first use of geosynthetic reinforced soil – integrated bridge system in illinois

41
First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois Keith Sargent, P.E. Associate Thomas Engineering Group Dr. Riyad Wahab, P.E. State Geotechnical Engineer IL Dept. of Transportation

Upload: thomas-engineering

Post on 16-Jul-2015

151 views

Category:

Engineering


7 download

TRANSCRIPT

Page 1: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

First Use OfGeosynthetic Reinforced Soil –

Integrated Bridge Systemin Illinois

Keith Sargent, P.E.Associate

Thomas Engineering Group

Dr. Riyad Wahab, P.E.State Geotechnical Engineer

IL Dept. of Transportation

Page 2: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

What is GRS-IBS?• Alternating layers of compacted granular fill

material and sheets of geotextile reinforcement.

• Face of GRS-IBS wall is CMU or modular blocks.

• Wall is constructed on top of a “Reinforced Soil Foundation” (RSF).

• FHWA promotes the use of GRS-IBS through their “Every Day Counts” and “Accelerated Bridge Construction” programs.

Page 3: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Typical GRS Section

Page 4: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Construction Sequence: Step One

• Lay a row of facing blocks.

Page 5: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Construction Sequence: Step Two

• Add a layer of compacted fill.

Page 6: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Construction Sequence: Step Three

• Add a layer of geosynthetic fabric

Page 7: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

What are the benefits?• GRS uses common, readily available materials and

equipment.

• Cost can be up to 25 to 60 percent less than bridges built with traditional methods.

• Easy to maintain due to fewer construction items.

• Reduces construction time.

• Eliminates deep foundations and approach slabs.

Page 8: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Approximate GRS-IBS Costs

• FHWA estimates GRS-IBS using CMU facing to be approximately $33/SF.

• If a wet-cast modular block is used, the estimated cost increase is approximately $28/SF ($61/SF).

• Costs for approach slabs and deep foundations eliminated.

• Comparison: MSE wall costs approximately $55/SF.

Page 9: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

GRS-IBS Use in IllinoisFHWA contacted IDOT to search for projects, and in turn IDOT contacted Districts and Local agencies looking for suitable projects:

• Competent soils resistant to scour

• Waterways with 100-yr velocities of 3 ft/sec max

• Non-staged construction

• Low Average Daily Traffic volumes

• Single Span superstructure - range (25 ft - 80 ft)

• Skew 15° or less

• Abutment wall heights not exceeding 30 ft

Page 10: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

GRS-IBS Use in Illinois

• The Village of Lombard showed interest in using the GRS-IBS technology for their Great Western Trail project.

• Original plan was to use MSE wall retaining pile supported abutments

• Bollinger, Lach and Associates worked with FHWA and the Village to incorporate GRS-IBS technology into Contract Drawings.

Page 11: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Project Location

Page 12: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

MSE Configuration to be Replaced

• 48” deep precast prestressed concrete I beams spanning 92’-6”.•Integral abutments supported by 8 H-piles 80’ long.• 30 ft approach pavement spanning to 10’ wide spread footing.• MSE retaining walls used to shorten span and retain embankment.• Although bridge is for pedestrian use, it is designed for H-20 loading

Page 13: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

MSE Configuration to be Replaced

Page 14: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

GRS-IBS Design• FHWA has assembled guidelines for design of

GRS-IBS.

• Guidelines provide example plan sheets and details along with approximate quantities.

• Detailed construction specifications are also provided within the guidelines.

• Guidelines account for “favorable” and “poor” soil conditions.

Page 15: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois
Page 16: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois
Page 17: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois
Page 18: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois
Page 19: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Normal Use is with Concrete Deck Beams

Page 20: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Revised Elevation with GRS-IBS

• Increased Span Length by 6 ft to accommodate blocks and footing.• Deleted 30 ft by 15 in. thick approach pavement and 10 ft footings.• Deleted piles, added 6 ft wide spread footings.• Kept Aggregate column ground improvement.

.

Page 21: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Revised Section with GRS-IBS

• C.I.P. Footing.

• Reinforced Soil Foundation (RSF) on Aggregate Columns.

• Used Extra GRS Aggregate Backfill to transition approach settlement.

• Approach is 3” HMA.

Page 22: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Current Construction Status

• Project was on September 23, 2011 Letting.

• Aggregate Column Ground Improvements - completed on May 29th, 2012.

• Reinforced Soil Foundation and Modular Block Walls (both east and west sides) - completed on August 17th.

• C.I.P. footings - installed August 25th.

• PPC I-Beams to be erected in October.

• Instrumentation to monitor wall movement installed at the end of August (paid for by FHWA).

Page 23: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Aggregate Column Installation

Page 24: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Aggregate Column Installation

Page 25: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Aggregate Column Installation• Installation of Aggregate Columns went

smoothly. • Approximately two days of work for each

abutment.• Approximately 65 columns per abutment.• Test column provided excellent results.

– Loaded to 150% of design load (48 kips)– Deflected less than a ½”

• Total Cost: $108,000

Page 26: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

RSF Shop Drawings

Page 27: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

RSF Installation

• Four Step Process:– Install geotextile fabric on subgrade leaving excess on

the sides.– Compact lifts of CA-06 stone.– Install layers of geogrid reinforcement.

– Wrap foundation with geotextile fabric.

• Installation of RSF is simple, however this project required foundation steps that complicated the construction.

Page 28: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

RSF Construction

Page 29: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Block Shop Drawings

Page 30: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

RECON Blocks Selected

• 16”tall, 48”wide 24”deep

• Other approved blocks included Redi Rock and Stone Strong

• Wet Cast Block Required

• To be stained and anti-graffiti surface applied

Page 31: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Modular Block Installation

• Block installation took longer than anticipated given the size of the block (4FT wide x 16” tall x 24” deep).

• FHWA intent is to use 45 LB CMU blocks, not 1600 LB wet cast blocks.

• Approximately 400 blocks per wall.• Making certain blocks are level and set into place

is very important.• Block constructed with no batter, so precision was

crucial.

Page 32: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Modular Block InstallationSetting first row level and in line was very important.

Page 33: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Modular Block InstallationExcavator needed to set block – very time

consuming and difficult to perform precisely.

Page 34: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Geosynthetic Reinforced Soil Installation

• Soil reinforcement was Tenax TT L Type 70 geogrid.– Delivered in 4 FT wide rolls.

– Difficult to cut and lay flat.– Stretching tight was important.

• Select Fill was CA-16.– Required little compaction

– Easy to work with.

Page 35: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Geosynthetic Reinforced Soil Installation

Tenax installed between blocks and halfway up block.

Page 36: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Geosynthetic Reinforced Soil Installation

Page 37: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Final Product

Page 38: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

FHWA Monitoring Research• FHWA hired TEG to perform survey monitoring at

regular intervals over the next two years• Goal is to monitor horizontal and vertical displacement of

the wall.

Page 39: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Remaining Work

• Installation of PPC I-Beams

• Superstructure with Safety Railing

• Decorative lighting

• Staining/Coloring of Wall

• Anti-Graffiti Coating with UV Protection

Page 40: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Final Thoughts• The use of GRS-IBS for the Great Western

Trail project in Lombard may not be representative of a usual GRS-IBS project.

• Modular block used for Great Western Trail was large and required heavy machinery and added labor to set in place.

• Modular block used was much more expensive than a standard CMU.

• Overall cost was higher than MSE wall.

Page 41: First Use Of Geosynthetic Reinforced Soil – Integrated Bridge System in Illinois

Questions?

Email: [email protected]

http://www.fhwa.dot.gov/everydaycounts/technology/grs_ibs/