Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

APPENDIX I (See paragraph – 6)    F O R M – 1 (I)      Basic Information 

 Sr. No.  

Items  Details 

1.  Name of the project/s  “Proposed Project”   At Taloja, Navi Mumbai 

2.  S.No. in the schedule  8 (a)  

3.  Proposed capacity/area/length/tonnage  to  be handled/ command area/lease area/ number of wells to be drilled 

Total Plot Area  = 6399.13 Sq. M Built – Up Area = 9631.536 Sq. M (FSI) Built – Up Area. = 17090.30  Sq. M (Non FSI) Total Construction Area= 26721.836 Sq. M. 

4.  New / Expansion / Modernization New 

5.  Existing Capacity/ Area etc.

Total Plot Area  = 6399.13 Sq. M Built – Up Area = 9631.536 Sq. M (FSI) Built – Up Area. = 17090.30  Sq. M (Non FSI) Total Construction Area= 26721.836 Sq. M. 

6.  Category of Project i.e. ‘A’ or ‘B’ Category  ‘B’7.  Does it attract the general condition? 

If Yes, please specify. NA

8.  Does it attract the specific condition? If Yes, please specify. 

No  

9.  Location    Plot/Survey/Khasra No. Plot no. 114, 115, 116, Sector­ 14   Village   Taloja  Tehsil  Raigad  District   Raigad  State   Maharashtra10.  Nearest  railway  station/airport 

along with distance in kms. Taloja Railway Station – 1KM  Mumbai Airport– 44.5 KM Proposed Navi Mumbai Airport‐ 13.3 KM 

11.  Nearest  town,  city,  district headquarters  along with  distance  in kms. 

Navi Mumbai Municipal Corporation

12.  Village  panchayats,  Zila  Parishad, Municipal  Corporation,  Local  body (complete  postal  addresses  with telephone nos. to be given) 

Navi Mumbai Municipal Corporation

13.  Name of the applicant  Shelter Builders and Developers 14.  Registered address  NL- 6/9/03, Sector- 15, Nerul, Navi Mumbai 400 706.

Page 3: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

15.  Address for correspondence:    Name   Mr. Rabbani Khan    Designation (Owner/Partner/CEO)  Director   Address  NL- 6/9/03, Sector- 15, Nerul, Navi Mumbai 400 706.   Pin Code  400706  Authorized Representative Mr. K Srinivasan  Contact No.  +919820641612  E‐mail  [email protected]   Telephone No.   Fax No. 16.  Details  of  Alternatives  Sites

examined,  if  any.  Location  of  thesesites  should  be  shown  on  aToposheet 

No  

17.  Interlinked Project  NA18.  Whether  separate  application  of

interlinked  project  has  beensubmitted? 

NA

19.  If Yes, date of Submission NA20.  If no, reason  NA21.  Whether  the  proposal  involves

approval/clearances  under:  if  yes,details of the same and their status tobe given. The Forest (Conservation) Act, 1980? The Wildlife (Protection) Act, 1972? The C.R.Z Notification, 1991?  

No 

22.  Whether  there  is  any  GovernmentOrder  /Policy  relevant/  relating  tothe site? 

NA

23.  Forest land involved (hectares) NA24.  Whether  there  is  any  litigation

pending  against  the  project  and/orland  in which  the project  is  proposeto be set up? Name of the court  Case No.  Orders/directions of the Court, if anyand  its  relevance with  the  proposedproject.  

No 

 

Page 4: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

  (II) Activity  

 1.  Construction, operation or decommissioning of  the Project  involving 

actions, which will cause physical changes in the locality (topography, land use, changes in water bodies, etc.) 

 Sr. No. 

Information/Checklist confirmation  

Yes/ No 

Details  thereof (with approximate quantities  /rates,  wherever possible)  with  source  of information data 

1.1  Permanent  or  temporary  change  in land  use,  land  cover  or  topography including increase in intensity of land use  (with  respect  to  local  land  use plan)   

No  Basically  land  is  Barren  land.  The proposed  project  site  is  designated for  the  intended  purpose  and  the proposed built‐up area is 26721.836  

1.2  Clearance of existing land, vegetation and buildings? 

No  NA 

1.3  Creation of new land uses? 

No  NA 

1.4  Pre‐construction  investigations  e.g. bore houses, soil testing? 

Yes Please  refer  Ground  water  quality Analysis Report. Annexure: 6 Soil Testing Report. Annexure: 7 

1.5  Construction works?  

Yes  About 26721.836  Will be construction work.  

1.6  Demolition works?  No  NA  

1.7  Temporary  sites  used  for construction  works  or  housing  of construction workers? 

Yes  During construction total 150 nos. of workers will be on site.   

1.8  Above  ground  buildings,  structures or Earthworks  including  linear structures, cut and fill or excavations   

  Plot  area  is  barren  land.  Excavated material  during  construction will  be used  for  landscape  and  backfilling therefore  there will  not be  any  solid waste  problem  from  the  generation of construction‐excavated earth.  

1.9  Underground works including mining or     tunneling? 

No NA 

1.10  Reclamation works?  No NA

1.11  Dredging?  No NA

Page 5: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

Sr. No. 

Information/Checklist confirmation  

Yes/ No 

Details  thereof (with approximate quantities  /rates,  wherever possible)  with  source  of information data 

1.12  Offshore structures?  No NA

1.13  Production  and  manufacturing processes? 

No NA 

1.14  Facilities  for  storage  of  goods  or materials?  

Yes For  the  temporary  storage  of  the construction material on the one side of the plot. 

1.15  Facilities for treatment or disposal of solid waste or liquid effluents? 

Yes Solid Waste Management a) During Construction phase:  Construction  debris will  be  used  for construction  site  itself  and  therefore there  will  not  be  any  solid  waste problem  from  generation  of construction‐excavated earth.   Septic  tank  and  soak  pit  will  be provided  for  proper  disposal  of liquid effluent.  b) During Operation Phase:­ Total  population  of  the  residential scheme is 980 nos. and Commercial scheme is 141 nos. For total 1121 nos For Residential and Commercial Quantity  of  solid  waste  –  476.25 kg/day i.e.0.48 T/day approx. Quantity of wet waste –   0.28 T/day  Quantity of dry waste – 0.20 T/day  Biodegradable  and  non biodegradable  waste  will  be segregated. Dry waste will be sent for recycling  and  wet  waste  will  be treated  by  ‘Organic  Waste Converter’ for composting.  Liquid waste management  During construction: 50 M3/DAY Source: Tanker Water During operation: 

Page 6: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

Sr. No. 

Information/Checklist confirmation  

Yes/ No 

Details  thereof (with approximate quantities  /rates,  wherever possible)  with  source  of information data 

Source: CIDCO o Total  Water  Demand  is  148.91 

M3/DAY o Domestic Water Demand is 90.32 

M3/DA o Flushing  water  demand  is  48.33 

M3/DAY o Landscape  Water  Requirement 

39.39 M3/DAY  o Total  treated  water  available 

124.79  M3/DAY o 113.85  M3/DAY  treated  water 

will be reused.  

1.16  Facilities  for  long  term  housing  of operational workers? 

No NA

1.17   New  road,  rail  or  sea  traffic  during construction or operation? 

No NA

1.18   New  road,  rail,  air  waterborne  or other  transport  infrastructure including  new  or  altered  routes  and stations, ports, airports etc? 

No NA

1.19  Closure  or  diversion  of  existing transport  routes  or  infrastructure leading  to  changes  in  traffic movements? 

No NA

1.20  New or diverted transmission lines or pipelines? 

No NA

1.21  Impoundment,  damming,  culverting, realignment  or  other  changes  to  the hydrology      of  watercourses  or aquifers? 

No NA

1.22  Stream crossings?  No NA 

1.23  Abstraction  or  transfers  of  water form ground or surface waters? 

Yes  During  Construction  phase  CIDCO water supply / Tanker water will be used for the construction purpose  

1.24  Changes  in water  bodies  or  the  land surface affecting drainage or run‐off? 

No NA

Page 7: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

Sr. No. 

Information/Checklist confirmation  

Yes/ No 

Details  thereof (with approximate quantities  /rates,  wherever possible)  with  source  of information data 

1.25  Transport  of  personnel  or  materials for  construction,  operation  or decommissioning? 

Yes Only material transport. Approx. 10 trucks per day. 

1.26  Long‐term  dismantling  or decommissioning  or  restoration works? 

No NA

1.27  Ongoing  activity  during decommissioning  which  could  have an impact on the environment? 

No NA

1.28  Influx  of  people  to  an  area  in  either temporarily or permanently? 

Yes Influx During construction:  150 Nos. workers & 35 Nos. Staff  Influx  during  operation: Approximately  1121  persons  are going  to  reside  in  this  Residential  & commercial complex.  

1.29  Introduction of alien species? No  NA

1.30  Loss  of  native  species  or  genetic diversity? 

No  NA  

1.31  Any other actions?  No  NA 

 2.  Use of Natural resources for construction or operation of the Project (such 

as  land, water, materials  or  energy,  especially  any  resources which  are non­renewable or in short supply): 

 Sr. No. 

Information/checklist confirmation  

Yes/ No 

Details  thereof  (with  approximate quantities /rates, wherever possible) with source of information data 

2.1  Land  especially  undeveloped  or agricultural land (ha) 

No N.A

2.2  Water  (expected  source  & competing users) unit: M3/DAY 

Yes Liquid waste management  During construction: 50 M3/DAY Source: Tanker Water 

 During operation:  Source: CIDCO 

Page 8: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

Sr. No. 

