first below ground traction at church road anook k gupta
TRANSCRIPT
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
1/49
First Below Groundirst Below Groundirst Below Groundirst Below Ground
Tractionractionractionraction Substation at Church Roadubstation at Church Roadubstation at Church Roadubstation at Church Road
New Delhi) Receiving SubstationNew Delhi) Receiving SubstationNew Delhi) Receiving SubstationNew Delhi) Receiving Substation
A case Studycase Studycase Studycase Study
By:
Anoop Kumar Gupta, Director (Electrical)
Mahendra Kumar, Chief General Manager
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
2/49
This presentation covers -
About DMRC
Progress/achievements so far Status of Phase III
Operational Highlights
Power Supply Arrangement in DMRC
Power Supply requirement
Power System Architecture
Contract Demand and Energy Consumption
Construction of below ground Substation Challenges faced
Layout Plan
Glimpses of the site
2
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
3/49
About DMRCAbout DMRC
3
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
4/49
4
4
DELHI METRO RAIL CORPORATION (DMRC)
• Set up in May’95 under the Indian Company Act.
• A joint venture between the GOI and the GNCT Delhi,
with equal equity.
• DMRC has the responsibility for construction andoperation of Delhi Metro.
• A Master Plan had been drawn up for Delhi Metro
expansion, consisting of 12 lines, covering 420 kms to
be completed by 2021 in four Phases.
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
5/49
5
5
DMRC – PROGRESS/ ACHIEVEMENTS SO FAR
• Phase-I – 65 kms Completed in 7 years and 3 months(2 years & 9 months ahead of schedule).
• Phase-II – 125 kms -- Though double the length,
completed in half the period taken for Phase-I, and fivemonths ahead of schedule.
• Phase III - 136 km Sanctioned in Sept 11 and has been
committed to the Govt. for completion in 4.5 years.
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
6/49
6
Phase IIIPhase III
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
7/49
STATUS OF PHASE-III
• Further expansion by 136 kms. 110 km (50 km U/G) inDelhi & 26 km in Haryana (14 km) Line-6 Badarpur to
YMCA Chowk, Faridabad & (12 km) Mundka to
Bahadurgarh.
• The contracts are in place and the work is in progress.
• For the first section Trial run was flagged off in
December 2013 for the CTST- Mandi house corridor
of phase III
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
8/49
STATUS OF PHASE-III
8
• Phase-III likely to be completed by 2016
• On completion of Phase-III Delhi will have a
metro network covering 326 kms.
• Delhi is the fastest growing metro network
in the world outside China.
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
9/49
Operational HighlightsOperational Highlights
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
10/49
10
10
• DMRC is having 142 Stations and 190 Km in operation. This is
including high speed Airport Express line having 6 stationsand 23 km section.
• About 2800 train trips a day – with 208 train sets (1100
Coaches) on 6 lines.
• Each train used to consist of 4 coaches. With the increase in
commuters, the trains are progressively being lengthened to
6 coaches and finally to 8 coaches. We have already near
about 100 six car sets.
• Average Ridership – more than 2.3 million passengers per
day. (meaning about 1,00,000 vehicles off the road)
OPERATION HIGHLIGHTS
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
11/49
11
OPERATION HIGHLIGHTS
Frequency during peak hours – 2 m 40 sec on 2 out of 6 lines
(on other lines 3 to 5 mts).
DMRC has around 7,000 employees, besides contract staff.
Op. Ratio 62%
Fare : From 8/- to 30/-. The system is making an
operational profit from Day-1.
DMRC is able to service and pay back the loans despite nosubsidy from the Government and the Fare Structure being
lowest in the world except Kolkata.
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
12/49
12
12
•
20% of DMRC’s revenue is from Non-operational sources –mainly real estate development and advertisements.
• The system is fully Barrier Free for Physically challenged.
• The trains operate from 6 AM to 11 PM.
• DMRC has introduced feeder bus short loop services to help
the commuters.
• Punctuality measured with a least count of 60 sec and the
punctuality percentage has been above 99%.
