form-i for seeking clearance for project attracting...
TRANSCRIPT
1
Form-I for seeking clearance for project attracting CRZ notification
Basic information
Name of the Project Resort project at VarachaPatta, Guhagar, Ratanagiri.
Location or site alternatives under
consideration
S. no. 53/1,55/1 at VarachaPatta, Guhagar, Ratanagiri.
Latitude 17°29'39.41"N
Longitude 73°11'17.62"E
Location Map is enclosed as Annexure-I
Size of the project (in terms of total area) Total plot area is 4070 m2
CRZ classification of the area CRZ-III
CRZ Map is enclosed as Annexure-II
Expected cost of the project Rs. 2,00,00,000 / -
Contact Information
Mr.Suhas M. Ponkshe/MrNitin M Ponkshe
ShriArihant co-op HsgSoc, Plot no. 23, Flat no. B105,
Sector 16A, VASHI – 400703 Maharashtra
Near State Board building
Mob:9867612678
Email: [email protected]
(II) Activity
1. Construction, operation or decommissioning of the Project involving actions, which will cause
Physical changes in the locality (topography, land use, changes in water bodies, and the like)
Sr.no. Information/Checklist
confirmation Yes/No
Details thereof (withapproximate quantities
/rates,wherever possible) with sourceof
information data
1.1
Permanent or temporary change
in land use,land cover or
topography including increase
inintensity of land use.
No There is no permanent or temporary change in land
use, land cover or topography.
1.2
Details of CRZ classification as
per theapproved Coastal Zone
Management Plan?
CRZ-III
As per the CRZ map prepared by NCSCM,
Chennai, the proposed project activity comes
under CRZ-III category.
1.3 Whether located in CRZ-I area? No -
2
1.4 The distance from the CRZ-I
areas. No
Development activities are proposed beyond NDZ
i.e. 200 m from high tide line.
1.5
Whether located within the
hazard zone as mapped by
Ministry of Environment and
Forests/National Disaster
ManagementAuthority?
No -
1.6
Whether the area is prone to
cyclone, tsunami, tidal surge,
subduction, earthquake etc.?
No None
1.7 Whether the area is prone for
saltwateringress? No -
1.8 Clearance of existing land,
vegetation and buildings? No -
1.9 Creation of new land uses? No Open land will be developed for tourism which is
in accordance with local development rules.
1.10 Pre-construction investigations
e.g. bore hole, soil testing? Yes
Geotechnicalinvestigation will be conducted for
the proposed project site.
1.11 Construction works? Yes
S.
No
Project Component Area
in m2
1 COTTAGE 546.84
2 SUITES 149.24
3 ADMIN 39.49
4 CLUB HOUSE 40.56
Tota
l
762.50
1.12 Demolition works? No --
1.13
Temporary sites used for
construction works or housing of
construction workers?
No --
3
1.14
Above ground buildings,
structures orearthworks including
linear structures, cut and fill or
excavations
Yes
Nearly leveled ground, cutting filling nearly
balances, top-soil used for greening, excavation in
the form of rubble will be partly used for back-
filing and as sub-structure for roads.
1.15 Underground works including
mining ortunneling? No None
1.16 Reclamation works? No --
1.17
Dredging/reclamation/land
filling/disposal of dredged
material etc.?
No --
1.18 Offshore structures? No --
1.19 Production and manufacturing
processes? No --
1.20 Facilities for storage of goods or
materials? No Storage facilities are not envisaged
1.21 Facilities for treatment or disposal
of solid waste or liquid effluents? Yes
STP for treatment of sewage during the operation
phase.
Segregation of solid waste into non-biodegradable
and biodegradable waste in the construction and
the operational phase.
Biodegradable waste will be treated in an OWC
during the operational phase.
Segregation of Non-biodegradable waste into
recyclable & non-recyclable during operational
phase.
Recyclable waste: Will be handed over to the
recyclers
Non-Recyclable waste: Will be handed over to the
local authorized vendors during the operational
phase.
Dried sludge from STP: Will be used as manure
after treatment during operational phase.
1.22 Facilities for long term housing of Yes Existing staff quarters available
4
operational workers?
