first below ground traction at church road anook k gupta

Upload: muthuraj74

Post on 07-Jul-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    1/49

    First Below Groundirst Below Groundirst Below Groundirst Below Ground

    Tractionractionractionraction Substation at Church Roadubstation at Church Roadubstation at Church Roadubstation at Church Road

    New Delhi) Receiving SubstationNew Delhi) Receiving SubstationNew Delhi) Receiving SubstationNew Delhi) Receiving Substation

    A case Studycase Studycase Studycase Study

    By:

    Anoop Kumar Gupta, Director (Electrical)

    Mahendra Kumar, Chief General Manager

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    2/49

    This presentation covers -

      About DMRC

     Progress/achievements so far   Status of Phase III

     Operational Highlights

      Power Supply Arrangement in DMRC

     Power Supply requirement

     Power System Architecture

      Contract Demand and Energy Consumption

      Construction of below ground Substation  Challenges faced

     Layout Plan

      Glimpses of the site

    2

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    3/49

    About DMRCAbout DMRC

    3

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    4/49

    4

    4

    DELHI METRO RAIL CORPORATION (DMRC)

    •  Set up in May’95 under the Indian Company Act.

    •   A joint venture between the GOI and the GNCT Delhi,

    with equal equity.

    •   DMRC has the responsibility for construction andoperation of Delhi Metro.

    •  A Master Plan had been drawn up for Delhi Metro

    expansion, consisting of 12 lines, covering 420 kms to

    be completed by 2021 in four Phases.

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    5/49

    5

    5

    DMRC  – PROGRESS/ ACHIEVEMENTS SO FAR

    •   Phase-I  – 65 kms Completed in 7 years and 3 months(2 years & 9 months ahead of schedule).

    •   Phase-II   –   125 kms -- Though double the length,

    completed in half the period taken for Phase-I, and fivemonths ahead of schedule.

    •   Phase III - 136 km Sanctioned in Sept 11 and has been

    committed to the Govt. for completion in 4.5 years.

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    6/49

    6

    Phase IIIPhase III

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    7/49

    STATUS OF PHASE-III

    •   Further expansion by 136 kms. 110 km (50 km U/G) inDelhi & 26 km in Haryana (14 km) Line-6 Badarpur to

    YMCA Chowk, Faridabad & (12 km) Mundka to

    Bahadurgarh.

    •   The contracts are in place and the work is in progress.

    •   For the first section Trial run was flagged off in

    December 2013 for the CTST- Mandi house corridor

    of phase III

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    8/49

    STATUS OF PHASE-III

    8

    •  Phase-III likely to be completed by 2016

    •   On completion of Phase-III Delhi will have a

    metro network covering 326 kms.

    •   Delhi is the fastest growing metro network

    in the world outside China.

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    9/49

    Operational HighlightsOperational Highlights

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    10/49

    10

    10

    •   DMRC is having 142 Stations and 190 Km in operation. This is

    including high speed Airport Express line having 6 stationsand 23 km section.

    •   About 2800 train trips a day   –   with 208 train sets (1100

    Coaches) on 6 lines.

    •   Each train used to consist of 4 coaches. With the increase in

    commuters, the trains are progressively being lengthened to

    6 coaches and finally to 8 coaches. We have already near

    about 100 six car sets.

    •   Average Ridership   –  more than 2.3 million passengers per

    day. (meaning about 1,00,000 vehicles off the road)

    OPERATION HIGHLIGHTS

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    11/49

    11

    OPERATION HIGHLIGHTS

      Frequency during peak hours – 2 m 40 sec on 2 out of 6 lines

    (on other lines 3 to 5 mts).

      DMRC has around 7,000 employees, besides contract staff.

      Op. Ratio 62%

      Fare : From 8/- to 30/-. The system is making an

    operational profit from Day-1.

      DMRC is able to service and pay back the loans despite nosubsidy from the Government and the Fare Structure being

    lowest in the world except Kolkata.

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    12/49

    12

    12

      20% of  DMRC’s revenue is from Non-operational sources  –mainly real estate development and advertisements.

    •   The system is fully  Barrier Free for Physically challenged.

    •   The trains operate from 6 AM to 11 PM.

    •   DMRC has introduced feeder bus short loop services to help

    the commuters.

    •   Punctuality measured with a least count of 60 sec and the

    punctuality percentage has been above 99%.

