flood risk management strategy for milton and the ...flood risk management strategy for milton and...

42
Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton July 2007

Upload: others

Post on 28-Dec-2019

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Flood Risk Management Strategy for Milton and the Tokomairiro Plain

Ajax Street (foreground), Milton June 1972 Ajax Street, Milton July 2007

Page 2: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Clutha District Council (CDC) P O Box 25, 1 Rosebank Terrace, Balclutha 9240 Phone 03 419 0200 Fax 03 418 3185 Freephone 0800 801 350 www.cluthadc.govt.nz Otago Regional Council (ORC) Private Bag 1954, 70 Stafford Street, Dunedin 9054 Phone 03 474 0827 Fax 03 479 0015 Freephone 0800 474 082 www.orc.govt.nz © Copyright for this publication is held by the Otago Regional Council. This publication may be reproduced in whole or in part, provided the source is fully and clearly acknowledged. ISBN 978-0-478-37670-8 Published July 2012 Prepared by: Michael Goldsmith, ORC, manager natural hazards, and Murray Brass, CDC, planning and environmental manager

Page 3: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page ii

Table of Contents

1 Introduction ................................................................................................................................... 1

2 Scope ........................................................................................................................................... 1

2.1 Geographical ....................................................................................................................... 1

2.2 Risk ..................................................................................................................................... 1

2.3 Strategy development ......................................................................................................... 1

3 Environment setting ...................................................................................................................... 4

3.1 Geographical setting ........................................................................................................... 4

3.2 Meteorological setting ......................................................................................................... 4

3.3 Hydrological setting ............................................................................................................. 5

3.4 Community setting .............................................................................................................. 8

4 Legislative context ........................................................................................................................ 9

5 Principles .................................................................................................................................... 11

6 Strategic elements ...................................................................................................................... 12

6.1 Understanding natural river and catchment processes ..................................................... 12

6.2 Understanding infrastructural flood risk ............................................................................. 13

6.3 Flood sensitive urban design ............................................................................................ 14

6.4 Robust community response systems............................................................................... 15

6.5 Physical works .................................................................................................................. 16

7 Flood risk management maps .................................................................................................... 16

8 Control Mechanisms ................................................................................................................... 20

9 Possible mitigation works ........................................................................................................... 31

9.1 Road and rail infrastructure ............................................................................................... 31

References .......................................................................................................................................... 32

Glossary ............................................................................................................................................... 33

Resource consent requirements - Types of activities .......................................................................... 34

Appendix 1. Characteristics of Flood Hazard on the Tokomairiro Plain ......................................... 35

Appendix 2. Inundation depths across the roading network in Milton and the Tokomairiro floodplain, which could be expected during a high magnitude flood. .................................................................... 37

Appendix 3. Milton 2060 Action Plan: Flood Risk Management Initiatives – July 2012.................. 38

Page 4: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 1

1 Introduction

Flooding as a result of heavy rainfall in the Tokomairiro catchment is a natural process which is largely uncontrollable. Milton, which sits at the centre of the Tokomairiro Plain (Figure 1) is prone to flooding, often with adverse effects. The Otago Regional Council (ORC) and the Clutha District Council (CDC) have proposed the Milton 2060 Flood Risk Management Strategy to enable long-term, sustainable occupation and development in Milton. The strategy’s objectives are to:

identify the characteristics of flood events, and their effect on Milton and the northern Tokomairiro plain;

equip the community to understand, and live with, the effects of flooding; guide the nature and extent of land use development so that that flood risk does not increase

and that this risk is progressively reduced, and; support the investigation and implementation of flood risk reduction measures.

Sections 2 and 3 respectively describe the scope of the strategy, and the environment within which it sits. Section 4 describes the legislative context within which the strategy has been defined and will operate. Sections 5 and 6 outline the strategy’s guiding principles and core components. Defined areas with common flood hazard characteristics are mapped in Section 7. The control mechanisms for managing and reducing flood risk within those areas are outlined in Section 8. Section 9 describes some physical works which could reduce the flood hazard in parts of Milton. 2 Scope

2.1 Geographical

The strategy’s geographical scope is the Milton urban area, including Tokoiti and Helensbrook. It also encompasses the full width of the Tokomairiro floodplain between Clarkesville and Milburn (Figure 2). The natural and social setting specific to Milton and the surrounding floodplain is discussed in Section 3.

2.2 Risk

This strategy addresses Milton and the surrounding floodplain’s flood hazard, focusing on the risks and impacts associated with high river levels and surface runoff. It is recognised that heavy rainfall events may lead to a range of other risks, including sediment movement and land instability. There are several other natural hazards in the Tokomairiro catchment. These include seismic activity associated with local fault systems and other major faults in the lower South Island, and extreme sea levels associated with storm surge or tsunami activity. While numerous other natural hazards exist, the strategy is primarily concerned with the flood risk associated with high river levels and the drainage of surface runoff across the Tokomairiro Plain.

2.3 Strategy development

The strategy is intended to be a living document, which will evolve in response to new information on flood hazard and risk,1 the needs of the community, and the work of the respective councils. It will be reviewed every three years as part of both councils’ long-term planning process. The review process will be a joint one between ORC and CDC. It will involve executive staff with responsibilities for land use planning and control, building control, utilities and natural hazards; and CEO’s and local councillors from both councils. The review is proposed to monitor the strategy’s effectiveness; the workability of the principles, relevance of the identified issues and success of the initiatives actioned.

1 Including additional understanding of flood hazard and risk gathered during future flood events.

Page 5: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 2

Figure 1. Tokomairiro catchment boundary.

Page 6: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 3

Figure 2. Location of Milton and the northern Tokomairiro Plain.

Page 7: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 4

3 Environment setting

The natural and social settings’ special characteristics which shape the flood hazard in the study area are as follows:

3.1 Geographical setting

The town of Milton is located on the Tokomairiro Plain, which lies within the Tokomairiro catchment (Figure 1), between Dunedin and Balclutha. The plain has been formed as gravel. Sediment has been eroded from the surrounding hill country, and subsequently deposited in the depression between the eastern and western hills. This process is thought to be still occurring on a limited scale, in areas actively affected by floodwater, such as Salmond’s Creek to the north of Milton. Sediment carried by flood flows in these creeks can be deposited in the catchment’s lower reaches, where the slope is shallower and stream velocity reduces. The remainder of the plain has been identified as an inactive floodwater dominant alluvial fan (Opus, 2009).

3.2 Meteorological setting

The Tokomairiro catchment is located on the east coast of the lower South Island, within Clutha District. Flood events in coastal catchments such as the Tokomairiro are generally caused by persistent rain-bearing easterlies, with continual rainfall over several days saturating the soil, leading to rapid runoff. Generally these types of events occur in late summer to late autumn, although they can occur at any time of the year. Figure 3 shows the distribution of rainfall across the catchment during a severe storm in July 2007. During this event, the heaviest rain fell in a band along the low-lying area between Milton and Waihola, with more moderate totals to the east and west of this band. A similar pattern occurred in April 2006. Anecdotal evidence suggests that rainfall is often more intense through this low-lying part of the catchment. While Figure 3 shows a number of daily manual rain gauges spread across the catchment, automatic (instantaneous) records did not start until August 2011, when a gauge was installed at Table Hill Road in the upper north branch. The nearest long-term automatic gauges are at Riccarton Road on the Taieri Plain, and at Balclutha. Although weather conditions generally clear reasonably quickly after heavy rainfall events, enabling river levels to drop away, a sequence of fronts will occasionally move across the east coast, bringing further rain to already saturated catchments. The effect of these frontal bands can sometimes be compounded by the added runoff from snowmelt in the upper catchment.

Page 8: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 5

Figure 3. Rainfall totals (in mm) at manual rain-gauge stations on 29 and 30 July 2007. Isohyets are shown as thick red lines, separating areas of low (<40mm), medium and high (>100mm) rainfall intensity during this period.

3.3 Hydrological setting

The entire Tokomairiro River catchment is 393 km2 in area, and extends from Toko Mouth approximately 30km inland to the north and northwest. The highest point is 584m above sea level in the far north of the catchment. River flow information is limited to one long-term river monitoring site on the west branch of the Tokomairiro River at SH8, commissioned in 1981. The catchment area upstream of this site is 69km2 and is shown in Figure 1. Figure 4 shows the full flow record for this site - the largest flood events on record occurred in April 2006 (147 cumecs), July 2007 (134 cumecs), February 1991 (102 cumecs) and May 2010 (83 cumecs).2 Additional evidence (photos, council reports) also exists of flood events in the Tokomairiro catchment during the 1960’s and 70’s and earlier (Figure 5).

2 Normal base flow at the site is less than 1 cumec.

Page 9: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 6

Figure 4. Flow record for the Tokomairiro River at West Branch Bridge, December 1981 to November 2011. The river can rise reasonably quickly at the west branch site during flood events, with a rate of rise of up to 30 cumecs per hour over a three to four hour period observed. Although currently un-gauged, the north branch of the Tokomairiro River has similar physical characteristics to the west branch site, including relief, catchment area and topography (Figure 3). Other major tributaries also contribute to flow in the north branch as it crosses the plain, including Salmond’s and Gorge Creeks (Figure 2). Figure 5 shows the north branch just upstream of its confluence with the west branch during a flood event in June 1972.

Page 10: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 7

Figure 5. The north branch of the Tokomairiro River just upstream of its confluence with the west branch in June 1972. The view is from Milton towards the southwest along SH1. This photo was not necessarily taken at the peak of the flood event. In addition to these main tributaries, there are several natural overland flow paths or ‘floodway corridors’ which drain surface runoff during flood events (Figure 6 and Figure 7). These flow paths can take numerous forms, ranging from reasonably incised channels (1-2m lower than the surrounding land) through to relatively wide and shallow features, which can be difficult to identify during dry ‘non-flood’ conditions. Although flood flows in these drainage corridors are generally smaller than those in the main river and the larger tributaries, they are still critical drainage features. They form a network which is necessary to allow flood water to drain quickly and efficiently from the eastern hill catchments and the floodplain into the larger tributaries of the Tokomairiro River. As a result, there is a level of flood hazard associated with these features, although this can easily be overlooked or underestimated as many do not normally carry water, or are not obvious drainage features. The physical geography of Milton means it is exposed to flooding from a number of sources. The town is located in the lower reaches of the Tokomairiro basin, with the upstream catchment consisting of extensive hill country and a smaller floodplain component (Figure 1). The main tributaries of the Tokomairiro River and a number of overland flow paths converge at this point, before draining to the Pacific Ocean through a narrow gorge. Natural drainage through the gorge is restricted as the river lies close to sea level through this reach, and is tidally influenced for approximately 14km upstream of Toko Mouth. Although Milton itself is elevated some 10-20m above mean sea-level, much of the town sits at a relatively low level compared to the network of tributaries which converge in this area. The southwestern end of the town is particularly vulnerable to flooding - there are two residential areas which sit in bowl-shaped depressions which are natural collection points for floodwater and surface runoff (Figure 10). Water can pond in these areas for a day or more after a flood, due to limited drainage capacity. Physical works (floodbank and pump station) constructed by the CDC to help mitigate this flood hazard are described in Section 6.2.