1.23 New road, rail or sea traffic
during construction or operation? No
During construction and operationstage the existing
facilities will be used.
1.24
New road, rail, air waterborne or
othertransport infrastructure
including new oraltered routes
and stations, ports, airports etc?
No --
1.25
Closure or diversion of existing
transportroutes or infrastructure
leading to changes intraffic
movements?
No No closure or diversion of existing transport routes
or infrastructure.
1.26 New or diverted transmission
lines orpipelines? No --
1.27
Impoundment, damming,
culverting,realignment or other
changes to the hydrologyof
watercourses or aquifers?
No --
1.28 Stream and river crossings? No --
1.29 Abstraction or transfers of water
form groundor surface waters? No Nil
1.30
Changes in water bodies or the
land surfaceaffecting drainage or
run-off?
No Nil
1.31
Transport of personnel or
materials forconstruction,
operation, decommissioning?
Yes Labours will be transported to site during
construction period only.
1.32
Long-term dismantling or
decommissioning, restoration
works?
No Nil
1.33
Ongoing activity during
decommissioningwhich could
have an impact on
theEnvironment?
No Nil
5
1.34
Influx of people to an area in
either temporarily or
permanently?
No
During Construction Phase:
Maximum 20 workers during construction.
During Operation Phase:
There will be an influx of approx. 60-80people in
the proposed project which comprises of the
visitors.
1.35 Introduction of alien species? No None.
1.36 Loss of native species or genetic
diversity? No Proposed area is not in an eco-sensitive area
1.37 Any other actions? No None
2. Use of Natural resources for construction or operation of the Project (such as land, water,materials or
energy, especially any resources which are non-renewable or in short supply):
Sr. No. Information/ checklist
confirmation
Yes/
No
Details thereof (withapproximate quantities
/rates, wherever possible) with source of
information data
2.1 Land especially undeveloped or
agriculturalland (ha)
No Proposed development is in the existing land under
development.
2.2 Water (expected source &
competing users) unit: KLD
Yes During Construction Phase:
From water tankers(for construction): 5 m3/day
For Workers :Water of potable quality from tankers:
2.25 m3/day
During operational Phase:
Source of water: Local Authority
Domestic: 5 m3/day
Flushing: 3 m3/day
Gardening(Recycled water):2 m3/day
2.3 Minerals (MT) No --
2.4 Construction material – stone,
aggregates, sand/soil (expected
source – MT)
Materials like sand, gravel, cement will be procured
from nearby licensedsources/ reputed manufacturers
as per requirement.
2.5 Forests and timber (source – MT) Yes Timber required for doors sourced from local
suppliers.
6
2.6 Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW)
Yes Source:MSEDCL
During Operation phase-
Connected load :105KW
Maximum demand:84.48
DG Sets: 1 DG set of 100kVA
2.7 Any other natural resources (use
appropriate standard units)
No Nil
3. Use, storage, transport, handling or production of substances or materials, which could be harmful to
human health or the environment or raise concerns about actual or perceived risks to human health.
Sr
No.
Information/checklist
confirmation
Yes/
No
Details thereof (withapproximate quantities
/rates,wherever possible) with source of
information data
3.1 Use of substances or materials,
which are hazardous (as per
MSIHC rules) to human health or
the environment (flora, fauna, and
water supplies)
Yes Minor quantities of empty paint cans andwaste oil
will be generated during construction phase.
3.2 Changes in occurrence of disease
or affect disease vectors (e.g.
insect or water borne diseases)
No None
3.3 Affect the welfare of people e.g.
by changing living conditions?
No
3.4 Vulnerable groups of people who
could be affected by the project
e.g. hospital patients, children, the
elderly etc.,
No None
3.5 Any other causes, that would
affect local communities, fisher
folk, their livelihood, dwelling
units of traditional local
communities etc
No None
7
4. Production of solid wastes during construction or operation or decommissioning (MT/month)
Sr
No.
Information/checklist
confirmation
Yes/
No
Details thereof (withapproximate quantities
/rates,wherever possible) with sourceof
information data.
4.1 Spoil, overburden or mine wastes No --
4.2 Municipal waste (domestic and or
commercial wastes)
Yes
Type Nos.
