floating pv candidate site report
TRANSCRIPT
Floating PV Candidate Site Report
Joydia Baor, Bangladesh
Asian Development Bank
September 2020 Rev03
Floating PV Candidate Site Report
September 2020 │ Rev03
Contents
Glossary ............................................................................................................................................ 6
Executive Summary .......................................................................................................................... 8
1 Introduction .............................................................................................................................. 13
1.1 Background ...................................................................................................................... 13
1.2 Initial site selection and scope of the study ..................................................................... 14
1.3 FPV technology overview ................................................................................................ 14
2 Site Characteristics ................................................................................................................. 22
2.1 Joydia Baor ...................................................................................................................... 22
2.2 Ownership, management and current uses of the lake ................................................... 22
2.3 Ground conditions ............................................................................................................ 23
2.4 Climate ............................................................................................................................. 23
2.5 Site access and laydown area ......................................................................................... 23
2.6 Site assessment findings ................................................................................................. 25
2.7 Conclusions ..................................................................................................................... 37
3 Design Studies and Final Concept .......................................................................................... 38
3.1 FPV design considerations .............................................................................................. 38
3.1.1 Behaviour of the structure in relation to movement of the water .......................... 38
3.1.2 Design studies ....................................................................................................... 38
3.1.3 Ground investigations ........................................................................................... 39
3.2 FPV construction methodology ........................................................................................ 40
3.2.1 Detailed design ..................................................................................................... 40
3.2.2 Installation ............................................................................................................. 40
3.2.3 Testing and commissioning .................................................................................. 41
3.2.4 Operation and maintenance ................................................................................. 41
3.3 FPV Subproject layout and electrical configuration ......................................................... 42
3.3.1 Site constraints ...................................................................................................... 42
3.3.2 Final concept design ............................................................................................. 43
3.3.3 Auxiliary structures ................................................................................................ 49
4 Irradiation and Yield ................................................................................................................ 50
4.1 Introduction ...................................................................................................................... 50
4.2 Irradiation ......................................................................................................................... 50
4.2.1 Global and Diffuse Horizontal Irradiation .............................................................. 50
4.2.2 Global Inclined Irradiation ..................................................................................... 51
4.3 System Design ................................................................................................................. 52
4.3.1 Modelled system design and approach ................................................................ 52
4.3.2 String sizing ........................................................................................................... 53
4.4 Detailed Performance Ratio Calculations ........................................................................ 53
4.4.1 PR Calculations..................................................................................................... 53
4.4.2 Availability assumptions ........................................................................................ 55
4.4.3 Yield estimations ................................................................................................... 55
Floating PV Candidate Site Report
September 2020 │ Rev03
4.5 Uncertainty Analysis ........................................................................................................ 55
4.5.1 Long-term irradiation variability ............................................................................. 55
4.5.2 Irradiation uncertainty over multiple years ............................................................ 56
4.5.3 Uncertainty in yield modelling assumptions .......................................................... 56
4.5.4 Combined uncertainties ........................................................................................ 56
4.5.5 Probabilities of exceeding estimation ................................................................... 57
4.5.6 Yield probability calculation approach .................................................................. 57
5 Grid Assessment ..................................................................................................................... 58
5.1 Introduction ...................................................................................................................... 58
5.2 Option 1............................................................................................................................ 60
5.2.1 Substation site ....................................................................................................... 61
5.2.2 Security of supply .................................................................................................. 61
5.2.3 Physical connection .............................................................................................. 61
5.2.4 Cost ....................................................................................................................... 62
5.3 Option 2............................................................................................................................ 64
5.3.1 Substation site ....................................................................................................... 64
5.3.2 Security of supply .................................................................................................. 65
5.3.3 Physical connection .............................................................................................. 65
5.3.4 Cost ....................................................................................................................... 66
5.4 Conclusion ....................................................................................................................... 67
6 Social Impact Assessment ...................................................................................................... 68
6.1 Background and general socio-economic profile ............................................................ 68
6.2 Impact .............................................................................................................................. 73
6.3 Land acquisition and involuntary resettlement (permanent) ........................................... 73
6.4 Impacts due to grid connection / evacuation lines (temporary) ....................................... 74
6.5 Indigenous Peoples ......................................................................................................... 75
6.6 Impact on fishing and livelihood ...................................................................................... 75
6.7 Social, poverty and gender .............................................................................................. 76
6.8 Other impacts ................................................................................................................... 77
6.9 Public consultations and findings .................................................................................... 77
6.10 Conclusion and recommendations .................................................................................. 81
7 Environmental Assessment..................................................................................................... 84
7.1 General ............................................................................................................................ 84
7.2 Potential environmental impacts and mitigation measures ............................................. 85
7.2.1 Potential land loss ................................................................................................. 85
7.2.2 Impacts on Indigenous People ............................................................................. 86
7.2.3 Potential loss of livelihood, food and ecosystem services ................................... 86
7.2.4 Site clearance and site preparation ...................................................................... 88
7.2.5 Impact to local roads and traffic ............................................................................ 88
7.2.6 Navigation and transportation at lakeside and on the water ................................ 89
7.2.7 Air quality and noise quality .................................................................................. 89
7.2.8 Changes to water quality at the Baor.................................................................... 90
7.2.9 Construction waste and hazardous waste generation .......................................... 93
7.2.10 Land use and land value ....................................................................................... 93
7.2.11 Habitat and aquatic life impacts ............................................................................ 94
Floating PV Candidate Site Report
September 2020 │ Rev03
7.2.12 Impacts on protected and internationally recognised areas ................................. 95
7.2.13 Social impacts associated with construction ........................................................ 96
7.2.14 Employment opportunities and income generation .............................................. 96
7.2.15 Industrial and economic development .................................................................. 96
7.2.16 Human safety ........................................................................................................ 96
7.2.17 Climate change impacts ........................................................................................ 97
7.2.18 Objects of cultural or achaeological importance ................................................... 98
7.2.19 Visual intrusion and reflection issues.................................................................... 98
7.2.20 Subproject decommissioning ................................................................................ 99
7.3 Conclusions and recommendations ................................................................................ 99
8 Financial Analysis.................................................................................................................. 102
8.1 Introduction .................................................................................................................... 102
8.2 Methodology and major assumptions ............................................................................ 102
8.2.1 Subproject cost estimate ..................................................................................... 102
8.3 Weighted Average Cost of Capital (WACC) .................................................................. 104
8.4 Financial Internal Rate of Return (FIRR) ....................................................................... 105
8.4.1 Sensitivity analysis .............................................................................................. 106
8.5 Conclusion ..................................................................................................................... 106
9 Economic Assessment .......................................................................................................... 107
9.1 Power sector and renewable energy development ....................................................... 107
9.1.1 Renewable energy policy target ......................................................................... 107
9.1.2 Macroeconomic background ............................................................................... 107
9.1.3 Electricity demand ............................................................................................... 108
9.1.4 Electricity supply ................................................................................................. 109
9.1.5 Fuel mix ............................................................................................................... 109
9.1.6 Potential role of floating PV................................................................................. 110
9.2 Economic evaluation of the proposed Subproject ......................................................... 111
9.2.1 Background ......................................................................................................... 111
9.2.2 Subproject costs.................................................................................................. 111
9.2.3 Subproject benefits ............................................................................................. 113
9.2.4 Economic feasibility ............................................................................................ 114
9.2.5 Sensitivity and risk analysis ................................................................................ 119
9.2.6 Conclusion .......................................................................................................... 120
10 Climate Hazard Risk Assessment for Joydia Baor ............................................................... 121
10.1 Introduction .................................................................................................................... 121
10.2 Biophysical context ........................................................................................................ 121
10.3 Current climate ............................................................................................................... 121
10.4 Observed and projected climate change ....................................................................... 123
10.5 Assessed climate change risks for Joydia ..................................................................... 124
10.6 Potential climate proofing measures ............................................................................. 129
Appendices
A. Subproject Configuration and Layout
B. Irradiation Database Information
Floating PV Candidate Site Report
September 2020 │ Rev03
C. Irradiation Methodology
D. System Design
E. PR losses
F. Uncertainty in Yield Modelling Assumptions
G. Grid Impact Study
H. Breakdown of Subproject Cost Estimates
I. Report of Local Livelihoods and Activities of Joydia Baor
J. Project Spill Response Plan
K. Constrcution and Operation Waste and Hazardous Waste Management Plan
Floating PV Candidate Site Report
September 2020 │ Rev03 6
Glossary
Acronym Meaning
AC Alternating Current
ADB Asian Development Bank
BDT Bangladeshi Taka
BFDC Bangladesh Fisheries Development Corporation
BERC Bangladesh Energy Regulatory Commission
BPDB Bangladesh Power Development Board
BRTA Bangladesh Road Transport Authority
BREB Bangladesh Rural Electrification Board
CRVA Climate Risk and Vulnerability Analysis
DC Direct Current
DFO Divisional Forest Officer
DHI Diffused Horizontal Irradiation
EIRR Economic Internal Rate of Return
EPC Engineering, Procurement and Construction
EYA Energy Yield Assessment
FIRR Financial Internal Rate of Return
FPV Floating Photovoltaic
GDP Gross Domestic Product
GIS Geographic Information System
GHG Greenhouse Gas
GHI Global Horizontal Irradiation
GM Ground-Mounted
GOB Government of Bangladesh
HDPE High-Density Poly-Ethylene
HV High Voltage
IP Indigenous Peoples
IPP Independent Power Producers
LV Low Voltage
MPEMR Ministry of Power, Energy and Mineral Resources
MV Medium Voltage
MVPS Medium Voltage Power Station
NREL National Renewable Energy Laboratory
O&M Operation and Maintenance
Floating PV Candidate Site Report
September 2020 │ Rev03 7
Acronym Meaning
PBS Palli Bidyut Samiti (rural electricity co-operative)
PGCB Power Grid Company of Bangladesh Limited.
PoC Point of Connection
PR Performance Rati
RINA RINA Tech UK Ltd
RMSE Root Mean Squared Error
SCF Standard Conversion Factor
SEA Strategic Environmental Assessment
SERF Shadow Exchange Rate Factor
SIA Social Impact Assessment
SMP Social Management Plan
SPS Safeguard Policy Statement
SREDA Sustainable Renewable Energy Development Authority
STATCOM Static Compensator
SWRF Shadow Wage Rate Factor
UNESCO United Nations Educational, Scientific and Cultural Organization
UNO Upazila Nirbahi Officer (sub-district officer of Bangladesh Administrative
Service)
USD United States Dollar
WACC Weighted Average Cost of Capital
WMO World Meteorological Organisation
WTP Willingness To Pay
Floating PV Candidate Site Report
September 2020 │ Rev03 8
Executive Summary
Bangladesh aims to increase its installed renewable energy capacity significantly over the next 20
years, with solar and wind technologies to be the key focus areas for future capacity addition. Due
to the increasingly high demands placed on land, e.g. for agricultural and forestry purposes, the
Government of Bangladesh has initiated a programme of development for floating photovoltaic
(‘FPV’) technology; this is expected to involve a combination of public and private development.
This Feasibility Study Report presents an assessment of Joydia Baor (the ‘Subproject’), in which
the main criteria affecting the future deployment of floating PV have been assessed with respect to
the constraints of the water body.
Site characteristics
Joydia Baor is an oxbow lake located in Jhenaidah District, within the Khulna Division of
Bangladesh. The activities carried out at the Baor include fishing (commercial and recreational),
jute retting, cropland irrigation, washing and bathing, cooking and duck farming. There is a regular
boat service route connecting the communities on the east and west banks of the Baor.
In general, water bodies in Bangladesh are owned by the Ministry of Land and leased by other
agencies and organisations to meet different needs. Joydia Baor is leased and managed by the
Department of Fisheries. The community members of the Baor include 184 fishermen. These
people are responsible for guarding the Baor to prevent poaching and also to catch fish during the
harvesting season. Other local fishermen have licenses to catch small fish with local handmade
traps and specific nets to earn their livelihood. The community members get 40% share of the total
harvest and 35% goes to Department of Fisheries. The remaining 25% belongs to local District
Commissioner Office as an annual lease fee.
Access to the lake is unsuitable for large vehicles due to a number of sharp turns and narrow
culverts; however, small trucks may be used to gain access to the site. It is recommended that
materials are stored at Jessore PBS Warehouse and transported to site with small trucks/vans.
The soil surrounding Joydia Baor is clay loam. The ground in the vicinity of the Baor is
predominantly flat, with a slope towards the water body. We recommend that further geophysical
and geotechnical analysis of the lakebed where the floating platforms, inverter stations and anchors
are to be located should be conducted as part of the development phase. This is because, although
the overall geological structure of the lake has been considered in this study, the detail of specific
areas of the lakebed should be fully investigated prior to installation works.
Concept design
The conceptual design presented in this report features six similar FPV DC platforms. Preferably,
platform design should aim for simple shapes (regular squares or rectangles) bearing in mind the
prevailing wind direction to account for wind loads. In this case, a longer east-west axis would
enable increased mooring points to counter the effects of wind considering the south and southeast
prevailing winds of the region. Although the waterbody offers an open surface onto which to locate
regular-shaped platforms, the presence of the aforementioned numerous komors conditions the
available space. This represents the main constraint accounted for in terms of design.
Floating PV Candidate Site Report
September 2020 │ Rev03 9
On the LV DC-side, the FPV array has a total capacity of 9,072.0 kWp, which consists of 22,680 x
400 Wp modules distributed in 840 strings of 27 modules across the six platforms. The system
features three AC floating skid medium voltage power stations (MVPS) platforms totalling a
cumulative AC capacity of 7,500 kVA (at 50°C). Each of these MVPS platforms collects 3,024 kWp
of module DC cumulative power.
The platforms cover large areas and have been located to minimise disruption on navigation and
fishing within the lake. Particularly, platform locations have been envisaged to minimise the
disruption on the ‘inner’ half section of the Baor, where fishing activity has greater presence.
The module row distance and tilt angle are specified in accordance with typical FPV technology
designs from a leading supplier. It is noted that the tilt angle of FPV systems are lower than normally
seen on ground-mount arrays; this design was developed to reduce wind loading on the platforms.
Energy yield
An Energy Yield Assessment (EYA) was carried out to determine the expected energy yield of the
proposed plant. The analysis was based on the indicative design information developed by RINA
for the concept design and irradiation data from satellite and ground station databases.
Global Horizontal Irradiation (GHI) was assessed from a number of sources before a value of 1,752
kWh/m2/yr was selected. This value was then uplifted to be appropriate for module arrays facing
south (azimuth: 0°) and inclined at 11° to horizontal. On the basis of the system design assumptions
detailed in this report, a Performance Ratio (PR) has been calculated using industry standard
PVsyst software and RINA proprietary models.
Calculations have been performed using hourly irradiance and ambient temperature values
generated for the site. Shading has been estimated using a 3D model constructed in PVsyst (v6.75)
and based on the detailed module layout, findings during the site visit and online mapping images.
Resulting first year energy yield predictions are shown in Table 1.
Table 1: Year one energy yield summary
PR Installed
capacity (kWp)
Probability of
exceedance
Specific yield
(kWh / kWp)
1st year
production
(kWh)
81.4% 9,072.00
P50 1,495 13,563,495
P75 1,445 13,110,536
P90 1,400 12,702,858
The P50 specific yield already contains an assumption of 0.2% for the first-year degradation. When
used to calculate output in subsequent years, a linear degradation of 0.4% should be applied.
This energy yield study assumes 100% availability of the plant. Final achieved availability will
depend on technical characteristics of the Subproject and the contractual guarantees, however a
value of 100% is unlikely to be achievable. It is noted that the FIRR and EIRR analysis has
considered availability separately to the energy yield figure.
Floating PV Candidate Site Report
September 2020 │ Rev03 10
Grid impact
The grid impact study analyses the impact on the Bangladeshi network as a result of the connection
of a 9.1 MWp FPV plant at Joydia Baor.
There are two possible options to connect the Joydia FPV plant to the Bangladeshi grid network:
1. Connect to the 33 kV bus of the Moheshpur-2 33/11 kV substation; and
2. Connect to the 33 kV bus of the Kotchandpur substation.
From the practical perspective the best option is connecting to the 33 kV substation at the
Kotchandpur substation as this is nearest to the site and will be the most economic option. This
requires construction of 9.33 km of overhead line (OHL) from the onshore station to the
Kotchandpur substation. The proposed route of the 33 kV OHL line will run along the public highway
thus negating the complications associated with the routing through private land.
The grid impact analysis has therefore been conducted for the preferred connection option of
connecting at the Kotchandpur substation 33 kV substation.
Social impact assessment
The Subproject will have some negative impacts in terms of loss of income and livelihood due to
restriction of water use for fishing. However, some local employment will be generated temporarily
during construction. Based on the assessment and also suggestions from the local people, various
conclusions, suggestions and recommendations are provided. A summary is provided below and
the social management plan for mitigation measures is provided in Section 6.10 of the main report.
The Subproject planning shall avoid fishing areas and use only the water body areas where
there are no fishing activities;
The Subproject shall not take more than 10% of the surface area. If possible, dredging options
shall be explored if no adverse environment impacts. However, dredging seems to be
unlikely; and
People expect some direct benefits from the Subproject. This requires adequate mitigation
measures for uninterrupted fishing activities and any loss in the future shall be compensated
and mitigated by the Subproject.
Environmental impact assessment
There are various impacts associated with the Subproject during construction and operations,
including impacts to land, roads, water quality, wildlife (birds and fish), fishing activity and livelihood,
navigation and recreational activities.
Most environmental impacts identified can be reduced to acceptable levels with the implementation
of various avoidance and mitigation measures proposed in the IEE and EMP along with those
measures recommended in the Strategic Environmental Assessment (SEA) and Social
Management Plan (SMP).
It is recommended that the Subproject should be categorised as B for ADB environmental
assessment purpose.
Floating PV Candidate Site Report
September 2020 │ Rev03 11
The major potential impact from the Subproject will be to fishing activity and the potential lost
revenues, livelihood and food source. It is important that the Executing Agency for the Subproject
work with the Lands Department, the Department of Fisheries and the Baor fishing community to
implement the SMP measures. All stakeholders need to come to agreement on future leasing
arrangements for joint use of the water resource to allow for fishing activity to continue and for the
Subproject to be developed.
Financial analysis
The financial evaluation of the proposed investments was carried out in accordance with the Asian
Development Bank (ADB) Financial Management and Analysis of Subprojects. Cost streams used
to determine the financial internal rate of return (FIRR) include capital costs (excluding price
contingencies), operation and maintenance (O&M) costs, and taxes and duties. The weighted
average cost of capital (WACC) was calculated and compared with the FIRR to ascertain financial
viability.
WACC as calculated in real terms is 0.8%, considering loans from external financing to be extended
to the government, which will be on-lent to the implementing agency. On-lending from these
external sources will be in foreign currency (US$) for a period of 20 years with a 5-year grace
period. Government on-lending margins and lending rates have been modelled in accordance with
the GOB regulation.
For the purpose of financial analysis, the rate for ground mounted solar PV projects of 12.00
BDT/kWh has been considered. The applicability of this tariff to an FPV project may need to be
confirmed in regulation, however as an FPV project might be expected to have a higher cost than
a ground mounted PV project, the rate is not considered unreasonable at this stage. The FIRR has
been calculated at 8.1%.
The FIRR is expected to comfortably exceed the WACC for the Joydia Subproject. Sensitivity and
risk analysis indicate that the FIRR are robust under most conditions. As such, each investment
Subproject is concluded to be financially viable.
Economic assessment
The economic evaluation of the proposed investment was carried out in accordance with ADB’s
guidelines on Power Sector Project Appraisal. The background costing study presented three
financial price scenarios for the Subproject. This study is considered the base cost case in the
analysis. Under the base case, the total Subproject cost (direct and indirect costs) would amount
to US$ 11.85 million. All Subproject costs were expressed in terms of economic prices. Investment
and O&M costs in financial prices were adjusted to reflect the economic resource cost of Subproject
inputs in terms of domestic price numeraire.
The economic assessment shows that the economic performance of the Subproject can be
considered as robust, considering that the EIRR of 9.31% is above the benchmark rate of 9% used
in the study. A sensitivity analysis was carried out showing that even with a relatively high increase
in key investment parameters, the proposed Subproject would remain economically viable. From
an economic standpoint, the Subproject is considered beneficial to the economy and should be
financially supported.
Floating PV Candidate Site Report
September 2020 │ Rev03 12
Climate hazard assessment
The Joydia Subproject is located on the Ganges floodplain in Jhenaidah District, which is already
affected by a range of climate-induces hazard risks, including strong winds and cyclonic events,
variations in temperature and rainfall, and flooding and sedimentation.
The main risks for Joydia Baor are based on the preliminary site visit, and as assessed under the
CRVA for the Subproject, are those arising from an increase in extreme rainfall events and
cyclones, and include flooding, erosion and sedimentation.
It is expected that these hazards will be exacerbated by changes in the climate and the intensity of
climatic disasters like tropical cyclones, droughts and floods into the future and these need to be
fully taken into account during the detailed design phase of the Subproject, especially in relation to
the sensitivity of FVP infrastructure to: increasing temperatures extremes and hot days; increasing
intensity of rainfall and associated fluctuations in water levels; increased frequency and intensity of
flood events and associated sedimentation; and increasing intensity of wind velocity and cyclone
weather conditions.
Based on the review of literature and best practice undertaken for the CRVA, we further identified
a limited range of hazard risk mitigation measures for climate proofing infrastructure proposed
under this Subproject, including the following:
It is recommended that the effects of changing flood levels and behaviour due to climate change
be taken into account and accommodated in the Subproject design process through application
of appropriate international standards and guidelines;
FVP infrastructure to be located in low risk areas to minimise system vulnerabilities to possible
climate impacts and threats from string winds, currents and debris associated with floods;
Identify and select suitable materials for construction of infrastructure assets and structures to
minimise damage and/or deterioration of FVP infrastructure cyclonic winds and other related
climate change impacts.
Floating PV Candidate Site Report
September 2020 │ Rev03 13
1 Introduction
1.1 Background
Bangladesh is one of the fastest growing economies in South Asia. Over the past decade, it has
been growing at an annual rate of around 6%1. The Government of Bangladesh aims to achieve
the status of a ‘middle-income country’ by 2021 and that of a ‘high-income country’ by 2041.
Electricity plays a vital role in poverty eradication, sustained economic growth, infrastructure
development and security of a country. For this reason, Bangladesh intends to address the barriers
to higher growth posed by low access to reliable and affordable power; limited availability of
serviced land; rapid urbanisation; vulnerability to climate change and natural disasters, to achieve
its socioeconomic growth targets.
The performance of Bangladesh’s power sector in the last five years has been impressive due to
the progressive efforts of policymakers, support from development partners, and effective project
implementation by public and private developers. The growth in terms of capacity addition in the
last 10 years has been remarkable, from around 4.5 GW in 2007–08 to 17.8 GW in 20192 . Private
sector participation in generation accounts for about 60% of the total installed capacity.
In accordance with the recent Power System Master Plan, Bangladesh aims to add 2 GW
renewable energy projects to achieve a total installed capacity of 2,470 MW by 2021, and to
increase that to 3,864 MW by 2041. Solar and wind will be the key focus areas for future capacity
addition, accounting for c. 50% and 40% of the renewable installed capacity by 2021 respectively3.
Consideration for Floating Photovoltaic (FPV) systems has been prioritised due to the fact that
many surface water bodies located in developing regions have considerable solar resource.
Floating PV uses the surfaces of rivers, lakes and reservoirs by mounting PV modules on floating
structures. It was first deployed commercially in 2007 with a project in the Japanese prefecture of
Aichi. The surface area of existing water bodies such as reservoirs, lakes, and exposed water
storage/treatment basins could be used to accommodate FPV technology, giving added value to
the area. It also has the potential to improve water security in hotter climates by reducing water
losses due to evaporation. Furthermore, research undertaken by the Malardalen University in
Sweden indicates that FPV may improve module energy yield due to the cooling effect of the water
body4. This report presents an FPV Feasibility Study for Joydia Baor (the ‘Subproject’), which is
located in the Jhenaidah District in Bangladesh.
FPV is an effective way of scaling up solar generating capacity, especially in countries with high
population density and competing uses for available land. It is noted that there are significant
pressures on land availability in Bangladesh due to the high density of people in the country
combined with a growing population. Considering the high percentage of land usage for essential
1 World Bank national data and OECD national Accounts Data files (2017).
2 Overall public and private generating capacity accounted in June 2019. The figure does not include imported
capacity from India (approximately 1,160 MW) and captive generation (approximately 2,800 MW).
3 Power System Master Plan, Government of the People’s Republic of Bangladesh (2016).
4 Optimization of Floating PV Systems: Case Study for a shrimp farm in Thailand, L. Wasthage, Malardalen
University, Sweden (2017)
Floating PV Candidate Site Report
September 2020 │ Rev03 14
activities such as agriculture and the availability of large water bodies in certain regions, solutions
supporting the development of PV solar projects on water are considered more appropriate.
1.2 Initial site selection and scope of the study
In order to select appropriate water bodies for potential installation of FPV plants, an initial study
was undertaken to identify all large water bodies, reservoirs and lakes which could be considered
suitable options. This initial investigation used satellite imagery5 to survey permanent areas of
surface water across the whole of Bangladesh. Certain types of water bodies were rejected due to
reasons of ecological sensitivity, seasonality and technical difficulties in implementation (e.g.
wetlands). As a result of this assessment, several key areas of Bangladesh were selected and a
number of candidate sites identified for further investigation.
The scope of this report is to provide a feasibility assessment of the potential for the installation of
a floating PV (‘FPV’) plant at one of the candidate sites, Joydia Baor (the ‘Subproject’), located in
Jhenaidah region. Additionally, an assessment of available grid infrastructure as well as any
necessary reinforcement works is provided. This report deliverable covers the following topics:
Site assessment;
Concept design;
Yield and irradiation analysis;
Grid impact assessment;
Social impact assessment;
Environment impact assessment;
Financial analysis of the Subproject;
Economic assessment; and
Climate change vulnerability assessment.
This FPV Feasibility Report presents the results of these assessments for the Subproject.
1.3 FPV technology overview
The basic configuration of an FPV system comprises a floating platform to retain the PV modules,
combiner boxes and cables, rather than typical ground or roof mounting steel structure. The floating
platform is held in place on the lakebed or shores with mooring lines connected to anchors. The
system feeds into inverter stations, from which point the FPV system does not differ from a ground
mount system.
Figure 1 below is indicative of typical FPV plants. It is noted that this report does not cover less
commonly used innovative technologies, e.g. floating concentrated PV and partially submerged
thin film arrays.
5 https://global-surface-water.appspot.com/map
Floating PV Candidate Site Report
September 2020 │ Rev03 15
Figure 1: Typical FPV schematic
Source: Solar Energy Research Institute of Singapore (SERIS)
In electrical terms, FPV systems are identical to traditional ground-mounted (‘GM’) PV systems.
That is to say, DC electricity is generated by PV modules and fed into inverters which convert the
energy generated into useable AC electricity. This is then either directly consumed at the point of
connection or fed into a distribution or transmission network to be consumed remotely.
The single greatest difference lies in how the PV modules are mounted or placed. In the case of
GMPV systems, the mounting of panels is based on a rigid structure with a firm foundation. Static
and dynamic loads are readily calculated according to established engineering methods and the
geometry of the module arrangements is relatively easy to control.
By contrast, in FPV systems the dynamic nature of the water surface, along with the various forces
acting on the modules (wind drag, tethering cables, wave motion etc.), require more novel structural
designs that are able to withstand significant movement, and wear and tear. In addition, control of
the module geometry and implementation of tracking is particularly challenging to achieve.
A further significant difference is in the physical construction and design of electrical equipment,
such as inverters and cabling, which have to be marine rated for FPV systems. This typically
requires IP ratings and corrosion resistant materials that are usually not necessary for standard
GMPV systems.
With regards to the stakeholder structure, the major difference to GMPV is frequently the presence
of more competitive uses for water reservoir, in comparison to the land used for standard PV plants.
More stakeholders may need to be managed and also changes in future use cases need to be
considered when implementing an asset of 25-year lifetime on reservoirs that may require de-silting
from time to time or that may be used for recreational or fishing purposes.
Floating PV Candidate Site Report
September 2020 │ Rev03 16
A comprehensive comparison of FPV systems versus GMPV systems is presented in Table 2
below. This includes characteristics already discussed, such as FPV resolving land scarcity issues,
and additional characteristics such as the relative safety of the two different systems.
Floating PV Candidate Site Report
September 2020 │ Rev03 17
Table 2: Comparison of GMPV and FPV systems characteristics
Characteristic FPV GMPV
Advantages Disadvantages Advantages Disadvantages
Land/water
surface use
Does not compete for land
with agricultural, industrial, or
residential projects.
More appropriate solution in
densely populated areas.
Since water bodies often
have a single owner, the
permitting process is often
less complicated.
Expected lower leasing cost
Potential integration with
aquaculture.
May save water resources by
reducing water evaporation.
Competes with fishery, boat
and recreational activities.
Potential ecological impact on
water bodies.
No impact on potentially
sensitive water bodies.
Potential integration for certain
farming activities (e.g.
grazing).
Suitable/affordable land may
be far away from load centres,
thus requiring costly
transmission infrastructure.
Requires land usable for
commercial/industrial
installations.
Competes for land with city
dwellings, industrial
development, and agriculture.
Plant design Modular design on flat
surface.
Anchoring cables require
periodic inspection and
maintenance of at least every
5 years.
Design must consider changes
in water level over season and
over plant lifetime and
subsurface terrain elevations.
Design should intent to never
have the reservoir area below
the FPV plant dry out
Easier to implement tracking.
Yield prediction is better
established.
Design must accommodate
terrain and area constraints.
Floating PV Candidate Site Report
September 2020 │ Rev03 18
Characteristic FPV GMPV
(minimum water depth
requirement) and to not
exceed current maximum
water level depths of 90m.
Design must consider
humidity, wet conditions
through wave height and
occurrence and flooding
(storm).
Limited tilt due to wind load
considerations imply a lower
energy yield in high-latitude
regions.
Performance/
energy yield
Lower module temperatures
(effect is dependent on
climate).
Nearly no shading.
Lower soiling from dust from
within the Subproject site.
Overall 5–10 percent higher
initial performance ratio
(climate specific) determined
by experiments performed by
SERIS considering the
cooling effect of water
evaporated, wind speeds,
Long-term degradation (e.g.,
potential induced degradation)
is still uncertain.
Can benefit from tracking,
bifacial, and optimum tilt angle.
Increased temperature losses
in hot climates.
Floating PV Candidate Site Report
September 2020 │ Rev03 19
Characteristic FPV GMPV
and reduction of inter-row
shading and dust.6
Installation and
deployment
In general, easy assembly,
but highly variable depending
on location and workforce
availability.
Transportation of floats to site
is difficult; favours local
production.
Needs suitable launching area.
Needs underwater anchoring
of the floating structures.
In general, easy assembly, but
highly variable depending on
location and workforce
availability.
Needs heavy equipment and
land preparation.
Depends on soil quality.
Power system
Synergy with existing
electrical infrastructure.
Possible hybrid operation
with hydropower.
Intermittent power generation. Synergy with existing electrical
infrastructure.
Intermittent power generation.
Environmental Potential to reduce algae
growth.
Potential to reduce water
evaporation.
Potential destructive impact on
aquatic ecosystems, birds and
other animal habitats (anchors
penetrating ground, FPV
blocking sunlight penetrating
into water body, cooling water
body, among others).
Long-term effects on water
quality are not well
established.
Generally low impact, only
some adverse impacts during
construction.
Potential habitat loss or
fragmentation.
Potential detrimental impact on
ecosystems, birds and other
animal habitats.
6 World Bank Group, ESMAP and SERIS. 2019. Where Sun Meets Water: Floating Solar Market Report. Washington, DC: World Bank.
Floating PV Candidate Site Report
September 2020 │ Rev03 20
Characteristic FPV GMPV
Investment Cost of floats may drop as
scale of deployment
increases.
Slightly higher costs on
average due to floats,
anchoring, mooring, and plant
design.
Higher perceived risk due to
lower level of maturity,
resulting in typically higher
interest rates for loans and
lower availability of project
finance options and
commercial lenders. Balance
sheet finance is still commonly
applied for FPV projects to
mitigate this early technology
risk.
Huge installed capacity and
hence very established
investment and financing
sector.
Costs continue to drop.
Operation and
maintenance
Easy access to water for
cleaning.
Lower risk of theft/vandalism.
Harder to access and replace
parts.
Biofouling.
Animal visits and bird
droppings.
Harder to maintain anchoring.
Can be affected by aquatic
growth in some regions.
Easy to access.
Easier to deploy cleaning
routines.
Generally more affected by
vegetation growth.
Safety Less affected by risks of
burning vegetation in dry
season.
Close to water, tend to have
lower insulation resistance to
ground.
Generally safe. More affected by risks of
burning vegetation in dry
season.
Floating PV Candidate Site Report
September 2020 │ Rev03 21
Characteristic FPV GMPV
Constant movement poses
challenge for equipment
grounding.
Risk of personnel falling into
water.
Safety easier to manage as
the plant can be easily fenced
off.
Regulation and
Permits
More difficult for natural lakes
and easier for artificial ponds.
Lack of specific regulations
and potentially additional
complexity due to new players
such as reservoir owner and
/or management agency.
Well established permitting
process.
Clear regulations.
Experience/
level of maturity
Cumulative capacity as of end
of 2019: >1.3 GWp.
Only 4 years of experience
with large-scale projects.
Cumulative capacity as of end
of 2019: >500 GWp.
Thousands of projects built
10–30 years of experience.
Floating PV Candidate Site Report
September 2020 │ Rev03 22
2 Site Characteristics
2.1 Joydia Baor
Joydia Baor is an oxbow lake located in the Jhenaidah District, within the Khulna Division of
Bangladesh. The lake, pictured in Figure 2, has a crescent shape and is approximately 6 km long
with a width of 250-400 m.
Figure 2: Joydia Baor
The Baor is widely used for washing and bathing by many in the wider lakeside community; people
also use the water for cooking and washing their clothes. There is a regular boat service route
connecting the communities on the east and west banks of the Baor.
2.2 Ownership, management and current uses of the lake
The Department of Fisheries is responsible for the entire management of the Baor. The Baor is
owned by the Ministry of Land. The Department of Fisheries took lease of the Baor from the local
District Commissioner. Fish stocking is the sole responsibility of the Department of Fisheries. The
community members of the Baor include 184 fishermen. These people are responsible for guarding
the Baor to prevent poaching and also to catch fish during the harvesting season. Other local
fishermen have licenses to catch small fish with local handmade traps and specific nets to earn
Floating PV Candidate Site Report
September 2020 │ Rev03 23
their livelihood. The community members get 40% share of the total harvest and 35% goes to
Department of Fisheries. The remaining 25% belongs to local District Commissioner Office as an
annual lease fee.
In addition to fishing, the Joydia Baor is used for:
Irrigation of adjacent croplands;
Jute retting;
Washing and bathing;
Cooking; and
Duck farming.
Further details regarding activities and management of the Baor are provided in the survey report
included in Appendix I.
2.3 Ground conditions
The soil surrounding Joydia Baor is clay loam. The ground in the vicinity of the Baor is
predominantly flat, with a slope towards the water body. There are relatively few publicly available
data on the physical environment. It is recommended that the lake’s morphometric and
hydrographic features are fully investigated prior to the finalisation of the design. Responsibility for
these investigations should rest with the EPC contractor.
Furthermore, it is expected that a geotechnical investigation would be performed by the EPC
contractor prior to designing the final layout and anchoring of the PV plant. The ground
investigations required and allocation of responsible parties to conduct them are fully described in
Section 3.1.3.
2.4 Climate
Joydia Baor lies in the path of heavily moisture-laden monsoon winds. The rainy season extends
from June through November and about 80% of the annual rainfall is concentrated in this season.
Humidity is 35-45% between November and March and it increases to approximately 80% during
the rainy season (June to October). We recommend that final design adheres to international
design requirements, for which the EPC contractor is expected to assume responsibility. Based on
data available from the Global Wind Atlas, it is noted that the lakes experiences average speeds
of approximately 3.03 m/s at a height of 10 m.
2.5 Site access and laydown area
Site visits were undertaken to Joydia Baor area between the 20th and 23rd of November 2019 by
the team of Consultants.
Access to the Baor is gained via a brick flat soling road which is connected to a paved regional
road. The brick flat soling road is approximately 10 feet wide, which is considered to be suitable for
small trucks. The limited road width and turn means that it is not suitable for large trucks. An access
way to carry equipment from road to the assembly point would need to be created by shaping the
land and correcting the slope.
Floating PV Candidate Site Report
September 2020 │ Rev03 24
We have identified a large, empty and generally flat area adjacent to the lake, which we would
consider suitable as a storage area. It is recommended that the assembly area is located closer to
the lake.
The area surrounding the lake is largely flat. However, it is noted that many of the banks of the lake
are sloped and as such would require a pulley system to lower the floating platform onto the Baor’s
surface. Nevertheless, this is not expected to pose a material risk to the construction of the plant.
Figure 3 below shows the potential storage and assembly areas.
Figure 3: Proposed storage and assembly areas
Potential
Assembly
Point Potential
Storage
Area
Floating PV Candidate Site Report
September 2020 │ Rev03 25
2.6 Site assessment findings
Table 3 below provides an overview of the most notable features based on the obtained evidence.
Each of the broad criteria, together with any sub-criteria and their associated conditions of
acceptability are presented in general, with a specific assessment for Joydia Baor given in the right-
hand columns.
Floating PV Candidate Site Report
September 2020 │ Rev03 26
Table 3: Joydia Baor site visit assessment details
Criterion Sub-criterion Description Comment Evidence
Topography Suitability of
terrain for
assembly.
Assessment of site
accessibility for:
1. construction /
assembly phase
and
2. O&M.
Ideally a flat area
is required for
assembly of the
floats and
modules.
The proposed assembly
area is on the north western
bank of the Baor.
The soil is clay loam type.
Semi-flat with a slope
towards the water body.
Floating PV Candidate Site Report
September 2020 │ Rev03 27
Criterion Sub-criterion Description Comment Evidence
Available area
at the proposed
assembly
location.
Is area available
and suitable for
assembly of
floating platforms?
The proposed assembly
area is approximately
1,400 m2 (based on Google
Maps imagery) which is
adequate for assembling.
Landfilling is required in
some places and levelling is
required all through for a
flat surface.
Suitability of
location for
storing
equipment (site
building) during
assembly and
operation
phase.
- The road adjacent to the
proposed assembly point is
approx. 10 feet wide. It is a
brick soling road that is
connected to a paved
regional road.
Material shifting from
central warehouse/storage
is possible for small trucks,
but not for large trucks due
to the limited road width
and turn.
An access way to carry
equipment from road to the
assembly point needs to be
created by shaping the land
and correcting the slope.
Floating PV Candidate Site Report
September 2020 │ Rev03 28
Criterion Sub-criterion Description Comment Evidence
Obstructions on
site.
As above.
Specifically, with
regards to floating
system assembly
area and O&M
buildings.
A few trees may require
cutting down on the
roadside for access of
equipment to the area.
Geology Suitability of
soil/subsoil.
Assessment of
sedimentation,
geology of
potential
anchoring points,
evidence of
eutrophication.
The soil is clay loam type.
The anchoring needs to be
arranged on the Baor bed
with proper civil works.
There is no evidence of
eutrophication observed.
Floating PV Candidate Site Report
September 2020 │ Rev03 29
Criterion Sub-criterion Description Comment Evidence
Any suitable
banks for
anchoring?
Used to inform
assessment
anchoring design
options. Bank
anchoring is
typically the most
cost-effective to
construction and
for O&M activities
The north shore of the Baor
adjacent to the pontoons
may be used for shore
anchoring. This will be
limited anchoring only to
one side; others needs to
be done on the waterbody
(Baor) bed.
N/A
Ask if de-silting
is planned for
these
reservoirs and
discuss
anchoring
obstruction.
Used to inform
assessment
anchoring design
options.
No Information received
from managing authority
(Dept. of Fisheries) but the
local community has
requested dredging.
N/A
Erosion. Used to inform
assessment
anchoring design
options. May
adversely affect
bank anchoring.
No consistent erosion has
been observed.
N/A
Seismic zone. Used to determine
the risk of
anchoring coming
The area falls within
Seismically Quiet Zone III.
Source: Bangladesh Disaster Knowledge Network.
Floating PV Candidate Site Report
September 2020 │ Rev03 30
Criterion Sub-criterion Description Comment Evidence
loose and/or water
disturbance during
a seismic event.
Also required for
O&M building
design.
Hydrology What are the
min and max
water levels for
the reservoir?
The operating
water level range
affects the design
of the mooring
system and it
should be
considered at
detailed design
stage.
The water level of the Baor
varies between 1 to 10 m.
The proposed location for
pontoons has relatively
lower depth of up to 2 to
3 m.
N/A
Water level
measurements
available?
In order to verify
the minimum and
maximum levels
stated.
Not available. N/A
Are flow rate
measurements
available?
Necessary to
determine drag
loads on the floats,
and anchoring.
Not available. The water is
discharged through
controlled irrigation canal.
N/A
Wind speed
measurements
/ data
available?
Necessary to
determine wind
loads on the
panels, floats, and
anchoring.
1 – 2.4 m/s. Cyclone data is
unavailable.
Source: https://www.bamis.gov.bd/agro-
climate/normal/graph/windspeed
Floating PV Candidate Site Report
September 2020 │ Rev03 31
Criterion Sub-criterion Description Comment Evidence
Cyclone
occurrence?
Frequency of
cyclones at the
lake.
Frequency not known. N/A
Max wind
speed of
cyclone?
- Not recorded, but being
adjacent to Jessore, it can
be assumed to be the same
as 110 km/hr recorded in
1988 at Jessore.
Source: https://met.baf.mil.bd/front/doc/climate/jesclimate.pdf
Evaporation
rate
measurements
/ data
available?
Useful in
determining the
anticipated water
saving due to
reduced
evaporation.
Not available.
N/A
What are the
max. wave
heights on site?
Necessary to
determine wave
loads on the floats
and anchoring.
No high wave experienced. N/A
Flooding risk. Used to inform
assessment
anchoring design
options.
There were instances of
flooding in 2000, 2005,
2008, and 2015.
Source: Current status and barriers to fisheries co-
management: evidences from an oxbow lake of Bangladesh,
Md. Monirul Islam, Chandan Kar, Goutam Kumar Kundu,
Gouri Mondal and Mohammad Shahneawz Khan
Actual
discharge
drainage
system.
Reservoirs should
have spill-over
points.
Water is discharged through
one sluice gate at southern
end and a canal (not
controlled) at northern end.
N/A
Floating PV Candidate Site Report
September 2020 │ Rev03 32
Criterion Sub-criterion Description Comment Evidence
Water quality. Necessary to
assess possible
corrosion of
equipment and to
verify against
equipment ratings.
It is used for fishing and
expected to be non-
corrosive.
N/A
Depth of
reservoirs,
bathymetry.
Used to inform
assessment
anchoring design
options.
Bathymetric survey
undertaken by the national
consultant team. Coarse
measurement data will
need to be verified for final
anchoring design.
N/A
Solar
Resource
Measurements
of Solar
resource and
Temperatures
(yearly
averages).
Useful for Energy
Yield Studies and
system design.
No ground measurements
locally available. Satellite
data is suitable for energy
yield modelling.
N/A
Far shading
(e.g. Hills,
buildings, trees,
etc.)
To inform Energy
Yield Studies and
system design.
Not likely. N/A
Near shading
(buildings,
trees, poles,
fences, large
boats).
To inform Energy
Yield Studies and
system design.
The floating system will be
set up some distance from
shore, which avoids near
shading obstructions.
