foreword - oilweb - corporate intranet portal standard...(oisd) staffed from within the industry for...

38

Upload: buicong

Post on 08-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

<< Back Home Next >>

Page 2: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

FOREWORD

The Oil Industry in India is more than 100 years old. Because of various

collaboration agreements, a variety of international codes, standards and

practices have been in vogue. Standardisation in design philosophies and

operation and maintenance practices at a national level was hardly in existence.

This coupled with feed back from some serious accident that occurred in the

recent past in India and abroad, emphasised the need for the industry to review

the existing state of the art in designing, operating and maintaining oil and gas

installations.

With this in view, the Ministry of Petroleum and Natural Gas in 1986

constituted a Safety Council assisted by the Oil Industry Safety Directorate

(OISD) staffed from within the industry for formulating and implementing a series

of self regulatory measures aimed at removing obsolescence, standardising and

upgrading the existing standards to ensure safe operations. Accordingly, OISD

constituted a number of functional committees of experts nominated from the

industry to draw up standards and guidelines on various subjects.

The present guidelines, earlier titled Standard on “Combined Operations”,

was published in August, 2000. It was taken up for review by the functional

committee, constituted for the purpose, in the year 2007. The standard has been

changed to guidelines and renamed as “Simultaneous Operations in Exploration

& Production Industry”. The document is based on the accumulated knowledge

and experience and the various national and international codes and practices.

The guidelines are meant to be used as supplement and not as a

replacement for existing codes and practices.

It is hoped that provisions of this guidelines, if implemented objectively, may

go a long way to improve the safety and reduce accidents in Exploration &

Production Industry. Users are cautioned that no guidelines can be a substitute

for the judgement of responsible and experienced personnel involved in

simultaneous operations.

Suggestions are invited from the users after it is put into practice to improve

the document further. Suggestions for amendments to the document should be

addressed to the Coordinator, Committee on “Simultaneous Operations in

Exploration & Production Industry”, Oil Industry Safety Directorate, 7th Floor, New

Delhi House, 27-Barakhamba Road, New Delhi - 110 001.

Page 3: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

These guidelines in no way, supersedes the statutory requirements of bodies

like DGMS, PESO or any other Government Body which must be followed as

applicable.

(i)

COMMITTEE FOR PREPARING STANDARD ON

COMBINED OPERATIONS

2000 ----------------------------------------------------------------------------------------------------

Name Organisation Position in Committee ----------------------------------------------------------------------------------------------------- 1. Shri J.T. Mahavar ONGC Leader 2. Shri A.B. Chakraborty ONGC Member 3. Shri D. Kumar OIL Member 4. Shri R.G. Goel ONGC Member 5. Shri P.K. Jain ONGC Member 6. Shri T.Singh OISD Coordinator -----------------------------------------------------------------------------------------------------

Page 4: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

(ii)

COMMITTEE FOR REVIEW OF GUIDELINES ON

SIMULTANEOUS OPERATIONS IN EXPLORATION & PRODUCTION INDUSTRY

2008

----------------------------------------------------------------------------------------------------Name Organisation Position in Committee

----------------------------------------------------------------------------------------------------- 1. Shri Rajesh Kakkar ONGC Leader 2. Shri K.C. Patel ONGC Member 3. Shri Ahmed Javed ONGC Member 4. Shri B.N. Sahoo OIL Member 5. Shri A. Bora OIL Member 6. Shri D.K.Varshney OISD Coordinator -----------------------------------------------------------------------------------------------------

(iii)

Page 5: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

Guidelines on Simultaneous Operations in Exploration & Production Industry

Contents

(iv)

S.No. Description Page No

1.0 Introduction

1

2.0 Scope

1

3.0 Definition

1

4.0 Offshore Simultaneous Operations

2

4.1 Simultaneous Operations on and around well platform related to jack-up drilling rig (for drilling and workover)

2

4.2 Simultaneous Operations on a process platform

9

4.3 Non – rig related simultaneous activities on a well platform 13 5.0 Onshore simultaneous operations

13

5.1 Simultaneous Operations involving drilling rig / workover rig 14 5.2 Simultaneous Operations inside production installation

21

Annexure-A - Delegation of Authority letter, in case of hired rig

24

Annexure-B - Pre-operations check list (offshore)

25

Annexure-C - Documents / information (offshore)

27

Annexure-D - Platform handover form for drilling / working over 28 Annexure-E - Post-operations check list (offshore)

30

Annexure-F- Simops - sample matrix

31

Annexure-G- Simops checklist (onshore)

32

Page 6: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

1

GUIDELINES ON SIMULTANEOUS OPERATIONS IN EXPLORATION & PRODUCTION INDUSTRY

1.0. INTRODUCTION

This document presents the procedures for safe conduct of drilling, workover, production, revamping / construction and other related activities simultaneously from the same well platform / process platform / well site / production installation. The purpose of this document is to specify the limitations under which various operations can be carried out simultaneously such as to ensure the safe conduct of operations. Simultaneous operations should be thoroughly analysed and planned with the objective of limiting additional risk imposed by multiple activities and operations being undertaken at the same place or in the vicinity at the same time as opposed to the risk associated with the execution of these individually. Risk assessment studies should form the basis for deciding upon simultaneous operations.

2.0. SCOPE

The guidelines broadly cover the following related to simultaneous operations (SIMOPS) in E&P industry:

- Organisation and management structure. - Practices to be followed. - Scenarios for both offshore and onshore.

3.0. DEFINITION

3.1 Cold work: An activity which does not produce sufficient heat to ignite a flammable air - hydrocarbon mixture or a flammable substance.

3.2 Drilling: A process to produce cylindrical hole in earth, called ‘well’, using a drilling rig, to access hydrocarbon bearing reservoir.

3.3 Hot work: An activity that can produce a spark or flame or other source of ignition having sufficient energy to cause ignition, where the potential for flammable vapours, and gases exists.

3.4 PPE - Personal Protective Equipment: Devices or clothing used to insulate an

individual from the chemical, thermal, explosive, electric shock or other hazards presented by the environment in which one is working. Some of PPEs are Safety goggles, Apron, Safety shoes, Chemical-resistant gloves, helmet etc.

3.5 Process platform / production installation: Facility, in offshore / onshore, where

produced fluid is processed (oil / water / gas separation, gas dehydration etc.) before onward transportation.

3.6 Simultaneous operations (SIMOPS): Also called ‘combined operations’ are

those where more than one major activity e.g. drilling, production, workover operation, revamping / construction etc. is undertaken at the same place or in the

Page 7: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

2

vicinity along-with activities such as material handling and hot work in an environment where oil / gas is present or produced nearby.

3.7 Station bill: A written list posted in the crew’s quarters and other conspicuous

places, listing the station of the crew.

3.8 Workover: It involves any well maintenance / repair job, water shut off job, installation / repair of artificial lift /changing of production zone etc by using workover / drilling rig. The term includes any associated cold work.

3.9 Xmas tree: An assembly of valves and fittings in upper part of well, to control flow of

fluids from the well.

4.0 OFFSHORE SIMULTANEOUS OPERATIONS Typical scenarios covered under offshore are:

· Simultaneous activities on and around well platform related to –

a) Jack-up drilling rig and production operations, and

b) Jack-up drilling rig and revamping / construction.

· Simultaneous activities on a process platform related to –

Production operations, revamping / construction and marine operations.

· Non- rig related simultaneous activities on a well platform

The above scenarios are indicative only. The companies should develop their own scenarios based on the risk assessment of various SIMOPS activities.