Page 11: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 8

Figure 6. Rural floodway corridor near Back Road draining surface runoff during a rainfall event in February 2012.

Figure 7. Aerial view showing a network of overland flow paths to the east of Milton, following a flood event in August 1974. The Tokomairiro River can be seen to the left of the image.

3.4 Community setting

Milton plays an important role in the wider community, at a local, district, and regional level. It is a service centre and focal point for the surrounding rural community. Some key links in the lower South Island transport network also cross the Tokomairiro Plain, including State Highway’s 1 and 8 and the main trunk railway line.

Page 12: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 9

The Otago Corrections Facility is also situated near Milton, and accommodates up to 335 prisoners and employs 200 staff. Although the town’s population has gradually fallen in recent decades3, there has been some expansion in the local farming industry, due to a number of dairy conversions. Commercial development is also occurring (and is expected to continue) on the Tokomairiro Plain to the north of Milton. Residential and commercial development has occurred within areas which are naturally prone to flooding from the Tokomairiro River and from surface runoff draining the hill catchments to the east. Milton has been affected by flooding on a number of occasions since it was first settled (Soil Conservation and Rivers Control Council, 1957). More recently, extensive flooding of Milton and the surrounding area occurred in April 2006, July 2007 and May 2010. At least 80 residential properties and a number of commercial premises in Milton and Helensbrook were badly affected by flooding in July 2007, with water above the floor level of approximately 20 houses. As well as the tangible impacts of floods, such as inundation and damage to property, flooding can also have a range of indirect effects on the wider community. These include interruptions to the transport network (including local roads, State Highways, and the South Island Main Trunk Line); closure of community services such as schools, workplaces, and health services; and restricted access to the town centre. 4 Legislative context

The manner and degree to which the flood risk of the Tokomairiro Plain can be managed by the community, CDC and ORC is influenced by the obligations, powers, and restrictions set out in various statutes. The Resource Management Act (RMA) takes an effects-based approach to resource management, including the management of flood risk. Further, minimum standards of flood protection for communities are not prescribed in law. The building code (Building Regulations 1992) states a minimum standard (50 year return period) for inundation of dwellings, but other factors, such as the consequences of “superdesign”, determine the appropriate standard in any particular situation. Therefore, the Building Act alone cannot be relied upon to achieve good flood risk management outcomes4. The legislation provides for a high degree of community participation, which helps shape the form the flood risk reduction takes. This is supported by CDC and ORC’s obligation to make relevant information available to the community to enable informed decision-making. This allows a high degree of community input to the management of flood risk at planning and implementation stages. No legislation confers the exclusive power or right for managing flood risk, on ORC or CDC, whether through works or services. Individuals are empowered to initiate their own measures provided they operate within the law. They are also allowed to develop and promote proposals for flood protection works, to apply for and hold the necessary resource consents, and to privately fund works and services should they wish to do so. The legislation relating to the management of flood risk gives ORC and CDC various powers and responsibilities at strategic and operational levels. Both councils can achieve their respective statutory functions through a variety of complementary methods, including regulation, education and awareness, and works and services. The legislation provides for the avoidance of new or additional risks as well as reduction of existing risks. There are however, constraints on what can practically be achieved through consideration of environmental effects and funding mechanisms. The law provides for a range of methods which both councils and the community can use to manage flood risk. These do not just relate to physical works, but also to planning, information, and emergency

3 From 2,088 in 1991 to 1,887 to 2006 (NZ Census data). 4 Flood Risk Management, A Position Statement from Local Government, 27 February 2007, Local Government New Zealand, 9p.

Page 13: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 10

preparedness and response. These can only be implemented after taking environmental effects into account (under the RMA) and funding considerations (under the Local Government Act). The latter includes consideration of the distribution of benefits between the community as a whole, any identifiable part of the community, and individuals. This ‘legislative context’ within which the strategy is defined and operated is outlined as follows:

The duty of both CDC and ORC to gather information, including information on natural hazards (RMA), make such information publicly available and provide information upon request, including information on natural hazards in Land Information Memoranda (Local Government Official Information and Meetings Act).The ORC flood manager also plays an important role during flood events, disseminating information to the public and the media, Civil Defence staff, and CDC assets managers.

The obligations of CDC as a territorial authority regarding land use planning and the role it plays in influencing and guiding community development through District Plans (RMA). The Act requires that everyone exercising functions and powers under the Act will have particular regard to the effects of climate change amongst other things.

The matters to be considered by CDC when making decisions on planning for land use and

proposals to subdivide land (RMA) and altering and constructing buildings (Building Act) which influence community exposure to natural hazards. The RMA places restrictions on use and subdivision of land.

Controls on activities, including structural measures that affect flooding risk, and the

requirement to consider effects on the environment (RMA). This applies irrespective of whether such measures are undertaken by CDC, ORC, or the community. The RMA places restrictions on certain uses of beds of lakes and rivers.

The joint responsibilities and obligations of CDC and ORC regarding planning, preparing and responding to natural hazard events individually, together, and with other agencies through the Civil Defence Emergency Management Act (CDEM Act). These matters are set out in detail in the Otago Civil Defence and Emergency Group Plan 2012-2015, which puts some emphasis on risk reduction through lifelines and land use planning.

The obligations of CDC as a lifeline utility provider (CDEM Act) arising from its ownership and

operation of community water supply and sewage collection and treatment systems. This is additional to CDC’s other emergency preparedness and response responsibilities listed above.

The obligations of lifeline utility operators, in addition to CDC, regarding emergency

preparedness, response and recovery planning (CDEM Act).

The powers of the ORC to undertake works and services where appropriate to manage flooding risk (Soil Conservation and Rivers Control Act). This is a policy matter for the ORC to decide in consultation with the community and having regard to environmental and funding considerations.

The controls under the Otago Flood Protection Management Bylaw 2008 which prevent any

person interfering with flood protection and control works that have been constructed by or for ORC.

The obligations on both councils to consult with their communities over projects, budgets, and

funding under the Local Government Act 2002.

Page 14: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 11

5 Principles

The Milton 2060 Strategy is intended to provide a framework through which the CDC, the ORC, and the community will work to actively manage flood risk in Milton and the surrounding floodplain area. The framework draws extensively from New Zealand Standard 9401:2008 Managing Flood Risk, and centres on the following principles: PRINCIPLE 1: ENSURE SAFETY

Flood risk management will ensure the safety of people, and the effective operation of community infrastructure and public and private assets, both now and into the foreseeable future.

Community concerns over flood risk (including the residual risk5 associated with ‘super design’ events) will be addressed.

The management or mitigation of flooding will not exacerbate or negatively impact the wider

community. Understanding the underlying natural systems and processes that operate in the Tokomairiro catchment is crucial to managing flood risk and ensuring community safety. PRINCIPLE 2: PLAN AHEAD Manage for uncertainty. An adaptive approach to flood risk management will allow for changes in flood hazard due to natural climate variability and improvements in the understanding of flood hazard. Consider the impacts of climate change. Recognise that the effects of changes in climate and sea level may not be felt until late within the current planning horizon. Ensure that future generations do not have to cope with the results of poor planning decisions made today. Adopt a responsible approach when considering new development on potentially flood-prone land and when mitigating the flood risk of existing development. Use resources wisely to ensure that the location and form of community assets and essential infrastructure will result in a more resilient community. Ease transitions. The risk associated with flooding will reduce over time by taking a broad-scale, adaptive approach over the longer term. The ability to respond to changes in the nature and extent of risk, and provide the level of safety desired by the community is essential. PRINCIPLE 3: SUSTAINABLE LAND USE Decisions enabling the sustainable and appropriate use of land will be informed by:

Community awareness and acknowledgement of both the benefits and the risks (including the residual risk associated with ‘super design’ events) that exist for development already located in flood hazard areas.

Consideration of all available options to manage flood risk, including structural and non-structural options.

Land use planning controls. Decisions on land use also need to be compatible with the other principles outlined above.

5 See the Glossary for definitions of these and other key terms.

Page 15: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 12

6 Strategic elements

These are areas where the CDC, the ORC, and the community can achieve positive outcomes for Milton and the surrounding area. They are derived from the principles outlined in Section 5 and aim to:

ensure that flood risk does not increase beyond current levels, actively reduce flood risk where there is opportunity to do so, improve resilience through risk reduction, readiness, response, and recovery from flooding.

The strategy’s strategic elements are:

1. Understanding natural river and catchment processes and the potential impacts of climate variability / climate change on those processes.

2. Identifying and managing risks posed to and by community infrastructure and services (roading, water supply reticulation, wastewater collection and disposal, stormwater collection and disposal) and other utilities (telecommunications, electricity), with links to Lifelines Planning.

3. Flood-sensitive urban design and the incorporation of flood awareness and risk mitigation into all relevant council activities such as community plans and bylaws, building consents and infrastructure planning, renewal and maintenance.

4. Robust community response systems; informed by reliable flood warning and prediction tools, increased public awareness of flood hazard, and information sharing through ‘linked-up’ communication networks.

5. Commissioning of appropriate and affordable capital and maintenance works where the residual flood risk is significant.

6. Defining and articulating roles and responsibilities amongst individuals, communities, and the two councils.

7. Assisting the community to develop innovative and appropriate methods of managing flood risk by:

outlining strategic objectives, education and awareness, providing clear and practical base data and information, and enhancing personal accountability and capability.

Progressing some of these elements may influence the effectiveness of other elements. 6 A coordinated approach is therefore required to ensure that progress in one area does not inadvertently offset or invalidate improvements that have been achieved elsewhere. Sections 6.1 to 6.5 describe work which has been undertaken, and existing knowledge about the strategic elements outlined above. This information has then been incorporated into a list of proposed activities for controlling or managing flood risk. These activities have been derived using the principles and elements outlined above. To enable the community to easily identify how and where these activities will be implemented, the activities which are relevant to defined areas with different flood hazard characteristics is provided in Section 6 and 7.