N/A
Floating PV Candidate Site Report
September 2020 │ Rev03 33
Criterion Sub-criterion Description Comment Evidence
Photographs
should be
taken, where
possible, of
west, south &
east to enable
a horizon line to
be mapped.
To inform Energy
Yield Studies and
system design.
- West:
South:
Floating PV Candidate Site Report
September 2020 │ Rev03 34
Criterion Sub-criterion Description Comment Evidence
North:
Local road
networks
Road Access;
can large (40
foot) lorries get
to site?
Assessment of site
suitability for
construction and
O&M.
The connecting road is
herringbone brick at one
end and to the water body
end it is earth road with a
very narrow (approximately
10 feet wide) steep sloping
road. The access facility
needs to be developed.
The access road connects
the assembly area to the
regional asphalt paved road
which is approximately 15 -
20 feet wide. Access is not
possible for a trailer but
small trucks can move
Floating PV Candidate Site Report
September 2020 │ Rev03 35
Criterion Sub-criterion Description Comment Evidence
easily. There are sharp
turns on the road. Materials
may be stored at Jessore
PBS Warehouse and
transported to site with
small trucks/vans.
Data network
access.
Assessment of site
connection to
BPDB
headquarters /
mobile phone
coverage etc.
Mobile phone coverage is
fair.
N/A
Construction
power and
water supply
and discharge.
Assessment of
power and water
requirements for
construction and
O&M.
Water is available from
lake. Power connection
may be extended from
0.4 kV line in close
proximity.
N/A
Impact of water
level changes
on access.
Assessment of site
for construction
and O&M (during
high water /
flooding).
During high flood the
assembly point may be
inundated.
N/A
Is site access
secured?
Site suitability for
construction and
O&M.
Not very secured inside the
Baor; the shore is
accessible to all. Need
N/A
Floating PV Candidate Site Report
September 2020 │ Rev03 36
Criterion Sub-criterion Description Comment Evidence
security for storage and
construction materials.
Preference for
overhead or
underground
lines?
Used to assess
Subproject costs.
Overhead line to be
constructed.
N/A
Floating PV Candidate Site Report
September 2020 │ Rev03 37
2.7 Conclusions
The site is considered to be technically feasible for a floating solar application, although it is noted
that the water body is currently leased by the local fishing community and negotiations will need to
take place with the leaseholders in order for the Subproject to proceed at the Baor.
The access to the site is considered unsuitable for large vehicles. However, the plant equipment
could be ferried to the site in smaller trucks from a warehouse located in the nearby town of Jessore.
Various geophysical and geotechnical investigations should be conducted in the confirmed location
where the floating platforms, inverter stations and anchors are to be placed. This is because,
although the overall geological structure of the lake has been assessed, it is expected that the
lakebed may vary from one location to another.
The feasibility study has included some measurements and investigations of the lake depth, as well
as the collection of water level data. However, it is considered that more detailed bathymetric
studies will be required at the final confirmed location before the Subproject is tendered. These
investigations are described in more detail in Section 3.1.3.
It is recommended that a suitable construction methodology is developed to ensure equipment can
be safely installed when it is launched into the lake from the assembly area.
Floating PV Candidate Site Report
September 2020 │ Rev03 38
3 Design Studies and Final Concept
3.1 FPV design considerations
A number of key considerations apply to FPV installations that are not relevant to ground or roof
mounted projects. These considerations are outlined below. It should be noted that these
considerations are in addition to those which would typically apply to a solar farm and recommend
the responsibility for the fulfilment of these considerations are placed with the EPC contractor under
the EPC contract.
High-density polyethylene (‘HDPE’) float systems are widely considered as safe for use in potable
water applications. However, the safety of the plant for application on any water bodies used for
drinking water should be confirmed at the tender design stage in consultation with suppliers and
with reference to any relevant local laws and regulations.
Although not a specific technical risk the Consultant would also recommend advice is taken on
appropriate insurance in the event of major failure or a catastrophic event such as flooding or dam
failure.
3.1.1 Behaviour of the structure in relation to movement of the water
The final design of the floating platform at Joydia Baor must take into account the changes in water
level as well as the expected velocity of waves during the monsoon season. Furthermore, attention
should be paid to the location of the anchoring system as the monsoon season is likely to carry
debris that may damage the mooring lines or the floating platform itself.
3.1.2 Design studies
Given the specific challenges affecting design and implementation of FPV systems, a number of
studies are required prior to the finalisation of the plant’s structural and electrical layouts, as
detailed in the following sections. It is noted that the nascent FPV industry is yet to standardise
testing and certification for the partially understood elements of FPV plants. These partially
understood elements include the following:
Selection and location of floating platform, considering construction, O&M and safety.
Selection and location of anchoring and mooring solution, considering construction, O&M and
safety.
The Consultant suggests that the floating element selection process is led by the developer. A
number of site studies should be prepared to be provided to tenderers, and tenderers should
produce Subproject specific design studies and installation and O&M strategies, focussing on
demonstrating how their technologies meet characteristics of the site and will be buildable and
operable over the Subproject lifetime. The Consultant suggests the following studies are performed
prior to tendering, but would suggest supply chain engagement to define whether any additional
studies would be valuable to tenderers to allow them to reduce costs or risks associated with
technology deployment:
Geotechnical study (discussed further below)
Identification of design wind, wave and water flow conditions and potentially other water quality
tests to identify any corrosion, microbial corrosion, or other risks represented by the water body.
Floating PV Candidate Site Report
September 2020 │ Rev03 39
It should be noted that the minimum and maximum wind resistance requirements for a floating
platform will be determined by a number of factors including inclination, final size of platform
and whether a rigid or flexible platform is chosen.
The choice of electrical layout fundamentally surrounds inverter positioning. The Consultant would
typically recommend inverters are placed onshore, to reduce cost and risk. In this feasibility report,
the Consultant has preliminarily placed the inverter and transformer stations (medium voltage
power stations or MVPS henceforth) on floating platforms near the PV arrays due to uncertainties
pertaining to the access of the surrounding land, which is privately owned and used for agricultural
activities. However, given the regular shape of the waterbody and the proximity to the banks, the
Consultant recommends that the option of locating the MVPS platforms onshore is explored
through appropriate community engagement and satisfactory compensatory measures to drive
down MVPS-related construction and operational costs.
The manufacturer confirmed that the SMA MVPS-2500 inverter station can be fitted with an oil
bund underneath the transformer to contain any leakages and avoid spillage into the water. While
dry type and cast resin transformers are commonly used in FPV applications, they are very
susceptible to weather conditions. They will require to be housed in a sealed enclosure which also
allows access. An alternative solution would be to utilise a transformer with biodegradable, natural
esters instead of oil. Oil or ester filled transformers have a longer life, higher reliability and the
insulating fluid provides an excellent medium to provide an understanding of the asset’s health.
However, there will be an increase in the cost of the transformer. The MIDEL 7131 is a
biodegradable synthetic ester which is readily biodegradable and exceptionally high moisture
tolerance and works well in a sealed or breathing transformer. Detailed transformer design will be
performed during the design phase.
3.1.3 Ground investigations
The geotechnical investigation step is vital for the success of any FPV plant. Typically, the work is
divided into three phases, with desk study performed to attempt to identify any red flags prior to
more costly intrusive investigations. It is noted that part of the Phase 1 has already been conducted
during the preparatory phase of the Subproject.
Phase 1: Desk study
– This phase involves gathering information from various sources, including scientific
literature, a variety of databases, with the purpose of assessing design options as well as
the planning of other phases.
Phase 2: Owner surveys
– Geophysical and bathymetric surveys
Depending on the level of desk-based information available, it may be necessary to
perform bathymetry and geophysical surveys to establish the shape of the lake’s bed
and soil structure across the site.
– Geotechnical surveys
This phase involves a combination of sampling for onshore laboratory testing and
offshore in-situ testing.
Phase 3: Contractor surveys
If possible, at a reasonable risk premium, the developer should attempt to have the contractor take
all ground risk. As such, Phase 2 studies would have been performed with the intention of providing
Floating PV Candidate Site Report
September 2020 │ Rev03 40
the developer and contractor with sufficient information to establish the feasibility of the Subproject,
without incurring undue costs. However, more comprehensive ground studies could be performed
by the contractor during construction in order to obtain sufficient information for full detailed design
of the anchoring, following the selection of the floating platform technology and considering any
further requirements or design specifications.
3.2 FPV construction methodology
The majority of construction tasks associated with an FPV project are similar or identical to a ground
mount project. Some specific differences worthy of consideration are discussed below. The below
sections focus solely on additional or different work which should be performed for an FPV project.
Construction of a solar PV plant requires safe and reliable access for large and heavy vehicles.
The bulk of the plant equipment is likely to be manufactured overseas and shipped to the nearest
port before being transported to site typically via road. It is therefore important to consider which
routes are likely to be used and the suitability of the existing infrastructure along those routes.
Joydia Baor is connected to the highway via the village road. Small trucks could access the site
bringing the PV system equipment and floats from a central warehouse based in Jessore. The
responsibility for the planning and execution of Subproject equipment transport and construction
traffic management would typically fall under the responsibility of the EPC contractor as part of its
scope of works.
3.2.1 Detailed design
The Consultant recommends the following studies are included as part of the Subproject’s detailed
design package when created by the contractor:
Analysis of hydraulic forces on anchoring system in extreme conditions.
Analysis of the fatigue to be experienced by the various parts comprising the mooring system.
Analysis of the maximum loading capacity of the mooring ropes.
We recommend any generic technology testing or bankability reports are provided at the tendering
stage and subject to careful review prior to selecting preferred suppliers.
3.2.2 Installation
Installation procedure is typically floater manufacturer/mooring system specific. Based on the
information gathered for Joydia Baor, both of the proposed assembly areas are considered to be
spacious, flat and allow for easy access to the water. The FPV platform sections would be
assembled in rows on shore and connected in small blocks prior to being launched into the lake
and towed to their final location by boat.
Final assembly and construction duration varies according to the available ground area for floater
assembly however an FPV plant of this capacity is expected to be completed within 5 – 6 months.
The plant can then be constructed with the dry season period (October to March).
The Consultant also recommends that temporary anchoring is utilised during the assembly process
to ensure that platform sections are not damaged by sudden change in wind or wave patterns.
Floating PV Candidate Site Report
September 2020 │ Rev03 41
3.2.3 Testing and commissioning
Due to the lack of standards in the industry, a number of additional tests are specified below. It is
suggested the following tests form the basis of any contractor’s inspection and test plan, however
it is noted this list is not exhaustive:
Fatigue tests on the chosen mode of floating island connection (e.g. connection pins, spreader
bars between floats, etc.) – required to ensure that means of float connections can withstand
the effects of repeated wave action. Low wave action places considerable strain on the
element’s connection the floating platform, which if not accounted for completely could
endanger the stability of the platform;
Anchor installation and pull-out tests – carried out to verify the results of the geotechnical study
and determine whether the anchors can withstand the maximum design loads. These are
typically carried out prior to construction commencement; however, we would recommend that
the designer provides alternative solutions based on the geotechnical study to ensure
construction is not delayed if the primary design proves to be unviable.
3.2.4 Operation and maintenance
O&M services for PV projects are typically undertaken by experienced O&M contractors, operating
under an O&M contract, based on a fixed scope of services undertaken for a fixed price, with
optional additional services undertaken at a pre-agreed price per event or hourly rates basis.
Attentive O&M practices are necessary in order to maximise system performance and availability
during operation, in addition to maximising the operating lifetime of the PV plant equipment, and
ensuring enforceability of manufacturer’s warranties, which may require a certain degree of
preventative maintenance to be conducted in accordance with the manufacturer’s guidelines.
The appropriate maintenance methodology depends largely on the final design of the plant. A
system layout that provides access floats between the module floats is more suitable in our view
as it allows O&M personnel easy and safe access. We would typically recommend that connection
points of the island, floats, and the anchoring system are inspected bi-annually.
O&M activities on site can be separated into preventative, corrective, and operational services.
Anticipated non-contracted maintenance expenditure should be considered separately within the
financial model; potentially large or uneven costs (such as inverter repair and replacement) are
typically accounted for within a maintenance reserve account (‘MRA’).
FPV specific activities relate to the floating platform and its mooring and anchoring system:
Visual inspections of all floats and fixings, at least annually;
Anchors and mooring lines should be inspected after the first strong wind incidence reaching
70-80% of the design wind speed, then after every stronger incident and as a minimum every
5 years;
Polyester mooring lines need to be replaced every 5 – 10 years;
Build-up of weeds and debris around floats and mooring lines should be assessed and removed
regularly, depending upon the aquatic culture and lake conditions. Where water hyacinth is a
known problem, then every two months is advisable.
Our experience on other FPV plants indicates that bird fouling can be a significant source of soiling.
Birds may use the floating platform to perch or nest. Like shading, soiling from bird fouling can have
Floating PV Candidate Site Report
September 2020 │ Rev03 42
a surprisingly large impact on generation and should be regularly assessed, considered in yield
estimates and managed as part of the O&M activities. A number of technological solutions designed
to deter birds are available. For example, there are solutions that make use of lighting, wire
deterrents and sound systems. The suitability of these solutions should be examined against their
cost. We recommend more than one system is used, preferably utilising auditory and visual
deterrents, to ensure that birds do not become accustomed to a single solution over the lifetime of
the plant. We recommend that the modules are cleaned 2 - 4 times a year.
3.3 FPV Subproject layout and electrical configuration
The configuration presented in the FPV concept design conducted for Joydia Baor is based on
bankable standard FPV technology. Hence, the technical specification of the system conceived is
based on currently available floating platforms, PV modules, and inverter stations, all of which have
been confirmed as suitable for FPV projects.
3.3.1 Site constraints
In FPV project design, the layout is relatively flexible such that multiple platform sizes can be used
to accommodate various shapes of lake. However, the simplest, most regular design options are
usually the most cost effective, therefore it is desirable to look for large, open expanses of water.
Although multiple locations have been considered initially, the final location of the platforms is
based on our desk-based review and essential inputs from local people, the national fisheries
expert and the safeguarding team. As a result, the Consultant is aware of the presence of thirteen
fishing grounds (locally known as ‘komors’). The location of the platforms is targeting a minimal
disruption to the local activities and livelihoods, therefore avoiding the aforementioned fishing areas
of the Baor. Figure 4 shows the thirteen komors as well as the ferry route across the Baor.
Floating PV Candidate Site Report
September 2020 │ Rev03 43
Figure 4: Komor locations
3.3.2 Final concept design
The concept design presented in this report features six similar FPV DC platforms. Preferably,
platform design should aim for simple shapes – regular squares or rectangles – bearing in mind
the prevailing wind direction to account for wind loads. In this case, a longer east-west axis would
enable increased mooring points to counter the effects of wind considering the south and southeast
prevailing winds of the region. Although the waterbody offers an open surface onto which locate
regular-shaped platforms, the presence of the aforementioned komors places conditions on the
available space. This represents the main constraint in terms of design. As a result, a bespoke
shape has been devised to:
Provide a longer east-west axis to allow for additional southern mooring points;
Avoid locating the platforms onto any current known komor location;
Optimise the surface usage ratio on the areas where platforms have been located; and
Maximise the system cumulative capacity given the great lake surface available while
maintaining a low total surface coverage.
It must be noted that this bespoke layout entails a downside consisting on a slightly more complex
mooring system that will feature crossing mooring lines. However, this is technically feasible and is
not expected to result into any technical challenge when the detailed design is conducted in due
course.
Floating PV Candidate Site Report
September 2020 │ Rev03 44
On the LV DC-side, the FPV array is conceived with a 9,072.0 kWp capacity, which consists of
22,680 x 400 Wp modules distributed in 840 strings of 27 modules across the six platforms. A more
detailed configuration description is provided in Table 4 below. As discussed above, location of the
platforms near to the banks of the lake does allow for onshore MVPS design. However, since all
surrounding land is privately owned and used for agricultural purposes, and in order to minimise
the impact of the FPV installation on the locals’ livelihood, the Consultant has considered floating
MVPS to be a satisfactory solution. Nonetheless, it is recommended that the alternative of placing
the MVPS onshore should be further explored in an attempt to drive down installation and
operational costs.
We note that the final concept design presented in this report assumes a system with central
inverters, however the use of central inverters is not a strict requirement and string inverters would
also be a technically acceptable solution, to be finalised within the EPC contractor detailed design.
The module row distance and tilt angle are specified in accordance with typical FPV technology
designs from a leading supplier. It is noted that the tilt angle of FPV systems is lower than normally
seen on ground-mount arrays; this design was developed to reduce wind loading on the platforms.
The typical dimensions can be seen in Figure 5 below.
Figure 5: FPV simplified diagram with module tilt and row distance
The gap between the floats carrying PV modules is unlikely to allow significant amounts of sunlight
to the water below, so it is recommended that dual glass PV modules are specified in order to
increase the light transmission. Most floating support platforms have gaps within their structural
design, such that between 40% and 75% of the water surface below the PV modules is exposed,
however the final spacing will be dependent on the choice of float manufacturer. It is considered
that the FPV layout proposed is not expected to pose a significant risk to the lake’s ecosystem as
the entire platform will cover only a fractional percentage of the lake. Examples of typical floating
platforms are shown in Figure 6, Figure 7 and Figure 8 below.
Floating PV Candidate Site Report
September 2020 │ Rev03 45
Figure 6: Example A of FPV platform design
Figure 7: Example B of FPV platform design
Floating PV Candidate Site Report
September 2020 │ Rev03 46
Figure 8: Example C of FPV platform design
The proposed FPV design features three AC floating skids – the MVPS platforms – totalling a
cumulative AC capacity of 7,500 kVA (at 50˚C). Each of these MVPS platforms collects 3,024 kWp
of module DC cumulative power. Given that each MVPS platform features an MV turnkey station
with 2.5 MVA central inverter coupled to an MV transformer and RMU (ring main unit) the resulting
DC:AC ratio is 1.21. Subject to ensuring that the suggested electrical design is adhered to, ratios
of up to 1.30 would be considered feasible through the increase of installed capacity.
Figure 9 below presents a satellite image with the FPV array layout super-imposed. The detailed
layout drawings are included in Appendix A.
Floating PV Candidate Site Report
September 2020 │ Rev03 47
1Figure 9: Joydia proposed 9 MWp layout with satellite imagery
2
The platforms cover large areas and have been located to minimise disruption on navigation and
fishing within the lake. Particularly, platform locations have been envisaged to minimise the
disruption on the ‘inner’ half section of the Baor, where fishing activity has greater presence.
For the purposes of this assessment, the Consultant has assumed regular yearly water level
variations. The aerial view presented in Figure 9 above represents the expected water level during
what is considered to be the most unfavourable part of the year, i.e. during dry season when water
levels are lower. However, this will need to be refined during more advanced engineering design
stages, once specific studies are available to confirm water level variation.
Whereas the final location of platforms is to be confirmed upon review of the bathymetric data, and
although locating MVPS onshore would substantially reduce O&M costs, the Consultant has
located all MVPS in floating platforms near the LV cable tray of the DC platforms. Key reasons are
summarised as follows:
Shorter distances between platforms and final MVPS locations are expected to reduce LV cable
losses; and
Uncertainties pertaining to land securement/control in order to accommodate the MVPS in the
banks near the PV platforms. Due to land being privately owned, planning complexity might
Floating PV Candidate Site Report
September 2020 │ Rev03 48
significantly increase to secure the required land for the MVPS installation onshore.
Additionally, the perception of the Subproject’s impact on the local community would also be
amplified.
Therefore, based on our desk-based assessment and data gathered through our site visits, the
Consultant has considered floating MVPS to be the simplest solution from a social point of view,
thus the most likely to be feasible.
It is anticipated that in addition to the temporary structures required during the construction phase,
permanent buildings will need to be placed around the site’s vicinity. These sites are expected to
have a small footprint and will serve as office space for site security and maintenance staff, as well
as for spare parts storage. Permanent jetties will also be required at intervals to allow access to
the floating platforms.
Table 4: Summary of main characteristics of the FPV conceptual design
Detail Design
DC platforms
DC capacity (kWp) 1,512.0
No. of platforms 4 2
Dimensions (m) (120.29 x 68.31) +
(120.29 x 53.99)
(120.29 x 84.07) +
(120.29 x 36.79)
Area covered (m2) 14,732.42 14,607.22
No. of modules 3,780
No. of combiner boxes 7
No. of strings per combiner box 20
No. of modules per string 27
AC platform
AC capacity at 50°C (kVA) 2,500
Approx. dimensions (m) 10.5 x 4.9
Approx. area covered (m2) 51.45
Overall installation
Total DC capacity (kWp) 9,072.0
Total AC capacity at 50°C (kVA) 7,500.0
No. of DC platforms (FPV) 6
No. of AC platforms (MVPS) 3
Total area covered (m2) 88,298.47
The system proposed also presents a mooring/anchoring configuration, which is indicative only and
is subject to change due to findings of the final stages of geotechnical testing to be undertaken by
the developer or the EPC contractor. However, there are several assumptions that have been
considered when designing the anchoring configurations. These are as follows:
A distance of the FPV platforms to the water body contours of 20m was respected in order to
allow for certain water level variations and ensure mooring lines can be designed with certain
slack. Water level variation data was not available at the time of drafting. The operating water
Floating PV Candidate Site Report
September 2020 │ Rev03 49
level range affects the design of the mooring system and it should be considered at the final
design stage;
Our concept is designed on the basis that submerged anchors will provide additional security –
ensuring that this critical component of any FPV installation is not accessible for unauthorised
personnel. It is anticipated that the soil conditions will be more uniform if all anchors are
submerged rather than having some anchoring points on shore;
Until suitable bathymetric data is available, an average depth of 5m has been assumed for any
area of the lake distant from the banks. A configuration, therefore, was devised with uniform
mooring line lengths, which would simplify the design when possible. However, it should be
noted that decisions about length of mooring cables and size on anchors cannot be determined
with any degree of finality prior to determining the manufacturer of the floating platform and the
results of the final design tests discussed above;
The preliminary layout is design on the basis that the most unfavourable water level situation
will be similar to the one presented in Figure 9, hence assuming anchors and mooring lines will
remain submerged, avoiding any potential interference with the floating MV cable pontoons
running along the ‘outer’ bank of the Baor. This risk is to be assessed during the detailed design
stage when accurate data concerning water variation levels is expected to be available.
No detailed data was available at the time of drafting. However, the Consultant is aware of the
prevailing wind being south and southeast. Accordingly, anchoring needs to be reinforced in
the southern side of platforms.
Other environmental conditions relevant to the design of the PV plants include geology, wind
characteristics and wave characteristics. Studies to define these conditions should be conducted
and results assessed at the next stage of design.
3.3.3 Auxiliary structures
It is anticipated that in addition to the temporary structures required during the construction phase,
permanent buildings may need to be placed in the site’s vicinity. These buildings are expected to
have a small footprint and will serve as office space for site security and maintenance staff, as well
as for spare parts storage. Permanent jetties will also be required at intervals to allow access to
the floating platforms.
Floating PV Candidate Site Report
September 2020 │ Rev03 50
4 Irradiation and Yield
4.1 Introduction
An energy yield assessment was undertaken for the Subproject. The analysis is based on a
capacity of 9.1 MWp for Joydia Baor, which is considered indicative.
The Consultant has taken the following steps to establish the energy yield for the Subprojects:
Acquired and analysed Global Horizontal Irradiation (GHI) and Diffused Horizontal Irradiation
(DHI) data from a range of databases;
Calculated a GHI and DHI profile based on the available data;
Uplifted the calculated GHI and DHI profile to establish the Global Inclined Irradiation (GII) as
appropriate for the Subproject location and module orientation;
Modelled the system configuration performance ratio and resultant first year specific yield
estimate;
Calculated combined uncertainties to give long term specific yield estimates at various
probabilities of exceedance.
Each step is described in the following sections.
4.2 Irradiation
4.2.1 Global and Diffuse Horizontal Irradiation
The global irradiance is the measure of the solar electromagnetic power in watts passing through
a surface of area 1 m2, expressed in W/m2, and is composed of both direct and diffuse (scattered)
sources. Global Horizontal Irradiation (GHI) is a measure of total energy incident on a horizontal
plane, or the irradiance (W/m2) incident for a period of time and is expressed in watt hours per unit
area (Wh/m2). Diffuse Horizontal Irradiation (DHI) is a similar measure, representing the energy
that did not arrive directly from the sun but that had been scattered on its path before hitting the
plane.
The irradiation is the energy source for a solar project and as such it is important that sufficient
data is collected for the sites in question. A location at the centre of the site was selected as the
point of interest for the irradiation assessment.
There are several representative databases available for the Subproject location that use
information from either satellite (along with other observations and models) or ground
measurements in order to estimate long-term average GHI and DHI values. The Consultant has
taken GHI values from the databases included in Table 5, which are described in Appendix B.
Table 5: Annual GHI from various sources
Data source Period Spatial
resolution (km)
GHI
(kWh/m2)
Difference from
WM (%)
Meteonorm 7.3 1991-2010 8 1,719 -1.9%
SolarGIS 1999-2015 1 1,702 -2.9%
3TIER 1999-2010 3 1,752 0.0%
Floating PV Candidate Site Report
September 2020 │ Rev03 51
Data source Period Spatial
resolution (km)
GHI
(kWh/m2)
Difference from
WM (%)
PV GIS
(SARAH)
2005-2016 6 1,869 6.7%
NREL SUNY 2000-2014 10 1,832 4.6%
Weighted Mean 1,752
The Weighted Mean (WM) value above has been weighted accounting for the number of years of
data available and inversely weighted based on the spatial resolution of each source. Each
parameter contributes 50% to the weighting. Along with the weighted mean, the weighted deviation
of each dataset relative to the WM value as well as the corresponding standard deviation has been
calculated. Details on the Consultant’s approach to assess long-term GHI is given in Appendix C.
For this site, above data sources result in a weighted standard deviation of ±3.5%, which informs
the GHI uncertainty analysis in Section 4.5.3 and Appendix F.
The weighted mean value of 1,752 kWh/m2/year has been selected for the continuation of our
irradiation assessment.
DHI values have been extracted from the databases detailed in Table 5, where available, and the
ratio of DHI to GHI calculated on a monthly basis. The weighting approach as adopted for the
calculation of the Weighted Mean GHI value is utilised for DHI ratios resulting in a weighted DHI
ratio to take forward for further analysis, these figures are presented in Table 6.
4.2.2 Global Inclined Irradiation
GHI and DHI values have been uplifted to GII using the industry standard Perez model. For the site
in question, we understand modules orientation to be facing due south. Monthly and yearly inclined
irradiations shown at the relevant inclination(s) in Table 6 can be expected.
Table 6: Monthly and yearly incident irradiation for the Subproject (kWh/m²)
Tilt -
azimuth
J F M A M J J A S O N D Total7
GHI 119 135 176 184 183 148 144 146 137 139 126 114 1,752
DHI 60 60 77 87 97 90 89 89 76 69 59 57 909
GII – 11°,
0°
135 149 187 187 181 144 141 146 141 151 143 131 1,836
We would consider that an inclined irradiation of 1,836 kWh/m2/year can legitimately be applied to
the site and this figure has been carried forward in the analysis.
7 Any apparent discrepancies in the annual totals arise because the monthly values have been rounded to the
nearest integer for display purposes
Floating PV Candidate Site Report
September 2020 │ Rev03 52
4.3 System Design
4.3.1 Modelled system design and approach
There are a number of losses associated with the harvesting of sunlight for the generation of DC
power and there are further losses in the conversion of DC power from the modules to the useful
AC power that feeds to the grid, the cumulative loss of which defines a project’s Performance Ratio
(PR).
These specific losses are dependent on the system design and key plant components. For this
Subproject, the modelled system design characteristics were based on communication with and
information provided by the Client. Details are summarised in Table 48 to Table 50 in Appendix D.
Each individual loss has been modelled taking into account the information provided (and
considered sufficient) and RINA proprietary models.
Some specific losses are influenced by factors which cannot always be quantified at an early stage
of a project. However, these should be considered in order to accurately determine the performance
of the whole Subproject. Should specific information be provided regarding those losses, then this
can be reviewed, and the figures adjusted accordingly. Below is a non-exhaustive list describing
some of these factors:
Variation in performance and efficiencies under real operating conditions;
Characteristics that vary due to the manufacturing and sorting process of PV modules;
Performance measurements that are not identified on standard data sheets;
Current technology in the PV industry;
Quality of design and installation method;
Power Factor different from unity or grid maximum export limitation.
In consideration of the above, the following assumptions have been made in relation to the
expected system design and installation:
Standard quality of the executed installation method;
General design and sizing criteria in line with quality standards. Quality standards include cable
voltage drop limits, cabin heating and ventilation, control and protection settings etc.;
Final configuration of Project equipment to be completed using a standard approach;
For the purpose of this yield the Consultant has assumed a Power Factor of unity (PF=1) at the
inverter level. There is likely to be a small amount of power factor required to overcome the
inductive losses of the electrical transmission from the inverters to obtain unity at the connection
point. We have modelled the most likely occurring power factor experienced on similar sites.
The inverters are capable of operating in the range of 0.8 leading to 0.8 lagging, however
running the site constantly at a PF 0.8 will make a significant difference in the losses. It should
be noted that in the event the grid operator requires the Plant to operate within this range, the
yield should be updated. This power factor may also impact the under-sizing loss for the higher
DC:AC ratios.
Where relevant PVsyst software (v6.75) is used, calculations are performed using hour-by-hour
irradiance and ambient temperature values generated for the site. The shading has been estimated
according to a 3D model. As this system is a floating photovoltaic (‘FPV’) system, the shading
model is flat. The uncertainties associated with the shading assumptions are considered in
Appendix F.
Floating PV Candidate Site Report
September 2020 │ Rev03 53
The yield is based on the site layout design developed by the Consultant, which connects strings
comprising of 27 modules along the length of the row. This configuration has been modelled
accordingly in PVsyst.
4.3.2 String sizing
Modules are connected in strings (a number of panels connected in series). A number of strings
may then be connected in parallel to an inverter. String and panel arrangements are determined
by the following factors:
The MPP voltage range of the inverter;
The highest MPP current capacity of the inverter; and
The maximum system voltage of the panels.
For this, the electrical characteristics of the strings and array are calculated for 70°C and 5°C8
module temperature and compared against the above parameters in order to ensure that the
Subproject is suitably designed.
A summary of the string configuration, power ratio, voltage and current compatibility of the string
arrangement are detailed in Table 7.
Table 7: System configuration
Array size
(kWp)
String
configuration
No. of
inverters
Power
ratio
(AC:DC)
Module Max.
voltage
compatible
Max.
current
compatible
9,072.00 280 strings of
27 modules
per SG2500-
HV-MV-20
inverter
3 1:1.21 JKM400
M-72L-V
ü
The AC:DC ratio is based on the nominal inverter power (2,500 kVA at 50°C), which is in line with
market standard practices.
The maximum voltage and current expected to be produced by the PV array has been calculated
considering the climatic conditions at the site, and was not found to exceed the operational limits
of each inverter. As such we consider the system configuration to be suitable.
4.4 Detailed Performance Ratio Calculations
4.4.1 PR Calculations
The PR has been estimated following the process outlined in the previous section and a breakdown
can be seen in Table 8; further details explaining these losses are included in Appendix E.
8 We have reviewed long term site temperature data and consider a minimum temperature assumption of 5°C
to be appropriate for this calculation for the Project location.
Floating PV Candidate Site Report
September 2020 │ Rev03 54
Table 8: PR Calculations
Description Loss
Far shadings 0.0%
Near shadings: irradiance loss 1.2%
Spectral 0.0%
Angular / IAM 2.0%
Soiling / snow cover 1.5%
Low irradiance performance 1.1%
Light Induced Degradation (LID) 1.4%
Module quality / power tolerance -0.6%
Module temperature losses 7.2%
Near shadings: Electrical effect 0.2%
Mismatch 0.5%
Ohmics, DC wiring 1.3%
Inverter efficiency 1.2%
Undersizing of the inverter 0.0%
MPPT performance 0.4%
Ohmics, AC LV wiring 0.2%
LV-MV transformer 1.5%
Ohmics, AC MV wiring 0.5%
Self-consumption 0.4%
Module degradation 0.2%
PR at PF=1 (at 100% availability) 81.4%
All subsequent yield calculations in this report are based on the PR modelled at the export meter,
located at the onsite substation. MV line losses have been computed based on the assumption of
33kV level connection point.
The calculated PR does not include any allowance for plant or grid availability losses.
For the purpose of this yield the Consultant has assumed a power factor of unity at the inverter
level. There is likely to be a slight power factor required to overcome the inductive losses of the
electrical transmission from the inverters to obtain unity at the connection point. A detailed review
to obtain this figure is outside of the scope of this report.
The Consultant has applied a soiling loss of 1.5% to the model, based on the site location and
satellite based precipitation data (MERRA 2 satellite data). Based on our experience of FPV
projects, we recommend that the modules are cleaned 2 - 4 times a year as a minimum, depending
on lake conditions.
We have conducted a literature review on module degradation with a focus on modern commercial
c-Si products. Following this review, a degradation rate of 0.4%/year is considered to be an
appropriate assumption for inclusion in the Subproject financial model.
Floating PV Candidate Site Report
September 2020 │ Rev03 55
For year one, we take the average degradation of 0% at the starting point and 0.4% at the end of
year 1. Therefore, for the purposes of modelling first year PR numbers a value of 0.2% has been
used.
4.4.2 Availability assumptions
This energy yield study assumes 100% availability of the plant. Final achieved availability will
depend on technical characteristics of the Subproject and the contractual guarantees, however a
value of 100% is unlikely to be achievable. It is noted that the FIRR and EIRR analysis has
considered availability separately to the energy yield figure.
It is recommended that a conservative estimate of grid availability is included in the final version of
the financial model, in line with local records of grid availability.
4.4.3 Yield estimations
Specific yield is a measure of the output of a PV system per unit of installed capacity (kWh/kWp).
It is a function of the irradiance experienced by a system, and its PR. Year one specific yield
calculations for the Subproject are shown in Table 9.
Table 9: Year one energy yield for the system
PR Installed
capacity (kWp)
Probability of
exceedance
Specific yield
(kWh/kWp)
1st year
production
(kWh)
81.4% 9,072.00
P50 1,495 13,563,495
P75 1,445 13,110,536
P90 1,400 12,702,858
Plant and grid availability has been excluded from our year one specific yield figures in Table 9.
The figures in Table 9 already contain an allowance for the first year’s degradation. For future years’
output we recommend that a linear degradation of 0.4% be applied. P75, and P90 numbers are
based on an uncertainty analysis outlined in Section 4.5.
4.5 Uncertainty Analysis
The uncertainties feeding into our yield analysis can be separated into three discrete parts:
Variation in year on year irradiation
Duration of forward modelling period irradiation variability
Uncertainties in the yield modelling assumptions.
Each of these uncertainties is discussed in turn below.
4.5.1 Long-term irradiation variability
Variability of irradiation is a key driver for the income of the Subproject. Long term irradiation data
from satellite-derived data from NREL SUNY was used to assess irradiation variability and details
are shown in Table 10.
Floating PV Candidate Site Report
September 2020 │ Rev03 56
Table 10: Satellite long-term time series data
Data source Years of
data
Standard
deviation
Standard error of
the mean
NREL Suny Satellite Data,
23.445°N, 88.942°E
15 1.2% 0.3%
4.5.2 Irradiation uncertainty over multiple years
Uncertainties associated with annual irradiation over a longer period of time are dependent upon
the number of years within that period. Over a longer modelling period, the standard error would
be expected to reduce. Additional uncertainties associated with various forward modelling periods
for are shown in Table 11.
Table 11: Standard error of irradiation data over various modelling time periods
Number of years Standard error of the mean
1 1.2%
10 0.4%
20 0.3%
4.5.3 Uncertainty in yield modelling assumptions
Uncertainties in the GHI, GII and PR modelling assumptions are shown in Table 12. A detailed
breakdown of these uncertainties can be found in Appendix F.
Table 12: Yield modelling uncertainty
Description Total for site
Modelling uncertainty ± 4.8%
The overall uncertainty in the yield modelling assumptions is calculated via the standard error
approach and corresponds to a value of ± 4.8%.
4.5.4 Combined uncertainties
The three uncertainties listed above are combined using the common standard error approach.
The overall combined uncertainty which will be applied to the calculated specific yield figures in the
next section for a 1-year, 10-year and 20-year period are shown in Table 13.
Table 13: Combined uncertainties over various modelling time periods
Uncertainties
Number of years being modelled 1 10 20
Standard error historic irradiation uncertainty 0.3%
Standard error irradiation uncertainty over time 1.2% 0.4% 0.3%
Standard error PR uncertainty 4.8%
Combined uncertainty 5.0% 4.8% 4.8%
Floating PV Candidate Site Report
September 2020 │ Rev03 57
4.5.5 Probabilities of exceeding estimation
Specific yields at varying levels of probability and over varying time periods may be calculated by
applying the factors in Table 14 below to the first year P50 value found in previous sections.
Table 14: Specific yield probability adjustment factors for year 1
Modelling period 1-year 10-year 20-year
Probability Level P50 1.00000 1.00000 1.00000
P75 0.96660 0.96756 0.96761
P90 0.93655 0.93836 0.93846
4.5.6 Yield probability calculation approach
The probability of exceedance factors for the various modelling periods shown in Table 14 are
statistical parameters used for Subproject financial modelling. These factors reflect the uncertainty
associated with the solar resource and its annual variance in addition to the analysis methodology
uncertainty for the estimation of the Subproject generation for year 1; e.g. a P90 is a downside
case that provides the PV generation with a 90% probability of being exceeded over the specified
forward-looking modelling period.
The modelling period solely accounts for the impact of the inter-annual variability and is not
inclusive of any module degradation; e.g. for a 10-year period, the inter-annual solar resource
variation is spread over a 10-year sample, so that low irradiation years are statistically offset by
high irradiation years within the 10-year period. The longer the forward-looking modelling periods,
the smaller the potential variance associated with the solar resource estimate.
Floating PV Candidate Site Report
September 2020 │ Rev03 58
5 Grid Assessment
5.1 Introduction
The grid impact study analyses the impact on the Bangladeshi network resulting from the
connection of a 9.1 MWp FPV plant at Joydia Baor. The FPV plant is proposed to include 3 x
2.5 MVA inverters and transformers installed in three platforms and the installation of medium
voltage floating cables between the floating platforms and the onshore station. There are two
possible options to connect the Joydia 9.1 MWp floating PV to the Bangladeshi distribution network:
1. Connect to the 33 kV bus of the Moheshpur-2 33/11 kV substation.
2. Connect to the 33 kV bus of the Kotchandpur substation;
From the physical perspective the best option is connecting to the 33 V substation at the
Kotchandpur substation as this is nearest to the site and will be the most economic option. This
requires construction of 9.33 km of OHL from the onshore station to the Kotchandpur substation.
The proposed route of the 33 kV overhead line will run along the public highway thus negating the
complications associated with the routing through private land.
Based on the GIS maps for the region it is understood that no 33kV OHL already exists along the
proposed route. It is recommended that a detailed survey be carried out in order to identify any
potential grid connection constraints along such a route.
The network model as obtained from the PGCB indicates low voltage at the Jhenaidha 132/33 kV
grid substation. The Khulna 230/132 kV substation transformer taps and Jhenaidha 132/33 kV
transformer taps were adjusted to maintain the Jhenaidha 33 kV bus at 1 pu. The voltage at the
Jhenaidha 132 kV bus is around 0.92 pu which is still below the planning limits for Voltage.
The Jhenaidha substation transformer taps were adjusted to the extreme to maintain the Jhenaidha
33 kV bus at around 1 pu during the maximum day demand. With the taps at the extreme position
during minimum demand the 33 kV bus voltage at the Jhenaidah substation will increase to 1.08 pu
which is above the planning limit. Therefore, it is suggested to equip the Jhenaidah transformer
with the AVC.
The total Kotchandpur feeder length to the Kotchandpur substation is around 19.5 km. The
Mohespur-3 (Sarotala) substation, which is under construction, will be connected to the
Kotchandpur feeder and is expected to have an initial load of 4 MW. With the connection of the
Mohespur-3 substation, the Kotchandpur voltage will further drop to 0.91 pu during the peak
demand, which is below the planning limits for voltage.
Therefore, it is suggested to install a capacitor bank of around 6 MVAr at the Kotchandpur
substation. With the installation of the capacitor bank, the Kotchandpur 33 kV bus voltage will
increase to 0.95 pu (with the Jhenaidha transformer taps at the extreme position) during day peak
demand and 0.97 pu voltage during minimum day demand (with the Jhenaidha transformer taps at
the nominal position).
Considering the connection option-2 i.e. connecting at Mohespur-2 substation, which is also fed by
Jhenaidha 132/33 kV substation, the total feeder length to the Moheshpur-2 substation is around
39.8 km and the total connected load on the feeder is around 35 MW. Therefore, the voltage at the
Moheshpur-2 substation would be even lower than the voltage at Kotchandpur substation and
hence below the planning limits.
Floating PV Candidate Site Report
September 2020 │ Rev03 59
The grid impact analysis was conducted for the preferred connection option of connecting at the
Kotchandpur 33 kV bus, which will be fed by the Jhenaidah 132/33 kV substation. The grid impact
analysis was conducted considering a 6 MVAr capacitor bank at Kotchandpur and the Jhenaidah
transformer equipped with AVC.
The grid impact analysis was checked against the Bangladesh Transmission grid code in the
absence of a Distribution grid in Bangladesh for compliance. The results of the load flow studies,
for the intact running arrangements comply with the planning limits and do not overload the
transmission lines.
The 3 x 2.5 MVA inverter design for the floating PV farm does not comply with the Bangladesh grid
code requirements for the reactive power capability at grid supply voltages from 0.94 pu to 1.06 pu
and hence reactive compensation support will be required. Reactive power compensation support
could be provided through STATCOMs, SVCs, Capacitor banks, synchronous reactors or
additional inverters. Increasing the inverter rating from 3 x 2.5 MVA to 2 x 2.75 + 1 x 3.0 MVA will
increase the reactive power capability of the PV farm and enables the floating PV to comply with
the grid code requirements.
Dynamic analysis of the Joydia floating PV plant was carried out to check its capability to remain
connected to the grid for various grid disturbances including under voltage, under/ over frequency
etc. The studies were carried out considering a generic model for the PV inverter and the protection
settings were also assumed to be in line with the proposed draft grid code requirements. From the
studies carried out, it is observed that the FPV plant is able to remain connected with the grid as
well as providing the required active/ reactive power support to the grid during the disturbances.
Furthermore, as the dynamic studies are carried out considering generic models of the PV
inverters, it is recommended that these studies are repeated during the detail design stage of the
Subproject with the actual OEM model of the PV inverters.
The sections below provide more information about each option.
Floating PV Candidate Site Report
September 2020 │ Rev03 60
5.2 Option 1
Figure 10: Grid connection at Moheshpur-2 substation
Jhenaidah
Jhenaidah 132 kV bus
132 / 33 kV 80/120 MVA transformers
Jhenaidah 33 kV bus
Other 33 kV feeders
33 kV OHL477 MCM 11.36 km
FPV
33 kV OHL12.2 km
33 kV OHL477 MCM 7.23 km
Kaliganj
33 kV OHL477 MCM 11.64 km
Kaliganj -1 (Patvila)
Mahespur -2 (Valipur)
33 kV OHL477 MCM 21.49 km
33 kV OHL477 MCM 15.34 km
Mahespur -1 (Voiroba)
FPV onshore station
Floating PV Candidate Site Report
September 2020 │ Rev03 61
5.2.1 Substation site
The Mohespur-2 33/11 kV substation is owned and operated by BREB and is located to the north-
west of the city of Jessore, and to the south of Joydia Baor.
The distance between the Mohespur-2 substation and the proposed landing site for the Joydia Baor
solar PV is approximately 12.2 km based on use of the public highway, and alternatively 9.5 km via
a straight-line path. Due to the complexity of obtaining planning permission for the use of private
land, the public highway option has been considered in all cases.
The substation site at Mohespur-2 consists of a typical outdoor busbar arrangement, being similar
to other BREB substations. With this arrangement the 11 kV and 33 kV busbars are supported from
the same structures, with overhead busbars run in parallel between the structures.
Tapping connections are then made to the transformers, with 33 kV droppers connected to an open
terminal transformer connection. The 11 kV transformer connections are connected in a similar
manner, with droppers connecting to open terminals on the transformers. There are seven
transformers located at the site; six being single phase and rated at 1.667/2083 MVA each, and
the fourth being three phase and rated at 5/6.25 MVA. It should be noted that there was no LV
supply to the fans therefore the lower transformer rating should be considered.
The transformers included a tap changer for voltage regulation; however it was noted that the
transformers required de-energisation prior to changing the tap position. Obviously, there was no
AVC available on site and therefore the majority of the voltage regulation was either undertaken
via the 11 kV system balancers or via voltage regulation of the 132/33 kV transformers at Jhenaidah
132/33 kV substation.
Protection systems were located within the 33 kV and 11 kV auto-reclosers, and therefore there is
no control room, or any outbuildings located within the site.
The site is considered to be in good condition, well maintained and clear of any vegetation. The
steel structures, busbars and switchgear were found to be in satisfactory condition, although
maintenance records were not viewed during the site visit.
5.2.2 Security of supply
The Mohespur- 2 33/11 kV substation is connected via a radial 33 kV overhead line circuit to the
Jhenaidah 132/33 kV grid substation. This overhead line is approximately 39.8 km in length, which
suffers an approximate average tripping frequency of 5.6 events per month. This value appears to
be average for the area concerned and the only real option to enhance the security of supply would
be to install ring feeder/s to the site which would increase the cost and complexity of the Subproject.
5.2.3 Physical connection
For the connection of the new 33 kV overhead line for the floating solar plant there was one spare
bay available, however due to the quantity of existing overhead lines within the site and the
congested nature of the site it would be difficult to connect a new 33 kV overhead line directly.
Therefore, it is proposed that the overhead line is terminated close to or inside the substation
boundary fence, cable sealing ends are installed, and the final section of circuit is terminated into
Floating PV Candidate Site Report
September 2020 │ Rev03 62
the substation via 33kV XLPE cable. A new auto-recloser will be installed and connected to the
busbar.
Figure 11: Proposed location of new 33 kV bay and cable sealing end
It should be noted that there was no SCADA control at the site, therefore, to ensure visibility of the
circuit breaker and ensure that the system is intact while operating the solar PV it may be necessary
to install remote monitoring and control. An alternative solution would be to have all the control
facilities at the solar PV site, with suitable islanding protection, therefore reducing the requirement
for controls at the Mohespur 2 substation site.
5.2.4 Cost
The Table 15 below shows the indicative cost of constructing the 33 kV overhead line and
connecting at the Moheshpur-2 33 kV substation. The cost of SCADA is also included in the cost,
but it is worth noting that installation of SCADA will improve the visibility and controllability of the
substation equipment and is not directly associated with the grid connection of the floating PV.
Table 15: Grid connection cost - Option 1
Items Cost (BDT)
12.2 km of 33 kV OHL (Linnet 336.MCM) 73,200,000
33 kV breaker (2 set) 6,542,000
SCADA 26,328,000
200m of 33kV Cable 1,566,000
Civils 5,600,000
Structures 3,227,000
Protection and control 2,000,000
Control cabling 500,000
Labour 2,000,000
Floating PV Candidate Site Report
September 2020 │ Rev03 63
Items Cost (BDT)
Sub total 125,963,000
Contingency 18,894,450
Prelims and design 12,596,300
Total 144,857,450
Floating PV Candidate Site Report
September 2020 │ Rev03 64
5.3 Option 2
Figure 12: Grid connection at Kotchandpur 33 kV bus
Jhenaidah
Jhenaidah 132 kV bus
132 / 33 kV 80/120 MVA transformers
Jhenaidah 33 kV bus
Other 33 kV feeders
Kotchandpur 33/11 kV
substation
33 kV OHL477 MCM 19.5 km
Kotchandpur 33 kV bus
FPV
33 kV OHL9.33 km
33 kV OHL477 MCM 2.83 km
Mohespur-3 ( Sarotala) substation ( under
construction)
33 kV OHL477 MCM
12 km(Under
construction)
5.3.1 Substation site
The Kotchandpur 33/11 kV substation is owned and operated by BREB and is located to the north-
west of the city of Jessore, and to the east of Joydia Baor.
The distance between the Kotchandpur substation and the proposed landing site for the Joydia
Baor solar PV is approximately 9.5 km based on use of the public highway, and alternatively 6.8 km
Floating PV Candidate Site Report
September 2020 │ Rev03 65
via a straight-line path. Due to the complexity of obtaining planning permission for the use of private
land, the public highway option has been considered in all cases.
The substation site at Kotchandpur consists of a typical outdoor busbar arrangement, being similar
to other BREB substations.
Tapping connections are made to the transformers, with 33 kV droppers connected to an open
terminal transformer connection. The 11 kV transformer connections are connected in a similar
manner, with droppers connecting to open terminals on the transformers. There are two
transformers located at the site, with both being three phase and rated at 5/6.67 MVA each. It
should be noted that there is no LV supply to the fans therefore the lower transformer rating should
be considered.
The transformers included a tap changer for voltage regulation, however there was no AVC
available on site therefore the majority of the voltage regulation is undertaken via voltage regulation
of the 132/33 kV transformers at Jhenaidha 132/33 kV substation.
Protection systems were located within the 33 kV and 11 kV auto-reclosers, therefore there is no
control room, or any outbuildings located within the site.
The site is considered to be in good condition, well maintained and clear of any vegetation. The
steel structures, busbars and switchgear were found to be in satisfactory condition with some
surface rust apparent, although maintenance records were not viewed during the site visit.
5.3.2 Security of supply
The Kotchandpur 33/11 kV substation is connected via a radial 33 kV overhead line circuit to the
Jhenaidha 132/33 kV grid substation. This overhead line is approximately 24.8 km in length, which
suffers an approximate average tripping frequency of 2.8 events per month. This value appears to
be lower than average for the area concerned and the only real option to enhance the security of
supply would be to install ring feeder/s to the site which would increase the cost and complexity of
the Subproject. It was noted that an alternate circuit ran within 200 m of this overhead line and
therefore a ring circuit configuration could be easily obtained.
5.3.3 Physical connection
For the connection of the new 33 kV overhead line for the floating solar plant, there was one spare
bay available, however due to the quantity of existing overhead lines within the site and the
congested nature of the site it would be difficult to connect a new 33 kV overhead line directly.
Therefore, it is proposed that the overhead line is terminated close to or inside the substation
boundary fence, cable sealing ends are installed, and the final section of circuit is terminated into
the substation via 33 kV XLPE cable. A new auto-recloser will be installed and connected to the
busbar.
Floating PV Candidate Site Report
September 2020 │ Rev03 66
Figure 13: Proposed location of new 33 kV bay and cable sealing end
It should be noted that there was no SCADA control at the site, therefore, to ensure visibility of the
circuit breaker and ensure that the system is intact while operating the solar PV it may be necessary
to install remote monitoring and control. An alternative solution would be to have all the control
facilities at the solar PV site, with suitable islanding protection, therefore reducing the requirement
for controls at the Kotchandpur substation site.
5.3.4 Cost
The Table 16 below shows the indicative cost of constructing the 33 kV overhead line and
connecting to the 33 kV bus of Kotchandpur. The cost of SCADA is also included in the cost, but it
is worth noting that installation of SCADA will improve the visibility and controllability of the
substation and is not directly associated with the grid connection of the floating PV.
Table 16: Grid connection cost - Option 2
Items Cost (BDT)
9.3 km of 33 kV OHL (Linnet 336.MCM) 57,000,000
33 kV breaker (2 set) 6,542,000
SCADA 26,328,000
200m of 33 kV Cable 1,566,000
Civils 5,600,000
Structures 3,227,000
Protection and control 2,000,000
Control cabling 500,000
Labour 2,000,000
Control room equipment 5,000,000
Floating PV Candidate Site Report
September 2020 │ Rev03 67
Items Cost (BDT)
Sub total 109,763,000
Contingency 16,464,450
Prelims and design 10,976,300
Total 126,227,450
5.4 Conclusion
In conclusion, Option 2 is the preferred option based on the following advantages:
Lower overall cost.
Shorter overall route compared to the Mohespur-2 option.
Better resilience due to lower average tripping frequency.
Possibility of obtaining a ring circuit configuration at a reasonable capital cost.
Nevertheless, it is noted that a disadvantage of this option is the lack of local control or SCADA
facilities, therefore the cost of the required SCADA upgrades have been included in the
recommendations.
Floating PV Candidate Site Report
September 2020 │ Rev03 68
6 Social Impact Assessment
6.1 Background and general socio-economic profile
Joydia Baor is situated in Jhenaidah District. The total area of the Joydia Baor is approximately 189
hectares in wet season and 150 hectares in dry season. The Baor has an approach road which
traverses though the villages. It is noted that the road is not paved and in general not in good
conditions. There are four villages within approximately 2 kilometres of the Baor, namely:
Balaramnagar (having 300 households);
Joydia (having 200 households);
Datiarkoti (having 60 households); and
Narayanpur (having 100 households).
Joydia Baor is a government-owned Baor, belonging to the district commissioner’s office and
fishing in the Baor is managed by the Department of Fisheries. Land in the surrounding area is also
government-owned and comprises mainly of agricultural use. Some of the local residents have land
in their possession but many are landless except for a small piece of land for their dwelling. Most
of the nearby dwellings are made of brick and tin and are considered semi-permanent in nature.
There are nearby schools, hospitals and there is drinking water available. Drinking water is mostly
taken from the tube wells. However, 50% of the households have their own drinking water tube
wells and the remaining 50% fetch water from their neighbours who have their own tube wells.
The Baor is primarily used for fish catching. In addition to fish catching, The district commissioner’s
office is the owner of the Baor but does not control it, the department of fisheries takes it on lease
and makes it available to the fishermen for fishing purpose, where there is a revenue sharing
mechanism among district commissioner’s office, department of fisheries and fishermen. The
annual target of fish catch is 90 metric tonnes. For the last five years, the target was achieved over
the yearly cycle. The executing agency for the Subproject is not yet known however the Subproject
is likely to be developed by the private sector.
People also use the Baor for bathing and cleaning clothes. Water from the Baor is used for
cultivation through pumping systems. The following section briefly describes the demographic and
socio-economic condition of the Subproject district as collected from secondary sources of data
(Bangladesh Bureau of Statistics).
Floating PV Candidate Site Report
September 2020 │ Rev03 69
Table 17: Area, households, population, density by residence and community
Area
[sq. km]
Total
households
Population - total
Population density
(Total population
per sq. km)
Total In household Floating
Jhenaidah 485,506 422,332 1,771,304 1,770,608 696 3.6
Sabderpur 6,584 5,313 22,321 22,307 14 3.4
Table 18: Distribution of households and population by gender, gender ratio, residence and community
Households Population Gender ratio
(Males /
Females) Total General Institutional Others Both Male Female
Jhenaidah 422,332 421,300 173 859 1,771,304 886,402 884,902 1.00
Sabderpur 5,313 5,310 2 1 22,321 11,356 10,965 1.04
Table 19: Percentage distribution of general households by size, average size, residence and community
General
households
Percentage of households comprising Average size
of
household 1 person 2 persons 3 persons 4 persons 5 persons 6 persons 7 persons 8+
persons
Jhenaidah 421,300 2.4 10.8 22.0 29.2 18.8 8.9 3.9 3.9 4.2
Sabderpur 5,310 1.8 9.3 22.9 29.7 19.8 9.2 3.9 3.4 4.2
Table 20: Percentage distribution of population by age groups, residence and community
All ages Percentage of population in the age group
0-4 5-9 10-14 15-19 20-24 25-29 30-49 50-59 60-64 65+
Jhenaidah 1,771,304 9.0 11.0 11.1 8.3 8.8 9.7 26.8 6.9 2.9 5.4
Sabderpur 22,321.0 9.1 10.6 11.1 8.6 9.3 9.9 27.1 6.4 2.7 5.2
Floating PV Candidate Site Report
September 2020 │ Rev03 70
Table 21: Percentage distribution of population aged 10 years and above by gender, marital status, residence and community.
Total
male
% Male Total
female
% Female
Never
married
Married Widowed Divorced /
separated
Never
married
Married Widowed Divorced /
separated
Jhenaidah 706,607 34.0 65 0.5 0 709,765 21 70.2 8 0.9
Sabderpur 9,085 33.6 66 0.7 0 8,836 20 70.8 8 1.4
Table 22: Distribution of population aged 7 years and above by literacy, gender, residence and community
Literate (can write a letter) Literacy rate (%)
Both Male Female Both Male Female
Yes No Yes No Yes No
Jhenaidah 741,905 791,076 386,228 379,335 355,677 411,741 48.4 50.5 46.3
Sabderpur 9,266 9,987 4,877 4,900 4,389 5,087 48.1 49.9 46.3
Table 23: Distribution of population aged 3-14 years by age groups, school attendance, gender, residence and community
Population aged 3-5 years Population aged 6-10 years
Attending school Not attending school Attending school Not attending school
Male Female Male Female Male Female Male Female
Jhenaidah 4,759 4,694 51,072 50,126 81,556 80,213 23,017 19,869
Sabderpur 88 93 659 593 952 918 309 258
Table 24: Distribution of population aged 15-29 years by age groups, school attendance, gender, residence and community
Population aged 15-19 years Population aged 20-24 years Population aged 25-29 years
Attending school Not attending
school
Attending school Not attending
school
Attending school Not attending
school
Male Female Male Female Male Female Male Female Male Female Male Female
Jhenaidah 41,604 34,290 35,106 35,949 12,553 6,887 54,180 83,104 2,657 931 75,674 92,167
Sabderpur 497 360 509 552 123 56 773 1,116 24 6 1,046 1,138
Floating PV Candidate Site Report
September 2020 │ Rev03 71
Table 25: Percentage distribution of population by type of disability, residence and community
Total
Population
Type of disability (%)
All Speech Vision Hearing Physical Mental Autism
Jhenaidah 1,771,304 1.6 0.2 0.3 0.1 0.7 0.2 0.1
Sabderpur 22,321 1.9 0.3 0.2 0.2 0.9 0.4 0.0
Table 26: Distribution of population aged 7 years and above not attending school by employment status, gender, residence and
community
Population aged 7+ and not
attending school
Employment status
Employed Looking for work Household work Do not work
Both Male Female Male Female Male Female Male Female Male Female
Jhenaidah 551,434 255,667.0 295,767 224,118.0 9,020 690.0 468 2,044.0 244,598 28,815.0 41,681
Sabderpur 6,258 2,993 3,265 2,607 86 7 3 17 2,690 362 486
Table 27: Distribution of population aged 7 years and above not attending school but employed by field of activity, gender,
residence and community
Population aged 7+, not attending
school and employed
Field of activity
Agriculture Industry Service
Both Male Female Male Female Male Female Male Female
Jhenaidah 233,138 224,118 9,020 183,835 2,530 10,484 1,373 29,799 5,117
Sabderpur 2,693 2,607 86 2,075 24 55 14 477 48
Table 28: Distribution of ethnic households, population by gender, residence and community
Ethnic Ethnic population in main groups
Households Population Tripura Barmon Chakma Others
Both Male Female
Jhenaidah 704 3,108 1,528 1,580 272 102 89 2,645
Sabderpur 10 41 22 19 - - 30 11
Floating PV Candidate Site Report
September 2020 │ Rev03 72
Table 29: Distribution of population by religion, residence and community
Total Muslim Hindu Christian Buddhist Others
Jhenaidah 1,771,304 1,601,086 167,880 975 28 1,335
Sabderpur 22,321 20,229 2,091 - 1 -
Table 30: Percentage distribution of general households by type of structure, toilet facility, residence and community
Number of
households
Type of structure (%) Toilet facility (%)
Pucka Semi-pucka Kutcha Jhupri Sanitary
(water-
sealed)
Sanitary
(non water-
sealed)
Non-
sanitary
None
Jhenaidah 421,300 15 29 52 4 24 33 37 5
Sabderpur 5,310 19 28 52 1 44 35 17 4
Table 31: Distribution of general households by source of drinking water, electricity connection and housing tenancy status, by
residence and community
Number of
households
Source of drinking water (%) Electricity
connection (%)
Housing tenancy (%)
Tap Tube-well Other Owned Rented Rent free
Jhenaidah 421,300 2 95 2 59 94 3 2
Sabderpur 5,310 0 99 1 68 98 1 2
Floating PV Candidate Site Report
September 2020 │ Rev03 73
6.2 Impact
The impacts of the Subproject are primarily related to fishing activities and are therefore more
significant for fishing communities and fishing families. A summary of impacts is listed below and
details of each type of impact are provided in the following sections.
Total area of the Joydia Baor is 189 hectares in wet season and 150 hectares in dry season.
This is a government owned Baor and fishing is managed by the Department of Fisheries;
There are four villages surrounding the Baor;
No land acquisition or involuntary resettlement are required by the Subproject;
There would be no impact on indigenous peoples as there are no indigenous peoples living in
the surrounding area;
Impacts are foreseen to be restriction on fishing areas leading to lack of fish production which
will have indirect impact on the whole fishing community in terms of loss of income from fishing,
thereby impacting livelihood;
The Baor is managed by government officials from the Fisheries Department with an annual
target for fishing; once the target is achieved, then the production is stopped;
There are 186 licensed fishing families who are involved in catching large fish;
Distribution of revenue is done among three parties as follows: 40% for the fishermen, 25% for
the District Commissioner and 35% for the fisheries department;
Additionally, informal fishing also takes place in the Baor which is for small fish using small nets
and usually done by the same people. Small fish is mostly used for daily consumption and
excess is sold in the market directly;
Cost related to fish breeding, security etc. is provided by the government;
Government land is available for other Subproject related facilities such as work shed,
maintenance, jetty area and assembly point. The land is available on the bank of the Baor with
less encroachment. Therefore, no land acquisition is required for associated facilities;
There would be approximately 9.32 km of 33 kV lines to be constructed; this will not require
land acquisition, however there may be some temporary impacts on loss of crops when the line
passes over paddy fields etc. which shall be avoided or mitigated during line construction;
The evacuation of power will be connected to the existing substation at Kotchandpur which will
not require any additional land acquisition.
The Subproject is categorised as “C” or possibly “B”9 for involuntary resettlement and ‘’C” for
Indigenous Peoples as per ADB’s Safeguard Policy Statement (SPS), 2009. A detailed social
impact assessment report is being prepared that includes possible mitigation measures and a
social management plan. The following subsections describe various potential social impacts of
the proposed Subproject on Joydia Baor.
6.3 Land acquisition and involuntary resettlement (permanent)
There will be no permanent land acquisition and involuntary resettlement for placement of the FPV
panels as the surface area of the existing lake will be used. The entire lake is government-owned
and belongs to Lands Department and local District Commissioner’s Office. The total surface area
9 Category B for IR is only for the temporary impacts in terms of loss of trees and crops for distribution lines and
other construction related impacts in terms of partial loss of income of the fishermen if not avoidable or else, the
Subproject will remain as C for IR category.
Floating PV Candidate Site Report
September 2020 │ Rev03 74
of the Baor in dry season is 150 hectares, of which around 88,144 m2 equivalent to 8.81 hectares
of surface water area will be used for the floating solar panel, this is about 5.88% of the total surface
area of the lake. There are no physical displacements or relocation resulting from the Subproject.
The Subproject requires small scale land for other associated facilities such as assembly area, jetty
area and security and maintenance of boat area, work shed / O&M /monitoring and security
building, storage container, cable landing point and switch gear cabin etc. All these facilities will be
built on the government-owned land. Therefore, there will be no compulsory land acquisition. The
impacts remain negligible because the land requirement is minimal; only around 138 m2 for all the
associated facilities (some only temporary) and this is not concentrated in one place. Details on the
land requirement and ownership of the associated infrastructure is provided in Table 32 below.
Table 32: Land requirements for associated facilities and infrastructure
Type of associated
infrastructure
Land area
requirement
(meter X
meter)
Type of
land
ownership
Impact on
land
acquisition
and
involuntary
resettlement
Remarks
1 Assembly area-
temporary
10 x 18 Government Nil There could be
possible
encroachment
of land use for
cultivation,
which is
minimal and in
case of such
impacts, the
losses will be
compensated
based on
direct
negotiation
prior to
construction.
2 Jetty area - security &
maintenance boat
area
1 x 5 Government Nil
3 Work shed / control,
O&M and security
building
8 x 3 Government Nil
4 Storage container 6 x 3 Government Nil
5 Cable landing points
area
1 x 2 Government Nil
6 Switch gear cabin 3 x 3 Government Nil
Note: The Work Shed, used to store tools and equipment during construction, can subsequently be used as the
O&M Building during the operation phase of the plant. The O&M Building will be required for the security and
maintenance staff. It will house the SCADA monitoring system (desk computer and monitor etc.) as well as any
tools and cleaning equipment. During construction, the storage container will be used to house daily deliveries of
the floaters, any assembly kit and PV modules.
6.4 Impacts due to grid connection / evacuation lines (temporary)
The power will be evacuated at a 33 kV voltage line. There will be a total of 9.32 kilometers of 33 kV
line that will be constructed to evacuate the power from the FPV. The 33 kV line is a pole-based
line which does not require any land acquisition. There will be approximately 40 poles which will be
constructed. There is no such right of way reserved for the 33 kV line. The line will mostly pass
through the Baor area, roads and in some places through the agricultural fields. The agriculture
Floating PV Candidate Site Report
September 2020 │ Rev03 75
field is partly government owned land which is part of Baor and some public land being used for
paddy cultivation. There could be some temporary impacts during the construction in terms of loss
of crops. There could be loss of some trees or trimming of some trees. All of these impacts are
construction-related and will be compensated, if unavoidable, during the construction phase
through consultation with the people. Furthermore, impacts can also be avoided by choosing off
season as the construction period. The evacuation line will be connected to the existing substation
at Kotchandpur where land is available for the transformers. Therefore, there will be no impact in
terms of land and resettlement for the transformer.
6.5 Indigenous Peoples
Indigenous Peoples or Upajati do not live in the vicinity of the Joydia Baor area, therefore there will
be no corresponding impacts. The population in the Subproject area is predominantly of Muslim
people and there are some Hindu communities also but no Upajatis live in the Subproject area.
6.6 Impact on fishing and livelihood
The Baor is owned by the government, belonging to the Department of Land and under the
management of the District Commissioner. The Baor is primarily used by the local people for
fishing. The water is fished intensively and provides food and income to the Baor population. The
Subproject has the potential to impact on fishing livelihood by reducing the area available for fishing
activity and restricting access to fishing grounds. However, as mentioned above, the total coverage
of the Baor for the Subproject’s solar panels is about 5.88% of the surface water. The fishing is
managed by the Department of Fisheries. Licenses are issues to fishermen. There are 186 licensed
fishermen who are eligible for catching the big fish using big nets. The license fee is BDT 460 per
year. Fish breeding and providing security is managed and handled by the department of fisheries.
There is an annual target of 92 tons of fish catching and beyond that the fishing is not allowed.
Once the target is achieved, fishing is stopped. Therefore, the income of these fishermen is limited.
The earnings and revenue from the fish selling is divided according to the following proportions:
40% for the fishermen, 25% for the District Commissioner and 35% for the Department of Fisheries.
In addition to the big fish catching, there are people who prefers to catch the small fish using small
nets where they do not have to take permission from the Department of Fisheries. They can sell
those small fish in the market and can use for their daily intake also. There is no such registered
society for the fishermen in the case of Joydia since the Baor is managed by the Department of
Fisheries. The Subproject has the potential impact of lower fish production due to the reduced size
of fishing area, and this would indirectly cause a loss of income. Fish stock of Joydia Baor is
described in the Table 33 below.
Table 33: Fish stocking in Joydia Baor
Sl. No. Local Name/English Name Scientific Name Stocked Amount
1 Rui Labeo rohita 1.50 MT
2 Catla Catla catla 1.50 MT
3 Mrigel Cirrhinus cirrhosus 1.50 MT
4 Silver Carp Hypophthalmichthys molitrix 8.00 MT
Floating PV Candidate Site Report
September 2020 │ Rev03 76
Sl. No. Local Name/English Name Scientific Name Stocked Amount
5 Common Carp Cyprinus carpio var. communis 1.50 MT
6 Mirror Carp Cyprinus carpio var. specularis
7 Black Carp Mylopharyngodon piceus 100.00 Kg
8 Grass Carp Ctenopharyngodon idella 2.00 MT
9 *Chital Chitala chitala 160 Nos.
Total 16.10 MT
*Chital is introduced for the first time to check their growth performance and production.
The average annual income from fishing, as per the socio-economic surveys is found to be
75,220 BDT per fishermen family. Placing of FPV will cause temporary restriction to the access
during construction at the water’s edge and in the Baor area when assembly of the floatation units
and solar PV panels is taking place. However, the restriction is partial and temporary and people
will still have the access to Baor for their use. During operations, with up to 5,88% coverage of the
Joydia Baor surface by PV pontoons, there is the potential for a reduction in fish habitat and fish
catches, and impacts to the fishing resource of the Baor. After the Subproject’s construction, the
solar panels may cause restriction to fishing due to fish taking shelter under the panels. Fishermen
will be negatively impacted, though the impacts are not significant and is partial loss of income due
to the Subproject.
6.7 Social, poverty and gender
The impacts are expected to be positive in terms of additional power generation and enhanced
power supply in Bangladesh in general. Subproject beneficiaries are those that will directly benefit
from the reliable power supply to be generated from the proposed floating solar which will be
harnessed in addition to the existing conventional source of power generation. The beneficiaries in
the Subproject are general and thus it will positively impact the country as a whole, with indirect
benefits to local consumers including domestic, agricultural, commercial and industrial sectors.
Additionally, the Subproject shall provide some temporary job opportunities during construction.
The Subproject will improve power sector reliability in Bangladesh. It will therefore indirectly
contribute to poverty reduction through more reliable electric services to the households. Under the
Subproject, improved and uninterrupted power supply will result in increased agricultural,
commercial and industrial activities contributing to economic growth in general, however this may
not have any direct positive impact to the local area. It is expected to have a positive impact and
improve the quality of life of the local population, including vulnerable groups, and minimise power
shortage. An adequate electrical power supply is essential for achieving sustainable economic
growth. With improved and uninterrupted power supply the Subproject will directly and indirectly
contribute to poverty reduction at local level, through: the creation of unskilled/semi-skilled
employment during the construction phase; income generation and livelihood activities associated
with the business; and minimisation of load shedding. The economic growth, particularly through
commercial and industrial activities, will contribute to the country’s gross domestic product. With
effective mitigation measures the negative impacts on the fishing communities can be minimised.
The Subproject will have a positive long-term impact on the country’s economy and living standards
of the population.
Floating PV Candidate Site Report
September 2020 │ Rev03 77
Women in the Subproject area are generally engaged in household activities. Women are equally
involved in the decision-making of the family and also contribute to family income when feasible.
Women were participants during the general consultations. Special focused group discussions
were conducted during the feasibility studies and women viewed that there are no such negative
impacts to them due to the Subproject. It is understood that there is no female labour work within
the fish landing station. Female labour mostly consists of crop cultivation and household activities.
There will be no negative impact on women due to the floating solar projects. Women may be
trained, and they may find opportunities to take part in the Subproject operation. Should any
negative impacts occur during the Subproject, they will be mitigated, and women will be given
special attention.
6.8 Other impacts
People living adjacent to Joydia Baor use the Baor water for bathing, cleaning clothes and
occasionally for cooking, though they do not use it for drinking. In addition, they use the Baor water
for their animals.
Water from the Baor is also used for agriculture through pumping. There are tube wells for water
intake. The Subproject will not cause shortage of water and there will be no such hindrance to
water use due to the Subproject. However, during construction, special attention needs to be given
to ensure water accessibility is not disturbed.
6.9 Public consultations and findings
Initial consultation was conducted informally with the villagers and the fishermen and particularly
with the fishing community in the month of December, 2019. There was participation of both men
and women in the consultation meetings. Additionally, formal consultation meetings was also held
with multi stakeholders in the month of February, 2020. The response of initial consultations from
the public are related to the fish catching of the Baor and possible loss of fish catch and loss of
income due to the proposed Subproject. Most of the people were partially aware about the
Subproject as they had witnessed various technical surveys being undertaken. The public were
generally curious about the Subproject and raised concern about their fishing activities. During the
multi stakeholders’ formal consultation, people raised concerns and was not supportive of the
Subproject and mostly opposed to the plan because of restriction to fishing and income. People
focused more on to the use of unused filled in land and dredging it to make it waterbody and placing
the panel without interfering existing Baor. However, it was clarified that dredging or excavation
has adverse environment impacts and also to the water body and this is not the scope under the
Subproject to excavate and put panels. Necessary mitigation measures were discussed. Core
findings of the consultations are presented below in Table 34.
Floating PV Candidate Site Report
September 2020 │ Rev03 78
Table 34: Findings of Consultations
Issues Discussed Views of the People/Suggestion
I. Informal Consultation with villager especially the fishermen at Joydia Baor (December, 2019)
Awareness about of the Subproject.
Baor management and dependency on Baor.
Fishing Activities.
Potential threat to the people due to Subproject.
Potential benefits.
Expectation from the Subproject.
Suggestive Measures.
Impact on livelihood and compensation expectation.
Support to the Subproject.
Suggestion and Recommendations.
Some people were not aware about the Subproject. However, the initial consultation
is perceived to be beneficial to the local community as they got to know about the
proposed Subproject.
In general, people are neutral as far as their support is concerned. Support for the
Subproject was expressed given that it is the country’s plan and government will
manage the Subproject. On the other hand, they do not see any benefit to the local
people and do not support the Subproject.
People fear that fishing activities will be disrupted if adequate mitigation is not taken.
Loss of fishing will led to loss of income and livelihood.
People suggested that there are dry areas (near Balaram Nagar village) which can be
dredged and can be used for the pontoons so that Baor is not affected. However, this
was clarified that dredging is not within the Subproject scope.
People expressed concerns that fish would be hidden under the pontoons area, which
would restrict the fishermen’s access to fish.
People also highlighted that the fishing families have small land holding or may be no
land holding and they mostly depend on the Baors.
People suggested future consultation and engagement of people during detailed
planning and construction.
People suggested that all the losses should be assessed properly and should be
mitigated with an action plan and shall be compensated.
II. Formal Consultation with multi stakeholders such as Personnel of REB, UNO Kotchandpur Upazaila, Member of Fisheries Department, Baor
Mangement, Chairman and Member of Union including local people, Fishermen of Joydia Baor. (February, 2020)
Awareness about the floating solar Subproject. 50% of the Stakeholders and aware of floating solar Subproject on the Baor.
Floating PV Candidate Site Report
September 2020 │ Rev03 79
Issues Discussed Views of the People/Suggestion
Support to the Subproject.
Baor management and fishing pattern.
Impact on land and other assets.
Impact on crops due to evacuation line.
Socio-economic activities.
Construction related impacts and concerns.
Current electricity supply and reliability.
Potential benefits.
Potential losses.
Critical issues.
Compensation issues.
Suggestion and recommendations from the people on
Subproject implementation.
Presence of local NGO and CBO.
People strongly opposed the Subproject, as they think that the Subproject will have a
direct negative impact on the livelihoods of the fisherman. Presently, silt accumulation
declined the area of Baor. Excavation of bottom soil as well as the peripheral area is
the priority at this stage, then floating solar will be welcomed by the local people.
If excavation is done, the people will voluntarily cooperate in the implementation of
the Subproject. However, it was clarified that excavation is a separate subject which
may not be applicable to the current Subproject scope.
Availability of land for small scale Subproject activities is not a problem and people
viewed that the land belongs to the Baor.
Various economic activities as mentioned by the people are Fishing, agricultures,
business, service, cottage industries etc.
Regarding the evacuation line, people are in favour of upgrading the electrical
network. Female participants reported that there is no street light which restrict their
mobility after sunset. There is no problem if the line passes along the roadway and
along the pathway.
Regarding any loss, people expect cash compensation for small loss in terms of
crops and trees due to the evacuation line.
Participants said that they are involved in fishing form their childhood. They do not
know any other work to earn their livelihood. They said that they do not want this
Subproject to take place in the Joydia Baor.
People viewed that Putting solar panel on the Baor water will occupy an area of the
Baor. Hence, fishing area will be reduced.
While asking about the suggestion for continued fishing during and post
implementation of the Subproject, people suggested the following:
- Development of the Baor including removing deposited soil by excavation,
protecting shore from land sliding etc. is needed.
- Providing job to the fishermen or compensate by cash, during construction.
- After construction, allow the fishermen to catch fish within the solar panel area.
Floating PV Candidate Site Report
September 2020 │ Rev03 80
Issues Discussed Views of the People/Suggestion
- There is one inlet and one outlet. Fish movement should be restricted through this
inlet and outlet, by constructing sluice gate.
- If fish production reduces due to floating solar panel, then the authority will have to
grant subsidies or compensation or alternatives to the affected fishermen.
As far as the positive impact is concerned, people viewed that no environmental
pollution as electricity will be produced using renewable energy which will meet the
local power demand.
Negative impacts are perceived to be many such as the Subproject will occupy fishing
areas. It will reduce production of captured fish. In addition, fishing activity will be
interrupted. Fishermen were concerned that fish will hide below the panel and
fishermen will have less access to fishing activities.
People further suggested that Excavation of the filled-up land is very important at this
point. Because of excessive sediment water surface of the Baor is shrinking day by
day.
The participants will welcome the Subproject and will be cooperating during the
implementation, subject to the excavation of Baor prior to the start the Subproject.
Each of the pontoon of PV panel needs security light/fog light and security tower.
Other issues suggested by the people are: every year water hyacinth covers a large
part of the Baor. Local fisherman requested to introduce new technologies to inhibit
the growth of the aquatic nuisance.
Floating PV Candidate Site Report
September 2020 │ Rev03 81
6.10 Conclusion and recommendations
The Subproject will have some negative impacts in terms of loss of income and livelihood due to
restriction of water use for fishing. However, some local employment will be generated temporarily
during construction. Based on the assessment and also suggestions from the local people, various
conclusions, suggestions and recommendations are provided. Suggestions and recommendations
are provided below and a social management plan for mitigation measures is provided in Table 35.
The Subproject planning shall avoid fishing areas and shall use the surface water where there
are no fishing activities;
The Subproject shall not take more than 10% of the surface area. If possible, dredging options
shall be explored if no adverse environment impacts. However, dredging seems to be
unlikely; and
People expect some direct benefits from the Subproject. This requires adequate mitigation
measures for uninterrupted fishing activities and any loss in the future shall be compensated
and mitigated by the Subproject.
Floating PV Candidate Site Report
September 2020 │ Rev03 82
Table 35: Social Management Plan
Predicted Impacts Intensity Mitigation Measures Responsible
Agencies
Timing
Land acquisition and involuntary
resettlement
None Negotiation with land department and
Baor authority with due consultation with
local people
No monetary compensation required
Private developer
through SREDA
Prior to construction
and during
construction
Temporary impacts due to
construction of evacuation line
Low Consultation with local people
Consultation with BREB
Line route to mostly follow along the
road and Baor area without interfering in
to agricultural land or habitat area and
also construction to commence during
off the crop season.
Cash compensation for loss of crops
and trees if damages are not avoidable
during construction
Private developer
with assistance from
SREDA and BREB
Prior to construction
and during
construction
Impact on indigenous peoples None Not Required as no indigenous peoples
are to be impacted
Not Applicable Not Applicable
Impact on fishing and livelihood
(For the Fishing Community as a
whole consisting of 186
fishermen families)
Medium Compensation by providing 20% of
additional cash grant to their current
40% share from fish income for the
entire life of the Subproject to be borne
by the Subproject developer
Construction of two grill gates to avoid
outward fish migration which shall be @
1 million Tk per gate equivalent to a total
Private developer
through SREDA
Prior to construction
and during
construction
Floating PV Candidate Site Report
September 2020 │ Rev03 83
Predicted Impacts Intensity Mitigation Measures Responsible
Agencies
Timing
of 2 million Tk to be borne by the
Subproject developer
Cash grant for fish feeding
Sufficient distance between each block
of panels so that fishing activities will be
continued
Avoid construction during fish breeding
Studies to identify potential in fish
growth and fish production
Continued consultation
Potential engagement of local people
during Subproject construction
Decrease in surface water due to
floating solar panel
Medium Liaise with Joydia, fishing committee
and local people and technical team
Catchment management and siltation
management
No construction work during monsoon
while fish breeding starts
Private developer
through SREDA and
Baor management
As soon as possible
based on final design
Impact on approach road None Rehabilitation of approach road Private developer
through its contractor
Prior to construction
Others in terms of continuous use
of Baor water for various human
consumption
Low Water quality to be maintained safe and
shall not be diluted
Private developer
through its contractor
During construction
and operation
Floating PV Candidate Site Report
September 2020 │ Rev03 84
7 Environmental Assessment
7.1 General
Joydia Baor is an oxbow lake with a dry season area of 150 ha situated in Kaliganj, Jhenaidah
District. It has the typical crescent shape of an oxbow lake being 6 km long and having a width of
250-400 m. Approximately 80% of the land around the lake is developed with the lake frontage
being occupied by village housing and homestead gardens stretching down to the water’s edge.
Encroachment has occurred at the lake over a number of years as water levels have receded.
Housing is mainly of a semi-permanent nature and while some village houses are constructed in
concrete, the majority are made of tin and mud.
Agricultural land is principally given over to jute cultivation, but rice and vegetables are also grown
along with local fruit trees (guava and banana). In addition, commercial timber trees (teak and
mahogany) are also grown. Water is pumped to irrigate crops with many water pumps around the
Baor and two canals are directly connected to the Baor. Water hyacinth is present on the lake
surface, particularly in the south, which hampers movement and activity through the water.
The Baor is widely used for washing and bathing by many in the wider lakeside community; people
also use the water for cooking and washing their clothes. The Baor area is very much modified and
changed by human activity.
There is a regular boat service route connecting the communities on the east and west banks of
the Baor.
There is intensive use of the Baor for fishing, principally from three main villages located to the
north with 13 organised and registered fishing groups. Fishing provides an important source of
income and food for people living at the Baor.
The Subproject consists of floating pontoons supporting PV (photovoltaic) cells on the Joydia water
body with inverters and transformers on floating platforms and with underwater cables to bring
power ashore. The Subproject will need to have supporting infrastructure to connect to the
Bangladesh National Grid. This involves the construction of 9.325 km of 33 kV transmission line to
evacuate power to an existing substation at Kotchandpur where land will be available for the
installation of transformers and for a bay extension. Land will be required for a temporary storage
container for daily deliveries of the floatation units and PV modules prior to assembly, and land is
also required at the water’s edge for final assembly of the floating facility prior to positioning of the
panels on the lake. There will be a need to identify land for a work-shed/jetty. The work shed, used
to store tools and equipment during construction, can subsequently be used as the O&M building
during the operation phase of the plant. The O&M Building will be required for the security and
maintenance staff. It will house the SCADA monitoring system (desk computer and monitor etc.)
as well as any tools and equipment required for cleaning and de-weeding, general maintenance
and operations as well as security on the pontoon floating structures during operations. Currently
it is intended to use land on the north east shore of the Baor to accommodate temporary and
permanent Subproject activities.
Floating PV Candidate Site Report
September 2020 │ Rev03 85
The new evacuation/transmission line will follow existing roads and thereby avoid crossing private
farmlands.
The Implementing Agency for the Subproject will only be decided following the acceptance of the
Feasibility Study.
7.2 Potential environmental impacts and mitigation measures
The potential environmental impacts associated with the Subproject have been identified and are
discussed below along with potential mitigation measures and recommendations.
7.2.1 Potential land loss
There will be need to occupy land temporarilly during construction. Land will be required for such
purposes as:
Assembly of the PV panels and floatation units at the lake side – an area approximately 1000 m2
is required;
Access to establish the associated 33 kV power evacuation line between the floating solar
facility on the lake and the designated Kotchandpur substation; and
Possibly for a workers camp.
The land at the edge of the Baor is much encroached upon by land users but is government land.
The land required for panel assembly on the eastern shores of the Baor is government land and is
available for construction activities.
The power evacuation line (9.325 km) to link to Kotchandpur substation is pole based
(approximately 40 poles) and will be through some lake and road side villages with potential
temporary loss of trees and crops. These impacts are construction related and will be compensated
for if unavoidable through consultation with the public. There is space at Koatchandpur to
accommodate a 3 m x 3 m switch cabin gear to link the Subproject to the grid system.
For the operations phase some land will be required permanently for such things as the
establishment of a secure area on the lake shore for the SCADA monitoring system, a boat for de-
weeding, cleaning and security equipment (Table 32). Government land in the ownership of Lands
Department and District Commissioner’s Office is available for Subproject infrastructure. The Social
Impact Assessment study finds that there will be no permanent land acquisition or involuntary
resettlement as a result of the Subproject. The land required for the Subproject for permanent
facilities is just 58m2.
As the solar arrays, inverters and transformers are designed to be stationed over water, the overall
amount of land required for the Subproject is small by comparison with other power generating
projects and there is likely to be a relatively small land based environmental impact only. Any
temporary losses during construction (e.g. loss of income from destruction of crops and trees) will
be settled through agreement. There will be environmental impacts to the water lake system (to
human activities and to aquatic systems which are discussed below in Chapters on Potential Loss
of livelihood, food and ecosystem services and Changes to water quality at the lake.
No private land acquisition is required for the Subproject.
Floating PV Candidate Site Report
September 2020 │ Rev03 86
7.2.2 Impacts on Indigenous People
The Social Impact Assessment (SIA) finds that there is no impact on indigenous people as
indigenous people or “Upajati” do not live in the vicinity of the Joydia Baor area. The Subproject
area is dominated by a majority Muslim population with some Hindu population particularly around
the Baor.
7.2.3 Potential loss of livelihood, food and ecosystem services
The Subproject will cause some small loss of access during construction at the water’s edge and
in the lake area when assembly of the pontoons and solar panels is taking place and they are towed
into place on the Baor. During operations with up to 5.8% of the dry season surface area covered
by panels, there is the potential for a reduction in fish habitat and impact to aquatic systems. The
panels may interfere with fish breeding and the ability of fishermen to catch fish and access to
fishing grounds.
The Joydia Baor is fished intensively and is an important source of livelihood for local fishermen
and an important source of food for village populations around the Baor.
The Subproject, therefore, has potential to have impacts to fish production and fishing livelihood
and there is expectation by affected people and stakeholders for compensation for this loss.
Fishing is undertaken at two levels:
Organised large scale community fishing: (186 licensed fishing families) who operate a
commercial type operation using large nets to catch larger fish: they guard the Baor to prevent
illegal fishing. Members are divided into 13 groups and each group is responsible for
management of one Komor or local fishing ground;
Small scale fishing, undertaken by the same group of fishermen to catch small fish for their own
consumption and as a source of income. They catch small indigenous species and use small
mesh sized nets and handmade traps to catch small fish.
The community fishery relies heavily on regular stocking of the Baor by Department of Fisheries
which is undertaken year-round and harvesting of the fish is undertaken multiple times between
September and June (the dry season). There is a fish target of 92 tons annually and when this is
reached fishing is stopped.
Fish are introduced every year to the Baor with 16.00 MT of fish fry released in 2019/20 at an
estimated cost of BDT 2,000,000. Table 33 above indicates details of fish species stocked last
year.
