“financing transport infrastructure” - unece homepage · pdf file“financing...

38
“Financing Transport Infrastructure” 10 th September 2013 - Geneva Esmaeil Tekyeh sadat Director Transport and Communication ECO 9/23/2013 1

Upload: vuphuc

Post on 15-Mar-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

“Financing Transport Infrastructure”

10th September 2013 - Geneva

Esmaeil Tekyeh sadat

Director Transport and Communication

ECO

9/23/2013 1

Page 2: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

future of railway freight depend on

• travel time, costs,

• legal system,

• cargo types and,

• environmental considerations.

9/23/2013 2

Page 3: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

ECO Railway potential in East-West Asia

• The ECO rail network by connecting Europe to China, India and central Asia has the potential to offer a promising alternative to the sea-air option, if it can lower prices and offer a reliable and efficient service.

9/23/2013 3

Page 4: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Rail Network Privilege

• Rail’s primary advantage is its transport time. Railway transport from terminal to terminal is roughly twice as fast shipping by ocean –going vessel.

9/23/2013 4

Page 5: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Outstanding Issues

• Obsolete rolling stock and shortage of rail cars, containers and locomotives;

• Non-compliance of existing infrastructure and technology with international quality standards;

• Inefficient processing capacity at border crossing points;

• Poorly developed logistic and communications networks and road services facilities;

• Insufficient capacity for cargo handling and, • Different rail gauges

9/23/2013 5

Page 6: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Rail transport on Euro-Asian routes governments/ operators

• Governments and investors need to modernize transport infrastructure and harmonies the legal environment.

• Operators have to improve their delivery time and service quality,

9/23/2013 6

Page 7: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

“ECO Railway Network Development Plan” The “ECO Railway Network Development Plan” has been prepared by the Consultant (Professor Dimitrios Tsamboulas-Consultant),.

1. Identifying the main rail transport corridors in the ECO Member States . 2. Identifying the priority rail transport infrastructure projects along the proposed ECO priority rail routes. 3. Develop an ECO Railway Network Investment Plan of priority on-going and/or planned rail transport infrastructure projects along the proposed ECO priority rail routes.

9/23/2013 7

Page 8: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Two key tasks of the study

• Identification of the main rail transport corridors in the ECO region

• Identification of the priority transport infrastructure projects along the proposed routes,

9/23/2013 8

Page 9: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

I-- ECO Rail Routes

The key rail links and rail border crossings in the ECO territory, based on the following guidelines:

• Proposed links/routes should be of international importance for transport between the ECO countries

• Proposed links/routes should connect to the proposed ECO routes

9/23/2013 9

Page 10: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

. ECO Rail Route 1

• starts at the eastern borders of Turkey with Bulgaria and Greece,

crosses Turkey through Istanbul, Ankara, as well as through the Lake Van by rail-ferry. It continues through the border crossing of Kapikoy onto Iran, crossing the Iranian territory through Aprin (near Tehran) and ending up at the border crossing with Pakistan (Mirjaveh). Finally, it follows a north-eastern direction through the Pakistani territory ending up in Islamabad.

• The route serves the connection of the ECO Member States Turkey, Iran, and Pakistan with possible extensions towards India, Iraq and China. It is also connected to key maritime ports in the ECO region, in Turkey, Iran and Pakistan

• A missing link is considered as an additional extension to the route, that is, the Rawalpindi-Havelian towards the border with China onto Khanjurab.

9/23/2013 10

Page 11: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

9/23/2013 11

Page 12: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

ECO Rail Route 2A

• Route 2A is similar to Rail Route 1 up to the city of Aprin (near Tehran, Iran), following then a north eastern direction through Turkmenistan (Mary), Uzbekistan (Navoi, Tashkent) and ending up at the borders of Kazakhstan with China, after having passed the city of Almaty.

• The route serves the connection of the ECO Member States Turkey, Iran, Turkmenistan, Uzbekistan and Kazakhstan. It is also connected to maritime ports in the ECO region, in Turkey and Iran.

9/23/2013 12

Page 13: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

9/23/2013 13

Page 14: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

ECO Rail Route 2B

• This route is similar to Rail Route 2A up to the city of Neyshabur in Iran, continuing on an eastern direction onto Afghanistan through Herat. Then it follows on the missing link Heart-Mazar e Sharif- Nijniy Pyanj (border with Tajikistan), followed by the missing link Nijniy Pyanj -Kurgan Tube in Tajikistan. Finally, the route ends with the missing link Karamyk-Irkhestam through Kyrgyzstan towards China.