6.1 Understanding natural river and catchment processes

A good understanding of natural river and catchment processes is required to ensure that appropriate and sustainable flood risk management measures can be put in place. To this end, flows associated with a high magnitude flood event (approximately equivalent to a 1:100 year flood) in the north and west branches of the Tokomairiro River and Salmond’s Creek have been modelled. These estimates have been verified with observations and measurements wherever possible. The maximum modelled

6 Note that the effect on other elements may be beneficial, detrimental or neutral.

Page 16: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 13

flow was 427 cumecs, below the confluence of the west and north branches. For comparison, this is similar to flows in the Clutha River at Balclutha during typical low-flow conditions. This information, combined with topographical data has been used to determine the likely characteristics of flood events in Milton and the surrounding area. These include the depth and extent of inundation, the speed (velocity) of water at the peak of the flood, and the length of time flooding may persist. For smaller tributaries of the Tokomairiro River and major overland flow paths, the estimated bank full extent (i.e. the point where flood flows begin to overtop the bank and spread across the floodplain) was determined using topographical information. The exception was Gorge Creek, where historical flood information was available to map the flood extent. Land within the Milton 2060 study area which is susceptible to flooding is mapped in Appendix 1. These maps show in general terms the characteristics of flood hazard within the study area.

6.2 Understanding infrastructural flood risk

To enable timely, focused flood response and recovery, both councils recognise the need to understand the flood risk posed not only by the natural, but by the structural or built environment. Accordingly, CDC and ORC have gathered information and undertaken remedial works in the following areas: Identifying and remedying restrictions within the stormwater network CDC has undertaken work to maintain and upgrade the stormwater network in Milton in recent years. This has included CCTV examinations of stormwater pipes, as well as cleaning and enlargement of pipes. This work will continue as and where required as part of the normal asset maintenance programme. Even with ongoing scheduled maintenance and improvements, the stormwater network will still occasionally be overwhelmed by large ‘super-design’ events. Overland flowpaths complement the stormwater network in those situations and are therefore important to safe and effective stormwater management. Historic drainage Milton has a historic network of stone and brick drains which formerly provided stormwater and sewerage drainage for the town. The CDC is aware of these and has some records of them, but they have largely fallen into disrepair and are not maintained. They are not part of the current stormwater network, so any drainage they do provide would be in addition to the newer works that the CDC has designed and maintains. They are unlikely to provide any significant drainage during floods, as the outlets are generally at a low level and so are drowned during flood events. However, any interference with this network (e.g, by blocking or redirecting the flow) may reduce its effectiveness, and exacerbate flooding in some areas. Mill Street floodbank and pump station The CDC constructed a 700m long floodbank along the true left (north) bank of the Tokomairiro River below SH1 in 2009-10. The floodbank works in conjunction with the Mill Street Pump Station which was completed in 2010. The Pump Station has a rated capacity of 1200 litres of water per minute at its peak. This is equivalent to the peak flow generated in a 10 year return period, 30 minute long rainstorm. These assets enable water to be pumped from low-lying areas, whilst preventing the river from flowing back into the drainage area, even when the river is high. The floodbank is not intended to provide direct flood protection to Milton. Roading and railway infrastructure impacts and vulnerabilities Road and railway infrastructure can reduce the ability of floodwater to drain rapidly along natural overland flow paths. For example, an ORC investigation found that elevating SH1 by about 25cm above the surrounding land at Helensbrook has been sufficient to impede the natural drainage of flood

Page 17: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 14

water along a swale towards the Tokomairiro River. As a result, residential properties along SH1 can be affected by flood water during heavy rainfall events. Designations within the District Plan provide for the use and development of this infrastructure. These designations do not have conditions relating to diverting, or restricting the conveyance of floodwater. However, there are provisions within the Regional Plan: Water which do relate to the diversion of floodwater. It is likely that the effect of the infrastructure does not comply with the Regional Plan permitted activity provisions. It is important that ongoing maintenance, improvements, or changes to roading and railway infrastructure on the Tokomairiro Plain does not unduly restrict or alter the conveyance of floodwater, or result in additional flood risk elsewhere. This issue will be addressed through both councils’ resource consent processes and a greater awareness of the potential effects of these assets by those responsible for managing them. Roads also act as corridors for safe access and egress, especially in ponding areas. The criticality of particular roads will be considered when deciding priorities and timing for road improvements and maintenance within Milton. To help inform these processes, the depth of flooding which could be expected to occur on flood-prone sections of the state highway network and local roads has been mapped, and is included in Appendix 2.

6.3 Flood sensitive urban design

Parts of Milton have been developed on land that is naturally prone to flooding from the Tokomairiro River and from surface runoff draining the hill catchments to the east. As such, flooding is inevitable in some areas, and buildings must have the durability to withstand inundation by contaminated water for extended periods. Some residential and commercial building owners in Milton have already taken steps to make their buildings able to withstand inundation. The challenge however, is to make such measures widespread. This task can be hindered by the cost of flood-proofing a building relative to its value, and the fact that flooding can occur relatively infrequently, and therefore the exposure to flood risk may be seen to be relatively small. Where property owners intend to retain ownership of a building for some time, or when inundation occurs several times over a short period,7 then property owners may be more willing to consider flood sensitive design as a worthwhile investment in their property. Raising the floor of a building above the design flood level is one method which has been used in Milton to avoid flood damage to the building and its fittings (Figure 8). Although this process may have tangible benefits for property owners and residents, there are a number of potential conflicts and issues which should also be considered. These include building accessibility issues, the ability to gain access to and clean the sub-floor space following a flood (particularly where contamination of floodwater has occurred), and any negative effect of inundation and subsequent drying on the piles, beams, and joists used to suspend the floor. CDC intends developing a set of guidelines to disseminate local knowledge gained from past floods with regards to durable building design. This will include initiatives such as movable storage for commercial premises and the use of flood resilient construction techniques. Guidance on appropriate methods for raising the floor level of existing or new buildings above the flood level will also be included. The guidelines will be made available for community comment and input to create discussion and raise awareness of flood risk management through good design.

7 as occurred for many properties during flood events in 2006, 2007 and 2010.

Page 18: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 15

Figure 8. Residential building on raised foundations.

6.4 Robust community response systems

Greater awareness of flood hazard, easily accessible information, and timely and relevant flood warnings are useful tools for improving the community’s ability to respond, both during and before to a flood event. A well prepared community response will help to reduce the economic and social impact of flooding. Relevant initiatives which have been recently undertaken, or which are proposed include: Improved flood warning and modelling processes ORC operates two permanent hydrological sites in the Tokomairiro catchment. The flow site on the west branch of the Tokomairiro at SH8 and the rainfall site at Table Hill Road provide ‘real-time’ information during flood events. The Table Hill Road rain gauge was installed in 2011 to provide additional information and warning during flood events, and to provide an independent source of local information. ORC also operates a sea level gauge at Green Island, located offshore from Dunedin, and tidal information from this site can be used during flood events to estimate the timing of flood peaks in the Tokomairiro catchment.8 The hydrological information from these and other nearby sites is used by the ORC flood manager to provide flood warnings to CDC Civil Defence staff. It can also be accessed by the public via ORC’s Water Info website and phone service.9 Even with these sources of information, the timing and magnitude of flood events in the Milton area can be difficult to predict, as several tributaries with different characteristics converge near the town, rainfall totals can vary significantly across the catchment (Figure 3), and runoff can drain rapidly from upper catchment areas. ORC does not currently have flood models which predict the timing or magnitude of water levels or flows at Milton. Therefore, if community response systems are to be sufficiently robust, they need to be informed not only by the ORC’s flood warning network, but also by additional sources of relevant information including the media, the Civil Defence network, and local observations. In addition, ORC will continue to review its monitoring and prediction systems to ensure their robustness.

8 As much of the river channel in the lower reaches of the Tokomairiro River (between Coal Gully Road Bridge and Toko Mouth) is at or below mean sea level, conditions at the mouth (including tides and storm surge) can limit the ability of flood waters to drain. 9 This service can be accessed online at www.orc.govt.nz/WaterInfo or by phoning 0800 426 463.

Page 19: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 16

Review of ORC flood procedures manual The ORC flood procedures manual specifies the warning, communication, and response procedures the council follows during a flood event. It is reviewed and updated annually. As part of the Milton 2060 Strategy, a specific review of improvements which could be implemented in the Tokomairiro catchment is to be undertaken in 2012. The focus of this review will be assuring and improving inter-council communication and flood warning systems where necessary. Flood communication workshops To enable more effective dissemination of meaningful information prior to, during and after a flood event, a flood communication workshop made up of the flood management teams from both councils is to be held in 2012 to enable more effective dissemination of information before, during, and after a flood event. The workshops will occur annually in the early summer before the flood season as a key means of achieving the strategy initiatives of improving flood warning and response systems. It will also act as a means of preparing the relevant staff, confirming communication protocols, reaffirming roles and responsibilities, raising flood awareness, and improving overall event response. Pre-flood readiness actions Modern technology and forecasting systems mean there should be at least one to two days warning before a large flood event in the catchment. As part of the response to such to an event, there are a number of actions which should be taken by CDC and ORC, individually and together, before flooding occurs to protect public safety and property, and to help communities recover. Those actions include, for example, checking that critical floodways are clear of debris and that stormwater outlets to the Tokomairiro River are functioning correctly. These actions will be set out in an operating protocol to be developed and agreed by utilities staff from both organisations. The actions will be reviewed after major flood events, and during the annual flood communication workshop described above.

6.5 Physical works

A range of mitigation works has been identified which would provide additional flood protection for the Milton urban area. The intention of these works is summarised where appropriate in Section 8, while a more detailed description is presented in Section 9. It should be noted that an element of residual risk would remain, even if these works were to be put in place.

7 Flood risk management maps

Land within the strategy study area which is known to be susceptible to flooding has been identified. The characteristics of large flood events are shown in Appendix 1 (this includes the depth of inundation, the velocity of water at the peak of the flood, and the length of time flooding may persist).

Figure 9 and Figure 10 below show defined areas which have similar flood hazard characteristics. These include: Area 1: The Tokomairiro River Floodplain.

Area 1A is the floodplain area which can be flooded by the north and west branches of the Tokomairiro River.

Area 1B is the part of the floodplain where flood flows are sufficiently fast and / or deep to cause a significant safety risk (for the purposes of this report, the term ‘floodway corridors’ has been used to describe areas with these characteristics).

Area 2: Low-lying ponding areas. These are urban areas where water ponds during prolonged heavy rainfall events.