4.1 Simultaneous operations on and around well platform related to jack-up drilling rig (for drilling and workover)

4.1.1 SIMOPS Organisation and management:

When the drilling rig / workover rig is operating over the well platform, both the facilities should be defined and considered as a single combined installation. During the period of time, the offshore drilling rig is adjacent to the well platform, then for safety aspects such as fire suppression system, mustering, works permits, etc., the well platform should be considered as an extension to the drilling rig. However, the production representative should be deputed by the concerned offshore installation manager (OIM) of the process complex, on need basis, to monitor production well systems on the well platform. For various SIMOPS, document should be prepared by the company outlining all the dos and don’t’s, special safety precautions to be taken, roles and responsibilities of key personnel, operations which have to be stopped / can be continued / can be continued with prior approval (at appropriate level), emergency response plan, etc.

Page 8: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

3

The person responsible for SIMOPS should be the custodian of SIMOPS document and it is the responsibility of the custodian to seek agreement or approval from appropriate authority for any amendment.

4.1.2 Responsibilities

4.1.2.1 In case of hired rig

The responsibilities as enumerated below are also applicable to company owned rigs operating under operation and maintenance / man management contract.

Company man The Company representative on board the rig, has the overall responsibility for SIMOPS. Controls and regulates the work of the drilling / well intervention programmes on the combined installation. Is authorised as per Annexure-A, by the company as overall responsible for SIMOPS on the combined installation.

Rig OIM Is responsible for the safety of personnel and equipment on board the rig and performs work programme approved by the company management.

Offshore Installation Manager (OIM)

Any operation in the operating field should be with the knowledge of the offshore installation manager (OIM). Liaises with the company man and production representative for all operational matters related to SIMOPS and also co-ordinates the shut down requirements of the wells.

Production Representative (Wellhead Manager) The representative of the production department (of the company) on the combined installation, ensures that all production operations on the installation are carried out in the accepted and safe manner at site. Works closely with rig OIM and company man as part of the onsite SIMOPS team and advises the company man of any operations / practices which could be hazardous or are in violation of the approved SIMOPS procedures. Also liaises with well services representative. Engineering and Construction Representative Responsible for revamping / construction activities, liaises with company man and production representative for day to day activities related to revamping / construction and works closely with them to ensure adherence to SIMOPS procedures. Obtains necessary work permit and clearance from company man and production representative before commencing revamping / construction activities. Contractor Representative The onsite representative of contractor engaged for revamping / construction activities, follows the directions of the engineering and construction representative. Ensures that the contractor’s personnel carry out tasks in a safe manner in accordance with SIMOPS procedures and conditions laid out in work permit. Also ensures that the contractor’s personnel have been imparted mandatory HSE trainings before being deployed for the job at site, and that they use PPE while on the job.

Page 9: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

4

4.1.2.2 In case of company owned rig

Rig OIM Has the overall responsibility for SIMOPS. Is responsible for the safety of personnel and equipment on board the rig and performs work programme approved by the company management. Offshore installation manager (OIM) Any operation in the operating field should be with the knowledge of the concerned offshore installation manager (OIM). Liaises with rig OIM and production representative for all operational matters related to SIMOPS and also coordinates the shut down requirements of the wells. Production Representative (Wellhead Manager) The representative of the production department on the combined installation, ensures that all production operations on the installation are carried out in the accepted and safe manner at site. Works closely with rig OIM as part of the onsite SIMOPS team and advises the rig OIM of any operations / practices which could be hazardous or are in violation of the approved SIMOPS procedures. Also liaises with well services representative.

Engineering and Construction Representative Responsible for revamping / construction activities, liaises with rig OIM and production representative for day to day activities related to revamping / construction and works closely with them to ensure adherence to SIMOPS procedures. Obtains necessary work permit and clearance from rig OIM and production representative before commencing revamping / construction activities. Contractor representative The onsite representative of contractor engaged for revamping / construction activities, follows the directions of the engineering and construction representative. Ensures that the contractor’s personnel carry out tasks in a safe manner in accordance with SIMOPS procedures and conditions laid out in work permit. Also ensures that the contractor’s personnel have been imparted mandatory HSE trainings before being deployed for the job at site, and that they use PPE while on the job.

4.1.3 Basic Procedures to be followed during SIMOPS (a) SIMOPS Programme

Prior to the drilling rig moving to a new well platform location, a meeting of the drilling, production and HSE representative should be held to agree and confirm the programme and preparatory activities. Prior to undertaking SIMOPS, job safety analysis should be carried out by the person responsible for SIMOPS (company man / rig OIM, as the case may be) with all agencies associated with SIMOPS, to ensure that all the hazards related to the proposed operations are identified, assessed and determined to have the risk as low as reasonably practicable. Job analysis report should be approved by offshore installation manager (OIM).

Page 10: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

5

(b) Well Closure

Prior to the Drilling Rig moving onto the production well platform, a deep set barrier (plug) should be set in the existing well completions or subsurface safety valve should be closed. Also, wing valve to be closed. Normal production can be resumed after the rig is jacked up to the required air-gap and cantilevered out over the wellhead.

(c) Well Platform Control

The telemetry control system for the well platform should remain operational.

(d) Hazardous Areas Hazardous area classification for well platform and the rig’s hazardous area classification should be combined to establish a composite hazardous area classification for the combined installation.

(e) ESD Interfaces

Well platform ESD system should be extended to the jack-up via an interface box. An interface box with ESD Button should be located at least at each of the following locations on the rig using the same system gas used presently for instrumentation;- · Driller’s console on Drill Floor · Near Tool pusher office In the event of an emergency on the well platform or rig, the manual ESD buttons should be operated. On evaluation of the audibility of hooter of the rig, at the well platform, extension of the same should be provided on the well platform, if necessary. Persons working on rig should be trained in use of ESD systems, during rig induction for SIMOPS.

(f) Well Platform Gas Venting

Required venting from the lubricators should be controlled by permit to work (PTW) system. A gas detector should be installed below the cantilever to monitor the venting gas.

(g) Fire Water System

In order to fight any fires on the well platform, which does not have fire water line provision, the rig should install an adequate size sea water line from the rig to the well platform. It should be kept pressurised with adequate pressure in readiness to fight fires. Fire fighting hoses and nozzles should be strategically positioned, and regularly tested, by the production representative.

(h) Communication and Coordination

Appropriate interfacing and good communication is required between the well platform personnel and drilling rig crew throughout the simultaneous activities. A pre-start meeting should be held onboard drilling rig with attendance of senior personnel

Page 11: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

6

from process platform. The company man / rig OIM, as the case may be, should conduct a daily meeting either in person or over radio / phone with the in-charge of the project activities / offshore installation manager (OIM) / production representative at a mutually convenient time. There must be regular telephonic conversation between offshore installation manager (OIM) and the company man / rig OIM to ensure communication on PTW and work plan. Radio contact should be established between the involved installations and communication channel maintained.

(i) Drilling Rig Induction, Station Bill & Mustering The rig should initiate a SIMOPS “induction” for all personnel when they arrive on the drilling rig. There should be no routine mustering on the well platform. Only in the case of emergency should persons muster on the well platform, in that case they should immediately call the drilling rig control room to inform the muster checker. All the drilling rig station bills and muster points should have a note added to intimate the additional muster point at the well platform.

(j) Emergency response

In the event of any emergency involving well platform or rig it is the responsibility of the company man / rig OIM, as the case may be, to initiate and co-ordinate all emergency response actions. The primary escape means for the crew on well platform deck should be the rig evacuation means in case the rig is attached to the well platform. The secondary means of evacuation for the well platform based crew should be by mustering at designated muster point on the well platform and launching of life rafts.