The carp species used for stocking are either from other parts of the world or are species from
other parts of the region. This is the first year that Chital is stocked in the lake. Chital is a native
carnivorous species which preys on small indigenous species; the species has been intentionally
removed elsewhere from closed aquatic ecosystems to ensure the protection of smaller species
on which small scale fishing relies at the Baor.
The SIA study confirms the importance of fishing income for the people around the Baor. All the
210 households surveyed engaged in fishing for their main or as a secondary source of income
and 57.6% of families went fishing more than 22 days per year. 78.2% of households had 1 to 3
members engaged directly in fishing as their primary activity. Income from fishing contributed on
Floating PV Candidate Site Report
September 2020 │ Rev03 87
average 75,220 BDT (US$ 887) to surveyed households, or more than half the total household
income of 139,503 BDT (US$ 1644) of the people in the Baor area.
There are various ecosystems service the Baor provides to local people which may be impacted
by the Subproject. The main service, as already described, is the provision of fish as a source of
food and livelihood. The resource on which the 13 main fishing groups rely is, however, based
mainly on introduced carp species which compete with indigenous fish. Without stocking of the
Baor the Department of Fisheries organised commercial type fishery would have significantly
reduced income if it could exist at all. The indigenous species do, however, provide important
ecosystem services and the villagers rely in part on this source for food and some income.
Other ecosystem services identified at the Baor are:
Water is pumped from the lake for irrigation purposes during the dry season and provides
important input to agricultural production;
Clothes washing and bathing by the local community (the water is occasionally used for cooking
but not for drinking);
Ducks and water birds probably provide a food source to local people;
Jute Retting with farmers using the Baor to submerge, soak and clean fibres;
Recreational boating activities, ecotourism and ornithology;.
The fishermen are mainly from the Hindu faith and they use the lake side for their Puja and
Ganga Puja harvest festival and cultural services which take place on the banks of the Baor.
The Subproject has a small footprint and is not polluting and is not anticipated to have significant
impact on any of the activities and services identified above which occur mainly around the
perimeter and edges of the Baor.
It is unclear the extent of impact the Subproject will have on fish numbers available in the Baor for
local fishermen and this needs to be monitored in future as part of the Subproject monitoring
program. The Subproject will not trigger any criteria with regard to any long-term impacts to
ecosystems services and cultural values.
Although the panels can act as fish sanctuaries, the Subproject is indicated as a concern to
fishermen on the lake who fear that catches and livelihood income will be reduced. There was
particular concern that fish can hide under the platforms and evade capture and that the panels
should be screened off some way so that fish cannot shelter beneath the PV panels. It is regarded
as impractical to screen off the panels; this will just reduce potential fish habitat and may itself result
in reduced fish numbers. This should be discussed with the fishing community in conjunction with
the SIA benefits package which is intended as compensation for lost income and potential reduction
in fishing catch. The fish population will also be monitored during the Subproject life to determine
if there is impact from the panels.
Fishing activity is undertaken most of the year from August through to July and stocking takes place
most of the year. The wet season is the time of least activity. It is proposed that the Subproject is
undertaken in the six month period beginning July. The best solution to having least impact to
fishing is for the contractor to consult with the Community Fishing Groups and the Department of
Fisheries and schedule activities, particularly for the placing of any anchors, to ensure least impact
to fishing.
Floating PV Candidate Site Report
September 2020 │ Rev03 88
7.2.4 Site clearance and site preparation
During the construction phase of the Subproject, a small amount of land clearance and preparation
will be required for certain support infrastructure i.e. for a storage area, float assembly area,
associated road and drainage construction and maybe for a small workers camp. There may be
some impact to topsoil and soil quality and soil characteristics may deteriorate. There is also the
potential for oil contamination (discussed in Section 7.2.9).
The proposed assembly area identified is approximately 1,400 m2 and the site is relatively flat.
Some landfilling is required in places and fill in others to level the site for a flat assembly surface.
The Subproject does not include major excavation works during a short 6-month construction
phase, and any residual, solid soil waste will be small. Any unused excavated soil will be disposed
of in designated areas which will be stipulated in a final Waste Management Plan. Topsoil will be
removed, stored and used in restoring the site. Any revegetation will be undertaken with native
species. The Baor banks are steep and it is intended that a pulley system is used to lower the
floating platform into the Baor surface.
Site clearing and site preparation activities will also result in loss of some vegetation cover (grass
and shrubs). A small area of existing vegetation/trees may also need to be cut down or cutback
along the route of the new transmission lines, from the water body to the existing substation. A
small amount of secondary vegetation damage may occur during the stringing of transmission lines.
This will be a minor impact and losses, if any, will be assessed and compensated for by agreement.
Impacts will be minor and can be mitigated.
7.2.5 Impact to local roads and traffic
The solar cells and floating components for the Subproject are likely to be manufactured overseas
in Singapore, India or China. It is calculated that for transportation of the HDPE floats required for
the Subproject, between 18 to 29 container loads are needed to deliver 9 MW of resulting power
for the Subproject (RINA Feasibility Study). This means an increase of less than 1.5 vehicles per
day over the 6 month Subproject life. Imported components will be transported by road from
Chittagong port. There is the possibility that manufacture of the floats can take place in country but
any decision to do this would only be taken at Subproject tender time.
Access to the lake and proposed assembly area is by a herringbone brick surfaced road at one end
merging into an earth road at the Baor edge; there are some sharp turns on this road. This access
will be improved and sealed at Subproject cost. This road connects to the regional asphalt paved
road which is approximately 6 metres wide.
During construction, a temporary storage container at the lake side will be used to house daily
deliveries of the floaters, any assembly kit and PV modules. The equipment will need to be
transported to the Baor on a daily basis from the PBS BREB warehouse, at Jessore where there is
space for storage and where there is road access for large (40 ft) lorries from the port. Smaller
vehicles will then move the components to the assembly area on the Baor.
Some road crossing sites may be temporarily impacted during the process of installation and
stringing of transmission lines between new power poles. There will be some small short-term
increase in the number of vehicles in the area with increased risk of traffic accidents.
Floating PV Candidate Site Report
September 2020 │ Rev03 89
The Subproject contractor will develop a Traffic Management Plan ensuring measures, such as
moving loads out of peak hour traffic and ensuring traffic safety training for its workforce.
Procedures will be put in place informing residents in advance of the need for any temporary
closures. The Management Plan will also include navigation and water movements during
construction and operations; it will particularly define arrangements for informing local people and
authorities when the PV platforms are towed into place and secured.
Impacts are regarded as small, over a short construction period, and can be mitigated with
management measures.
During the operations phase there is negligible vehicle traffic associated with the Subproject and
the Traffic Management Plan will be in place to cover traffic movements on the water.
7.2.6 Navigation and transportation at lakeside and on the water
The Baor is 7 km long and is narrow and local people use a boat service across the lake as
communication between east and west sides. There is a regular boat service route connecting the
communities on the east and west banks of the Baor with movement of food, agricultural goods
and jute across the lake. This route is not affected by the PV panel locations.
The floating solar panels are to be erected on open water used by local people in their small boats
(dungas) around the Baor to catch fish for their own consumption or as part of registered fishing
groups. The new situation will require changes to some local boat movements.
The floating panels layout is designed to allow adequate clearance of boats during the lowest water
levels in the Baor with 20 m clearance to the shore and this will be monitored in the low water dry
season to ensure this clearance is maintained.
For safety during construction, work areas will be properly defined by marked buoys and
appropriate lighting and adequate publicity will be provided to local people of the changed situation.
Potential silting and reduction in water levels is not covered in the feasibility study and this needs
to be considered in detailed design. The impacts of siltation and on the possible removal of existing
sediments and dredging of the lake as requested by fishermen is also not part of feasibility study;
this should be considered later during Subproject operation with detailed technical studies and an
environmental assessment of potential impacts.
7.2.7 Air quality and noise quality
Air and noise quality can be affected during the six months of Subproject construction with the use
of equipment and machinery for such activities as:
Temporary and permanent road construction/improvements to existing access roads/tracks;
Site preparation work for the floatation and solar panel storage and assembly area where the
solar facility is floated out into the water;
Temporary access for transmission line pole placement and stringing of lines between
poles; and
Possible construction of a small workers camp.
Floating PV Candidate Site Report
September 2020 │ Rev03 90
Loading and unloading of any materials and components and traffic movements along unsealed
roads can generate dust and other polluting gases (e.g. CO, SOx, NOx and hydrocarbons) and
there will also be some deterioration in noise quality. There will be some road construction and
traffic movements and the need to suppress dust particularly close to homes of local residents
along the approach road to the panel assembly site.
Air quality and noise impacts will be small and manageable during the construction phase. There
will, however, be measures in place for air and noise mitigation included in the IEE mitigation plan
i.e.
All vehicles to carry valid fitness certificates issued by BRTA and renewed annually under the
Motor Vehicles Ordinance 1983, Section 48, Chapter IV and the rules thereunder;
All construction vehicles and equipment to be maintained as per manufacturer’s
recommendations and to conform to good industrial practice;
Avoid construction activity at night-time with work to be restricted to sociable hours (07.00 am
to 18.00 pm);
Site speed limits of 10 km per hour in construction areas and posted. Water to be sprayed on
roads to suppress dust in dry season and a spraying schedule to be prepared by the contractor;
Any construction vehicles carrying loose materials to be securely covered;
Temporary fencing to be installed at construction and assembly site, and any camps;
Ensure that any generators and heavy-duty equipment are insulated or placed in enclosures to
assist in minimizing noise levels;
Prepare and implement a vehicle and machine maintenance program, with construction
machinery to be kept in good condition to reduce noise generation;
Optimise scheduling of vehicles and construction equipment to reduce noise;
Monitor noise levels on site and adjoining roads; and
Develop a Noise and Dust Control Plan in consultation with community prior to the beginning
of construction.
As part of a Noise and Dust Control Plan contractors will be obliged to undertake base line sampling
for noise and air quality prior to construction at areas such as the float/panel assembly areas,
Subproject lake side activities and along the transmission line. Local noise receptors such as
houses, and school facilities will be identified and sampled. Monitoring will be required as part of
the Subproject approved IEE/EIA.
During operation of the solar facility such impacts will be negligible.
7.2.8 Changes to water quality at the Baor
Water Quality measurements were undertaken as part of the Strategic Environmental Assessment
(SEA) study in the wet and dry season 2019/2020 and this information will form the base line for
further water quality studies.
The study found there were no significant differences in water quality parameters measured at the
surface (above 2 m) compared with water quality measured below 2 m depth. However, water
quality variability between sampling locations was notable for pH, DO, Chlorophyll-a and blue-green
algae. This indicates that the water has likely been affected by surrounding land uses and terrestrial
inputs. Joydia Baor is a small water body with a maximum recorded depth of 10.3 m, with the
deepest water quality profile taken at 7 m. As expected, water temperature at the surface (above
Floating PV Candidate Site Report
September 2020 │ Rev03 91
2 m) was 2°C warmer in the afternoon compared with the morning. The water pH was neutral to
alkaline (pH 8 to 8.5) in both wet and dry seasons. The lowest pH values (below 8) were measured
below 4 m depth. Slightly higher electrical conductivity values were recorded in the wet season
compared with the dry season. This could be due to the higher inputs from runoff and storm water
and water mixing in the wet season. Overall, the conductivity at Joydia Baor was low to medium
(276 to 348 µs/cm) and TDS remained unchanged with depths and seasons. Dissolved oxygen
ranged from 6 to 10 mg/L in the surface layer but decreased to 1.3 mg/L below 5 m in the wet
season. DO was relatively evenly distributed across the water profile in the dry season (6 to
9.5 mg/L). The water column remained in an oxidizing state at most of the sampling locations. In
the case of four of the sample sites, however, reducing conditions were measured along the entire
water profile indicating that there was some degree of anthropogenic inputs present. This is
consistent with a self-cleaning process in the Baor where bacteria decompose dead tissues and
contaminants, which uses up a substantial amount of the available oxygen in the water. Medium
levels of chlorophyll (up to 22 µg/L) were measured in the wet season. These levels decreased in
the dry season (max. at 6.7 µg/L). Insignificant concentrations of blue-green algae indicated that
the Baor has good quality primary production (phytoplankton). Very low turbidity levels were
recorded (approx. 2 FNU) throughout the water column in both wet and dry seasons.
Joydia is classified as a hypereutrophic system based on its overall water quality index (TSI),
meaning that the waterbody has an overabundance of nutrients and can potentially support the
highest level of biological productivity (e.g., an abundance of algae, aquatic plants, birds, fish,
insects, and other wildlife). However, in both wet and dry seasons the biodiversity index of benthic
macroinvertebrate, phytoplankton and zooplankton in Joydia Baor were classified as medium. This
could be due to some degree of anthropogenic inputs present in the Baor particularly in the middle
section where the greatest amount of anthropological activities was observed. This area is also
near a small inflow channel that enters the waterbody on the north side and may be contributing to
the observed results. Highest Chlorophyll-a, BGA and negative ORP were detected in this area.
Cyanobacteria (Oscillatoria, Merismopedia, Microcystis and Pelonema) were detected at most
locations across the Baor in the wet season and only at one in the dry season. These results were
consistent with the high levels of Chlorophyll-a and BGA and observed dissolved oxygen conditions
of the Baor.
The hypereutrophic classification means that the Baor is likely to be susceptible to algal blooms at
certain times of the year.
The Baor is already a much-changed system with village housing and garden land down to the
water’s edge. A number of anthropogenic activities add to impacts and reduction in water quality in
what is a relatively small and shallow water body i.e.
Many of the farmers around the Baor perform jute-retting or rotting directly in the Baor water,
to more easily extract jute fibres;
Human washing and bathing, clothes washing of lake side communities directly in the Baor;
Use of agricultural chemicals with run off to the Baor;
Adding fish food to the Baor in the dry season to feed released fish fry; and
Duck and geese raising of birds in the water and at the water’s edge.
The Subproject may also further impact water quality. In the construction phase there is potential
to contaminate water and affect human welfare, as well as fish breeding and aquatic habitat and in
turn affect the fishing livelihood of local people. Such Subproject activity can include small amounts
Floating PV Candidate Site Report
September 2020 │ Rev03 92
of land clearing, backfilling and levelling with increased chance of run-off to the Baor. Soil erosion
and run off are of particular concern during the monsoon season (May to October)
During anchoring the floating platforms, there will be disturbance of lake bottom sediments. The
details of the anchoring mechanism to be adopted are the subject to further technical studies. The
anchor process can be carefully managed and complied with and anchors lowered slowly to reduce
any disturbance and the dispersal of sediments can be kept to a minimum. Normally, the position
of anchors can be determined accurately, and the anchors then slowly lowered by cranes so that
the impact force of collision between the anchor system and the lakebed is reduced. With proper
procedures the impact to water quality should be small and temporary. The contractor will be
obliged to submit a management plan with respect to final placement of any anchors to minimise
disturbance of sediments and impact to turbidity. With proper procedures the impact to water quality
should be small and temporary.
Domestic wastewater from the Subproject also has the potential to contaminate the lake from toilets
and washing facilities during construction. With a small work force and short construction period
and proper sanitary arrangements for workers, this impact can be managed and should be minor.
During construction and operations there is the possibility of contamination of water bodies and soil
from spillage of oil from equipment and from transformer oil and from potentially inadequate
containment and handling procedures where hazardous liquid materials are stored and used
including over water on the floating facilities. Impacts from these sources can be minimised by
proper mitigation, by proper containment and waste management planning. Bunded transformers
will be stipulated for use over water to avoid water contamination. A spill management plan will be
developed prior to construction to be implemented in the event of unexpected releases and a draft
spill management plan is attached in Appendix J. It is likely that oil type transformers may be
preferred for the reasons given in Section 3.1.2 of this report. It is therefore recommended that if
oil type transformers are employed that clauses should be added in the contracts that only
biodegradable natural esters are used instead of oils and that adequate bunding will be required.
Materials and metal parts on floating facilities are subject to accelerated corrosion with exposure
to water and UV radiation. FPV pontoon mounting structures are typically manufactured from HDPE
plastic or similar inert materials. Likewise, floating raft installations make use of HDPE piping and
marine grade stainless steel structural elements. The standard PV modules used are typically
aluminium framed and pose no risk of water contamination. However, the contacts for the
Subproject will state that inert materials will be used for all panel materials. Any mooring ropes will
be checked regularly and replaced to ensure that microplastics do not enter the water and food
chain.
The PV panels and the floating pontoon structure supporting the panels will shade the water body
and reduce water evaporation, reduce solar energy absorption, decrease water temperature, and
increase the dissolved oxygen concentration in the water. There will be a changed environment in
the water area beneath the panels and it is likely that this can provide favourable conditions for fish
and aquatic life to flourish and result in positive impacts. The panel areas may, therefore, function
as sanctuaries for fish.
To ensure some light penetration to the surface of the water beneath the pontoon structure, the
design will recommend the use of dual glass modules and allow for some gaps in the solar panel
layout and this provision will be included in contracts.
Floating PV Candidate Site Report
September 2020 │ Rev03 93
It is recognised that locating a floating solar PV system on large water bodies is a new concept and
there are few largescale projects worldwide that have been in existence for longer than 7 years. In
practice there may be impacts to water bodies over the Subproject life that are unforeseeable. With
little long-term research into how a lake system would be impacted by a floating solar PV system,
it is still not fully clear as to the potential environmental effects (positive and/or negative). Any
impact will likely be proportional to cover of the lake and it is wise, therefore, to be conservative
and keep the percentage of the lake coverage down. It is proposed that 5.8% of the Joydia total
lake surface will be covered by this proposal and this is a precaution against any unforeseen
impacts.
Any foreseeable negative impact of the PV panel system on the surface of the lake is considered
manageable, and there are likely to be positive impacts to water quality and possibly for fish species
and fish numbers. However, because of the water quality pressures already described, it will be
necessary to carefully monitor water quality once the PV panels are in place and assess if there
are any impacts as a result of the Subproject.
7.2.9 Construction waste and hazardous waste generation
Apart from cut and fill soil activities already discussed, the Subproject will generate various non-
hazardous waste streams mainly during the construction phase from activities at vehicle/machinery
maintenance and repair areas, any camps, working and storage areas. Waste materials will be
diverse in nature (e.g. timber, plywood, metals, concrete, gravel, stone, glass, topsoil, green waste,
plastics, PVC, mixed wastes).
Hazardous wastes will also be generated including oils (from various sources e.g. transformers and
vehicles), medical waste, sewage (from septic tanks at site, maybe also on the floating panels and
at camps), contaminated soil, vehicle batteries and oil filters, and it will be necessary to set up
procedures for separation, containment, recycling and agree final disposal of all waste streams. A
Solid and Hazardous Management Plan will be in place prior to construction activity and also for
the operations phase of the Subproject. A draft example of a Solid and Hazardous Waste
Management Plan is attached in Appendix K.
Provided the Waste Management Plan is implemented in accordance with the recommendations
therein the environmental impacts associated with waste management are expected to be
manageable.
7.2.10 Land use and land value
The land around the water body is either village land for local housing or farmland with some fruit
and other trees. There will be only a very small change in land use as a result of Subproject
development.
The Subproject has a relatively small footprint and employs few people during operations. The
Subproject will contribute to consistency of overall power availability in the country. There is
anticipated to be minimal direct impact on land values as a result of the Subproject.
Floating PV Candidate Site Report
September 2020 │ Rev03 94
7.2.11 Habitat and aquatic life impacts
There will be impacts to animal and aquatic life during construction and some impacts to aquatic
life and habitat loss during operations.
Joydia is situated within a mosaic of modified habitats. While the Baor itself is a naturally formed
oxbow lake, the plant and animals present at the lake are largely formed of deliberately introduced
species. Human activity has modified the area’s primary ecological functions and species
composition. Many non-native species are present in association with homestead vegetation which
provides habitat of limited value for bird species.
The SEA surveyed the littoral vegetation present at the Baor during the dry season, January 2020.
The survey observed that overhanging vegetation within the littoral area was rare and most mature
riparian vegetation is set back at least 1-2 m from the water’s edge owing to low water levels during
summer months. Crops frequently border the waters’ edge, however these were typically shorter
species such as red spinach or corn that provided little to no shade in the littoral zone. Vegetation
was dominated by three species. Floating water hyacinth (Eichhornia crassipes) was typically
present up to the waterline and was also noted to be exceptionally abundant during the wet season.
The two other species, Japanese bamboo (Blyxa japonica) and hornwort (Ceratophyllum
demersum) were both submerged species and appeared in patches throughout the littoral zone
between 0.1 to approximately 4.5 m.
The SEA identified bird species listed as critically endangered and endangered which are known
or likely to occur at Joydia Baor. The Indian spotted eagle (endangered) and the common pochard
which is listed as vulnerable were considered as candidate bird species to potentially trigger IUCN
and SPS criteria. (see SEA Study). Congregatory species were also considered.
The SEA also identified 15 fish species which are critically endangered and/or endangered and are
known or likely to occur at Joydia.
Wet and dry season bird field surveys were also undertaken directly in the SIA and 37 species of
which 24 are considered riparian vegetation dependent were identified. 10 species were seen in
both seasons, while 12 species were present only in dry season and are considered as migrants.
Waterbirds were present in large numbers included cormorants and lesser whistling ducks which
were present in wet and dry seasons, suggesting it is an important roosting area. Birds were less
inclined to use the northern section of the Baor where the panels are to be located. The northern
side supported less aquatic vegetation and roosts were typically associated with fish komors in the
mid and southern parts of the Baor. Fewer ducks were noted than expected.
The SEA also undertook fish survey in wet and dry and identified a total of 35 fish species directly
observed at the Baor. 21 species were observed only in the wet season and six only in the dry. The
majority of fish species were found to be habitat generalist that readily inhabit a variety of
waterbodies such as lakes, ponds and rivers. Hotspots of fishing activity where seen in the centre
of the waterbody in association with the fish sanctuaries.
The SEA study found that there are no bird or fish species present at the Subproject site which
would trigger any critical habitat under the relevant IFC guidelines or the corresponding ADB SPS
guidelines.
Floating PV Candidate Site Report
September 2020 │ Rev03 95
With regard to terrestrial species likely to be impacted by the Subproject, there is little suitable
habitat for mammals of any size in the area of the Baor and no mammal species endangered or
critically endangered are found close to the Baor. Thirteen terrestrial species 7 of which were
amphibians were assessed as likely to be present in the wider area which might trigger IFC SBS
habitat trigger criteria for endangered species. Assessment of species likely to be present is
ongoing and will be finalised at the IEE/EIA stage of the Subproject.
The Baor provides important income and sustenance to local people from fishing and some tourism
services which has been discussed (see Potential Loss to Livelihood Food and Ecosysems
Services).
The SEA examined various aspects of potential impact to birds and fish life at the site i.e. habitat
disturbance, habitat degradation, change to aquatic systems, aquatic habitat loss and mortality.
The study indicates potential for impacts to bird and aquatic systems, some of which are potentially
long term and makes recommendations for mitigation measures which can reduce impacts to
acceptable levels.
The SEA also points out that the potential introduction of invasive species could have
consequences through loss of native species, through habitat degradation and with significant
impact to aquatic species. The susceptibility of the system to invasive species and the potential
occurrence of edge effects and disruption to riparian vegetation is considered high if there were to
be significant land clearance at the lake with alterations to runoff and erosion.
The lake side areas required for the Subproject are small and mainly required for the brief
construction period. However, the O & M contractor providing services for the Subproject who will
have responsibility for compliance during construction and will also be required:
To ensure a risk analysis for invasive species is conducted prior to the start of the Subproject;
Develop an erosion and sediment management plan to prevent runoff entering
waterbodies; and
Ensure materials that will not affect water quality are used for solar installations.
It is recommended that there should be roosting, and resting platforms installed for water birds
(cormorants, egrets and darters) in locations away from the PV panels and the main navigation
channels. This will provide alternative sites for birds to congregate and also allow the scaring away
of birds from the PV panels to avoid soiling and loss of generation capacity, as per measures
included in the Subproject feasibility study. It will also allow the installation of appropriate lighting
taking into consideration of bright lighting attracting migrating birds and the need for human safety
of navigation at night.
With the various implementation, avoidance and mitigation measures, recommended by SEA study
and included in EMP mitigation, potential impact magnitude to birds and fish and their habitat can
be reduced to acceptable levels.
7.2.12 Impacts on protected and internationally recognised areas
There are no UNESCO natural world heritage areas or RAMSAR wetlands of international
importance affected by the Subproject (Joydia is more than 50 km from the Sundarbans).
Floating PV Candidate Site Report
September 2020 │ Rev03 96
The Baor is within a general delta area recognised as globally important for the conservation of bird
populations. There is also a Wildlife Sanctuary in Narendrapor over the border in West Bengal just
to the west of Kolkata, India which is within 50 km of the Baor.
The Subproject is not located within any protected areas.
7.2.13 Social impacts associated with construction
Social impacts include potential for conflict between workers from outside the Subproject with local
people. There can be pressure on local infrastructure and services, increase in commodity prices,
conflict/tension between migrant and local people and, increased risk of infectious diseases
including sexual transmitted infections.
If workers are employed from outside the immediate Subproject area, they will be housed in a small
camp inside a designated site boundary for the length of the construction phase. However,
contractors and sub-contractors will be strongly encouraged to employ and train local labour to
reduce or eliminate any requirements for a camp.
The Subproject will be required to implement communicable disease awareness and prevention
measures targeting risk of spread of STIs and HIV. The Subproject work force is small in scale and
limited to a short construction period.
Proper health and safety plans will be in place to minimise impacts and residual impacts are
anticipated to be minor.
7.2.14 Employment opportunities and income generation
For construction, there will be need for a limited number of skilled and non-skilled jobs and some
few employment opportunities will be created for people in the immediate Subproject area i.e.
unloading parts, moving floatation parts and solar panels by forklift trucks to the final assembly
location, operating pulley system and putting together the floatation structures. The number of jobs
during construction – mainly unskilled for the six months of construction activities are few
(maximum 30) and will result in only a small increase in productivity and capital income of the
people in the area. For the operations phase for cleaning panels, removing weed and security, a
team of local workers will be employed and trained.
7.2.15 Industrial and economic development
The Subproject will contribute to electricity supply in the area and to the country as a whole and to
general industrial development. The country has been hampered by undersupply and the
Subproject will help boost supply and reliability and will encourage growth in all development
sectors. This will result in increased productivity and GDP and support the national economy.
7.2.16 Human safety
During construction and operations there will be human safety issues. During construction the
safety of workers, local villagers and land users will need to be protected. Appropriate safety
measures will be required. The Subproject contractor and sub-contractors will be required to
develop an occupational health and safety policy and plan prior to construction work to ensure
Floating PV Candidate Site Report
September 2020 │ Rev03 97
safety measures are in place and ensure employees have been trained. In particular there will be
risks in working over water and during project operations.
The cleaning of the solar panels and the removal of floating weed and other debris from the panels
will be ongoing activities for employees and these workers will be properly trained in the cleaning
and de-weeding process. For all workers including security staff, training in the use of lifejackets
and buoyance aids will be essential.
Community health/safety will also be at risk during construction and operations phases and
unauthorised entry to the general public will not be allowed. Work areas including storage and
assembly areas will be fenced off and appropriate signage will be posted at site with health and
safety aspects explained. For operations, the designated area for a boat, and buildings or
designated areas for storage of cleaning equipment and materials and any staff facilities including
toilets will be fenced. A Health and Safety plan will be in place to minimise impacts in both
construction and operations phases.
The O&M contractor providing services to the Subproject will have responsibility for compliance
during construction. To ensure the Subproject is prepared to cope with emergencies e.g. fire,
abnormal weather events, accidental oil spills etc. an emergency response plan will be developed
prior to the construction and operation phases of the Subproject. The plan will develop procedures
to define communications links for local and regional response and the relevant health authorities
and will stipulate available dedicated equipment (boats, oil spill equipment etc.).
A risk assessment will be required to inform an occupational and community health and safety
management plan is in place and health and safety plans will be developed to minimize impacts.
With respect to electromagnetic fields, the Project will conform to ICNRIP guidelines as per SPS
2009 EHS guidelines.
7.2.17 Climate change impacts
The majority of climate change projections for Bangladesh suggest that the average temperature
in the country is likely to increase by 1°C by 2030, 1.4°C by 2050 and 2.4°C by 2100 (Ramamasy
& Baas, 2007) against the baseline period (1960-1990), and there will be a significant increasing
trends in cyclone frequency and intensity over the Bay of Bengal during November and May.
The Fifth Assessment Report of the IPCC from 2014 stresses that climate change-related risks
stemming from extreme events such as extreme precipitation, cyclones and flooding can already
be observed in Bangladesh. Global average tropical cyclone wind speed and rainfall is likely to
increase in the future, and the global average frequency of tropical cyclones is likely to decrease
or remain unchanged.
The main Climate change risks for the lake are those arising from an increase in extreme rainfall
events and cyclones. It is expected that these hazards will be exacerbated by changes in the
climate and the intensity of climatic disasters like tropical cyclones, droughts and floods into the
future and these need to be fully taken into account during the detailed design phase of the
Subproject; this is especially so in relation to the sensitivity of FVP infrastructure to various factors
including increasing temperature, increase in extreme hot days, increasing intensity of rainfall,
Floating PV Candidate Site Report
September 2020 │ Rev03 98
increased frequency and intensity of flood events; and increasing intensity of wind velocity and
cyclone weather conditions.
For FVP infrastructure design and construction standards it is recommended in the Climate Risk
and Vulnerability Assessment, that the effects of changing flood levels and behaviour due to climate
change be taken into account and accommodated in the Subproject design process.
FVP infrastructure placement, and alignment will be located in low risk areas to minimise system
vulnerabilities to possible climate impacts and threats from string winds, currents and debris
associated with floods.
Suitable materials will be identified for construction of infrastructure assets and structures to
minimise damage and/or deterioration of FVP infrastructure in the light of cyclonic winds and other
related climate change impacts and ensure that platforms can withstand harsh environmental
conditions for a minimum of 30 years operations.
Appropriate international standards and guidelines (IEC and ASTM guidelines) will be applied to
cover PV modules, PV inverters, system design and installation, PV system performance and
operations, floating platform and floaters as recommended in the Climate Risk and Vulnerability
Assessment undertaken for the Subproject. (see Climate Risk and Vulnerability Assessment for
the Subproject).
7.2.18 Objects of cultural or achaeological importance
The land requirement for the Subproject is small and there is no evidence of sites of cultural and
archaeological importance in the area though there are various tombs, temples and other sites in
the Jessore area and the country as a whole.
There is still the possibility to unearth or discover objects of a cultural nature during Subproject
activities that will need to be protected. It is, therefore, prescient to have in place some mechanism
to ensure that, if there are discoveries, that, there is a procedure to handle this. In the event that
object of cultural or archaeological nature are unearthed, work will be stopped temporarily, and the
discovery referred to the Department of Archaeology, Ministry of Cultural Affairs GOB who are the
responsible authority under the Antiquities Act 1968. Work is only to recommence with the approval
of the Department of Archaeology, Ministry of Cultural Affairs.
7.2.19 Visual intrusion and reflection issues
As with other power generation and transmission infrastructure (e.g. transmission towers, wind
farms) there will be some inevitable visual intrusion on the landscape and waterbody from the
Subproject. The solar panels sit relatively low in the water, (a few meters high) and do not dominate
the landscape in the way transmission towers and wind farms do. The new solar arrays may also
prove a source of interest to local visitors. There is potential for reflection from the large expanse
of panels and specifically to any air traffic and pilots in the area. PV panels are designed to absorb
light and not reflect it; less light is actually reflected than directly received from the sun. Studies
(e.g. General Design Procedures for Airport-Based Solar Photovoltaic Systems, Energies 2017)
conclude that reflection from panels is less intense than from water bodies i.e. modern PV panels
have less intense reflectivity than still surface water. It is likely, therefore, that aquavoltaics will
contribute to reducing water surface glare from the water body on which they are located.
Floating PV Candidate Site Report
September 2020 │ Rev03 99
There are no airports within 15 km of the Subproject site and reflection is not anticipated to be an
issue from the Subproject.
7.2.20 Subproject decommissioning
At the time of decommissioning the PV floatation modules and cells can readily be removed and
recycled. The PV modules do not contain any hazardous materials and can be sent to landfill if
necessary; contracts will, nevertheless, stipulate that the construction materials used in the
Subproject will contain no toxic materials.
At the conclusion of the 30 year project life, an economic assessment will be conducted to
determine whether the life of the Subproject will be extended and if the Subproject complies with
IFC/World Bank Environmental Health and Safety Guidelines and all other subsequently
recognised applicable standards.
7.3 Conclusions and recommendations
The key findings and recommendation of the environmental assessment are summarised as
follows:
The Subproject construction phase involves the assembly of parts (PV cells and floatation units)
and the fixing this infrastructure on the Baor surface. The construction phase will take just six
months.
Potential environmental impacts are associated with the Subproject during the construction and
operation phases, including impacts on land, water quality, wildlife, fishing, movements on the
Baor.
Placing the FPV solar panels on water means only a relatively small amount of land surface
area is required for Subproject operation in a region of high population densities; the Subproject
has only a small environmental footprint.
There may be some irreversible impacts to aquatic environment over the Subproject life, but
most environmental adverse impacts are temporary and are not likely to extend beyond the
environmental footprint of the Subproject. If eventually the panels are to be removed, most
impacts can be regarded as reversible in nature.
The Subproject is a renewable energy project which is not resource intensive and by nature is
not polluting. The FPV structures are manufactured from inert material and the PV modules
pose no risk of water contamination. The Subproject avoids the need for alternative
consumption of fossil fuels to create the equivalent amount of electric power.
The land required for the Subproject is Government land. The envelope for solar PV activities
and facilities (storage area and assembly area for construction and the PV floating platforms)
will be on government owned and controlled land. The evacuation line will follow along the
existing highway to the existing substation at Kotchandpur.
No indigenous groups are directly impacted by the Subproject.
Total panel coverage has been kept down to less than 6% of the total dry season water surface
area of the Baor, and this is a precaution against unexpected potential negative impacts which
may occur as a result of the Subproject.
The Subproject is not within any protected areas.
The Strategic Environmental Assessment (SEA) study identifies potential impacts to bird and
fish habitat and the potential introduction of invasive species. With the implementation of the
Floating PV Candidate Site Report
September 2020 │ Rev03 100
various, avoidance and mitigation measures recommended in the SEA and included in the IEE
and EMP for the Subproject, impact magnitude can be reduced to minor or acceptable levels.
The placing of floating panels on open water bodies anywhere in Bangladesh presents
exposure to climate risk. The climate risk analysis for the Subproject recommends that, because
of the nature of the Subproject on open waters, and because of prevailing climate and future
projected changes to climate, that the Subproject will be required to be engineered with the
best infrastructure design and construction standards and practises.
Stakeholder consultations were carried out at the Subproject location in November 2019 and
February 2020 to document any issues/concerns and to ensure that such concerns were
addressed in the Subproject design and also in the consideration of compensation measures
which have been included in a Social Management Plan (SMP) for the Subproject.
The Social Impact Assessment Study which was conducted in parallel to this Environmental
Assessment recommends a range of compensation measures as already indicated above in the
Social Chapter of this report, including:
Construction of two gates/grills at the Baor.
Paying the 186 fishing families 20% of the cost of current fishing income (based on fishing
income of households indicated in the SIA social survey) over the 30 life of the Subproject.
Assistance with a lump sum grant for fish feeding.
These measures, more detailed costing and other social mitigation measures are described in more
detail in the Social Impact Assessment Chapter above.
In addition to the proposals in the SIA the Subproject budget will also include the following:
Ongoing survey/monitoring to cover the cost of half yearly surveys for water quality, bird and
aquatic surveys, lake biology (benthic and phytoplankton), lake habitat (side-scan sonar and
field habitat assessments), aquatic species (fishing, fish nursery grounds, eDNA and
consultation with local fishermen), and fish biomass. Also, there is need for fishing catch
surveys in the Subproject area and livelihood surveys in local villages - $60,000 annually in
Subproject costs for first year and then from Subproject revenues.
For the EA to monitor the EMP implementation and monitoring programme which is likely to be
implemented by a private consultant and assist in ADB compliance monitoring and reporting -
$50,000 in the Subproject cost for the first year and then from annual Subproject revenues.
Most impacts environmental impacts identified can be reduced to acceptable levels with the
implementation of various avoidance and mitigation measures proposed in the IEE and EMP along
with those measures recommended in the SEA and SMP.
It is recommended that the Subproject should be categorised as B for ADB environmental
assessment purpose.
The major potential impact from the Subproject will be to fishing activity and the potential lost
revenues, livelihood and food source. It is important that the Sustainable and Renewable Energy
Development Authority (SREDA) work with the Lands Department, Department of Fisheries and
the Baor fishing community to implement the Social Management Plan measures. All stakeholders
need to come to agreement on future leasing arrangements for joint use of the water resource to
allow for fishing activity to continue and for the floating solar power generation Subproject to be
developed.
Floating PV Candidate Site Report
September 2020 │ Rev03 101
Floating PV Candidate Site Report
September 2020 │ Rev03 102
8 Financial Analysis
8.1 Introduction
The financial evaluation of the proposed investments was carried out in accordance with the ADB
Financial Management and Analysis of Projects.10 The financial evaluation covers the following
output of the technical assistance: Joydia Floating PV power plant.
8.2 Methodology and major assumptions
Cost streams used to determine the financial internal rate of return (FIRR) include capital costs
(excluding price contingencies), operation and maintenance (O&M) costs, and taxes and duties.
The capital costs comprised land development, civil works, equipment, engineering consulting and
Subproject management costs as applicable to the output and contingencies. Taxes and duties
were included, as were financial charges during construction. The weighted average cost of capital
(WACC) was calculated and compared with the FIRR to ascertain financial viability. The anticipated
capital mix of debt to equity was used for estimating the WACC. The sensitivity of the FIRR to
adverse changes in the underlying assumptions was also assessed.
The financial benefit of the Subproject is incremental electricity sales from the floating PV power
plant, valued at 12 BDT/kWh.11 Income tax was computed using the prevailing corporate income
tax rates,12 which were applied to profits.
8.2.1 Subproject cost estimate
The detailed cost estimates includes physical contingencies, price contingencies and interest and
other charges during construction. The estimates have been computed in domestic currency units
in nominal terms; taking into account the effect of domestic and international inflation and foreign
exchange fluctuations. A detailed breakdown of the Subproject cost estimates is included in
Appendix H.
Table 36: Project cost estimates for Joydia Subproject
Sl
No
Item Local currency (million
BDT)
Foreign currency
(million USD)
% of
base
costs Foreign
costs
Local
costs
Total Foreign
costs
Local
costs
Total
A Investment costs (Note-1)
1 Civil works 96 30 126 1.13 0.35 1.49 15%
2 Equipment 433 - 433 5.10 - 5.10 53%
10 ADB: Financial Management and Analysis of Projects, 2005
11 The tariff as applicable for ground mounted solar PV power plants (to be verified with BERC)
12 It has been assumed that the income tax rate applicable to the implementing agency would be 37.5%
Floating PV Candidate Site Report
September 2020 │ Rev03 103
Sl
No
Item Local currency (million
BDT)
Foreign currency
(million USD)
% of
base
costs Foreign
costs
Local
costs
Total Foreign
costs
Local
costs
Total
3 Engineering
consulting - design
and supervision
36 - 36 0.43 - 0.43 4%
4 Inland transport - 48 48 - 0.56 0.56 6%
5 Taxes and duties
(Note-2)
- 112 112 - 1.32 1.32 14%
Sub-total (A) 565 190 755 6.65 2.24 8.90 92%
B Other investment costs
1 Land & civil works - 3 3 - 0.04 0.04 0%
2 Environmental and
social costs (Note-3)
- 22 22 - 0.26 0.26 3%
3 Subproject
management &
construction
supervision
- 38 38 - 0.45 0.45 5%
Sub-total (B) - 64 64 - 0.76 0.76 8%
Total base costs (A)
+ (B)
565 255 819 6.65 3.00 9.65 100%
C Contingency
1 Physical (Note-4) 45 20 66 0.53 0.24 0.77 8%
2 Price (Note-5) 26 22 48 0.31 0.26 0.57 6%
Sub-total (C) 71 43 114 0.84 0.50 1.34 14%
D Financial charges during implementation (Note-6)
1 Interest during
implementation
67 5 72 0.78 0.06 0.84 9%
2 Commitment charges 0.98 - 0.98 0.01 - 0.01 0%
3 Front end fee - - - - - - -
Sub-total (D) 68 5 73 0.80 0.06 0.85 9%
Total Subproject
cost (A) + (B) + (C) +
(D)
704 302 1,006 8.29 3.56 11.85 123%
Note:
1. Base Costs are expressed in Jul-20 prices.
2. Taxes have been assumed at an average rate of 26% (tax incidence on solar modules is
11.33% (HSC 8541.40.20; Bangladesh customs/gov.bd ) and VAT Rate is 15% (NRB,
Bangladesh))
Floating PV Candidate Site Report
September 2020 │ Rev03 104
3. Environment and Social Mitigation Costs include the following:
a. Ongoing Survey / Monitoring Work to cover bird and aquatic surveys, water quality and
other measures ; US$ 60,000/y, capitalised for first year
b. Environmental monitoring (Hire a consultant to monitor IEE/ EIA compliance and to ensure
proper implementation of mitigation measures; US$ 50,000/y, capitalised for first year
c. Social Costs towards construction of two (2) grill gates, crop compensation, engagement of
social safeguard specialist for monitoring- 10.2 Million BDT (One-Time)
d. Social costs towards other compensation -2.8 Million BDT per year (capitalised for first year)
4. Physical contingencies are computed at 5% of base costs for both LC and FC
5. Price contingencies are based on domestic (for Bangladesh) and international cost escalation
factors as projected by ADB’s Economic and Research Department. Price contingencies have
been computed as per ADB’s Financial Management and Analysis of Projects, 2005:
Inflation projections 2020 2021 2022 2023 2024 2025
Domestic inflation rate 5.50% 5.80% 5.80% 5.80% 5.80% 5.80%
International inflation rate 2.8% 3.1% 3.1% 3.1% 3.1% 3.1%
6. Financial Charges during implementation have been computed assuming financing plan as
described below (Table 37) and lending rate for external loans would be similar to ADB’s
Indicative Lending rate for loans under the LIBOR Based Loan Facility (dated 06-Jan-20). It
includes interest during construction (IDC) and commitment charges. IDC has been computed
at the 5-year forward LIBOR Rate+ a spread of 0.30%. IDC to be paid for GOB Debt has been
computed at 3% p.a.
A breakdown of the Subproject cost estimates is included in Appendix H.
8.3 Weighted Average Cost of Capital (WACC)
WACC, calculated in real terms is 0.8%, considering loans from external financing to be extended
to the government, which will be on-lent to the implementing agency. On-lending of external
financing will be in foreign currency (US$) for a period of 20 years with a 5-year grace period.
Government on-lending margins and lending rates have been modelled in accordance with the
GOB regulations: 4% on-lending margin to the implementing agency; and a local currency loan
interest rate of 3%.13 The domestic annual inflation rate was assumed to be 5.5% for the local
currency loans. The return on government equity and internal funds was estimated at 12.25%.14
Table 37 shows the calculation of WACC for each output.
Table 37: Weighted Average Cost of Capital
Item Amount
(million BDT)
Weight (%) Pre-tax
nominal cost
(%)
Post-tax real
cost (%)
External financing 633 63 4.0 (0.58)
Govt. loan 122 12 4.0 (3.12)
Equity 251 25 9.25 3.26
13 Ministry of Finance, GOB, Lending and re-lending terms of local/ foreign currency loans, 2011
14 Cut off yield of GOB treasury bonds (15 Year) 9.25% and sector premium of 3%
Floating PV Candidate Site Report
September 2020 │ Rev03 105
Item Amount
(million BDT)
Weight (%) Pre-tax
nominal cost
(%)
Post-tax real
cost (%)
Total 1,006 0.8
8.4 Financial Internal Rate of Return (FIRR)
The Subproject involves the construction of a 7.5 MW floating solar PV power plant15 which would
be able to operate at a 17% annual capacity factor, to generate 13.6 Giga-Watt-hour (GWh) per
year. Linear degradation of output has been considered at the rate of 0.4% per year.