Information/checklist confirmation  

Yes/ No 

Details  thereof  (with  approximate quantities /rates, wherever possible) with source of information data o Total  Water  Demand  is  148.91

M3/DAY o Domestic  Water  Demand  is  90.32 

M3/DA o Flushing  water  demand  is  48.33 

M3/DAY o Landscape  Water  Requirement 

39.39 M3/DAY  o Total treated water available 124.79  

M3/DAY o 113.85 M3/DAY  treated  water  will 

be reused. 2.3  Minerals (MT)  No NA2.4  Construction  material  – stone, 

aggregates,  sand  /  soil  (expected source – MT) 

Companies  authorized/  approved  local vendor 

2.5  Forests and timber (source – MT) No NA

2.6  Energy  including  electricity  and fuels  (source,  competing  users) Unit: fuel (MT), energy (MW)  

Source:  Maharashtra  State  Electricity Distribution Company Limited. ( MSEDCL) Total  Demanded  load  For  Project  = 2422.50 KW.  During Construction  Source  of  Power  Supply  For  Project  ‐ D.G Sets (75 KVA , 1 nos)     During Operation Source :‐‐ MSEDCL   Alternative  Back  Up:‐  Diesel  Generator (DG)  Set  for  lifts,  Common    Lighting, Water pumps & other essential services. Capacity  of  D.G.  Set  for  Common Amenities: 400KVA ‐ 2 Nos. 400 KVA for Fire  Pump  With  AMF  &  Auto  Load Sharing  Panel  with  Sound  Proof Enclosure  with  dB  level  not  greater than 75 dB (A).   

2.7  Any  other  natural  resources  (use appropriate standard units) 

NA

 

Page 9: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

3.       Use, storage, transport, handling or production of substances or materials, which  could  be  harmful  to  human  health  or  the  environment  or  raise concerns about   actual or perceived risks to human health. 

 Sr.  No. 

Information/Checklist confirmation 

Yes/ No 

Details  thereof  (with approximate quantities/ rates, wherever  possible)  with source of information data 

3.1  Use of substances or materials, which are hazardous (as per MSIHC rules) to human  health  or  the  environment (flora, fauna, and  water supplies) 

No NA

3.2  Changes  in  occurrence  of  disease  or affect  disease  vectors  (e.g.  insect  or water borne diseases) 

NoNA 

3.3  Affect  the  welfare  of  people  e.g.  by changing living conditions? 

No It  can  help  in  improving  the living standards of that area. 

3.4  Vulnerable  groups  of  people  who could  be  affected  by  the  project  e.g. hospital patients, children, the elderly etc., 

No NA

3.5  Any other causes  No NA 

4.  Production  of  solid  wastes  during  construction  or  operation  or decommissioning (MT/month) 

 

Sr. No. 

Information/Checklist confirmation 

Yes/ No 

Details  thereof  (with approximate  quantities/rates, wherever  possible)  with source of information data 

4.1  Spoil, overburden or mine wastes No Excavated material  will  be  used for back filling at the site. 

4.2  Municipal  waste  (domestic  and  or commercial        wastes) 

Yes Solid Waste Management b) During Operation Phase:­ Total  population  of  the residential  scheme  is  980  nos. and  Commercial  scheme  is 141 nos. For total 1121 nos For  Residential  and Commercial Quantity  of  solid  waste  –  693 kg/day i.e.0.44 T/day approx. 

Page 10: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

10 

Sr. No. 

Information/Checklist confirmation 

Yes/ No 

Details  thereof  (with approximate  quantities/rates, wherever  possible)  with source of information data 

Quantity  of  wet  waste  –      0.24 T/day  Quantity  of  dry  waste  –  0.20 T/day  Biodegradable  and  non biodegradable  waste  will  be segregated.  Dry  waste  will  be sent  for recycling and wet waste will  be  treated  by  ‘Organic Waste  Converter’  for composting.  

4.3  Hazardous wastes  (as  per  Hazardous Waste        Management Rules) 

No NA

4.4  Other industrial process wastes 

No NA

4.5  Surplus product  No NA

4.6  Sewage  sludge  or  other  sludge  from effluent        treatment 

YES Sludge from STP will be used as manure  for  Green  belt development at site. 

4.7  Construction or demolition wastes No Approx.  500  cu.  ft  Will  be earthwork  and  will  be  used  for back filling. 

4.8  Redundant machinery or equipment No NA

4.9  Contaminated soils or other materials No NA

4.10 Agricultural wastes  

No NA

4.11  Other solid wastes  

No NA

 

Page 11: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

11 

  5. Release of pollutants or any hazardous, toxic or noxious substances to air 

(Kg/hr)  

  Sr.  No. 

  Information/Checklist confirmation 

  Yes/ No 

Details  thereof  (with approximate quantities/rates, wherever  possible)  with source of information data 

5.1  Emissions  from  combustion  of  fossil fuels  from  stationary  or  mobile sources 

No NA

5.2  Emissions from production processes 

No NA

5.3  Emissions  from  materials  handling including   storage or transport  

No NA

5.4  Emissions from construction activities including plant and equipment  

No NA

5.5  Dust  or  odour  from  handling  of materials  including  construction materials, sewage and  waste  

Yes As per EMP

5.6  Emissions from incineration of waste 

No NA

5.7  Emissions  from  burning  of  waste  in open  air  (e.g.  slash  materials, construction debris)  

No NA

5.8  Emissions from any other sources 

No NA

              

Page 12: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

12 

6. Generation of Noise and Vibration, and Emissions of  Light and Heat: 

Sr. No. 

Information/Checklist confirmation 

Yes/ No 

Details  thereof  (with approximate  quantities/ rates, wherever possible) with source  of  information  data with  source  of  information data 

6.1  From  operation  of  equipment  e.g. engines, ventilation plant, crushers   

Yes Sources  of  noise  Pollution during  construction  phase  are machinery  like  compressor, Compactors,  Concrete  Plant, Cranes  and  transportation materials.  During  operation  phase DG  sets will be provided with Canopy to reduce noise and vibration.  

6.2  From industrial or similar processes 

No NA

6.3  From construction or demolition Yes As per EMP

6.4  From blasting or piling 

No NA

6.5  From  construction  or  operational traffic  

Yes As per EMP

6.6  From lighting or cooling systems 

No  NA

6.7  From any other sources No NA

 7.  Risks of contamination of land or water from releases of    pollutants into the 

ground or  into  sewers,  surface waters, groundwater,  coastal waters or  the sea: 

 

Sr. No. 

Information/Checklist confirmation 

Yes/ No 

Details  thereof  (with approximate  quantities/rates, wherever  possible)  with source of information data 

7.1   From  handling,  storage,  use  or spillage of hazardous materials 

No NA

7.2   From  discharge  of  sewage  or other      effluents  to  water  or  the land (expected mode and place of  discharge) 

No Sewage effluents will  be  treated and  reused  for  flushing, gardening areas.  113.85  M3/DAY  treated  water will be reused  

Page 13: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

13 

7.3  By deposition of pollutants emitted to air into the land or into water 

No NA

7.4  From any other sources 

No NA

7.5  Is there a risk of long term build up of  pollutants  in  the  environment from these sources? 

No NA

 8.  Risk  of  accidents  during  construction  or  operation  of  the  Project, which 

could affect human health or the environment  

Sr.  No. 

Information/Checklist confirmation 

Yes/ No 

Details  thereof  (with approximate  quantities/ rates,  wherever  possible) with  source  of  information data 

8.1  From  explosions,  spillages,  fires  etc from  storage,  handling,  use  or production of hazardous substances

No  NA 

8.2  From any other causes 

Yes There  is  a  risk  of  accident during  construction  however proper  safety measures will  be taken. 

8.3  Could  the  project  be  affected  by natural  disasters  causing environmental damage   (e.g. floods, earthquakes,  landslides,  cloudburst etc)? 

No Floods  and  landslides  are  not expected in the area.  Earthquake  proneness:  The area falls under Zone III as per IS­ 1893­2002. Hence relevant design parameters as per zone III  have  been  considered  for RCC design of the buildings.  Dynamic  analysis will  be  done by Response spectrum method. Importance  factor  1  special moment  resisting  frame  R‐5, Zone factor Z‐ 0.16. Annexure  10  (Seismic  Zoning Map of India.) 

   9.  Factors which  should  be  considered  (such  as  consequential  development) 

which  could  lead  to  environmental  effects  or  the  potential  for  cumulative impacts   with    other existing or planned activities in the locality 

 

Page 14: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

14 

Sr. No. 

Information/Checklist confirmation 

Yes/ No 

Details  thereof  (with approximate  quantities /crates,  wherever  possible) with  source  of  information data 

9.1  Lead to development of supportingfacilities,  ancillary  development  or development  stimulated  by  the project which could have impact on the environment e.g.: 

 •  Supporting  infrastructure  (roads, 

power  supply,  waste  or  waste 

water treatment, etc.) 

•   housing development 

•   extractive industries 

•   supply industries 

•   other 

Yes Housing development            There  are  many  industries  and colleges  in  the  vicinity  of  this project  site.  The  Proposed development  will  cater  the needs of the residents. 

9.2  Lead  to after‐use of  the  site, which could  have  an  impact  on  the environment 

No NA

9.3  Set  a  precedent  for  later developments 

No NA

9.4  Have  cumulative  effects  due  to proximity  to  other  existing  or planned  projects  with  similar  effects 

No NA

       

Page 15: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

15 

 (III)  Environmental Sensitivity  Sr. No. 