4.1.4 Simultaneous Operations scenarios: 4.1.4.1 Various scenarios under SIMOPS, involving drilling rig and production

operations activities on well platform, include:

I. During rig approach, piling activity, rig skidding, jack down and pull away from well platform;

II. During drilling- with diverter system, regular drilling and H2S environment;

III. During well completion, well testing and well control;

IV. During hot work;

V. During helicopter operation.

I. During rig approach, piling activity, rig skidding, jack down and pull away from well platform;

Moving a jack up rig from and to an oil / gas production well platform is a critical operation due to safety and environmental hazards associated with it. There are number of oil, gas and water injection pipelines around the well platforms. Sea bed survey is to be carried out to protect the pipelines during positioning of the rig. After the sea bed survey, when the jack up rig approaches the well platform for docking, its legs are lowered to touch the seabed and then the rig is pulled / positioned by the towing boats. (i) Prior to rig move to platform, the pre-operations checklist should be signed by

the company man / rig OIM, as the case may be, as per Annexure-B, to ensure that all preparatory activities have been completed as per approved SIMOPS.

Page 12: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

7

(ii) All the documents / information of the platform as shown in Annexure-C, should be handed over to company man / rig OIM, as the case may be, prior to rig move to platform.

(iii) Complete drawings of pipelines laid within 1000-m radius of the jacket should

be available on board of the jack up rig. The pipelines in the vicinity of the well platform are required to be marked with buoys prior to approach of the rig to the well platform.

(iv) Platform should be handed over by OIM to company man / rig OIM, as the

case may be, when the rig is moved to the well platform and when the rig is moved out, the company man / rig OIM, as the case may be, should hand over well platform to OIM as per Annexure-D.

(v) All pipelines (oil, gas, and gas injection) of the well platform are required to be

isolated from both ends to ensure no ingress of inventory. Information about the pipelines, which are not connected to the jacket but are laid in the close vicinity of the platform should be available with the rig before the rig movement to decide upon the requirement of isolation of any of these lines, depending upon their distance from the likely positions of spud tanks. The underwriters may require the company to provide specific means to monitor the distance between the pipeline and the spud tank continuously either by deploying the divers or by providing transponders and receivers.

(vi) In order to have good visibility, co-ordination and control of the tugs, the

approach to the well platform should be done only during daylight. (vii) Crane operations, supply vessel approach, maintenance of gas and fire

detectors, sampling, well acidization and wire-line operation, on the adjacent wells are not to be performed on well platform during movement of jack up rig, piling activity, rig skidding (during rig move), jack down and pull away from well platform.

(viii) Adjacent wells should be kept closed during rig approach, rig skidding and pull away. Wells can be kept on production, during piling activity.

(ix) The post-operations checklist, as depicted in Annexure-E, should be signed by company man / rig OIM, as the case may be.

II. During drilling- with diverter system, regular drilling: and H2S environment

(i) Approach of supply vessel, maintenance of gas and fire detectors, ESD maintenance, well acidization, wire line work on adjacent wells, flow line hook up are not permitted to be performed on well platform during drilling with diverter system where there is medium / high potential of shallow gas. Keeping adjacent wells on production, during drilling with diverter system is to be decided by OIM and company man / rig OIM, as the case may be, on case-to-case basis.

(ii) During regular drilling, adjacent wells can be kept on production and most of the routine activities on the well platform are permitted. However, based on risk perception, activities like ESD maintenance, well acidizing, line pigging, wire line operations, flow line hook up may require prior approval.

(iii) Crane operations, approach of supply vessel, maintenance of gas and fire detectors, venting through boom, ESD maintenance, well acidization, wire line work on adjacent wells, flow line hook up are not permitted to be performed on

Page 13: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

8

well platform during drilling in H2S environment. Adjacent wells can be kept on production.

III. During well completion, well testing and well control

(i) During installation of Xmas tree, ESD maintenance on well platform is not to be performed.

(ii) During running of explosives / radio active resources in the hole and during well control activities, operations namely crane operations, sampling / leak test, approach of supply vessel, maintenance of gas and fire detectors, ESD maintenance, well acidization, wire line work on adjacent wells, flow line hook-up are not permitted on well platform. Also, all nearby radio communication to be switched off during running of explosives / radio active resources. However, adjacent wells can be kept on production during running of explosives / radioactive sources in the hole. During well control activities, flowing of adjacent wells is to be decided by OIM and company man / rig OIM, as the case may be, on case-to-case basis.

IV. During hot work:

(i) When the hot job is planned in the well bay or in vicinity of the wells, wells on production, approach of supply vessel, maintenance of gas and fire detectors, sampling / leak test, ESD maintenance, well acidization are not permitted. However, allowing of crane operation, line pigging, wire lining and flow line hook-up should be decided by OIM and company man / rig OIM, as the case may be.

(ii) Refer OISD-STD-105 for requirements related to work permit.

V. During helicopter operation:

During any simultaneous operations, the well platform helideck shall be “OUT OF USE”. Helicopter contractor should be so informed, and the requisite signs should be positioned on the well platform helideck. All helicopter flights should use rig helideck. Due to the close proximity of the drilling rig, the well platform boat landing should be “OUT OF USE” during SIMOPS. Use of boat landing of well platform in a restricted manner may be allowed with prior permission from company man / rig OIM, as the case may be. All marine contractors should be so informed. During helicopter operations, well platform related routine activities are allowed. The above scenarios are typical cases. It is recommended that organisation should develop their own SIMOPS matrix, covering all the envisaged activities related to drilling rig and well platform indicating activities which are permitted, which are not permitted and which require prior approval. SIMOPS- sample matrix is given in Annexure F, for reference.

4.1.4.2 Various scenarios under SIMOPS, involving drilling rig and revamping /

construction activities on well platform, include :

I. During rig approach, piling activity, rig skidding, jack down and pull away from well platform;

II. During drilling- with diverter system regular drilling and H2S environment;

III. During well completion, well testing and well control;

IV. During hot work;

Page 14: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

9

V. During helicopter operation.

I. During rig approach, piling activity, rig skidding, jack down and pull away from well platform

(i) No revamping / construction related activities like pressure testing, radiography, hot work, confined space entry, scaffolding erection, diving within 100 meters from rig / well platform, working at height, working over side, night operations are permitted on well platform during rig approach and piling activity.

(ii) Pressure testing and diving activity within 100 meters from rig / well platform

are not permitted during jack down and pull away. Other revamping / construction related activities can be carried out with prior approval of OIM and company man / rig OIM, as the case may be.

II. During drilling - with diverter system, regular drilling and H2S environment

(i) Diving activity within 100 meters from rig / well platform, working at height and night operations are not to be performed when drilling with diverter system where there is potential of shallow gas.

(ii) During regular drilling most of the revamping / construction related activities

can be carried out. Some of the activities like radiography, hot work on platform, confined space entry, working at heights, night operations may require prior approval of OIM and company man / rig OIM, as the case may be, on case-to-case basis.

(iii) During drilling in H2S environment, none of the activities related to revamping /

construction is to be allowed.

III. During well completion, well testing and well control:

During running of explosives or radio active sources and during well control activities, no activity related to revamping / construction is to be performed on well platform.

IV. During hot work:

(i) During hot work in the well bay or in the vicinity of the wells, the platform wells are to be kept closed. The various activities related to revamping and construction activities on well platform are permitted to be performed with prior approval except pressure testing.

(ii) Refer OISD-STD-105 for requirements related to work permit.

V. During helicopter operation:

During helicopter operations, the various activities related to revamping / construction can be performed except diving. For diving, prior permission from company man / rig OIM, as the case may be, should be taken during helicopter operation.

