers/plot, <1/2 in diameter, <8 in tall
Initial permit issued on 2/8/12 with 0 permanent markers
GRBA 12/20/11 3/26/12 Submitted with only initial park review of potential monitoring areas
JOTR 12/20/11 1/10/12 2/28/12 Will need to coordinate sites w/ park archaeologist for clearance
Went through NEPA compliance
LAKE 12/20/11 1/10/12 3/15/12 Permitted for 9 sites: 6 sites, 1 modified site, & 2 training sites3
Only culturally cleared sites were included on the permit
MANZ 12/19/11 1/10/12 Proposed sites have been culturally cleared; waiting for permit to be issued
MOJA 12/20/11 1/10/12 3/2/12 Will need to coordinate sites w/ park archaeologist for clearance
PARA (NPS) 12/20/11 1/11/12 3/14/12 1 site on the NPS side of PARA
Only culturally cleared sites were included on the permit
PARA (BLM) 12/20/11 1/11/12 2/24/12 Working with BLM archaeologist to obtain cultural compliance for all proposed sites
10
1Sites selected from the GRTS draw were submitted to the VWG members to review for general accessibility and concerns. After correspondence with parks, a final list of 35 sites was submitted with the application.2Copies of the application and field site information (UTMs and GIS layers) were also emailed to permit coordinators since the online system did not allow for certain attachments.3Number of discussions occurred and it was decided that only fields sites could be culturally cleared would be included on the research permit.