Areas  Name/ Identity 

Aerial  distance  (within 15 km.) Proposed project location boundary 

1  Areas  protected  under  international conventions,  national  or  local  legislation  for their  ecological,  landscape,  cultural  or  other related value 

No NA

2  Areas  which  are  important  or  sensitive  for ecological  reasons  ‐  Wetlands,  watercourses or  other  water  bodies,  coastal  zone, biospheres, mountains, forests 

Yes NA

3  Areas  used  by  protected,  important  or sensitive      species  of  flora  or  fauna  for breeding,  nesting,  foraging,  resting,  over wintering, migration 

No NA

4  Inland,  coastal,  marine  or  underground waters. 

No NA

5  State, National boundaries. No NA

6  Routes  or  facilities  used  by  the  public  for access  to  recreation  or  other  tourist,  pilgrim areas. 

No  

7  Defence installations  No NA

8  Densely populated or built‐up area Yes Census  Data  2001 Annexure: 11 

9  Areas  occupied  by  sensitive  man‐made  land uses  (hospitals,  schools,  places  of  worship, community facilities) 

Yes Census Data 2001 Annexure: 11  

10  Areas  containing  important,  high  quality  or scarce  resources.  (ground  water  resources, surface  resources,  forestry,  agriculture, fisheries, tourism, minerals) 

No NA

11  Areas  already  subjected  to  pollution  or  environmental  damage.  (those where  existing legal environmental standards  are exceeded) 

No NA

12  Areas  susceptible  to  natural  hazard  which could  cause  the  project  to  present environmental  problems.  (earthquakes, subsidence,  landslides,  erosion,  flooding  or extreme or adverse climatic conditions) 

No NA   

 (IV).Proposed Terms of Reference for EIA studies        N. A. 

Page 16: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

16 

 “I hereby given undertaking that the data and information given in the application 

and enclosures are true to the best of my knowledge and belief and I am aware that 

if any part of the data and information submitted is found to be false or misleading 

at any stage, the project will be rejected and clearance give, if any to the project will 

be revoked at our risk and cost. 

 Date: 04.12.2013  Place: Navi Mumbai  

   Mr. Zaid Khan 

                                                                                             NL- 6/9/03, Sector- 15, Nerul, Navi Mumbai 400 706  

                           

Page 17: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

17 

FORM ­ 1 A (Only for construction projects listed under item 8 of the Schedule)   CHECK LIST OF ENVIRONMENTAL IMPACTS  

(Project proponents are required to provide  full  information and wherever 

necessary  attach  explanatory  notes with  the  Form  and  submit  along with 

proposed environmental management plan & monitoring programme) 

       1.  LAND ENVIRONMENT       (Attach panoramic view of the project site and the vicinity)  

1.1. Will the existing land­use get significantly altered from the project 

that  is  not  consistent with  the  surroundings?  (Proposed  land­use must 

conform  to  the  approved Master  Plan  / Development Plan  of  the  area. 

Change of land­use if any and the statutory approval from the competent 

authority be submitted).  Attach Maps of (i) site location, (ii) surrounding 

features  of  the  proposed  site  (within  500  meters)  and  (iii)  The  site 

(indicating  levels  &  contours)  to  appropriate  scales.  If  not  available 

attach only conceptual plans.  

   The proposed land use is in conformity with the DP of the area.  

  

Annexure – 1  : Building perspective View  

Annexure – 2  : Master Plan  

Annexure – 3  : Site Location Map  

Annexure – 4   : Landscape plan 

 

Page 18: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

18 

 

1.2. List out all the major project requirements in terms of the land area, built up area, water consumption, power requirement, connectivity, community facilities, parking needs etc.  Total Area of the Plo   :  6399.13 Sq. M Total Built‐up Area       :  26721.836 Sq.M       Landscape area  :  2268.327q. M. Road / Pathway area  : 30 Sq. M. 

The overall area of  the plot  is 6399.13 Sq. M of which an area 26721 Sq. M 

will  be  the  built‐up  area.  Landscape  area  will  be  2268.327Sq.M.  Total 

Population will be 1121.      

 

AREA STATEMENT 

Area Statement SQ.MTS AREA OF PLOT 6399.13 F.S.I 1.5 PERMISSIBLE B.UA. 26721.836 TOTAL B.U.A CONSUMED 26721.836 BALANCE B.U.A. 0.00 CONSUMED F.S.I. 1.5 BALANCE F.S.I 0.00 TOTAL COMMERCIAL UNIT 47 NOS TOTAL RESIDENTIAL UNIT 196 NOS TOTAL B.U.A. OF THE BUILDING 26721.836  

PARKING STATEMENT:  

 

Particular  Car  Scooter  Cycle 

Required  212 ‐‐‐ ‐‐‐

Proposed  212 ‐‐‐ ‐‐‐

  

(REFER ANNEXURE 5 – Parking Plan)  vi)   LANDSCAPING AND TREE PLANTATION 

The  landscape  area  will  be  2268.327  Sq.M  to  keep  the  campus  green  and 

environment friendly. The list of trees to be planted is as follows‐ 

In this Plot area total 65 number of trees will be planted. 

Page 19: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

19 

PLANTATION: TREES AND SHRUBS  

List of Native Trees suitable for roadside/ border side plantation / avenue :  

Tree Common Name  

Scientific Name 

Shirish  Albizia lebbeckNeem,  Azadiracta indicaMaharukh  Ailanthus excelsaNandruk,  Ficus retusaSatwin  Alstonia scholarisKaranj  Pongamia pinnataSita Ashok  Saraca asokaKatesavar  Bombax ceibaKadamb  Anthocephallus cadamba

     List of native trees suitable for beautification in garden / building premises:  

Common name  Scientific name Bahava  Cassia fistulaBakul  Mimusops elengiParijatak  Nyctanthes arbortristisTamhan  Lagerstroemia flosregineae Kunti  Murraya paniculataSita Ashok  Saraca asokaShivan  Gmelina arboreaApta,  Bauhinia racemosaNeem  Azadirachta indicaKate sawar  Bombax ceibaPangara  Erythrina indicaPalas / Flame of the forest Butea monospermaFish tail palm  Caryota urensNandruk  Ficus retusaSon chafa  Michelia champacaPutranjiva  Putranjiva roxburghiiKadamb  Anthocephallus cadamba Satwin,  Alstonia scholarisCurry leaf / kadipatta Murraya koengiiLemon  Citrus

 Shrubs 

Shrub / climber  Scientific name Nirgudi  Vitex negundoAdulasa  Adhatoda vasicaWhite plumbago  Plumbago zeylanicaBer  Ziziphus mauritianaStachytarpheta  Stachytarpheta sp

Page 20: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

20 

Takala,  Cassia toraTarwad  Cassia auriculataKusar / ran‐jai(Climber) ­­Sagargota  ­­Krushna kamal  Passiflora edulis

 Gallery / balcony Plants 1. Lemon grass / Gavati Chaha 2. Tulas 3. Korphad 4. Adulasa 5. Chitrak 6. Krushna kamal 7. Kadipatta 8. Wala 9. Wekhand 10. Gokarna 

  

Shrubs/small trees For Home Garden  1. Nirgudi 2. Adulasa 3. Apta 4. Piwala Kanchan 5. Kunti 6. Bahava 7. Kadipatta 8. Madhunashini (climber) 9. Wala 10. Tamhan 11. Kusar (climber) 

 

The Project proponents have proposed a  landscape development plan, which 

includes  planting  of  flowering  and  shady  trees,  shrubs  and  lawn within  the 

plot. 

The open spaces inside the plot will be suitably landscaped and covered with 

vegetation of indigenous variety.  

 

1.3  What  are  the  likely  impacts  of  the  proposed  activity  on  the  existing facilities adjacent  to  the proposed site? (Such as open spaces, community facilities,  details  of  the  existing  land  use  and  disturbance  to  the  local ecology). 

 

Page 21: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

21 

Although  it  is  a  construction activity,  its  impact on air quality, water quality, 

noise  and  soil will  not  be  notable.  As  a matter  of  fact  this  activity will  have 

positive impact on socio‐economic culture of people residing in the vicinity of 

the proposed area. There will not be any disturbance to the local ecology as the 

selected site for the construction is a barren land. 

 

The project site and the surrounding area have residential buildings. The open 

area will be occupied by vegetation, which will be helpful in increasing green 

cover of the area. Proposed project will require manpower during construction 

phase and operational phase thereby creating  job opportunities. Local skilled 

and  unskilled  laborers  will  have  an  opportunity  for  employment  directly  or 

indirectly.  

There will be additional employment for  the poor strata of society by way of 

domestic helpers, drivers, cleaners etc. 

 

Due  to  the  proposed  project,  facilities  are  likely  to  grow  in  line  with  the 

development. As during the construction and operational phases of the project 

a workforce will  be  needed  this will  be  including  both  skilled  and  unskilled 

people.  The  introduction  of  workers  from  areas  outside  the  region,  could 

introduce a potential effect on the local culture, habits and economics.  

 

1.4  Will  there  be  any  significant  land  disturbance  resulting  in  erosion, subsidence  &  instability?  (Details  of  soil  type,  slope  analysis, vulnerability to subsidence, seismicity, etc may be given).  A.  Details of Soil quality and slope 

The texture of all the soil samples was dominated by “Loam”. Hence, the soil at   project  area  is  “loamy  soil”.  The  texture  of  all  the  soil  samples  in  the project area   was varied   from loam, sandy loam, clay loam, sandy clay loam, loamy sand, silt   loam to clay. A soil   dominated  by  one  or  two  of  the three particle size groups   behaves like loam. Samples  were  collected  within a radius of 10 Km in the study area.   Soil  samples  collected  and  were analyzed for pH, moisture content, water holding   capacity,  organic matter,  ammonia  nitrogen,  potassium,  phosphorous,  Magnesium  as  Mg,   Chlorides  as  Cl‐,  Sulphates  as  SO4‐‐  using  standard  methods  of Association of Official Agricultural Chemist.   