Solid Waste generation (kg/day)
Biodegra
dable
Non
DegradableTotal
Guest59 19 8 27
Staff
4.3 Hazardous wastes (as per
Hazardous Waste Management
Rules)
No Minor quantities of empty paint cans and waste oil
will be generated during construction phase, which
will be sent to authorize contactor.
4.4 Other industrial process wastes No Nil
4.5 Surplus product No Nil
4.6 Sewage sludge or other sludge
from effluent treatment
Yes Dried sludge from STP will be used as manure for
landscaping.
4.7 Construction or demolition
wastes
Yes Solid waste generation during construction phase is
mainly due to excavation in the form of rubble and
soil. Part of this soil and rubble will be used for
back filling and remaining material will be disposed
by covered trucks to the authorized sites if required.
4.8 Redundant machinery or
equipment
No Nil
4.9 Contaminated soils or other
materials
No Nil
4.10 Agricultural wastes No Nil
4.11 Other solid wastes No Nil
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr)
Sr No. Information/checklist
confirmation
Yes/
No
Details thereof (withapproximate quantities
/rates,wherever possible) with source
8
of information data
5.1 Emissions from combustion of
fossil fuels from
stationary or mobile sources
Yes Operation of Diesel generators and Construction
machineries may cause emission of SO2, NOx and
CO which will be monitored periodically and to
lower the point source emissions.
5.2 Emissions from production
processes
No --
5.3 Emissions from materials
handling includingstorage or
transport Emissions from
materials handling
includingstorage or transport
No The project may cause rise in dust levels during
construction
phase.Watersprinklingwillbedoneatregularintervalst
oreducecontrolofdustgeneration.
5.4 Emissions from construction
activities includingplant and
equipment
No No major Plant and Equipment source at site.
5.5 Dust or odours from handling of
materialsincluding construction
materials, sewage and waste
No Dust generation will be controlled as described
above at serial no 5.3. Proper ventilation will be
provided around STP and solid waste management
facilities for odour control.
5.6 Emissions from incineration of
waste
No --
5.7 Emissions from burning of waste
in open air (e.g.slash materials,
construction debris)
No --
5.8 Emissions from any other sources No --
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
Sr.
No.
Information/checklist
confirmation
Yes/
No
Details thereof (withapproximate quantities
/rates,wherever possible) with sourceof
information data
9
6.1 From operation of equipment e.g.
engines,ventilation plant, crushers
Yes For control of noise following measures shall be
adopted:
Regular noise monitoring to be scheduled to
maintain the noise level within the levels
prescribed by CPCB during day and night time
Provision of ear plugs to workers
Use of good efficiency mufflers
Regular maintenance of noise generating
machinery
No noise polluting work in night shifts
6.2 From industrial or similar
processes
No --
6.3 From construction or demolition Yes Noise from the machineries shall be kept below the
threshold noise level. Personnel Protection
Equipment (PPE) will be provided to workers
during construction activities.
6.4 From blasting or piling No
6.5 From construction or operational
traffic
Yes During Construction phase:
Proper traffic management for the construction
vehicles
Regular maintenance of vehicles with suitable
enclosures and intake silencers
Planning and ensuring effective implementation of
the waste movement plan for loading and offsite
movement in non-traffic hours.
During Operation Phase :
Install traffic control measures to regulate the flow
of traffic
Assign traffic wardens to regulate flow of project
traffic during peak hours
6.6 From lighting or cooling systems No --
6.7 From any other sources No --
10
7. Risks of contamination of land or water from releases of pollutants into the ground or into sewers,
surface waters, groundwater, coastal waters or the sea:
Sr
No.
Information/checklist
confirmation
Yes/
No
Details thereof (withapproximate quantities
/rates,wherever possible) with sourceof
information data
7.1 From handling, storage, use or
spillage ofhazardous materials
No During construction stage there may be
storage/handling of hazardous materials for various
construction related activities.
Such materials shall be stored and handled as per
the provisions of the manufacturer, storage and
import of Hazardous Chemical Rules, Hazardous
Wastes (Management and Handling)
Rules and Amendments thereof.