• The route serves the connection of the ECO Member States Turkey, Iran, Afghanistan, Tajikistan and Kyrgyzstan. It is also connected with maritime ports in the ECO region, in Turkey and Iran.

9/23/2013 14

Page 15: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

9/23/2013 15

Page 16: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

ECO Rail Route 3

• Route 3 constitutes the “left side route” of the Caspian Sea. It follows a southern direction, originating at the border crossing of Afghanistan with the Russian Federation, crossing on a southern direction the two ECO Member States, Azerbaijan and Iran, ending up at the Bandar e Abbas port in Iran. In this particular route, a key link is under construction, this of Astara, which involves a bridge connecting the railway of the two countries.

• The route serves the connection of the ECO Member States Afghanistan, Azerbaijan and Iran. It is also connected with key maritime ports in the ECO region, in Turkey and Iran.

9/23/2013 16

Page 17: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

9/23/2013 17

Page 18: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

ECO Rail Route 4

• constitutes the “right side route” of the Caspian Sea. It starts in Kazakhstan at the border crossing with the Russian Federation (Zhaisan), continuing on a south-western direction to Aktau, continuing then south onto Turkmenistan (Bereket), to the border with Iran, crossing the Iranian territory through Neyshabur and ending up in Bandar e Abbas port. There is a major link under construction at the borders of Turkmenistan with Kazakhstan. This route constitutes the main alternative to the North-South corridor that currently connects the Russian Federation with the port of Bandar Abbas in Iran.

• The route serves the connection of the ECO Member Kazakhstan, Turkmenistan and Iran.

9/23/2013 18

Page 19: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

9/23/2013 19

Page 20: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

ECO Rail Route 5

• Route 5 Originates in the borders with the Russian Federation (Mamlyutka or Bulaevo), crossing Kazakhstan on a southern direction through Shymkent, crossing onto Uzbekistan through Tashkent and Bukhara to the border with Turkmenistan. It then continues on a south-western direction through Turkmenistan, crossing over to Iran and ending up at the Bandar e Abbas port.

• The route serves the connection of the ECO Member Kazakhstan, Uzbekistan, Turkmenistan and Iran, with extensions towards China and the Russian Federation. It is also connected with key maritime ports in Iran.

9/23/2013 20

Page 21: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

9/23/2013 21

Page 22: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

II--ECO rail transportation infrastructure projects

• a database, listing the rail infrastructure

projects per country, together with key information regarding their location with regard to the identified routes, current status, start and end dates, cost and sources of financing, etc.

9/23/2013 22

Page 23: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

key information database listed on the basis of 4 Categories

• Category I: projects, which have funding partially secured and are on-going and expected to be completed in the near future (up to 2013).

• Category II: projects, which may be funded or their plans are approved and are expected to be implemented rapidly (up to 2016).

• Category III: projects requiring some additional investigation for final definition before likely financing and implemented (up to 2020).

• Category IV: projects requiring further investigation for final definition and scheduling before possible financing, including projects, for which insufficient data existed. (most likely to be implemented after 2020)

9/23/2013 23

Page 24: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

key information (Iran/Afganistan)

9/23/2013 24

Page 25: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

key information(Kazakhistan)

Iran Chabahar-Zahedan Railway 1-B-E 2014 3951 I

Kazakhstan Electrification section of the

Makat-Kandyagash 4 240 IV

Kazakhstan Electrification section of the

Dostyk - Aktogai 2A 2009 2012 546 I

Kazakhstan Electrification section of the

Almaty - Aktogai 2A 2009 2013 1054.4 I

Kazakhstan

Construction of second tracks at

sunset stretches on sections

Iletsk – Zhaisan and Kyzylorda –

Shieli

5

IV

Kazakhstan Increasing transport capacity of

the railway line Shu-Almaty 2A 2012 I

Kazakhstan

Construction of a new railway

Uzen- border of Turkmenistan -

This project aims at the creation

of additional transit routes

directly connecting Kazakhstan

and central regions of Russia,

Turkmenistan, Iran, Persian Gulf

countries, South and South-East

Asia

4 2009 2011 442 I

9/23/2013 25

Page 26: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

key information (Turkey) Turkey Ankara – Istanbul High Speed Train Project 1,2A,2B 2003 2013 3713.9 I

Turkey Marmaray Project - It covers the railway line between Halkali – Sirkeci (Istanbul) – Tube Tunnel under Istanbul Strait - Haydarpasa

(Istanbul) – Gebze 1,2A,2B 2004 2013 5037.5 I

Turkey

Bogazkopru – Ulukisla, Ulukisla-Yenice, Mersin – Adana – Toprakkale Signaling, Telecommunication and Station Extension Project - The

existing railway line will be rehabilitated with station loop extensions, new signaling and telecommunication systems will be installed

during the years of 2008 – 2012.

