first test firing of an ariane-5 production · pdf filebooster-motor performance ... the...

4
r bulletin 104 — november 2000 62 First Test Firing of an Ariane-5 Production Booster A. González-Blázquez Directorate of Launchers, ESA, Paris A. Constanzo Direction du Développement Ariane, CNES/Arianespace, Evry, France Introduction Ariane-5 accompanying activities started in 1996 with ARTA-5, based on the experience gained from Ariane-3 and 4. The objectives of this ESA programme are to monitor the performance and reliability of the Ariane-5 launcher during its operational phase, deal with ground and flight non-conformances, and assess the validity of design and material changes. The high reliability requirements set for Ariane- 5 and the aim of reducing both production and operating costs have resulted in a launcher configuration that differs substantially from that of previous generations. The chosen configuration required a new solid-propellant booster. The initial development of the booster served to freeze its definition and establish the production procedures and hardware acceptance criteria. Five development and two qualification tests were performed. Presently three types of activities are being carried out under ARTA-5: – analysis of in-flight measurements during operational launches – recovery of flight specimens for inspection (thickness of thermal protection, nozzle parts, field joints) – ground firings of full-scale production boosters. The ground test conducted on 16 May was the first firing of a production booster. CNES, on behalf of ESA, supervised all of the test-related activities. Europropulsion was responsible for the manufacture of the booster (Fig. 1). Test objectives The main objectives of the test were: verification of the performance of the motor and of the overall stage (actuators, high- pressure vessels, cable ducts, etc.) qualification of a new European procurement source for the binder used in the solid propellant of the middle segment (S2) examination of the effects of ageing on a six- year-old nozzle and evaluation of the performances of the various mechanical components – qualification of the forward segment (S1) loaded with an extra 2.2 tons of propellant. This segment provides about 50% of total thrust during the first phase of an Ariane-5 flight. This increase, corresponding to 10% of total S1 mass, will provide an extra The first test firing of a production P230 booster for the Ariane-5 launcher was conducted successfully on 16 May 2000, on the solid- propellant-booster test stand (BEAP) in Kourou, French Guiana. The test formed part of the Ariane-5 Research and Technology Accompaniment Programme (ARTA-5)*. * For background information on ARTA-5, booster development and facilities, see ESA Bulletins 94 (May 1998), 69 (February 1992) and 75 (August 1993). Figure 1. Test firing of the ARTA01 booster on 16 May 2000

Upload: vudang

Post on 15-Mar-2018

219 views

Category:

Documents


1 download

TRANSCRIPT

r bulletin 104 — november 2000

62

First Test Firing of an Ariane-5 ProductionBooster

A. González-BlázquezDirectorate of Launchers, ESA, Paris

A. ConstanzoDirection du Développement Ariane, CNES/Arianespace, Evry, France

Introduction Ariane-5 accompanying activities started in1996 with ARTA-5, based on the experiencegained from Ariane-3 and 4. The objectives ofthis ESA programme are to monitor theperformance and reliability of the Ariane-5launcher during its operational phase, deal withground and flight non-conformances, andassess the validity of design and materialchanges.

The high reliability requirements set for Ariane-5 and the aim of reducing both production andoperating costs have resulted in a launcherconfiguration that differs substantially from that of previous generations. The chosenconfiguration required a new solid-propellantbooster. The initial development of the boosterserved to freeze its definition and establish the production procedures and hardwareacceptance criteria. Five development and two qualification tests were performed.Presently three types of activities are beingcarried out under ARTA-5: – analysis of in-flight measurements during

operational launches– recovery of flight specimens for inspection

(thickness of thermal protection, nozzleparts, field joints)

– ground firings of full-scale productionboosters.

The ground test conducted on 16 May was thefirst firing of a production booster. CNES, onbehalf of ESA, supervised all of the test-relatedactivities. Europropulsion was responsible for themanufacture of the booster (Fig. 1).

Test objectives The main objectives of the test were:– verification of the performance of the motor

and of the overall stage (actuators, high-pressure vessels, cable ducts, etc.)

– qualification of a new European procurementsource for the binder used in the solidpropellant of the middle segment (S2)

– examination of the effects of ageing on a six-year-old nozzle and evaluation of theperformances of the various mechanicalcomponents

– qualification of the forward segment (S1)loaded with an extra 2.2 tons of propellant.This segment provides about 50% of totalthrust during the first phase of an Ariane-5flight. This increase, corresponding to 10%of total S1 mass, will provide an extra

The first test firing of a production P230 booster for the Ariane-5launcher was conducted successfully on 16 May 2000, on the solid-propellant-booster test stand (BEAP) in Kourou, French Guiana. Thetest formed part of the Ariane-5 Research and TechnologyAccompaniment Programme (ARTA-5)*.

* For background informationon ARTA-5, boosterdevelopment and facilities, seeESA Bulletins 94 (May 1998),69 (February 1992) and 75(August 1993).

Figure 1. Test firing of the ARTA01 booster on 16 May 2000

GON 11/8/00 9:23 AM Page 2

Figure 2. Booster-motorperformance characteristics

test firing new ariane-5 booster

63

payload capacity of about 200 kg for injectioninto Geostationary Transfer Orbit (GTO)

– validation of a new repair process developedfor the thermal insulation. A repair operationwas executed on a rear booster segment(S3)

– verification of the new thrust profile with theextra-loaded S1 segment and modifiedignition delay, and validation of themathematical model used to predict thisprofile for operational launches.

Appraisal of a set of design enhancements,basically aimed at mass reduction, was anotherobjective. These modifications include a newattachment system for the electrical lines (nowsecured directly to the booster’s skin byadhesive, in place of mechanical attachments)and a stretched nozzle.

