Gas-volumes integral certification (updated 16/09/2004). Read-out panels integral assembly (updated 16/09/2004). Setup H8 muon chambers. Endcap. Barrel. BOS. TGCs. MBPL. Magnet. CSC. BIL su supporto rotante. Barrel Stand. BIL on rotating support. BML MDT-RPC BOL MDT-RPC. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Gas-volumes integral certification (updated 16/09/2004)

Gas-volumes integral certification(updated 16/09/2004)

0

500

1000

1500

2000

2500

3000

3500

15/03/2002 02/07/2002 19/10/2002 05/02/2003 25/05/2003 11/09/2003 29/12/2003 16/04/2004 03/08/2004 20/11/2004 09/03/2005

Goal: 3704 gas volumes accepted before 15/02/2005

Page 2: Gas-volumes integral certification (updated 16/09/2004)

Read-out panels integral assembly(updated 16/09/2004)

0

1000

2000

3000

4000

5000

6000

7000

8000

01/04/2001 12/08/2001 23/12/2001 05/05/2002 15/09/2002 26/01/2003 08/06/2003 19/10/2003 29/02/2004 11/07/2004 21/11/2004 03/04/2005

0

200

400

600

800

1000

1200

1400Goal: 8016 assembled standard panelsbefore 15/03/2005

Goal: 528 assembledspecial panelsbefore 15/03/2005

Page 3: Gas-volumes integral certification (updated 16/09/2004)

Units Production

0

200

400

600

800

1000

1200

20-giu-2001 6-gen-2002 25-lug-2002 10-feb-2003 29-ago-2003 16-mar-2004

2-ott-2004 20-apr-2005

un

its a

ssem

ble

d

units done: 62%

BML = 90% BMS = 91% BOS = 26% BOL = 0%special = 11%

Page 4: Gas-volumes integral certification (updated 16/09/2004)

Setup H8 muon chambers

BIL su supporto rotante

CSC

Magnet

BOS

MBPL

TGCs

Barrel

Endcap

Page 5: Gas-volumes integral certification (updated 16/09/2004)

Barrel Stand

BML MDT-RPC

BOL MDT-RPC

BIL on rotating support

Page 6: Gas-volumes integral certification (updated 16/09/2004)

H8 Set-up for the muon chambers• Barrel:

– 6 MDT (2 BIL, 2 BML, 2 BOL)• FE and 1 MROD

– 6 RPC (4 BML, 2 BOL): only ¼ with new PAD trigger and readout boards

– 2 more chambers (BIL and a BOS complete station (MDT+RPC)

• Endcap– 6 MDT (2 EI, 2 EM, 2 EO)

• FE and 1 MROD

– 3 TGC

• Barrel ed Endcap with the complete allineament system

Page 7: Gas-volumes integral certification (updated 16/09/2004)

H8: BML+BOL RPC efficiency vs HV

Page 8: Gas-volumes integral certification (updated 16/09/2004)

Cluster size vs HV: RPC η read-out strip planes

Page 9: Gas-volumes integral certification (updated 16/09/2004)

Cluster size:RPC φ read-out strip planes

Page 10: Gas-volumes integral certification (updated 16/09/2004)

H8 event displayed with Persint

Page 11: Gas-volumes integral certification (updated 16/09/2004)

Status of the MDT-RPC muon station integration at BB5

• June 2004 6 BMLD

2 BOL

1 BOS

• 23 Settembre 10 BMLD

Page 12: Gas-volumes integral certification (updated 16/09/2004)

Tuesdays MDT No. Assembly RPC no. MDT Assembly No. Cosmics Installationprep. Line 1 prep prep. Line 2 Test