For the purpose of financial analysis, the rate for ground mounted solar photovoltaic projects, of
12.00 BDT/kWh has been considered. The applicability of this tariff needs further assessment.
Cash flows for Joydia are summarised in Table 38. The FIRR is 8.1%.
Table 38: FIRR for Joydia project (amounts are in million BDT)
FY ending Benefits Costs Taxes New Cash
Flow Sales Capital O&M
2021 - (99) - - (99)
2022 - (365) - - (365)
2023 - (421) - - (421)
2024 163 - (23) (39) 101
2025 162 - (34) (34) 94
2026 161 - (34) (34) 93
2027 161 - (34) (34) 93
2028 160 - (34) (34) 93
2029 160 - (34) (34) 92
2030 159 - (34) (33) 92
2031 158 - (34) (33) 91
2032 158 - (33) (33) 91
2033 157 - (33) (33) 91
2034 156 - (33) (33) 90
2035 156 - (33) (32) 90
2036 155 - (33) (32) 90
2037 154 - (33) (32) 89
2038 154 - (33) (32) 89
2039 153 - (33) (31) 89
2040 152 - (33) (31) 88
15 Site rating 9,072 kWp
Floating PV Candidate Site Report
September 2020 │ Rev03 106
FY ending Benefits Costs Taxes New Cash
Flow Sales Capital O&M
2041 152 - (33) (31) 88
2042 151 - (33) (31) 88
2043 150 - (32) (31) 87
2044 150 - (32) (30) 87
2045 149 - (32) (30) 87
Net Present Value (NPV) at WACC of: 0.8% 908
Financial Internal Rate of Return (FIRR): 8.1%
() = negative, O&M = operation and maintenance; WACC: Weighted average cost of capital
8.4.1 Sensitivity analysis
Analyses were carried out to examine the sensitivity of the FIRR to changes in assumed values of
the key variables. Since the FIRR values easily exceed the WACC rate, only the adverse changes
were considered in the sensitivity analysis. The changes considered were 10% increase in
investment cost, 10% increase in operation and maintenance costs, and 10% decrease in benefits.
The FIRR was also computed for generation corresponding to P75 and P90. Table 39 shows the
effect of these changes on the FIRR. The financial performance of the Joydia Subproject is robust
for all the sensitivities tested.
Table 39: Sensitivity analysis
Sensitivity parameter Variation (%) Joydia (%)
Base case 8.1%
1. Subproject capital costs +10 7.0%
2. Operating costs +10 7.8%
3. Reduction in benefits -10 6.8%
4. Reduction in benefits Generation P75 7.6%
5. Reduction in benefits Generation P90 7.2%
6. Reduction in benefits Tariff @ 8 BDT/kWh 3.3%
In the recent past, GOB has been availing loan in Euro, at a lower cost than foreign currency loans
available in US$, the financial performance would be better, if the external financing is in EURO
instead of US$. The IRR calculated is for the loan period of 20 years, against the Subproject lifetime
of 30 years.
8.5 Conclusion
The FIRR is expected to comfortably exceed the WACC for the Subproject. Sensitivity and risk
analysis indicate that the FIRR are robust under most conditions. As such, the investment
Subproject is concluded to be financially viable.
Floating PV Candidate Site Report
September 2020 │ Rev03 107
9 Economic Assessment
9.1 Power sector and renewable energy development
9.1.1 Renewable energy policy target
The Bangladesh power sector is under the policy oversight of the Power Division of the Ministry of
Power, Energy and Mineral Resources (MPEMR) and regulatory oversight of the Bangladesh
Energy Regulatory Commission (BERC). The power industry is unbundled into three segments:
generation, transmission and distribution, with the Bangladesh Power Development Board (BPDB)
acting as the single buyer of power from generation companies and seller of bulk power to
distribution utilities. Power generation is carried out by public generation companies (e.g. Ashuganj
Power Station Company, Electricity Generation Company of Bangladesh, North-West Power
Generation Company, and Rural Power Company) and independent power producers (IPPs).
Power transmission is carried out by the Power Grid Company of Bangladesh (PGCB) Limited.
Power distribution is undertaken by BPDB (most urban centres except Dhaka City); the Dhaka
Power Distribution Company and Dhaka Electric Supply Company (Dhaka City); West Zone Power
Distribution Company (Khulna); and the Bangladesh Rural Electrification Board (BREB) (rest of the
country).
The Power Division of MPEMR is responsible for the formulation of the Renewable Energy Policy.
The Sustainable Renewable Energy Development Authority (SREDA), established in 2012 under
the SREDA Act, is tasked to be the nodal agency in promoting and developing renewable energy
in the country. In addition, government owned utilities have established units to focus on renewable
energy development.
The Renewable Energy Policy was issued by the Power Division of MPEMR in 2008 with the key
objectives of i) alleviating the impact of the declining fossil fuel reserves and energy price volatility
in the international market, ii) reducing carbon dioxide emissions and mitigating climate change,
and iii) enhancing energy security. The Policy aims to increase the share of generation in the total
power demand by 5% in 2015 and 10% in 202016. With power demand projected to increase rapidly
in the next 10 to 20 years, the Power Division of MPEMR intends to extend the 10% target to
204117.
9.1.2 Macroeconomic background
Bangladesh is one of the densely populated countries in South Asia with a total population of
165.55 million in 2019, an increase of around 14.8% in the past 10 years. The country’s population
is projected to reach 202 million in 205018.
16 MPEMR, 2008. Renewable Energy Policy of Bangladesh.
17 MPEMR, 2018. Revisiting PSMP 2016.
18 UN DESA, Population Division, 2019. World Population Prospects.
Floating PV Candidate Site Report
September 2020 │ Rev03 108
In terms of economic growth, Bangladesh has recorded the fastest growth rate in South Asia during
the fiscal year 201919. The economy expanded 8.1% between 2018-2019 reaching USD 299 billion
in current prices (BDT 25,362 billion), driven mainly by robust private sector consumption and
strong exports20. In the past 10 years, the economy grew at an average annual rate of 6.7% and
had experienced rapid acceleration in the last 4 years with annual growth rate averaging at 7.6%21.
This momentum is expected to be sustained in 2020 with the economy projected to grow at 8.0%22,
though the government is more optimistic projecting a much higher expansion of 8.2%, 8.4% and
8.6% in 2020, 2021 and 2022 respectively23. The sustained rapid economic expansion would be
supported by strong exports, robust private consumption, accommodative policy on private sector
credit, institutional reforms, and stepped up investments to develop infrastructures24.
The government aims to achieve an upper middle-income status by 2031 and a high-income country by 2041. In order to achieve these targets, the economy must grow at an average rate of 8.4% from 2018 to 2031 and at around 9.0% from 2031 to 204125.
Income per capita reached USD 1,804 in current prices (BDT 153,197) in 201926 which is 3.17
times higher than that in 2009. Based on the government’s economic projections, the income per
capita would reach USD 10,993 by 204127.
9.1.3 Electricity demand
One of the determinants of electricity demand, in addition to population growth and economic
development, is the rural electrification rate. In the past 10 years, the share of population with
access to electricity services (grid and off-grid) have almost doubled from 47% in 2008 to 93% in
2019. The government aims to achieve universal access (100% of population with access to
electricity services) by 2021.
With robust economic growth, population growth and increased access to electricity services,
electricity demand has accelerated in recent years. Grid electricity sales in 2018 amounted to
55,103 GWh which is 2.43 times higher than that in 2008. During the 5-year period 2013 - 2018,
total electricity sales had grown by an average annual rate of 11% compared with an average rate
of 7.7% during the period 2008 – 201328.
19 Fiscal year (FY) 2019 ended 30 June 2019.
20 Asian Development Bank, 2019. Asian Development Bank Outlook 2019 Update. September 2019.
21 Ministry of Finance, 2019. Bangladesh Economic Review 2019. June 2019.
22 Asian Development Bank, 2019, op. cit.
23 Ministry of Finance, 2019. op. cit.
24 Asian Development Bank, 2019. op. cit.
25 Power Division MPEMR, 2018. Revising PSMP 2016. November 2018.
26 Ministry of Finance, 2019. op. cit.
27 Power Division MPEMR, 2018. op. cit.
28 Bangladesh Power Development Board, 2019. Annual Report 2017 – 2018.
Floating PV Candidate Site Report
September 2020 │ Rev03 109
Consistent with the optimistic economic growth projections, electricity consumption (sales) is also
forecast to grow rapidly in the next few decades. The Power Sector Master Plan (PSMP) 2018
Revision estimated that electricity consumption, under the baseline case, would increase annually
by 11.7% from 2020 to 2025, but would slightly decline to 9.4% annually from 2025 to 2030. In
average, electricity consumption is projected to increase at an average rate of 8.4% per year from
2020 to 2041.
The per capita grid electricity consumption has also accelerated in recent years. Per capita
consumption reached 336 kWh in 201829, an annual increase of 9.5% per year from 2013 level.
This rate is significantly faster than the annual growth rate of 6.1% during the period 2008 to 2013.
In addition, the PSMP 2018 Revision projected that electricity consumption per capita under the
baseline case would reach 437 kWh in 2020 and would further increase to 1,084 kWh in 2030 and
2,030 kWh in 2041.
Electricity peak demand has followed a similar pattern with that of electricity consumption. Peak
demand grew at a rate of almost 11% per year during the period 2013-2018 compared with 8.4%
per year during the period 2008-2013. Peak demand reached 14,014 MW in 2018.
9.1.4 Electricity supply
Until recently, shortage of power supply characterised the electric power system in Bangladesh.
Peak demand was relatively much higher than peak generation capacity due to lack of capacity
and lower availability of ageing power plants. The period 2006-2013 represents the worst period
where power shortages hover above 1,000 MW per year30.
Recent investments to increase the power supply have resulted in tapering off power supply
shortage. The total available capacity increased rapidly at annual rate of 12.5% per year during the
period 2013-2018. The total available capacity (derated capacity) reached 15,410 MW in 2018.
Since 2013, power shortages had progressively eased off. The amount of energy not served
declined from 1,070 GWh in 2013 to around 32 GWh in 2018. Power supply interruptions in the
past few years were no longer due to lack of generation capacity but mainly with inadequate
transmission and distribution facilities.
One of the goals of the PSMP 2018 revision is to eliminate power supply shortages by 2041. The
PSMP 2018 Revision aims to gradually decommission older plants during this period and outlines
an investment plan for new capacity totalling 74,524 MW between 2020 and 2041.
9.1.5 Fuel mix
Due to availability of natural gas as a domestic energy resource, fuel for power generation has
been dominated by this single fuel. Natural gas consumption for power generation has been
constantly growing since the past decades. Natural gas consumption grew at annual rate of almost
3% over a long period from 1998-2018. The total consumption in 2018 amounted to 211,342 million
cubic feet.
29 Bangladesh Power Development Board, 2019. ibid.
30 Bangladesh Power Development Board, 2015. Annual Report 2013 – 2014.
Floating PV Candidate Site Report
September 2020 │ Rev03 110
Of the total installed capacity of 15,953 MW in 2018, natural gas-based power plants accounted
61.89%. This was followed by other fossil fuel-based power generation plants: fuel oil 21.58%,
diesel oil 8.65% and coal 3.28%. Power imports accounted 4.14% while renewable-based
technologies such as hydropower and solar PV represented 1.44% and 0.02% respectively.
The PSMP 2016 (the basis for the PSMP 2018 Revision) had not considered renewable energy
integration in the power development plan. Thus, the supply scenarios reviewed in the PSMP 2018
Revision did not take into account renewable energy in the future power generation mix. In the high
demand case generation scenario, natural gas would remain the dominant fuel accounting 45.8%
of the total target capacity additions of 74,524 MW between 2020 and 2041. This is followed by
coal (30.3%), electricity imports (14.9%), liquid fuels (2.8%) and nuclear power (6.0%). Hydropower
would only account 0.1%.
9.1.6 Potential role of floating PV
One important contribution of PSMP 2018 Revision is to integrate renewable energy in power
development planning. Extending the 10% renewable energy policy target to 2041, the required
renewable energy capacity would be 2,800 MW in 2021 and 9,400 in 2041 under the high case
scenario and 2,600 MW in 2021 and 7,950 in 2041 under the low case scenario31. The policy target
is linked with power demand. The Power Division of MPEMR and SREDA consider total installed
capacity to represent power demand with reasonable reliability, thus policy targets were estimated
as percentage of the projected installed capacity.
Renewable energy resources available in Bangladesh include solar, wind, biomass, biogas and
hydropower (micro and mini-hydropower), though solar and wind have the highest potential that
can substantially contribute in meeting the renewable energy target capacities. Bangladesh, in
average, receives around 4.5 kWh/m2/day of solar irradiation. SREDA is currently undertaking wind
resource assessment in 13 locations. Solar energy is uniformly distributed throughout the country
while wind energy and other renewable energy resources are however available only in specific
locations or sites.
Utility-scale renewable energy project development has been very slow. Total renewable energy
installed capacity as of end of 2019 amounted to 606.2 MW, of which solar PV accounted 61.4%,
hydropower 37.9% and the rest 0.7%32. Also, of the total installed capacity 50.4% are grid-
connected and the rest are off-grid systems. For solar PV installations, 74.4 MW are grid-connected
while 297.9 MW are off-grid.
With total installed capacity of only 606.2 MW as of end of 2019, the 2020 renewable capacity
target of 2,500 MW would likely be missed. Similarly, a huge gap exist between the long-term target
capacities and the proposed projects from both the public utilities and the private sector. Projects
planned by government-owned utilities and private companies totalled 2,883 MW from 2018-2041
(1,883 MW from public utilities and 950 MW from IPPs). This is far below the 7,950 – 9,400 MW
target capacities for 2041.
Of the planned renewable energy projects from the public and private sector, 2,322 MW are solar
PV projects, and these are mainly utility-scale ground-mounted systems. The proposed wind power
projects amount only to 510 MW. Solar PV could however contribute in filling up the capacity gap
31 Power Division MPEMR, 2018. op. cit.
32 www.sreda.gov.db, accessed 1 January 2020.
Floating PV Candidate Site Report
September 2020 │ Rev03 111
since solar energy resources, as mentioned earlier, are uniformly distributed throughout the
country.
One of the main constraints of ground-mounted utility-scale solar PV projects is land availability as
these projects may compete with the utilisation of land for agriculture and forestry. One strand of
development which is currently being pursued by the government is the development of small-scale
solar PV systems such as solar rooftops and mini-grid systems. Solar PV plants could be further
scaled-up by promoting the development of floating systems in several water bodies (dams, lakes,
ponds and off-shore areas) in the country.
9.2 Economic evaluation of the proposed Subproject
9.2.1 Background
The economic evaluation of the proposed investments was carried out in accordance with ADB’s
guidelines on power sector projects appraisal33.
Joydia Baor’s proposed Subproject would have a total installed capacity of 9.072 MWp. This would
entail the use of 22,680 solar PV modules, each with nominal power of 400 Wp, and inclined at 11°
angle facing true south. The site’s specific yield at 50% probability of exceedance (P50) amounts
to 1,495 kWh/kWp. With this, the plant’s power generation in the first year is estimated to be
13,563,495 kWh. Electricity generation is expected to decline yearly at a linear degradation rate of
0.4%.
A recent World Bank34 report indicated that the energy yield of a floating solar PV plant is 10-15%
higher than that of equivalent land-based power plant (solar PV plants in ‘hot climates’). However,
it should be noted that this estimate is not supported by empirical evidence and as such was not
considered in the yield analysis (Section 4).
9.2.2 Subproject costs
The background costing study presented three price scenarios for the Subproject. This study
considered the base cost case in the analysis. The low and high cost cases were taken into
consideration in the sensitivity analysis. Under the base case, the total Subproject capital cost
(direct cost and indirect costs) would amount to US$11.85 million (cost breakdown included in
Appendix H). The technology supplier is envisaged to provide technical support during the first 2
years of operation, hence the estimated base operation and maintenance (O&M) cost during this
period is US$241,400 per year. From year 3 onwards, it is presumed that the floating solar power
plant will be mainly operated by Subproject owners. The O&M cost is estimated to increase to
US$374,302 per year.
All Subproject costs were expressed in terms of economic prices. Investment and O&M costs in
financial prices were adjusted to reflect the economic resource cost of Subproject inputs in terms
of domestic price numeraire. Costs were categorised into traded goods, non-traded goods, foreign
skilled labour, local unskilled labour, fuel and transfer payments, and were adjusted with
33 ADB (2017). Economic Analysis of Projects. Manila, Philippines.
34 IBRD/The World Bank (2018). Where Sun Meets Water: Floating Solar PV Market Report. Washington DC.
Floating PV Candidate Site Report
September 2020 │ Rev03 112
appropriate conversion factors. The shadow exchange rate factor (SERF) was used to convert
traded costs while the shadow wage rate factor (SWRF) was used for unskilled labour. Transfer
payments and price contingencies were not considered in the analysis.
The SERF was calculated as the inverse of the standard conversion factor (SCF). SERF values for
the last five years were estimated as shown in Table 40, and the 5-year average value of 1.03 was
used in the analysis. Owing to high underemployment in Bangladesh, a shadow wage rate of 0.80
was used to estimate the economic value of unskilled labour.
The exchange rate in January 2020 of BDT 84.90 = US$1.0 was used in the analysis. All costs
were expressed in 2020 prices. A discount rate of 9 percent (according to ADB benchmark) and a
Subproject lifespan of 30 years were used in the economic assessment.
The financial and economic costs are shown in Table 41.
Table 40: Shadow Exchange Rate Factor (SERF) estimation
Item FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Average
Exports ($m)
Total exports 29,777 30,697 33,441 34,019 36,205
Export subsidy 0.02% 0.01% 0.01% 0.01% 0.01%
Imports ($m)
Total imports 36,571 37,662 39,901 43,491 54,463
Import tax 4.76% 5.16% 5.48% 6.27% 5.94%
SCF 0.97 0.97 0.97 0.97 0.97 0.97
SERF 1.03 1.03 1.03 1.04 1.04 1.03
SCF = (e × X + n × M)/[ e × X(1-tx) + n × M(1+tm)], where X = fob value of exports; M = cif value of
imports; e = elasticity of export supply (assumed to be unity); n = elasticity of import supply (assumed
to be unity); tx = tax on exports (%); tm = tax on imports (%).
Table 41: Financial and economic costs
Item Description Financial Economic
FC
($m)
LC
(BDT
million)
Total
(BDT
million)
FC
($m)
LC
(BDT
million)
Total
(BDT
million)
A Investment costs
1 Civil works 1.13 30.09 126.36 1.17 24.07 123.33
2 Equipment 5.10 0.00 432.63 5.25 0.00 446.04
3 Engineering consulting -
design and supervision
0.43 0.00 36.08 0.44 0.00 37.20
4 Inland transport 47.76 47.76 0.00 47.76 47.76
5 Taxes and duties 112.48 112.48 0.00 0.00 0.00
Sub-total (A) 6.65 190.33 755.31 6.86 71.83 654.33
Floating PV Candidate Site Report
September 2020 │ Rev03 113
Item Description Financial Economic
B Other investment costs
1 Land & civil works 3.44 3.44 0.00 2.75 2.75
2 Environmental and
social costs
22.34 22.34 0.00 22.34 22.34
3 Subproject management
& construction
supervision
38.40 38.40 0.00 38.40 38.40
Sub-total (B) 0.00 64.18 64.18 0.00 63.49 63.49
Total base costs (A) +
(B)
6.65 254.50 819.49 6.86 135.31 717.82
C Contingency
1 Physical 0.53 20.36 65.56 0.55 20.36 66.96
2 Price 0.31 22.40 48.33 0.00 0.00 0.00
Sub-total (C) 0.84 42.76 113.89 0.55 20.36 66.96
D Financial charges during implementation
1 Interest during
implementation
0.78 4.96 71.57 0.00 0.00 0.00
2 Commitment charges 0.01 0.98 0.00 0.00 0.00
3 Front end fee 0.00 0.00 0.00 0.00
Sub-total (D) 0.80 4.96 72.55 0.00 0.00 0.00
Total Subproject cost
(A) + (B) + (C) + (D)
8.29 302.22 1,005.93 7.41 155.67 784.78
9.2.3 Subproject benefits
Various benefits have been cited in the literature for floating solar PV projects35. This includes: i)
higher level of generation compared with ground mounted systems due to the cooling effect of
water bodies; ii) no land is being used hence avoiding the potential conflict between power
generation and food production; iii) and others such as reduction of water evaporation due to the
shading which limits the evaporative effect of wind, and water quality improvement due to reduced
algae growth. In addition, some studies have indicated that floating solar PV systems could
potentially reduce fish populations which many livelihoods depend upon and could have a negative
economic impact to the local community.
Many of the above benefits (costs) are however difficult to quantify. This study however focuses
mainly on quantifiable benefits of the Subproject. In the ‘without the project’ case, electricity
generation in the Khulna District where Joydia Baor is located, would be mainly coming from fossil
fuels (natural gas, fuel oil and diesel fuel). Benefits being quantified in this study (‘with the project’
35 See for example World Bank Group, ESMAP and SERIS. 2018. Where Sun Meets Water: Floating Solar
Market Report—Executive Summary. Washington, DC: World Bank.
Floating PV Candidate Site Report
September 2020 │ Rev03 114
case) are mainly fossil fuel savings in power generation and the reduction of carbon dioxide
emissions associated with lower fossil fuel consumption.
Outputs of the Subproject are classified into incremental and non-incremental36. Incremental
outputs refer to the additional output produced by the Subproject over and above what would be
available in the without-Subproject situation. Non-incremental output is the output produced by the
Subproject that displaces high cost or unreliable supplies without the Subproject. Incremental
outputs are valued using the WTP37 methodology with adjustments made for transmission and
distribution losses, while non-incremental outputs are valued at resource cost savings.
Energy generation from the proposed 9.072 MWp Joydia Baor floating solar PV plant is expected
to displace fuel fossil generation rather than meeting Khulna Division’s incremental demand. This
study considers Joydia’s floating solar PV output to be non-incremental and valued at resource
cost savings at short-run marginal cost. Prices of displaced fossil fuels prices were derived from
the projected global spot market prices of crude oil (global average), natural gas (Japan’s LNG spot
prices) and coal (Australian coal spot prices) from the most recent World Bank Commodity Markets
Outlook38.
Similarly, the Subproject’s non-incremental output would also contribute to reducing carbon dioxide
emissions from the power sector. The ADB 2017 Economic Analysis guideline recommends to use
the Intergovernmental Panel for Climate Change (IPCC) methodology in translating the renewable
power generation into carbon dioxide equivalent reductions. The methodology for estimating the
grid emission factor is data intensive. In the case of Bangladesh, this study uses the grid emissions
factor of 0.635 tCO2 per MWh for wind and solar PV projects as recommended by the ADB
Guideline for Estimating Greenhouse Gas Emissions39. In addition, the Guideline also suggests to
use a value of US$ 36.30 per tonne of CO2 (in 2016 prices) as a global social cost of carbon
dioxide, and to be escalated at 2% per year to represent the ‘potential of increasing marginal
damage of global warming over time’.
As an alternative analysis, the floating solar PV project could potentially displace a ground-mounted
solar PV system. One of the floating solar PV benefits is the savings of land that would have been
used for a land-based solar PV project. In valuing the land, ADB’s 2017 guideline recommended
to use the opportunity cost rather than the market prices of land. In the case of Bangladesh however
floating solar PV projects would not likely displace land-based solar PV systems, hence this level
of analysis is not being considered in the study.
9.2.4 Economic feasibility
The proposed floating solar PV project will represent as one of the first utility-scale floating solar
PV projects in Bangladesh. On its first year of operation, the Subproject is expected to generate
13,563,495 kWh of electricity (P50 value). Over its estimated lifespan of 25 years, annual electricity
36 ADB (2017). Economic Analysis of Projects. Manila, Philippines.
37 WTP - willingness-to-pay
38 World Bank (2016). Commodity Markets Outlook. January 2016 update.
39 ADB (2017). Guidelines for Estimating Greenhouse Gas Emissions Asian Development Projects: Additional
Guidance for Clean Energy Projects. Manila, Philippines.
Floating PV Candidate Site Report
September 2020 │ Rev03 115
generation is expected to decline gradually at the rate of 0.4%. The present value generation would
amount to 129,154,630 kWh based on a discount rate of 9% (ADB benchmark).
The electricity generated from the Subproject will be injected into the Khulna Power Zone and
estimated to displace generation from fossil fuel-based power plants in the Division. As of 2018,
these conventional power units generated around 2,572 GWh of electricity. Of these, gas-fired
power plants accounted 48.9% share, diesel-fired power plants 41.2% and fuel oil-fired plants
9.9%. This study used the said fossil fuel electricity generation mix to estimate the amount of each
fuel type displaced by the Subproject. In calculating the displaced fuel consumption from electricity
generation data, the study takes into account the existing power plant efficiencies and calorific
values. From Bangladesh Power Development Board’s (BPDB) database, the study estimated the
weighted average efficiency of power plants in Khulna Division. For 2018, the weighted average
efficiency of gas-fired power plants was 38.84% while those of diesel-fired power plants and fuel
oil-fired plants were 38.73% and 38.00% respectively.
With the above, the yearly savings by fuel type was estimated. These physical savings was
converted to economic values using the projected delivered prices of diesel, fuel oil and natural
gas derived from World Bank’s Commodity Markets Outlook. Using a discount rate of 9%, the
present value of the savings throughout the Subproject’s lifetime would amount to BDT 1,074
million.
In addition to the displaced fuel, the study also estimated the corresponding reductions of carbon
dioxide emissions that would be generated by the Subproject. With the recommended grid emission
factor of 0.635 tCO2 per MWh for wind and solar PV projects in Bangladesh, the Subproject could
potentially contribute, in present value terms, a reduction of 82,013 tons of carbon dioxide
equivalent emissions for the period of 25 years.
In estimating the value of the above benefit, the study used the recommended value for global
social cost of carbon dioxide emissions to the atmosphere. The recommended unit value was
originally expressed in terms of 2016 prices. The adjusted value, in terms of 2019 prices, amounts
to US$ 38.67 per ton of carbon dioxide equivalent. Following the ADB Guideline, the study also
escalated this value at an annual rate of 2% to reflect the rising marginal damage of climate change.
In total, the present value benefit would amount to BDT 360 million throughout the Subproject
lifetime.
The estimated benefits yield a robust investment EIRR. Considering only the displaced fuel, the
EIRR would amount to 9.31% which is just slightly higher than the benchmark rate, and including
the reduction of carbon emissions, the EIRR would increase to 14.79%.
The study also calculated EIRRs for both P75 and P90 values of electricity generation. The results
show that EIRRs would slightly decrease with higher confidence level of electricity generation. The
EIRRs for ‘without GHG savings’ would decrease to a rate marginally lower than the benchmark
rate while those for ‘with GHG savings’ would remain at robust rate. For P75, the EIRRs are 8.71%
and 14.09% for ‘without GHG savings’ and ‘with GHG savings’, respectively. Those for P90 are
8.16% (below the benchmark rate) and 13.46% (above the benchmark rate), respectively.
Floating PV Candidate Site Report
September 2020 │ Rev03 116
Table 42: EIRR Calculation for 9.072 MWp Joydia Baor Floating Solar PV (for P50)
Year
Costs (million BDT) Benefits (million BDT) Net benefits (million BDT)
Capital O&M Fuel
savings
GHG
savings
Without
GHG
savings
With GHG
savings
2020 784.78 0.00 0.00 0.00 -784.78 -784.78
2021 0.00 21.13 123.23 32.19 102.10 134.28
2022 0.00 21.13 121.43 32.70 100.30 133.00
2023 0.00 32.76 119.99 33.22 87.22 120.44
2024 0.00 32.76 118.56 33.75 85.79 119.54
2025 0.00 32.76 117.15 34.28 84.39 118.67
2026 0.00 32.76 113.57 34.83 80.81 115.64
2027 0.00 32.76 110.13 35.38 77.37 112.75
2028 0.00 32.76 106.84 35.95 74.08 110.02
2029 0.00 32.76 103.68 36.52 70.92 107.44
2030 0.00 32.76 100.65 37.10 67.89 104.99
2031 0.00 32.76 100.25 37.69 67.48 105.18
2032 0.00 32.76 99.85 38.29 67.08 105.38
2033 0.00 32.76 99.45 38.90 66.68 105.59
2034 0.00 32.76 99.05 39.52 66.29 105.81
2035 0.00 32.76 98.65 40.15 65.89 106.04
2036 0.00 32.76 98.26 40.79 65.50 106.28
2037 0.00 32.76 97.87 41.44 65.10 106.54
2038 0.00 32.76 97.47 42.10 64.71 106.81
2039 0.00 32.76 97.08 42.77 64.32 107.09
2040 0.00 32.76 96.70 43.45 63.93 107.38
2041 0.00 32.76 96.31 44.14 63.55 107.69
2042 0.00 32.76 95.92 44.84 63.16 108.00
2043 0.00 32.76 95.54 45.56 62.78 108.34
2044 0.00 32.76 95.16 46.28 62.39 108.68
2045 0.00 32.76 94.78 47.02 62.01 109.03
2046 0.00 32.76 94.40 47.77 61.64 109.40
2047 0.00 32.76 94.02 48.53 61.26 109.79
2048 0.00 32.76 93.65 49.30 60.88 110.18
2049 0.00 32.76 93.27 50.09 60.51 110.59
2050 0.00 32.76 92.90 50.88 60.13 111.02
2051 0.00 32.76 92.53 51.69 59.76 111.46
Floating PV Candidate Site Report
September 2020 │ Rev03 117
Year
Costs (million BDT) Benefits (million BDT) Net benefits (million BDT)
Capital O&M Fuel
savings
GHG
savings
Without
GHG
savings
With GHG
savings
EIRR 9.31% 14.79%
Table 43: EIRR Calculation for 9.072 MWp Joydia Baor Floating Solar PV (for P75)
Year
Costs (million BDT) Benefits (million BDT) Net benefits (million BDT)
Capital O&M Fuel
savings
GHG
savings
Without
GHG
savings
With GHG
savings
2020 784.78 0.00 0.00 0.00 -784.78 -784.78
2021 0.00 21.13 119.10 31.11 97.97 129.08
2022 0.00 21.13 117.36 31.60 96.23 127.83
2023 0.00 32.76 115.97 32.11 83.20 115.31
2024 0.00 32.76 114.59 32.62 81.82 114.44
2025 0.00 32.76 113.23 33.14 80.46 113.60
2026 0.00 32.76 109.76 33.66 77.00 110.66
2027 0.00 32.76 106.44 34.20 73.68 107.88
2028 0.00 32.76 103.26 34.74 70.50 105.24
2029 0.00 32.76 100.21 35.30 67.44 102.74
2030 0.00 32.76 97.28 35.86 64.51 100.37
2031 0.00 32.76 96.89 36.43 64.13 100.55
2032 0.00 32.76 96.50 37.01 63.74 100.75
2033 0.00 32.76 96.12 37.60 63.35 100.95
2034 0.00 32.76 95.73 38.20 62.97 101.16
2035 0.00 32.76 95.35 38.81 62.58 101.39
2036 0.00 32.76 94.97 39.42 62.20 101.63
2037 0.00 32.76 94.59 40.05 61.82 101.87
2038 0.00 32.76 94.21 40.69 61.45 102.13
2039 0.00 32.76 93.83 41.34 61.07 102.40
2040 0.00 32.76 93.46 41.99 60.69 102.69
2041 0.00 32.76 93.08 42.66 60.32 102.98
2042 0.00 32.76 92.71 43.34 59.95 103.29
2043 0.00 32.76 92.34 44.03 59.58 103.61
2044 0.00 32.76 91.97 44.73 59.21 103.94
2045 0.00 32.76 91.60 45.44 58.84 104.28
2046 0.00 32.76 91.24 46.17 58.47 104.64
Floating PV Candidate Site Report
September 2020 │ Rev03 118
Year
Costs (million BDT) Benefits (million BDT) Net benefits (million BDT)
Capital O&M Fuel
savings
GHG
savings
Without
GHG
savings
With GHG
savings
2047 0.00 32.76 90.87 46.90 58.11 105.01
2048 0.00 32.76 90.51 47.65 57.74 105.39
2049 0.00 32.76 90.15 48.41 57.38 105.79
2050 0.00 32.76 89.78 49.18 57.02 106.20
2051 0.00 32.76 89.43 49.96 56.66 106.62 EIRR 8.71% 14.09%
Table 44: EIRR Calculation for 9.072 MWp Joydia Baor Floating Solar PV (for P90)
Year
Costs (million BDT) Benefits (million BDT) Net benefits (million BDT)
Capital O&M Fuel
savings
GHG
savings
Without
GHG
savings
With GHG
savings
2020 784.78 0.00 0.00 0.00 -784.78 -784.78
2021 0.00 21.13 115.39 30.14 94.26 124.40
2022 0.00 21.13 113.71 30.62 92.57 123.19
2023 0.00 32.76 112.36 31.11 79.59 110.70
2024 0.00 32.76 111.02 31.60 78.25 109.85
2025 0.00 32.76 109.70 32.10 76.94 109.04
2026 0.00 32.76 106.35 32.61 73.58 106.20
2027 0.00 32.76 103.13 33.13 70.36 103.50
2028 0.00 32.76 100.04 33.66 67.28 100.94
2029 0.00 32.76 97.09 34.20 64.32 98.52
2030 0.00 32.76 94.25 34.74 61.49 96.23
2031 0.00 32.76 93.87 35.29 61.11 96.40
2032 0.00 32.76 93.50 35.86 60.73 96.59
2033 0.00 32.76 93.12 36.43 60.36 96.79
2034 0.00 32.76 92.75 37.01 59.99 96.99
2035 0.00 32.76 92.38 37.60 59.62 97.21
2036 0.00 32.76 92.01 38.20 59.25 97.44
2037 0.00 32.76 91.64 38.80 58.88 97.68
2038 0.00 32.76 91.27 39.42 58.51 97.93
2039 0.00 32.76 90.91 40.05 58.15 98.19
2040 0.00 32.76 90.55 40.69 57.78 98.47
2041 0.00 32.76 90.18 41.33 57.42 98.75
Floating PV Candidate Site Report
September 2020 │ Rev03 119
Year
Costs (million BDT) Benefits (million BDT) Net benefits (million BDT)
Capital O&M Fuel
savings
GHG
savings
Without
GHG
savings
With GHG
savings
2042 0.00 32.76 89.82 41.99 57.06 99.05
2043 0.00 32.76 89.46 42.66 56.70 99.36
2044 0.00 32.76 89.11 43.34 56.34 99.68
2045 0.00 32.76 88.75 44.03 55.99 100.02
2046 0.00 32.76 88.39 44.73 55.63 100.36
2047 0.00 32.76 88.04 45.44 55.28 100.72
2048 0.00 32.76 87.69 46.17 54.93 101.09
2049 0.00 32.76 87.34 46.90 54.57 101.48
2050 0.00 32.76 86.99 47.65 54.23 101.87
2051 0.00 32.76 86.64 48.41 53.88 102.28
EIRR 8.16% 13.46%
9.2.5 Sensitivity and risk analysis
Risks exist that these projects would not achieve the hurdle economic returns due to uncertainties
in the values of key parameters used in the analysis. These parameters include capital costs (10%
increase), O&M costs (10% increase) and energy yield (5% decrease). To investigate the impact
of the uncertainties on Subproject viability, the sensitivity of EIRR to the variation of these
parameters were analysed. The sensitivity analysis shows that the potential variation of key
Subproject parameters such as an increase in capital and O&M costs as well as the combination
of these parameters under the ‘without the GHG savings case’ would generate EIRRs below the
benchmark rate. On the other hand, considering the social impacts of climate change, even with
the combination of the changes of these parameters would still render the Subproject economically
viable.
The study also estimated the switching values for Subproject. The switching value is defined as the
percentage change in a variable required to make the Subproject EIRR equal to the benchmark
discount rate (in this case 9%). The switching value of the capital cost under the ‘with the GHG
impact case’ is relatively high. This means that it will take a high percentage increase in capital cost
to make the Subproject economically unviable.
Table 45: Sensitivity analysis (P50)40
Item EIRR41 (%) Switching Value (%)
Without GHG With GHG Without GHG With GHG
Base capital
costs
9.31% 14.79%
40 Source: ADB estimates
41 EIRR = economic internal rate of return
Floating PV Candidate Site Report
September 2020 │ Rev03 120
Item EIRR41 (%) Switching Value (%)
Without GHG With GHG Without GHG With GHG
Capital costs
increase (10%)
8.13% 13.27% 2.50% 51.60%
O&M costs
increase (10%)
8.80% 14.37%
Yield decrease
(-5%)
8.41% 13.74%
Combined 6.97% 11.91%
9.2.6 Conclusion
The economic assessment shows that the economic performance of the Subproject is robust. The
Subproject EIRR is above the benchmark rate of 9% used in the study. The sensitivity analysis
shows that even with high increase in key investment parameters under the ‘with GHG savings
case’, the proposed Subproject would remain economically viable. From an economic standpoint,
the Subproject is considered to be beneficial to the economy and should be financially supported.
Floating PV Candidate Site Report
September 2020 │ Rev03 121
10 Climate Hazard Risk Assessment for Joydia Baor
10.1 Introduction
This section provides an initial review of the future climate change hazard risk for the Joydia
Subproject. It is based on the key findings from the site visit undertaken between the 20th and 23rd
of November 2019 and the Climate Risk and Vulnerability Analysis (CRVA) currently under
preparation for this Subproject. In this context the review of climate hazard risks for the Subproject
should be considered supplementary to the full CRVA for the Subproject.
The climate risk management approach of the Asian Development Bank (ADB) aims to reduce
risks resulting from climate change to investment projects in Asia and the Pacific. ADB’s framework
identifies climate change risks to Subproject performance in the early stages of Subproject
development and incorporates adaptation measures in the design of projects at risk.
This review corresponds to the first step in this process, and involves the preliminary climate
change assessment for the Subproject to identify the potential risks that may affect the feasibility
of the Subproject, and for the evaluation and selection of climate resilience measures to include in
the Subproject design and implantation arrangements.
10.2 Biophysical context
Joydia Baor is a freshwater wetland or oxbow lake of fluvial origin located on the Ganges floodplain
in Jhenaidah District, in the southwestern part of Bangladesh. There are thousands of lakes of
varying sizes in Bangladesh, the greatest concentrations being in the main delta region covering
the districts of Rajshahi, Pabna, Khulna, Jessore, Faridpur, Comilla and Noakhali. The notable
baors of the country include Sagarkhali, Jaleshwar, Khedapara, Rampur, Pathanpara, Kathgara,
Jogini Bhagini, Ichamati, Bukbhara, Marjat, Harina and Arial. They range in size from half a square
kilometre to 13 km2. 42
Baors receive water only when the parent river is in high flood. Usually, during wet monsoon a baor
will receive local rainwater, and will be subject to periodic flooding and moderate to high levels of
sedimentation and siltation.42
10.3 Current climate
Joydia Baor lies in the path of heavily moisture-laden monsoon winds. The rainy season extends
from June through November and about 80% of the annual rainfall is concentrated in this season.
The annual rainfall in the area is estimated at 2,200 mm to 3600 mm. Humidity is 35-45% between
November and March when it increases to approximately 80% during the rainy season.
Average temperatures are 26.1⁰C, however this can vary between 15⁰C and 34⁰C throughout the
year. The warmest months coincide with the rainy season (March-September), while winter
(December-February) receives less rainfall. It is one of the wettest countries of the world, with most
areas receiving at least 1500 mm and others receiving as much as 5800 mm of rainfall per year.
42 Source: Banglapedia
Floating PV Candidate Site Report
September 2020 │ Rev03 122
Rainfall is driven by the Southwest monsoon, which originates over the Indian Ocean and carries
warm, moist, and unstable air, beginning approximately during the first week of June and ending in
the first week of October.
Figure 14 shows mean historical monthly temperature and rainfall simulated climate data-set for
Jhenaidah for the time period 1985-2014.
Figure 14: Average monthly temperature and rainfall for Jhenaidah (1985-2014)43
In Figure 14, the ‘mean daily maximum’ shows the maximum temperature of an average day for
every month for Jhenaidah. Likewise, ‘mean daily minimum’ (shown as the solid blue line) shows
the average minimum temperature. Hot days and cold nights (dashed red and blue lines) show the
average of the hottest day and coldest night of each month of the last 30 years.
Figure 15 shows the maximum temperature diagram for Jhenaidah and displays how many days
per month reach extreme temperatures (i.e. > 40oC).
43 Source: Meteoblue global NEMS weather model
Floating PV Candidate Site Report
September 2020 │ Rev03 123
Figure 15: Temperature extremes for Jhenaidah43
10.4 Observed and projected climate change
Over the past 100 years (1906-2005), the average temperature in Bangladesh has increased about
0.3°C. Average monsoon-season maximum and minimum temperatures show an increasing trend
annually at the rate of 0.05°C and 0.03°C, respectively. An increasing trend of about 1°C in May
and 0.5°C in November during the 14-year period from 1985 to 1998 has also been observed.
Annual rainfall in Bangladesh has decreased by 2 to 3 per cent across Bangladesh this century,
with most of this reduction occurring during the December-February period, the wettest season of
the year (Ramamasy & Baas, 2007).
The majority of climate change projections for Bangladesh suggest that the average temperature
in the country is likely to increase by 1°C by 2030, 1.4°C by 2050 and 2.4°C by 2100 (Ramamasy
& Baas, 2007) against the baseline period (1960-1990), and a significant increasing trends in
cyclone frequency and intensity over the Bay of Bengal during November and May.
The Fifth Assessment Report of the IPCC from 2014 stresses that climate change-related risks
stemming from extreme events such as extreme precipitation, cyclones and flooding can already
be observed in Bangladesh. Global average tropical cyclone wind speed and rainfall is likely to
increase in the future, and the global average frequency of tropical cyclones is likely to decrease
or remain unchanged.
In the Bay of Bengal, it is expected that the frequency of tropical cyclones may increase and,
according to the IPCC’s Third Assessment Report, there is “evidence that the peak intensity may
increase by 5% to 10% and precipitation rates may increase by 20% to 30%” (IPCC 2001). Hence,
the present hazard level in areas currently affected by tropical cyclones may increase in the long-
term.
Floating PV Candidate Site Report
September 2020 │ Rev03 124
Figure 16 shows the historical cyclone tracks for the Bay of Bengal between 1969 and 2009.
Subprojects located in such areas should be robust to future increases in cyclone hazard. Although
most of the impacts associated with tropical storms and cyclones occur in the ocean and coastal
areas, these storms can impact inland areas such as Jhenaidah.
Figure 16: Cyclone tracks for the Bay of Bengal 1969-200944
10.5 Assessed climate change risks for Joydia
The Subproject is located on the Ganges floodplain in Jhenaidah District, which is already affected
by a range of climate-induces hazard risks, including strong winds and cyclonic events, variations
in temperature and rainfall, and flooding and sedimentation.
Table 46 provides a preliminary assessment of the climate hazards risks for the Subproject, which
should be considered in Subproject design and implementation to promote disaster and climate
resilience. The assessment highlights the likelihood of different natural hazards affecting the
Subproject components and infrastructure (i.e. these being Very Low, Low, Medium and High), and
provides an insight the opportunities and constraints that need to be considered in this Feasibility
Study.