Area 2A is to the north and west of SH1. Area 2B is to the south and east of SH1.

Page 20: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 17

Area 3: Milton urban area. Area 3A is the Milton urban area, excluding the areas which act as floodway corridors (Area

3B), and low-lying ponding areas (Areas 2A and 2B). Area 3B includes the floodway corridors which drain internal runoff and water from the

floodplain and eastern hill catchments through the Milton urban area. Area 4: Rural and semi-rural areas on the Tokomairiro Plain.

Area 4A refers to the rural / semi-rural floodplain area to the north and east of Milton (excluding the floodway corridors identified as Area 4B). 10

Area 4B includes the floodway corridors which drain water from the floodplain and eastern hill catchments.

Mechanisms for controlling or managing flood risk within each of these defined areas are discussed in Section 8.

10 A geomorphological approach has been taken to mapping the Area 4A floodplain – i.e. as a landform composed primarily of unconsolidated depositional material, derived from sediments which have been transported by fluvial processes (Department of Regional Development and Environment, 1991). As such, parts of Area 4A may not be directly inundated by adjacent waterways during flood events, but may be affected by surface runoff.

Page 21: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 18

Figure 9. Flood Risk Management Areas on the Tokomairiro Plain.

Page 22: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 19

Figure 10. Flood Risk Management Areas in the Milton urban area. The locations of possible mitigation work (as described in Section 9) are also shown.

Page 23: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 20

8 Control Mechanisms

The flood management issues encountered in each of four areas which have common flood hazard characteristics (as shown in Figure 9 and Figure 10) are shown in the tables below. Mechanisms for controlling or managing flood risk and activities which can be used to implement each of these mechanisms are also identified. These have been derived using the principles and strategic elements outlined in Sections 5 and 6. These controls would apply to new activities. Existing activities have “existing use rights” under the Resource Management Act, so are not affected. In the event that an existing activity stops for a short time, there is a 12 month period during which existing use rights continue to apply (e.g, if a house in a flood prone area burnt down, rebuilding could start within a year without needing resource consent).

Page 24: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page

21

Are

a 1

- Tok

omai

riro

Riv

er F

lood

plai

n.

A

rea

1A –

Flo

odpl

ain

area

whi

ch c

an b

e flo

oded

by

the

north

and

wes

t bra

nche

s of

the

Toko

mai

riro

Riv

er.

A

rea

1B –

Flo

odw

ay c

orrid

or w

here

wat

er d

epth

is 0

.3m

or g

reat

er, a

nd v

eloc

ity is

0.2

5m/s

or g

reat

er d

urin

g flo

od e

vent

s (i.

e. fl

ood

flow

s ar

e su

ffici

ently

fast

and

/ or

dee

p to

cau

se a

sig

nific

ant s

afet

y ris

k).

Floo

d H

azar

d C

hara

cter

istic

s Fl

ood

Man

agem

ent

Issu

es

Con

trol

Mec

hani

sms

Ass

ocia

ted

Polic

y / R

ule

/ Act

ivity

Dep

th o

f wat

er:

up to

2 m

. D

urat

ion

of

flood

ing:

24-

36

hrs.

M

ediu

m to

ver

y hi

gh v

eloc

ity.

Toko

mai

riro

Riv

er

flood

pea

ks:11

E

ast B

ranc

h, 2

10

to 2

20 c

umec

s.

Bel

ow w

est

bran

ch

conf

luen

ce, 4

30

cum

ecs.

Pea

k flo

w (d

epth

and

ve

loci

ty -

safe

ty).

Con

veya

nce

(stru

ctur

es, e

arth

wor

ks

redi

rect

or i

mpe

de

over

land

flow

and

dr

aina

ge o

f flo

od

wat

er).

Rel

ianc

e on

an

outle

t (s

ea le

vel,

cond

ition

s at

rive

r mou

th in

fluen

ce

dura

tion)

. D

isru

ptio

n of

and

da

mag

e to

regi

onal

/ lo

cal t

rans

port

links

.

Per

sona

l acc

ount

abili

ty

(rea

dine

ss, r

espo

nse)

. D

efin

ed e

scap

e pa

thw

ays.

M

anag

e ris

ks p

osed

to a

nd

by c

omm

unity

infra

stru

ctur

e an

d se

rvic

es.

Ena

ble

relo

catio

n ou

t of

haza

rdou

s ar

eas

/ re

deve

lopm

ent i

nto

safe

ar

eas.

La

nd u

se c

ontro

ls.

Indi

vidu

al re

spon

se p

lan:

A

war

enes

s of

floo

d ha

zard

. A

cces

sibl

e flo

od w

arni

ng in

form

atio

n an

d an

und

erst

andi

ng o

f its

re

leva

nce

to in

divi

dual

circ

umst

ance

s.

Kno

wn

evac

uatio

n ro

ute,

des

tinat

ion

(and

alte

rnat

ives

). P

repa

red

for r

oad

clos

ures

, dis

rupt

ion

to s

ervi

ces

/ util

ities

. D

istri

ct P

lan

prot

ectio

n of

def

ined

esc

ape

path

way

s to

con

trol a

ctiv

ities

w

hich

may

rest

rict s

afe

acce

ss o

r egr

ess

durin

g flo

ods.

Par

ticul

ar ro

ads

to

be m

anag

ed b

y ro

adin

g au

thor

ity a

s id

entif

ied

esca

pe a

nd a

cces

s ro

utes

13.

Floo

d pr

oofin

g of

ser

vice

s an

d ut

ilitie

s. E

nsur

e th

at m

odifi

catio

ns to

ass

ets

and

infra

stru

ctur

e (in

clud

ing

road

and

rail

trans

port

links

, flo

odba

nks

and

drai

ns) d

o no

t exa

cerb

ate

flood

haz

ard

else

whe

re, a

nd a

im to

redu

ce fl

ood

haza

rd w

here

pos

sibl

e.

Dis

trict

Pla

n zo

ning

of a

ltern

ativ

e ar

eas

with

min

imal

floo

d ris

k. R

equi

re

cons

ent a

pplic

atio

ns to

con

side

r all

avai

labl

e op

tions

to re

duce

exp

osur

e to

flo

odin

g. In

clud

e co

nsid

erat

ion

is g

iven

to n

on-s

truct

ural

met

hods

suc

h as

av

oidi

ng fl

ood-

pron

e ar

eas,

and

rem

ovin

g pe

ople

and

ass

ets

from

risk

ar

eas.

D

istri

ct P

lan

give

s co

ntro

l ove

r ide

ntifi

ed a

ctiv

ities

to a

void

any

net

incr

ease

in

risk

14 a

nd to

ens

ure

area

s w

ith u

nacc

epta

ble

flood

haz

ard

are

avoi

ded:

(1

) D

istri

ct P

lan

zoni

ng o

f Are

a 1A

to in

clud

e:

the

cla

ssifi

catio

n of

dw

ellin

gs/a

ctiv

ities

that

acc

omm

odat

e pe

ople

as

disc

retio

nary

,15

the

cla

ssifi

catio

n of

oth

er b

uild

ings

as

rest

ricte

d di

scre

tiona

ry o

r

11 a

s m

odel

led

for a

hig

h m

agni

tude

eve

nt, a

ppro

xim

atel

y eq

uiva

lent

to a

1:1

00 y

ear f

lood

. 13

See

App

endi

x 2.

14

e.g

. thr

ough

mor

e in

tens

ive

deve

lopm

ent o

r sig

nific

antly

incr

easi

ng th

e nu

mbe

r of r

esid

ents

15

See

def

initi

ons

of th

is a

nd o

ther

term

s in

the

Glo

ssar

y

Page 25: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Pag

e 22

Ens

ure

adeq

uate

co

nvey

ance

and

effi

cien

t dr

aina

ge.

Pre

vent

alte

ratio

n of

ove

rland

flo

w p

aths

.12

Pre

vent

the

crea

tion

of n

ew

flood

haz

ard,

or t

he

aggr

avat

ion

of e

xist

ing

flood

ha

zard

.

cont

rolle

d,

allo

win

g ot

her a

ctiv

ities

suc

h as

fenc

es a

nd e

arth

wor

ks a

s pe

rmitt

ed

activ

ities

, sub

ject

to c

erta

in s

tand

ards

and

con

ditio

ns.

(2)

Dis

trict

Pla

n zo

ning

of A

rea

1B to

incl

ude:

t

he c

lass

ifica

tion

of d

wel

lings

/act

iviti

es th

at a

ccom

mod

ate

peop

le a

s no

n-co

mpl

ying

, t

he c

lass

ifica

tion

of fa

rm a

nd o

ther

bui

ldin

gs, a

nd s

tora

ge o

f mat

eria

ls

as d

iscr

etio

nary

, a

dditi

onal

con

trols

ove

r act

iviti

es s

uch

as fe

nces

and

ear

thw

orks

, a

revi

ew o

f the

app

ropr

iate

ness

of i

ndus

trial

zon

ing.

In

clus

ion

of th

ese

mat

ters

in th

e co

ntro

ls u

nder

Dis

trict

Pla

n R

ules

. P

rote

ctio

n of

OR

C d

rain

age

syst

em th

roug

h R

egio

nal C

ounc

il Fl

ood

Pro

tect

ion

Byl

aw.

Mai

nten

ance

of d

rain

age

and

flood

pro

tect

ion

wor

ks b

y bo

th C

ounc

ils.

12 e

xclu

ding

wor

ks a

ssoc

iate

d w

ith a

ny p

ublic

floo

d pr

otec

tion

sche

me.

Page 26: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page

23

Are

a 2:

Low

-lyin

g po

ndin

g ar

eas.

Urb

an a

reas

whe

re w

ater

pon

ds d

urin

g pr

olon

ged

heav

y ra

infa

ll ev

ents

.16

A

rea

2A is

to th

e no

rth a

nd w

est o

f SH

1.

Floo

d H

azar

d C

hara

cter

istic

s Fl

ood

Man

agem

ent

Issu

es

Con

trol

Mec

hani

sms

Ass

ocia

ted

Polic

y / R

ule

/ Act

ivity

Dep

th o

f wat

er: 0

to

1.5

m.

Dur

atio

n of

flo

odin

g: 2

4-36

hr

s.

Min

imal

vel

ocity

. P

revi

ousl

y flo

oded

, inc

ludi

ng

July

200

7.

Cur

rent

m

itiga

tion:

S

torm

wat

er

syst

em, e

leva

ted

land

to n

orth

wes

t (r

ailw

ay

emba

nkm

ent)

and

sout

hwes

t.

Pon

ding

dur

atio

n an

d de

pth

of in

unda

tion.

