gainesville atms: a regional success! october 29, 2012 matthew weisman, pe its operations engineer -...

43
Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Upload: tatiana-larmer

Post on 30-Mar-2015

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Gainesville ATMS: A Regional Success!

October 29, 2012

Matthew Weisman, PE

ITS Operations Engineer - City of Gainesville, Fl

2012 Transpo – Bonita Springs

Page 2: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Outline

• What is the City responsible for?• How we are/were funded• Latest Regional Incentives

• Interstate 75 Deployment• Outside City Limits• District 2 ITS• District 5 ITS

Page 3: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Traffic Management System

• The City of Gainesville maintains• Traffic signals• School beacons• Flashing beacons• ITS

• Includes• Unincorporated Alachua County• University of Florida• Smaller Cities in Alachua County

Page 4: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Traffic Management System

Page 5: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Funding Partnerships

Capital Funding Methodology: City, County, MTPO, FDOT and University Staff

worked together to develop a funding methodology for this project.

Maintenance Funding: Inter-local agreements with other County

agencies FDOT D2

Page 6: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Funding Commitments to Date

Agency

City

County

U.F.

FDOT

Fair Share

25.1% ($ 3.6 mil)

22.7% ($ 3.3 mil)

3.9% + $ 3.2 mil =

($ 3.8 mil)

50.0% ($ 9.1 mil)

Committed

$ 5.0 mil

$ 2.2 mil

$ 3.8 mil

$ 9.1 mil

Page 7: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Phasing Costs

Phase I

Phase II

Phase III

Phase IV

Total

$ 7.5 million

$ 5.8 million

$ 4.1 million

$ 820,000

$ 18.2 million

Page 8: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Traffic Management System

Page 9: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Traffic Management System

Page 10: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Original ATMS Scope

New cabinets and controllers at EVERY intersection Communications backbone PTZ Cameras Construction (installing cabinets etc…) Consulting services Software (ATMS software, Cameras, signal timing…) TMC Building Equipment for the TMC Emergency vehicle preemption/priority

Page 11: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Original Scope Lacked I-75: Original intention of the $18.2 M was for

Gainesville’s arterial street network and not the interstate.

However, not having access to the interstate often impeded our ability to properly manage arterials during I-75 incidents.

Page 12: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Local Agency VS FDOT: Initially, CoG requested permission from FDOT to

permit traffic camera poles near the main interchanges in Gainesville

Request was politely denied. FDOT is the only agency that can permit on the interstate.

Page 13: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Local Agency VS FDOT: Begun petitioning District II’s ITS office for

interstate cameras shortly afterwards.

Page 14: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

THE DESIGN! Original plan attempted to use existing cantilever and light

pole structures on the interstate to keep costs down.

Page 15: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

THE DESIGN! CoG conducted it’s own site surveys to confirm

wireless connectivity and good visuals.

Page 16: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

THE DESIGN! Included cameras from the south end of Paynes

Prairie to Alachua, Fl

Page 17: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

THE DESIGN!

Roughly 20 miles from first camera in the south of the Prairie to the Alachua US441 interchange

Page 18: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Morning of January 29, 2012

Page 19: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Morning of January 29, 2012

Page 20: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Page 21: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Page 22: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Page 23: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Spring into action! FDOT agreed to pay their “push button” contractor to plant

ten new poles on the interstate. FDOT also agreed to start supplying replacement back up ITS equipment to CoG.

CoG was responsible for everything else. As no other infrastructure was going on the interstate, these 10 camera poles had to communicate over wireless and use solar power.

Page 24: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Spring into action! Sign cantilever idea went bust. Photocells brought on too

many problems. Post January 29th design kept two cantilever structures,

Alachua (US441) and Williston Rd (SR121) interchanges.

Page 25: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Spring into action! In order to use existing cantilevers, FDOT policy was

waived and FDOT issued CoG permits to construct conduit to these existing signs.

Page 26: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

FDOT plants poles 67’ (or 55’ tall) poles

Page 27: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Spring into action! Solar system was designed to our specific equipment

Page 28: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Spring into action! PoE radios were used to shoot back to our fiber.

Page 29: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Wireless on the Prairie PoE radios were used to

shoot back to our fiber.

Page 30: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Finished Product

Page 31: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Interstate 75

Final Cost $79,000 FDOT $160,000 CoG TMS Total = $240,000

Page 32: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Outer County

Page 33: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Outer County

Roof of the Seagle Building – Better than a tower!!

Page 34: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Outer County

Wireless verification … aka … job perks

Page 35: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Outer County

More wireless verification … aka … more job perks

Page 36: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Outer County

More wireless verification … aka … more job perks

Page 37: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Alachua & High Springs

FDOT Tower @ NW 39th Ave (SR222)

Page 38: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Give up yet?

Page 39: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Connection to D2

• Gainesville Traffic Operations has recently become a member of the Florida Lambda Rail!

• This will allow a 1GIGE connection to FDOT D2 Jacksonville with possibility of expanding to other

FDOT districts.

Page 40: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Expansion to D5

• CoG has replaced an old I-Florida PTZ camera in Marion County. Exit 368 is the last NB exit before entering Alachua County

• Communication will be maintained via a cellular modem over the Verizon network. Verizon provides the City with a static IP. The modem uses an embedded VPN to connect into our network.

Page 41: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Good News!

Page 42: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Webpage

gac-smartraffic.com

Page 43: Gainesville ATMS: A Regional Success! October 29, 2012 Matthew Weisman, PE ITS Operations Engineer - City of Gainesville, Fl 2012 Transpo – Bonita Springs

Contact

[email protected]