gary peak field service engineer mccauley propeller systems building on the best

46
Gary Peak Field Service Engineer McCauley Propeller Systems uilding On The Best

Upload: zachery-steel

Post on 14-Dec-2015

245 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Gary Peak

Field Service Engineer

McCauley Propeller Systems

Building On The Best

Page 2: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Product Support for 2010

Technical Publications McCauley Training Foreign Certifications Threaded Propellers Service Bulletins & Letters Pending service Information Field Issues

Page 3: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Recent Manual Revisions

MPC26 CD Owner’s Manual Rev. 1• Original issue April, 2008• Rev. 1 issued December, 2009 added the

information for fixed pitch propellers• Contains owner’s manual information for all

C200 through C1100 series as well as fixed pitch aluminum propellers

Page 4: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Planned Manual Revisions

MPC1100 (est. completion 4th qtr 2010)? CMM1100 (est. completion 4th qtr 2010)? BOM100 (est. completion 4th qtr 2010)? SPM100 (est. completion 4th qtr 2010)

• Should include C3400 hub information• Will include all De-Ice information • (830415 De-ice manual will be obsolete)

Page 5: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

New Product Manuals

MPC28 Owner’s Manual – Fixed Pitch Composite

MPC110 Service/Overhaul Manual – Fixed Pitch Composite

MPC3400 Service/Overhaul Manual- Constant Speed Composite

MPC27 Propeller Operator’s Manual Composite Propellers

BOM200 Blade Overhaul Manual (Constant Speed Composite Blades)

Page 6: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

McCauley Training

McCauley Training Advantages:• Flexible training schedule• Class book provided can be used for future

reference• Competitive prices• Knowledgeable trainers• Cost effective way to train new employees

without disrupting existing personnel• Assistance in making lodging and rental car

arrangements

Page 7: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

New Courses for 2010

C300/C500 Feathering Propeller Overhaul

Intro. to McCauley Propeller and Field Maintenance

Fixed Pitch Propeller Maintenance

Boot R& I Optional With Constant Speed Overhaul

Page 8: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

McCauley Training

Available Classes

Constant Speed Overhaul Turbine Overhaul Blade Overhaul Manual C703 Field Reassembly C1103 Field Reassembly Courses Can Be Combined

Visit www.mccauley.textron.com for a full list of available courses

Page 9: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Owner’s/Operators Class

Propeller/Governor operation theory Participate in a build up/tear down of a

C400 series propeller Discussion of active service letters and

service bulletins

Page 10: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Composite Training Development

Composite Blade Overhaul 1L100 Overhaul C3400 Overhaul

Page 11: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Composite Blade Overhaul Class

Damage assessment/Inspection Minor blade repair Leading edge guard replacement Resonance testing

Page 12: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

C3400 Composite Overhaul Class

Design overview Operational differences Damage assessment Assembly/Disassembly Adjustments Hub repairs

Page 13: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

1L100 Composite Overhaul Class

Damage assessment/Inspection Minor Blade repair Leading edge guard replacement Resonance testing

Page 14: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Composite Tooling Requirements

Majority of tools utilized are common with other composite blade manufacturer’s

McCauley specific tooling:• Resonance Test Equipment • Resonance Testing

Fixture/Adapter• Shank adapter for

utilizing existing collets

Page 15: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Composite Qualification

Complete qualification process still under development

Will require procurement of applicable tools and fixtures

Approved personnel must complete McCauley composite training

May require work to be completed on a “qualification blade” and then approved by McCauley prior to obtaining certification

Page 16: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

16

Recent Foreign Approvals

COUNTRY AUTHORITY MODEL # Aircraft DATE RECD

Argentina DNA C443 Cirrus SR22 3/12/2009

Brazil ANAC C447 - STC Cessna 400 8/11/2009

Indonesia DGCA 1A170/JHA Cessna 172 R/S 9/1/2009

Indonesia DGCA 1C235/LFA Cessna 172 R 9/1/2009

Korea CASA C98 Cessna A188B 8/14/2009

China CAAC 1A170/JHA Cessna 172R/S 9/15/2010

China CAAC 1C235/LFA Cessna 172R 9/15/2010

China CAAC C431 Cessna 182T 9/15/2010

China CAAC C442 Cessna T182T 9/15/2010

China CAAC C432Cessna

206H/T206H 9/15/2010

Page 17: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

17

Recent Foreign Approvals

COUNTRY AUTHORITY MODEL # Aircraft DATE RECD

China CAAC C444/C447 Cessna 350/400 Submitted

Germany EASA C447 Cessna 400 03/09/2010

Ukraine SAA C768 King Air C90A Submitted

Ukraine SAA C703 Cessna 208/208B Submitted

Page 18: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Threaded Propeller Part Production Ceased production of threaded blades in

2002 Last parts orders for threaded parts was

10/1/2010 Consumables and other purchase parts will

continue to be available through McCauley Technical support of the product line will

continue indefinitely

Page 19: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Threaded Propeller Parts Stopped

Page 20: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Information Overview

Service Letters• SL2008-3• SL2009-1• SL2010-1A• SL2010-2• SL2010-3

Service information released since last WAPA meeting:

Service Bulletins•SB137AE•ASB221E•ASB250A•ASB255A•SB263•ASB264

Page 21: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

SB137AE - Time Between Overhaul (TBO)

• Adds long term storage requirements for TD propellers

• Increased governor TBO from 1800 hours/60 months to 2000 hours/60 months

• Adds a table with all of our component life limits

Page 22: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

ASB221E – Inspection of 1A103/TCMChanges from ASB221D to ASB221E

• Adds inspection and reaming of the bolt holes

• Adds visual and mag particle inspection of steel reinforcement plate

• Adds mag particle inspection of mounting bolts

• Adds visual inspection of mylar gasket AD 2010-04-05, effective March 10, 2010

Page 23: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

ASB221E (continued)• ASB221E vs. AD 2010-04-05

• The difference between the ASB and the AD is the repetitive inspection

/ASB221E has a repetitive inspection every 750 hours or 36 months, whichever occurs first

/AD 2010-04-05 requires the repetitive inspection be performed every 750 hours. There is no calendar limit on the AD.