D

rain

age

capa

city

(r

elia

nce

on a

n ou

tlet).

C

onta

min

atio

n of

flo

odw

ater

.

Per

sona

l acc

ount

abili

ty

(rea

dine

ss, r

espo

nse)

. D

efin

ed e

scap

e pa

thw

ays.

M

anag

e ris

ks p

osed

to a

nd

by c

omm

unity

infra

stru

ctur

e an

d se

rvic

es.

Ena

ble

relo

catio

n ou

t of

haza

rdou

s ar

eas

/ re

deve

lopm

ent i

nto

safe

ar

eas.

La

nd u

se c

ontro

ls.

Indi

vidu

al re

spon

se p

lan:

A

war

enes

s of

floo

d ha

zard

. A

cces

sibl

e flo

od w

arni

ng in

form

atio

n an

d an

und

erst

andi

ng o

f its

re

leva

nce

to in

divi

dual

circ

umst

ance

s.

Kno

wn

evac

uatio

n ro

ute,

des

tinat

ion

(and

alte

rnat

ives

). P

repa

red

for r

oad

clos

ures

, dis

rupt

ion

to s

ervi

ces

/ util

ities

. D

istri

ct P

lan

prot

ectio

n of

def

ined

esc

ape

path

way

s to

con

trol a

ctiv

ities

w

hich

may

rest

rict s

afe

acce

ss o

r egr

ess

durin

g flo

ods.

Par

ticul

ar ro

ads

to

be m

anag

ed b

y ro

adin

g au

thor

ity a

s id

entif

ied

esca

pe a

nd a

cces

s ro

utes

. S

ealin

g of

was

tew

ater

col

lect

ion

syst

em –

Red

uce

inflo

w a

nd in

filtra

tion.

Fl

ood

proo

fing

of o

ther

ser

vice

s an

d ut

ilitie

s.

Impr

oved

cap

acity

to d

rain

floo

dwat

er fr

om p

ondi

ng a

rea.

E

nsur

e th

at m

odifi

catio

ns to

ass

ets

and

infra

stru

ctur

e (in

clud

ing

road

and

ra

il tra

nspo

rt lin

ks, f

lood

bank

s an

d dr

ains

) do

not e

xace

rbat

e flo

od h

azar

d el

sew

here

, and

aim

to re

duce

floo

d ha

zard

whe

re p

ossi

ble.

D

istri

ct P

lan

zoni

ng o

f alte

rnat

ive

area

s w

ith m

inim

al fl

ood

risk.

Req

uire

co

nsen

t app

licat

ions

to c

onsi

der a

ll av

aila

ble

optio

ns to

redu

ce e

xpos

ure

to

flood

ing.

Ens

ure

that

con

side

ratio

n is

giv

en to

non

-stru

ctur

al m

etho

ds s

uch

as a

void

ing

flood

-pro

ne a

reas

, and

rem

ovin

g pe

ople

and

ass

ets

from

risk

ar

eas.

D

istri

ct P

lan

give

s co

ntro

l ove

r ide

ntifi

ed a

ctiv

ities

to a

void

any

net

incr

ease

in

risk

17 a

nd to

ens

ure

area

s w

ith u

nacc

epta

ble

flood

haz

ard

are

avoi

ded.

(1

) B

uild

ing

alte

ratio

ns a

nd fo

otpr

int e

xten

sion

s/an

cilla

ry b

uild

ings

in A

rea

2A to

bec

ome

cont

rolle

d ac

tiviti

es u

nder

the

Dis

trict

Pla

n to

ens

ure:

A m

inim

um fl

oor h

eigh

t of 1

3m a

bove

mea

n se

a le

vel.18

Sui

tabl

e co

nstru

ctio

n m

etho

ds a

nd fl

ood

proo

f util

ity c

onne

ctio

ns.

S

afe

egre

ss d

urin

g flo

od e

vent

s.

16 S

ee S

ectio

n 3.

3 fo

r add

ition

al e

xpla

natio

n of

the

flood

haz

ard

in th

ese

area

s.

17 e

.g. t

hrou

gh m

ore

inte

nsiv

e de

velo

pmen

t or s

igni

fican

tly in

crea

sing

the

num

ber o

f res

iden

ts

18 L

and

in th

is a

rea

is g

ener

ally

bet

wee

n 11

and

13m

abo

ve m

ean

sea

leve

l.

Page 27: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Pag

e 24

Add

ition

al m

itiga

tion.

(2)

New

dw

ellin

gs, c

omm

erci

al re

side

ntia

l and

oth

er a

ctiv

ities

that

ac

com

mod

ate

peop

le to

bec

ome

disc

retio

nary

und

er th

e D

istri

ct P

lan.

In

vest

igat

e ef

fect

s of

con

stru

ctin

g a

flood

ban

k al

ong

Tow

er R

oad

(see

S

ectio

n 9)

.

Page 28: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page

25

Are

a 2:

Low

-lyin

g po

ndin

g ar

eas

(con

tinue

d). U

rban

are

as w

here

wat

er p

onds

dur

ing

prol

onge

d he

avy

rain

fall

even

ts.

A

rea

2B is

to th

e so

uth

and

east

of S

H1.

Floo

d H

azar

d C

hara

cter

istic

s Fl

ood

Man

agem

ent

Issu

es

Con

trol

Mec

hani

sms

Ass

ocia

ted

Polic

y / R

ule

/ Act

ivity

Sce

nario

1 (P

ump

stat

ion

and

flood

bank

rem

ain

oper

atio

nal):

D

epth

: 0 to

0.2

m.

Dur

atio

n: u

p to

24

hour

s

Min

imal

vel

ocity

. S

cena

rio 2

(Pum

p st

atio

n fa

ilure

): D

epth

: 0 to

0.7

m

Dur

atio

n: 2

4-36

ho

urs

M

inim

al v

eloc

ity.

Sce

nario

3

(Flo

odba

nk

failu

re):

Dep

th: 0

to 1

.5m

. D

urat

ion:

24-

36

hour

s

Mod

erat

e to

hig

h ve

loci

ty.

Pre

viou

sly

flood

ed, i

nclu

ding

Ju

ly 2

007.

C

urre

nt

miti

gatio

n:

Dry

den

Stre

et

flood

div

ersi

on

Pon

ding

dur

atio

n an

d de

pth

of in

unda

tion.

D

rain

age

capa

city

(r

elia

nce

on a

n ou

tlet).

C

onta

min

atio

n of

flo

odw

ater

. R

elia

nce

on c

ritic

al

flood

pro

tect

ion

asse

ts:

Flo

odba

nk

over

topp

ing

(add

ition

al p

ondi

ng).

Flo

odba

nk b

reac

h /

failu

re (r

apid

in

unda

tion

of p

ondi

ng

area

- ve

loci

ty a

nd

dept

h).

Pum

p fa

ilure

(a

dditi

onal

pon

ding

, ex

tend

ed d

urat

ion)

.

Per

sona

l acc

ount

abili

ty

(rea

dine

ss, r

espo

nse)

. D

efin

ed e

scap

e pa

thw

ays.

M

anag

e ris

ks p

osed

to a

nd

by c

omm

unity

infra

stru

ctur

e an

d se

rvic

es.

Ena

ble

relo

catio

n ou

t of

haza

rdou

s ar

eas

/ re

deve

lopm

ent i

nto

safe

ar

eas.

La

nd u

se c

ontro

ls.

Indi

vidu

al re

spon

se p

lan:

A

war

enes

s of

floo

d ha

zard

. A

cces

sibl

e flo

od w

arni

ng in

form

atio

n an

d an

und

erst

andi

ng o

f its

re

leva

nce

to in

divi

dual

circ

umst

ance

s.

Kno

wn

evac

uatio

n ro

ute,

des

tinat

ion

(and

alte

rnat

ives

). P

repa

red

for r

oad

clos

ures

, dis

rupt

ion

to s

ervi

ces

/ util

ities

. D

istri

ct P

lan

prot

ectio

n of

def

ined

esc

ape

path

way

s to

con

trol a

ctiv

ities

w

hich

may

rest

rict s

afe

acce

ss o

r egr

ess

durin

g flo

ods.

Par

ticul

ar ro

ads

to

be m

anag

ed b

y ro

adin

g au

thor

ity a

s id

entif

ied

esca

pe a

nd a

cces

s ro

utes

. S

ealin

g of

was

tew

ater

col

lect

ion

syst

em –

Red

uce

inflo

w a

nd In

filtra

tion.

Fl

ood

proo

fing

of o

ther

ser

vice

s an

d ut

ilitie

s.

Ens

ure

that

mod

ifica

tions

to a

sset

s an

d in

frast

ruct

ure

(incl

udin

g ro

ad a

nd

rail

trans

port

links

, flo

odba

nks

and

drai

ns) d

o no

t exa

cerb

ate

flood

haz

ard

else

whe

re, a

nd a

im to

redu

ce fl

ood

haza

rd w

here

pos

sibl

e.

Dis

trict

Pla

n zo

ning

of a

ltern

ativ

e ar

eas

with

min

imal

floo

d ris

k. R

equi

re

cons

ent a

pplic

atio

ns to

con

side

r all

avai

labl

e op

tions

to re

duce

exp

osur

e to

flo

odin

g. E

nsur

e th

at c

onsi

dera

tion

is g

iven

to n

on-s

truct

ural

met

hods

suc

h as

avo

idin

g flo

od-p

rone

are

as, a

nd re

mov

ing

peop

le a

nd a

sset

s fro

m ri

sk

area

s.

Dis

trict

Pla

n gi

ves

cont

rol o

ver i

dent

ified

act

iviti

es to

avo

id a

ny n

et in

crea

se

in ri

sk19

and

to e

nsur

e ar

eas

with

una

ccep

tabl

e flo

od h

azar

d ar

e av

oide

d.

(1)

Bui

ldin

g al

tera

tions

and

foot

prin

t ext

ensi

ons/

anci

llary

bui

ldin

gs in

Are

a 2B

to b

ecom

e co

ntro

lled

activ

ities

und

er th

e D

istri

ct P

lan

to e

nsur

e:

A

min

imum

floo

r hei

ght o

f 12m

abo

ve m

ean

sea

leve

l. 20

S

uita

ble

cons

truct

ion

met

hods

& fl

ood

proo

f util

ity c

onne

ctio

ns.

S

afe

egre

ss d

urin

g flo

od e

vent

s.

19 e

.g. t

hrou

gh m

ore

inte

nsiv

e de

velo

pmen

t or s

igni

fican

tly in

crea

sing

the

num

ber o

f res

iden

ts

20 L

and

in th

is a

rea

is g

ener

ally

bet

wee

n 9.

