g sgallen arbitration dispute

17
Rebecca Allen Arbitration Arbitration Dispute Arbitration Dispute United Natural Gas v. Eastern Europe Efficiency Table of Contents 1. Arbitration Clause 2. Outline of Rules included: rules applied, improvements that could be made to rules 3. Plaintiff’s claim for relief serves notice, summary of facts, claims for relief used by arbitrators 4. Defendant’s response affirms notice was given, counterarguments 5. Perry Deposition 6. Lopez Deposition 7. Kensington Deposition

Upload: rebecca-allen

Post on 13-May-2017

219 views

Category:

Documents


0 download

TRANSCRIPT

Rebecca AllenArbitration

Arbitration Dispute

Arbitration DisputeUnited Natural Gas v. Eastern Europe Efficiency

Table of Contents

1. Arbitration Clause2. Outline of Rules

­ included: rules applied, improvements that could be made to rules3. Plaintiff’s claim for relief

­ serves notice, summary of facts, claims for relief­ used by arbitrators

4. Defendant’s response­ affirms notice was given, counterarguments

5. Perry Deposition6. Lopez Deposition7. Kensington Deposition

ARBITRATION CLAUSE

1. In the case of any dispute arising out of this agreement, arbitration administered by

the International Chamber of Commerce in accordance with International Arbitration

Rules will be the exclusive means of resolving such disagreement. The arbitration panel

is to adhere to United States law. By signing this agreement, both parties consent to

United States federal law as the law governing the dispute. The decision of the

arbitration panel shall be binding. The judgment on the award rendered in any such

arbitration will be entered by whichever court that has jurisdiction.

1.1: Service. The arbitration demand must be delivered either in person or by

certified mail to the parties involved. It must include a clear statement of the dispute. A

response must be served within the following three weeks. The response must respond

to any issues raised in the initial demand and must also raise any counterclaims that will

be relied upon.

1.2: Arbitrator. Following proper service and response the parties will have

three (3) weeks to collaboratively select three (3) arbitrators from the International

Chamber of Commerce. The selected arbitrators must have over ten (10) years of

experience in the area of the dispute. If the parties cannot agree on a panel of arbitrators

they must submit a petition to the International Chamber of Commerce to select a panel

for them. At this time the selections of the International Chamber of Commerce will be

binding.

1.3: Pre-hearing Procedure.

1.3(a): Conferences. The panel of arbitrators shall hold at least one (1)

meeting with the parties and their representation to establish arbitration schedule and

the rules by which the arbitration shall be governed.

1.3(b): Discovery. Any discovery request shall be reviewed by the

arbitrators and if necessary to the claims and defenses of the parties shall be approved.

This includes expert reports, any necessary depositions, names and addresses of the

witnesses, and anything else the parties deem necessary.

1.3(c): Motions. Any and all motions must be filed with the panel of

arbitrators before the beginning of the arbitration.

1.4: Hearing

1.4(a): Location. The hearing will be held at a site deemed agreeable by

the panel and the parties prior to the beginning of the arbitration.

1.4(b): Time. The hearing must not last beyond a three (3) month

period.

1.4(c): Award. The arbitrators must submit their decision in written

format no later than one (1) month after the conclusion of the hearing. The sole remedy

allowed shall be actual damages.

1.5: Costs and Fees. Barring any contrary agreement by the parties and

arbitrators, the cost of the location, arbitrators, and any other expenses shall be split

evenly by the parties.

Outline

The arbitration dispute involves a failure to deliver natural gas from Eastern European

Efficiency to United Natural Gas. The facts, which are further expanded upon in the plaintiff’s

claim, are as follows: the parties entered into a contract for the sale of $2.2 million US worth

of natural gas. Eastern European Efficiency failed to deliver and the parties signed an

amended contract to deliver two weeks later. They failed to deliver again. At this point, United

Natural Gas filed a suit in the 9th Circuit against Eastern European Efficiency. Eastern

European Efficiency filed a response and the claim was then sent to arbitration, where it is to

be decided by a panel of arbitrators from the International Chamber of Commerce.

The arbitration clause signed by the parties states several actions that must occur

before the beginning of arbitration. First, according to rule 1.1, an arbitration demand must be

delivered to the parties involved and include a clear statement of the dispute. In this case, the

plaintiff served notice when they filed a claim with the courts. Additionally, the defendants

acknowledged service when they filed an answer in court.

According to 1.2 the parties have three weeks to select from the International Chamber

of Commerce three arbitrators. The rules of the International Chamber of Commerce will

govern the dispute, therefore the arbitrators must be pre-selected by the organization.

In terms of other processes that must occur, the parties must meet to establish the

arbitration meeting times under rule 1.3. In the pre-arbitration meeting the parties can also

decide on the location of the arbitration. Additionally, the arbitrators can review and approve

any discovery requests and any and all motions. In this case, the parties each produced

depositions that were completed prior to arbitration and those were used by the arbitrator. The

Perry, Lopez, and Kensington depositions are all attached.

As part of the initial claim required by 1.1 and by 1.3, each party has stated what they

want out of their deposition. The plaintiff is seeking damages for the lost profits and delivery

of the goods, whereas the defendants want the contract nullified under the doctrine of

impossibility. Because they are submitted prior to the hearing the arbitrator can know,

entering the dispute, what the parties will be arguing for or against.

Finally, under rule 1.4, the arbitrators will come to a decision for or against the

plaintiff, which in this case would either grant them damages and delivery or deny them

completely. The costs would then be split between the two parties under rule 1.5, unless the

arbitrators included a decision that one party would pay for the entire arbitration.

In terms of improvements that could be made to these rules, I would revise Rule 1.4 to

be more structured in terms of what the actual arbitration process between the two parties

would look like. Because this is an international dispute, I should have written the rules to

allow the arbitrator to decide on a location if necessary, not relying on the ability of the parties

involved to compromise. Additionally, while I intended the International Chamber of

Commerce rules to govern the arbitration, I should have made it more clear as to the

jurisdiction of the United States.

PLAINTIFF’S CLAIM FOR DELIVERY OF GOODS AND DAMAGES

CLAIM SUBJECT TO ARBITRATION - 1

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Johnny Smith

Bar #385189

Smith International Litigation

9TH CIRCUIT COURT

United Natural Gas,

Plaintiff,

vs.

Eastern Europe Efficiency,

Defendant

)

)

)

)

)

)

)

)

)

)

Case No.: 9700185

PLAINTIFF’S CLAIM FOR DELIVERY OF

GOODS AND DAMAGES

CLAIM SUBJECT TO ARBITRATION

Summary of the Facts

United Natural Gas and Eastern Europe Efficiency have

entered into contracts since February of 1999. United Natural Gas, a

Portland-based company, deals exclusively in natural gas purchases from

Eastern Europe. From there, they distribute natural gas throughout North and

South America. Eastern Europe Efficiency is a prominent Ukraine-based natural

gas refining and transporting business.

On November 2, 2013 defendant entered into a contract with

plaintiff for the sale of $2.2 million (US) worth of natural gas to be

delivered by February 2, 2014. Following the delivery of the natural gas, the

$2.2 million would be paid to the defendant and the delivery would be

distributed by plaintiff to the distributing purchases.

On February 1, 2014 defendant informed plaintiff that due

to political unrest it would be unlikely that they would able to be complete

the agreement as signed. Because it was only a day away from the scheduled

delivery date the defendants had no choice but to renegotiate a delivery

agreement, allowing the defendants a two-week extension that they repeatedly

PLAINTIFF’S CLAIM FOR DELIVERY OF GOODS AND DAMAGES

CLAIM SUBJECT TO ARBITRATION - 2

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

said they could fulfill. The parties both signed an amended contract with an

extended delivery date of February 15th, 2014.

Defendants failed to deliver the natural gas by February

25th. Additionally, the plaintiff repeatedly attempted to contact the

defendant in order to determine that delivery was going to be completed and

defendants failed to get in touch with plaintiff.

Due to the failed delivery of the natural gas, United

Natural Gas sustained $900,000 in lost profits and the loss of two

distributing contracts.

Argument

I. The Plaintiff is entitled to delivery of the natural gas

a. Due to the scarcity of natural gas and the existing contract with

Eastern Europe Efficiency, plaintiffs should be able to complete

the purchase of the $2.2 million worth of natural gas.

II. The Plaintiff is entitled to damages in the amount of the lost

profit and lost contract

a. The plaintiff began suffering losses following the breach of the

February 2nd, 2014 contract delivery date and should receive the

amount in lost profits and lost contract damages in the amount of

$862,000.

i. The lost profits of $900,000 occurred when the defendant

failed to deliver and several clients could not purchase in

the amount of their order.

ii. The three lost clients will cost United Natural Gas

$862,000 in the next fiscal year. The clients left United

Natural Gas exclusively because of the failed February 2014

delivery, otherwise satisfied with their experience as

long-time customers of United Natural Gas

PLAINTIFF’S CLAIM FOR DELIVERY OF GOODS AND DAMAGES

CLAIM SUBJECT TO ARBITRATION - 3

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Conclusion

Due to the failure to deliver the contracted amount of

natural gas the plaintiff’s are entitled to delivery of the natural gas and

damages stemming from the failure of delivery

Dated this 10th of March, 2014

JOHNNY SMITH, # 385189

DEFENDANT’S RESPONSE TO PLAINTIFF’S CLAIM FOR DELIVERY OF GOODS AND

DAMAGES UNDER UCC 2-615 - 1

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Carol Andrews

Bar # 3252291

Andrews Defense

9TH CIRCUIT COURT

United Natural Gas,

Plaintiff,

vs.