Page 22: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

22 

(REFER ANNEXURE 7 – Soil Analysis Report) The  geological  formations  of  the  entire  study  area  consist  of  dark  coloured volcanic lava flows, basaltic in composition.   Basaltic rocks: The lava flows were poured out of long and narrow fissures in the  earth’s  crust,  during  the  Upper  Cretaceous  to  Lower  Eocene  period approximately, 80 to 100 million years ago. These are spread out in the form of horizontal   sheets  or beds and   constitute  the  innumerable  spurs, hills  and hill ranges, bold flat   topped ridged, lofty peaks   and plateaus with  impressive cliffs.  A characteristic   feature  of  these  flows  is  their  horizontal   disposition and considerable lateral   extent with almost  incredible uniformity  in  their  composition  and  appearance.  Kamothe  is  situated  at latitude of 19o 00’ N and longitude 73005’ E.  

B.  Vulnerability to Seismicity and precautions: 

As per the Seismic Zoning Map of India (given in Enclosures) Mumbai region 

falls  under  Zone‐  4.  Stability  Certificate,  as  per  prevalent  IS  Code  will  be 

obtained  for  these  buildings  from  registered  Consulting  Structural  Engineer 

considering the seismic forces and wind forces etc. 

(REFER ANNEXURE 10 – Seismic Zoning Map) 

C.  Vulnerability to Subsidence 

Ground  level  of  the plot  is plain  land. Backfilling  in  the vicinity of  site  is not 

included in the project plan. Hence, subsidence is not expected. 

  

1.5 Will  the proposal  involve  alteration of natural drainage  systems?  (Give details on a contour map showing the natural drainage near the proposed project site)  

  Not Applicable.  

1.6. What  are  the  quantities  of  earthwork  involved  in  the  construction activity­cutting,  filling, reclamation etc. (Give details of  the quantities of earthwork involved, transport of fill materials from outside the site etc.)  During construction total earthwork involved 1000 Cu Ft. This will be used for backfilling purpose onsite  

1.7.  Give  details  regarding  water  supply,  waste  handling  etc  during  the construction period. 

 CONSTRUCTION PHASE: 

Page 23: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

23 

Total  water  requirement  during  construction  phase  shall  be  100  cum/day approximately for construction as well as domestic use for the workers working on  the  site  and  also  for  the  construction  purpose.  This  water  will  be  made available from Tanker water. Toilet block will be provided with Septic tank and Soak pit.   The Biodegradable waste will be composted at site and non‐biodegradable solid waste  will  be  sent  recycling.  The  construction  debris  will  be  used  for development of Landscape. All  required sanitary and hygienic measures should be  in place  before starting construction activities and to be maintained throughout the construction phase.  

CONSTRUCTION PHASE: 

1.8.   Will the low lying areas & wetlands get altered? (Provide details of how low lying and wetlands are getting modified from the proposed activity) 

 Not Applicable 

 1.9.     Whether  construction  debris & waste  during  construction  cause  health 

hazard?    (Give  quantities  of  various  types  of wastes  generated  during construction  including  the  construction  labour  and  the  means  of disposal)  Construction  debris  and  waste  during  construction  will  not  cause  health hazard. Temporary housing will be provided at the site  for 60 workers  in the form  of  Labour  camp  within  the  site.  Construction  debris  generated  will  be used  for  development  of  landscape.  All  the waste  generates will  be  properly treated and taken care of, therefore will not create any health hazard.  

2. WATER ENVIRONMENT  2.1.   Give  the  total  quantity  of water  requirement  for  the  proposed  project 

with  the breakup of  requirements  for various uses. How will  the water requirement met?  State  the  sources  &  quantities  and  furnish  a  water balance statement.  The proposed source of water will be CIDCO  

It  is proposed that water will be available from the CIDCO. The under ground tank  (UGT)  be  provided  for  the  filtered  water  storage  tank.  Water  may  be pumped from proposed UGT to the overhead tanks on all buildings through a hydro  pneumatic  tank  filling  system.  It  will  be  then  distributed  to  Overhead tank on terrace building.  During construction: 50 M3/DAY Source: Tanker Water  

Page 24: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

24 

During operation:  1.  Source: CIDCO 

o Total Water Demand is 250.02 M3/DAY o Domestic Water Demand is 131.17 M3/DA o Flushing water demand is 69.61 M3/DAY o Landscape Water Requirement 11.34 M3/DAY  o Total treated water available 180.42 M3/DAY o 113.85 M3/DAY treated water will be reused.  

  

2.2. What is the capacity (dependable flow or yield) of the proposed source of     water?  

No of units  (Tenant 198  and shops 47)  

No of population= 1121

Description   Water  requirement  

Loss m3/day  

Sewage generation 

Water use  

m3/day  m3/day  Fresh   Recycled Domestic for residence (@  90  LPCD  )    980 population  

88.2 8.82 79.38 88.2   0.00 

Flushing  for residence(@ 45 LPCD ) 980  population  

44.10 4.41 39.69 0.00   44.10

Domestic for shops (@ 15  LPCD  )  141 population  

2.12 0.21 1.91 2.12  0.00 

Flushing  for  shops  (@ 30  LPCD  )  141 population  

4.23 0.42 3.81 0.00   4.23

Landscaping   11.34 1.13 0.00  0.00   11.34Swimming  pool  make up  

5.00  5.00  0.00  5.00   0.00

Car wash@ 15 liters   3.18  3.18  0.00   0.00   3.18 TOTAL   158.17 23.17 124.79 95.32  62.85Out  of  total  sewage  generation of  124.79 m3/day.  62.85 m3/day will  be used  for  flushing and landscaping and the remaining 61.94 m3/day water will be used in landscaping of trees in the periphery of the plot.  

 

Page 25: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

25 

The proposed source of water during operation is CIDCO.  

 2.3.   What  is  the quality of water  required,  in  case,  the  supply  is not  from a 

municipal source? (Provide physical, chemical, biological characteristics with class of water quality)  The water will be available from Tanker and CIDCO, which will accomplish the water requirement for this residential complex. 

            (REFER ANNEXURE: 6­ BASELINE STATUS OF WATER QUALITY)   2.4.   How much  of  the water  requirement  can  be met  from  the  recycling  of 

treated wastewater? (Give the details of quantities, sources and usage)  

About  67.92  CUM  of  water  will  be  recycled  for  Landscape  and  Flushing  at residential building, club house & Gym.  

  

2.5.   Will  there  be  diversion  of water  from  other  users?  (Please  assess  the impacts  of  the  project  on  other  existing  uses  and  quantities  of consumption) 

 Not Applicable. 

2.6.   What is the incremental pollution load from wastewater generated from the proposed activity? (Give details of the quantities and composition of wastewater generated from the proposed activity)  The  quantity  of  sewage  is  about  90%  of  domestic  water  consumption.  The wastewater‐generated  from  the  proposed  activity  shall  be  domestic.  The sewage will be collected from 198 tenements & 47 Commercial Shops.  

2.7. Give  details  of  the  water  requirements  met  from  water  harvesting? Furnish details of the facilities created.  Rainwater  Harvesting  Tank  Capacity  of  40  KLD  has  been  provided  with  a retention time of 2 days.  

2.8. What would be  the  impact of  the  land use changes occurring due  to  the proposed  project  on  the  runoff  characteristics  (quantitative  as well  as qualitative)  of  the  area  in  the  post  construction  phase  on  a  long  term basis? Would  it  aggravate  the problems of  flooding or water  logging  in any way?  The proposed  land use  is  in  conformity with  the DP  so  there will  not be  any land use  change. The  runoff  from  the project  site will be used  for  recharging the aquifers.   

Page 26: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

26 

The Storm water drains of the area are proposed to be connected to the future drain line which is future development along the project. 

 2.9.   What are the impacts of the proposal on the ground water? (Will there be 

tapping  of  ground  water;  give  the  details  of  ground  water  table, recharging capacity, and approvals obtained from competent authority, if any) 

 Source of water  supply will be  from CIDCO and Tanker water existing within the project site. The overall ground water level shall rise due to the proposed rainwater harvesting measures. No tapping of ground water is proposed in the operative phase of the project, except during emergency. 

  Rain water entering into the stilt & lower ground floor through ramps etc shall be  collected  by  Provision  of  channel  drain  with  pre  cast  RCC  /  CI  gratings discharging by gravity in to  the nearest external storm drain. 

 2.10.   What  precautions/measures  are  taken  to  prevent  the  run­off  from 

construction  activities  polluting  land  &  aquifers?  (Give  details  of quantities and the measures taken to avoid the adverse impacts) 

 The general ground level of the project site will not be elevated. The run off from the site will be filtered mechanically through recharge pits and then will reach aquifers thereby preventing direct pollution of land or aquifers. 