    OPERATION HIGHLIGHTS

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    13/49

    DWARKA

       L   A   X   M   I   N   A   G   A   R

       Y   A   M   U   N   A   B   A   N   K

       N   I   R   M   A   N   V   I   H   A   R

       P   R   E   E   T   V   I   H   A   R

       K   A   R   K   A   R   D   U   M   A

    BOTANICAL GARDEN

    GOLF COURSE

    NOIDA CITY CENTRE

    DHAULA KUAN

    DELHI AEROCITY

    DWARKA SEC 21

       A   S   H   R   A   M

       S   R   I   N   I   V   A   S   P   U   R   I

    `

    KALINDI KUNJ

    PALAM

    DHSRATH PURI

    DABRI MOR

    BOTANICAL GARDEN

    DELHI GATE

    JAMA MASJID

    LAL QUILA

    •PHASE –I = 65.1Km

    •PHASE –II = 125.0 Km

    Phase –

    III = 136.0 KmTotal = 326.0 Km

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    14/49

    Power Supply ArrangementsPower Supply Arrangements

    in DMRCin DMRC

    14

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    15/49

    • Electricity is required for:

      Running of trains,

      Station services

    • Power requirements are determined by peak-hour demands

    of power for traction and auxiliary applications.

    • Broad estimation of auxiliary and traction power demand is

    made based on :

      Regeneration by rolling stock – Up to 35%

      Elevated station load – about 500 KW

      underground station is assessed at about 3.2 MW

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    16/49

    •   From the reliability point of view Power supply at 220 kV, 132

    kV or 66 kV level is taken from the Grid Sub Stations of 

    DTL/UPPCL/HVPN.

    •   At the RSS it is stepped down to 25 kV to feed the OHE with

    single phase traction transformers and 33 kV with 3 phase

    auxiliary transformers to feed the auxiliary requirements. Bothare with 100% standby capacity.

    •  33 kV is distributed through duplicate ring feeders along the

    corridor and at every station it is stepped down to 400 volts(3 phase supply) through dry type transformers. This

    substation is termed as Auxiliary Substation (ASS) in our

    system. This is distributed in the station to meet the power

    supply requirements of the stations.

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    17/49

    POWER SYSTEM ARCHITECTURE

    •   DMRC is taking power supply through two incomers

    through underground cables.

    •   In case of failure in one incoming circuit the other

    cable will be able to take full load.

    •   Power failure from one RSS , adjacent RSS can takefull load

    •   Failure of one transformer, the standby can take the

    full load.

    Thus adequate redundancy has been built in at all stages

    from the reliability point of view

    17

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    18/49

    POWER SUPPLY IN DMRC

    Incoming power supply from Grid 220/132/66000KV

    Transformers

    25000

    volts

    33000

    volts

    25000

    volts

    33000

    volts

    To DMRC line

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    19/49

    CONTRACT DEMAND & ENERGY CONSUMPTION SINCE 2006-07

    S. No. AS ONCONTRACT DEMAND

    in MVA% increase

    1 31.03.2007 47

    2 31.03.2008 52 10.6 %

    3 31.03.2009 52 10.6%

    4 31.03.2010 75.5 58.5%

    5 31.03.2011 115 144.6%

    6 31.03.2012 130 176.5%

    7 31.03.2013 138 193.6%

    8 AS ON 01.08.2013 141 200%

    CONTRACT DEMAND

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    20/49

    ENERGY CONSUMPTION

    S.No Financial Year MU % increase

    AMOUNT PAID

    in million

    1 2006-2007 189.52 480.60

    2 2007-2008 199.61 10.5 514.80

    3 2008-2009 220.14 16.15 707.20

    4 2009-2010 254.49 34.33 832.29

    5 2010-2011 422.73 123.05 1390.05

    6 2011-2012 577.56 204.7 2139.24

    7 2012-2013 596.69 214.84 3198.61

    8  2013-14

    upto Oct-13410.33 271.17 2554.09

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    21/49

    Rss in phase-1

    LINE RSSIncoming

    Voltage

    LINE-1 KASHMERE GATE 220 kV

    LINE-1 RITHALA 66 kV

    LINE-2 NEW DELHI 66 kV

    LINE-3 DWARKA 66 kV

    LINE-3 SUBHASH NAGAR 66 kV

    LINE-3 INDRAPRASTHA 66 kV

    TOTAL 6 SUBSTATIONS

    RSS IN PHASE I

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    22/49

    LINE RSS Incoming Voltage

    LINE-2   • JAHANGIRPURI,

    • CHHATARPUR

    • SUSHANT LOK (HCC)