The hazard risk ratings are derived based on the climate change analysis undertaken in the CRVA
for the Subproject and modulated based on the contextual understanding of Subproject location
and biophysical conditions assessed during the field visits.
However, it is expected that these hazards will be exacerbated by changes in the climate and the
intensity of climatic disasters like tropical cyclones, droughts and floods into the future and these
need to be fully taken into account during the detailed design phase of the Subproject, especially
in relation to the sensitivity of FVP infrastructure to:
Increasing temperatures extremes and hot days;
Increasing intensity of rainfall and associated fluctuations in water levels;
44 Source: WBG Climate Change Knowledge Portal
Floating PV Candidate Site Report
September 2020 │ Rev03 125
Increasing frequency and intensity of flood events and associated sedimentation; and
Increasing intensity of wind velocity and cyclone weather conditions.
Floating PV Candidate Site Report
September 2020 │ Rev03 126
Table 46: Preliminary climate hazard risk screening for Joydia Baor
Climate hazard risk Climate change Risk assessment Risk mitigation measures
Rising temperatures and extreme
heat hazard risk
(Hazard level: MEDIUM)
According to the Intergovernmental
panel on Climate Change (IPCC,
2013), annual mean temperatures
and extremely high daily
temperatures will continue to rise,
and warming will be large
compared to natural variability.
Temperatures in Bangladesh have
warmed and will continue to warm
with more very hot days by 2050
(Very high confidence).
Whilst the IPCC predict that the
temperature increase over the next
fifty years in Bangladesh will be
slightly lower than the worldwide
average, it will still be significant.
This increase may be as high as
1°C by 2030 and 1.4°C by 2050
under the worst cases (IPCC
2013). Extreme maximum
temperatures are also projected to
increase.
In the adjacent District of Jessore,
extreme heat hazard is classified
as MEDIUM based on modelled
heat information currently
available.
This means that prolonged
exposure to extreme heat, resulting
in heat stress, is expected to occur
at least once in the next five years.
The location of FVP infrastructure
on the Baor water surface will
reduce the impact of extreme
temperature exposure on the
Subproject (due to the localised
effects of evaporation from the
wetland surface).
Suitable risk reduction and
control measures exist to
mitigate the adverse impacts of
increasing temperatures and
extreme heat hazard risk on
FVP and associated
infrastructure and assets.
In particular, Subproject
planning decisions, Subproject
design, construction methods
and construction materials
should adhere to international
design requirements and take
account of extreme heat hazard
risks to minimise damage and/or
deterioration of energy
generation capacity.
Consideration should be given to
the vulnerability of other assets
within the Subproject's
dependency network.
Specific attention should be given
to the identification and select
selection of suitable materials for
construction of FVP infrastructure
assets.
Floating PV Candidate Site Report
September 2020 │ Rev03 127
Climate hazard risk Climate change Risk assessment Risk mitigation measures
Seasonal rainfall, rainfall intensity and flooding hazard risk
(Hazard level: MEDIUM)
Most models covering Bangladesh
predict increased average annual
and seasonal rainfall into the
future. It is likely that there will be
changes in rainfall patterns,
seasonality and drought through to
2050, with annual precipitation
projected to increase by 70mm,
which represents a 3.9% increase
over the baseline period.
IPCC forecasts for Bangladesh
suggest both increased average
monthly rainfall of between 5.0%
and 9.0% by 2050, and an
increase in extreme rainfall days
from 4 times per year to more than
6 times per year by 2050 (IPCC
2013).
Flood hazard for the Subproject is
assessed as MEDUIM based on
modelled flood information
currently available, and the actual
location of the FVP infrastructure
being on the Baor.
Flood hazard on FVP infrastructure
is likely to be low, with the
exception of areas of rapid
sedimentation and siltation.
It is highly likely that the present
hazard level from flooding and
sedimentation is likely to increase
in the future due to climate change
and the increasing incidence of
extreme rainfall events.
Suitable risk reduction and
control measures exist to
mitigate the adverse impacts of
extreme rainfall and flooding on
FVP and associated
infrastructure and assets.
Subproject planning decisions,
Subproject design, and
construction methods should
take account of flood levels and
hazard.
The position of Subproject
components in the landscape
will be key in defining whether
there is a risk.
Cyclones, flooding and rapid
sedimentation pose the greatest
risk to Subproject infrastructure
and assets, and exposure to this
hazard should be minimised
through the appropriate siting
and location of pontoons.
Consideration should be given to
the vulnerability of assets within
the Subproject's dependency
network including transmission
lines and substations.
High wind speed and tropical cyclone hazard risk
Global average tropical cyclone wind speed and rainfall are likely to
For the Subproject, the cyclone
hazard is classified as HIGH
Suitable risk reduction and
control measures exist to
Floating PV Candidate Site Report
September 2020 │ Rev03 128
Climate hazard risk Climate change Risk assessment Risk mitigation measures
(Hazard level: HIGH) increase in the future, and the global average frequency of tropical cyclones is likely to decrease or remain unchanged. It is projected that the frequency of intense tropical cyclones will increase substantially in areas such as the Bay of Bengal that are currently severely affected by tropical cyclones (IPCC, 2013). Climate change modelling for the Bay of Bengal predicts an increase in the intensity of cyclones of 60% by 2030, and an increase in the intensity of cyclones of 100 % by 2050 (IPCC, 2013).
It is also likely that the average
tropical cyclone wind speed and
rainfall will increase in the future.
Cyclones are defined as storms
with winds of between 119
kilometres per hour and can reach
wind speeds of over 220 kilometres
per hour.
according to the information that is
currently available.
This means that there is more than
a 20% chance of potentially
damaging wind speeds occurring in
the Subproject area in the next 10
years.
Increasing intensity and frequency
of extreme storm events and
cyclones, accompanied by high
winds and intense rainfall can
cause extensive flooding and
damage to critical infrastructure
such as power plants and
transmission infrastructure.
mitigate the adverse impacts of
high wind speed and tropical
cyclone hazard risks to FVP and
associated infrastructure and
assets.
Based on this information,
Subproject planning decisions,
Subproject design, layout and
construction methods should
take account of the level of high
wind and cyclone hazard in the
Subproject area.
Consideration should also be
given to the integration and
incorporation of the emergency
response and early warning
systems for cyclones into the
Subproject.
Floating PV Candidate Site Report
September 2020 │ Rev03 129
10.6 Potential climate proofing measures
Based on the review of literature and best practice undertaken for the CRVA, we further identified
a limited range of hazard risk mitigation measures for climate proofing infrastructure proposed
under this Subproject, including the following:
FVP infrastructure design and construction standards: It is recommended that the effects of
changing flood levels and behaviour due to climate change be taken into account and
accommodated in the Subproject design process through application of appropriate
international standards and guidelines.
Placement, design and alignment of FVP infrastructure assets. FVP infrastructure to be located
in low risk areas to minimise system vulnerabilities to possible climate impacts and threats from
string winds, currents and debris associated with floods.
Materials selection. Identify and select suitable materials for construction of infrastructure
assets and structures to minimise damage and/or deterioration of FVP infrastructure cyclonic
winds and other related climate change impacts.
It is challenging to fully mitigate extreme event risk through design, and insurance will also be
required to respond to any unexpectedly large events which may occur over the Subproject lifetime.
Floating PV Candidate Site Report
September 2020 │ Rev03 130
Appendices
A. Subproject Configuration and Layout
The CAD layout and electrical design details are provided separately to the client.
B. Irradiation Database Information
The Consultant frequently reviews database updates available on the market and considers the
datasets included in Table 47 to be the most applicable to a detailed irradiation analysis for this
site.
Table 47: Irradiation data sources
Database Description
Meteonorm 7.3 Meteonorm blends ground and satellite data for the period 1991-2010 from
a database of approximately 1,325 weather stations with global radiation and
temperature data. Where no radiation measurement is available nearer than
200 km (or 50 km in Europe) from the selected location, satellite information
is used. If the nearest site is more than 30 km away (or 10 km in Europe), a
mixture of ground and satellite information is used. In Europe the spatial
resolution is between 2-3 km and 8 km for the rest of the world. The
uncertainty of ground measurements ranges between 2% and 10%.
PVGIS (SARAH)
Photovoltaic
Geographical
Information
System
The Surface Solar Radiation Data Set - Heliosat (SARAH) is a satellite-based
climatology of the solar surface irradiance, the surface direct normalised
irradiance and the effective cloud albedo derived from observations from
geostationary Meteosat satellites. This data cover Europe, Africa, most of
Asia, and parts of South America. The time period for the data is 2005-2016.
The data have hourly time resolution and a spatial resolution of approx. 3
arc-minutes (5.5 km).
SolarGIS iMaps This dataset is calculated from satellite observations made by Meteosat,
GOES EAST and MTSAT satellite and MACC-II and GFS, CFSR
atmospheric data. The data are spatially enhance to 1 km resolution, the
averaging periods are: 1994-2015 for Europe, Africa and the Middle East,
1999-2015 for Asia, 1999-2015 for Americas and 2007-2015 for the Pacific.
3TIER Solar
Prospecting Tool
Meteosat, GOES, GMS and MTSAT satellite visible imagery for cloudiness
and other information to model the amount of solar radiation at the Earth’s
surface is used in this dataset. Available averaging period range from 1997-
2010 in the Western Hemisphere, 1998-2010 in Europe and Africa to 1999-
2010 in South Asia, Middle East, East Asia and Oceania. The spatial
resolution is globally approximately 3 km.
NREL SUNY The model uses data from Meteosat 5 and 7 geostationary meteorological
satellites and is calculated using the semi-empirical satellite model
developed by Perez et al. This dataset has a spatial resolution of 0.1 degrees
in both latitude and longitude, or nominally 10 km in size. The time period of
the data is 2000 to 2014. The dataset covers India, Bangladesh Bhutan,
Nepal, Sri Lanka and parts of Pakistan, Afghanistan and India.
Floating PV Candidate Site Report
September 2020 │ Rev03 131
C. Irradiation Methodology
In order to determine the most accurate long-term GHI estimates, RINA continuously evaluates
databases available on the market and data selection or weighting approaches. In this research,
currently 38 locations spread over the global and in all relevant climate zones are used as
benchmark locations. The benchmark data are predominantly taken from scientific radiation
networks, which aim to provide data on climate change and model validation. Monthly and annual
reference averages are based on a recent, period spanning several years.
Following RINA’s research, weighting methods have been found to provide more accurate long-
term GHI estimates and typically outperform single databases, i.e. are superior to data selection.
This can be explained by the nature of most databases, which is predominately model-reliant in
terms of spatial resolution of information and sourcing. Furthermore, input data can be incomplete
or not fully representative for a given location. Thus, location-specific estimates of single databases
vary within modelling limits or can be biased. The most accurate single database evaluated so far
comes globally with an uncertainty (RMSE) of the annual long-term GHI estimate of 2.6%.
Weighting of various datasets appears to overcome partially this deficiency, with appropriate
database selection being crucial in this context.
RINA has reviewed various approaches to combine datasets. Weighting of the databases on the
basis of the number of years contained in each dataset and based on the inverse spatial resolution
has been found globally most accurate with an uncertainty (RMSE) of the annual long-term GHI
estimate of 2.2%. In this regard, spatial resolution and its inclusion in the weighting has shown
increased significance when comparing the results obtained for locations binned into continental,
coastal and small island sites.
For monthly long-term GHI estimates, similar results have been obtained with WM numbers being
globally more accurate than single databases.
The results of RINA’s benchmarking effort have been published on 4th International Conference
Energy & Meteorology in Bari, Italy in June 2017.
Egler, M.; Rusbridge, S.; Santos, C.: Solar Resource Databases vs Weighted Means – Results Of
A Global Benchmarking Effort; 4th International Conference Energy Meteorology 2017; Bari, Italy;
DOI: 10.13140/RG.2.2.36161.76646
Floating PV Candidate Site Report
September 2020 │ Rev03 132
D. System Design
D.1. Joydia Baor
Specific losses are dependent on the system design and key Subproject components. For this
Subproject, the modelled system design characteristics in Table 48 are based on the concept
design proposed in Section 3 and the corresponding data sheets from the manufacturers.
Table 48: Summary of modelling assumptions
Description Assumptions Source
DC installed capacity
(kWp)
9,072.00 JOYDIA_RINA LAYOUT -
G002_v2.0_for check
AC nominal capacity
(kW; at 50°C)
7,500.00
AC maximum capacity
(kW; at 45°C)
8,250.00
Grid maximum export
capacity (kW)
None Client Communication
Power factor 1.00 RINA Assumption
Table configuration 1 x 27 modules in landscape JOYDIA_RINA LAYOUT -
G002_v2.0_for check Module tilt (°) 11
Pitch (m) 1.44
Site inclination Flat
Near shadings Assumed none
Metering point location Onshore substation, assumed voltage
level of 33kV
The key equipment and string configuration is summarised in Table 49 and Table 50 below.
Table 49: Equipment assumptions summary
Equipment
type
Assumptions Source
Manufacturer and
model
Nominal
power
Units Quantity
Modules Jinko Solar Eagle
JKM400M-72L-V
400 Wp 22,680 JOYDIA_RINA
LAYOUT -
G002_v2.0_for
check Inverter Sungrow SG2500-
HV-MV-20
2,500 kVA 3
Floating PV Candidate Site Report
September 2020 │ Rev03 133
Table 50: Module string layout for PVsyst simulation
Module
String
layout
Assumptions Source
Module
model
Inverter
model
No
inver-
ters
Modules
per
string
No
strings
per
inverter
String conf 1 Eagle
JKM400M-
72L-V
SG2500-
HV-MV-20
3 27 280 JOYDIA_RINA
LAYOUT -
G002_v2.0_for
check
D.2. FPV layouts
The detailed design drawings for the FPV layout are currently available in AutoCAD or PDF format
and hence supplied separately to the client. Final PDF issue will incorporate complete layout
documentation.
E. PR losses
The explanation of the PR losses and our approach is detailed in Table 51 below.
Table 51: PR losses description
Loss Description Modelling approach
Near
shadings
Loss of irradiance affecting the modules
due to obstruction of diffuse and direct
sunlight from surrounding objects, e.g.
external shading from nearby trees or
large buildings, and mutual shading
from neighbouring modules.
Modelled using PVsyst near
shading engine, according to the
system design outlined in Appendix
D.
Spectral This takes into account the effect of
operating at a different air mass and
solar spectrum than STC.
Spectral losses are considered to
be effectively zero for crystalline
silicon modules.
Angular / IAM The loss due to times when the sun is
not 90° to the module. This causes an
increase in the reflection of light from
the solar glass.
User defined profile provided by
independent laboratory model in
PVsyst.
Soiling Loss of light reaching the cells. Over its
working life the module will collect dust,
dirt, bird droppings and vegetation on its
surface.
RINA has applied a soiling loss of
1.5% to the model, based on the
site location and satellite based
rainfall data (MERRA 2 satellite
data).
Additionally, we would recommend
that soiling is monitored and limited
under O&M.
Floating PV Candidate Site Report
September 2020 │ Rev03 134
Loss Description Modelling approach
Low
irradiance
performance
This loss considers the relative
efficiency of the module when operating
at an irradiance level other than STC.
We account for this loss in the
module pan files within PVsyst
using information provided in the
module datasheets.
LID This degradation causes performance
loss and occurs during a module’s first
operating hours in outdoor conditions
and will reduce the module’s
performance when compared to the
standard values measured at STC.
This loss is estimated based on a
review of available literature on LID
effects in crystalline silicon
modules.
Module
quality /
power
tolerance
The loss / gain due to the module power
tolerance is a result of the deviation in
the average effective module efficiency
with respect to manufacturer
specifications.
This loss is estimated based on the
datasheet module tolerance
information.
Module
temperature
losses
This takes into account of the loss when
operating at a temperature other than
STC.
Modelled within PVsyst using
module datasheet information and
based on ambient temperature
information taken from Meteonorm
7.
Shading:
electrical
effect
Loss due to the current of a string of
modules / cells being reduced to the
current in the most shaded module /
cell, this loss identifies the electrical
effect due to the near shadings
described above.
Modelled using PVsyst near
shading engine, according to the
system design outlined in Appendix
D.
Mismatch Similar to the previous, this effect takes
place when combining modules with
varied characteristics, such as
variations between allowable
manufacturing tolerances, which will
again limit the current and ultimately the
power for all the modules linked in the
string.
This loss is estimated based on the
inverter type and module tolerance,
informed by RINA’s experience of
real module test data.
Ohmics, DC
wiring
Electrical loss due to the Joule Effect
proportional to the voltage drop along
the wiring between the modules and the
inverters.
A max. voltage drop of 2% at STC
has been estimated based on
RINA’s experience for this type of
project design.
Inverter
efficiency
Loss due to inverter inefficiencies in
converting DC power from the modules
to an AC power the grid can accept.
Modelled in PVsyst based on
datasheet inverter efficiency
information.
Floating PV Candidate Site Report
September 2020 │ Rev03 135
Loss Description Modelling approach
Undersizing of
the inverter
This power loss is caused when inverter
power is determined by the AC output
power rating of the inverter components
rather than available DC power at its
input from the PV system. This loss
typically occurs due to the DC field
being oversized with respect to the AC
rated output of the inverter.
This is modelled in PVsyst based
on module and inverter datasheet
information as well as the electrical
design for the site.
MPPT
performance
Loss due to accuracy of the maximum
power point tracking algorithm of the
inverter. As operating conditions
change, the inverter must determine the
maximum power available from the
modules and adjusts the operating point
as required. The accuracy of this control
algorithm incurs a loss.
RINA has developed a
methodology to estimate the MPPT
loss, based on climatic information
for the site region, and detailed
inverter efficiency information if
available.
Ohmics, AC
LV wiring
Electrical loss due to the Joule Effect
proportional to the voltage drop along
the wiring between the inverters and the
transformers.
A max. loss of 0.3% at STC has
been estimated based on RINA’s
experience for this type of project
design and site conditions.
LV to MV
transformer
Loss due to how efficiently the
transformer is able to convert the power
from LV to MV for compliance with the
connection characteristics of the grid.
Estimated based on RINA’s
experience for this type of project
design and site conditions.
More detailed analysis can be
applied if transformer datasheets
are provided for review.
Ohmics, AC
MV wiring
Electrical loss due to the Joule Effect
proportional to the voltage drop along
the wiring between the transformers and
point of connection.
Estimated based on RINA’s
experience for this type of project
design and site conditions
considering the connection point to
be at 33 kV level.
Self-
consumption
Loss due to energy consumption from
the site deducted from the generation,
which can include fans, heaters, air
conditioning, CCTV, lights, etc. This
loss does not account for the imported
energy when the plant is not producing
energy, i.e. self-consumption during
standby and night-time is excluded.
Estimated based on RINA’s
experience for this type of project
and, location.
This loss is also exclusive of any
large on site loads.
Module
degradation
Loss due to natural degradation of the
modules performance during its
operating life.
RINA has undertaken a literature
review on module degradation, and
considers a linear annual
degradation rate of 0.4% to be an
appropriate assumption for
crystalline silicon modules.
Floating PV Candidate Site Report
September 2020 │ Rev03 136
F. Uncertainty in Yield Modelling Assumptions
Uncertainties in the GHI, GII and PR modelling assumptions are shown in Table 52. Note these
figures impact the overall yield of the plant.
Table 52: Yield modelling uncertainty
Item Uncertainty
on energy
Explanation
Global Horizontal
Irradiance
± 3.4% Uncertainty associated with metrological and methodical
uncertainty of the site-specific solar resource and the
applied value in yield calculations.
Horizontal-to-
inclined calculation
± 0.8% Additional uncertainty associated with the calculation
model for the different components of inclined surface
irradiation.
Near shadings ± 1.0% Uncertainty arising from the temporal resolution and from
the approximations made in the simulation.
Spectral ± 0.5% Uncertainty due to the estimation of the effect of solar
spectrum on modules according to literature.
Angular / IAM ± 0.3% Uncertainty associated with the calculation model.
Soiling ± 2.0% Uncertainty associated with the estimation of soiling loss.
Low irradiation ± 0.4% Uncertainties of η(G) mainly arise only during periods of
low irradiance.
LID ± 0.6% Uncertainty associated with the estimation of LID loss.
Module quality /
power tolerance
± 1.5% Uncertainty (standard deviation) obtained in round-robin
tests performed at international calibration laboratories.
Module
temperature
losses
± 1.0% Uncertainty arising from uncertainties of input data.
Mismatch ± 0.4% Uncertainty coming from input data tolerances as well as
approximations made in the calculation.
Ohmics,
DC wiring
± 0.4% Uncertainty arising mainly due to the calculation of low DC
power.
Inverter efficiency ± 1.0% Uncertainty arising from uncertainties of input data as well
as approximations made in the model.
Undersizing of the
inverter
± 0.0% Uncertainty induced by temporal resolution and approxi-
mations made in the simulation.
MPPT
performance
± 0.1% Uncertainty coming from input data uncertainties and
approximations made in the calculation.
Ohmics,
AC LV wiring
± 0.1% Uncertainty arising mainly due to the calculation of low
voltage AC power.
Ohmics,
AC MV wiring
± 0.2% Uncertainty arising mainly due to the calculation of medium
voltage AC power.
LV to MV
transformer
± 0.5% Uncertainty in the calculation of transformer losses.
Floating PV Candidate Site Report
September 2020 │ Rev03 137
Item Uncertainty
on energy
Explanation
Self-consumption ± 0.3% Uncertainty in the calculation of self-consumption losses.
Degradation ± 0.3% Uncertainty due to the assumption of published
degradation rates.
Total uncertainty ± 4.8%
GHI uncertainty is combined uncertainty from basic metrological calibration uncertainty (±1.6%),
RINA’s WM approach (see Appendix C) and site-specific variance of the solar resource databases
as presented in Section 4.2. Uncertainties are combined using the standard error approach.
The overall uncertainty in the yield estimations is calculated via the standard error approach and
corresponds to a value of ± 4.8%.
G. Grid Impact Study
The Grid Impact Study has been issued as a separate report to the Client.
H. Breakdown of Subproject Cost Estimates
Table 53: Subproject base cost estimates
Sl No Item Total cost –
base case
(Million US$)
A Investment Costs
1 Civil Works
Anchoring and Mooring system $0.23
Floating system $0.91
Labour cost $0.35
Subtotal $1.49
2 Equipment
PV modules $2.00 Inverters $0.53
Meteorological stations $0.01
DC & AC cables $0.41
Grid infrastructure to connect the Subproject $1.49
Launching platform, jetty, maintenance boats & water quality
sensors
$0.11
Testing, commissioning and performance test $0.01
Profit margin $0.55
Subtotal $5.10
3 Engineering Consulting - Design and Supervision
Floating PV Candidate Site Report
September 2020 │ Rev03 138
Sl No Item Total cost –
base case
(Million US$)
Grid and power system studies $0.02
Feasibility study $0.05
Yield study $0.01
Geotechnical study $0.02
Bathymetry study $0.01
Environmental Impact Assessment (EIA) $0.08 Detailed engineering design $0.12
Method statement, testing plan, documentation, warranty setup $0.02
Detailed engineering test $0.09
Financing cost (pre-construction through operation) - Lender's
engineer/ Independent engineer
$0.03
Subtotal $0.43
4 Inland transport
Logistics $0.56
Subtotal $0.56
5 Taxes and Duties
Total Tax Incidence: Solar Modules or Panels 11.33%
VAT Rate 15.00%
Subtotal $1.32
Subtotal (A) $8.90
B Other Investment Costs
1 Land & Civil Works
Land preparation & civil works (assembly area, site office for
security staff, monitoring and spares storage)
$0.04
Subtotal $0.04
2 Environmental and Social Costs
1) ongoing survey/monitoring work to cover bird and aquatic surveys
and water quality and other measures
$0.06
2) environmental monitoring for the IA to hire a consultant to monitor
IEE/EIA compliance and to ensure proper implementation of the
mitigation measures and the IEE/EIA monitoring program and assist
in ADB compliance monitoring and reporting
$0.05
3) environmental training for IA staff -
4) Social Management Costs $0.15
Subtotal $0.26
3 Subproject Management Construction Supervision
Formal tender for EPC + O&M - Technical $0.02
Floating PV Candidate Site Report
September 2020 │ Rev03 139
Sl No Item Total cost –
base case
(Million US$)
Formal tender for EPC + O&M - Legal $0.01
Lease - Transaction/legal $0.01
Agency fee - permitting and approval $0.01
Financing cost (pre-construction through operation) - Financial
advisor
$0.02
Financing cost (pre-construction through operation) - Legal advisor $0.04
Subproject insurance $0.14
Subproject management $0.09
Owner's engineer $0.11
Subtotal $0.45
Subtotal (B) $0.76
C Contingency
1 Physical $0.77
2 Price $0.57
Subtotal (C) $1.34
D Financial charges during implementation
1 Interest during implementation $0.84
2 Commitment charges $0.01
Subtotal (D) $0.85
Total Subproject cost (A) + (B) + (C) + (D) $11.85
Floating PV Candidate Site Report
September 2020 │ Rev03 140
I. Report of Local Livelihoods and Activities of Joydia Baor
Housing
The type of housing facilities that we have found around Joydia Baor are made of materials such
as concrete, tin and mud, and are home to a community of fishermen, who do not make much in
the way of income.
Figure 17: Types of local housing
Uses of Lake
Jute rotting –Joydia Baor is surrounded by a lot of land where jute is cultivated. Farmers do a
lot of jute-rotting in the Baor.
Figure 18: Jute rotting
Washing and bathing – Joydia is also used for household washing and bathing purposes by the
inhabitants of the region. However, a large portion of the shoreline is covered by water
hyacinths and because of that the villagers need to clear the water surface every time before
going into the water.
Floating PV Candidate Site Report
September 2020 │ Rev03 141
Figure 19: Washing and bathing
Cooking – People use water from the lake to cook their meals, and they especially prefer lake
water to water pumped from the well, the latter of which contains a lot of iron that causes their
boiled rice to turn out a slightly different colour. Someone also mentioned that the food taste
good when cooked using Baor water.
Subsistence fishing – The community mostly engages in subsistence fishing as a primary
source of income, which is not more than 300-500 BDT a day. Small mesh size fishing nets and
local handmade traps are mainly used for catching the small indigenous species. Fisherman
normally used small boats and local made ‘dunga’ to fish from the lake.
Figure 20: Subsistence fishing
Duck farming – A lot of ducks are brought to the Baor to graze. Khaki Campbell and swan were
the common types found during the visit.
Floating PV Candidate Site Report
September 2020 │ Rev03 142
Figure 21: Duck farming
Navigation – The lake is used for navigation purposes also. People use boats to traverse the
lake through the middle. Villagers living on the West side mainly use the navigation route the
cross the Baor.
Figure 22: Navigation
Adjacent farmland
Joydia Baor is surrounded by croplands where rice, jute and vegetables are cultivated. Banana and
Guava plantation is very popular in this part of the country and multiple plantation sites were found
on both sides of the shore. Commercial timber producing trees such as Teak, Mahogany are also
available close to the shoreline.
Floating PV Candidate Site Report
September 2020 │ Rev03 143
Figure 23: Adjacent farmland
Fish species
Multiple fish samples were collected each day from the local fisherman and the Fisheries expert
identified the species using the identification manual. Species identified are summarised in the
following table.
Table 54: Summary of fish species
Sl.
No.
Scientific Name English Name Local Name
1. Aplocheilus panchax Blue Panchax Tin Chokka, Kanpona, Korkuna
2. Badis badis Blue Badis Bot Koi, Koi Bandi, Napte Koi
3. Chanda nama Elongated Glass
Perchlet
Chanda, Nama Chanda
4. Channa marulius Bullseye Snakehead Gajar, Gajal, Gajori
5. Glossogobius giuris Tank Goby Bele, Baila
6. Gudusia chapra Indian River Shad Chapila, Chaipla, Suiya, Khaira
7. Heteropneustes fossilis Stinging Catfish Shing, Jiol, Shingi
8. Hyporhamphus limbatus Congaturi Halfbeak Ek Thuita, Ek Thota
9. Macrobrachium sp. Small Prawn Gura Chingri
10. Macrognathus pancalus Barred Spiny Eel Guchi, Pankal, Turi, Chirka
Floating PV Candidate Site Report
September 2020 │ Rev03 144
Sl.
No.
Scientific Name English Name Local Name
11. Mastacembelus armatus Zigzag Eel Baim, Bam, Sal Baim
12. Mystus tengara Tengara Mystus Bujuri Tengra
13. Mystus vittatus Striped Dwarf Catfish Tengra
14. Nandus nandus Mud Perch Meni, Bheda, Roina
15. Notopterus notopterus Bronze Featherback Foli, Pholoi
16. Osteobrama cotio Dhela Dhela, Mou, Moa, Keti
17. Pethia conchonius Rosy Barb Kanchan Punti, Punti, Taka
Punti
18. Pseudambassis lala Highfin Glassy Perchlet Choto Chanda, Lal Chanda
19. Pseudambassis ranga Indian Glassy Fish Lal Chanda, Ranga Chanda
20. Pseudosphromenus
cupanus
Spiketailed Paradise
Fish
Naptani
21. Puntius phutunio Pigmy Barb Phutani Punti
22. Puntius puntio Puntio Barb --
23. Puntius ticto Ticto Barb Tit Punti
24. Tetraodon cutcutia Ocellated Pufferfish Tepa, Kutkuitta, Potka
25. Trichogaster lalius Dwarf Gourami Chuchra, Buicha, Choto
Kholisa
Floating PV Candidate Site Report
September 2020 │ Rev03 145
Figure 24: Fish species
Distribution lines
Joydia Baor has REB distribution lines spanning across all sides of it. New electric poles are being
erected as renovation of the existing line is underway.
Floating PV Candidate Site Report
September 2020 │ Rev03 146
Figure 25: Distribution lines
Substation
The substation near Kotchandpur is 10 km from Joydia. It has a 33/11 kV transformer that has a
capacity of 10 MVA, with 5 active feeders. Upon visit, no oil leakages were observed. There is no
environmental audit and the transformer oil is generally sent to the store for proper disposal.
Figure 26: Substation
Road communication
The Baor is surrounded by poorly-paved brick roads and dirt roads. The conditions of the roads are
better on the South East side compared to North East and West side.
Floating PV Candidate Site Report
September 2020 │ Rev03 147
Figure 27: Road communication
Vegetation
Dhancha, a plant which makes for good fuel wood, along with water hyacinths make up the
vegetation that can be found in the Baor. The dense water hyacinth cover on the water surface is
inhibiting navigation, fishing and general uses of the lake water.
Figure 28: Vegetation
Floating PV Candidate Site Report
September 2020 │ Rev03 148
J. Project Spill Response Plan
All Subproject locations during construction and operations will be required to implement an
operation and maintenance program that includes an employee training component and has the
ultimate goal of preventing or reducing pollutant runoff from sites. Spill response plans will be
required:
During construction at the Subproject panel storage area, panel and floatation assembly area,
the existing substation site, the Subproject lakeside assembly area and while working over water
to put the panels in place and to anchor them on the lake bottom.
During operations for any area required for long term operations at the lake side, for the panel
areas on the lake and at the substation facility.
Preventing spills of materials and wastes is a significant component of compliance. Even with the
best prevention efforts, spills may still occur and when they do, it is up to facility personnel to
respond quickly and effectively to clean-up the spilled material or notify someone who can. The
Subproject will develop site specific individual Spill Response and Prevention Plan. The plan/s will
be kept in a central locations easily accessible for employees.
Responsibilities will be clearly defined with named Responsible Person or Persons who will have
primary responsibility for coordinating the response to emergencies, including chemical spills.
Supervisors should ensure that employees are familiar with these procedures and that they receive
any necessary training.
All employees should follow these procedures in the event of a spill.
Emergency Contact Numbers of personnel to be contacted in the case of a spill should be posted
in conspicuous locations and this will include
Emergency services (police, fire department, ambulance services).
The Subproject responsible officer or officers (e.g. project manager, project safety officer).
For response to spills over water, during construction and operations, the location of a boat and
name(s) of the officer/employee(s) who operate the boat and who will be trained in emergency
response.
Any other defined Government agencies.
Clean-up Procedures Spilled chemicals should be effectively and quickly contained and cleaned
up. Employees should clean up spills themselves only if properly trained and protected. Employees
who are not trained in spill clean-up procedures should report the spill to the Responsible Officer(s)
listed above, warn other employees, and leave the area.
The Maximum Clean-up Amounts that properly trained employee should clean-up will be listed in
the plan (e.g. 1 litre of liquid and ½ kg by weight unless other information is available). In the event
of spills greater than these amounts, contact the appropriate responders listed in the Emergency
Contact Numbers listed above.
The following general guidelines should be followed for evacuation, spill control, notification of
proper authorities, and general emergency procedures in the event of a chemical incident in which
there is potential for a significant release of hazardous materials.
Floating PV Candidate Site Report
September 2020 │ Rev03 149
1. Evacuation - Persons in the immediate vicinity of a spill should immediately evacuate the
premises (except for employees with training in spill response). If the spill is of “medium” or “large”
size, or if the spill seems hazardous, immediately notify emergency response personnel.
2. Spill Control Techniques - Once a spill has occurred, the employee needs to decide whether
the spill is small enough to handle without outside assistance. Only employees with training in spill
response should attempt to contain or clean up a spill. Spill control equipment should be located
wherever significant quantities of hazardous materials are received or stored. Common spill
response items include Material Safety Data Sheets (MSDS), absorbents, over-pack containers,
container patch kits, spill booms, shovels, acid/base neutralisers, and “caution-keep out” signs.
For overwater response, floating booms, a specific marine absorbent kit with appropriate
absorbents, booms, pads, scoops and containers for contaminated materials.
3. Spill Response and Clean-up - Chemical spills should be divided into three categories: Small,
Medium and Large. Response and clean-up procedures will vary depending on the size of the spill.
Small Spills: Any spill where the major dimension is less than ½ metre (m) in diameter or are less
than 300 millilitres (mL) in volume can generally be handled by internal personnel and usually do
not require an emergency response by police or fire department teams:
Quickly control the spill by stopping or securing the spill source. This could be as simple as up-
righting a container and using floor-dry or absorbent pads to soak up spilled material. Wear
gloves and protective clothing, if necessary.
Put spill material and absorbents in secure containers if any are available.
Consult with the Facility Responsible Person and the MSDS for spill and waste disposal
procedures.
In some instances, the area of the spill should not be washed with water. Use Dry Clean-up
Methods and never wash spills down the drain, onto a storm drain or into water bodies.
Both the spilled material and the absorbent is considered hazardous waste and must be
disposed of in compliance with Subproject solid and hazardous waste plan.
Medium Spills: Spills where the major dimension exceeds ½ m, but are less than 5m or are
between 300 mL and 5 Litre in volume. Outside emergency response personnel (police and fire
department teams) should usually be called for medium spills. Common sense, however, will
dictate when it is necessary to call them.
Immediately try to help contain the spill at its source by simple measures only. This means
quickly righting a container, or putting a lid on a container, if possible. Do not use absorbents
unless they are immediately available. Once a quick attempt has been made to contain the spill,
or once it is determined that is not possible to take any brief containment measures, leave the
area and alert Emergency Services. Give police accurate information as to the location,
chemical, and estimated amount of the spill.
Evaluate the area outside the spill. Any engines and electrical equipment near the spill area
must be turned off. Advise Emergency Responders on how to turn off engines or electrical
sources. Do not go back into the spill area once you have left. Help emergency responders by
trying to determine how to shut off any equipment, if necessary.
If emergency responders evacuate the spill area, follow their instructions in leaving the area.
After emergency responders have contained the spill, company personnel should be prepared
to assist them with any other information that may be necessary, such as MSDSs and questions
about the facility. Emergency responders or trained personnel with proper personal protective
equipment will then clean up the spill residue. Personnel should not re-enter the area until the
Floating PV Candidate Site Report
September 2020 │ Rev03 150
responder in charge gives the all clear and should be prepared to assist these persons from
outside the spill area with MSDSs, absorbents, and containers.
Reports must be filed with proper authorities. It is the responsibility of the spiller to inform both
his/her supervisor and the emergency responders as to what caused the spill. The response
for large spills is similar to the procedures for medium spills, except that the exposure danger
is greater.
Large Spills: Any spill involving flammable liquid where the major dimension exceeds 5 m or more
than 5L in volume; and any “running” spill, where the source of the spill has not been contained or
flow has not been stopped.
Leave the area and notify Emergency Responders. Give the operator the spill location, chemical
name, and approximate amount.
From a safe area, attempt to obtain MSDS information for the spilled chemical for the
emergency responders to use. Also, be prepared to advise responders as to any ignition
sources, engines, electrical power sources that may need to be shut off. Advise responders of
any absorbents, containers, or spill control equipment that may be available. Use radio or phone
to assist from a distance, if necessary.
Only emergency response personnel, in accordance with their own established procedures,
should handle spills greater than 5m in dimension. Once the emergency responders’ team is
on the job cleaning up spills or putting out fires, the area is under their control and no one may
re-enter the area until the responder in charge gives the all clear.
Provide information for reports to supervisors and responders, just as in medium spills.
Each Subproject site will detail the following and have information available:
1 Materials at Site that Require Special Clean-up in the Event of Spills
Describe any materials used at your facility that requires special materials and procedures for
clean-up. Provide details regarding hazards associated with these materials:
Material Hazards Associated with Material
1
2
2 Materials Inventory
List all materials or wastes that may require clean up. List the average and maximum amounts on
site and their storage locations. (Example materials are listed for convenience only. Ignore any that
do not apply and add any other materials of concern that are onsite.
Material Amount (avg/max} Locations
Diesel Fuel
Motor Oil
Hydraulic Oil
Used Oil
Paints
Etc
Floating PV Candidate Site Report
September 2020 │ Rev03 151
3 Maximum Clean-up Amounts
Identify the maximum volume of spill that may be cleaned up by employees or contractors based
on material (use 1 litre or ½ kg unless other information is available.). Also identify how wastes
from a spill of any material will be disposed of (for example, absorbed and placed in special
containment) and the location of the offsite facility to which clean-up wastes will be sent for
hazardous waste disposal, if applicable:
Material Maximum Volume to be cleaned Disposal Method/Location
e.g. Used Oil
4 Facility Map
Attach a map or sketch of the facility including substation site and wharf and panel locations during
operations showing:
the locations of each spill response kit,
the locations where the materials identified in the Material Inventory are normally stored or
used, and,
the location of each storm drain inlet or drainage ditch.
5 Spill Kit Inventory and labelling
List the spill response equipment that will be maintained at each site location
LOCATION ABSORBENTS
(bags of loose
absorbents, rolls of
sheet, containers of
neutralizing agents
etc). Marine
specific absorbents
for use lake
cleanup,
TOOLS (shovels,
brooms, dust pans,
waste containers,
squeegees etc).
Scoops for removal
of material on water
and containers for
temporary storage
of contaminated
material
PERSONAL
PROTECTIVE
EQUIPMENT
(gloves,
goggles,
aprons, boots,
dust masks
etc)
OTHER
SUPPLIES
(Warning
tape, labels,
markers,
MSDSs etc)
6 Label Spill Kits
Label each spill kit prominently with the words “SPILL KIT” or “ABSORBENTS” “MARINE SPILL
KIT” etc.
Label or stencil the necessary emergency telephone number(s) of persons to be contacted in case
of a spill or leak.
7 Employee Training Log
Floating PV Candidate Site Report
September 2020 │ Rev03 152
Identify the spill response training provided to each employee or contractor who is charged with
responsibility for spill response. This will include the need to show that contractors during
construction and the IA during operations have trained their staff to handle spill response over water
and this needs to include health and safety training for working over water:
NAME OF EMPLOYEE
for Contractor or
Implementing Agency
during operations)
INSTRUCTOR NAME DATE OF TRAINING
8 Spill Log
Provide information for all spills greater than I litre giving date, material, quantity, responsible
person to contact, a description of spill and if there was discharge to a water body, clean-up method
and disposal.
Floating PV Candidate Site Report
September 2020 │ Rev03 153
K. Constrcution and Operation Waste and Hazardous Waste Management Plan
General
In planning stages of the Project, it is important to understand what excess materials are likely to
be generated and then focus on how the generation of those excess materials can either be
avoided or the material can be diverted from landfill.
A construction waste and hazardous waste management plan will be developed with key objectives
to:
1. Minimise the amount of waste generated as part of the Subproject
2. Maximise the amount of material which is sent for reuse, recycling or reprocessing
3. Minimise the amount of material sent to landfill.
When developing and implementing the construction waste management plan the following key
elements should be considered:
1. Waste streams: identify which waste streams are likely to be generated and estimate the
approximate amounts of material
2. Focus on waste avoidance: instead of managing the waste once it has been generated, look at
ways to avoid the generation of that waste in the first place; use of modular component and
prefabrication of solar panels off-sit significantly reduces wastage on-site
3. Services: identify site personnel who are responsible for management of the waste streams
generated and data on waste/recycling generation
4. On-site: understand how the waste management system will work site, including bin placement
and access and ensure that non-hazardous waste and hazardous waste are properly separated
and contained
5. Clearly assign and communicate responsibilities: ensure that those involved in the construction
phase are aware of their responsibilities in relation to the construction waste management plan
6. Engage and educate personnel: be clear about how the various elements of the waste
management plan will be implemented and ensure personnel have an opportunity to provide
feedback on what is/isn’t working
7. Monitor: to ensure the plan is being implement, monitor on-site
The Waste Plan will document the following:
How will materials be stored on-site for reuse and recycling? e.g. in skip bins. Indicate
arrangements of storage of oils etc with arrangements for bunding and capacity of bunding
(see hazardous waste arrangements below)
How will site operations be managed to ensure minimal waste creation and maximum reuse
and recycling?
Indicate separate area set aside for sorted wastes,
Indicate designated waste collection points at site. Indicate that there will be sufficient collection
points with adequate capacity
Floating PV Candidate Site Report
September 2020 │ Rev03 154
Indicate any reuse and recycling of materials
indicate clear signage arrangements for waste
Indicate staff training
indicate checking procedures and designated personnel responsible
An inventory of all wastes including hazardous wastes will be compiled and will include
quantities of waste. The inventory will be kept up to date and available at site
Indicate landfill sites utilised for final disposal and arrangements for transfer of materials
For Hazardous Waste
The arrangements for any recycling and final disposal and compliance with relevant standards
will be documented and any agreements with agencies employed will be explained
For any medical waste indicate the arrangements for storage, handling, transportation and final
disposal. E.g. Incineration at approved medical facility
Indicate designated facilities for collection and temporary on-site storage and where applicable
there is appropriate fencing, signage, roofing, lighting, a means of communication in case of
emergencies and lightning protection
Demonstrate that waste storage areas and/or containers meet the risk needs for hazardous
materials (e.g. impervious floor, bunded areas with drainage/containment systems, lids to
prevent light material from blowing away or sealed containers)
Store any empty print cartridges in a designated box at specified location until removal from
site
Store any fluorescent tubes in a special labelled steel drum at designated sites e.g. any
engineering workshop.
Arrangements for collection and storage of miscellaneous hazardous waste i.e. car batteries,
batteries, oil filters, oil soaked rags until such time that the amounts can be removed from site.
Ensure that the contractor’s responsible are made aware of these procedures.
Indicate how the plan will be evaluated, and who is responsible for the evaluation? e.g.
feedback from staff collected by the site supervisor, regular reporting to implementing agency
and to ADB through monitoring reports.
Floating PV Candidate Site Report
September 2020 │ Rev03 155
Management plans will be in place to cover the construction sites (on the lake and lakeside
assembly and storage area and the transmission line construction route and at the Subproject
substation site) and during operations at the floating facility, transmission line and substation site.
The following form to be used to specify waste streams at site, volumes generated and indicating
any reuse and recycling. Disposal method and landfill destination will be indicated.
General and Hazardous Waste Streams
Reuse and Recycling Disposal
Materials Generated
Specify all non
hazardous waste
materials
e.g.
