National University of Malaysia The Environmental Site Assessment of Oil Contaminated Site in Gong Badak, Terengganu, Malaysia Wan Zuhairi W.Y. 1 * , Abdul Rahim S. 1 , Ahmad Nazri Saidin 2 , Shahril Mod Husin 2 & Mohd Noh Ahmad 2 1 Geology Programme, Faculty of Science and Technology, Universiti Kebangsaan Malaysia, 43600 Bangi, Selangor, Malaysia 2 TNB Research Sdn. Bhd. (TNBR) No 1, Lorong Air Hitam, Kawasan Institusi Penyelidikan 43000 Kajang, Selangor, Malaysia 23-May-13 12th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea 1

Upload: wan-zuhairi-yaacob

Post on 01-Dec-2014

204 views

Category:

Education


0 download

DESCRIPTION

Environmental Site Assessment of contaminated soil

TRANSCRIPT

Page 1: Gee2013 seoul korea

National University of Malaysia

12th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

1

The Environmental Site Assessment of Oil Contaminated Site in Gong Badak, Terengganu, Malaysia

Wan Zuhairi W.Y.1*, Abdul Rahim S.1, Ahmad Nazri Saidin2, Shahril Mod Husin2 & Mohd Noh Ahmad2

1Geology Programme, Faculty of Science and Technology, Universiti Kebangsaan Malaysia, 43600 Bangi, Selangor, Malaysia

2TNB Research Sdn. Bhd. (TNBR) No 1, Lorong Air Hitam, Kawasan Institusi Penyelidikan 43000 Kajang, Selangor, Malaysia

23-May-13

Page 2: Gee2013 seoul korea

National University of Malaysia

212th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

• New Guidelines in Malaysia• Published June 2009

Introduction

23-May-13

Page 3: Gee2013 seoul korea

National University of Malaysia

3

Site Assessment and Management Process

23-May-1312th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National

University, Seoul, Korea

Tier 1

Page 4: Gee2013 seoul korea

National University of Malaysia

412th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

Study Area

23-May-13

110 m

116 m

108 m

113 m

12,760 m2

Page 5: Gee2013 seoul korea

National University of Malaysia

512th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

Study Area

23-May-13

Page 6: Gee2013 seoul korea

National University of Malaysia

612th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

Conceptual Site Model

23-May-13

Page 7: Gee2013 seoul korea

National University of Malaysia

712th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

Site Investigation

Soil drilling Monitoring well

23-May-13

Page 8: Gee2013 seoul korea

National University of Malaysia

812th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

• GroundwaterSampling locations

23-May-13

Page 9: Gee2013 seoul korea

National University of Malaysia

912th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

Sampling locations• Surface soil, subsurface soil, surface water and air

sample.

23-May-13

Page 10: Gee2013 seoul korea

National University of Malaysia

1012th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

• Surface soil

Result 1

23-May-13

Page 11: Gee2013 seoul korea

National University of Malaysia

1112th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

• Groundwater & Surface water

Result 2

23-May-13

Page 12: Gee2013 seoul korea

National University of Malaysia

1212th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

• Subsurface soil

Result 3

23-May-13

Page 13: Gee2013 seoul korea

National University of Malaysia

1312th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

• Air samples

Result 4

23-May-13

Page 14: Gee2013 seoul korea

National University of Malaysia

1412th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

• Source – Pathways - Receptors

Risk Assessment

23-May-13

Page 15: Gee2013 seoul korea

National University of Malaysia

1512th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

Risk Assessment

23-May-13

Page 16: Gee2013 seoul korea

National University of Malaysia

1612th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

1. Two types of chemical of concerns (COCs) ; Naphthalene and Total Petroleum Hydrocarbon (TPH).

2. The source of contaminant is within the concrete rim No 1 and 2.

3. Most of the environmental media are not impacted by these COCs from the source zone except slightly higher concentrations of Naphthalene and TPH in air samples.

4. Tier 1 risk assessment has been performed using SSLs as guidance and indicated that there is no risk except in air media for naphthalene and in the surface soil inside two concrete rims of No 1 and 2.

Conclusions

23-May-13

Page 17: Gee2013 seoul korea

National University of Malaysia

1712th Global Joint Seminar on Geo-Environmental Engineering :: May 31-June 1, 2013, Seoul National University, Seoul, Korea

1. Contaminant source control. A contaminated soil in concrete rims no 1 and 2 must be covered and protected from contact with water and wind.

2. Clean up the contaminated soil using soil washing technique using water jet spray with biodegradable surfactant or detergent.

3. Cover the site with a layer of silt/clay and grow small plants and grass to prevent infiltration of water and contact with air after the completion of soil remediation.

Recommendations

23-May-13

Page 18: Gee2013 seoul korea

National University of Malaysia

18

Thank you for your kind attention

Acknowledgement:

• Universiti Kebangsaan Malaysia & TNB Research Sdn. Bhd• Research Grant STGL-011-2012