OPERATION HIGHLIGHTS
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
13/49
DWARKA
L A X M I N A G A R
Y A M U N A B A N K
N I R M A N V I H A R
P R E E T V I H A R
K A R K A R D U M A
BOTANICAL GARDEN
GOLF COURSE
NOIDA CITY CENTRE
DHAULA KUAN
DELHI AEROCITY
DWARKA SEC 21
A S H R A M
S R I N I V A S P U R I
`
KALINDI KUNJ
PALAM
DHSRATH PURI
DABRI MOR
BOTANICAL GARDEN
DELHI GATE
JAMA MASJID
LAL QUILA
•PHASE –I = 65.1Km
•PHASE –II = 125.0 Km
•
Phase –
III = 136.0 KmTotal = 326.0 Km
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
14/49
Power Supply ArrangementsPower Supply Arrangements
in DMRCin DMRC
14
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
15/49
• Electricity is required for:
Running of trains,
Station services
• Power requirements are determined by peak-hour demands
of power for traction and auxiliary applications.
• Broad estimation of auxiliary and traction power demand is
made based on :
Regeneration by rolling stock – Up to 35%
Elevated station load – about 500 KW
underground station is assessed at about 3.2 MW
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
16/49
• From the reliability point of view Power supply at 220 kV, 132
kV or 66 kV level is taken from the Grid Sub Stations of
DTL/UPPCL/HVPN.
• At the RSS it is stepped down to 25 kV to feed the OHE with
single phase traction transformers and 33 kV with 3 phase
auxiliary transformers to feed the auxiliary requirements. Bothare with 100% standby capacity.
• 33 kV is distributed through duplicate ring feeders along the
corridor and at every station it is stepped down to 400 volts(3 phase supply) through dry type transformers. This
substation is termed as Auxiliary Substation (ASS) in our
system. This is distributed in the station to meet the power
supply requirements of the stations.
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
17/49
POWER SYSTEM ARCHITECTURE
• DMRC is taking power supply through two incomers
through underground cables.
• In case of failure in one incoming circuit the other
cable will be able to take full load.
• Power failure from one RSS , adjacent RSS can takefull load
• Failure of one transformer, the standby can take the
full load.
Thus adequate redundancy has been built in at all stages
from the reliability point of view
17
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
18/49
POWER SUPPLY IN DMRC
Incoming power supply from Grid 220/132/66000KV
Transformers
25000
volts
33000
volts
25000
volts
33000
volts
To DMRC line
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
19/49
CONTRACT DEMAND & ENERGY CONSUMPTION SINCE 2006-07
S. No. AS ONCONTRACT DEMAND
in MVA% increase
1 31.03.2007 47
2 31.03.2008 52 10.6 %
3 31.03.2009 52 10.6%
4 31.03.2010 75.5 58.5%
5 31.03.2011 115 144.6%
6 31.03.2012 130 176.5%
7 31.03.2013 138 193.6%
8 AS ON 01.08.2013 141 200%
CONTRACT DEMAND
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
20/49
ENERGY CONSUMPTION
S.No Financial Year MU % increase
AMOUNT PAID
in million
1 2006-2007 189.52 480.60
2 2007-2008 199.61 10.5 514.80
3 2008-2009 220.14 16.15 707.20
4 2009-2010 254.49 34.33 832.29
5 2010-2011 422.73 123.05 1390.05
6 2011-2012 577.56 204.7 2139.24
7 2012-2013 596.69 214.84 3198.61
8 2013-14
upto Oct-13410.33 271.17 2554.09
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
21/49
Rss in phase-1
LINE RSSIncoming
Voltage
LINE-1 KASHMERE GATE 220 kV
LINE-1 RITHALA 66 kV
LINE-2 NEW DELHI 66 kV
LINE-3 DWARKA 66 kV
LINE-3 SUBHASH NAGAR 66 kV
LINE-3 INDRAPRASTHA 66 kV
TOTAL 6 SUBSTATIONS
RSS IN PHASE I
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
22/49
LINE RSS Incoming Voltage
LINE-2 • JAHANGIRPURI,
• CHHATARPUR
