from 3.5 tev to 7 tev: solution for the interconnect consolidation francesco bertinelli cern –...
DESCRIPTION
CERN Machine Advisory Committee 2nd Meeting – 26 April, 2010. From 3.5 TeV to 7 TeV: Solution for the interconnect consolidation Francesco Bertinelli CERN – Technology Department – MSC Group. Who is studying the solution and how? What does the new design look like? - PowerPoint PPT PresentationTRANSCRIPT
From 3.5 TeV to 7 TeV:Solution for the interconnect
consolidationFrancesco Bertinelli
CERN – Technology Department – MSC Group
20 minutes presentation, 10 minutes discussion: 26 slides
CERN Machine Advisory Committee2nd Meeting – 26 April, 2010
Who is studying the solution and how? What does the new design look like? How will it be implemented?
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
2
Splices Task Force
Mandate November 2009 (35th LMC, 4 Nov. 2009)To review the status of all superconducting splices in the LHC machine and prepare the necessary consolidation actions for 7 TeV operation.
Time frame:6-8 months starting November 2009. Originally to prepare for a shutdown 2010-2011: plans for the main IC splices maintained after Chamonix2010 (→ shutdown 2012).
Participation: 12 members from different CERN groups and departments. P. Limon (Tevatron), K.-H. Mess (Hera), RHIC this week
www.cern.ch/splicesF. Bertinelli, N. Catalan Lasheras, P. Fessia, C. Garion, S. Mathot, A. Perin, C. Scheuerlein, S. Sgobba, H. ten Kate, J.-P. Tock, A. Verweij, G.
Willering
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
3
Reminder from Chamonix2010Energy tRB [s] Max. Raddit,RB [mW] tRQ [s] Max. Raddit,RQ [mW]
3.5 TeV 50 76 10 80
5 TeV 75 43 15 41
7 TeV 100 11 20 14
by considering unbiased data, ~15% splices would need redoing from R16 ( = copper stabiliser continuity) alone;
but segment measurements cannot identify them precisely enough (for MQ in particular), plus need to open all M sleeves for a given segment, estimate ~90% of sleeves;
if in addition we consider repairs from visual and preference towards systematically adding a shunt/clamp, we conclude:
Open all W interconnects and cut open all M sleeves, make local R16 measurement, redo ~20% splices, add shunt to 100% splices
from
A. V
erwe
ij
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
4
Insulation and transversal restraint: injection molding in RYTON (PPS)
Sn-Pb solder for
shunt
Mechanical clamping (not
present in Tevatron and Hera …)
but same Sn-Ag solder where we
redo splices
For latest update see Splices Task Force
meeting no.17:https://espace.cern.ch/lhcsplices/Meeting%2017/default.aspx
The consolidated main IC splice
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
5
Rationale behind the design i/ii “Flexible” shunts
• e.g. Braids or lamellar construction (EMS-DE)• Should adapt to existing defects• Avoid in-situ machining and copper swarf• Stress-free (or as low as possible) Sn-Pb interface: limit risk of
potential degradation• Designed for 13 kA. Critical parameters are thickness and
unsoldered length (→ difficult to achieve flexibility with 10 mm ...)
Solder 60Sn-40Pb• Lower melting point than Sn-Ag• “classic” solution (Tevatron, Hera)• ... but additional safety requirements: Safety Commission
already involved
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
6
Rationale behind the design ii/ii Mechanical clamp
• Shall not depend on solder strength• Designed to survive ramp-down time
Insulation• Combines electrical function and mechanical restraint to
bending• Allows efficient cooling from LHe• Ease of assembly• Current question: Include additional insulation?
nQPS• Build-in monitoring of segment resistances in time• Dedicated resistance measurement campaigns scheduled in
Operations General approach: seek redundancy and safety, do not want to
intervene again (but no paranoia ...)
2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
716 March, 2010
13 kA IC: 3 directions for development
13 kA coordination
P. Fessia
13 kA interconnect
re-development
Shunt development
Insulation development
~500 splices redone in 2008-09
Improved process and QC Further improvements:
• loss of solder• avoid cutting spools• Process speed
Shunt geometry Solder options Soldering process
• Inductive (as for splice)• Resistive oven (“classic”)• “Fast” resistive
Mechanical clamp
FEA computations Materials, availability, costs Design insulation test
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
8
13 kA splice and process improvements
Optimise temperature profile• Thermocouples• Optimise geometry of inductive
coils
Simplify mechanics for easier use• verify the minimum force to get a
good joint (samples at 3 level of force 50%, 25%, 15%) → avoid cutting spools
• Include external water cooling after soldering → faster process
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
9
Eight measurement points located on the upper surface of the bus-bar.
Temperature sensors: Thermocouples type K with Inconel sleeve. Tester: Data logger by ATP Messtechnik (Sampling Time = 10s). Standard inductive soldering procedure. Kapton stripes around the interconnection to avoid Sn flow off.
Precise measurement of temperature profile
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
10
A simplified 3D magneto-static model of the inductor and of the bus-bar has been done.
The aim of the model is to understand the relationship between the field and temperature profiles along the interconnection, during the soldering plateau.
Optimisation of temperature profile
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
11
Shunt soldering process
Slow process, resistive oven
Fast process development.
Resistive micro welding
Room temperature tensile testing [kN]
6.1 ± 0.9 6.5 ± 0.2
Liquid nitrogen tensile testing [kN]
7.1 ± 0.9 7.9 ± 0.1
Liquid He tensile testing [kN]
Resistive oven “Fast” resistive process Inductive soldering
(possibly several shunts in parallel)
Note: 550 N required
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
12
Baseline is 60Sn-40Pb, will be fully developed first Other studies will be performed later, same temperature as
60Sn-40Pb Verification of theoretical mechanical properties still to be
checked
Other alloys that we will study
Alloy Melting temp. rangeSn77.2-In20-Ag2.8 175-187 C
In96.8-Ag3.2 157 CIn90-Ag10 157-210 C
Sn62-Pb34-Sb0.5-Ag3 180-187 CIn80-Ag5-Pb15 142-149 C
2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
13
Insulation studies
Max displacement reduced from 0.25 mm to 0.06 mm
and displaced out of the connection and far from the
shunt
26 April, 2010
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
14
13 kA IC Quality Control Progressing in parallel to IC work First tests of electrical resistance
at warm Launching feasibility studies with
EMPA (CH) and BAM (DE)
Defect type 3
A B
Defect type 2
Defect type 1
Ultrasonics test
Shunt contact resistance
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
0 2 4 6 8 10 12 14 16 18 200
10
20
30
40
50
60
Current (kA)R
unaw
ay t
ime
(s)
Quadrupole busbar, constant current 2 shunted defects measured (3 mm thick, 6 –
10 mm non-soldered length)
No shunt
Shunted
Shunts show a large improvement of stability However, results are not directly applicable to the LHC
machine situation: → simulation work
FRESCA results and “proof of principle” test See L. Bottura 27 April
15
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
16
In SM18 two special SSS cold masses in series (MQM for Q8 and Q9)
the M1 and M3 busbars are not connected to the magnet, hence no inductance during splice testing
in preparation for July 2010
Final Validation Test
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
17
Review
Formal reviews will be organised:• for the main IC splice design and process• two stages: before Validation Test and end 2010• Composition?
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
18
Scenario for implementation Series experience = real data
• Average 30 IC activities per week• Capacity designed for 40 IC activities per week
Plan 2012 intervention to 50 IC activities per week (ambitious goal)• repair ≠ new • once work starts there will be huge pressure, many intervenants,
little possibility for adaptations → do not count on learning curve• So many aleas at this stage → resist temptation to “squeeze”
planning too much already now Organise work as a train
• Proceed to adjacent sector (→ do not jump), extend over 2-3 sectors
• keep General Access mode as long as possible (→ cooldown and power as late as possible)
• there will be additional work and surely unexpected work (→ Special Interventions Team)
See K. Foraz 27 April
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
19
Sector 1-2 production
0
5
10
15
20
25
30
35
1-M
ar-0
7
15-M
ar-0
7
29-M
ar-0
7
12-A
pr-0
7
26-A
pr-0
7
10-M
ay-0
7
24-M
ay-0
7
7-Ju
n-07
21-J
un-0
7
5-Ju
l-07
19-J
ul-0
7
2-A
ug-0
7
16-A
ug-0
7
30-A
ug-0
7
13-S
ep-0
7
27-S
ep-0
7
11-O
ct-0
7
25-O
ct-0
7
8-N
ov-0
7
Num
ber o
f IC
per
wee
k
Solder main splices
Weld M sleeves90% work in 11 wks …
… but last 10% work in 9 wks
Series experience: soldering busbars
from P. Fessia
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
20
Length of shutdown: estimate @50 IC/week
Closing W
VAC sector leak test
Holes and NC
wk 9 wk 10 wk 11
Holes and NC
wk 13 wk 14
Welding M sleeves
wk 12
Repairs
wk 7
ELQA
Opening W
Cutting M sleeves
QC, R16, segment resistance
wk 6
Sect
or 7
-8
wk 3 wk 4 wk 5wk 1 wk 2
VAC QC bellows and protection
Spools and insulation
Solder shunt
Desolder/resolder/shunt splices
QC Welding
wk 8
QC splices/shunts
The next sector ends 5 weeks later and so on ...