5 an

d 12

m a

bove

mea

n se

a le

vel.

Page 29: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Pag

e 26

and

Toko

mai

riro

Riv

er fl

oodb

ank

and

pum

p st

atio

n.

Ens

ure

the

effe

ctiv

enes

s of

ex

istin

g flo

od p

rote

ctio

n.

(2)

New

dw

ellin

gs, c

omm

erci

al re

side

ntia

l and

oth

er a

ctiv

ities

that

ac

com

mod

ate

peop

le to

bec

ome

disc

retio

nary

und

er th

e D

istri

ct P

lan.

E

nsur

e co

ntin

ued

oper

atio

n of

exi

stin

g flo

od p

rote

ctio

n:

B

uild

redu

ndan

cy in

to M

ill S

treet

Pum

p S

tatio

n (s

pare

s, p

reve

ntat

ive

and

plan

ned

mai

nten

ance

, bac

kup

pow

er s

uppl

y, s

ite a

cces

s du

ring

flood

ing)

.

Dis

trict

Pla

n de

sign

atio

n to

allo

w fo

r ope

ratio

n, u

pgra

de, m

aint

enan

ce

and

acce

ss, a

nd to

con

trol a

ctiv

ities

that

may

neg

ativ

ely

affe

ct th

e flo

odba

nk.

Page 30: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page

27

Are

a 3:

Milt

on u

rban

are

a

Are

a 3A

– T

he M

ilton

urb

an a

rea,

exc

ludi

ng la

nd w

hich

act

s as

a fl

oodw

ay c

orrid

or (A

rea

3B),

or lo

w-ly

ing

pond

ing

area

s (A

reas

2A

and

2B

).

Are

a 3B

– F

lood

way

cor

ridor

s w

hich

dra

in in

tern

al ru

noff

and

wat

er fr

om th

e flo

odpl

ain

and

east

ern

hill

catc

hmen

ts th

roug

h th

e M

ilton

urb

an a

rea.

Floo

d H

azar

d C

hara

cter

istic

s Fl

ood

Man

agem

ent

Issu

es

Con

trol

Mec

hani

sms

Ass

ocia

ted

Polic

y / R

ule

/ Act

ivity

Dep

th o

f wat

er: 0

to

0.3

m

Dur

atio

n of

flo

odin

g: 6

-18

hrs.

Low

to m

ediu

m

velo

city

. P

eak

flow

s:

0.6

to 2

cum

ecs.

C

urre

nt

miti

gatio

n:

Dry

den

Stre

et

and

Kei

nan

Ave

flo

od d

iver

sion

ch

anne

ls.

Pea

k flo

w (d

epth

and

ve

loci

ty).

Con

veya

nce

(stru

ctur

es, e

arth

wor

ks

redi

rect

or i

mpe

de

drai

nage

of f

lood

wat

er).

Dis

rupt

ion

of re

gion

al /

loca

l tra

nspo

rt lin

ks.

Link

ages

to p

ondi

ng

area

s / T

okom

airir

o R

iver

.

Per

sona

l acc

ount

abili

ty

(rea

dine

ss, r

espo

nse)

. D

efin

ed e

scap

e pa

thw

ays.

M

anag

e ris

ks p

osed

to a

nd

by c

omm

unity

infra

stru

ctur

e an

d se

rvic

es.

Land

use

con

trols

(to

appl

y w

ithin

Are

a 3B

floo

dway

co

rrid

ors)

.

Indi

vidu

al re

spon

se p

lan:

A

war

enes

s of

floo

d ha

zard

. A

cces

sibl

e flo

od w

arni

ng in

form

atio

n an

d an

und

erst

andi

ng o

f its

re

leva

nce

to in

divi

dual

circ

umst

ance

s.

Kno

wn

evac

uatio

n ro

ute,

des

tinat

ion

(and

alte

rnat

ives

). P

repa

red

for r

oad

clos

ures

, dis

rupt

ion

to s

ervi

ces

/ util

ities

. D

istri

ct P

lan

prot

ectio

n of

def

ined

esc

ape

path

way

s to

con

trol a

ctiv

ities

w

hich

may

rest

rict s

afe

acce

ss o

r egr

ess

durin

g flo

ods.

Par

ticul

ar ro

ads

to

be m

anag

ed b

y ro

adin

g au

thor

ity a

s id

entif

ied

esca

pe a

nd a

cces

s ro

utes

. Fl

ood

proo

fing

of s

ervi

ces

and

utili

ties.

Im

prov

e ca

paci

ty o

f sto

rmw

ater

net

wor

k to

cop

e w

ith fl

oodw

ater

. Ens

ure

that

mod

ifica

tions

to a

sset

s an

d in

frast

ruct

ure

(incl

udin

g ro

ad a

nd ra

il tra

nspo

rt lin

ks, f

lood

bank

s an

d dr

ains

) do

not e

xace

rbat

e flo

od h

azar

d el

sew

here

, and

aim

to re

duce

floo

d ha

zard

whe

re p

ossi

ble.

D

istri

ct P

lan

give

s co

ntro

l ove

r ide

ntifi

ed a

ctiv

ities

to a

void

any

net

incr

ease

in

floo

d ris

k.

(1)

Min

or b

uild

ing

alte

ratio

ns/fo

otpr

int e

xten

sion

s an

d an

cilla

ry b

uild

ings

ar

e a

perm

itted

act

ivity

pro

vide

d:

flo

or h

eigh

t is

suffi

cien

tly e

leva

ted

to a

void

inun

datio

n,

su

itabl

e co

nstru

ctio

n m

etho

ds &

floo

d pr

oofe

d ut

ility

con

nect

ions

are

us

ed, a

nd

an

y re

-dire

ctio

n of

floo

d flo

ws

is a

void

ed.

(2)

Dw

ellin

gs a

nd fo

otpr

int e

xten

sion

s/an

cilla

ry b

uild

ings

ove

r a c

erta

in

size

are

a c

ontr

olle

d ac

tivity

in re

gard

to:

ea

rthw

orks

(avo

id re

-dire

ctio

n of

floo

d flo

ws)

,

suita

ble

floor

hei

ght (

to a

void

inun

datio

n),

su

itabl

e co

nstru

ctio

n m

etho

ds (t

o w

ithst

and

inun

datio

n to

a d

efin

ed

dept

h an

d ve

loci

ty),

flo

od p

roof

ing

of u

tility

con

nect

ions

,

loca

tion

(avo

idin

g ar

eas

of e

xces

sive

dep

th o

r vel

ocity

, or r

e-di

rect

ion

Page 31: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Pag

e 28

Ens

ure

adeq

uate

co

nvey

ance

and

effi

cien

t dr

aina

ge.

Pre

vent

alte

ratio

n of

ove

rland

flo

w p

aths

.21

Pre

vent

the

crea

tion

of n

ew

flood

haz

ard,

or t

he

aggr

avat

ion

of e

xist

ing

flood

ha

zard

. E

nabl

e di

vers

ion

of fl

ood

wat

er to

eas

t of M

ilton

.

of fl

ows)

, and

safe

egr

ess

durin

g flo

od e

vent

s.

Incl

usio

n of

thes

e m

atte

rs in

Dis

trict

Pla

n R

ules

. P

rote

ctio

n of

OR

C d

rain

age

syst

em th

roug

h R

egio

nal C

ounc

il Fl

ood

Pro

tect

ion

Byl

aw.

Mai

nten

ance

of d

rain

age

and

flood

pro

tect

ion

wor

ks b

y bo

th C

ounc

ils.

Dis

trict

Pla

n de

sign

atio

n al

low

s fo

r ope

ratio

n, u

pgra

de, m

aint

enan

ce,

acce

ss o

f the

Dry

den

Stre

et fl

ood

dive

rsio

n.

Inve

stig

ate

effe

cts

of a

dditi

onal

div

ersi

on o

f flo

od w

ater

, inc

ludi

ng th

e ef

fect

iven

ess

of th

e K

eina

n A

ve. d

iver

sion

(see

Sec

tion

9).

21 e

xclu

ding

wor

ks a

ssoc

iate

d w

ith a

ny p

ublic

floo

d pr

otec

tion

sche

me.

Page 32: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page

29

Are

a 4:

Rur

al a

nd s

emi-r

ural

are

as o

n th

e To

kom

airir

o Pl

ain.

Are

a 4A

– T

he ru

ral /

sem

i-rur

al fl

oodp

lain

are

a to

the

north

and

eas

t of M

ilton

(exc

ludi

ng th

e flo

odw

ay c

orrid

ors

iden

tifie

d as

Are

a 4B

).

Are

a 4B

– F

lood

way

cor

ridor

s w

hich

dra

in w

ater

from

the

flood

plai

n an

d ea

ster

n hi

ll ca

tchm

ents

.22

Floo

d H

azar

d C

hara

cter

istic

s Fl

ood

Man

agem

ent

Issu

es

Con

trol

Mec

hani

sms

Ass

ocia

ted

Polic

y / R

ule

/ Act

ivity

Dep

th a

nd e

xten

t of

floo

d w

ater

va

riabl

e.

Dur

atio

n 6-

18 h

rs.

Low

to m

ediu

m

velo

city

. P

eak

flow

s in

flo

odw

ay

corr

idor

s:

0.6

to 4

cum

ecs.

R

ural

sta

ndar

d dr

aina

ge n

etw

ork,

ov

erla

nd fl

ow

path

s.

Avo

idin

g ad

ditio

nal

flood

risk

(lan

d-us

e de

cisi

ons

enab

le

sust

aina

ble

deve

lopm

ent t

o oc

cur)

. R

educ

ing

exis

ting

flood

ris

k (a

llow

for m

itiga

tion

mea

sure

s to

redu

ce

flood

risk

in M

ilton

and

th

e tra

nsiti

onal

are

a to

th

e ea

st).

Per

sona

l acc

ount

abili

ty

(rea

dine

ss, r

espo

nse)

. D

efin

ed e

scap

e pa

thw

ays.

M

anag

e ris

ks p

osed

to a

nd

by c

omm

unity

infra

stru

ctur

e an

d se

rvic

es.

Ena

ble

deve

lopm

ent o

f saf

e ar

eas.

La

nd u

se c

ontro

ls (t

o ap

ply

with

in A

rea

4B fl

oodw

ay

corr

idor

s).

Indi

vidu

al re

spon

se p

lan:

A

war

enes

s of

floo

d ha

zard

. A

cces

sibl

e flo

od w

arni

ng in

form

atio

n an

d an

und

erst

andi

ng o

f its

re

leva

nce

to in

divi

dual

circ

umst

ance

s.