29-ago BML-D 10

04-set 5 BML-168011-set BML-D 1020-set 5 BML-168027-set BML-D 1004-ott 5 BML-1680 BML-D 1011-ott BMF-x 10 BMF18-ott 5 BML-1680 BML-E 10 BOF BMF 625-ott BOF/BOG 10 BOF BMF 601-nov 5 BML-1440 BML-E 10 BMS BOF 408-nov BMS 10 BOG BMS 515-nov 5 BML-1440 BMS 10 BOG BOG 322-nov BML-E 10 BMS BOG 3 BMF29-nov 5 BML-1440 BML-E 10 BMS BMS 5 BMF06-dic BMS 10 BMS 10 BOG13-dic 5 BML-1440 BMS 10 BOF20-dic27-dic

Christmas shutdown of CERN

MDT-RPC integration plans in 2004

Page 13: Gas-volumes integral certification (updated 16/09/2004)

MDT-RPC integration plans in 2004

• By Dec 2004 we plan to assembly the following muon stations:

45 BML 12 BMF (Dec 04 installation in the ATLAS pit) 10 BOF/G (Dec 04 installation in the ATLAS pit)

20 BMS

This is equivalent to 164 RPC pre-assembly chambers( ~2 RPC units)

Page 14: Gas-volumes integral certification (updated 16/09/2004)

RPC Pre-assembly at BB5

Page 15: Gas-volumes integral certification (updated 16/09/2004)

BML-RPC Integration in BB5

Page 16: Gas-volumes integral certification (updated 16/09/2004)

BML-RPC Integration

Page 17: Gas-volumes integral certification (updated 16/09/2004)

3 BML muon stations

Page 18: Gas-volumes integral certification (updated 16/09/2004)

Schedule MDT-RPC muon station integrationAssembly Total

line Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep requ.BB5-1 BML MDT 2 4 10 0 10 10 10 10 10 10 10 10 0 96

integral 2 6 16 16 26 36 46 56 66 76 86 96 96BML RPC 4 8 10 10 20 20 20 20 20 16 14 16 14

integral 4 12 22 32 52 72 92 112 132 148 162 178 192 192

BML Stations 2 4 0 0 10 10 10 10 10 12 12 8 8integral 2 6 6 6 16 26 36 46 56 68 80 88 96 96

BOL MDT 5 10 10 10 10 16 16 14 5Integral 5 15 25 35 45 61 77 91 96 96

BOL RPC 5 10 10 10 10 16 16 14 5Integral 5 15 25 35 45 61 77 91 96 96

BOL Stations 5 10 10 10 10 16 16 14 5Integral 5 15 25 35 45 61 77 91 96 96

BB5-2 BMS/F MDT 0 0 12 10 10 10 10 10 10 10 2integral 0 0 12 22 32 42 52 62 72 82 84 84

BMS RPC 14 0 10 20 20 20 20 20 20 20 4integral 14 14 24 44 64 84 104 124 144 164 168 168

BMS Stations 0 0 12 10 10 10 10 10 10 10 2integral 0 0 12 22 32 42 52 62 72 82 84 84

BOS/F MDT 4 5 10 10 10 10 15 15 5integral 4 9 19 29 39 49 64 79 84 84

BOS RPC 4 5 10 10 10 10 15 15 5integral 4 9 19 29 39 49 64 79 84 84

BOS Stations 4 5 10 10 10 10 15 15 5integral 4 9 19 29 39 49 64 79 84 84

BOG MDT 3 3 6 6integral 3 6 12 18 18

BOG RPC 3 3 6 6 12integral 3 6 12 18 30 30

BOG Stations 3 3 6 6integral 3 6 12 18 18

Total RPC planes 4 8 10 24 20 37 43 40 45 57 60 56 54 42 31 29 10integral 4 12 22 46 66 103 146 186 231 288 348 404 458 500 531 560 570

20052004

Page 19: Gas-volumes integral certification (updated 16/09/2004)

Milestones 2005

• 100% RPC units (1016 standard chambers 31/5/2005

• 100% delle unità provate con RC 31/7/2005

• 100% integrated RPC-MDT muon station 30/9/2005