The ARTA01 motor The Ariane-5 configuration is made up of twosolid-propellant boosters attached to acryogenic stage, the boosters providing 90% ofthe total propulsion at lift-off.

The P230 stage is built up from the followingelements:– solid-propellant motor (see current

performance/characteristics in Fig. 2)– nozzle control unit– electrical and pyrotechnic subsystem– forward and aft skirts– forward and aft attachment devices

interfacing with the cryogenic stage.

The main element is the motor, which has ametal casing in seven cylindrical sections. Thecasing with liner and thermal insulation ischarged with three blocks of solid propellant.The nozzle has a Sepcarb throat and phenolicinsulation. The igniter starts the combustion,which reaches a radial velocity of around 7.4 mm/s. The total burn time is 130 s.

For this test, the motor had the followingspecial features:– serial motor casing with forward segment

reinforced– thermal insulation applied using new

machinery– extra-loaded S1 forward segment– new binder in the S2 segment– repaired thermal insulation on the S3

segment– new nozzle (M2R).

This nozzle is a preliminary version of theP2002 configuration due to be tested in thesecond test firing. Several nozzle parts havebeen modified, including the nose, throat andconvergent inserts and the divergent. New

materials have been used, namely CR 151 andSepcarb 54-45. These modifications weredriven by the need to replace obsolescentmaterials and optimise mass and cost.

Test-facility preparation The BEAP test stand was built for thedevelopment of the full-scale booster and alsofor use during the production phase. Thestand, located near the production and launchsite, was designed for test-firing boostersmounted vertically, nozzle downwards, therebyreproducing flight conditions as closely aspossible (Fig. 3).

The test facilities consist of the servicing tower(62 m high), the flame trench (60 m deep, 200m long and 35 m wide), and the test control

Igniter• 1.18 m long

(1.25 m with initiator)• 0.47 m diameter• 315 kg• 65 kg propellant

S3 aft segment• 11.1 m long• cylindrical grain• 106.7 metric tons propellant

Steerable nozzle 6° (max. 7.3°)• 3.78 m long*• 2.99 m nozzle outlet diam.*• metallic/composite• 6.4 metric tons* For flight 501, extended from flight 502

Booster case• steel• 7cylindrical segments

(8 mm thick)• 2 bulkheads

S1 forward segment(star-shaped grain)• 3.5 m long• 23.4 metric tons propellant

S2 centre segment• 10.17 m long• cylindrical grain• 107.4 metric tons propellant

Intersegment seal

Intersegment seal

Internal thermal insulation(rubber based)

Liner based on propellantbinder(to bind propellant to insulation)

The solid propellant is a mixtureof:• 68% ammonium perchlorate

(oxidizer)• 18% aluminium (fuel)• 14% polybutadiene (binder)

and misc.

Ø 3050

27343

Vacuum thrustmaximum 6709 kN average 4984 kN

Max. pressure 61.34 bar

Specific impulse 275.4 sec

Burn time 129 sec

Mass at liftoff:inert : 31.2 metric tons

propellant: 237.7 metric tons

Total mass:269 metric tons

Prime contractor:EUROPROPULSION

GON 11/8/00 9:23 AM Page 3

Figure 3. The booster teststand

Figure 4. The ARTA01booster prepared for firing

– good behaviour of the phenolic carbon ofthe divergent, both the currently used CR138 and the C 151 under qualification

– a preliminary measurement of mean throaterosion of 41 mm, well within the predictedrange.

The full test-result analysis is being performedin three steps:– preliminary data analysis in the days

following the tests– Level-0 data analysis at the end of June of

the whole measurement set with the help ofthe powerful ETNA 5+ software

– Level-1 data analysis, currently beingperformed together with detailed hardwareinspection.

The Level-0 data analysis found goodcorrelation between the predicted andmeasured combustion pressures, showinggood booster performance and validating theprediction model. Final analysis at Level-1 willhelp to qualify the booster modificationsincluded in this test configuration.

Conclusion ARTA-5 accompanying activities are set tocontinue throughout the lifetime of the Ariane-5launcher. The analysis of flight data combinedwith the sample testing for key launcher

r bulletin 104 — november 2000

64

building located 600 m away. The main functionof the tower is to hold the booster and measurethe thrust during testing. The control buildinghouses the electrical equipment and the roomfrom which to monitor the firing.

Fifteen people were involved in the testcampaign, which commenced with preparationof the stand. The mechanical and fluid systemshad been dismantled on completion of thebooster development and qualification phases.They were therefore reinstalled for this testfiring. Initial preparation tasks on the facilitytook three months, from September toDecember 1999. The work continued fromJanuary to mid-March 2000 to achieve the finalconfiguration required for the test. Aconsiderable amount of instrumentation wasused, requiring the installation of 429 sensors inthe booster (Fig. 4).

Test resultsThe test was successfully performed on 16May 2000, after a delay due to extremeweather conditions during the rainy season inFrench Guiana (Fig. 5).

The visual inspection after the firing (Fig. 6) wasessentially devoted to the nozzle, and itconfirmed:– integrity of the divergent extremity

GON 11/8/00 9:23 AM Page 4

Figure 5. The booster firingsequence

elements will serve to maintain high reliability forAriane-5. The test described here was acontribution to this objective in the solid-propulsion domain. This first test firing of anAriane-5 production booster has shown thegood functioning of the solid-rocket motor andvalidated proposed modifications.

AcknowledgementsThe authors wish to thank CNES andEuropropulsion for providing the photographsfor this article. r

test firing new ariane-5 booster

65

Figure 6. Post-firing boosterinspection

GON 11/8/00 9:24 AM Page 5