Estimated
volume (m3 ) or
Area (m2 ) or
weight (t) (refer
On-site (How
will materials
be reused
and/or recycled
on-site?)
Off-site
(Specify the
contractor and
recycling
agent)
Specify the
contractor
and/or landfill
site
Timber (specify type)
Wood waste(e.g.
MDF, plywood)
Ferrous metals (e.g.
iron and steel
Nonferrous metal (e.g.
copper wiring)
Concrete
Gravel
Gypsum board (e.g.
drywall)
Plaster
Paint
Plumbing fixtures and
fittings
Stone
Asphalt
Glass
Sand/fill
Topsoil
Green waste
Fluorescent light
tubes
Plastics
PVC
Co-mingled
recyclables
Others (specify)
Floating PV Candidate Site Report
September 2020 │ Rev03 156
Hazardous Waste Streams
Reuse and Recycling Disposal
Hazardous Materials
Generated
Specify
Estimated
volume (cu m)
or Area (sq m)
or weight (t)
On-site (How
will materials
be reused
and/or recycled
on-site?)
Off-site
(Specify the
contractor and
recycling
agent)
Specify the
contractor and
method of
disposal
Used oils from various
sources –
transformers, vehicle
use etc
Any medical waste
from first aid and
medical facilities
Miscellaneous waste
i.e. car batteries, other
batteries, oil filters, etc
Sewage from septic
tanks at site or camps
Contaminated soil
Others (specify)
All movements of waste material from site will be documented using the form below and information
will be available for inspection at site.
Documentation of Waste Materials Movement from site
Waste Material
(describe)
Volume (cu m)
or weight (t)
Destination e.g.
recycling agency,
landfill,
incineration
Signature of
responsible
person
Date
Floating PV Candidate Site Report
September 2020 │ Rev03 157
RINA Tech UK Ltd.
Huntingdon House,
20-25 North Street
Brighton, BN1 1EB,
UK
+44 (0)1273 819 429
rina.org
Joydia Baor, Bangladesh
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0
Rev. 1.0
Description First Issue
Prepared by D. Bertalot / C. Constantin
Controlled by C. Shayer
Approved by A. Wilshaw
Date 10/07/2020
July 2020 Rev 1.0
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
Rev. Description Prepared by Controlled by Approved by Date
1.0 First Issue D. Bertalot / C.
Constantin C. Shayer A. Wilshaw 10/07/2020
All rights, including translation, reserved. No part of this document may be disclosed to any third party,
for purposes other than the original, without written consent of RINA Consulting S.p.A.
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 1
TABLE OF CONTENTS
Page
1 INTRODUCTION 3 1.1 SCOPE OF DOCUMENT 3 1.2 DEFINITIONS 4 1.3 GENERAL REQUIREMENTS 4 1.4 INTERNATIONAL STANDARDS 4 1.5 UNIT SYSTEM 4
2 CONTRACTOR RESPONSIBILITIES 5 2.1 GENERAL 5 2.2 APPLICATIONS AND PERMITS 5 2.3 HEALTH, SAFETY, ENVIRONMENT 5 2.4 QUALITY MANAGEMENT AND ASSURANCE 5
2.4.1 Personnel Characteristics 5 2.5 SURVEY INSTRUMENTATION AND EQUIPMENT 6
3 POSITIONING SYSTEMS 7 3.1 SURVEY REFERENCE SYSTEMS 7
3.1.1 Unit of Measurement 7 3.1.2 Land Vertical Benchmarks 7 3.1.3 Positioning System 7 3.1.4 Underwater Positioning 7
4 BATHYMETRIC SURVEY 8 5 GEOPHYSICAL SURVEY 9 6 GEOTECHNICAL SURVEY 10
6.1 LABORATORY TESTING 10 7 OVERALL APPROACH TO SURVEY DESIGN AND EXECUTION 12 8 DATA ACQUISITION AND DATA PROCESSING 13
8.1 DATA ACQUISITION 13 8.1.1 Bathymetric Data 13 8.1.2 Hydrographic Data 13 8.1.3 Geophysical Data 13 8.1.4 Geotechnical Data 13
8.2 FIELD DOCUMENTATION 14 9 DELIVERABLES - FINAL TECHNICAL REPORT 15
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 2
ABBREVIATIONS AND ACRONYMS
BH Borehole
CPT Cone Penetration Test
DGPS Differential Global Positioning System
DTM Digital Terrain Model
FPV Floating Photovoltaic
HSE Health, Safety, Environment
PV Photovoltaic
SPT Standard Penetration Test
u1 Pore Water Pressure on the Cone
u2 Pore Water Pressure behind the Cone
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 3
1 INTRODUCTION
1.1 SCOPE OF DOCUMENT
The present document states the minimum requirements (basic data, standards and criteria) for the bathymetric survey and the geophysical & geotechnical investigation campaign to be carried out for anchoring and mooring system design of the Floating Photovoltaic (FPV) Project at Kaptai Lake.
The area considered for the installation of the plant is shown in Figure 1.1. Purpose of the planned investigations is to define:
the underwater topography, in terms of bathymetric map with contours and digital terrain model (DTM);
hydrological data;
building a ground model via geophysical and geotechnical investigations.
Figure 1.1: Floating Solar PV – Project Area
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 4
1.2 DEFINITIONS
Client: Implementing Agency / To Be Confirmed
Client’s Representative: the personnel appointed by Client to supervise the works
Contractor: the firm in charge of the bathymetric, geophysical, and geotechnical activities at site, for laboratory works and reporting
Shall: is an absolute requirement. Noncompliance with a “shall” requirement shall be approved in writing by the Client.
Should: is a recommendation. Alternative solutions having the same functionality and quality are acceptable to the Client.
1.3 GENERAL REQUIREMENTS
All the services shall be in accordance with this document unless otherwise specified by the Client or requested by local regulations.
Data acquisition shall be performed to achieve the highest possible standard and to ensure that survey objectives will be fulfilled and will be not jeopardized by inadequate data quality.
Any exceptions from the requirements of this specification and any other contractual documents shall be clearly identified and explained.
The Contractor shall supply fully operating equipment, instruments, personnel, and labour required for execution of the surveys, laboratory tests, permits, results interpretation and preparation of reports.
The Contractor shall take responsibility to ensure that all operations are conducted safely and with full regard to human life of personnel employed in the operations and to international and local environmental considerations.
In any case, nothing in this specification shall relieve the Contractor of his responsibility to comply with good survey practice.
1.4 INTERNATIONAL STANDARDS
[1] NORSOK Standard G-001 Rev. 2, October 2004, Marine Soil Investigations
[2] ISSMGE Geotechnical & Geophysical Investigations for Offshore and Nearshore Developments
[3] ASTM Annual Book of ASTM Standards - Volume 04.08 (I): Soil and Rock
[4] ASTM Annual Book of ASTM Standards - Volume 04.09 (II): Soil and Rock/Geosynthetics
[5] ASTM ASTM D2488 “Description and Identification of Soils (Visual-Manual Procedure)”.
[6] BSI 5930:1999 Code of Practice for Site Investigations”
[7] ISRM Suggested methods “Rock characterisation testing and monitoring”, Pergamon Press.
1.5 UNIT SYSTEM
The units of measure of the International System (SI) shall be used.
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 5
2 CONTRACTOR RESPONSIBILITIES
2.1 GENERAL
The Contractor shall be responsible for the overall survey execution and for the quality of the data collected. In particular, the responsibility of the Contractor shall consist in:
satisfying the international and local safety rules applicable in the working area;
acquiring all the permits, authorisations, visas, custom clearance required to operate in the work area;
holding all necessary certification for seaworthiness in Bangladesh;
providing suitably qualified and experienced personnel to ensure the execution of the work in compliance with the technical specifications;
quality and quantity of survey works and acquired data;
procurement of most adequate barges/platforms/pontoons for survey works;
providing logistics and support for all the required activities for the execution of the work;
providing consumables, fuel, lubricants and any other item necessary for operations;
providing appropriate spare parts and back-up equipment to ensure continuous operations;
ensuring the proper functioning and calibration of instrumentation and equipment;
ensure overall quality of survey works and acquired data;
safety of personnel and equipment during activities shall never be compromised. In addition, the Contractor shall consider providing personnel for the security of the Contractor personnel and equipment;
having a contingency plan in case of a mechanical breakdown;
recording the acquired data on adequate support;
interpretation of survey results and preparation of the required technical reports.
2.2 APPLICATIONS AND PERMITS
The Contractor shall be responsible to arrange all the applications and to obtain all necessary permits, licences, etc. from the appropriate Authorities with respect to materials, equipment, instruments, means and personnel to be employed for the survey work.
2.3 HEALTH, SAFETY, ENVIRONMENT
It is the Contractor’s duty to comply with the local and international regulations on health, safety and environmental (HSE) protection applicable to the work, and to proceed according to OSHAS 18001 / ISO 45001 and any Client’s HSE requirements.
Compliance with HSE requirements and regulations does not relieve the Contractor from the obligation to act in a responsible manner and to take every reasonable precaution to protect the health and safety of the involved peoples and public, and to protect the environment and the existing structures, if any.
2.4 QUALITY MANAGEMENT AND ASSURANCE
It is the Contractor’s duty to fulfil and implement the requirements for Quality Management (QM) and Quality Assurance (QA) contained in the Contractual Documents. The QM/QA system to be applied during the service shall be properly defined in a Contractor’s Quality Plan complying with ISO 9001 and any Client’s Quality Management specification.
Without prejudice to the obligations undertaken by the Contractor, Client shall have the right to perform Quality Assurance audits to verify that the Contractor meets the requirements as set forth in the Contract.
2.4.1 Personnel Characteristics
The Contractor shall propose the following key qualified personnel for the survey:
Project Manager, having at least 10 years’ experience;
Party Chief responsible for the on-board work, having at least 10 years of relevant experience;
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 6
adequate survey team, including engineers and technicians having fully documented experience in the instruments to be used, in the data acquisition and in processing activities.
The Contractor shall submit a list of the proposed key personnel and their relevant CVs, in the offer, to be approved in advance by Client. Any further modification shall be submitted to Client for approval. No change will be allowed during the survey unless due to force majeure; in that case Client shall be advised to approve the proposed substitution.
The Contractor shall have full working knowledge of the site including the prevailing climatic and environmental conditions. The Contractor shall be familiar with all necessary information, circumstances, or conditions (including assessment of contingencies) which may affect the amount or nature and/or the performance of the work.
2.5 SURVEY INSTRUMENTATION AND EQUIPMENT
The Contractor shall provide instruments and equipment meeting the following characteristics:
reliability: all instruments and equipment shall be widely proven and tested, in order to ensure adequate measurements in the environmental conditions typical of the area to be investigated;
compliance: all instruments and equipment shall be widely proven and tested, in order to ensure full compliance with all local and international regulations on health, safety and environmental protection applicable to the work;
stability: all instruments shall allow accurate measurements, to be repeated without involving drift problems;
accuracy: all instruments shall offer an adequate level of accuracy in compliance with the scope of the work;
range: instruments range shall be selected to ensure the best acquisition of data considering the environmental conditions typical of the working area;
redundancy: equipment shall have an adequate redundancy to overcome possible system errors or breakdown;
calibration: all equipment shall be calibrated. Calibration and start up testing must be performed before the beginning of any operations and, in addition, every time the equipment is changed/added to the initial configuration and in all cases that it is necessary. Calibrations and testing can be executed in port or in the operations area. For the equipment calibrated in the factory or workshop, calibration certificates shall be provided to Client before mobilisation;
maintenance: instruments to be used shall require little maintenance; the electronic components shall be checked, tested and repaired by the Contractor;
availability on the market: proposed instruments shall be easily available on the market, in order to ensure a timely replacement in case of equipment failure;
spare parts: Contractor shall have available on-board sufficient quantities of equipment, associated consumables and manufacturer’s recommended spares to perform the work described in this specification, thus avoiding excessive and unacceptable downtimes.
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 7
3 POSITIONING SYSTEMS
3.1 SURVEY REFERENCE SYSTEMS
3.1.1 Unit of Measurement
The units of measure of the International System (SI) shall be used.
3.1.2 Land Vertical Benchmarks
The Contractor shall establish minimum 4 (four) permanent benchmarks at the bank for minimum life span of five years for use in future check surveys. The minimum number of required permanent benchmarks should be reassessed proportionally to the extension of the project area.
3.1.3 Positioning System
For Land survey is recommended the use of Total Station / equivalent levelling instrument.
3.1.4 Underwater Positioning
For position fixing, the Contractor shall use DGPS. Alternatively, a position fixing system that meets with horizontal positional accuracy of + 1 m may be accepted by the Client, provided that at least 3 lines of position can be used to determine final position. The position fixing system shall be calibrated against a most accurate system or a fixed base line before deployment.
The Contractor shall use Echo-sounder equipment (having depth recording accuracy of 0.10 m, for ascertaining the depth), DGPS and suitable traversing equipment for this work. The Contractor shall clearly indicate the methodology for maintaining the horizontal control/vertical control for the survey in the proposal/write up. The desired accuracy for the survey is as below:
NAME OF WORK MINIMUM ACCURACY
Bench Mark + 0.005 m
Horizontal Control + 1m
Vertical Control + 0.1 m
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 8
4 BATHYMETRIC SURVEY
The main scope is to characterise the superficial soil up to 6 m below the seabed/riverbed relevant for design of the anchoring system that will be installed for the construction of the FPV plant. The aim is to determine the elevation of the base of the lake or water body to design this system.
The purpose of the planned investigations is to define the underwater topography, in terms of bathymetric map with contours and digital terrain model (DTM).
The geotechnical investigation shall be carried out after completion of the bathymetric survey, using the bathymetric data to define locations and depths of coring/testing.
The measured data points shall follow the below specifications:
- 0.1 m precision on elevation data
- Measurement every 5 metres
- Measurement should include the adjacent banks
- Permanent reference points: max 20 metres between the points, located on the banks, at least 1 metre back from the water’s edge, in an accessible area.
The deliverable shall be in the form of a georeferenced CAD file with the location of the measurement points and the corresponding elevation data. The following details shall be included:
- Section drawing showing the slope of the banks and the water level the day of the survey.
- If possible, the mapping should show isometric lines showing the various elevation levels, with a 0.5 metre pitch for elevation.
- Location of reference points on the map (location and coordinates in the appropriate coordinate system).
- Definition / description of the coordinate system.
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 9
5 GEOPHYSICAL SURVEY
The Scope of Work (SoW) will include the acquisition, processing, interpretation and reporting of appropriate geophysical data as required to:
establish lakes topography with contours, digital terrain model (DTM) and fly-over models;
provide detailed evaluation of lakes morphology, including topographic features, unevenness, geohazards, man–made hazards and obstructions;
provide sub-bottom stratigraphic profile;
detect main metallic debris/objects which can be potentially hazardous for installation.
The SoW is addressed to collect information using one or more of:
multibeam echo-sounder;
side scan sonar;
shallow profiling of seabed by means of sub-bottom profiler
magnetometer
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 10
6 GEOTECHNICAL SURVEY
The geotechnical survey will provide important information with the following objectives:
Investigate the distribution, the nature, the thickness and the geotechnical properties of the shallow deposits – underwater survey;
Investigate the distribution, the nature, the thickness, the geotechnical and mechanical properties of the superficial soils;
Correlate soil description and geophysical investigation results;
Facilitate the installation and define the anchoring solutions.
The scope may include piston/gravity corers or vibrocorers to 3 m below the mudline, for the underwater survey. The piston/gravity corers are preferable in cohesive/soft soils whilst vibrocorers are necessary in granular soils to ensure sufficient penetration. At the end of the fieldwork the recovered samples will be sent to a shore-based geotechnical laboratory where a complete testing programme will be carried out including classifications. The collected soil samples shall be shipped to a geotechnical laboratory to determine soil classifications and mechanical properties.
NOTE: Geophysical and geotechnical data shall be integrated in a final report.
6.1 LABORATORY TESTING
After completion of the fieldwork, all the recovered samples, from both underwater and on-land surveys, shall be sent to an approved qualified onshore laboratory where an extensive and advanced testing programme shall be carried out.
Of the more representative samples (those that can be classified as undisturbed and of “good quality” after an accurate visual examination) proposed by the Contractor, geotechnical laboratory tests and analyses shall be performed.
The onshore laboratory testing programme shall be submitted to the Client for approval.
The final choice of type and number of laboratory tests will be established based on soil description from the previous bulk or tube sampling results. The selection shall be done by the Contractor following recognised international standards (as listed in Section 1.4) and according to the soil type.
Type and quantity of laboratory shall be suitable to allow for a good and reliable definition of the soil properties relevant for design of the planned facilities.
Samples shall be properly preserved and transported to the laboratory. The transport shall be at the Contractor care. The laboratory shall store the soil samples in a moisture and temperature-controlled room.
The laboratory program proposed by the Contractor should comprise a selection of the types of tests shown in Table 6.1, as appropriate to the samples collected and the purpose of the investigations (anchoring and mooring studies).
All the remaining samples and waste material coming from lab testing should be properly labelled and stored for possible additional test and/or inspection. The obtained samples shall be conserved at least for 1 year after completion of the onshore laboratory testing. Samples shall not be discarded until approved by Client.
Test Type of Testing Type of Sample
Visual classification (USCS) and sample description
classification testing Cohesive
Atterberg limits (LL, PL, PI)
Natural water (moisture) content
Dry, bulk and submerged density
Particle size distribution
% passing #200 sieve
Specific gravity of soil
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 11
Test Type of Testing Type of Sample
Clay fraction
Carbonate content1
Organic content
Unconsolidated undrained triaxial testing (UU) (for firm to stiff cohesive soils)
Sensitivity (e.g. by laboratory fall cone or in-situ vane tests or UU tests on remoulded samples)
Visual classification (USCS) and sample description
classification testing Non- Cohesive
Particle size distribution
% passing #200 sieve
Natural water (moisture)content
Dry, bulk and submerged density
Maximum and minimum dry density
Carbonate content
Microscopic examination
classification testing Rock Natural water (moisture)content
Unit weight
Carbonate content
Point load index
strength testing Rock Uniaxial compression. measurement of Young's modulus and Poisson's ratio to be performed on selected samples
Table 6.1: Laboratory Testing
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 12
7 OVERALL APPROACH TO SURVEY DESIGN AND EXECUTION
The abovementioned surveys represent the Client’s assessment of a reasonable strategy to survey the project site in a sufficient manner to build an appropriate ground model for design of the FPV project. These requirements should be critically assessed by the Contractor, and it should develop a survey strategy sufficient to meet its design obligations under the Contract. In particular, the Contractor shall be cognizant of the fact that surveys need to be performed on lakes in remote regions of Bangladesh and shall develop a survey strategy which meets appropriate design requirements within the context of available equipment. The final survey strategy shall be subject to Client review. Innovative solutions may be considered by the Client. The geophysical survey can be performed by means of a small boat (e.g. a pilot boat, inflatable boat, etc), which can operate with a small draft.
The execution of the geotechnical surveys requires a vessel equipped with an A-Frame or crane to be used for deployment of drop/gravity corers or vibrocorers.
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 13
8 DATA ACQUISITION AND DATA PROCESSING
8.1 DATA ACQUISITION
The information gathered during the survey shall be stored in an appropriate digital format using hardware and software systems able to manage the acquisition and processing of data coming from different instruments and historical data sources.
The following data shall be acquired during the survey:
Bathymetric data:
Hydrographic data;
Geotechnical data.
8.1.1 Bathymetric Data
Bathymetric data acquisition shall be performed to the highest possible standard to ensure that investigation objectives will not be prejudiced by inadequate data quality.
The purpose of the bathymetric survey is to locate any bed rock outcrops, any obstacles at bed level etc. and to prepare the bed contour plans at specified contour interval with reference to Datum level, collection of data for depth of water (Season wise) and water level variations under waves or similar action, water flow velocity and soil composition of the banks and bottom of the water body, etc.
8.1.2 Hydrographic Data
Hydrographic data acquisition shall be performed/supplied to the highest possible standard to ensure that investigation objectives will not be prejudiced by inadequate data quality.
In general, the Contractor will acquire:
historical detailed bank to bank hydrographic survey of the area under study in a grid of 20m x20m to get the reservoir bed levels. The soundings are to be reduced to Chart Datum (CD) / Sounding Datum (SD) to assess the bed profile. At the time execution of the survey work depending on the actual area size, the Client may change the grid spacing without changing the number of survey points;
historical data of daily & seasonal water level variations, low water level (LWL), high water level (HWL);
The Current velocity (at Surface level, half of the depth & above riverbed) Float observation (right side, centre & left side of the river) and discharge are to be observed once. Their positions & value are to be plotted on the chart and details are to be mentioned in the report;
All prominent shore features, berthing place, existing jetty, ferry ghats, approach roads and other conspicuous objects are to be fixed and indicated on the chart. A brief write-up on condition of the shore features are to be included in the report.
8.1.3 Geophysical Data
Geophysical data acquisition shall be performed to the highest possible standard to ensure that investigation objectives will not be prejudiced by inadequate data quality.
In general, the Contractor will acquire data on:
Lakes’ topography with contours;
digital terrain model (DTM) and fly-over models
lakes morphology, including topographic features, unevenness, geohazards, man–made hazards and obstructions;
detection of main metallic debris/objects which can be potentially hazardous for installation.
8.1.4 Geotechnical Data
Geotechnical data acquisition shall be performed to the highest possible standard to ensure that investigation objectives will not be prejudiced by inadequate data quality.
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 14
In general, the Contractor will acquire:
coordinates (Northing and Easting), WD and penetration associated to boring/testing locations;
CPT readings and ASCII files;
sample/cores description;
preliminary stratigraphy.
8.2 FIELD DOCUMENTATION
The Contractor shall record and maintain a complete and accurate log of field operations, including drilling, sampling, coring and testing.
The log must show:
Start and completion date;
name of the Contractor drillers and engineer;
location data, drill rig make and drilling method;
borehole number and coordinates;
water depth - the water depth shall be measured every day, before starting operations;
sampler type used;
depth, interval, type and number of each sample/core taken and sample recovery;
soil description per ASTM D2488 [5] “Description and Identification of Soils (Visual - Manual Procedure)” or, alternately, per BSI 5930:1999 [6] “Code of Practice for Site Investigations”, if requested by Client.
any other data pertinent to identification, strength and consistency of the materials (pocket penetrometer, torvane, etc.);
unusual condition such as fluid loss, hard drilling, etc. or any pertinent notes that would influence the stratification from drillers notes.
Floating Solar PV Project 9.072 MWp
Technical Specification for Bathymetric, Geophysical and Geotechnical Survey
July 2020 Rev 1.0 Page 15
9 DELIVERABLES - FINAL TECHNICAL REPORT
A Final Report is required to integrate the Bathymetric, the Geophysical and Geotechnical data collected. Following items to be included:
brief assessment of the performed survey operations; description of the operations;
boring logs;
high quality colour photos of the material recovered during drilling operations;
survey locations map;
HSE and QA-QC related registers and statistics.
equipment/tools technical characteristics and operating parameters;
software description;
detailed description of adopted procedure;
results of calibrations;
results of coring and laboratory testing;
integrated Boring/CPT logs;
list of key-personnel involved;
opinion on whether the site is suitable for an FPV project
Recommendations for future investigations
any specific deliverables resulting from bathymetric and hydrographic data e.g. DTM model.
The Draft Issue of the final report shall be submitted as digital copy to the Client within 15 days from the date of completion of each phase of the survey.
The Final Issue of the report shall be submitted to Client within 1 week from the receipt of Client comments.
RINA Consulting S.p.A. | Società soggetta a direzione e coordinamento amministrativo e finanziario del socio unico RINA S.p.A.
Via San Nazaro, 19 - 16145 GENOVA | P. +39 010 31961 | [email protected] | www.rina.org C.F./P. IVA/R.I. Genova N. 03476550102 | Cap. Soc. € 20.000.000,00 i.v.
LAKE BOUNDARY/DEVELOPMENT AREA
20m SETBACK FROM LAKE BOUNDARY
ANCHOR POINTS AND LINES
CABLE TRAY LOCATIONS ON FLOAT
LV CABLE FROM PV FLOAT TO MVPS
MV CABLE FROM MVPS TO SHORE
MVPS FLOATING PLATFORM
MVPS: 2,500kVA INVERTER + TRANSFORMER + MV SWITCHGEAR
PRELIMINARY COMBINER BOX LOCATIONS
PROPOSED ASSEMBLY AREA
FENCE LINE
KOMOR (FISHING AREA)
984 mm
456 mm
1,440 mm
11
PRELIMINARY
NOT FOR
CONSTRUCTION
ORIGINAL SIZE:
SHEET
H
G
F
E
D
C
B
A
87654321
RIN
A C
ON
SU
LT
IN
G
WW
W.R
IN
AG
RO
UP
.O
RG
WW
W.R
IN
AC
ON
SU
LT
IN
G.O
RG
SCALE
RE
VD
ES
CR
IP
TIO
ND
AT
EC
HK
DD
WN
01
27
/0
8/1
9IS
SU
E F
OR
C
AP
AC
IT
Y E
ST
IM
AT
IO
ND
CF
RR
02
27
/0
1/2
0U
PD
AT
E F
OR
C
AP
AC
IT
Y E
ST
IM
AT
IO
ND
CF
KK
LATTITUDE:
LONGITUDE:
AD
B - Jo
yd
ia
B
ao
r
BA
NG
LA
DE
SH
23.445 N
88.941 E
GE
NE
RA
L
CO
NC
EP
TU
AL
L
AY
OU
T
AS SHOWN
ISO A1
G002
LEGEND
N 1
SITE PLAN
SCALE: 1: 5,000 @ A1
ANCHOR: 2 MOORING
LINES PER ANCHOR.
USED ON NORTH AND
EAST AND WEST
SIDES OF PLATFORM.
ANCHOR: 4 MOORING
LINES PER ANCHOR.
USED ON SOUTH SIDE
OF PLATFORM.
3
PITCH & INCLINATION DETAIL
MODULES IN LANDSCAPE
N 2
SCALE: 1: 17,500 @ A1
AERIAL VIEW
4
SCALE: 1: 50 @ A1
DETAIL OF FLOATS
N
MVPS PLATFORMS
5
SCALE: 1: 500 @ A1
DETAIL OF PLATFORM
N
PV MODULE
MAIN FLOAT
COMBINER BOX
CABLE TRAY
SECONDARY FLOATS
LV CABLE
MV CABLES
MVPS PLATFORM
2.5MVA CENTRAL INVERTER +
TRANSFORMER + MV SWITCHGEAR
LV CABLES
SYSTEM CONFIGURATION:
3 CENTRAL INVERTERS
3 NOS. OF 2,500kVA MVPS
(1x2,500kVA INVERTER PER MVPS)
INVERTER:
MODULE:
RATED POWER 400Wp
DIMENSIONS: 1,979 x 1,002 x 40mm
No OF PLATFORMS: 6
No OF MODULES: 22,680
840 STRINGS OF 27 MODULES
No OF COMBINER BOXES: 42
20 STRINGS PER COMBINER BOX
14 COMBINER BOXES PER INVERTER
DC POWER: 9.072.0kWp
AC POWER @45C: 8,250.0kVA
AC POWER @50C: 7,500.0kVA
AC:DC RATIO: 1:1.21
LAKE SURFACE USAGE:
ESTIMATED TOTAL AVAILABLE AREA:
DRY SEASON: 1,364,810.98m²WET SEASON: 1,623,979.00m²
ESTIMATED LAKE COVERAGE:
DRY SEASON: 6.42%
WET SEASON: 5.43%
MV CABLES
DRY SEASON LAKE BOUNDARY
20m SETBACK
PROPOSED LANDING POINT
PROPOSED O&M BUILDING
PROPOSED
ASSEMBLY
AREA
PLATFORM TYPE 1
No OF PLATFORMS: 4
DC CAPACITY:1,512.0kWp
No OF MODULES: 3,780
No OF COMBINER BOXES: 7
PLATFORM AREA: 14,732.42m²
PLATFORM TYPE 2
No OF PLATFORMS: 2
DC CAPACITY:1,512.0kWp
No OF MODULES: 3,780
No OF COMBINER BOXES: 7
PLATFORM AREA: 14,607.22m²
FISHING AREAS
(KOMORS)
NOTES:
1. ALL DIMENSIONS ARE INDICATIVE AND IN "METRES" UNLESS
OTHERWISE STATED.
2. DESIGN BASED ON SATELLITE IMAGES AND .KMZ FILES CREATED BY
RINA.
3. THE DESIGN ASSUMES THAT ALL OBSTRUCTIONS WITHIN THE
BOUNDARY OF THE LAKE AND ON THE SHORE/BANK, WHICH COULD
SHADE THE PV ARRAY, WILL BE REMOVED PRIOR TO THE
INSTALLATION.
4. A 20m SETBACK FROM BANKS HAS BEEN CONSIDERED IN LAYOUT,
WHICH IS SUBJECT TO CHANGE DURING DETAILED DESIGN PHASE
5. ANCHORING POINT LOCATIONS ARE BASED ON HIGH LEVEL
CALCULATIONS AND ARE INDICATIVE ONLY. PV ARRAY
ARRANGEMENT, MOORING LINES AND FINAL ANCHOR POINT
LOCATIONS ARE SUBJECT TO CHANGE ONCE THE MOUNTING
STRUCTURE SYSTEM AND EQUIPMENT MANUFACTURER ARE DEFINED
DURING THE DETAILED DESIGN PHASE.
6. LOCATION OF THE INVERTER SUBSTATIONS (MVPS) ARE INDICATIVE
ONLY AND ARE SUBJECT TO CHANGE DURING THE DETAILED DESIGN
PHASE.
7. MOORING OF THE MVPS TO BE DEFINED DURING THE DETAILED
DESIGN PHASE.
8. MV CABLE ROUTING IS INDICATIVE ONLY AND IS SUBJECT TO CHANGE
DURING THE DETAILED DESIGN PHASE.
9. POINT OF CONNECTION NOT YET DEFINED AND LANDING POINT BASED
ON DISCUSSIONS HELD WITH LOCAL TEAM. FINAL LOCATION TO BE
DEFINED DURING THE DETAILED DESIGN PHASE.
10. NO BATHYMETRIC SURVEY OR DEPTH SEASONAL VARIATION DATA
WAS AVAILABLE WHEN THIS LAYOUT WAS PRODUCED. HENCE,
LAYOUT PROVIDES A CONSERVATIVE CAPACITY ESTIMATION BASED
ON TYPICAL PLATFORM CONFIGURATIONS AND AVAILABLE DATA.
11. APPROXIMATELY 6.5% OF THE TOTAL AVAILABLE AREA HAS BEEN
COVERED BY THE PLATFORMS CONSIDERING THE DRY SEASON LAKE
BOUNDARY. A MORE IN-DEPTH ASSESSMENT WOULD BE REQUIRED IN
ORDER TO OPTIMISE THE ACHIEVABLE CAPACITY.
12. A SOUTHERN PREVAILING WIND HAS BEEN CONSIDERED, HENCE
MOORING / ANCHORING BEING REINFORCED IN THE SOUTHERN SIDE
OF THE PLATFORMS. ANCHORAGE CONFIGURATION IS HOWEVER
INDICATIVE ONLY AND IS SUBJECT TO CHANGE DURING THE DETAILED
DESIGN PHASE.
ASIAN DEVELOPMENT BANK
TA-9628-BAN
Capacity Development for Renewable Energy Investment
Programming and Implementation
1 Solar PV Power Investment Plan
Appendix G
Grid Impact Study Report Joydia Floating PV
August 2020
Prepared for:
Asian Development Bank
Submitted by:
RINA Consulting & eGen Consultants
Grid Impact Study Report - Draft
Revisions
Revision Date Comment Signatures
Originated by Checked by Approved by
1.0 24/01/2020 Draft for approval G Balamurali/ V Prakash
Michael Beech
Simon Ebdon
2.0 25/08/2020 Updated costs G Balamurali A Wilshaw S Ebdon
Grid Impact Study Report - Draft
ABBREVIATIONS
ADB Asian Development Bank BPDB Bangladesh Power Development Board BREB Bangladesh Rural Electrification Board EMS Energy Management System FPV Floating Photovoltaics Ft Feet GW Gigawatt kV Kilo Voltage kA Kilo Ampere MVA Mega Volt Amperes MW Megawatt
MWp Megawatt peak NLDC National Load Despatch Centre OHL Overhead line PGCB Power Grid Company of Bangladesh Ltd PPC Power Plant Controller PoC Point of Connection PSS/E Power System Simulator for Engineering Pu Per unit PV Photovoltaic
PVPS Photovoltaic Power Station RE Renewable Energy RTNA Real Time Network Analysis SLD Single Line Diagram SREDA Sustainable Renewable Energy Development Authority S/S Substation TSO Transmission System Operator VRE Variable Renewable
Grid Impact Study Report - Draft
Contents
1 SCOPE OF WORK – OUTPUT 3: GRID IMPACT ASSESMENT 1
2 DATA COLLECTION ASSUMPTIONS AND CLARIFICATION 1
2.1 Assumptions 2
3 BANGLADESH POWER SYSTEM 3
3.1 Power Demand of Bangladesh 4
3.1.1 Forecasted Demand 4
3.1.2 Daily operational reports 5
3.2 Grid network – Jhenaidha 33 kV 5
3.2.1 Jhenaidha 132/33 kV substation 6
3.2.2 Kotchandpur 33/11 kV Substation 6
3.2.3 Moheshpur-2 33/11 kV Substation 7
3.2.4 Substation Loadings 7
3.2.5 Generators connected to the Jhenaidha 33 kV network 7
4 JOYDIA LAKE FLOATING PV 8
4.1 Grid Connection Options 8
4.1.1 Option 1 – Mohespur-2 33/11 kV Substation – 33 kV Connection 8
4.1.2 Option 2 - Kotchandpur 33/11 kV Substation – 33 kV Connection 11
4.2 Preferred Option 14
5 SYSTEM MODELLING 14
5.1 Bangladesh PSS/E transmission model review 14
5.2 Jhenaidha 132/33 kV substation 16
5.3 Joydia FPV and the grid connection 17
5.3.1 Dynamic model 18
6 GRID IMPACT STUDY 22
6.1 Steady state analysis 22
6.1.1 Study criteria 22
6.1.2 Base case 23
6.1.3 Load flow analysis 26
6.1.4 Contingency analysis 28
6.1.5 Short circuit analysis 28
Grid Impact Study Report - Draft
7 FLOATING PV REACTIVE CAPABILITY 29
7.1 Reactive power support through AN increased inverter capacity 30
8 DYNAMIC ANALYSIS 30
8.1 Grid code requirements 31
8.1.1 Fault ride through (Performance during Grid Disturbances) 31
8.1.2 Frequency Withstand Capability 32
8.1.3 Active Power Control 32
8.2 Fault ride through analysis 32
8.2.1 Case-1: 0.0pu voltage at grid during disturbance 32
8.2.2 Case-2: 0.25pu voltage at grid during disturbance 33
8.2.3 Case-3: 0.35pu voltage at grid during disturbance 34
8.2.4 Case-4: 0.85pu voltage at grid during disturbance 35
8.3 Frequency disturbance analysis 37
8.3.1 Over frequency disturbance 37
8.3.2 Under frequency disturbance 37
9 DISCUSSION 38
APPENDIX A. SINGLE LINE DIAGRAM OF THE BANGLADESH TRANSMISSION
NETWORK 40
APPENDIX B. GEOGRAPHICAL MAP OF THE BANGLADESH TRANSMISSION
NETWORK 41
APPENDIX C. SINGLE LINE DIAGRAM OF JENAIDHA SUBSTATION 42
APPENDIX D. LAYOUT DIAGRAM OF JOYDIA FPV 44
APPENDIX E. SUB MARINE CABLES – ELECTRICAL PARAMETER 45
APPENDIX F. OHL PARAMETERS 46
APPENDIX G. INVERTER DATASHEET 47
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
1
1 SCOPE OF WORK – OUTPUT 3: GRID IMPACT ASSESMENT
The scope of work for this report focuses on analysing the impact on the Bangladeshi transmission grid due to the connection of floating PV at Joydia Lake, which will be connected to the Jhenaidha 33 kV network.
1. Data Review and data request.
2. Identification of grid interconnection options and recommendation of the techno-
economic grid connection option.
3. Modelling of each candidate site in PSS/E – both static and dynamic models.
(generic only) for each site will be built. The model will also include the proposed
grid interconnection.
4. Preforming static studies to determine the impact on transmission or distribution
networks due to the integration of floating PV plants. Static studies will include Load
Flow analysis, Contingency analysis and short circuit analysis.
5. Performing dynamic studies to determine the stability of each proposed floating PV
site to remain connected to the grid under disturbances. The dynamic studies will
include voltage and frequency stability analysis.
6. Concept design for the grid interconnection.
7. A report detailing feasibility analysis and the grid impact assessment, and
recommendations for improvements and future works.
2 DATA COLLECTION ASSUMPTIONS AND CLARIFICATION
The RINA team undertook considerable effort to collect actual and accurate data for all the network elements pertaining to the Bangladeshi transmission and distribution network.
A significant amount of information was obtained from the Power Grid Company of Bangladesh Ltd website https://www.pgcb.org.bd including the single line diagram describing the Bangladesh Transmission network and Daily operational report.
During the initial few days of the inception mission (15-18th June 2019) the RINA team attended a number of meetings with the client (ADB) and various project stakeholders including Sustainable Renewable Energy Development Authority (SREDA), Bangladesh Power Development Board (BPDB) and Power Grid Company of Bangladesh (PGCB). This was followed by site visits to the two candidate sites of Kaptai and Mohamaya Lakes and a number of substations near each lake (19-21st June 2019). Further meetings were attended with the few remaining project stakeholders on our return to Dhaka (22-26th June 2019) including the Bangladesh Rural Electrification Board (BREB) and the National Load Despatch Centre (NLDC). RINA team visited the candidate sites of Bhukbara, Joydia and Khajura lakes in the Jessore area and a number of substations near each lake during the second site visit in 17-25 November 2019. Further meetings were attended with the project stake holders.
1. PSS/E models: The System planning department provided PSS/E models (static only)
for the years 2019 and 2025. The models require updating as the solar PV plant
currently in operation or under construction has not been modelled. It was understood
that working dynamic PSS/E models for the Bangladesh grid are not available due to
a lack of generator data. The system planning (PGCB) Superintending Engineer (Mr
Shahabunur) clarified that although dynamic models for only a small number of
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
2
generators are available these are of ‘generic type’ and therefore do not represent the
actual response of the generator. He further clarified that the current dynamic model
is incomplete and does not represent the actual system response. PGCB is in the
process of procuring the services of an independent consultant to collect generator
data and build a working dynamic model of the Bangladesh power system, however
this model will not be available in the near future and therefore cannot be used for the
grid impact study.
2. Transmission network data – PGCB: PGCB clarified that most of the demand and
generation data is available from their website (www.pgcb.org.bd). An SLD and
Geographic map of the compete Bangladesh transmission system is also available
from the PGCB website. The information on future development of the PGCB network
is available from the revised PSMP 2016.
• Power System Master Plan 2016, Summary.
• Revisiting Power System Master plan 2016.
• PGCB grid network – Existing 400 kV , 230 kV and 132 kV grid network of
Bangladesh.
• PGCB Geo map – 765 kV, 400 kV, 230 kV and 132 kV grid network
(Existing, U/C and planned).
• Substations under the PGCB.
• List of RE sites - RE Installation list with Evacuation IPP.
• Zonal map of 132/33 kV Grid S/S, 33/11 kV S/S and 33 kV lines under the
UREDS Project - Chittagong zone, Bangladesh rural electrification board.
• A list of generation stations currently providing frequency control from the
NLDC.
• Information on the water head and generation at Kaptai power station.
3. Renewable connection to BREB network: BREB clarified that they would only
accept a connection of the renewable plant directly into their 33 kV substation. A
computer model of the BREB network is not available. Therefore in order to conduct
the grid impact study for a connection into the BREB network this would require
building a computer model of a portion of their network and amalgamating it with the
PSS/E model obtained from the PGCB.
The locations of the substations and the overhead line routes were obtained from the
BREB’s GIS map data from their website (http://gis.brebms.com/)
2.1 ASSUMPTIONS
The following assumptions were made in the absence of data.
1. All Bangladesh network data provided is accurate and appropriate for this study.
2. The thermal ratings of the transmission line, transformers and other equipment in the PSS/E model obtained from the PGCB are assumed to be correct.
3. Since it is at a very early stage of the project and no detailed design is available for the floating PV, generic data for the inverters, transformers and submarine cables were assumed.
4. There is no reactive power compensation equipment present at the PV plant.
5. For the steady state analysis it is assumed that the floating PV does not provide any reactive power support during normal operation however the study will identify the reactive power requirements for the floating PV as per the grid code.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
3
6. The proposed cables and overhead lines are selected to carry the rated transformer capacity.
7. The 33 kV overhead line electrical parameters were not provided by the PGCB thus publicly available datasheets were used to obtain the electrical parameters of the overhead line based on the conductor size (datasheet attached in Appendix F).
8. The 33 kV BREB substations do not have capacitor banks installed.
3 BANGLADESH POWER SYSTEM
Bangladesh has one national grid with an installed capacity of 18.5 GW as of June 2019. The Bangladesh’s energy sector is booming and is expected to grow by approximately 10 -14 %1 in the next 10 years. At present approximately 93 % of the population has access to electricity. The power grid is composed of one HVDC substation, four 400/230 kV substations, twenty seven 230/132 kV substations and one hundred and twenty five 132/33 kV substations.
The Bangladeshi power grid imports power from India via the HVDC interconnection and the interconnection between Cumilla (south) and Tripura in India. The HVDC interconnection is a 1 GW back-to-back HVDC link between Baharampur, India and Bheramara, Bangladesh.
Figure 1: Bangladeshi power sector: at a glance
The RINA team visited the potential sites for the floating PV during their site visit to Bangladesh. During the visit RINA made the following observations regarding the Bangladesh network.
• Voltage Control – Based on the visit to the two sites and further substantiated by the
NLDC and operational discussions it was found that Automatic Voltage Control (AVC) is
not widely used on the transmission system. The usual practice was for the NLDC
Operational (Switching) Engineer to monitor the voltage profile from the Energy
Management System (EMS) via the remote SCADA system – when the voltages were
near to operating outside of the operational ranges the NLDC Operational (Switching)
Engineer would telephone the Substation Attendant Engineer to operate the tap-changer
and either increase or reduce the voltage accordingly.
• Frequency Control – The Operational (Generation Dispatch) Engineer has the
responsibility for the control of the frequency and monitors the frequency during their shift
period. During discussions it was found that many of the generators connected to the grid
1 Revisiting PSMP2016,Power Division Ministry of Power, Energy and Mineral resources
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
4
system do not have the capability to provide automatic frequency response, which makes
the task of frequency control more onerous. Any generation dispatch instructions were
carried out via telephone from the NLDC to the relevant generation personnel.
• Energy Management System (EMS) – the EMS provides the remote monitoring and
control of the system, and whilst much of the control can be undertaken by the Substation
Attendant Engineers via direct instruction from the NLDC the EMS can also provide further
functions including the monitoring of faults and contingency analysis. It is understood that
there is insufficient data to allow full operation of the state estimator and therefore the
Real Time Network Analysis (RTNA) tool. Having this fully operational would assist in the
operation of the system, which may prove more challenging after the adoption of further
renewable (and possibly intermittent) forms of generation.
During the Site visits, it was understood that the Bangladesh power grid also experiences low inertia which is key in restricting the rate of change of frequency during a disturbance in the grid network. Installation of PV plants, which do not have rotational parts, further reduces the system inertia by displacing the synchronous machines. This is not an isolated problem to Bangladesh, the whole world is experiencing this issue.