• SUSHANT LOK (HCC)
• 66 kV
• 66 kV
• 66 kV
LINE-3 • BOTANICAL GARDEN • 132 kV
LINE-5 • MUNDKA • 66kV
LINE-6 • SARITA VIHAR
• PARK STREET (CTST)
• 66 kV
• 66 kV
AIRPORT LINE • PARK STREET (CTST)• AIRPORT
• 66 kV• 66 kV
TOTAL 8 SUBSTATIONS
RSS IN PHASE II
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
23/49
NEW Rss in phase-3
LINE RSSIncoming
VoltageSTATUS
LINE-5 • MIE DEPOT RSS • 132 kV • Contract opening on 10.12.13
LINE-6 • KASHMERE
GATE
• FARIDABAD
• 220 kV
• 66 kV
• Power from existing Cables of
Phase I RSS of DMRC
• Work in process
LINE -7 • MUKUNDPUR
• DHAULA KUAN
• INA
• VINOD NAGAR
• YAMUNA VIHAR
• 66 kV
• 66 kV
• 66 kV
• 66 kV
• 66 kV
• Gopalpur DTL by 2016-17contingency from JP RSS
• One from Ridge valley + One
Park street
• From RK Puram RSS of DMRC
for One Circuit
• Two Circuits from Gazipur
• Power not available at Harsh
Vihar DTL
STATUS OF RSS IN PHASE III
To be contd ….
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
24/49
LINE RSSIncoming
VoltageSTATUS
LINE -8 • KALKAJI
• RKPURAM
• PALAM
• 66 kV
• 66 kV
• 66 kV
• One from Sarita Vihar DTL and2nd LILO of Existing
• One Ckt from Vasant Kunj and
second incomer being taken to
INA RSS
• No Ckt from Papankalan 3-
• Existing Subhas nagar to be
made LILO and 2nd ckt when
PPN 3 comes up
TOTAL 11 SUBSTATIONS
Contd ….
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
25/49
AUGMENTATION WORKS of RSS IN PHASE - III
LINE RSS
LINE-2 • JAHANGIRPURI
(One Trafo of 131 MVA -220/66 kV)
LINE-3 • BOTANICAL GARDEN
(2 nos 25 kV bays added)
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
26/49
Construction of belowConstruction of belowGround SubstationGround Substation
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
27/49
Construction of the Sub-Station at Church Road
• Line-6 and Airport Express Line in phase II were to be
fed from this RSS• The incoming supply was to come from Park Street
S/s of DTL 1.6 kms away
• Plot size of 5000 sqmts
• Tender was awarded for a normal RSS and materials
procured
• Being close to Rastrapati Bhawan it required
clearance from Central vista Committee• CVC desired that no part of the substation should be
above ground, except boundary wallTo be contd …
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
28/49
• The building housing GIS Hall and Control room shall
be 0.3 m high only from the road level.• The top of the roof may be landscaped to present a
green appearance and the height of solid portion of
boundary wall should be 1m high only
• Baffle wall only 1.2 m high from road level
• The layout was redesigned with incoming 66 kV cable
gallery at -9 m, GIS hall at -7 m level and transformer
yard at -6m level.
Contd …
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
29/49
LAYOUT PLAN
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
30/49
ELEVATION
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
31/49
ELEVATION
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
32/49
Challenges facedChallenges faced
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
33/49
Challenges faced
• Maintaining the clearances both in the vertical as well as
horizontal direction in the transformer bay was required.
• Ventilation for the underground substation- Forced
ventilation system for the equipment rooms was adopted -
Three AHU’s (2 Main + 1 Standby) have been provided
considering 15 Air changes per hour.
• Water drainage system for this catchment area. The cables
trenches were designed with hangers at a height of 300 mm
from the bottom on which the cables were laid and thebottom portion was used for draining the water to the water
tank with natural gravity towards the water collection tank.