As suggested under 4.1.4.1, organisation should develop their own SIMOPS matrix covering all the envisaged activities.

4.2 Simultaneous operations on a process platform

4.2.1 SIMOPS Organisation and management: For various SIMOPS on process platform, document should be prepared by the company outlining all the dos and don’t’s, special safety precautions to be taken, roles and responsibilities of key personnel, operations which have to be stopped /

Page 15: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

10

can be continued / can be continued with prior approval (at appropriate level), emergency response plan, etc. The person overall responsible for SIMOPS should be custodian of SIMOPS document and it is the responsibility of the custodian to seek agreement or approval from appropriate authority for any amendment.

4.2.2 Responsibilities

Offshore Installation Manager (OIM)

Has the overall responsibility for SIMOPS. Is responsible for the safety of personnel and equipment on the process platform. SIMOPS on a process platform should be in the knowledge of OIM.

Process Manager

Responsible for SIMOPS related to production activities and marine operations on a process platform. Ensures that all SIMOPS are carried out in a safe manner as per approved SIMOPS procedures. Maintains continuous liaison with OIM regarding SIMOPS. Logistics manager, if stationed on the process platform to deal with the activities related to marine operations, should be responsible for SIMOPS related to marine operations, instead of process manager. Maintenance Manager Responsible for SIMOPS related to revamping / construction activities pertaining to process equipment. Ensures that all SIMOPS are carried out in a safe manner as per approved SIMOPS procedures. Maintains continuous liaison with OIM and engineering and construction representative regarding SIMOPS. Engineering and Construction Representative Responsible for revamping / construction activities, liaises with OIM and process manager / maintenance manager for day to day activities related to revamping / construction and works closely with them to ensure adherence to SIMOPS procedures. Obtains necessary work permit and clearance from OIM / process manager / maintenance manager before commencing revamping / construction activities. Contractor representative The onsite representative of contractor engaged for revamping / construction activities, follows the directions of the engineering and construction representative. Ensures that the contractor’s personnel carry out tasks in a safe manner in accordance with SIMOPS procedures and conditions laid out in work permit. Also ensures that the contractor’s personnel have been imparted mandatory HSE trainings before being deployed for the job at site, and that they use PPE while on the job. Master of the vessel Responsible for following the marine procedures / guidelines for vessel’s operations. Liaises with the concerned process platform personnel, OIM and process manager / logistics manager during SIMOPS involving marine operations.

Page 16: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

11

4.2.3 Basic procedures to be followed during SIMOPS: (a) SIMOPS Programme

Prior to undertaking SIMOPS, job safety analysis should be carried out by process manager / logistics manager / maintenance manager, as the case may be, with all agencies associated with SIMOPS, to ensure that all the hazards related to the proposed operations are identified, assessed and determined to have the risk as low as reasonable practicable. Job safety analysis report should be approved by OIM.

(b) Hazardous Areas

Hazardous area drawings for process platform should be made available to the engineering and construction representative before carrying out revamping / construction activities. The work permit should be issued accordingly prior to commencement of activities and regularly monitored during permit duration.

(c) Fire water System

Availability of fire water system should be ensured during SIMOPS. In the event of its non availability, some of the SIMOPS, as described elsewhere, should not be undertaken.

(d) Communication and Coordination

Appropriate interfacing and good communication between the key process platform personnel and engineering & construction representative, during SIMOPS related to revamping / construction activities, is to be maintained. Regular meetings, as per written down schedule should be conducted by OIM with the concerned personnel to monitor SIMOPS activities.

(e) Station Bill & Mustering If the station bill / mustering points need to be shifted due to revamping / construction activities, prior to shifting, risk analysis should be carried out to identify additional risk, if any, due to the shift, and control measures required. The additional control measures, as required, should be taken before shifting station bill and mustering points. The shifting of station bill / mustering points should be known to all the personnel on board. The shifted points should be properly marked.

(f) Emergency response and Disaster Management Plan

Offshore installation manager (OIM) is to initiate, intimate and co-ordinate all emergency response actions from the field as per laid down policy of the company.

4.2.4 Various scenarios under SIMOPS on a process platform related to production

activities, revamping / construction activities and marine operations

I. Simultaneous activities on a process platform related to production activities:

There are many routine operations viz: well intervention (on well platform, bridge connected to process platform), opening of hydrocarbon line, instrumentation calibration, testing of PSVs, helicopter operations, crane operations, supply vessel

Page 17: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

12

approach, maintenance of gas and fire detectors and fire suppression system, maintenance of life saving appliances, etc carried out on process platform. (i) During helicopter operations, crane operations are to be suspended.

Maintenance of life boats should not be carried out during well intervention operations, helicopter operations and crane operation involving heavy lifts unless there is stand by capacity available to cater to emergency evacuation of platform personnel.

(ii) When any of these systems namely fire suppression system, gas and fire

detectors is under maintenance, operations like well intervention, opening of hydrocarbon line, instrumentation calibration, testing of PSVs, helicopter operations, crane operations involving heavy lifts, maintenance of life saving appliances are to be performed in a restricted manner with approval of OIM.

(iii) During diving operations, the routine operations can be carried out on process

platform. However, during diving operations, supply vessel approach is not to be permitted, helicopter operation and crane operations with small lifts can be performed with prior approval from OIM, on case- to- case basis.

II. Simultaneous activities on a process platform related to revamping /

construction activities

There are number of activities like painting, hydro-testing, scaffolding erection, working at height, Ultrasonic NDT, radiography, hot work, confined space entry etc related to revamping / construction activities carried out on process platforms. (i) Hydro-testing of equipment is not to be permitted when the fire suppression

system, detection (gas & fire) system are not available; other routine activities can be performed only after taking advance approval from offshore installation manager (OIM).

(ii) During radiography, activities like crane operations and approach of supply

vessel can be permitted in a restricted manner with clearance from OIM depending upon radiation level in that particular area. However, other operations can be carried out with approval of offshore installation manager (OIM).

(iii) During the hot job in the hazardous area on process platform, operations like

opening of hydrocarbon line, testing of PSVs, crane operations, maintenance of fire suppression system, gas and fire detectors, life saving appliances and sampling / leak test / venting are not permitted to be performed on platform. However, other operations can be carried out after taking permission from the offshore installation manager (OIM).

(iv) Confined space (vessel) entry is to be permitted only after obtaining work

permit and ensuring vessel is free of hydrocarbon environment with proper ventilation and supervision. Also, before entering, it is to be ensured that oxygen level is in the acceptable range. For further requirements, refer OISD-STD-105 on work permit.

(v) When the load is transferred above / near process facility by barge, on process

platform, activities namely well intervention, crane operations, maintenance of life saving appliances, fire suppression system, gas and fire detectors, sampling / leak test / venting, radiography, hot work in the process area are not to be carried out.

Page 18: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

13

(vi) During night time, well intervention operations, maintenance of life saving appliances, fire suppression system, gas and fire detectors and confined space entry are not to be carried out. Helicopter operations, crane operations involving heavy lifts and hydro-testing, should be allowed only after approval from OIM.

(vii) When testing ESD / F&G interlocks, operations viz. well intervention, opening

of hydrocarbon line, helicopter operations, crane operations, maintenance of gas and fire detectors, sampling / leak test / venting, load transfer above / near the process facility and night operations are not to be carried out.