The separate deliverable “Output 4: Updated grid code and operational guidelines proposed” is looking into these issues and the team will deliver their recommendation in a separate report.
This report analyses the impact on the Bangladesh grid due to the connection of floating PV at the Joydia Lake and which will be connected to the Jhenaidha 33 kV network.
3.1 POWER DEMAND OF BANGLADESH
3.1.1 Forecasted Demand
The Power Division of the Ministry of Power, Energy & Mineral Resources published “Power system Master plan (PSMP) 2016” in 2016 for the years up to 2041. Since then the PSMP 2016 was revised and published “Revisiting the PSMP2016” in 2018.
The “PSMP 2016” and “Revisiting the PSMP2016” includes the forecasted demand and daily load curves for each month for the Bangladeshi network for up to 2041. The month wise daily load curve for 2019, as published in the “Revisiting the PSMP2016”, is shown in Figure 2 below. The Bangladeshi power demand reaches the highest level in April and the lowest level in December and it is evident that the maximum day peak will occur at around 19:00 in April, which equates to approximately 15 GW, while the minimum day demand will occur at around 06:00 in December and is approximately 10 GW.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
5
Figure 2: Forecasted Month-wise Load curve for 20192
3.1.2 Daily operational reports
The PGCB publishes a daily operational report detailing the actual generator despatch data of the previous day and forecasted data of the day of publishing, on its website. In addition, the monthly operation report3 is also published on the PGCB website which details the maximum day peak and evening peak demand of the month and compares it with the maximum day peak and evening peak demand of the same month in the previous year. This report also states the maximum demand to-date.
The minimum demand in the last 12 months was identified as 3.366 GW, which occurred on 31st December 2018 at 05:004 . Considering this to be the minimum demand day, the generator despatch data for the generators connected to the Hathazari, Khulna and Bheramara 132 kV network was collected for the minimum daily demand (08:00) and the total generation at 08:00 was 4.7 GW5.
The maximum demand in the last 12 months occurred on the 29/05/20196, a value of 12.9 GW. Considering this to be the day with the maximum demand, the generator despatch data for the generators connected to the Hathazari, Khulna and Bheramara 132 kV network was collected for the day peak demand (19:00) and the total day peak generation was 10.36 GW7.
3.2 GRID NETWORK – JHENAIDHA 33 KV
The electricity network of the Joydia area, where the floating PV will be installed, is connected to the Jhenaidha 33 kV network. The Kotchandpur and Moheshpur-2 are the closest 33/11 kV substations to the proposed location of the Joydia floating PV.
2 Revisiting PSMP2016,Power Division Ministry of Power, Energy and Mineral resources 3 https://www.pgcb.org.bd/PGCB/?a=pages/operational_daily.php 4 Operational Monthly Report for December 2018 5 Daily report 01-01-2019 6 Operational Monthly Report for December 2018 and August 2019 7 Daily report 30-05-2019
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
6
Figure 3: Geographical location of Jhenaidha 132/33 kV substation, Kotchandpur 33/11 kV and Joydia lake
3.2.1 Jhenaidha 132/33 kV substation
Jhenaidha 132/33 kV substation is supplied from Khulna(S) 230/132 kV and Bheramara 230/132 kV grid substation. A 132 kV double circuit overhead line of Grosbeak 636 MCM (143 MVA of rated power8 each) from Khulna(S) substation connected to Jhenaidha via Khulna(C) Noapara and Jessore 132/33 kV substations. The total length of the overhead line between the Khulna(S) and Jhenaidha substation is around 107.3 km. Jhenaidha substation is equipped with 17.5 MVAr shunt capacitor.
A 132 kV double circuit line overhead line of Grosbeak 636MCM (143 MVA of rated power9 each) from Bheramara substation connected to Jhenaidha via Kushtia 132/33 kV substation. The total length of the overhead line between the Bheramara and Jhenaidha substation is 66.4 km.
The single line diagram for the Jhenaidha substation is attached in Appendix C. The Jhenaidha substation has two 80/120 MVA (ONAN/ONAF) 132/33 kV transformers with 10 x 33 kV feeders.
Conductor size and length of the overhead line for the relevant feeders was obtained from the BREB’s GIS map data10. The overhead line length between the Jhenaidha substation and the Kotchandpur is around 19.5 km.
3.2.2 Kotchandpur 33/11 kV Substation
A 19.5 km length of 33 kV overhead line of 477MCM (30 MVA of rated power) from Jhenaidha feeds the Kotchandpur 33/11 kV substation. The substation has two 5/6.67 MVA (ONAN/ONAF) 33/11 kV transformers.
8 PSS/E model for the Bangladesh transmission network 2019, as received from PGCB 9 PSS/E model for the Bangladesh transmission network 2019, as received from PGCB 10https://www.google.com/maps/d/viewer?mid=1RE6gr4P0xLMG47wvywwl4GHYpZo&ll=22.550909938253202%2C91.62398519986533&z=12
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
7
The maximum day demand of the substation is approximately 9.5 MW and the minimum day demand is approximately 4 MW. The Kotchandpur substation 33 kV buses are rated at 560 A with the short circuit capacity of 16 kA.
Under an N-1 contingency, when the Kotchandpur feeder is not available, the Kotchandpur substation will be transfered to the Moheshpur feeder.
At present the Kotchandpur feeder feeds only Kotchandpur substation. However the new Moheshpur -3 ( Soratola ) 33/11 kV substation which is under construction, will be connected to the Kotchanpur feeder within the next 3 months.
At the time of submitting this report, the line route or line length between the existing Kotchandpur feeder and the proposed substation were not available to RINA, and hence the line route was assumed along the roads, with the total length of the new line around 12 km.
3.2.3 Moheshpur-2 33/11 kV Substation
An overhead line of 477MCM (30 MVA of rated power) from Jhenaidha substation feeds Kaliganji-1 substation, Mohespur-2 and Moheshpur-1 substation. The total feeder length is around 45.3 km and the total length to the Moheshpur-2 substation is around 39.3 km.
The maximum day demand of the substation is approximately 12 MW and the minimum day demand is approximately 7 MW.
3.2.4 Substation Loadings
The following Table 1 shows the loading of the substations connected to the Churamonkathi feeder. It is expected the Moheshpur -3 (Soratola) 33/11 kV substation will have an initial load of 4 MW.
Table 1: Substation loadings
Day peak load Day min load
MW Mvar MW Mvar
Jhenaidha – Kotchandpur Feeder 9.50 4.75 4.00 2.00
Churamonkathi 9.50 4.75 4.00 2.00
Jhenaidha – Moheshpur Feeder
3.2.5 Generators connected to the Jhenaidha 33 kV network
There are no generators connected to the Jhenaidha 33 kV network.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
8
4 JOYDIA LAKE FLOATING PV
The proposed floating PV at the Joydia Lake will consist of 3 medium voltage platforms with a 2.5 MVA inverter and transformer. The proposed layout is attached in Appendix D.
4.1 GRID CONNECTION OPTIONS
The following section details the possible grid connection options to connect the floating PV to the Bangladeshi grid network.
4.1.1 Option 1 – Mohespur-2 33/11 kV Substation – 33 kV Connection
4.1.1.1 Connection scheme
Jhenaidah
Jhenaidah 132 kV bus
132 / 33 kV 80/120 MVA transformers
Jhenaidah 33 kV bus
Other 33 kV feeders
33 kV OHL477 MCM 11.36 km
FPV
33 kV OHL12.2 km
33 kV OHL477 MCM 7.23 km
Kaliganj
33 kV OHL477 MCM 11.64 km
Kaliganj -1 (Patvila)
Mahespur -2 (Valipur)
33 kV OHL477 MCM 21.49 km
33 kV OHL477 MCM 15.34 km
Mahespur -1 (Voiroba)
FPV onshore station
Figure 4: Grid connection at Moheshpur-2r 33 kV bus
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
9
4.1.1.2 Substation Site
The Mohespur-2 33/11 kV substation is owned and operated by BREB, and is located to the north-west of the city of Jessore, and to the south of Joydia Baor.
The distance between the Mohespur-2 substation and the proposed landing site for the Joydia Lake solar PV is approximately 12.2km based on use of the public highway, and alternatively 9.5 km via a straight line path. Due to the complexity of obtaining planning permission for the use of private land, the public highway option has been considered in all cases.
The substation site at Mohespur-2 consists of a typical outdoor busbar arrangement, being similar to other BREB substations. With this arrangement the 11kV and 33kV busbars are supported from the same structures, with overhead busbars run in parallel between the structures.
Tapping connections are then made to the transformers, with 33 kV droppers connected to an open terminal transformer connection. The 11 kV transformer connections are connected in a similar manner, with droppers connecting to open terminals on the transformers. There are seven transformers located at the site; six being single phase and rated at 1.667/2083 MVA each, and the fourth being three phase and rated at 5/6.25MVA. It should be noted that there was no LV supply to the fans therefore the lower transformer rating should be considered.
The transformers included a tap changer for voltage regulation, however it was noted that the transformers required de-energisation prior to changing the tap position. Obviously there was no AVC available on site and therefore the majority of the voltage regulation was either undertaken via the 11kV system balancers or via voltage regulation of the 132/33kV transformers at Jhenaidha 132/33kV substation.
Protection systems were located within the 33 kV and 11 kV auto-reclosers, and therefore there is no control room or any outbuildings located within the site.
The site is considered to be in good condition, well maintained and clear of any vegetation. The steel structures, busbars and switchgear were found to be in satisfactory condition, although maintenance records were not viewed during the site visit.
4.1.1.3 Security of Supply
The Mohespur- 2 33/11kV substation is connected via a radial 33 kV overhead line circuit to the Jhenaidha 132/33kV grid substation. This overhead line is approximately 39.8km in length, which suffers an approximate average tripping frequency of 5.6 events per month. This value appears to be average for the area concerned and the only real option to enhance the security of supply would be to install ring feeder/s to the site which would increase the cost and complexity of the project.
4.1.1.4 Physical Connection
For the connection of the new 33kV overhead line for the floating solar plant there was one spare bay available, however due to the quantity of existing overhead lines within the site and the congested nature of the site it would be difficult to connect a new 33kV overhead line directly. Therefore it is proposed that the overhead line is terminated close to or inside the substation boundary fence, cable sealing ends are installed and the final section of circuit is terminated into the substation via 33kV XLPE cable. A new auto-recloser will be installed and connected to the busbar.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
10
Figure 5: Proposed location of new 33kV bay and cable sealing end
It should be noted that there was no SCADA control at the site, therefore to ensure visibility of the circuit breaker and ensure that the system is intact while operating the solar PV it may be necessary to install remote monitoring and control. An alternative solution would be to have all the control facilities at the solar PV site, with suitable islanding protection, therefore reducing the requirement for controls at the Mohespur 2 substation site.
4.1.1.5 Cost
A very rough estimate for the cost associated with the grid connection option is calculated and presented in the tables below.
Table 2: Cost estimate for Grid connection option 1
Items Cost (BDT)
12.2 km of 33 kV OHL (Linnet 336.MCM) 73,200,000
33 kV breaker ( 2 set) 6,542,000
SCADA 26,328,000
200m of 33kV Cable 1,566,000
Civils 5,600,000
Structures 3,227,000
Protection and control 2,000,000
Control cabling 500,000
Labour 2,000,000
Sub total 125,963,000
Contingency 18,894,450
Prelims and design 12,596,300
Total 144,857,450
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
11
4.1.2 Option 2 - Kotchandpur 33/11 kV Substation – 33 kV Connection
4.1.2.1 Connection Scheme
Jhenaidah
Jhenaidah 132 kV bus
132 / 33 kV 80/120 MVA transformers
Jhenaidah 33 kV bus
Other 33 kV feeders
Kotchandpur 33/11 kV
substation
33 kV OHL477 MCM 19.5 km
Kotchandpur 33 kV bus
FPV
33 kV OHL9.33 km
33 kV OHL477 MCM 2.83 km
Mohespur-3 ( Sarotala) substation ( under
construction)
33 kV OHL477 MCM
12 km(Under
construction)
Figure 6: Grid connection at Kotchandpur 33 kV bus
4.1.2.2 Substation Site
The Kotchandpur 33/11 kV substation is owned and operated by BREB, and is located to the north-west of the city of Jessore, and to the east of Joydia Baor.
The distance between the Kotchandpur substation and the proposed landing site for the Joydia Lake solar PV is approximately 9.5 km based on use of the public highway, and alternatively
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
12
6.8km via a straight line path. Due to the complexity of obtaining planning permission for the use of private land, the public highway option has been considered in all cases.
The substation site at Kotchandpur consists of a typical outdoor busbar arrangement, being similar to other BREB substations.
Tapping connections are made to the transformers, with 33 kV droppers connected to an open terminal transformer connection. The 11 kV transformer connections are connected in a similar manner, with droppers connecting to open terminals on the transformers. There are two transformers located at the site, with both being three phase and rated at 5/6.67 MVA each. It should be noted that there is no LV supply to the fans therefore the lower transformer rating should be considered.
The transformers included a tap changer for voltage regulation, however there was no AVC available on site therefore the majority of the voltage regulation is undertaken via voltage regulation of the 132/33 kV transformers at Jhenaidha 132/33 kV substation.
Protection systems were located within the 33 kV and 11 kV auto-reclosers, therefore there is no control room or any outbuildings located within the site.
The site is considered to be in good condition, well maintained and clear of any vegetation. The steel structures, busbars and switchgear were found to be in satisfactory condition with some surface rust apparent, although maintenance records were not viewed during the site visit.
4.1.2.3 Security of Supply
The Kotchandpur 33/11kV substation is connected via a radial 33 kV overhead line circuit to the Jhenaidha 132/33kV grid substation. This overhead line is approximately 24.8 km in length, which suffers an approximate average tripping frequency of 2.8 events per month. This value appears to be lower than average for the area concerned and the only real option to enhance the security of supply would be to install ring feeder/s to the site which would increase the cost and complexity of the project. It was noted that an alternate circuit ran within 200m of this overhead line and therefore a ring circuit configuration could be easily obtained.
4.1.2.4 Physical Connection
For the connection of the new 33 kV overhead line for the floating solar plant, there was one spare bay available, however due to the quantity of existing overhead lines within the site and the congested nature of the site it would be difficult to connect a new 33 kV overhead line directly. Therefore it is proposed that the overhead line is terminated close to or inside the substation boundary fence, cable sealing ends are installed and the final section of circuit is terminated into the substation via 33kV XLPE cable. A new auto-recloser will be installed and connected to the busbar.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
13
Figure 7: Proposed location of new 33kV bay and cable sealing end
It should be noted that there was no SCADA control at the site, therefore to ensure visibility of the circuit breaker and ensure that the system is intact while operating the solar PV it may be necessary to install remote monitoring and control. An alternative solution would be to have all the control facilities at the solar PV site, with suitable islanding protection, therefore reducing the requirement for controls at the Kotchandpur substation site.
4.1.2.5 Cost
A very rough estimate for the cost associated with the grid connection option is calculated and presented in the tables below.
Table 3: Cost estimate for Grid connection option 2
Items Cost (BDT)
9.3 km of 33 kV OHL (Linnet 336.MCM) 57,000,000
33 kV breaker/auto-recloser 6,542,000
SCADA 26,328,000
200m of 33kV Cable 1,566,000
Civils 5,600,000
Structures 3,227,000
Protection and control 2,000,000
Control cabling 500,000
Labour 2,000,000
Control room equipment 5,000,000
Sub total 109,763,000
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
14
Items Cost (BDT)
Contingency 16,464,450
Prelims and design 10,976,300
Total 126,227,450
4.2 PREFERRED OPTION
The preferred option is option 2: Connecting at Kotchandpur based on the following.
Advantages:
• Lower overall cost.
• Shorter overall route compared to the Mohespur-2 option.
• Better resilience due to lower average tripping frequency.
• Possibility of obtaining a ring circuit configuration at a reasonable capital cost.
Disadvantages:
• Lack of local control or SCADA facilities
5 SYSTEM MODELLING
The grid impact analysis has been conducted for the connection of a PV plant which will be in operation during the daylight time only. Therefore for the purpose of analysing the impact on the grid resulting from the PV farm connection the 2019 peak model was modified to produce day peak and day minimum demand models as per the operational data. The grid impact assessment was carried out for minimum and maximum demand according to the collected data from the daily reports.
5.1 BANGLADESH PSS/E TRANSMISSION MODEL REVIEW
The system model was constructed in PSS/E based on the PSS/E data files of the Bangladeshi transmission network (132 kV to 400 kV) for the year 2019 provided by PGCB. The model included all of the generators connected to the Bangladeshi transmission network.
Figure 8 below shows the network summary data as obtained from PSS/E, and the total connected load is 13119.7 MW. The report “Revisiting PSMP2016” states the Peak load of 2019 as 14603 MW11 .
11 Revisiting PSMP 2016
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
15
Figure 8: Summary of the Bangladesh network (2019) as obtained
Figure 9: Bus voltages near the Jhenaidha 132/33 kV substation - 2019 model as obtained
It is noted that the voltages of the busbars near the Jhenaidha substation are below the planning voltage limits of ±6 % of nominal voltage in the network model as supplied by the PGCB. In practice, it is very unlikely to have 132 kV bus voltages below the planning limits.
Considering the minimum demand in the last 12 months, the model was fine-tuned by scaling down the generation and load to represent the minimum demand as identified in section 3.1.2. The generators connected at the Khulna and Bheramara 132 kV network were modified to dispatch the generation as in the daily report, whilst the remaining generators were scaled down appropriately. The demand for the entire Bangladesh network was also scaled down appropriately.
The same approach was followed to represent the maximum demand. The model was fine-tuned to represent the maximum day demand as identified in section 3.1.2. The generators connected to the Khulna and Bheramara 132 kV network were modified to dispatch the generation as in the daily report while the remainder of the generators were scaled up appropriately
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
16
Figure 10: Summary of the Bangladesh network (2019) – day peak model
Figure 11: Summary of the Bangladesh network (2019) - Minimum day load model
5.2 JHENAIDHA 132/33 KV SUBSTATION
The transmission network model was modified to include the two transformers at Jhenaidha substation and the Kotchandpur feeder. The overhead line was modelled based on the line length and conductor size collected from the BREB GIS map data. The electrical parameters
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
17
of the conductor were obtained from a publicly available datasheet and is attached in Appendix F
The remainder of the load on the substation was lumped at the 33 kV bus of the Jhenaidha substation.
As mentioned in section 5.1, the voltage of the Jhenaidha 132 kV bus is below the planning limit of ±6 % of nominal voltage. Therefore the Khulna substation transformer taps and Jhenaidha transformer taps were adjusted to maintain the Jhenaidha 33 kV voltage at 1 pu. It is noted that the voltage at the Jhenaidha 132 kV bus is around 0.92 pu which is still below the planning limits for Voltage.
Figure 12: Voltages around Jhenaidha substation
The Moheshpur -3 ( Soratola ) 33/11 kV substation, which is being constructed, is also modelled and the line route from Kotchandpur to Moheshpur -3 ( Soratola ) 33/11 kV substation was assumed to be constructed along the roads.
5.3 JOYDIA FPV AND THE GRID CONNECTION
The Joydia FPV was modelled based on the 2.5 MVA SMA MV power station (datasheet attached in Appendix G). The reactive power capability with the variation on the AC voltage was not available at this time for the SMA inverter, and thus it was assumed that with the AC voltage the inverter capacity will vary proportionally.
The submarine cables from the MVPS platforms to the onshore station were assumed to be 33 kV 3-core PILC cable of 70mm2 (datasheet is attached in Appendix E)
The single line diagram for the PV plant is shown in Figure 13 below:
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
18
Figure 13: Single line diagram for 7.5 MW floating solar PV plant
5.3.1 Dynamic model
5.3.1.1 Grid Infeed model
The grid infeed was modelled as an equivalent utility source at the PoC. An independent grid equivalent for each grid connection option was modelled considering a corresponding short circuit level.
5.3.1.2 PV plant dynamic model
For the dynamic analysis the generic dynamic model available in PSS/E v34.6 was used to simulate the dynamic response of the PV inverter. The details of the dynamic model selected are presented Figure 14 & Figure 15:
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
19
Figure 14: PSS/E PV converter model (REGCA1)
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
20
Figure 15: PSS/E Electrical Control Model for PV inverter (REECB1)
5.3.1.3 Power plant controller (PPC) model
The generic PPC model ‘PLNTBU1’ present in the PSSE is used to model the power plant controller for the PV plant. The purpose of the PPC is to control the active power as per the grid code requirements during frequency disturbances. The figure below shows the control schematics for the PPC.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
21
Figure 16: Generic PPC model in PSSE
5.3.1.4 Inverter protection settings
As the dynamic analysis has been carried out considering the generic models of the PV inverter the protection settings for the inverter are assumed in line with the proposed grid code requirements of the renewable plants, and are presented in Table 4 below.
Table 4: Inverter protection settings
Voltage settings
Voltage settings in pu Time settings in seconds
1.20 0.10
1.15 3.00
0.90 3.05
0.30 0.65
0.15 0.20
Frequency settings
Frequency settings in Hz Time settings in seconds
52.05 5.0
47.45 5.0
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
22
6 GRID IMPACT STUDY
The grid impact study was performed to check compliance with the grid code requirements, identify any potential issues that could arise due to the connection of the floating PV and determine suitable solutions that could remedy those issues. Detailed grid compatibility studies were performed which are classified in the following categories:
• Steady-state Studies;
• Dynamic Studies.
6.1 STEADY STATE ANALYSIS
6.1.1 Study criteria
At present a grid code for the distribution network is in the process of development by the authorities. In the absence of a distribution grid code in Bangladesh, the Bangladeshi transmission grid code was referenced to check for compliance.
The Draft Grid Code 201912 for the Transmission network of Bangladesh stipulates the following system planning and security standards.
1. Voltage limits:
o Normal Operating Condition:
• ±5% for 400 kV Bus.
• ±6% for 230 kV and 132 kV Bus.
o Emergency Condition:
• ±10 % for 400 kV Bus.
• +10/-15% for 230 kV and 132 kV Bus.
2. Minimum Contingency Criteria of Transmission Line Outages:
o Single contingency of a permanent three-phase outage of any one circuit
element or transformer.
3. Voltage Withstand Capability:
o The VRE Generating Units shall be capable of generating at maximum power
output, depending on the availability of the primary resource, and the
interchange of Reactive Power at the Connection Point, as specified in
paragraph 5.9.3 of the Grid code 2019, within the voltage variations within the
standard limits for normal operating condition. Outside this range, and up to a
voltage variation within standard limits for emergency condition, a reduction on
active and/ or Reactive Power can be allowed, provided that this reduction does
not exceed 5% of the Generator’s Declared Data.
4. Reactive Power Capability and Control of Variable Renewable (VRE) Generating
Units:
o shall be capable of supplying Reactive Power output, at its Connection Point,
within the following ranges:
▪ +/- 20 % of the Generating Plant capacity, as specified in the
Generator’s Declared Data, if the Active Power output, depending on
the availability of the primary resource, is equal or above 58% of the
Generating Plant capacity;
12 ELECTRICITY GRID CODE,2019, Bangladesh Energy Regulatory Commission
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
23
▪ Any Reactive Power value within the limits of power factor 0.98 lagging
to 0.98 leading, if its Active Power output, depending on the availability
of the primary resource, is within 10 % and 58% of the Generating Plant
capacity;
▪ No Reactive Power interchange with the Grid if the Active Power output,
depending on the availability of the primary resource, is equal or less
than 10% of the Generating Plant capacity.
6.1.2 Base case
6.1.2.1 Maximum Demand
The maximum demand day was identified as 29/05/2019 in section 2. The PSS/E model of the Bangladesh transmission network was modified to represent the day peak demand as in 29/05/2019. The generators connected to the network fed by the Khulna and Bheramara 132 kV network were also modified as per the daily report and the rest of the generation was adjusted appropriately to represent the total generation as on 29/05/2019.
Figure 17 below shows the voltages of the Jhenaidha to Kotchandpur 33 kV feeder. All the bus voltages remain within planning limit of ±6 % with the Jhenaidha transformer taps adjusted to maintain the 33 kV bus voltage at around 1 pu. The voltage at Jhenaidha 33 kV bus at 0.99 pu drops to 0.94 pu at the Kotchandpur 33 kV bus. It could be noted that the transformers are at the extreme tap position.
The overhead line of the Kotchandpur feeder is rated at 30 MVA and the loading level of the line remains within the thermal rating.
Figure 17: Results of Load flow - peak day demand with adjusted tap at Jhenaidha substation
If the network is considered with the Mohespur-3 (Sarotala) substation, the voltage at the Kotchandpur 33 kV bus will fall to 0.91 pu, which is below the planning limits for voltage.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
24
Figure 18: Results of Load flow - peak day demand with Mohespur-3 (Sarotala) substation
Therefore it is suggested to install a capacitor bank around 6 MVAr at Kotchandpur 33 kV bus to increase the Kotchandpur 33 kV bus votlage to 0.95.
Figure 19: Results of Load flow - peak day demand with 6 MVAr capacitor at Kotchandpur
The Grid impact study is conducted on the day peak model with Moheshpur-3 substation and the proposed capacitor bank.
6.1.2.2 Minimum Demand
The minimum demand day was identified as 31/12/2018 in section 2. The PSS/E model for the Bangladesh transmission network was modified to represent the minimum day demand as in 31/12/2018. The generators connected to the network fed by the Khulna and Bheramara 132 kV network were also modified as per the daily load report and the rest of the generation was adjusted appropriately to represent the generation as on 31/12/2018.
Figure 20 below shows the voltages of the Jhenaidha 33 kV feeder to Kotchandpur substation during minimum day demand. All the bus voltages remain within the planning limit of ±6 % of the nominal voltage. None of the transmission lines or the transformers were loaded above their thermal ratings.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
25
Figure 20: Power flow - minimum day load
If the transformer taps were maintained at the same position as for the maximum demand case, as the transformers were not equipped with the AVC, the voltage at the Jhenaidha 33 kV busbar will increase to 1.09 pu during minimum demand, which is above the planning limits.
Figure 21: Power flow - minimum day load with Jhenaidha transformer taps as in the day peak model
Considering the Jhenaidha transformer taps at nominal, installing the capacitor bank at the Kotchandpur substation will not increase the Kotchandpur bus voltage above the planning limit.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
26
Figure 22: Results of Power flow - minimum day load with capacitor bank at Kotchandpur
Therefore it is suggested to equip the Jhenaidha transformers with AVC such that the taps could be adjusted to maintain the Jhenaidha 33 kV voltage at 1 pu. For the purpose of the grid impact analysis, the transformer taps during minimum demand case was maintained at nominal.
6.1.3 Load flow analysis
The following study cases are analysed to study the impact on the 33 kV grid network as a result of connecting the Joydia floating PV at the proposed Kotchandpur 33 kV bus.
• Case 1: Maximum day demand and Maximum floating PV generation.
• Case 2: Minimum day demand and Maximum floating PV generation
6.1.3.1 Case 1: Maximum Demand and Maximum floating PV generation
Typically during the day, when the demand is high (around mid-day), floating PV is also expected to produce its maximum generation. The load flow analysis was performed on the day peak model with the maximum FPV generation of 7.5 MW. The load flow results are shown in Figure 23 below, and it is noted that the voltages remain within the planning limits. Considering the voltages of these buses prior to the connection of the floating PV, the variation on the voltage profile has slightly improved. The loadings of the transmission lines remain within their thermal rating.
The total losses from the onshore station to the proposed Kotchandpur 33 kV substation is estimated to be around 0.2 MW which is around 2.6 % of the total generating capacity of the floating PV.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
27
Figure 23: Power flow - Day peak model with maximum floating PV generation
6.1.3.2 Case 2: Minimum day demand and Maximum floating PV generation
The minimum day model was modified to include the maximum generation from the Joydia floating PV. The results of the load flow studies are presented in Figure 24 below. Reverse power flow through the Jhenaidha transformers is not expected to occur as the minimum day demand is much higher than the maximum export capacity of the Joydia floating PV. The voltages remain within the planning limits.
Figure 24: Power flow - Day minimum model with maximum floating PV generation
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
28
6.1.4 Contingency analysis
Simulations were performed to understand the impact on power flow during carefully selected possible contingency scenarios. The contingency analysis was simulated based on the day peak model and restricted to N-1 running arrangements only.
6.1.4.1 Outage of transmission line from Jhenaidha to Kotchandpur
During a contingency operation, such as a line fault on the line from Jhenaidha to Kotchandpur, the Kotchandpur substation will be transferred to the Moheshpur feeder. At the time submitting this report, it was not possible to determine the route, in addition the arrangement of connection of the feeders to the Kotchandpur line is not known. Therefore studies were not conducted for this scenario.
6.1.4.2 Outage of Jhenaidha transformer
Simulations were performed to study the changes in the Jhenaidha 33 kV network with the Joydia FPV, for a transfomer outage at the Jhenaidha substation. The voltages at the 33 kV buses remained within the planning limit of ± 6 % of nominal voltage. Loading of the Jhenaidha transformer reamined within its rating.
Figure 25: Results of the load flow studies for Jhenaidha transformer outage
6.1.5 Short circuit analysis
Short circuit analysis was performed on the 33 kV network for the connection of the 7.5 MW Joydia floating PV. Short circuit calculations were performed based on the IEC 60909 and the results are shown in Table 5 below. From the table it is noted that the connection of the Joydia floating PV increases the short circuit currents in the circuit however remaining below the short circuit rating of the Jhenaidha 132 kV and 33 kV breakers.
Table 5: Short circuit study for 3 phase faults
Bus name Voltage Short circuit current rating (kA)
Without FPV With FPV
Short circuit MVA
I"k (kA) Short circuit MVA
I"k (kA)
Jhenaidha 132 kV 40 1998 8.74 2,007 8.78
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
29
Jhenaidha 33 kV 31.5 946 16.55 953 16.69
Kotchandpur 33 kV 16 165 2.89 172 3.02
7 FLOATING PV REACTIVE CAPABILITY
The following section analyses the reactive power capability of the 7.5 MW floating PV. The Reactive power capability of the FPV was checked against the transmission grid code for compliance.
The PV farm reactive power capability varies for the different in-feed voltages at the grid in-feed point. A set of simulations were performed to ascertain the floating PV suitability for the full range of operating conditions at the PoC voltages varying from 0.94 pu to 1.06 pu at the maximum rated active power export capacity for the maximum and minimum reactive power import.
Figure 26: Joydia FPV reactive power capability at the Kotchandpur 33 kV PoC with voltage at 0.94 pu
Figure 27: Joydia FPV reactive power capability at the Kotchandpur 33 kV PoC with voltage at 1 pu
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
30
Figure 28: Joydia FPV reactive power capability at the Kotchandpur 33 kV PoC with voltage at 1.06 pu
The 3 x 2.5 MVA inverters design for the Joydia floating PV does not comply with the grid code requirements for the reactive power capability at grid supply voltages from 0.94 pu to 1.06 pu and hence reactive compensation support will be required. Reactive power compensation support could be provided through STATCOMs, SVCs, Capacitor banks, synchronous reactors, or inverters.
7.1 REACTIVE POWER SUPPORT THROUGH AN INCREASED INVERTER CAPACITY
The PV farm inverter rating was increased from 3x2.5 MVA to 2x2.75 MVA+1x3.0 MVA. Increasing the inverter capacity provides the reactive power for dispatch by an inverter. The simulation results are shown in Figure 29 and it can be seen that with the increased inverter capacity the PV farm is able to comply with the reactive power supply requirement at the lower extreme grid voltage of 0.94 pu.
We note that the reactive capability study has been performed based on widely available SMA Inverters. During the detailed design stage careful consideration should be given in selecting the inverters and a reactive power capability study should be repeated to confirm compliance with the grid code.
Figure 29: PV farm reactive capability with increased inverter capacity
8 DYNAMIC ANALYSIS
The dynamic analysis has been undertaken to verify the capability of the FPV plant under system dynamics resulting from disturbances e.g. system faults giving rise to voltage instability
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
31
especially for the duration of fault clearance and thereafter, generation load imbalance or load acceptance/ rejection events giving rise to frequency swings and renewable generation vulnerability due to cloud cover and/ or dawn/ dusk events.
The following section provides the grid code requirements and results of dynamic analyses, and provides comment on the FPV plant capability to remain stable and connected to the system during the grid disturbances.
8.1 GRID CODE REQUIREMENTS
The requirements specified in section 5.9 of the draft Electricity Grid Code 2019 are considered as the basis for carrying out the analysis.
8.1.1 Fault ride through (Performance during Grid Disturbances)
The required fault ride through capability for the plant is mentioned in the draft Electricity Grid Code 2019 and the requirements are shown in Figure 30 below:
Figure 30: Fault ride through requirements for the PV plant as per the draft Electricity Grid Code 2019
As per the requirements the PV plant must remain connected to the grid for the duration of the fault clearance (under voltage durations) shown in Figure 30. Additionally the PV plant should provide the reactive current support for grid stabilisation. The grid code requirements for reactive current injection during a fault are as presented in Figure 31 below:
Figure 31: Allowed generation of Reactive current during Voltage Dips
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
32
8.1.2 Frequency Withstand Capability
As per the draft Electricity Grid Code 2019 the PV plant should be capable of continuous operation with any variation of the power system frequency occurring within the range of 48.0 Hz to 51.5 Hz. Additionally the PV plant shall be capable of operation for at least 5 minutes in the case of an increase in frequency within the range of 51.5 Hz to 52 Hz and for at least 30 minutes in the case of a decrease in frequency within the range of 48.0 Hz to 47.5 Hz.
8.1.3 Active Power Control
In the case where system frequency exceeds 51.0 Hz the Active Power control system should reduce the Active Power injected into the Grid previously, according to the following formula:
∆𝑃 = 33 × 𝑃𝑚 × (51.0 − 𝑓𝑛
50)
Where: ΔP: is the variation in Active Power output that should be achieved Pm: is the Active Power output before the control is activated fn: is the Grid frequency.
8.2 FAULT RIDE THROUGH ANALYSIS
The fault ride through capability of the FPV plant has been carried out for the proposed point of connection. In order to capture the worst case impact of the under voltage stability, the FRT studies assumed voltage change at all three phases simultaneously. A number of different cases are considered for the analysis and are presented in Table 6 below:
Table 6: Cases for fault ride through analysis
Sl. No. Case Grid voltage during
fault
Required time to remain connected
to the grid
1 Case-1 0.0 pu 150 ms
2 Case-2 0.25 pu 600 ms
3 Case-3 0.35 pu 800 ms
4 Case-4 0.85 pu 2.8 seconds
8.2.1 Case-1: 0.0pu voltage at grid during disturbance
Under this case, a three phase to ground fault is simulated at the 33 kV bus in Kotchandpur substation resulting in a voltage of 0.0 pu at the point of connection (PoC) for a duration of 150 ms. With the recommended voltage settings for the PV inverter, the PV plant is found to be capable of riding through the grid disturbance as per the requirements of the grid code and remain connected to the grid. The analysis indicates that due to the fault simulated at the FPV plant connection point the active current generation reduced to around 0 pu during the fault clearance time (150ms) but the plant successfully delivered approximately 1 pu reactive current as per the grid code requirements. The results obtained from the analysis are as presented in Figure 32 and Figure 33 below:
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
33
Figure 32: Case-1 – Voltage at PoC and inverter terminal
Figure 33: Case-1 – PV plant active and reactive current at PoC
8.2.2 Case-2: 0.25pu voltage at grid during disturbance
Under this case, a three phase to ground fault is simulated at the 33 kV bus in Kotchandpur substation resulting in a voltage of 0.25 pu at the point of connection (PoC) for a duration of 600 ms. With the recommended voltage settings for the PV inverter the PV plant is found to be capable of riding through the grid disturbance as per the requirements of the grid code and remain connected to the grid. The analysis indicates that due to fault simulated at the FPV plant connection point the active current generation reduced to approximately 0 pu during the fault clearance time (600ms) but the plant successfully delivered approximately 1 pu reactive
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
34
current as per the grid code requirements. The results obtained from the analysis are as presented in Figure 34 and Figure 35 below:
Figure 34: Case-2 – Voltage at PoC and inverter terminal
Figure 35: Case-2 – PV plant active and reactive current at PoC
8.2.3 Case-3: 0.35pu voltage at grid during disturbance
Under this case, a three phase to ground fault is simulated at the 33 kV bus in Kotchandpur substation resulting in a voltage of 0.35 pu at the point of connection (PoC) for a duration of 3.0 s. With the recommended voltage settings for the PV inverter, the PV plant is found to be capable of riding through the grid disturbance as per the requirements of the grid code and
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
35
remain connected to the grid. The analysis indicates that due to the fault simulated at the FPV plant connection point the active current generation reduced to approximately 0 pu during the fault clearance time (3 s) but the plant successfully delivered approximately 1 pu reactive current as per the grid code requirements. The results obtained from the analysis are as presented in Figure 36 and Figure 37 below:
Figure 36: Case-3 – Voltage at PoC and inverter terminal
Figure 37: Case-3 – PV plant active and reactive current at PoC
8.2.4 Case-4: 0.85pu voltage at grid during disturbance
Under this case, a three phase to ground fault is simulated at the 33 kV bus in Kotchandpur substation resulting in a voltage of 0.85 pu at the point of connection (PoC) for a duration of
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
36
3 s. With the recommended voltage settings for the PV inverter the PV plant is found to be capable of riding through the grid disturbance as per the requirements of the grid code and remain connected to the grid. The analysis indicated that due to a fault simulated at the FPV plant connection point the active current generation remains around 1 pu with a slight increase in the reactive current injection, which is as per the grid code requirements. The results obtained from the analysis are as presented in Figure 38 and Figure 39 below:
Figure 38: Case-4 – Voltage at PoC and inverter terminal
Figure 39: Case-4 – PV plant active and reactive current at PoC
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
37
8.3 FREQUENCY DISTURBANCE ANALYSIS
8.3.1 Over frequency disturbance
In this case a disturbance is simulated in the grid causing the grid frequency to increase to 51.5 Hz. From the simulation results it is observed that the PV plant is capable of remaining connected to the grid for the required duration of five (5) minutes. Additionally, under this condition the FPV delivered around 1.8 MW of active power with the active power controls modelled in the PPC as per the grid code requirements. The results obtained from the simulations are as presented in Figure 40 below:
Figure 40: Frequency and active power from the PV plant during over frequency condition
8.3.2 Under frequency disturbance
In this case a disturbance is simulated in the grid causing the grid frequency to reduce to 47.5 Hz. From the simulation results it is observed that the PV plant is capable of remaining connected to the grid for the required duration of thirty minutes. The results obtained from the simulations are as presented in Figure 41 below:
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
38
Figure 41: Frequency and active power from the PV plant during under frequency condition
9 DISCUSSION
The grid impact study analyses the impact on the Bangladeshi network due to the connection of a 7.5 MW Joydia floating PV. The floating PV is proposed to include 3 x 2.5 MVA inverters and transformers installed in 3 platforms and the installation of medium voltage floating cables between the floating platforms and the onshore station (see Appendix D).
There are two possible options to connect the Joydia 7.5 MW floating PV to the Bangladeshi distribution network.
• Option 1: Connect to the 33 kV bus of the Kotchandpur substation.
• Option 2: Connect to the 33 kV bus of the Moheshpur-2 33/11 kV substation.
From the physical perspective the best option is connecting to the 33 kV substation at the Kotchandpur substation as this is nearest to the site and will be the most economic option. This requires construction of 9.33 km of OHL from the onshore station to the Kotchandpur substation. The proposed route of the 33 kV overhead line will run along the public highway thus negating the complications associated with the routing through private land.
The network model as obtained from the PGCB indicates low voltage at the Jhenaidha 132/33 kV grid substation. The Khulna 230/132 kV substation transformer taps and Jhenaidha 132/33 kV transformer taps were adjusted to maintain the Jhenaidha 33 kV bus at 1 pu. The voltage at the Jhenaidha 132 kV bus is around 0.92 pu which is still below the planning limits for Voltage.
The Jhenaidha substation transformer taps were adjusted to the extreme to maintain the Jhenaidha 33 kV bus at around 1 pu during the maximum day demand. With the taps at the extreme position during minimum demand the 33 kV bus voltage at the Jhenaidha substation will increase to 1.08 pu which is above the planning limit. Therefore it is suggested to equip the Jhenaidha transformer with the AVC.
The total Kotchandpur feeder length to the Kotchandpur substation is around 19.5 km. The Mohespur-3 (Sarotala) substation, which is under construction, will be connected to the
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
39
Kotchandpur feeder and is expected to have an initial load of 4 MW. With the connection of the Mohespur-3 substation, the Kotchandpur voltage will further drop to 0.91 pu during the peak demand, which is below the planning limits for voltage.
Therefore it is suggested to install a capacitor bank of around 6 MVAr at the Kotchandpur substation. With the installation of the capacitor bank, the Kotchandpur 33 kV bus voltage will increase to 0.95 pu (with the Jhenaidha transformer taps at the extreme position) during day peak demand and 0.97 pu voltage during minimum day demand (with the Jhenaidha transformer taps at the nominal position).
Considering the connection option-2 i.e. connecting at Mohespur-2 substaion, which is also fed by Jhenaidha 132/33 kV substation, the total feeder length to the Moheshpur-2 substation is around 39.8 km and the total connected load on the feeder is around 35 MW. Therefore the voltage at the Moheshpur-2 substation would be even lower than the voltage at Kotchandpur substation and hence below the planning limits.
The grid impact analysis was conducted for the preferred connection option of connecting at the Kotchandpur 33 kV bus, which will be fed by the Jhenaidha 132/33 kV substation. The grid impact analysis was conducted considering a 6 MVAr capacitor bank at Kotchandpur and the Jhenaidha transformer equipped with AVC.
The grid impact analysis was checked against the Bangladesh Transmission grid code in the absence of a Distribution grid in Bangladesh for compliance. The results of the load flow studies for the intact running arrangements comply with the planning limits and do not overload the transmission lines.
The 3 x 2.5 MVA inverter design for the floating PV farm does not comply with the Bangladesh grid code requirements for the reactive power capability at grid supply voltages from 0.94 pu to 1.06 pu and hence reactive compensation support will be required. Reactive power compensation support could be provided through STATCOMs, SVCs, Capacitor banks, synchronous reactors or additional inverters. Increasing the inverter rating from 3 x 2.5 MVA to 2 x 2.75 + 1 x 3.0 MVA will increase the reactive power capability of the PV farm and enables the floating PV to comply with the grid code requirements.
Dynamic analysis of the Joydia floating PV plant was carried out to check its capability to remain connected to the grid for various grid disturbances including under voltage, under/ over frequency etc. The studies were carried out considering a generic model for the PV inverter and the protection settings were also assumed to be in line with the proposed draft grid code requirements. From the studies carried out, it is observed that the FPV plant is able to remain connected with the grid as well as providing the required active/ reactive power support to the grid during the disturbances. Furthermore, as the dynamic studies are carried out considering generic models of the PV inverters, it is recommended that these studies are repeated during the detail design stage of the project with the actual OEM model of the PV inverters.
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
40
APPENDIX A. SINGLE LINE DIAGRAM OF THE BANGLADESH TRANSMISSION NETWORK
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
41
APPENDIX B. GEOGRAPHICAL MAP OF THE BANGLADESH TRANSMISSION NETWORK
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
42
APPENDIX C. SINGLE LINE DIAGRAM OF JENAIDHA SUBSTATION
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
43
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
44
APPENDIX D. LAYOUT DIAGRAM OF JOYDIA FPV
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
45
APPENDIX E. SUB MARINE CABLES – ELECTRICAL PARAMETER
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
46
APPENDIX F. OHL PARAMETERS
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
47
APPENDIX G. INVERTER DATASHEET
Grid Impact Study Report - Draft
Capacity Development for Renewable Energy Investment Programming and Implementation Solar PV Power Investment Plan
48