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
21
Activity QuantityExisting at
CERNTo come in
additionComments
Opening W 100% 1 20 FSUs as in 2008-09 (15 openings or closing per day)
VAC QC bellows and protection 100% 2 3 Project Associates?
Cutting & deburring M sleeves 100% 6 5 1 Team Leader, 7 mechanics cutting, 3 helpers
QC, R16, segment resistance 100% 2 4 Project Associates?
Solder shunt 100% 5 5 Project Associates?
Desolder/resolder/shunt splices 20% 2 4 Project Associates?
Spools and insulation 10% 2 4 Project Associates?
QC splices/shunts 100% incl. incl.
ELQA 100% 4 10 Project Associates?
Welding M sleeves 100% 5 5 EN-MME
QC Welding 100% 2 3 EN-MME "Institut de Soudure" visual control
Closing W 100% incl. incl.
Other 15 5 VAC (40-30), thermometers, IC QC, logistics, coordination …
Totals 46 68
DN200 4 sectors 2 15 Organise DUBNA and FSU
Resources for splices consolidation
Need to maintain a balance between “existing/experienced” resources and “newcomers”
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
22
Cost estimate of splices consolidationOnly material costs: FSU and Project Associates included, EN-MME jobs for weldingAssume all 8 sectors consolidated (start IC work in January 2012, scenario 49 weeks)
NOT included: splices development work in 2010 and 2011 "other" shutdown activities (e.g. DN200, etc.): note important implications on availability of CERN personnel VAC, ELQA, Cryo costs unknown complications/costs (at this stage) due to radioprotection constraints
kCHF %
Main components 2080 14%
Production tooling 1890 13%
Interconnection workOpening and closing W bellows, repair screens 2300 16%FSU and EN-MME welding 5100 35%
Quality Controlsplices and welding 1200 8%Project Associates Team (10 people) 880 6%
Logistics 995 7%
Vacuum activities … my first guess: 6 FSU - 1 year, 700 kCHF
ELQA activites … my first guess: 10 Proj Ass., 880 kCHF
Cryogenic activities …He for pressure tests 250 2%
Total 14695 100%
21.4 MCHF plus preparation in 2010-11
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
23
DN200 (arc pressure relief nozzles) 7-8, 8-1, 2-3, 4-5 (partly)Connection cryostats 7-8, 8-1, 2-3, 4-5Vacuum leaks 3-4, others?N line connections to check 7-86kA praying hands to check 7-8Spool connections to investigate/repair 8-1, others?Replace magnets? (damaged nested bellows, SC cable, quench heaters, IFS box …)
~2-4 cases (e.g. QBBI.10R7, QBQI.10L5 araldite repair)
Early dipole Busbars 1 to 10 in SSS Mainly 7-8Y-lines 7-8, 8-1, others?DFBA flexibles (and some splices?)Inner triplets copper braids Points 1, 2, 5 and 8Prepare and replace Q5L8 (SC corrector)
4-5
Stand Alone Magnets He guards 7-8, 2-3Damaged radiation/thermal screens All sectorsPIMs RF ball test, a few preventive
replacements, no global replacements?… 35 NCR, “closed with warning”, HWC cases
Additional magnets/splices work
a considerable amount of non-standard work !!!
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
24
Shutdown and resources issues Moving magnets at Point 3 for collimators?
• Same resources involved → there will be an inevitable time impact in the 2012 shutdown
• Surface preparation work (busbar area setup and work, ….) New Collaboration Agreement for Project Associates
• we will first use all available resources on site, …• … but some resources will need to continue other critical
activities• looking to set up a new Collaboration Agreement (“a la” Krakow
Institutes for series production)• otherwise FSUs• and integrate first persons with existing resources already in
2010 Xmas 2010 “Technical Stop”:
• Could we consolidate 1 sector? → power and test the consolidated solution (and magnets), learning could allow optimization of 2012 shutdown
• … or (not “and”) some of the “additional magnets/splices work”• If so needs to be decided by June 2010 (advice?)
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
25
Analysis of circuits 13 kA: inside DFBAs in particular 6 kA analysis started:
• inventory of splices present: Points 2 and 4 done
• Study failure mechanisms (multiple failures), quench detection, energy extraction → risk analysis
Slow progress (resources taken on LHC startup)Praying
hands too!
26 April, 2010 2nd MAC – From 3.5 TeV to 7 TeV- Francesco Bertinelli
26
Conclusions
13 kA IC: we have a candidate design, first test evidence is promising, Final Validation results by August
Scenario for 2012 Shutdown for 13 kA IC exists
Highlighted issues and current questions where advice is welcome