III. Simultaneous activities on a process platform related to marine operations

Marine activities include running anchors, hot work onboard vessel / barge, crane operations for load transfers, personnel transfer by crew boat, radiography onboard vessel / barge, diving from vessel / barge, inspection, maintenance & repair activities related to platform, riser installation, in field line pipe installation in the vicinity of process platform etc. (i) Diving is not to be allowed during running of anchors, personnel transfer by

crew boat and load transfer between platform and vessel / barge. (ii) Supply vessel approach on the same side is not to be allowed during diving

from vessel / barge. (iii) During load transfer, no operations in the vicinity are to be permitted. (iv) During riser installation and infield line pipe installation in the vicinity of

platform, the following operations should have prior approval of OIM- supply vessel approach, diving from platform, radiography, running of anchors, diving from vessel / barge and load transfer between platform and vessel / barge.

The above scenarios are typical cases. It is recommended that organisation should develop their own SIMOPS matrix, covering all the envisaged activities related to process platform indicating activities which are permitted, which are not permitted and which require prior approval.

4.3 Non-rig related simultaneous activities on a well platform

For any non – rig related job on an unmanned well platform like wireline, cased hole logging, coiled tubing unit assisted well intervention, revamping / construction etc, OIM shall have the overall responsibility of SIMOPS. Production representative (Wellhead manager) shall oversee SIMOPS on the well platform and shall closely liaise with the designated representative of the service provider. The SIMOPS related requirements as mentioned under ‘SIMOPS on a process platform’ should be followed, as applicable.

5.0 ONSHORE SIMULTANEOUS OPERATIONS

Typical scenarios covered under onshore are:

· Simultaneous operations involving drilling rig / workover rig, · Simultaneous operations inside production installation. The above scenarios are indicative only. The companies should develop their own scenarios based on the risk assessment of various SIMOPS activities.

Page 19: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

14

5.1 Simultaneous operations involving drilling rig / workover rig :

5.1.1 SIMOPS Organisation and management: When the drilling rig / workover rig is operating inside an installation (i.e. a location where oil / gas processing and transportation is being carried out in the vicinity of the well under drilling / workover) or at a cluster location, both the facilities should be defined and considered as a single combined installation. For various SIMOPS, document should be prepared by the company outlining all the dos and don’t’s, special safety precautions to be taken, roles and responsibilities of key personnel, operations which have to be stopped / can be continued / can be continued with prior approval (at appropriate level), emergency response plan, etc. The person responsible for SIMOPS should be the custodian of SIMOPS document and it is the responsibility of the custodian to seek agreement or approval from appropriate authority for any amendment.

5.1.2 Responsibilities

5.1.2.1 In case of hired drilling rig / workover rig The responsibilities as enumerated below are also applicable to company owned rigs operating under operation and maintenance / man management contract. Company man The Company representative at the rig, has the overall responsibility for SIMOPS. Controls and regulates the work of the drilling / well intervention programmes on the combined installation. Is authorised, as per Annexure-A, by the company as overall responsible for SIMOPS on the combined installation. Rig Manager Is responsible for the safety of personnel and equipment of the rig and performs work programme approved by the company management. Installation Manager (IM) Any operation in the operating field should be with the knowledge of the installation manager (IM) of the installation to which the well is connected. Liaises with the company man for all operational matters related to SIMOPS and also co-ordinates the shut down requirements of the wells. In case of drilling rig / workover rig inside an installation, though the primary responsibility for SIMOPS is of company man, installation manager (IM) ensures close liaison with the company man, related to SIMOPS.

5.1.2.2 In case of company owned drilling rig / workover rig

Rig Manager Has the overall responsibility for SIMOPS. Is responsible for the safety of personnel and equipment of the rig and performs work programme approved by the company management.

Page 20: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

15

Installation Manager (IM) Any operation in the operating field should be with the knowledge of the installation manager (IM) of the installation to which the well is connected. Liaises with the rig manager for all operational matters related to SIMOPS and also coordinates the shut down requirements of the wells. In case of drilling rig / workover rig inside an installation, though the primary responsibility for SIMOPS is of rig manager, installation manager (IM) ensures close liaison with the rig manager related to SIMOPS.

5.1.3 Basic procedures to be followed during SIMOPS:

(a) SIMOPS Programme

Prior to undertaking SIMOPS, job safety analysis should be carried out by the person responsible for SIMOPS (company man / rig manager, as the case may be) with all agencies associated with SIMOPS, to ensure that all the hazards related to the proposed operations are identified, assessed and determined to have the risk as low as reasonably practicable. Job analysis report should be approved by installation manager (IM).

(b) Well Closure

In case of drilling / workover activity inside an installation / at cluster location, prior to movement of the rig, detailed risk analysis should be carried out to determine the additional risks imposed due to drilling rig / workover rig related activities inside the installation / at cluster well location and additional controls required to handle these risks under the following scenarios : - production activities can continue during all phases of drilling rig / workover

rig activities with / without some restriction.

- production activities are to be suspended only till rig building stage and thereafter during rig dismantling and its transportation stage.

- production activities should remain suspended during period drilling rig / workover rig is inside the installation / at cluster locations.

Only after the additional control measures are in place, corresponding to one of the above scenarios, drilling rig / workover rig related activities should be undertaken under that scenario.

(c) Hazardous Areas

If rig is to be inside the installation, hazardous area classification drawing of the installation and rig’s hazardous area classification drawing should be combined to establish a composite hazardous area classification drawing.

(d) Fire water System

The rig should have independent fire suppression system which can handle fire on the rig and the cluster well. Fire fighting hoses and fire nozzles should be strategically positioned, and regularly tested.

(e) Communication and Coordination

Page 21: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

16

Appropriate interfacing and good communication between the installation and drilling rig / workover rig throughout the simultaneous activities is to be maintained. Company man / rig manager, as the case may be, should hold regular meetings, as per written down schedule, with all the concerned personnel to review SIMOPS.

(f) Drilling Station Bill & Mustering The drilling rig / workover rig should initiate a SIMOPS “Induction” for all personnel when they arrive on the rig. The personnel should be aware about the mustering points which should be used in case of emergency.

(g) Emergency response

In the event of any emergency on the rig involving a cluster well or installation having rig inside, it is the responsibility of the company man / rig manager, as the case may be, to initiate and co-ordinate all emergency response actions as per approved SIMOPS documents, in close liaison with IM.

5.1.4 Simultaneous operations involving drilling rig / workover rig, at cluster

locations include I. Movement of drilling rig / workover rig around the producing oil / gas wells,

II. Skidding of drilling rig and shifting of drilling rig / workover rig in cluster location,

III. Drilling / workover on one well and activation of / wireline job on another well in the cluster,

IV. Drilling / workover on one well and CTU / Stimulation job on another well in the cluster,

V. Drilling rig / workover rig inside the installation.

At a cluster location, more than one well is drilled from the same plinth. These may involve simultaneous operations like well drilling / workover operations / production related activities, at the same location. The SIMOPS may take place under various scenarios like:

(a) One well is under production and the rig building is in progress for drilling

second well.

(b) One or more wells are on production and the drilling / workover operation is in progress on another well.

(c) One well is under drilling, another well is under workover operations and other wells are under production. This scenario should be avoided.

The cluster wells are generally adequately spaced for carrying out drilling / workover operations in each well without creating any hindrance during transportation, rig building and rig dismantling. The routine operations involved in a producing well include: (a) Mechanical scraping, (b) Bottom Hole Studies

(c) Artificial lift monitoring / servicing / optimization, etc

Page 22: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

17

(i) In cluster drilling, a concern is below surface collision of the well with the

neighbouring well. The higher risk is in the upper part where all the wells are close to each other, but risk at depth still exists. Precautions should be taken while preparing well programme (well profile) to avoid this kind of situation otherwise consequences can be serious when the producing well is hit.

(ii) The SIMOPS checklist is to be filled up by company man / rig manager and

installation manager as shown as Annexure G, to ensure that all preparatory works have been completed prior to rig movement.