To be contd …
C td
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
34/49
• Smoke detectors have been provided in the cable trenches in
the - 9 m area and the yard.
• Precision type Floor mounted Air-conditioning system has
been provided for the cooling of Control & Relay room and
the server rooms with the arrangement of two main and one
standby AC units
• Water pumping arrangement has been made such that the
system can pump out 1 lakh liters of water in one hour
keeping in account the catchment area. Automation has
been provided with three pumps. The first pump operates at
25%, second pump at 50% and the third pump at 85% of the
water being filled up in the water tank.
Contd …
To be contd …
C td
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
35/49
• The soil resistivity of the substation indicated that soil is
having three layers with upper layer having low resistivity,
middle layer having high resistivity and bottom layer again lowresistivity.
• Upper strata is having low soil resistivity of 73 ohm-m, Middle
strata is having very high soil resistivity of 783 ohm-m andLower strata is again low resistivity of 63.2 ohm-m.
• For better performance of grounding system, grid is placed in
low resistivity soil and analysis has been done using Auto Grid
Pro software package. Satellite earthing had to be adopted
since mother earth was not available for the electrodes
Contd …
To be contd …
C td
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
36/49
• A DG set of capacity 125 kVA has been provided at a higher
platform to meet out the emergency power requirement in
case of power supply failure to run the ancillary system of thesubstation.
• Substation Automation based on Intelligent Electronic Device
on IEC 61850 has been provided for control and protection of the system.
• This substation is first of its kind with unique layout below
ground level.
• Each bay comprises of one circuit breaker and associated
disconnectors, earth switches and instrument transformers.
Contd …
To be contd …
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
37/49
37
• At bay level, the IEDs provide all bay level functions likecontrol (commands outputs), monitoring (status indications,measured values).
• The IEDs are directly connected to the switchgear avoidingthe need for additional interposing of transducers.
• Each bay control IED is independent of the others and itsfunctioning is not affected by any fault occurring in any of theother bay control units of the substation.
• The data exchange among bay level IED’s, and between baylevel and substation level take place via dual fiber-optic interbay bus according to IEC 61850-8-1 protocol. 37
Contd …
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
38/49
Station Level
• Human Machine Interface enables local station control and
monitoring through the vendor software package compatiblewith IEC 61850.
• DMRC Substation bays are limited the bay bus arrangementprovides independent station-to-bay and bay-to-bay data
exchange.
• Substation Configuration Language (SCL) facilitatesintegration of the system by the users/operators and can beused without detailed knowledge of real-time systems.
• An authorization mechanism has been provided to preventsystem access to unauthorized users
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
39/49
OCC Level
• IEC 61850 signals are converted to IEC 60870-
5-101 signals through a software based
gateway for communication from the substationto the OCC.
39
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
40/49
40
Glimpses of the SiteGlimpses of the Site
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
41/49
Before execution of the Below ground
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
42/49
View of the Rashtrapati Bhawan
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
43/49
CLEARANCES PLACEMENT OF THE DG SET
GIS H ll With V til ti A t
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
44/49
GIS Hall With Ventilation Arrangement
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
45/49
Views of landscape of the RSS
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
46/49
Full View of the RSS
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
47/49
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
48/49
CONCLUSION
Space has been a constraint for all the urban
cities. Now attempt is being made to
accommodate the RSS in a smaller space by using
GIS for the incomer yard, 33kV network and the
25 kV traction network. In one of the substationseven 25 kV AIS is being designed to make it
indoor below the control room from the cost
economics point of view . Study is under progress
to consider Hybrid Substation also where space is
a constraint.
http://www.delhimetrorail.com/Default.aspx
-
8/18/2019 First Below Ground Traction at Church Road Anook K Gupta
49/49
49
49
Thank You !!
DMRC Ltd.Metro Bhawan,
Fire Brigade Lane,
Barakhamba Road,
New Delhi - 110 003.
http://www.delhimetrorail.com/Default.aspxhttp://www.delhimetrorail.com/Default.aspx