Design-Build Services Workshop for the
Pedestrian and Bicycle Bridge
Mall to the Lakefront Project from the
Cuyahoga County of Ohio The Department of Public Works July 13, 2015
Cleveland Convention Center
Introductions and Agenda
• Project Background
• Design Features
• Status of Tasks and Approvals
• Procurement
• Schedule
Project Sponsors
• Cuyahoga County
Department of Public Works
• City of Cleveland
• Group Plan Commission
Project Background
• Parsons Brinckerhoff Team received NTP
to prepare Indicative Design and serve as
Owner’s Representative (Sept 2014)
• Public Meeting held (Nov 2014) and the
cable-stayed bridge concept selected
• Re-advertising the Design-Build Services
project with new 2017 completion
schedule
Owner’s Representative Team
• Parsons Brinckerhoff – Prime • Rosales & Partners – Architecture
• ASC Group, Inc – Environmental
• Euthenics, Inc – Survey, ROW, Utilities
• Hill International – Construction Services
• KMJM Land Services, LLC – Appraisals
• McGuiness Unlimited, Inc – Estimating
• Resource International, Ltd – Geotechnical
• Rowan Williams Davies & Irwin – Wind & Vibration
Analysis
____________________________________
Project Management Consultants LLC – Consultant to
Cuyahoga County
Project Background
Project Consists of:
• Coordination (NS, CSX, Amtrak, GCRTA,
City of Cleveland and ODOT)
• Coordination with Lakefront developers,
Great Lakes Science Center, Rock & Roll
Hall of Fame, Cleveland Browns, Port of
Cleveland and the Convention Center
• Utility Coordination
RFQ/RFP - Design & Reference Documents
• Indicative Plans / Visual Quality Manual
• Specifications
• Supplemental Information
• Geotechnical data
• Wind and Vibration Assessments
Indicative Plans – Tower
Orthotropic Composite
Supported Vertically &
horizontally Supported horizontally
only
Design – Status of Approvals
• Environmental
• Railroads
• ODOT
• FAA/BKL
• Right-of-Way
• Utilities
• Design Review • Downtown/Flats Design Review Committee
• City Planning Commission
Design – Environmental Approvals
ODOT approved the Categorical Exclusion
Environmental Commitments include:
• DBT will develop a Site specific health and
safety plan for possibility of encountering
natural gas
• DBT will develop a SWPPP and submit a NOI
under NPDES construction storm water
permit
Design – Status of Railroads
Impacted Railroads:
Norfolk Southern (PE Agreement)
CSX (PE Agreement)
Amtrak (Permit to Enter obtained for
geotechnical borings; seeking Air-Rights)
GCRTA (Waterfront Line) – Safety Procedures,
Maintenance of Rail Traffic, Work Zones and
Standard Rail Flagging Procedures to be
followed
Design – Status of Railroads
• DBT will submit final construction plans
• DBT will obtain Railroad’s Flagging Services
• DBT will submit ROW application, scope of
work, schedule and insurance requirements
• Work will not commence on railroad ROW until
an executed construction agreement is
received
Design – Status of Permit Approvals
• Permit for MOT impacts to the Shoreway
submitted to ODOT (based on permitted
lane closures)
• DBT to present MOT plan to ODOT if full
closure of the Shoreway is requested
• DBT will likely need MOT plan and
permit for Erieside Ave from Cleveland
Design – Status of FAA Approvals
FAA/BKL:
• Notice of Actual Construction must be
filed within 5 days after construction
reaches its greatest height
• Separate notice will need to be filed if
the construction equipment used will
exceed 174 feet above ground level.
Design – Status of Property
Property Owners on the Project Include: • The County of Cuyahoga, Ohio
• The City of Cleveland, Ohio
• Pennsylvania Lines (Norfolk Southern)
• National Railroad Passenger Corporation
• State of Ohio Department of Natural Resources
Utilities (Anticipated Relocations)
Storm Sewer
Water Main
Electric (Relocation by Cleveland Public Power)
*Gas Line (Relocation by Dominion)
*Telecommunications (Relocation by AT&T and 3rd Party Providers)
* (DBT to investigate providing concrete cap over
existing utilities in lieu of relocation)
Procurement
• Bridging Design-Build Project Delivery
• Open Book GMP Process
• Initial Cost Elements (Part I of RFP Process) --
Fee, General Conditions, Proposed Contingency
• Parallel GMP Development Process
• Meaningful Stipend to Finalists
• County Procurement Vendor Requirements
• Inclusion Goals
• 30% SBE
• Best Value proposal for local, minority and low
income labor and enterprise participation
• Prevailing Wage
• Performance and payment bond (SDI permitted at sub
level)
Procurement
• Subcontractor Bidding
• Prequalification
• Best value selection (may include target price
design/assist subcontracts)
• Self-performance permitted with restrictions
• Contingency Management/Reduction Plan
• Prompt Payment and Issue Resolution
• Reasonable Delay Liquidated Damages
• Reasonable Limitation on Design Liability (in
conjunction with approved insurance plan)
Selection Process
RFQ followed by Two-Part RFP Process:
• Part I: Best-Value Selection
• Shortlist two teams
• Part II: Selection of DBT based on:
• Detailed technical proposal
• Proposed Schedule
• Guaranteed Maximum Price
Schedule
Procurement Release Dates:
RFQ (Early August 2015) subject to approval • Quals Package Due 3 weeks after
RFP Phase I early September 2015 • Shortlisting (Selection of two teams)
RFP Phase II early October 2015 • Technical Proposal and GMP due early
February 2016
Design-Build Team selected in early 2016
Schedule
Project Delivery Timeframe:
• Contract Executed with Design-Build Team
in early 2016
• Construction begins Summer 2016
• Construction complete 2017