(iii) The cluster wells normally should not be permitted to flow during

transportation, rig building, rig dismantling (refer 5.1.3 (b)). The cluster wells should be permitted to be flown only after taking approval from SIMOPS incharge.

(iv) The escape routes of drilling rig / workover rig should be free from any

obstruction. (v) Hazardous zone classification around cluster wells should be done as per

latest guidelines of DGMS and hazardous zones should be free from any spark from engine exhaust / electric motor. The electrical equipment should be suitable for the hazardous area.

(vi) The Xmas tree of cluster wells and flow lines / injection lines should be

protected by means of temporary physical barrier above and around it, so that the same may not be damaged by falling objects and inadvertent hitting by rig equipment. The cluster wells should be taken up for temporary protection before the drilling rig / workover rig moves in.

(vii) Around the producing wells in the cluster, presence of gas to be monitored at

pre-defined intervals and records maintained. Possibility of installation of continuous gas monitoring system with a panel at driller's console connected to gas detecting probes placed at specific locations at the producing well / stand alone portable gas detectors covering large area, may be looked into. Besides monitoring of gas around the producing wells, continuous monitoring for the presence of gas be undertaken, at cellar pit of drilling well, and at mud channel at shale shaker end and corrective actions be taken as necessary and records maintained. In case of major leakage of oil / gas at the plinth, the company man / rig manager, as the case may be, should stop drilling operation till the leakage is rectified and the well has been brought to the safe condition. There should be a written down procedure to tackle the presence of gas, around the producing wells and at the rig.

(viii) Minimum three 20 Kg DCP trolley mounted fire extinguishers should be placed

in a cluster area. (ix) Flow line and gas injection line from / to the producing wells should be laid at

an adequate distance from substructure of rig and buried as far as possible or re- routed, if required to avoid damage during drilling / workover, rig building / dismantling, transportation etc.

(x) Caution notice board mentioning "DANGER - High pressure gas line / oil flow

line" should be displayed at appropriate places. Caution board mentioning "DANGER - Well on production" should be displayed at the producing well(s).

Page 23: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

18

(xi) In case of high pressure wells (high flowing tubing head pressure) in the cluster locations, a pneumatically / hydraulic controlled valve should be installed on the X-mas tree (wing valve) with remote control on the derrick floor near driller's control panel to shut-off flow in case of emergency.

(xii) Before carrying out of servicing, monitoring jobs etc on a producing well, pre-

planning of jobs should be done, keeping in view the drilling / workover operations in the vicinity. Special / additional procedures to be followed and safety precautions to be taken, under SIMOPS situation, should be clearly spelt out.

(xiii) Clearance from SIMOPS incharge (company man / rig manager, as the case

may be) should be obtained before undertaking any job on any cluster well and close coordination between well servicing / monitoring personnel and drilling / workover rig personnel should be maintained throughout.

(xiv) Basic safety precautions include:

1. Scraping winch should be placed at safe distance away from the producing

well as well as drilling well and the winch-engine should have a spark arrestor.

2. No welding, cutting or other hot work to be performed during the period of scraping, and bottom hole study.

3. Job safety analysis should be done before taking up any hot / cold jobs in the cluster locations.

4. No vehicular movement is to be allowed at site during SIMOPS unless it is permitted by company man / rig manager, as the case may be.

5. No gas should be allowed to vent from the well into the atmosphere in any operation.

6. Lubricator should be tested up to the expected maximum pressure so that no leakage of gas / oil takes place during scraping / BHS recording.

7. Assembly of perforation gun is to be carried out at a safe distance from the producing wells and area around the well should be gas free when perforation gun is assembled, run in and pulled out.

I. Movement of drilling rig / workover rig around the producing oil / gas wells

The risks involved during transportation of rig are fire and pollution due to damage of well flow lines / injection lines. The rig manager and logistic manager should inspect the route to check for any obstructions like overhead power lines, sharp bends, over ground pipelines etc. Thereafter, the route to be followed for rig movement by logistics should be decided prior to movement of the rig. (i) During transportation over the underground pipelines, the vehicle should pass /

cross over with utmost care. All vehicles, heavy earth moving equipment and the cranes should be fitted with spark arrestor. No unauthorized person should be allowed to enter in the operational area at drill site. It should be ensured that the flowlines / injection lines at the location, protected before the rig moves in, are at an adequate distance away from load carrying activities / vehicular movement.

Page 24: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

19

(ii) The producing wells should be checked for any leakage of gas / oil before and during movement of rig equipment in / around the area. IM should be informed in advance of the rig movement into his area.

II. Skidding of drilling rig and shifting of drilling rig / workover rig in cluster location

There are two methods of rig movement in a cluster location.

(a) Rig skidding

(b) Rig down and shifting

The rig skidding involves skidding of the rig structure along with mast through a small distance over the concrete foundation, while retaining other equipment e.g. mud handling system, power packs, diesel / water tanks etc. at the original position for undertaking drilling at new point in the cluster.

Shifting of the rig involves mast lowering and dismantling of the mast and

substructure thereafter shifting to the required location and subsequent erection.

(i) Company should develop their SIMOPS matrix covering all the envisaged activities related to shifting / skidding of rig indicating activities which are permitted, which are not permitted and which require prior permission.

(ii) Pre-operation meeting should be conducted and plan prepared for safe shifting

/ skidding of rig and its material. (iii) Before deciding for skidding, the risk of collapsing / toppling of mast should be

evaluated. It may damage the adjoining producing well resulting in leakage of oil / gas which may cause fire and environment pollution, besides equipment damage.

(iv) The skidding of rig is generally permitted when no loose equipment material

including BOP and tubulars are there on the substructure / mast and when there is no unevenness of the foundation which may lead to accident during skidding.

(v) Skidding of rig is not to be permitted if the flow lines / injection lines are not at a

safe distance from the skidding route. (vi) The rig should be allowed to skid / shift only when it is ensured that there is no

leakage of gas / oil from cluster wells as spark, which may occur during skidding / shifting, may lead to fire.

(vii) The skidding / shifting operations are permitted in day time only and after

carrying out of visual inspection of the mast and substructure for cracks, misalignment etc.

(viii) SRP units operation in the cluster location, should be stopped during rig

skidding / shifting. (ix) SRP units operation on the adjoining well (s) to be stopped, during rig down /

up.

III. Drilling / workover on one well and activation of / wireline job on another well in the cluster

Page 25: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

20

These operations involve drilling rig / workover rig on well by the side of another well which is being activated by displacement, compressor, nitrogen application etc. or under wireline job.

(i) Company should develop their SIMOPS matrix covering all the envisaged

activities related to drilling / workover on one well and activation of / wireline job on another well indicating activities which are permitted, which are not permitted and which require prior permission.

(ii) Hazards associated with activation jobs are fire due to gas spread, accidental

damage to X-mas tree, wellhead, flow line etc. During activation, no hot work is to be permitted in the hazardous zone.

(iii) Activation job is permitted only when the area is hydrocarbon free and checked

with the help of gas detector and all connections, flow lines & joints tested up to maximum expected pressure. Personnel not related to the job are not permitted to go near the flow lines and activation units. Activation jobs should be carried out in day time only.

(iv) Wireline lubricator should be prior tested for expected maximum pressure. (v) During wireline job, immediate work area should be kept free of non-essential

workers to avoid potential hazards of being struck by wireline & wireline equipment or getting caught in wire line.

IV. Drilling / workover on one well and CTU / Stimulation job on another well in the

cluster

These operations involve drilling rig / workover rig on a well in the cluster and CTU / stimulation job on another well. (i) Company should develop their SIMOPS matrix covering all the envisaged

activities related to drilling / workover on one well and CTU / stimulation job on another, which are permitted, which are not permitted and which require prior permission.