 2.11.   How  is  the  storm  water  from  within  the  site  managed?(State  the 

provisions made  to avoid  flooding of  the area, details of  the drainage facilities provided along with a site layout indication contour levels)  

 The storm water from the site will be used for recharging the aquifers.   Water Runoff Calculation 

 Storm Water Channel Design  

SHELTER BUILDING AT TALOJA,SEC-14 REV : R0

DATE : 10.03.14

ITEMS AREA SQ.M (A)

RUN-OFF COEFIECIENT

©

RAIN WATER INTENCITY

M/HR (I) DISCHARGE (Q)M3/HR

GROUND FLOOR LEVEL AREA OF LAND SCAPE ( AT PODIUM) 1390 0.3 0.125 52.125AREA OF ROAD AND PAVING 1036 0.7 0.125 90.65 AREA OF HARDSCAPE 2419 0.9 0.125 272.1375 AREA OF ROOF 0 0.9 0.125 0

Page 27: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

27 

TOTAL 4845 414.91 GRAND TOTAL IN CUM./HR. 414.91 GRAND TOTAL IN CUM/S 0.115 WIDTH OF TRENCH IN MTRS. 0.3 ASSUME DEPTH OF THE TRENCH IN MTRS. 0.3      

ANIL VERMA CONSULTANTS SHELTER BUILDING AT TALOJA,SEC-14

STORM WATER CHANNEL DESIGN

Q=DISCHARGE = 10 X CX I X A

C=(COEFFICIENT OF ROUGHNESS)= 0.8 .6 TO.8 I=INTENSITY OF RAINFALL= 125 MM/HR A=AREA= 0.4845 HECTORS TOTAL DISCHARGE FROM PLOT Q = 484.5 M3/HR TOTAL DISCHARGE FROM PLOT Q = 0.134583333 M3/SEC CONSIDER 2 NO.OF TRENCH DISCHARGE = Q1 = 242.25 M3/HR CONSIDER 2 NO.OF TRENCH DISCHARGE = Q1 = 0.067 M3/SEC MANINGS FORMULE VELOCITY = V= 1/N X R^2/3 X S ^1/2 0.838 WHERE N=COEFFICIENT OF ROUGHNESS 0.015 .01 TO .03 R=MEAN DEPTH= A/P 0.075 MET assumed A= 0.09 SQM P= 1.2 MET WIDTH OF TRENCH ASSUMED = 300 MM STARTING DEPTH OF TRENCH ASSUMED = 300 MM SLOPE S 0.005 i.e.(1:200) RECOMMENDED VELOCITY .75 TO 2.4

Page 28: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

28 

M/S check := velocity should in between the recommended velocity. DISCHARGE CAPACITY OF ONE TRENCH= AXV 0.0755 M3/SEC 271.63 M3/HR RUNNING FULL 89.18 % WHERE A=ASSUMED AREA OF TRENCH A= 0.09 M2 V=VELOCITY OF FLOW IN TRENCH V= 0.838 M/SEC HENCE TOTAL DISCHAGE CAPACITY FROM 2 NO. OF TRENCH Q = 543.26 M3/HR 0.891834339WHICH EXCEEDS THE TOTAL DISCHARGE FROM PLOT i.e = 484.5 M3/HR DISCHAGE CAPACITY TRENCH EXCEEDS THE DISCHAGE FROM PLOT. HENCE TRENCH DESIGN IS SAFE.

  RAIN WATER HARVESTING  

SHELTER BUILDING AT TALOJA REV R0 CALCULATION OF RAIN WATER TANK DATE

AVRAGE ANNUAL INTENSITY OF RAINFALL : MTRS./HR 0.05AREA NAME A+B WING AREA LAND SCAPE (AS PER DRAWING) SQM. 0

AREA ROAD AND PAVING (AS PER DRAWING) SQM. 0AREA OF ROOF (AS PER DRAWING) SQM. 1080AREA HARD SCAPE (AS PER DRAWING- ON 2ND FLOOR) SQM. 0 RUN-OFF COEFFICIENTS : LAND SCAPE 0.3ROAD & PAVING 0.7ROOF 0.9

Page 29: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

29 

HARD SCAPE - ON 2ND FLOOR 0.9 DISCHRARGE (Q) LAND SCAPE CUM./ HR. 0.0GROUND CUM./ HR. 0.0ROOF CUM./ HR. 48.6HARD SCAPE ( 2ND FLOOR) CUM./ HR. 0.0TOTAL 48.6 ASSUMING RETENSION TIME 2 RAIN WATER HARVESTING TANK CAPACITY CUM 98.00

  2.12.   Will  the deployment of  construction  laborers particularly  in  the peak 

period  lead  to  unsanitary  conditions  around  the  project  site  (Justify with proper explanation)  

   

During  construction  phase  number  of workers will  be  150. Municipal  solid waste generated during construction will be  composted at  site.  Septic Tank and soak pits are provided  for  the construction  labours. So activity will not lead to unsanitary conditions at the site. 

 2.13.   What on­site facilities are provided for the collection, treatment & safe 

disposal  of  sewage?  (Give  details  of  the  quantities  of  wastewater generation,  treatment  capacities  with  technology  &  facilities  for recycling and disposal) 

  The sewage will be collected from 286 tenements. The quantity of sewage is about 90% of domestic water consumption. The wastewater‐generated from the  proposed  activity  shall  be  domestic.  Sewage will  treated  in  the  Sewage Treatment  Plant  of  for  residential/commercial  190  CUM.  The  treated sewage will be partly  recycled  for  flushing & partly  connected  to Municipal sewer line.   SEWAGE TREATMENT BY SAFF Process – PROCESS DETAILS 

 The  waste  water  to  be  let  into  the  bar  screen  chamber  before  letting  to  the collection tank. The waste water from the kitchen and the toilets to be let to the oil and grease separator before letting to the collection tank. 

 The waste water goes through the following processes: 

    

Page 30: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

30 

BRIEF WRITE UP ON THE STP PROCESS   The  scheme  proposed  for  the  treatment  of  sewage  is  a  compact  and  effective Sewage  Treatment  Plant  of  for  residential  residential/commercial  150  CUM capacity  /  day  using  the  revolutionary  “Moving  Bed  Bio  Reactor  (MBBR)” technology.  The  concept  underlining  the  Moving  Bed  bioreactor  is  to  provide continuously  operating  bio‐film  reactor,  which  is  non‐cloggable,  does  not  require backwashing and has a very low pressure drop. This is achieved by growing the bio‐film  on  smaller  carrier  elements  that  move  along  with  the  waste  water  in  the reactor. The air stream constantly keeps the bio media  is  in suspension and at the same time provides the required oxygen to the biomass.   The system uses specially designed bio‐media, which provides a  large surface area for biological growth. The bio‐media is made of plastic material, which has a very long life. The media is cylindrical  in  shape  and  provides  a  large  surface  area  in  the  given  volume.  The media  provides  about  800m2  effective  area  for  growth  of  the  bio  film  per  m3  of volume.   

 The proposed system will consist of the following major stages: 

1. Sewage Collection and Pumping System 

2. Manual Bar Screen and Grit Chamber 

3. Aeration Tank and Tube‐deck Settlers 

4. Filtration System 

5. Disinfection System 

 1.  Sewage Collection and Pumping System: 

 Raw  sewage  will  enter  the  raw  sewage  sump.  Raw  sewage  transfer  pumps  will pump  the  sewage  to  the  STP  through  the  screen  and  grit  removing  stages.  One   Pump will be on duty and the other stand by.  

 2.   Manual Bar Screen and Grit Chamber: 

 A  combination of  coarse and  fine  screens will be provided  for  removal of  floating debris from the sewage.  The coarse screen will have spacing of 10 mm and will be periodically  cleaned. The  fine screen will have a spacing of 5 mm and will also be periodically  cleaned.    The  outlet  from  the  Screen  Chamber  is  let  into  the  sewage treatment system. 

           

Page 31: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

31 

3.    Sewage Treatment System:  SEWAGE TREATMENT BY SAFF PROCESS – PROCESS DETAILS  Bar Screen – Coarse­         Raw  sewage  from  the  source  is  usually  received  into  the  bar  screen  chamber  by gravity. Screen provided will  remove all  floating and big  size matter  such as plastic bottles, polythene bags, glasses, stones, etc., which may otherwise choke the pipeline and pumps.  Oil and Grease Trap   If the sewage generated includes maximum quantity from kitchen and canteen, there is a possibility of higher concentrations of oil and grease in the raw sewage.  It needs to  be  removed  before  biological  treatment  as  it  otherwise may  cause  problems  for biological  treatment.  Usually,  a  small  civil  construction  tank  with  a  baffle  wall  and slotted oil pipe skimmer is provided. The oil and grease removed by gravity floats to the surface, which is removed by the oil skimmer.  Equalization Tank   Usually, sewage generation is more during morning hours and evening hours. Visually no sewage is generated during night hours. Any biological system needs constant feed for bacteria to work efficiently. Hence,  it  is  important to put an equalization tank to collect  the  excess  flow during  peak  hours  and  feed  sewage  in  lean  hours.  A  typical equalization tank has a capacity of 6 hours of average flow rate. The tank is generally of civil construction by client.   Provision of  air  grid  is  to be made  for  thoroughly mixing  the  sewage  to make  it  of homogenous  quality  and  to  keep  the  suspended matter  in  suspension  and  to  avoid septic conditions.        

Page 32: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

32 

 SAFF REACTOR  The  various  toilet  streams  from  the  Shops  and  Residential  into  Septic  tank,  the 

overflow  seepage  of  septic  tank  is  pumped  into  the  Skid  mounted  Package  type 

Sewage treatment Plant  for biological oxidation of organic  impurities  in presence of 

activated (biomass) bacterial sludge.  

The aeration is imparted by Diffused type aerators installed in the tank. The biological 

treatment method  followed  is  of  Submerged Aeration  Fixed  Film  (SAFF).  The  air  is 

induced in the tank from bottom and it moves upward through Media. Media ensures 

full  utilization of oxygen  in  the  air before  it  reaches  top. The bacteria's which  form 

film  on  the Media  utilizes  this  oxygen  and  degrades  the  substrate  coming  from  the 

sewage water. Increased surface area increases the quantum of the biomass to great 

extent and thus can sustain shock loads.  

The  film  of  bacteria's  falls  down  as  soon  as  its  thickness  increases  beyond  certain 

limit.  The  anaerobic  growth  at  the  bottom  most  layers  makes  it  loose  and  it  falls 

down. This makes the maintenance of biomass fully automatic. The sludge settled at 

bottom is drained out, by Sludge transfer pump into filter press or centrifuge. 