Eastern Europe Efficiency,

Defendant

)

)

)

)

)

)

)

)

)

)

Case No.: 9700815

DEFENDANT’S RESPONSE TO PLAINTIFF’S

CLAIM FOR DELIVERY OF GOODS AND

DAMAGES UNDER UCC 2-615

Argument

I. The doctrine of impossibility protects defendants from being held

liable for the failed deliver of the natural gas

a. While it is unfortunate that plaintiff was unable to fulfill

their contractual distribution agreements, it was contractually

impossible for defendants to complete delivery of the natural gas

by the amended delivery date of February 15th, 2014.

b. Impossibility states the general rule is that a thing may be

impossible to perform when it would not be practicable to

perform. A contractual obligation is impracticable "when it can

only be done at an excessive and unreasonable cost"

(Transatlantic Financing Corp. v. United States, 363 F.2d 312

[D.C. Cir. 1966]). As anyone who has been following the

continuing unrest in Ukraine would know, the distribution and

transfer of natural gas is one of many things that has become

impossible for perform in Ukraine.

DEFENDANT’S RESPONSE TO PLAINTIFF’S CLAIM FOR DELIVERY OF GOODS AND

DAMAGES UNDER UCC 2-615 - 2

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

c. Because the contract was impossible to perform it is clear that

the defendant should not be held liable for the damages incurred,

nor should they have to deliver the natural gas, assuming it was

even possible now.

II. Plaintiff willingly entered into an amended contract for a later

delivery date, therefore defendant is not liable for the losses

beginning on February 2nd, 2014

a. Even if the defendant were held even partially liable for the

losses incurred by plaintiff, the plaintiff willingly entered

into a contract extending the delivery date to February 15th,

2014. According to the deposition of Diane Perry, CEO of

Vancouver Energy, plaintiff was going to lose their business even

if the natural gas would have been delivered on February 15th.

According to Perry, “We knew that we would have to find our

natural gas elsewhere beginning on February 3rd regardless of any

later shipment.” (Perry Dep. p. 2, 12-16).

b. Additionally, one of the other three clients that plaintiff cites

was planning on dropping United Natural Gas as their supplier at

the end of February regardless. According to Kyle Lopez, CIO of

Midwest Power, the plaintiff’s contract performance had been less

than satisfactory and they were planning on finding another

supplier in February. According to Lopez, “They were really

unreliable and we are all sick of dealing with it. There are

plenty of other suppliers we can turn to.” (Lopez Dep. p. 1-2,

25).

///

///

DEFENDANT’S RESPONSE TO PLAINTIFF’S CLAIM FOR DELIVERY OF GOODS AND

DAMAGES UNDER UCC 2-615 - 3

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Conclusion

The defendant should not be held liable for the losses

incurred nor can they be forced to deliver the goods as they are unable to do

so.

Dated this 10th of March, 2014

Carol Andrews, #3252291

Deposition of Diane Perry pursuant to FRCP 30 - 1

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Carol Andrews

Bar # 3252291

Andrews Defense

9TH CIRCUIT COURT

United Natural Gas,

Plaintiff,

vs.

Eastern Europe Efficiency,

Defendant

)

)

)

)

)

)

)

)

)

)

Case No.: 9700185

Deposition of Diane Perry pursuant to

FRCP 30

Deposition of Diane Perry

Deposition of Diane Perry, a witness in the above-entitled case, taken

before Saul Anderson, notary public located in Washington County, Oregon,

pursuant to Uniform Trial Court Rules.

Direct Examination by Ms. Andrews:

Q: Hello, Ms. Perry. Please state you name and occupation.

A: Diane Perry, CEO of Vancouver Energy.

Q: Thank you. Ms. Perry, you have had a contract for the purchase and

distribution of natural gas with United Natural Gas for the last 8 years,

correct?

A: Yes, we entered into a contract in 2006 and have continued doing business

together since then.

Q: What is the nature of your distribution?

A: We distribute natural gas to municipalities and entities like hospitals

and local businesses. We operate on a structure where we are incredibly

reliant on the deliver of gas by our supplier, as our customers need

predictability and reliability more than anything.

Deposition of Diane Perry pursuant to FRCP 30 - 2

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Q: That makes sense. Before February 2014 how was your working relationship

with United Natural Gas?