(ii) Pre-operation meeting should be carried out by company man / rig manager,

as the case may be, with IM and other concerned personnel (Incharge stimulation / CTU etc.) and plan prepared for CTU / stimulation job.

(iii) Hazards associated with these jobs are fire due to gas spread, sparking due to

loose motor connection, handling of heavy objects and accidental damage to Xmas tree, wellhead, flow lines etc. and handling of hazardous chemicals including concentrated acids.

(iv) Personnel not related to the job are not permitted to go near the high pressure

lines and stimulation / CTU units. During stimulation job namely acidisation or hydraulic fracturing, hot work is to be permitted only in designated area. Stimulation jobs should be carried out in day time only.

(v) Personnel should be trained to handle hazardous chemicals and should use

appropriate PPEs during stimulation job. (vi) Stimulation job is to be permitted only when the area is hydrocarbon free and

all connections, flow lines and joints are tested up to maximum expected pressure.

Page 26: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

21

(vii) CTU should be rigged up in accordance with manufacturer’s recommendations. V. Drilling rig / workover rig inside the installation

At location where production facilities have been created near the wells (mostly at installations of temporary nature like well head installation / early production system), for drilling / servicing of well, the drilling rig / workover rig has to come inside the installation. (i) Company should develop their SIMOPS matrix covering all the envisaged

activities related to drilling / workover operations inside the installation indicating activities which are permitted, which are not permitted and which require prior permission.

(ii) Pre-operation meeting should be carried out company man / rig manager, as

the case may be, with IM and other concerned personnel including logistics and plan prepared for rig operations inside the installation.

(iii) During transportation of rig and its material, safe distances are to be

maintained from process units / crude oil storage tanks. (iv) Only spark arrestor fitted vehicle should be allowed inside the installation. (v) Gas concentration is to be checked before shifting of the rig and during rig

operations and recorded. Hot jobs are to be permitted only after prior approval from company man / rig manager, as the case may be, and IM, and should be avoided during rig skidding. Refer OISD-STD-105 for requirements related to work permit.

(vi) Before deciding for skidding, the risk of collapsing / toppling of mast should be

evaluated. It may damage the adjoining flow lines, process units and crude oil storage tanks resulting in leakage of oil / gas which may cause fire and environment pollution.

(vii) Fire water network of the installation should be extended to interface with

drilling rig / workover rig fire fighting system, if required. Other safety precautions, as applicable, as per preceding sub-sections should be followed.

5.2 Simultaneous operations inside production installation 5.2.1 SIMOPS Organisation and management:

SIMOPS involve project activities related to revamping / construction carried out inside an installation. For various SIMOPS, document should be prepared by the company outlining all the dos and don’t’s, special safety precautions to be taken, roles and responsibilities of key personnel, operations which have to be stopped / can be continued / can be continued with prior approval (at appropriate level), emergency response plan, etc. The person responsible for SIMOPS should be the custodian of SIMOPS document and it is the responsibility of the custodian to seek agreement or approval from appropriate authority for any amendment.

5.2.2 Responsibilities

Page 27: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

22

Installation Manager (IM) Has the overall responsibility for SIMOPS. Is responsible for the safety of personnel and equipment of the installation. SIMOPS in the installation should be in the knowledge of IM. Installation shift incharge Responsible for SIMOPS related to production activities in an installation. Ensures that all SIMOPS are carried out in a safe manner as per approved SIMOPS procedures. Maintains continuous liaison with IM and engineering and construction representative, regarding SIMOPS. Engineering and Construction Representative

Responsible for revamping / construction activities, liaises with IM and installation shift incharge for day to day activities related to revamping / construction and work closely with them to ensure adherence to SIMOPS procedures. Obtains necessary work permit and clearance from IM / installation shift incharge before commencing revamping / construction activities.

Contractor representative

The onsite representative of contractor engaged for revamping / construction activities, follows the directions of the engineering and construction representative. Ensures that the contractor’s personnel carry out tasks in a safe manner in accordance with SIMOPS procedure and conditions laid out in work permit. Also ensures that the contractor’s personnel have been imparted mandatory HSE trainings before being deployed for the job at site, and that they use PPE while on the job.

5.2.3 Basic procedures to be followed during SIMOPS: (a) SIMOPS Programme

Prior to undertaking SIMOPS, job safety analysis should be carried out by the installation shift incharge with all the agencies associated with SIMOPS, to ensure that all the hazards related to the proposed operations are identified, assessed and determined to have the risk as low as reasonable practicable. Job analysis report should be approved by installation manager (IM).

(b) Hazardous Areas

Hazardous area drawing for the installation should be made available to the engineering and construction representative before carrying out revamping / construction activities. The work permit should be issued accordingly, prior to commencement of activities and regularly monitored during permit duration. The work permit should be closed after completion of the particular task.

(c) Fire water System

Availability of fire water system should be ensured during SIMOPS.

(d) Communication and Coordination

Page 28: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

23

Appropriate interfacing and good communication between the key installation personnel and engineering and construction representative, during SIMOPS related to revamping / construction activities, is to be maintained. Regular meetings, as per written down schedule should be conducted by IM with the concerned personnel to monitor SIMOPS activities.

(e) Mustering If the mustering points need to be shifted due to revamping / construction activities, prior to shifting, risk analysis should be carried out to identify additional risk, if any, due to the shift, and control measures required. The additional control measures, as required, should be taken before shifting mustering points. The shifting of mustering points should be known to all the personnel of the installation and contract workers. The shifted points should be properly marked.

(f) Emergency response

Installation Manager (IM) is to initiate, intimate and co-ordinate all emergency response actions from the field as per the emergency response plan.

5.2.4 Precautions during SIMOPS inside production installation

(i) The area, in which the project activities are being undertaken, should be

demarcated and caution board should be displayed around the construction site.

(ii) The permit to work is to be taken from IM / installation shift incharge before

commencing any activity. The work permit should be closed after completion of the particular task. Refer OISD-STD-105 for requirements related to work permit.

(iii) The job should be supervised by the engineering and construction

representative and ensured that all activities are carried out in safe manner and as per approved SIMOPS procedures.

(iv) Adequate fire fighting facility should be available during hot jobs. Gas

concentrations should be taken before and during the job and recorded. No hot job is to be carried out if the gas concentration is beyond the acceptable limit.

**********

Page 29: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

24

Annexure-A Delegation of Authority Letter, in case of hired rig Company Address: No.: Date:

DELEGATION OF AUTHORITY

Sh._________________ is hereby authorized as the ‘Company Man’ at your rig ________ .

He shall have the overall responsibility for all SIMOPS, whilst the rig is located at the

_________ offshore platform / onland well no _______.

He is authorized to have the signatory control of issuing all hot work and safety critical

permits related to SIMOPS, and shall ensure that all the activities comply with the

requirements of the company’s policy / procedures and applicable Govt. of India regulations.

Head of Drilling / Head of Well Services Company

Page 30: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

25

Annexure-B

Pre-Operations Check List (Offshore) The following check list should be used as a guideline and should be signed by the company man / rig OIM, as the case may be:

9 Install remote, portable P/A speaker on platform

After stairway is established

10 Install gas detector below cantilever near platform gas vent

After stairway is established

11 Connect up and pressurize seawater line to the platform. Connect firefighting hoses and nozzles and test same.

As soon as access stairway is established

12 Ensure interfacing of ESD system of the well platform with that of the rig. Test the ESD system is operational.

As soon as stairway is established

13 Ensure that all personnel are familiar with the location and limitations of the platform muster station and understand that it is only to be used if access to the rig`s muster stations is prevented.