7.2 From discharge of sewage or
other effluents towater or the land
(expected mode and place
ofdischarge)
No During Construction Phase:
Mobile sanitary toilets will be installed and toilets
will be regularly maintained by Authorized Vendor
During Operation Phase:
The treated sewage will be reused for flushing and
gardening within the premises. Excess treated
sewage will be disposed off to the existing sewer
line.
7.3 By deposition of pollutants
emitted to air into theland or into
water
No Dust will be generated during construction phase
from earthworks and movement of vehicles.
Appropriate fugitive dust control measures,
including watering, water sprinkling of exposed
areas and dust covers for trucks, will be provided
to minimize any impacts.
DG exhaust will be discharged at stipulated height
by providing adequate stack height to the DG sets
7.4 From any other sources No Nil
7.5 Is there a risk of long term build
up of pollutants in the
environment from these sources?
No Nil
11
8. Risk of accidents during construction or operation of the Project, which could affect human health or
the environment.
Sr
No.
Information/checklist
confirmation
Yes/
No
Details thereof (withapproximate quantities
/rates,wherever possible) with sourceof
information data
8.1 From explosions, spillages, fires
etc from storage,handling, use or
production of
hazardoussubstances.
No --
8.2 From any other causes
No --
8.3 Could the project be affected by
natural disasterscausing
environmental damage (e.g.,
floods, Earthquakes, landslides,
cloudburst etc)?
No The proposed construction is made to withstand the
most adverse conditions.
9. Factors which should be considered (such as consequential development) which could lead
toEnvironmental effects or the potential for cumulative impacts with other existing or planned activities in
the locality.
Sr
No.
Information/checklist
confirmation
Yes/
No
Details thereof (withapproximate quantities
/rates,wherever possible) with sourceof
information data
9.1 Lead to development of
supporting utilities, ancillary
development or development
stimulated by the project which
could have impact on the
environment e.g.:
Supporting infrastructure
(roads, power supply, waste or
waste water treatment, etc.)
No
Supporting infrastructure is already in existence.
12
housing development
extractive industries supply
industries
other housing development
extractive industries supply
industries other
9.2 Lead to after-use of the site,
which could have an impact on
the environment
No The proposed project would be a permanent
establishment.
9.3 Set a precedent for later
developments
Yes Will create job opportunity in construction phase
and operation phase for support staff like security,
maintenance, household workers, shop keepers etc.
9.4 Have cumulative effects due to
proximity to other existing or
planned projects with similar
effects
No
III. Environmental Sensitivity
Sr.no
Areas
Name/
Identity Aerial distance (within 15 km)Proposed project locationboundary
1 Areas protected under international
conventions, national or local
legislation for their ecological,
landscape, cultural or other related
value
No -
2 Areas which are important or sensitive
for ecological reasons - Wetlands,
water courses or other water bodies,
coastal zone, biospheres, mountains,
forests
Yes Guhagar beach at 0.50 km to the West
3 Areas used by protected, important or
sensitive species of flora or fauna for
breeding, nesting, foraging, resting,
No -
13
over wintering, migration
4 Inland, coastal, marine or underground
waters
Yes Arabian Sea is at 0.50km to the West
5 State, National boundaries No -
6 Routes or facilities used by the public
for access to recreation or other tourist,
pilgrim areas
No -
7 Defense installations No
8 Densely populated or built-up area No
9 Areas occupied by sensitive man-made
land uses (hospitals, schools, places of
worship, communityfacilities) Areas
occupied by sensitive man-made land
uses(hospitals, schools, places of
worship, community facilities)
No -
10 Areas containing important, high
quality or scarce resources (ground
water resources, surface resources,
forestry, agriculture, fisheries, tourism,
minerals)
No Nil
11 Areas already subjected to pollution or
Environmental damage. (those where
existing legal environmental standards
are exceeded)
No Nil
12 Areas susceptible to natural hazard
which could cause the project to
present environmental problems
(earthquakes, subsidence, landslides,
erosion, flooding or extreme or adverse
climatic conditions)
Yes The project falls under Seismic Zone III
(moderate earthquake zone) as per the
Seismotectonic Atlas of India. The project
area lies beyond the cyclone zone
andtherefore the risk of cyclones is not
significant. During the design stage, the
effects from natural disasters will be
considered and necessary precautionary
measures would be built-in / implemented.
14