• If the propeller was previously inspected per ASB221C or D the initial inspection is not required. The repetitive inspection schedule should be followed.

Page 24: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

ASB250A – Hub life limits for C1101 – C1104 C1101, C1102, C1103, and C1104 hubs are

now life limited to 6000 hours TTSN• All hubs with more than 5750 hours TTSN

/Remove from service within next 250 hours TIS

• All hubs with less than 5750 hours TTSN/Remove from service upon reaching 6000 hours TSN

Page 25: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

ASB255A – Jetstream J41 blade life limits and added blade inspections

All C1101-1104 blades are now life limited to 3,500 hours TTIS

Page 26: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

ASB255A (continued) Changes the inspection compliance

• For blades with less than 2400 hours TTIS/Inspect blades upon reaching 2500 hours TTIS

• For blades with more than 2400 hours TTIS/If blades have been inspected in accordance with ASB255 within past 2400 hours TIS

• Inspect upon reaching 2500 hours time since last inspection

/If blades have not been inspected in accordance with ASB255 within the past 2400 hours TIS

• Inspect blades within next 100 hours TIS

Page 27: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

ASB255A (continued) Removes the repetitive inspection requirement Adds an inspection of the shelf on the blade

shank where the split retainers ride C-5963 split retainers are replaced by C-7870

split retainers During reassembly the C-7870 split retainers

must be installed with the ends clocked 90 degrees from the counterweight hole

Page 28: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

ASB255A (continued) AD 2009-19-04, effective October 27, 2009 AD has different compliance times than ASB

• Blades with more than 10,000 hours TSN must be removed from service before next flight

• Blades with more than 3000 hours TSN must be removed from service within next 500 hours TIS, not to exceed 10,000 hours TSN

• Blades with less than 3000 hours TSN must be removed from service upon reaching 3500 hours TSN

Page 29: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

SB263 – Measuring feather angle on C652• C652 has a high feather angle• There have been issues with incorrect

feather measurements and adjustments which resulted in the propellers rotating backwards when feathered

• Make sure the protractor is on the correct side of 90 degrees

Page 30: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

ASB264 – Hub dowel hole inspection Drill point feature in the bottom of the

dowel holes on C1101, C1102, C1103, and C1104 hubs

Specific S/N range (041002 thru 090133) Drill point feature can vary in size If it has a drill point feature of any size it

is affected.

Page 31: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Bulletins

ASB264 (continued) Both pictures feature different size drill points Use a magnifying glass, wooden stick or

transfer putty to help identify drill the point

There is a warranty program for this ASB

Page 32: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Letters

SL2008-3 Added additional pitch range for the

1A100 and 1A135 fixed pitch

Page 33: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Letters

SL2009-1 (New fixed pitch model) 1A162/TCD6754

• Installed on Cessna 162 Skycatcher• Designed for TCM O-200-D engine with

lightweight “star” flange• Requires proper indexing for smooth

operation/Segment of crankshaft flange with flat spot at 12 o’clock and the prop at 10 and 4 position

Page 34: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Letters

Page 35: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Letters

SL2010-1A (new governor models) C290D3/T53

• Single rpm governor used on Cirrus SR22T

C290D4/T5• Created for Atlantic Aero Inc for their IO-550 STC

conversions on the Cessna 206 and 210

DCFUS290D10/T8• Counter-rotating mag head governor created for

Colemill Enterprises on their Piper Navajo/Chieftain synch system STC conversions

Page 36: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Letters

SL2010-2 (C447 oil level) Increased the oil fill level from 1300cc up

to 2000cc.

Page 37: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Service Letters

SL2010-3 (new cylinder gasket) Rubber gasket that does not use

permatex. Initially approved for use on C432 only Have been field testing it for 1 ½ years

with no leakage problems

Page 38: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Application Guide

MAG (McCauley Application Guide) Latest revision is February 2010 Added Non-McCauley STC’s It is available on the McCauley website Let me know if you find any errors or

have additional information you want added, or changed.

Page 39: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Pending Service Letters

SL2010-X (single piece piston rod) Single piece piston rods for C300 and

C500 series propellers Will eliminate pressure checking piston

rods and leakage issues at the brazed connection between the two pieces.

Page 40: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Pending Service Letters

SL2010-X 1L100 Spacer removal

Page 41: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Pending Service Letters

SL2010-X Definitions of a Service Letter and Service Bulletin

Page 42: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Field Issues

Deice lead restrainer strap installation Still having issues with tearing deice

boots Purpose of the restrainer strap is to hold

down the lead not the boot Looking at the feasibility of leaving the

restrainer strap location the same but positioning the boot farther outboard

Page 43: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Field Issues

Cad plated hardware You may notice a change in the

appearance of the Cad plating on some of our hardware. We are changing from type I to type II.

Page 44: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Enlist your Help

We also want your help.

Let us know if you have any ideas for new STC’s or other products to add to our line up.

Page 45: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Bonus

C400 series fixed pitch

Page 46: Gary Peak Field Service Engineer McCauley Propeller Systems Building On The Best

Gary Peak

Field Service EngineerMcCauley Propeller Systems

5800 East PawneeWichita, Ks 67218

800-621-7767316-831-3844

[email protected]

Building On The Best