After stairway is established

Contd./-

Pre-Operations Check List

S.No

Action Timing Company man / rig OIM signature

1 Ensure rig move meeting has been held, prior to rig move

Prior to rig move

2 All wells on the platform are shut in and de-pressured as detailed in the “Basic Procedures” (refer 4.1.3)

Prior to rig move

3 Ensure chemical containers and other loose materials are identified, labeled and secured on the Platform.

Prior to rig move

4 Communication, power and other systems to be provided by the rig to the platform and vice-versa, are available.

Prior to rig move

5 Ensure all lifting points on hatch covers on platform main deck are inspected and fit for use. Ensure availability of dedicated lifting slings.

Prior to rig move

6 Ensure that the last production crew, prior to the rig move, positions the platform crane in a safe way so that it does not hinder the rig`s access to the production platform.

Prior to rig move

7 Ensure there are sufficient portable gas detectors to cover all work on platform

Prior to rig move

8 Ensure the primary and secondary stairways are positioned between the rig and the platform as soon as jacking up is complete.

Immediately after cantilevering out over well head

Page 31: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

26

Pre-Operations Check List

S.No

Action Timing Company man / rig OIM signature

14 Carry out a muster drill involving personnel who are likely to work on the platform during the period rig is there.

As soon as practical after stairway is established

15 Ensure drilling rig “inductions” include all aspects of safety, relating to SIMOPS

Prior to commencing well operations.

16 Position an “OUT OF USE” sign at the access to the boat landing on the Platform

As soon as stairway is established

17 Ensure the Platform crane is in its cradle, Isolate and lock crane.

As soon as stairway is established

18 Inform logistics incharge of the company, OIM and Company’s base office that platform helideck is out of operation and that the rig`s helideck is available for use instead, till the rig is on the platform.

As soon as stairway is established

19 Establish communication with supply boats. Ensure vessels are familiar with procedures for coming under the drilling rig within proximity of the platform.

Prior to commencing operations

Page 32: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

27

Annexure-C

Documents / Information (Offshore)

· Well platform details related to safety valves and their control system, gas and fire detection system etc.

· Marine Operations Manual

· HSE bridging document, in case of hired rig

· Well platform risk register

· Hazardous area drawing

· Well platform handover as per Annexure D and delegation of authority letter as per Annexure A, if applicable.

· Emergency response plan - onsite

· Emergency response plan - offsite

Page 33: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

28

Annexure-D

Platform Handover Form for Drilling / Working over well no(s) _________

_________Platform Handover from____________ to __________ Date : ________

Platform Handover Form for Drilling / Working over

S.No Description Condition during

handover

Remarks

OIM to company man / rig OIM

Company man / rig OIM to OIM

Wellhead & Xmas tree (all the

platform wells)

1 Annulus Valves (Pressures in A,B

& C sections)

2 Housekeeping around wellhead

3 Any leaks

4 Any oil spills

5 Surface safety (MSDV,

WSDV)

6 Sub-surface safety (SSSV)

Manifold & flow lines 1 Condition of manifold valves

2 Any leaks from the valves

Main Hydraulic panel 1 Any hydraulic oil leaks from

control lines

2 Panel board covered with

tarpaulin & secured

Close drain drum 1 Condition of the pump

2 House keeping in and around

Instrument gas drum (IGD) 1 Condition of all manual valves

2 Condition of all inlet & outlet lines

Crane

1 Crane is in its cradle

2 Crane engine & winch covered

3 Crane isolated from starting

Page 34: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

29

Platform Handover Form for Drilling / Working over

S.No Description Condition during handover

Remarks

OIM to company man / rig OIM

Company man / rig OIM to OIM

Consumables – Stock 1 Diesel tank - stock

General 1 Condition of platform lighting

2 Condition of helideck

3 Condition of DG

4 Cover on well slots

5 Any hatches / openings on the

platform decks which are without

cover.

Life saving equipment 1 Swing ropes

2 Life jackets / work vest

3 Life raft

4 Life rings / throwing lines

5 Navigation lights

6 Fog horn

7 Wind sock condition

_________________ ____________ ____________________ __________ Signature Date Signature OIM Date Company man / RIG OIM

Page 35: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

30

Annexure-E Post - Operations Check List (Offshore) This check list, to be signed by the company man / rig OIM, as the case may be, covers the removal of the temporary services extended around the platform. The following to be checked prior to rig move:

Post-Operations Check List

S.No

Action Company man / rig OIM signature

1 Ensure rig move meeting has been held.

2 All wells on the platform are shut in and de-pressured during moving away from the platform.

3 Recover all the temporary facilities from the platform.

4 Recover the seawater line.

5 Remove any extraneous equipment / material from the Platform

6 Ensure all platform hatch covers are in place.

7 Remove the “OUT OF USE” sign from the boat landing.

8 Ensure Platform is clean from drilling mud etc.

9 Recover the Access Stairways.

10 Communicate the completion of all recovery to OIM.

11 Once clear of the platform, inform OIM.

Page 36: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

31

Annexure-F

SIMOPS - SAMPLE MATRIX (Drilling rig on well platform)

Wel

ls o

n p

rod

uct

ion

Ap

pro

ach

of

sup

ply

ves

sel

G &

F d

etec

tio

n m

ain

ten

ance

Cra

ne

op

erat

ion

s

_ _

_ _

_ _

_ _

_ _

_ _

_ _

_ _

_ _

_ _

_ _

_ _

_

Rig skidding (during rig move) NP NP NP NP Drilling with diverter system (med-high potential shallow gas) PPA NP NP PPA

Drilling in H2S environment P NP NP NP

Hot work in vicinity of platform wells NP NP NP PPA

Helicopter operations P P PPA NP

_ _ _ _ _ _ _ _ _ __ _ _ _ _ _

_ _ _ _ _ _ _ _ _ __ _ _ _ _ _

_ _ _ _ _ _ _ _ _ __ _ _ _ _ _

P - Permitted

NP - Not permitted PPA- Permitted with prior approval

Page 37: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

OISD-GDN-186

"OISD hereby expressly disclaims any liability or responsibility for loss or damage resulting from

use of the OISD Standards/ Guidelines/ Recommended Practices."

32

Annexure-G SIMOPS Check list (Onshore) The following check list should be used as a guideline before the rig moves to cluster location

/ inside the installation and should be signed by the company man / rig manager &

installation manager:

SIMOPS Check list (Onshore)

S.No Action Observations

Remarks

1 A meeting has been held among drilling rig /

workover, company man / rig manager, as the

case may be, and installation manager for

finalizing the SIMOPS programme and

accordingly preparatory activities have been

carried out before the rig is moved to cluster

location / inside installation?

2 Ensure that cluster wells shut down is as per

5.1.3 (a).

3 The Escape routes of drilling rig / workover rig

are identified and are free from any

obstruction

4 Ensure that there is no leakage of oil and gas

before the rig is moved and during rig

operations. Frequency of gas checking

should be established and followed.

5 The Xmas tree and flow lines / injections lines

of cluster wells are at safe distance from rig

substructure and temporarily physically

protected to prevent from damage due to fall

of material during rig transportation, rig

building / rig dismantling.

6 Minimum three 20 Kg DCP trolley mounted

fire extinguishers have been placed in cluster

area

7 The flow lines / injection lines passing through

the cluster location have been buried

underground.

Contd./-

Page 38: FOREWORD - OILWEB - Corporate Intranet Portal standard...(OISD) staffed from within the industry for formulating and implementing a series of self regulatory measures aimed at removing

<< Back Home Next >>