1,2A,2B,6 2008 2012 179.4

II

Turkey Electrification Project - new electrification system will be installed along the route during the years of 2011 – 2015. 1-B-B, 2A-B-B, 2B-B-B 2011 2015 89.6

Turkey

Ankara-Sivas High Speed Train Project - new double track high seed line with signalling, electrification and communication systems will

be constructed, 461 km in length, along with constituting the East-West axis in the high speed train line and shortening of the current

traveling time from 12 hours to 3 hours.

1,2A,2B 2007 2014 1451.3 II

Turkey

Eskisehir - Kutahya - Balikesir Signalling & Telecommunication Project will be realized during the years of 2011 – 2015.

1-B-C, 2A-B-C, 2B-B-C

2011 2015

237 III

Electrification project will be installed along the route during the years of 2012 – 2016. 2012 2016

Turkey

Initially Technical Assistance Project will be realized to facilitate the modernisation of the existing railway infrastructure between

Samsun and Kalin

1-B-A, 2A-B-A, 2B-B-A

2012 2013

179 III

Samsun - Kalin Modernization Project - Initially Technical Assistance Project will be realized to facilitate the modernisation of the

existing railway infrastructure between Samsun and Kalin 2013 2016

Turkey

Lake Van New Ferry Procurement (Northern Pass Project) - The overall objective of the project to improve the infrastructure and the

modal split in favour of railway sector, while increasing safety level and reducing travel time, by procurement of new ferries and

upgrading existing piers.

1,2A,2B 2006 2011 79.6 I

Turkey Kayas – Cetinkaya Electrification Project 1,2A,2B 2011 2015 116 II

Turkey Pehlivankoy - Uzunkopru –Border with Greece Modernization Project. the whole line section consisting of 30 km single track will be

signalled and its infrastructure will be upgraded for higher operational speed and higher line capacity. 1,2A,2B 2010 2012 17 I

9/23/2013 26

Page 27: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

key information (Kyrgyzsatn)

Kyrgyzstan

China-Kyrgyk-Uzbek trunk railway

project - Project's main idea is a

creation of south corridor of Eurasian

transcontinental trunk railway, which is

to connect pacific ports with Persian

Gulf and Mediterranean getting

through the territory of Kyrgyzstan.

5-E-B 2012 2018 2000 II

9/23/2013 27

Page 28: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

key information (Pakistan)

Pakistan

Up-gradation of Quetta-Kohi Taftan section which will be an important part of the

international route starting from China to Europe as conceived under Trans Asian

South Corridor.

1

625 III

Pakistan

New rail link for connecting Gwadar Port with existing Railway network at

Mastung. The rail link is considered absolutely essential for the optimum

operationof the port to transport the goods from the port to up country and

neighboring stated i.e. Afghanistan, Iran, and Central Asian Republics.

1-B-I

1987 III

Pakistan

New rail link from Havelian (Pakistan) to Khanjurab (Pak-China Border). It would

provide a direct link between Pakistan and China, which mutual trade is bound to

grow manifold in the future. The project would provide an opportunity to create

a new international corridor to link China, Central Asian States and Russia.

1-E-F

9589.6 II

Pakistan

New rail link between Peshawar and Jalalabad. It will boost up trade and

strengthen socio cultural relations between Pakistan and Afghanistan. It will

provide new opportunities to exlpore the vast market of Central Asia and even

Russia.

1-B-F

II

Pakistan

New rail link between Chaman (Pakistan) to Kandhar (Afghanistan). It will provide

access to Pakistani sea ports and as such, this route would be one of the busiest

and important links between the two neighboring countries.

1-B-H

148 II

Pakistan Provision of 3rd and 4th freight lines between Karachi-Kotri. 1-B-G

184.5 III

Pakistan Provision of alternative route to link Sibi with Spezand bypassing Bolan pass. 1

296.5 II

9/23/2013 28

Page 29: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

key information (Tajikistan)

Tajikistan

Construction of new railway line

Ayvaj(Tajikistan) – Taganguzar –

Khulm – (Afganistan). It will allow the

transportation of goods and

passengers within Tajikistan territory

from Russia, Kazakhstan and other

interested CIS countries, as well China

through Afghanistan to Iran, India,

Pakistan, Turkey and others.

2B

30.4 II

Tajikistan

Construction of Kolkhozabad-Nijniy

Pyanj-Kunduz (Afghan border). It aims

to create new transportation

opportunity for the country and allow

other countries to reach Afghanistan

using transit potential of Tajikistan.

2B

90 II

Tajikistan

Construction of Vahdat – Karamyk

railway. It will create a new railway

network connecting China with Iran

through the territory of Kyrgyzstan-

Tajikistan and Afghanistan

2B

3000 II

9/23/2013 29

Page 30: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Follow up actions on effectiveness of ECO Rail Routes and Projects

•The Council requested IDB to continue its assistance to ECO projects envisaged in the ECORNDP for conducting technical and financial pre-feasibility or feasibility studies. The Council asked the CPR to replenish the TTFA Fund to assist in financing feasibility studies and other activities related to effective implementation and monitoring of the ECORNDP. •The Council called on all relevant national, regional and international organizations and funding institutions, including IDB, ADB, ECO-TDB and WB to actively participate in financing and implementing the projects envisaged in the ECORNDP. •The Council instructed the Secretariat to organize donor conferences and inter-agency meetings in the context of the trilateral MoUs among ECO-IDB/UNEESCAP and ECO/IDB-UNECE to accelerate the preparation of the action plans and smooth financing of the projects. •The Council asked the ECO-TDB to set up a regional partnership forum to boost partnership with the development and financial agencies, and national and regional stakeholders for implementation of the ECORNDP.

9/23/2013 30

Page 31: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Follow up actions on harmonization the Rail legal environment in ECO

region

• Joint workshop with UNECE on Annex 9 of Harmonization Convention

• Joint workshop with UNECE on Unified Rail Law

• Action Plan signed between the ECO and the UIC

9/23/2013 31

Page 32: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Joint workshop with UNECE on Annex 9 of Harmonization Convention

• the ECO Secretariat will planning a joint

workshop with UNECE to encourage all member states to join Harmonization Convention and to promote implementation of the Annex 9 of the harmonization convention with the main objective the decrease of travelling time along ECO rail corridors

9/23/2013 32

Page 33: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Joint workshop with UNECE on Unified Rail Law

• ECO organized a joint workshop with UNECE

on June 2013 for promoting implementation of the common CIM/SMGS consignment note and the principles of the unified railway law with the main objective the decrease of travelling times and of the operational costs

9/23/2013 33

Page 34: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Action Plan signed between the ECO and the UIC

• ECO plans to take concrete measures for

implementing the activities envisaged in the Action Plan signed between the ECO and the UIC in June 2012

9/23/2013 34

Page 35: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

ECO Road/Transit Facilitation Projects

9/23/2013

35

• Islamabad- Tehran- Istanbul Corridor (ITI) • Kyrgyzstan, Tajikistan, Afghanistan , Iran

Corridor (KTAI)

Page 36: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

9/23/2013 36 9/23/2013 36

ECO-IRU cooperation Action plan

• OBJECTIVES:

strengthen joint ECO/IRU inter-Onizational cooperation

Promote the TIR system

Support implementation of TTFA

Cooperate to ensure IDB technical assistance to ECO

Promote road transport

Improve road safety

Fight against narcotics

Page 36 (c) International Road Transport Union (IRU) 2011

Page 37: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

9/23/2013 37 9/23/2013 37

• (iii) Upon instruction of ECO Heads of State in December 2010, they agreed to implement ECO Regular Monitoring of Trucks in partnership with NELTI-3 (ECO RMT), where 29 companies in 8 ECO Member States regularly provide data, now.

(iv) IRU supports to create a regional ECO License similar in nature with the ECMT.

(v) IRU supports to develop Islamabad-Tehran-Istanbul Corridor (ITIC) as proposed by some Member States and approved within the ECO. IRU proposed a draft framework and action plan and remain ready for necessary more support.

Page 37 (c) International Road Transport Union (IRU) 2011

ECO/IRU cooperation

Joint achievements

Page 38: “Financing Transport Infrastructure” - UNECE Homepage · PDF file“Financing Transport Infrastructure” 10th September 2013 - Geneva Esmaeil Tekyeh sadat ... 1,2A,2B 2007 2014

Thanks Esmaeil Tekyeh Sadat

Director of Transport & Communication PhD (Organization Development)

Web: www.ECOsecretariat.org Email: [email protected]

1 Golbou Alley, Kamranieh, Tehran, IR.Iran Telefax:(+9821) 2613 1409 Tel: (+9821) 2283 1733-4 Fax: (+9821) 2283 1732

9/23/2013 38