The overflow of Aeration tank is allowed to pass through a Tube Settler.  Tube settler The sloughed biomass must be removed before  the  treated sewage  can be disposed off. Hence a  secondary clarifier  (tube settler)  is provided. The secondary clarifier  is equipment  in  which  the  Bio‐mass  removed  &  suspended  solids  are  settled  under action of gravity.   Disinfection The  treated  sewage  is  then  added with  chlorine  to  kill  the  pathogens  /  E‐Coli  coli forms,  so  that  it becomes  fit  for disposal  in  the  lake / water ways. Chlorine being a very strong oxidizing agent, a small dose of 6 mg /l is enough to achieve desired levels of dis‐infection. Small residual chlorine (of the order of 0.2 – 0.25 mg / l) also ensures that  there  is no re‐growth of E‐coli,  till  the  final disposal point. The  treated sewage, now substantially free from organic contamination, free from coliform bacteria can be safely disposed off in the river, or in other water bodies. This water is fit for using for gardening and flushing purpose.      

Page 33: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

33 

   Tertiary Treatment              

Treated  sewage  after  disinfection  is  passed  through  Dual  Media  Filter  and Activated Carbon Filter for further polishing. 

Treated Water Collection Tank: The treated water collection tank can be of civil construction by client.   Sludge Handling: The sludge from the FAB and Tube settler tank is removed from the bottom of the tank and  Collected into the intermediated sludge holding tank and then transferred into the sludge  Holding tank and finally into the batch type centrifuge for dewatering of sludge.   

Page 34: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

34 

 

4. PROCESS BLOCK DIAGRAM  

      

BAR SCREEN (SEWAGE) 

OIL & GREASE TRAP 

EQUALISATION TANK 

SAFF REACTOR 1  

TUBE SETTLER 

DUAL MEDIA FILTER 

ACTIVATED CARBON FILTER 

TREATED WATER TANK 

AERATION SYSTEM 

INT. SLUDGE HOLDING TANK 

SAFF REACTOR 2 

SOFTNER 

CHLORINE CONTACT TANK 

FILTRATE 

SLUDGE HOLDING TANK 

BATCH TYPE CENTRIFUGE 

DRY SLUDGE  

Page 35: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

35 

 4.   Filtration System:  

 This consists of a Pressure Multimedia Filter that removes any remaining suspended solids  in  the  treated water so as  to ensure  its  total  conformance with  the discharge standards set by the regulatory authorities. The Filter is to be backwashed at pre‐set intervals with water from the Treated Water tank. 

 5. Disinfection System: 

 The  Disinfection  System,  which  comprises  of  a  dosing  system,  ensures  complete      removal  of  any  remaining  harmful  organisms  in  the water.  The water  flowing  into     the  Polishing  Filter  Feed Tank  is  dosed with  an  oxidant  above  and  then  allowed  to     remain in the tank for a predetermined time so that there is enough contact time for the oxidant to totally disinfect the water.   

  SLUDGE  The excess sludge is pumped to the sludge tank from where de‐sludging is to be done 

once   every 3 – 6 months (depending on load factors) by pumping out to tankers and 

disposal engaging corporation private agencies. 

                                           WASTE WATER CHARACTERISTICS  

PARAMETER  UNITS  IN  OUT    Nature  of  Waste water 

Domestic  Sewage and Kitchen Waste 

 

Avg daily flow  200  KL/day   PH  ‐‐‐ 6 – 8.5 7 – 7.5 Suspended Solids  PPM 200 – 300 mg/lt  < 30 BOD 5  PPM 200 – 350 mg/lit  < 5 

COD  PPM 500 – 700 mg/lit  < 15 Odour  ‐‐‐ Medium  to 

Strong  NIL 

Colour  ‐‐‐ Grace Brown ColorlessOil & Grease  ‐‐‐ Up to 50 mg/lit  < 5 mg/lit 

2.14.  Give  details  of  dual  plumbing  system  if  treated waste  used  is  used  for flushing of toilets or any other use. 

 The sewage will be collected from 286 tenements. The quantity of sewage is about  90%  of  domestic water  consumption.  The wastewater‐generated  from the proposed activity shall be domestic. Sewage will be treated in the Sewage 

Page 36: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

36 

Treatment Plant for residential/ commercial 120 CUM. The treated sewage will be recycled for flushing.  

3.  VEGETATION    3.1.   Is there any threat of the project to the biodiversity? (Give a description 

of the local ecosystem with it’s unique features, if any)   There will not be any threat of the project to the biodiversity. The selected site for project is barren land. The Project proponents have proposed a landscape development  plan,  which  includes  planting  of  flowering  and  shady  trees, shrubs and lawn within the plot. Flowering plants, shrubbery and lawns shall be planted. So, Biodiversity will in turn increase. 

 3.2.   Will  the  construction  involve  extensive  clearing  or  modification  of 

vegetation?        (Provide  a  detailed  account  of  the  trees  &  vegetation affected by the project)  

 Selected site is barren land. However, the project site will cover the flowering plants,  shrubs  and  lawns.  The  open  spaces  inside  the  plot  will  be  suitably landscaped and covered with vegetation of indigenous variety.  

 3.3. What  are  the  measures  proposed  to  be  taken  to  minimize  the  likely 

impacts  on  important  site  features  (Give  details  of  proposal  for  tree plantation,  landscaping, creation of water bodies etc along with a  layout plan to an appropriate scale)  The site presently  is Barren  land. There  is no  important site  feature so as  to cause any impact on important site features.   

LANDSCAPING AND TREE PLANTATION 

The area 10825.822 Sq.M. will be covered by tree plantation & landscaping so as to give rest of the area massive to keep the campus green and environment friendly.   The Project proponents have proposed a  landscape development plan, which includes  planting  of  flowering  and  shady  trees,  shrubs  and  lawn within  the plot.  The open spaces inside the plot will be suitably landscaped and covered with vegetation of indigenous variety.      

Page 37: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

37 

4. FAUNA  4.1.   There likely to be any displacement of fauna­ both terrestrial and aquatic 

or creation of barriers for their movement? Provide the details.  

The  floristic  component of  the area does not  include any  rare or endangered species. Thus, impact on rare and endangered species of flora is nil. There are no  potential  sources  of  impacts  on  terrestrial  biological  environment  during operation phase of residential complex.  

4.2 Any  direct  or  indirect  impacts  on  the  avifauna  of  the  area?  Provide details.  Biological Environment:  The project site and the surrounding area have plain land. The whole area will be  occupied  by  vegetation.  The  plantations,  which  would  be  grown  in  the residential  area,  will  be  helpful  in  increasing  green  cover  in  the  area.  This would also increase avifauna in the area.  

4.3. Prescribe measures such as corridors, fish ladders etc to mitigate adverse impacts on fauna.  The proposed project will not have any adverse impact on the flora or fauna.  

      

Page 38: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

38 

 5.   AIR ENVIRONMENT  5.1.   Will the project  increase atmospheric concentration of gases & result  in 

heat islands? (Give details of background air quality levels with predicted values  based  on  dispersion models  taking  into  account  the  increased traffic generation as a result of the proposed constructions)  

   As this will be a Residential complex, air pollution is not expected to be a major 

concern. There will not be notable  increase  in pollution  therefore dispersion model  calculations  are  not  done.  But  the  data  on  Ambient  Air  Quality  have been collected during the study period. 

   In  view of  the  revision of national Ambient Air Quality  Standards by Central 

Pollution  Control  Board  ambient  air  quality  stations  were  identified  and monitored.  The sampling locations are Project site and buffer zone.  

 (REFER ANNEXURE 8: BASELINE STATUS OF AIR QUALITY) 

5.2. What are  the  impacts on generation of dust,  smoke, odorous  fumes or other hazardous gases? Give details  in relation to all the meteorological parameters. 

   During construction phase, PM ‐ 2.5, PM‐10 will be the main pollutant, which 

could be generated from site development activities. Concentration of SO2, NO2 and  CO  may  rise  a  little  due  to  traffic.  Proper  upkeep  and  maintenance  of vehicles,  sprinkling  of  water  on  roads  and  construction  site  and  providing sufficient  vegetation  all  around  the plant  site  are  some of  the measures  that would reduce the impact during construction phase. 

       It is generally observed that PM‐2.5, PM‐10 levels are higher in dry weather i.e. during  summer  and  winter  seasons.  Pollutant  load  of  the  atmosphere  is generally low during monsoon as the gaseous pollutants tend to dissolve and particulate pollutants get adsorbed forming aerosols.  

        Fog  formation  aggravates  the  problem  as  rate  of  dispersion  of  pollutants reduces.  High  wind  velocity  is  helpful  for  dispersion  of  pollutants.  Higher temperature and pressure in the troposphere is helpful for better dispersion of pollutants.  In  general,  effective  dispersion  of  pollutants  in  the  atmosphere depends  primarily  on  the  degree  of  stability  of  the  atmosphere  and  on  its turbulent structure. 

 5.3. Will the proposal create shortage of parking space for vehicles? Furnish 

details  of  the  present  level  of  transport  infrastructure  and  measures proposed for improvement including the traffic management at the entry & exit to the project site.  

 The proponents will provide a total number of 344 for four‐wheelers parking as per the CIDCO norms.  