Kno

wn

evac

uatio

n ro

ute,

des

tinat

ion

(and

alte

rnat

ives

). P

repa

red

for r

oad

clos

ures

, dis

rupt

ion

to s

ervi

ces

/ util

ities

. D

istri

ct P

lan

prot

ectio

n of

def

ined

esc

ape

path

way

s to

con

trol a

ctiv

ities

w

hich

may

rest

rict s

afe

acce

ss o

r egr

ess

durin

g flo

ods.

Par

ticul

ar ro

ads

to

be m

anag

ed b

y ro

adin

g au

thor

ity a

s id

entif

ied

esca

pe a

nd a

cces

s ro

utes

. Fl

ood

proo

fing

of s

ervi

ces

and

utili

ties.

E

nsur

e th

at m

odifi

catio

ns to

ass

ets

and

infra

stru

ctur

e (in

clud

ing

road

and

ra

il tra

nspo

rt lin

ks, f

lood

bank

s an

d dr

ains

) do

not e

xace

rbat

e flo

od h

azar

d el

sew

here

, and

aim

to re

duce

floo

d ha

zard

whe

re p

ossi

ble.

Dis

trict

Pla

n re

-def

ines

Tra

nsiti

onal

Res

ourc

e A

reas

to d

isco

urag

e de

velo

pmen

t in

know

n flo

od h

azar

d ar

eas,

and

ena

ble

deve

lopm

ent i

n sa

fer

area

s.

Use

of ‘

stru

ctur

e pl

ans’

to g

uide

infra

stru

ctur

e la

yout

for n

ew d

evel

opm

ent

(e.g

. roa

ds, 3

wat

ers)

. D

istri

ct P

lan

give

s co

ntro

l ove

r ide

ntifi

ed a

ctiv

ities

to a

void

any

net

incr

ease

in

risk

, and

to e

nsur

e ar

eas

with

una

ccep

tabl

e flo

od h

azar

d ar

e av

oide

d.

(1)

Bui

ldin

gs a

nd a

ctiv

ities

with

in m

appe

d flo

odw

ay c

orrid

ors

that

ac

com

mod

ate

peop

le b

ecom

e no

n-co

mpl

ying

or d

iscr

etio

nary

ac

tiviti

es.

(2)

Oth

er b

uild

ings

and

stru

ctur

es23

with

in m

appe

d flo

odw

ay c

orrid

ors

beco

me

rest

ricte

d di

scre

tiona

ry a

ctiv

ities

. Dis

cret

ion

rest

ricte

d to

:

The

avoi

danc

e of

are

as w

ith e

xces

sive

dep

th o

r vel

ocity

of f

lood

w

ater

.

22 S

ee S

ectio

n 3.

3 fo

r an

expl

anat

ion

of th

e ha

zard

ass

ocia

ted

with

thes

e fe

atur

es.

23 e

xclu

ding

fenc

es, o

r wor

ks a

ssoc

iate

d w

ith a

pub

lic fl

ood

prot

ectio

n sc

hem

e.

Page 33: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Pag

e 30

Ens

ure

adeq

uate

co

nvey

ance

and

effi

cien

t dr

aina

ge.

Pre

vent

alte

ratio

n of

ove

rland

flo

w p

aths

(exc

ludi

ng w

orks

as

soci

ated

with

any

pub

lic

flood

pro

tect

ion

sche

me)

. P

reve

nt th

e cr

eatio

n of

new

flo

od h

azar

d, o

r the

ag

grav

atio

n of

exi

stin

g flo

od

haza

rd.

A

void

ing

the

obst

ruct

ion,

impe

danc

e or

re-d

irect

ion

of fl

ood

wat

er.

(3)

Ear

thw

orks

with

in m

appe

d flo

odw

ay c

orrid

ors

beco

me

rest

ricte

d di

scre

tiona

ry a

ctiv

ities

.24 D

iscr

etio

n re

stric

ted

to:

A

void

ing

the

obst

ruct

ion,

impe

danc

e or

re-d

irect

ion

of fl

ood

wat

er.

(4)

She

lterb

elts

, fen

ces,

pla

ntin

gs a

nd s

tora

ge a

reas

with

in m

appe

d flo

odw

ay c

orrid

ors

are

a pe

rmitt

ed a

ctiv

ity, p

rovi

ded

they

are

loca

ted

and

desi

gned

to e

nsur

e th

at th

e ex

istin

g ov

erla

nd p

assa

ge o

f st

orm

wat

er fl

ows

is n

ot o

bstru

cted

, im

pede

d or

redi

rect

ed.

Incl

usio

n of

thes

e m

atte

rs in

Dis

trict

Pla

n R

ules

. P

rote

ctio

n of

OR

C d

rain

age

syst

em th

roug

h R

egio

nal C

ounc

il Fl

ood

Pro

tect

ion

Byl

aw.

Mai

nten

ance

of d

rain

age

and

flood

pro

tect

ion

wor

ks b

y bo

th C

ounc

ils.

24 u

nles

s th

e ea

rthw

orks

are

par

t of a

ny p

ublic

floo

d pr

otec

tion

wor

k de

sign

ed to

miti

gate

or r

educ

e th

e ef

fect

s of

floo

ding

on

the

Milt

on to

wns

hip.

Page 34: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 31

9 Possible mitigation works

Possible mitigation works have been identified for each of the four diversion sites identified on Figure 10. It should be noted that the proposed works will not mitigate flooding caused by internal runoff and by the stormwater network. Additional work such as detailed investigation (design, and analysis, site visits and surveys), negotiation with landowners, consenting, management and supervision would be required before any of these possible works began. The works at the four sites are outlined as follows (in no particular order). Site 1 - Tower Rd Railway closure Works at this site would restrict significant inflow from the east branch of the Tokomairiro River into Milton. The works would comprise a bund no higher than 1m over a length of 250m. This work would not prevent ponding at the southern end of Milton by itself, but would mitigate the effects of potentially large inflows. Site 2 - Upstream of Dryden St diversion These works upstream of ORC’s T3 scheduled drain would enhance and extend the conveyance capacity of the existing Dryden Street diversion to the north. The works would comprise a bund no higher than 1m over a length of 250m. Site 3 - Keinan Ave diversion upgrade The upgrade of the Keinan Avenue diversion would enhance the mitigation this feature currently provides. The diversion provides some mitigation but it is neither an ORC nor a CDC flood mitigation asset and the standard of protection is relatively low. The works would comprise light channel excavation and widening, raising of the existing bund by up to 0.5m over a 160m length and upgrading of two existing culverts. Site 4 - Back Rd/Springfield Rd intersection drain improvements Water flows over Springfield Road during heavy rainfall due to a tight bend in the roadside drain next to Back Road. This impacts on users of one of the access and escape routes for Milton (Appendix 2). The works would comprise constructing a culvert beneath Springfield Rd and diverting the flow into the existing swale that crosses Back Rd immediately south of the Springfield Rd intersection.

9.1 Road and rail infrastructure

Following the adoption of this Strategy, further work will be required on road and rail infrastructure to ensure that:

in the short term, maintenance and upgrade works do not increase flood risk; and in the long term, existing impacts on other properties are eliminated or reduced.

Clutha District Council roads within the Tokomairiro Plains Prior to undertaking any works which could alter the road crest level or the flow of road drainage, an assessment will be made of impacts on flood risk. Works shall be done in such a way that there is no increase in flood risk for other properties. Over time, the intention will be to lower road crest heights in key locations, and/or improve drainage, so that flood risk for other properties is decreased. State Highways and railway lines The Clutha District Council and the Otago Regional Council will work with NZTA and KiwiRail to help them minimise flood risk impacts due to state highway and railway infrastructure. This will include developing a strategy for future works, so that impacts on other properties are avoided. Ideally, one strategy will cover Council roads, State Highways and rail, to ensure that work on all infrastructure is coordinated. It will also include implementing the Milton 2060 Strategy itself, so that roading and rail networks are also protected from increased flood risk arising from activities on other properties. There are currently no direct land use controls within the District Plan over the State Highway and Rail networks. Both NZTA and KiwiRail are ‘Designating Authorities’ under the RMA and have used that status so that they do not need District Plan resource consents for work on their networks. It would be possible to seek changes to the designations when they are next reviewed, but the preference is to address flood risk through a joint strategy approach.

Page 35: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 32

References

Clutha District Council and Otago Regional Council, 2008. Milton 2060 Draft Scoping Document. Clutha District Council, 2004. Issues and Options Study. Milton Stormwater Upgrades. Department for Communities and Local Government: London, 2006. Planning Policy Statement 25: Development and Flood Risk. Department for Communities and Local Government: London, 2007. Improving the flood performance of new buildings. Flood resilient construction. Department of Regional Development and Environment, 1991. Primer on Natural Hazard Management in Integrated Regional Development Planning. Draft New Zealand Protocol: Managing Flood Risk. December 2005. Soil Conservation and Rivers Control Council, 1957. Floods in New Zealand, 1920-53. With notes on some earlier floods. NZS 9401:2008 Managing Flood Risk – A Process Standard. Standards New Zealand. Local Government, New Zealand, February 2007. Flood Risk Management, A Position Statement from Local Government. Opus International Consultants, 2009. Otago Alluvial Fans Project, Report # 1205 – Version 2, prepared for Otago Regional Council. Opus International Consultants, 2007, Milton Stormwater. July 2007 – Flood Event. Walkover and Assessment. Opus International Consultants, 2007, Milton Stormwater. Tokomairiro Stopbank Options Report. Opus International Consultants, 2007, Milton Stormwater. Pope St Pump Station Concept Design Report. Otago Regional Council, 2012. Draft Flood Protection Management Bylaw. Otago Regional Council and Queenstown Lakes District Council, 2006. Learning to Live with Flooding: A Flood Risk Management Strategy for the communities of Lakes Wakatipu and Wanaka. Otago Regional Council, 2004. Flood Levels of the Tokomairiro River at Milton. Otago Regional Council, 1999. Clutha District Floodplain Report.

Page 36: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 33

Glossary

Average Recurrence Interval (ARI) An estimate of the average interval of time between events. Cumec (m3/s) A measure of flow rate, referring to a cubic metre of water per

second. Risk The likelihood and consequence of an event occurring. Flood Risk Management The management through a variety of means of the known flood

risk. For the purposes of this document the term flood risk management is considered analogous to the term flood risk mitigation.

Hazard A source of potential harm or an event with potential to cause loss. LiDAR Light Detection and Ranging is a mass of spot height information

captured over a wide area using an aircraft mounted laser. The Otago Regional Council’s LiDAR dataset has a vertical accuracy of ± 0.14m and was collected in 2004/5.

Lifelines Lifelines are the essential infrastructure and services that support life within a community. They include utility services such as water, wastewater and stormwater, electricity, gas, telecommunications, and transportation networks including road, rail, airports and ports.

Non-structural flood management options

Elements which are designed to either remove people and assets from risk or to manage exposure to flood effects. Examples include land use planning, emergency management, and flood-proofing buildings.

Residual risk The risk remaining after the implementation or undertaking of risk management measures.

Structural flood management options

Elements which are designed to contain floods and to limit erosion and deposition by controlling river behavior.

Super-design event/s Event/s exceeding the design capacity of the subject structure. True left river bank That which is on the left hand of a person who is facing

downstream. True right river bank That which is on the right hand of a person who is facing

downstream.

Page 37: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 34

Resource consent requirements - Types of activities

Permitted Activities No resource consent is required, provided that any conditions set in the District Plan are complied with.

Controlled activity Resource consent is required, but must be granted. Conditions can be imposed on the consent, but can only relate to matters that Council has specified in the District Plan.

Discretionary activities Resource consent is required, and can be granted or declined on a case by case basis. If the consent is granted, conditions can be imposed on any matters that Council considers necessary to address environmental effects.

Restricted discretionary Activities Resource consent is required, and can be granted or declined on a case by case basis. If the consent is granted conditions can be imposed, but can only relate to matters that Council has specified in the District Plan.

Non-complying activities Resource consent is required, and can only be granted if the effects are minor or the activity is consistent with the objectives and policies of the District Plan. If the consent is granted, conditions can be imposed on any matters that Council considers necessary to address environmental effects.

Prohibited activity No resource consent application can be made for a prohibited activity.

Page 38: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page

35

App

endi

x 1.

C

hara

cter

istic

s of

Flo

od H

azar

d on

the

Toko

mai

riro

Plai

n

Figu

re 1

1. F

lood

haz

ard

on t

he T

okom

airir

o Pl

ain.

The

blu

e sh

aded

are

as s

how

the

estim

ated

ext

ent

of fl

oodi

ng f

or a

hig

h m

agni

tude

flo

od. T

he g

reen

sha

ded

area

sho

ws

the

resi

dual

floo

d ris

k as

soci

ated

with

failu

re o

f the

Mill

Str

eet f

lood

bank

and

/or p

ump

stat

ion.

Page 39: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page 36

Figure 12. Flood hazard characteristics (extent, depth, velocity and peak flows) for a high magnitude flood in the Tokomairiro catchment at Milton.

Page 40: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page

37

App

endi

x 2.

In

unda

tion

dept

hs a

cros

s th

e ro

adin

g ne

twor

k in

Milt

on a

nd th

e To

kom

airir

o flo

odpl

ain,

whi

ch c

ould

be

expe

cted

du

ring

a hi

gh m

agni

tude

floo

d.

Page 41: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Pag

e 38

App

endi

x 3.

M

ilton

206

0 A

ctio

n Pl

an: F

lood

Ris

k M

anag

emen

t Ini

tiativ

es –

Jul

y 20

12

Stra

tegi

c El

emen

t A

ctio

n R

espo

nsib

ility

Com

men

cem

ent d

ate

Und

erst

andi

ng n

atur

al ri

ver a

nd c

atch

men

t pro

cess

es

Und

erst

and

flood

haz

ard

Cap

ture

floo

d ha

zard

info

rmat

ion

and

inco

rpor

ate

into

the

Ota

go N

atur

al

Haz

ards

Dat

abas

e, e

spec

ially

in re

latio

n to

the

Are

a 1B

and

Are

a 4B

flo

odw

ay c

orrid

ors.

OR

C

Dur

ing

and

afte

r maj

or

flood

eve

nts

Und

erst

andi

ng a

nd m

anag

ing

infr

astr

uctu

ral f

lood

risk

Impr

ove

resi

lienc

e of

Milt

on’s

ut

ility

infra

stru

ctur

e Id

entif

y an

d re

med

y re

stric

tions

with

in th

e st

orm

wat

er n

etw

ork,

and

its

outle

ts

to th

e To

kom

airir

o R

iver

. C

DC

C

urre

nt a

nd o

ngoi

ng

Sea

l the

was

tew

ater

col

lect

ion

syst

em to

redu

ce in

filtra

tion

and

cont

amin

atio

n of

sto

rmw

ater

. C

DC

“In

flow

and

Infil

tratio

n’

proc

ess

alre

ady

unde

r w

ay

Red

uce

the

nega

tive

effe

cts

of

infra

stru

ctur

e on

the

conv

eyan

ce o

f flo

odw

ater

Iden

tify

loca

tions

whe

re th

e ro

adin

g ne

twor

k ca

n be

mod

ified

, and

mea

sure

s w

hich

can

be

take

n to

redu

ce fl

ood

haza

rd fo

r roa

d us

ers

and

adja

cent

land

. C

DC

S

ep-2

012

Und

erta

ke m

easu

res

to re

duce

the

nega

tive

impa

cts

of th

e lo

cal r

oadi

ng

netw

ork

on fl

ood

haza

rd.

CD

C

Jan-

2013

Adv

ocat

e fo

r no

incr

ease

, and

a re

duct

ion

in fl

ood

haza

rd fo

r roa

d us

ers

and

priv

atel

y ow

ned

land

whe

n w

orks

are

und

erta

ken

by N

ZTA

and

Kiw

iRai

l to

mai

ntai

n or

upg

rade

the

stat

e hi

ghw

ay a

nd th

e S

outh

Isla

nd M

ain

Trun

k Li

ne.

CD

C /

OR

C

Sep

-201

2

Floo

d se

nsiti

ve u

rban

des

ign

Rai

se a

war

enes

s of

floo

d ris

k m

anag

emen

t thr

ough

goo

d de

sign

Dev

elop

and

pub

lish

a se

t of g

uide

lines

to e

ncou

rage

and

ass

ist f

lood

-dur

able

bu

ildin

g de

sign

. C

DC

D

ec-2

012

Rob

ust c

omm

unity

resp

onse

sys

tem

s R

evie

w O

RC

floo

d pr

oced

ures

R

evie

w th

e ac

tions

and

pro

cedu

res

to b

e un

derta

ken

durin

g flo

od e

vent

s, a

nd

ensu

re th

ese

are

reco

rded

in th

e O

RC

floo

d pr

oced

ures

man

ual.

OR

C

Nov

-201

2

Impr

ovem

ents

to O

RC

/ C

DC

flo

od c

omm

unic

atio

ns

Con

vene

ann

ual f

lood

com

mun

icat

ion

wor

ksho

ps, i

nvol

ving

the

flood

m

anag

emen

t tea

ms

from

bot

h co

unci

ls.

CD

C /

OR

C

Nov

-201

2 (a

nd th

en a

nnua

lly)

Page 42: Flood Risk Management Strategy for Milton and the ...Flood Risk Management Strategy for Milton and the Tokomairiro Plain Ajax Street (foreground), Milton June 1972 Ajax Street, Milton

Page

39

Pre

-floo

d re

adin

ess

actio

ns

Dev

elop

an

oper

atin

g pr

otoc

ol to

be

follo

wed

by

utili

ties

staf

f fro

m b

oth

coun

cils

bef

ore,

dur

ing

and

afte

r flo

od e

vent

s.

CD

C /

OR

C

Nov

-201

2

Phys

ical

wor

ks

Red

uce

flood

risk

in M

ilton

U

nder

take

det

aile

d in

vest

igat

ion

wor

k fo

r the

pos

sibl

e m

itiga

tion

wor

ks

iden

tifie

d in

the

stra

tegy

. C

DC

S

ep-2

012

Det

erm

ine

the

effe

cts

and

cost

of t

he p

ossi

ble

miti

gatio

n w

orks

iden

tifie

d in

th

e st

rate

gy, a

long

with

any

miti

gatio

n w

hich

may

be

requ

ired.

C

DC

Ju

n-20

13

Cha

nnel

man

agem

ent p

rogr

am

Und

erta

ke a

pro

gram

of w

orks

to e

nsur

e th

e ef

ficie

nt c

onve

yanc

e of

flo

odw

ater

in:

th

e no

rth b

ranc

h of

the

Toko

mai

riro

Riv

er b

etw

een

Tabl

e H

ill R

oad

and

Coa

l Gul

ly R

oad,

the

wes

t bra

nch

of th

e To

kom

airir

o R

iver

bet

wee

n C

richt

on R

oad

and

the

conf

luen

ce w

ith th

e no

rth b

ranc

h.

OR

C

Ong

oing

Enab

le lo

ng-te

rm, s

usta

inab

le o

ccup

atio

n an

d de

velo

pmen

t in

Milt

on

Land

use

pla

nnin

g In

corp

orat

e th

e Fl

ood

Ris

k M

anag

emen

t Are

as id

entif

ied

in th

e M

ilton

206

0 S

trate

gy in

to th

e C

luth

a D

istri

ct P

lan.

C

DC

A

sses

s Fl

ood

Ris

k M

anag

emen

t Are

a in

form

atio

n w

hen

cons

ider

ing

new

con

sent

ap

plic

atio

ns: i

mm

edia

te

Not

ify D

istri

ct P

lan

Cha

nge:

Feb

-201

3

Red

uce

expo

sure

to fl

oodi

ng

Inte

grat

e th

e po

licie

s id

entif

ied

in th

e M

ilton

206

0 S

trate

gy in

to th

e O

bjec

tives

, Pol

icie

s an

d su

bseq

uent

pro

visi

ons

of th

e C

luth

a D

istri

ct P

lan.

C

DC

A

sses

s po

licy

info

rmat

ion

whe

n co

nsid

erin

g ne

w

cons

ent a

pplic

atio

ns:

imm

edia

te

Not

ify D

istri

ct P

lan

Cha

nge:

Feb

-201

3

Rev

iew

Milt

on 2

060

Floo

d R

isk

Man

agem

ent S

trat

egy

R

evie

w o

f stra

tegy

R

evie

w th

e st

rate

gy’s

effe

ctiv

enes

s, th

e w

orka

bilit

y of

the

prin

cipl

es,

rele

vanc

e of

the

iden

tifie

d is

sues

and

suc

cess

of t

he in

itiat

ives

auc

tione

d.

CD

C /

OR

C

Nov

-201

4 (th

en e

very

thre

e ye

ars)