A: Generally, fine. There have been a couple of hiccups in terms of late

delivery, but never anything more than a few hours.

Q: Tell us about what happened in February 2014.

A: Well, they knew the nature of our business, specifically that it was part

of our business model to operate without a lot of wiggle room in terms of

time. They called us on February 1st and informed me that they would be unable

to the deliver and that that they could now make us a sale on February 16th,

2014. This didn’t work for me or our business model.

Q: So you decided to drop them as your supplier?

A: Yes, we had been pursued by other suppliers that had far better track

records and this was the last straw. I informed United Natural Gas at this

time that we would no longer be needing their services. We knew that we would

have to find our natural gas elsewhere beginning on February 3rd regardless of

any later shipment.

Q: Even if the delivery had come through on February 15th you would not have

retained your contract?

A: No. The second they said no February 2nd delivery we were done.

Dated this 10 of March, 2014

Carol Andrews, #3252291

Deposition of Kyle Lopez pursuant to FRCP 30 - 1

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Carol Andrews

Bar # 3252291

Andrews Defense

9TH CIRCUIT COURT

United Natural Gas,

Plaintiff,

vs.

Eastern Europe Efficiency,

Defendant

)

)

)

)

)

)

)

)

)

)

Case No.: 9700185

Deposition of Kyle Lopez pursuant to

FRCP 30

Deposition of Kyle Lopez

Deposition of Kyle Lopez, a witness in the above-entitled case, taken

before Saul Anderson, notary public located in Washington County, Oregon,

pursuant to Uniform Trial Court Rules.

Direct Examination by Ms. Andrews:

Q: Hello Mr. Lopez. Could you please state your name and occupation?

A: Kyle Lopez, CIO of Midwest Power.

Q: Ok Mr. Lopez, why don’t you tell us about the nature of Midwest Power’s

working relationship with United Natural Gas.

A: I have been in contracts with United Natural Gas on and off since 2000.

Q: Have you generally been satisfied with their work?

A: No, I haven’t actually. There simply haven’t been any meaningful

alternatives to their company.

Q: Are there now?

A: Yes, the market has expanded quite a bit. There are at least 3-4 that I

have been talking to for the last six months or so. They were really

Deposition of Kyle Lopez pursuant to FRCP 30 - 2

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

unreliable and we are all sick of dealing with it. There are plenty of other

suppliers we can turn to.

Q: So are you saying that you have planned to leave United Natural Gas?

A: Yes, since about November of 2013.

Q: Were they aware of this?

A: Yes. I informed them of competitive pricing and they didn’t give my threat

to leave much credence. I ultimately left in February 2014.

Q: Did their failure to deliver in February lead to that decision?

A: No, I was leaving no matter what.

Dated this 10 of March, 2014

Carol Andrews, #3252291

Deposition of Andrew Kensington - 1

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Johnny Smith

Bar #385189

Smith International Litigation

9TH CIRCUIT COURT

United Natural Gas,

Plaintiff,

vs.

Eastern Europe Efficency,

Defendant

)

)

)

)

)

)

)

)

)

)

Case No.: 9700185

Deposition of Andrew Kensington

Deposition of Andrew Kensington, a witness in the above-entitled case,

taken before Saul Anderson, notary public located in Washington County,

Oregon, pursuant to Uniform Trial Court Rules.

Direct Examination by Mr. Smith:

Q: Hi Mr. Kensington. Please state your name and occupation.

A: Andrew Kensington, owner and CEO of International Energy.

Q: Mr. Kensington, what is it that International Energy does?

A: We are a distributer of natural gas that we receive from Eastern Europe,

mainly Ukraine and parts of Russia.

Q: What is your knowledge of United Natural Gas?

A: They are one of our direct competitors.

Q: In the last few months have you received your natural gas shipments with

regularity?

A: Yes, although there is a lot of unrest in Ukraine we have been in

communication with the companies and beyond a little extra work there doesn’t

seem to be many issues in the transfer of natural gas.

Deposition of Andrew Kensington - 2

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

27

28

Q: So they haven’t had any trouble and you have received your normal

shipments?

A: Yes, and in talking to them I don’t know how shipments are being that

delayed.

Q: Why do you say that?

A: The companies state that they all have shipping clearance and there

shouldn’t be a delay in any company.

Q: Are you familiar with Eastern European Efficiency?

A: Yes, I am. I have worked with them before and they are incredibly

unprofessional.

Q: Why do you say that?

A: Well, they were never on time when I ordered from them. Also, talking to

my guys over there it sounds like they are just using the political issues to

make excuses for not being ready for the shipment.

Q: No further questions, thank you Mr. Kensington.

Dated this 10 of March, 2014

JOHNNY SMITH, # 385189