    • 66 kV

    • 66 kV

    • 66 kV

    LINE-3   • BOTANICAL GARDEN   • 132 kV

    LINE-5   • MUNDKA   • 66kV

    LINE-6   • SARITA VIHAR

    • PARK STREET (CTST)

    • 66 kV

    • 66 kV

    AIRPORT LINE   • PARK STREET (CTST)• AIRPORT

    • 66 kV• 66 kV

    TOTAL 8 SUBSTATIONS

    RSS IN PHASE II

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    23/49

    NEW Rss in phase-3

    LINE RSSIncoming

    VoltageSTATUS

    LINE-5   • MIE DEPOT RSS   • 132 kV   • Contract opening on 10.12.13

    LINE-6   • KASHMERE

    GATE

    • FARIDABAD

    • 220 kV

    • 66 kV

    • Power from existing Cables of

    Phase I RSS of DMRC

    • Work in process

    LINE -7   • MUKUNDPUR

    • DHAULA KUAN

    • INA

    • VINOD NAGAR

    • YAMUNA VIHAR

    • 66 kV

    • 66 kV

    • 66 kV

    • 66 kV

    • 66 kV

    • Gopalpur DTL by 2016-17contingency from JP RSS

    • One from Ridge valley + One

    Park street

    • From RK Puram RSS of DMRC

    for One Circuit

    • Two Circuits from Gazipur

    • Power not available at Harsh

    Vihar DTL

    STATUS OF RSS IN PHASE III

    To be contd ….

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    24/49

    LINE RSSIncoming

    VoltageSTATUS

    LINE -8   • KALKAJI

    • RKPURAM

    • PALAM

    • 66 kV

    • 66 kV

    • 66 kV

    • One from Sarita Vihar DTL and2nd LILO of Existing

    • One Ckt from Vasant Kunj and

    second incomer being taken to

    INA RSS

    • No Ckt from Papankalan 3-

    • Existing Subhas nagar to be

    made LILO and 2nd ckt when

    PPN 3 comes up

    TOTAL 11 SUBSTATIONS

    Contd ….

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    25/49

    AUGMENTATION WORKS of RSS IN PHASE - III

    LINE RSS

    LINE-2   • JAHANGIRPURI

    (One Trafo of 131 MVA -220/66 kV)

    LINE-3   •  BOTANICAL GARDEN

    (2 nos 25 kV bays added)

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    26/49

    Construction of belowConstruction of belowGround SubstationGround Substation

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    27/49

    Construction of the Sub-Station at Church Road

    •   Line-6 and Airport Express Line in phase II were to be

    fed from this RSS•  The incoming supply was to come from Park Street

    S/s of DTL 1.6 kms away

    •   Plot size of 5000 sqmts

    •   Tender was awarded for a normal RSS and materials

    procured

    •   Being close to Rastrapati Bhawan it required

    clearance from Central vista Committee•   CVC desired that no part of the substation should be

    above ground, except boundary wallTo be contd …

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    28/49

    •   The building housing GIS Hall and Control room shall

    be 0.3 m high only from the road level.•   The top of the roof may be landscaped to present a

    green appearance and the height of solid portion of 

    boundary wall should be 1m high only

    •   Baffle wall only 1.2 m high from road level

    •   The layout was redesigned with incoming 66 kV cable

    gallery at -9 m, GIS hall at -7 m level and transformer

    yard at -6m level.

    Contd …

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    29/49

    LAYOUT PLAN

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    30/49

    ELEVATION

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    31/49

    ELEVATION

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    32/49

    Challenges facedChallenges faced

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    33/49

    Challenges faced

    •   Maintaining the clearances both in the vertical as well as

    horizontal direction in the transformer bay was required.

    •   Ventilation for the underground substation- Forced

    ventilation system for the equipment rooms was adopted -

    Three   AHU’s   (2 Main + 1 Standby) have been provided

    considering 15 Air changes per hour.

