John F. Kennedy International Airport
General Manager’s Monthly Meeting
05.13.2020
![Page 2: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/2.jpg)
Charles R. Everett Jr. - Deputy Director of Aviation and JFK General Manager
Opening Remarks
![Page 3: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/3.jpg)
Guillio Minguillo - Assistant Manager, Aeronautical Services
Safety Moment
![Page 4: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/4.jpg)
Dave Siewert, Air Traffic ManagerAir Traffic Control Tower
![Page 5: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/5.jpg)
Frank Russo, Port Director
Customs and Border Protection
![Page 6: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/6.jpg)
Matthew Palo, Commander
Centers for Disease Control and Prevention
![Page 7: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/7.jpg)
John Bambury, Federal Security Director
Transportation Security Administration
![Page 8: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/8.jpg)
Richard Bellucci - Inspector
PAPD
![Page 9: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/9.jpg)
Jim Heitmann – Assistant Director, Aviation Development
Redevelopment
![Page 10: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/10.jpg)
Environmental Reviews Status
10
• JFK Redevelopment Environmental Assessment:• FONSI/ROD issued by FAA on April 21,2020
• T1 SEQRA Environmental Review:• Negative Declaration issued by New York Transportation Development Corporation on
May 6, 2020
• Public Information Access and Links:• FONSI/ROD, Final EA and Appendices available at http://www.panynj.gov/studies-reports• Negative Declaration available at http://www.dec.ny.gov/enb/enb.html
![Page 11: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/11.jpg)
New Terminal One (NTO)• Project Updates:
• Basis of Design is ongoing• Conceptual Design in May/June 2020• Planning and coordination with PA/JFK for:
• Green Garage closure and Traffic Mitigation Plan• AirTrain alternate service and shuttles• Staging/laydown areas in west airfield
• Ongoing Site Activities:• Geotechnical Surveys on NTO future lease area ongoing• Underground Utility & Manhole surveys are ongoing• Vibration and Noise Monitoring device installations are ongoing• Pile Test Program has commenced near Green Garage in
secluded surface• Topographic surveys are near complete
11
![Page 12: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/12.jpg)
Terminal 6 (JMP)• Project Updates:
• Basis of Design is ongoing
• Site activities:• Geotech investigations and subsurface surveys
in June/July 2020• Test piles• Building 83 Demo and Laydown Area• Early works (GTC, Utilities, T5 Gate Mods)
GEOTECH SURVEYPLAN
BUILDING 83 / LAYDOWN AREA
12
83
![Page 13: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/13.jpg)
Terminal 8 (AA)• Project Updates:
• Main Building Extension (30ft) – construction start Dec.2019• Concourse East Extension (60ft) – submittals review• 3 new Hardstands (parcel M) – submittals review• Gates 31, 32 & 46 up-gauge – design coordination• Refurbishment of ATO Head House – design coordination• Reconfiguration of 4th Level Club – design• Reinstallation / modification of screening subsystem
Installation of new CBRA – scheduled to start Summer 2020
• Current site activities:• Main Building Extension (30ft) – in construction
o Foundations – ongoing 90% completedo Utilities relocations/reconfigurations – ongoingo Steel Erection – scheduled to start Summer 2020
13
![Page 14: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/14.jpg)
PA Early Actions
14
• Surveys• Survey and 3D mapping of all utility systems within the CTA (electrical/communication underway)• KIAC property line survey ongoing• Topographic survey throughout the CTA both landside and airside
• Test Piles• Working with NTO as part of the Pile Test Program – to be used to enhance foundation design for
the GTC and elevated roadway structures
• Work Order Work• Early landside work in 2020-2021 will focus on critical path major utility work from KIAC to
Terminals 1 and 4, starting with the crossings under the Van Wyck Expressway. Intent is to enhance schedule certainty for providing timely utility service to Developers.
• Others• Traffic Mitigation Projects and Devices to support PA early work projects.
![Page 15: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/15.jpg)
KAAMCORoger Scott – President
![Page 16: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/16.jpg)
Teresa Rizzuto - JFK Interim Deputy General Manager
Resumption of Service Task Force and Closing Remarks
![Page 17: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/17.jpg)
Resumption of Service Guiding Principles
Minimize AccessRestrict public access to AirTrain stations, rental car facilities, public spaces in cargo facilities (patron business counters), and other areas where patron services are performed.
Minimize Dwell Speed the traveler journey within air terminals from the front door to the cabin door by minimizing dwell at passenger processing points and minimizing distractions along the way and providing clear directions and wayfinding.
Minimize ContactReplace customer-facing services with electronic servicing via customers’ mobile devices to reduce need for face-to-face interactions and minimize passenger contact with touch surfaces (such as kiosks) within the terminal. Push interactions to customer mobile devices.
Maximize HygieneEnhanced cleaning, sanitizing and disinfecting regimens have become the new normal and both employees and customers will continue to be expected to frequently wash their hands and/or use hand sanitizer.
![Page 18: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/18.jpg)
Communications Plan Framework
18
Safety LeadershipThe COVID-19 pandemic has required JFK to raise our demanding standards to an even higher level. Informed by in-house and industry experts, along with infection prevent and control leaders around the globe, we are launching new standards designed to respond to our new environment and enhance safety for all our passengers, employees and partners.
Trust
These are historic times and we want to welcome all our passengers, employees and partners back to an environment where they know they’ll be safe. Adopting to our new normal is a journey and in the weeks and months ahead we will continue to evolve our practices to ensure we are responding to the latest CDC/WHO guidelines to keep our airport, and broader communities healthy.
Collaboration
Throughout this pandemic, we have learned that we are all one community in this together. We must collectively care for each other and are counting on all our employees, partners and passengers to keep each other safe. We all play a role in abiding by government recommendations for distancing and hand hygiene and must adopt new behaviors and technologies to stop the spread of COVID-19 and make air travel safe for all.
LeadershipThe people of New York and New Jersey are renowned for rising up in the face of adversity and we will do it again. JFK is part of the lifeblood of our region and through innovation, resiliency, and commitment we will help lead the way for the rebirth of air travel for our region and country.
![Page 19: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/19.jpg)
Resumption of Service Subcommittees
19
Subcommittee Chair
Airlines John Arancio
Ground Transportation/Rental Car Community/Parking/DriverFacilities/FHV/Taxi/Cargo Facilities
Mike Driscoll
Terminal Operators/Security/ConcessionsTeresa RizzutoKim DickieGail Mitchell
Community Outreach Jim Steven
AOC/Data Collection & SharingCOVID Coordination Sean Holland
Sparkle & Shine Anlly PalaciosRobert Wetzel
Technology/Touchless Experience TBD
Health & Regulatory Sean Holland
Rail Ops Sanchita Banerjee-Jimenez
To Join Contact Djuana Davis [email protected]
![Page 21: General Manager’s Monthly Meeting · 2020. 5. 18. · Terminal 8(AA) •ProjectUpdates: •Main Building Extension (30ft) –construction startDec.2019 •Concourse East Extension](https://reader034.vdocuments.site/reader034/viewer/2022051809/60104f7ad9fa0b7e964d8a93/html5/thumbnails/21.jpg)
Thank You!