Page 39: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

39 

Measures proposed for improvement including traffic management at the entry and exit to the project site are:  

• Maintaining flow of traffic for approach roads • Entry and Exit points carefully placed so as not to disturb this flow • One  way  traffic  inside  the  complex  for  comfortable  movement  of 

vehicles and reduction in possibility of congestion. • There  will  be  one  entry  and  exit  gate  provided  to  enter  within 

campus and vehicles will be park accordingly with the building.   5.4.  Provide  details  of  the movement  patterns with  internal  roads,  bicycle 

tracks,  pedestrian  pathways,  footpaths  etc.,  with  areas  under  each category. 

 About 844.582 sq. m will be the area under roads.    

5.5.  Will  there  be  significant  increase  in  traffic  noise  &  vibrations?  Give details of  the  sources and  the measures proposed  for mitigation of  the above.   The  proposed  activity  being  of  Residential  type  will  not  cause  a  notable increase  in  the  noise  and  vibration during operation. However,  use  of  heavy machinery  is  inevitable  during  construction  phase  of  the  project.  Sources  of noise  Pollution  during  construction  phase  are  machinery  like  Earthmoving Machinery Mini Hoist Crane, Hoist Crane, Concrete mini mixer, Weigh batcher, Compressors and transportation materials.  Incremental  increase  in baseline noise  levels due  to  this Residential  complex will  not  exceed  55  dB  (A).  The  post  project  noise  levels  at  the  nearest habitation will be less than the stipulated standards of CPCB.   Noise has various adverse effects on workers and their activities. The first and foremost  effect  of  noise  on workers  exposed  to  high  noise  level  over  a  long period  of  severe  impulsive  noise  of  short  duration  is  ‘Loss  of  Hearing’.  This effect  is either temporary or permanent in nature depending upon the length and severity of noise exposure.  Other effects of noise are such as blood pressure, cardiovascular problems and ulcers.  Some  studies  also point  to noise  related  learning difficulties,  reduced work efficiency, irritation, fatigue, increased accidents and errors and socially undesirable behavior.  

Page 40: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

40 

 MITIGATIVE MEASURES: 

 The  project  proponents  have  agreed  to  take  precautions  to  control  noise pollution as mentioned under: 

Use of equipment generating noise of not greater than 90 dB (A). 

High  noise  generating  construction  activities  would  be  carried  out 

only during daytime. Also, adequate parking space will be provided to 

avoid crowding and noise pollution 

Installation, use and maintenance of mufflers on equipment. 

Workers working near  high noise  construction machinery would  be 

supplied with ear muffs/ear plugs. 

(Refer Annex –14 for EMP) 

 5.6. What will be  the  impact of DG sets & other equipment on noise  levels & 

vibration  in  &  ambient  air  quality  around  the  project  site?  Provide details. 

 DURING CONSTRUCTION PHASE: 

Sources  of  noise  Pollution  during  construction  phase  are  machinery  like Earthmoving  Machinery,  Mini  Hoist  Crane,  Concrete  Mixer,  Lift  lade,  JCB, Dumpers, Compressors and transportation materials.  

DURING OPERATION 

     These Machineries will be used only during daytime Canopies  will  be  provided  to  these  mechanical  devices  to  reduce  noise  and vibration. There will not be any considerable impact on the ambient air quality around  the  project  site  as  CPCB  approved DG  sets  along with  acoustic  room will be developed and plantations will be provided.  

6.   AESTHETICS   6.1.    Will the proposed constructions in any way result in the obstruction of a 

view, scenic amenity or  landscapes? Are these considerations taken into account by the proponents?  

     Proposed construction will not result  in obstruction of a view, scenic amenity 

or landscapes. The open spaces have been picturesquely landscaped to capture the variety of flowers and plants. 

 6.2.    Will there be any adverse impacts from new constructions on the existing 

structures?   What are the considerations taken into account? 

Page 41: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

41 

         Not Applicable 

  6.3.   Whether there are any local considerations of urban form & urban design 

influencing the design criteria? They may be explicitly spelt out.  

  No  

6.4.    Are there any anthropological or archaeological sites or artefacts nearby? State if any other significant features in the vicinity of the proposed site have been considered. 

   No    

7. SOCIO­ECONOMIC ASPECTS   7.1.   Will the proposal result  in any changes to the demographic structure of    

local population?  Provide the details.   

It  could  be  seen  that  the  overall  impact  on  Socio‐Economic  Environment  is 

positive  and  permanent  in  nature.  The  impacts  on  socio‐economic 

environment due to the proposed project are listed below: 

• Proposed  project  will  require  manpower  during  construction  phase  and      

operational  phase  thereby  creating  job  opportunities.  Local  skilled  and 

unskilled  laborers  will  have  an  opportunity  for  employment  directly  or 

indirectly. 

• There will be additional employment for the poor strata of society by way 

of helpers, drivers, cleaners etc. 

• Due  to  the  proposed  project,  facilities  are  likely  to  grow  in  line with  the 

development. 

• As  during  the  construction  and  operational  phases  of  the  project  a 

workforce will be needed  this will be  including both skilled and unskilled 

people.  The  introduction  of workers  from  areas  outside  the  region,  could 

introduce  a  potential  effect  on  the  local  culture,  habits  and  economics. 

Those  effects  have  both  positive  and  negative  elements  and  will  be 

managed  by  the  project  proponents  and  developers.  The  construction 

Page 42: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

42 

phase  induces  employment  opportunities  for  the  local  people.  About  300 

persons will be employed during peak period. 

 

(REFER  ANNEXURE  11:  CENSUS  DATA  &  SOCIOECONOMIC  ASPECTS  OF 

PROJECT AREA) 

7.2.  Give  details  of  the  existing  social  infrastructure  around  the  proposed project.  Bhagwati Developers proposed  to establish Residential  cum commercial  complex at 

Ulwe, Navi Mumbai. It  is a residential area in the vicinity of Navi Mumbai city.   This 

area is rapidly developing and near to Uran and Enroute to JNPT. Development of this 

residential complex will cater to the needs of residents in this area. 

 7.3. Will the project cause adverse effects on local communities, disturbance to sacred sites or other cultural values? What are the safeguards proposed?  

 

It  could be  seen  that  the overall  impact on Socio‐Economic Environment  is positive 

and  permanent  in  nature.  The  impacts  on  socio‐economic  environment  due  to  the 

proposed project are listed below: 

 

Positive Aspects of the Projects are as follows 

• Improvement in transport, communication facilities. 

• Improvement in lifestyle and social status, etc. 

• Increase in revenue generation. 

• Due  to  the  proposed  project,  facilities  are  likely  to  grow  in  line with  the 

development. 

• Possible sources of income for this community are direct like Construction 

and various job works in Residential complex.  

•    As during the construction phases of the project a workforce will be needed 

which will be including both skilled and unskilled people. The introduction 

of workers from areas outside the region, could introduce a potential effect 

on the local culture, habits and economics. Those effects have both positive 

and negative elements and will be managed by the project proponents and 

Page 43: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

43 

developers. The construction phase induces employment opportunities for 

the local people. About 300 persons will be employed during peak period.  

 

The  open  spaces  have  been  picturesquely  landscaped  to  capture  the  true  lavish 

ambience  of  a  vacation  resort  replete  with  palms,  water  bodies,  fountains  and  a 

variety of flowers and plants. 

 8. BUILDING MATERIALS  8.1.   May involve the use of building materials with high­embodied energy. Are 

the  construction     materials  produced with  energy  efficient  processes? (Give details of energy conservation measures in the selection of building materials and their energy efficiency) 

 ECBC (Energy Conservation Building Code`) norms will become applicable for  all  buildings  as  per  Energy  Conservation  Act  2001.  These  norms will  be recommended and included in design.   Following are some of the application to get compatible to ECBC Norms.   1)  Timer based automatic lighting control in parking with Motion Sensor.  2)  External  lighting  with  Astronomical  time  switch/  Photo  Sensors  which capable of automatic operation of External Lighting.   

 3)  LPD to be maintained as per recommendation tables.       Parking ‐3.2 W/ Sq Mtr       Facade – 2W/ Sq Mtr.  

 4)  Solar Water heating.  

 8.2.  Transport  and  handling  of materials  during  construction may  result  in 

pollution, noise & public nuisance. What measures are taken to minimize the impacts? 

 During construction phase, sources of noise pollution will be due to operation 

of  machinery  like  Earthmoving  Machinery,  Mini  Hoist  Crane,  Hoist  Crane, 

Concrete  mini  mixer,  Weigh  batcher,  Compressors  and  transportation 

materials  as well  as  transportation  vehicles.  This will  cause  nuisance  to  the 

occupants  of  the  nearby  area.  The  project  proponents  have  agreed  to  take 

precautions to control noise pollution as mentioned under: 

   Use of equipment generating noise of not greater than 90 dB (A). 

High  noise  generating  construction  activities  would  be  carried  out  only 

during daytime. 

Page 44: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

44 

Installation, use and maintenance of mufflers on equipment. 

Workers  working  near  high  noise  construction  machinery  would  be 

supplied with ear muffs/ear plugs. 

(REFER ANNEXURE 9 ­ BASELINE STATUS OF NOISE QUALITY) 

 8.3. Are recycled materials used  in roads and structures? State  the extent of 

savings achieved?  

Solid waste  that would be generated due  to excavation will be  in  the  form of 

rubble  and  soil.  This  soil  and  rubble  would  be  used  for  development  of 

Landscape. Construction debris will be reused for backfilling of roads and other 

construction. 

 8.4.  Give  details  of  the methods  of  collection,  segregation &  disposal  of  the 

garbage generated during the operation phases of the project.  

Solid waste will  be  generated  in  the  campus  is  domestic  type  having  source 

separated dry and wet components. As far as possible the dry waste like paper, 

cardboard  boxes,  thermocol  packing,  plastics  etc.  shall  be  sent  for  recycling 

purpose.  However, wet waste, which  is  biodegradable,  shall  be  converted  to 

bio‐compost by adopting  following aerobic composting method. The quantity 

of biodegradable waste generated  is about 0.306 Tons per day. The  ‘Organic 

Waste Converter’ will be used for composting of solid waste. 

 

Total Solid waste management 

Total  population  of  the  residential  scheme  is  980  nos.  and  Commercial scheme is 141 nos. For total 1211 nos  For Residential and commercial Quantity of solid waste – 436 kg/day i.e.0.44 T/day approx.  Quantity of wet waste –   0.24 T/day considering  

 Quantity of dry waste – 0.20 T/day 

 

Page 45: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

45 

Biodegradable and non biodegradable waste will be segregated. Dry waste will 

be  sent  for  recycling  and  wet  waste  will  be  treated  by  ‘Organic  Waste 

Converter’ for composting. 

           

(REFER ANNEXURE 13: Organic Waste Converter) 

 

9. ENERGY CONSERVATION  

9.1. Give details of  the power requirements, source of supply, backup source etc. What is the energy consumption assumed per square foot of built­up area? How have you tried to minimize energy consumption?  

 Source:  Maharashtra State Electricity Distribution Company Limited. (MSCEDCL)  

  During Construction    Total Demanded load For Project = KW.   Source of Power Supply For Project ‐ D.G Sets (75 KVA, 1 nos)       During Operation                Total Load: 2422.50 KW   Source: ‐‐ MSCEDCL      

  Alternative Back Up:‐ Diesel Generator (DG) Set  for lifts, Common  Lighting, Water pumps & other essential services. 

 Capacity of D.G. Set for Common Amenities: 400 KVA ‐ 2 Nos. and 400 KVA‐ 1 No.  for  Fire  Pump With  AMF  &  Auto  Load  Sharing  Panel  with  Sound  Proof Enclosure with dB level not greater than 75 dB (A).        

 

Page 46: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

46 

 9.2.   What type of, and capacity of, power back­up to you plan to provide?  

 

Alternative Back Up: ‐  

Capacity of D.G. Set for Common Amenities: 400 KVA ‐ 2 Nos. 400 KVA‐ 1 No. for  Fire  Pump.  With  AMF  &  Auto  Load  Sharing  Panel  with  Sound  Proof Enclosure with dB level not greater than 75 dB (A).            

9.3.  What  are  the  characteristics  of  the  glass  you  plan  to  use?  Provide 

specifications of  its  characteristics  related  to both  short wave and  long 

wave radiation? 

 Normal 6 mm clear float glass is used. The glass will allow short as well as long 

wave radiations to pass through. However, use of sunscreens on window panes 

will reduce heating inside the buildings.  

 

9.4. What passive solar architectural  features are being used  in the building? 

Illustrate the applications made in the proposed project. 

The  external  walls  exposed  to  high  solar  exposure  are  double  walls/cavity 

walls.  Most  of  the  openings  are with  appropriate  sunshades  to  cast  shadow 

inside the room. Most of the external facades are double height terraces, which 

help in reducing direct exposure to solar heat. 

 

Top terrace that is exposed directly to sun is covered by pergolas, which serve 

dual purpose. It helps in reducing the direct exposure to sun as pergolas cast 

shadow on the floor. 

   

ARCHITECTURAL DESIGN 

Maximum  ground  is  covered  by  green patches  to  reduce  reflection  of 

heat from ground surface. 

Shade giving trees are proposed around the condominium especially on 

South and west side to cast shadow on the ground and building. 

By accommodating maximum parking areas are covered parking, heat 

generation due to vehicle is compressed below the building. 

Page 47: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

47 

Thermal Paint application is proposed for external walls which reduce 

and reflect heat. Direct exposure to sun is reduced by proposing double 

height terraces and double wall external walls. Adequate sunshades are 

proposed. 

 9.5.     Does  the  layout  of  streets &  buildings maximize  the potential  for  solar 

energy  devices?  Have  you  considered  the  use  of  street  lighting, 

emergency  lighting and  solar hot water  systems  for use  in  the building 

complex? Substantiate with details. 

Street  lighting  will  be  considered  within  the  complex.  For  the  emergency 

lighting proper provision will make by considering available stocks. Solar hot 

water system will be not used within complex.  

The  appurtenant  spaces where  common  lighting  is  required  are proposed  to 

use unconventional energy. 

  9.6.  Is  shading  effectively  used  to  reduce  cooling/heating  loads?  What principles have been used to maximize the shading of Walls on the East and the West and the Roof?  How much energy saving has been effected?  

The construction  is designed in order to assure maximum of the natural  light 

and ventilation in the structure.  

Thermal  Paint  application  is  proposed  for  external  walls  which  reduce  and 

reflect  heat.  Direct  exposure  to  sun  is  reduced  by  proposing  double  height 

terraces and double wall external walls. Adequate sunshades are proposed. 

 

 9.7. Do  the structures use energy­efficient space conditioning,  lighting and mechanical  systems?  Provide  technical  details.  Provide  details  of  the transformers  and  motor  efficiencies,  lighting  intensity  and  air­conditioning load assumptions? Are you using CFC and HCFC free chillers? Provide specifications.  As  it  is  a  residential  complex  with  no  in  built  provision  for  space  cooling. 

Energy efficiency in lighting and mechanical systems will be achieved by: 

Purchase of energy efficient appliances 

Adjusting  the  settings  and  illumination  levels  to  ensure minimum 

energy used for desired comfort levels 

Page 48: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

48 

Installing programmable on/off timers and sensors for low  

      Occupancy areas 

Use of solar energy for street lights  

Use of compact fluorescent lamps and low voltage lighting. 

  9.8. What are  the  likely effects of  the building activity  in altering  the micro­

climates? Provide a self assessment on the likely impacts of the proposed 

construction on creation of heat island & inversion effects?    

  

The  proposed  project  is  of  Residential  type  and  will  not  have  space 

conditioners  or  glass  walls.  Alteration  of  microclimate  is  not  notable  in  this 

case. The glass will be used in a way just to provide optimal lights inside. Also 

the  glass  used  will  be  energy  efficient  to  reduce  the  heat  gain  inside  the 

building.  

             Systematic design of buildings in order to assure maximum natural ventilation 

and light will be considered to reduce the effect of creation of heat island.  

 

9.9. What are  the  thermal  characteristics of  the building envelope?  (a)  roof; 

(b) external walls; and (c) fenestration? Give details of the material used 

and the U­values or the R values of the individual components.  

Wall: 1] 13 mm Cement Plaster + 200 mm Concrete Block + 13 mm Cement  

Plaster: U Value – 0.309 BT/Hr. / SqFt °F 

 2] 13 mm Cement Plaster + 200 mm Concrete Block + Air Space +  200 

mm  Concrete Block + 13 mm Cement Plaster  U Value – 0.162 BTU / Hr. / 

SqFt °F          

  Exposed  Roof:  1]  13  mm  Gypsum  Board  +  Air  Space  +  75  mm  Concrete 

Block+13mm Tile +50 mm EPS Insulation U Value – 0.094 BTU/ Hr./ SqFt °F 

  Windows: 1] DGU – SKN754 Blue U Value – 0.264 BTU / Hr. / SqFt °F Shade  

Coefficient – 0.23 

Thermal Characteristics of the building envelope:  

• Terraces will be treated with a layer of brick bat coba for reduction in heat gain 

through roof. 

Page 49: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

49 

• Overhang projections and horizontal and vertical elevation band of 0.3m will 

be  provided  around  the windows which will  be  reducing  solar  heat  gain  but 

will assure maximum natural light and ventilation in the buildings. 

• External  shading  is  prominently  used  in  the  complex  it  intercepts  solar  heat 

before it reaches the glass/ wall. 

• External walls are 150 mm with 10 mm plaster on both the sides [cavity wall], 

double  height  terraces  are  provided  to  reduce  direct  exposure  to  sun.  The 

external walls of the buildings will be colored with light slightly tinted colours 

to reduce solar heat gain and will reflect heat. 

 

9.10. What precautions &  safety measures are proposed against  fire hazards? 

Furnish details of emergency plans. 

The  project  proponents  shall  follow  all  the  safety  rules  and  regulations  as 

prescribed by regulatory authority 

 

9.11. If you are using glass as wall material provides details and specifications 

including emissivity and thermal characteristics. 

The  entire  building  is  designed  with  appropriate  openings  to  reduce  heat 

energy inside the building. No use of glass as wall material. 

 

9.12. What is the rate of air infiltration into the building? Provide details of how 

you are mitigating the effects of infiltration. 

        The ground surfaces are covered with green patches to have dust control. These 

Openings too habitable spaces are adequate just to be functional. The openings 

are covered with dust proof, air and water light aluminum glazing. 

 

9.13. To what extent  the non­conventional energy  technologies are utilized  in 

the overall energy consumption? Provide details of the renewable energy 

technologies used.  

 

N.A 

 

Page 50: Form 1- Shelter, Taloja 13.03environmentclearance.nic.in/writereaddata/online/EC/23122014MZ4I… · Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi

Form 1 & 1A – Shelter Group, Plot no. -114, 115, 116, Sector- 14, Taloja, Navi Mumbai 

50 

10.   Environment Management Plan 

The  Environment  Management  Plan  (EMP)  would  consist  of  all  mitigation 

measures for each item wise activity to be undertaken during the construction, 

operation and the entire life cycle to minimize adverse environmental impacts 

as  a  result  of  the  activities  of  the  project.  It  would  also  delineate  the 

environmental  monitoring  plan  for  compliance  of  various  environmental 

regulations.  It  will  state  the  steps  to  be  taken  in  case  of  emergency  such  as 

accidents at the site including fire.