    •   Water drainage system for this catchment area. The cables

    trenches were designed with hangers at a height of 300 mm

    from the bottom on which the cables were laid and thebottom portion was used for draining the water to the water

    tank with natural gravity towards the water collection tank.

    To be contd …

    C td

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    34/49

    •   Smoke detectors have been provided in the cable trenches in

    the - 9 m area and the yard.

    •  Precision type Floor mounted Air-conditioning system has

    been provided for the cooling of Control & Relay room and

    the server rooms with the arrangement of two main and one

    standby AC units

    •   Water pumping arrangement has been made such that the

    system can pump out 1 lakh liters of water in one hour

    keeping in account the catchment area. Automation has

    been provided with three pumps. The first pump operates at

    25%, second pump at 50% and the third pump at 85% of the

    water being filled up in the water tank.

    Contd …

    To be contd …

    C td

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    35/49

    •   The soil resistivity of the substation indicated that soil is

    having three layers with upper layer having low resistivity,

    middle layer having high resistivity and bottom layer again lowresistivity.

    •   Upper strata is having low soil resistivity of 73 ohm-m, Middle

    strata is having very high soil resistivity of 783 ohm-m andLower strata is again low resistivity of 63.2 ohm-m.

    •   For better performance of grounding system, grid is placed in

    low resistivity soil and analysis has been done using Auto Grid

    Pro software package. Satellite earthing had to be adopted

    since mother earth was not available for the electrodes

    Contd …

    To be contd …

    C td

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    36/49

    •   A DG set of capacity 125 kVA has been provided at a higher

    platform to meet out the emergency power requirement in

    case of power supply failure to run the ancillary system of thesubstation.

    •   Substation Automation based on Intelligent Electronic Device

    on IEC 61850 has been provided for control and protection of the system.

    •   This substation is first of its kind with unique layout below

    ground level.

    •   Each bay comprises of one circuit breaker and associated

    disconnectors, earth switches and instrument transformers.

    Contd …

    To be contd …

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    37/49

    37

    •   At bay level, the IEDs provide all bay level functions likecontrol (commands outputs), monitoring (status indications,measured values).

    •   The IEDs are directly connected to the switchgear avoidingthe need for additional interposing of transducers.

    •   Each bay control IED is independent of the others and itsfunctioning is not affected by any fault occurring in any of theother bay control units of the substation.

    •   The data exchange among bay level   IED’s, and between baylevel and substation level take place via dual fiber-optic interbay bus according to IEC 61850-8-1 protocol.   37

    Contd …

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    38/49

    Station Level

    •   Human Machine Interface enables local station control and

    monitoring through the vendor software package compatiblewith IEC 61850.

    •   DMRC Substation bays are limited the bay bus arrangementprovides independent station-to-bay and bay-to-bay data

    exchange.

    •   Substation Configuration Language (SCL) facilitatesintegration of the system by the users/operators and can beused without detailed knowledge of real-time systems.

    •   An authorization mechanism has been provided to preventsystem access to unauthorized users

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    39/49

    OCC Level

    •   IEC 61850 signals are converted to IEC 60870-

    5-101 signals through a software based

    gateway for communication from the substationto the OCC.

    39

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    40/49

    40

    Glimpses of the SiteGlimpses of the Site

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    41/49

    Before execution of the Below ground

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    42/49

    View of the Rashtrapati Bhawan

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    43/49

    CLEARANCES PLACEMENT OF THE DG SET

    GIS H ll With V til ti A t

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    44/49

    GIS Hall With Ventilation Arrangement

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    45/49

    Views of landscape of the RSS

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    46/49

    Full View of the RSS

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    47/49

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    48/49

    CONCLUSION

    Space has been a constraint for all the urban

    cities. Now attempt is being made to

    accommodate the RSS in a smaller space by using

    GIS for the incomer yard, 33kV network and the

    25 kV traction network. In one of the substationseven 25 kV AIS is being designed to make it

    indoor below the control room from the cost

    economics point of view . Study is under progress

    to consider Hybrid Substation also where space is

    a constraint.

    http://www.delhimetrorail.com/Default.aspx

  • 8/18/2019 First Below Ground Traction at Church Road Anook K Gupta

    49/49

    49

    49

    Thank You !!

    DMRC Ltd.Metro Bhawan,

    Fire Brigade Lane,

    Barakhamba Road,

    New Delhi - 110 003.

    http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx