final stsm londonucl report

Upload: juangray

Post on 07-Jul-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Final STSM LondonUCL Report

    1/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    !"#$% '($) !*+(,%+-+* .+//+#, 0123 2#,4#,

    !"#$%&$'())(%" 5(6#$%

    "#$%&'()$*

    *=/? ,=05. *35@ ,-/31./A/- !/??/01 B,*,!C D

  • 8/18/2019 Final STSM LondonUCL Report

    2/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    .:$+/: .+9;:,

    !01:.=

     

    !3F

  • 8/18/2019 Final STSM LondonUCL Report

    3/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    -./0 !1 2345. 6.747 02 345.-/2846097 043-:.047

    *=3 .

  • 8/18/2019 Final STSM LondonUCL Report

    4/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    >=  *=3 '53?E1: 8/1X !"#$%&'(%)#*'+, .' /$'01#2 ; ,D3:31 B!"#$%&'($%2!"#$%CQ

    ,3-01:HJ9 .=3 /1.351

  • 8/18/2019 Final STSM LondonUCL Report

    5/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    M/1

  • 8/18/2019 Final STSM LondonUCL Report

    6/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    '1 V1.3513. D3 0N.

  • 8/18/2019 Final STSM LondonUCL Report

    7/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    H= 

    V(,(9E^9+;, B.(%$# 9+,(C8  V. ?33@? .0 N3 10 ,%" A05@3:Q *D0 4ENH/- ?3-.05 05F

  • 8/18/2019 Final STSM LondonUCL Report

    8/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    5(*#))(,4:%+#,/ :,4 -E%E$( R#$F8

    SE3 .0 .=3 /@405.

  • 8/18/2019 Final STSM LondonUCL Report

    9/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    SE5/1F .=3 A/5?. D33X 0A .=3 ,*,!9 .=3 :

  • 8/18/2019 Final STSM LondonUCL Report

    10/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    S)6#$%:,% *#,*9E/+#,/8

    • 

    SE5/1F .=3 450-3?? /. D

  • 8/18/2019 Final STSM LondonUCL Report

    11/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    Y+--+*E9%+(/ (^6($+(,*(4 4E$+,A %"( 6$#*(//8

    • 

    */@3 -01?E@/1F .0 F0 .=50EF= A/5?. 62L -

  • 8/18/2019 Final STSM LondonUCL Report

    12/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    -./0 ,1 345.-/28460 6.747 0D/2E5D 2345. :4772F7

    *=3

  • 8/18/2019 Final STSM LondonUCL Report

    13/97

  • 8/18/2019 Final STSM LondonUCL Report

    14/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    •  $H.=0EF= .=3 /1.31./01 D

  • 8/18/2019 Final STSM LondonUCL Report

    15/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    :@BBB >@=%#$

    *=3 @

  • 8/18/2019 Final STSM LondonUCL Report

    16/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    •  ,/F1/A/-

  • 8/18/2019 Final STSM LondonUCL Report

    17/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

     .##@N@B1

    M;!  *$=$*?@ 3@J=O%&P@)$ $@KO>=$@ L&% EQ 6R=##@> 0(##@> /=*> :*#H

    M;, 

    *$=$*?@ 3@J=O%&P@)$ $@KO>=$@ L&% 2%@B(#' :*#H

    M;C  7$=H@R&>'@% /@>=$*BR*O 3=OB

    M;G 

    2K#*SO%@B@#$ =)$&%B =#' 7-4B =#=>AB*B

    M;M  =$@ TU 2K@J= )=B@BV

    M;W 

    AB*B )&KK@#$B L&% EQ 6R=##@> 0(##@> /=*> :*#H =#'

    2%@B(#' :*#H

    M;X 

    "#*$*=> L%=K@I&%H '%=L$ L&% *'@#$*LA*#J $R@ @>@K@#$B &L #*#@ >@BBB *#

    K@J=O%&P@)$ )=B@B

  • 8/18/2019 Final STSM LondonUCL Report

    18/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    M;!  *$=$*?@ 3@J=O%&P@)$ $@KO>=$@ L&% EQ 6R=##@> 0(##@> /=*> :*#H

    D%=.8 ME() @(2=7,.) +,. %"/A &%, 7"#.,)=+"#("K %& E%I (= () @%))(V/. =% 2%G@/.=. =E. '.K+@,%0.2= =.G@/+=. I(=E

    9'!:; #+=+U ME. %,(K("+/ &(/.) +,. +==+2E.#U

  • 8/18/2019 Final STSM LondonUCL Report

    19/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    M;,  *$=$*?@ 3@J=O%&P@)$ $@KO>=$@ L&% 2%@B(#' :*#H

    D%=.8 ME() @(2=7,.) +,. %"/A &%, 7"#.,)=+"#("K %& E%I (= () @%))(V/. =% 2%G@/.=. =E. '.K+@,%0.2= =.G@/+=. I(=E

    9'!:; #+=+U ME. %,(K("+/ &(/.) +,. +==+2E.#U

  • 8/18/2019 Final STSM LondonUCL Report

    20/97

    !"#$%&'(")* )',* $-./01 2 ,*,! !"#$%&$'())(%" &3405. '+,()+ -.#,% +"# '(/0+" '(1(2

    67 8)9: 901;01 < !=5-> ?@

    !"#  $%&'()*+,(- /(+&%0*12)03 4&32

    !"  #$%&'() +,(-. /%(01$-234%)%(

    ,.=A3>0B;35 &3B=./01C>/4 !=4 0D '53CE1; 9/1A

    %50F3-.G

    5"  6787$419 :5;. 0B;35 &3B=./01C>/4 !=4 0D !0.05H=I $67

    %50F3-.G

    ="  >

  • 8/18/2019 Final STSM LondonUCL Report

    21/97

    MEGAPROJECT Case Study

    Basic Project Information

    Case compiled by: ...............................

    Contact details: ...............................

    Project Title  High Speed 1 (HS1) – Channel Tunnel Rail Link (CTRL)

    Location LONDON-KENT, UK

    Purpose Regional HSR in UK: increase rail capacity and reduce journey times between Londonand the Channel Tunnel. Link London with Paris and Brussels.

    Scope Integrated with Trans-European Transport Network (TEN-T)

    LENGTH: 113KMIN TUNNEL: 26KM

    Total Project Value 9.63bn (In 2010 USD)

    Project Status(i.e.. initiation, planning,

    construction, operation, dismantling)

    Planning start date: 1974Construction start date: 10/1998

    Operation start date: 11/2007

    Relevant Physical

    Dimensions (e.g. height, width,volume, length) 

    LENGTH: 113KM; IN TUNNEL: 26KM NUMBER OF BRIDGES: 152

    COST PER KM (2010 USD): 0.085BNThe Link was built in two sections – Section 1: Channel Tunnel to Fawkham Junction (constructed

    from October 1998 to September 2003) and Section 2: Southfleet Junction to St Pancras (constructedfrom July 2001 to November 2007).

    SECTION 1 - BASIC PROJECT INFORMATION

    !"#$%&' )*+,- .&/0$&1 2.3

    MEGAPROJECT Case Study

  • 8/18/2019 Final STSM LondonUCL Report

    22/97

    MEGAPROJECT Case Study

    Basic Project Information

    Case compiled by: ...............................

    Contact details: ...............................

    Contractual Framework

    (e.g. fixed price, cost-plus etc.)!"#$%#&' )*+ ,"-.%/ 0 12+ ,3%4567

    SECTION 1 - BASIC PROJECT INFORMATION

    MEGAPROJECT Internal Stakeholder Identification

  • 8/18/2019 Final STSM LondonUCL Report

    23/97

    Stakeholder

    Category 

    Case-Study  Comments

    (e.g. maturity, previous

    experiences of

    stakeholders, skills,influence on project)

    I    n t    er  n al    

    Supply-Side  Client  BRITISH RAIL (BR) & DEPARTMENT OF TRANSPORT

    Financiers  LCR (WITH GOVERNMENT BACKING)

    Sponsors  BRITISH RAIL (BR) & DEPARTMENT OF TRANSPORT

    Client’sCustomers 

    General public (passengers)

    Client’s Owners  UK Government

    Other internal

    supply-side

    categories

    ( please specify) 

    Category  Case-Study

    (Stakeholders with a direct legally sanctioned relationship with the project)

    SECTION 2 - PROJECT STAKEHOLDERS

    MEGAPROJECT Internal Stakeholder Identification

  • 8/18/2019 Final STSM LondonUCL Report

    24/97

    Stakeholder

    Category 

    Case-Study 

    I    n t    er  n al    

    Demand

    Side ) 

    Principal Contractor  CONCESSIONAIRE: LONDON & CONTINENTAL RAILWAYS (LCR) composed by Arup,

    Bechtel, Halcrow and SystraRAIL LINK ENGINEERING/LCR. Union Railways (URL) is formed to pursue the project.

    First Tier

    Contractors 

    RAIL LINK ENGINEERING (RLE) / LCR Project Manager

    General:

    Union Railways (URL). The LCR (acquiring ownership of Union Railways Ltd and European

    Passenger Services Ltd).

    Main contractors on section 1:

     Alfred McAlpine Construction, Co-contractor AMEC Civil Engineering

    Eurolink JV (Miller Civil Engineering, Dumez GTM, Beton-und Monlerbau), Co-contractor

    Beton- und Monierbau Gesellschaft.m.b.H. Morgan Est, Vinci Construction Grands Projects

    Hochtief/Norwest Holst JV, Co-contractor Hochtief (UK) Construction Ltd, Norwest Holst

    Construction. Kvaerner Construction Ltd, Skanska Construction UK Ltd. Balfour Beatty

    Construction

    Second Tier

    Consultants 

    Over 40 consultants were involved together with the Treasury, DOE and DTp.

    Professional

    Services Providers

    London Regeneration Consortium (the developers of the 135 acres of derelict railway lands at

    King's Cross). Foster Associates are the Masterplanners. Sir Alexander Gibb & Partners.

    Consulting service

    Other internalsupply-side

    categories 

    Category Case-StudyRailtrack is created to operate, maintain and develop the railway infrastructure of

    England (and Scotland and Wales). In 1998 LCR won its concession.

    (Stakeholders with a direct legally sanctioned relationship with the project)

    SECTION 2 - PROJECT STAKEHOLDERS

    MEGAPROJECT Internal Stakeholder Identification

  • 8/18/2019 Final STSM LondonUCL Report

    25/97

    689 7:;:?9:@AB 5CC9CC?9:@ />:CDB@A:@C

    I    n t    er  n al    

    (Stakeholders with a direct legally sanctioned relationship with the project)

    SECTION 2 - PROJECT STAKEHOLDERS

    MEGAPROJECT External Stakeholder Identification

  • 8/18/2019 Final STSM LondonUCL Report

    26/97

    Stakeholder

    Category 

    Case-Study  Comments 

    E x t    er  n al    

    Public  RegulatoryAgencies 

    Department of the Environment, Transport and the Regions (DETR)LOOK FOR SAFETY REGULATORY

    Local Government  Local authorities along the route, Newham Council (East London) in particular.

    National

    Government 

    UK Parliament

    Department for Transport (DfT) / Department of Transport (DoT)

    Other internal

    supply-side

    categories ( please

    specify) 

    Category  Case-study 

    Pressure Groups

    Forums & meetings (Chaired by the Minister of Transport, comprised

    representatives from all local authorities along the route)Land acquisition for Section 1 was carried out by Union Railways

    (South) as agent of the Secretary of State.

    Private Local residents  The Rail Link Countryside Initiative (RLCI)

    Local Landowners  RLCI

    Environmentalists  RLCI

    Conservationists 

    Archaeologists  

    Other ExternalPrivate

    stakeholders

    (please specify) 

    Category  Case-study Unsucessful Bidders, they promoted different roads

    The CTRL Complaints Commissioner, was established as a result of an

     Assurance given to Parliament during the passage of the CTRL Bill.

    King's Cross Railway Lands Community Development Group

    MEGAPROJECT External Stakeholder Identification

    SECTION 2 - PROJECT STAKEHOLDERS

    (Stakeholders with a direct interest in the project but with no legal contract)

    MEGAPROJECT Stakeholder Relationship Maps

  • 8/18/2019 Final STSM LondonUCL Report

    27/97

    E9F'

    G ,=>H9I@ 5I@>=

    G ,=>H9I@ =9BAJ>:C8:@=AI@DAB K=>H9I@

    =9BAJ>:C8N5I@>=

    $9CI=: >N=9BAJ>:C8N=9BAJ>:C8

  • 8/18/2019 Final STSM LondonUCL Report

    28/97

    E9F'

    G ,=>H9I@ 5I@>=

    G ,=>H9I@ =9BAJ>:C8:@=AI@DAB K=>H9I@

    =9BAJ>:C8N5I@>=

    $9CI=: >N=9BAJ>:C8N=9BAJ>:C8

  • 8/18/2019 Final STSM LondonUCL Report

    29/97

    SECTION 2 - PROJECT STAKEHOLDERS

    y

    ExternalStakeholder

    External Stakeholder’s Attitudeto this Project

    External Stakeholder’s Influenceon project

    Impact of Projecton ExternalStakeholder

    Phase of Project ofGreatest Interest

    (initiation, planning,

    construction,operation, dismantling) 

    Kent CountyCouncil

    Significantly influenced thesouthern route of the Link andinsisted on the inclusion of Ashford

    as one of the stations.In 1989, They refuse the routes

    contained in the BR report in 1988.

    Impact of fasterand more frequenttrains

    Initiation/Planning

    CamdenCouncil’s

    In 1988, it notes the need toimprove the transport interchange,

    provide housing, employment andrecreation for local people.

    Initiation/Planning

    National mediainterest, protestgroups formed,

    Local residents

    In 1988/89, public reaction waswholly adverse. Demonstrationsby S. London & Kent communities

    which culminated in a majordemonstration in Trafalgar

    Square.

    The east London route was

    extensively supported by lobbygroups such as the Stratford

    Promoter Group.

    82 petitions lodged in Parliamentagainst Private Bill authorisingconstruction of CTRL Terminal at

    King's Cross

    Initiation/Planning

    MEGAPROJECT External Stakeholder Attitude Analysis 

  • 8/18/2019 Final STSM LondonUCL Report

    30/97

    SECTION 2 - PROJECT STAKEHOLDERS

    ExternalStakeholder

    External Stakeholder’s Attitudeto this Project

    External Stakeholder’s Influenceon project

    Impact of Projecton ExternalStakeholder

    Phase of Project ofGreatest Interest

    (initiation, planning,

    construction,operation, dismantling) 

    LondonBorough ofNewham

    Became a serious opponent of theKing’s Cross Bill, and inNovember 1989 organized a

    conference as part of its efforts topromote an easterly approach with

    a station rather than a terminus atStratford – an idea supported byJohn Prescott, the Labour shadow

    Secretary of State for Transport.

    It lobbied successfully for aninternational station at Stratford aspart of a wider urban regeneration

    project.

    Initiation/Planning

    ECCommissioner

    Infringement Proceedings arebrought against the UnitedKingdom Government for the

    Environment in respect of theimplementation of EC Directive

    85/337/EEC on the EnvironmentalImpact Assessments of theChannel Tunnel Rail Link.

    Initiation/Planning

    EbbsfleetInternationalStation

    MEGAPROJECT Project Management 

  • 8/18/2019 Final STSM LondonUCL Report

    31/97

    Project Organisation

    Client Project Team Size &Structure 

    Contractor Project Team Sizeand Structure

    Sub-Contractor Project TeamInvolvement

    Project Tools and TechniquesPlease ! if present, x if absent , leave blank if unknown

    Life-Cycle Costing Approaches" 

    Stakeholder Involvement" 

    Building Information Modelling (BIM)" 

    Project Management Software" 

    Relationship Management Tools" 

    Project Knowledge Management Tools" 

    Lessons Learnt Transfers" 

    Team Building Tools" 

    Competency framework" 

    +/45$"/6&/078 *7/79&6&/0 !:;0&6

  • 8/18/2019 Final STSM LondonUCL Report

    32/97

    HR Management Processes Present (describe below ) !Not Present !  No Information! 

    Procurement Management Processes Present (describe below ) !Not Present !  No Information! 

    Integration Management Processes Present (describe below ) !Not Present !  No Information! 

    Scope Management Processes Present (describe below ) !Not Present !  No Information! 

    Time Management Processes Present (describe below ) !Not Present !  No Information! 

    Cost Management Processes Present (describe below ) !Not Present !  No Information! 

    Quality management Processes Present (describe below ) !Not Present !  No Information! 

    Communications Management

    Processes

    Present (describe below ) !Not Present !  No Information! 

    SECTION 3 - PROJECT MANAGEMENT

    !

    MEGAPROJECT Project Performance 

  • 8/18/2019 Final STSM LondonUCL Report

    33/97

    Aspects of Performance Concerned with Doing the Project Right

    Original Targets and changes to targets Actual Achievements Against

    TargetsPerformance relating to

    timeConstruction start:

    Section 1 – Forecast: 1998, Actual: 1998

    Section 2 – Forecast: 2001, Actual: 2001

    Construction completion:

    Section 1 – Forecast: 2003, Actual: 2003Section 2 – Forecast: 2007, Actual: 2007

    Months in planning: 264Months in construction: 109

    Project completed: 48 months

    behind schedule

    SECTION 4 - PROJECT PERFORMANCE

    MEGAPROJECT Project Performance 

  • 8/18/2019 Final STSM LondonUCL Report

    34/97

    Aspects of Performance Concerned with Doing the Project Right

    Original Targets and changes to targets Actual Achievements

    Against TargetsPerformancerelating to

    cost

    BR’s cost estimates for the Link increased steadily from GBP0.4bn in 1986 to GBP 1.255bn for Section 1 alone in 1990.

     At Royal Assent in December 1996, the estimated construction

    cost of the Link was GBP 3bni (USD 6.13bn at 2010 prices).

    In 1998 the target construction cost agreed between LCR and the

    UK Department of Transport, for sections 1 and 2 includingallowances for inflation, was GBP 5.233bnii.

    The final cost for Sections 1 and 2 was GBP 5.8bn (USD 9.63bn

    at 2009 prices) – 10% above the cost agreed in 1998 and 57%

    above the cost estimated at Royal Assent in 1996, adjusted forinflation.

    Costs (in 2010 USD)Predicted cost: 6.14bn

    Actual cost: 9.63bn

    Project completed: 57%

    over budget

    SECTION 4 - PROJECT PERFORMANCE

    MEGAPROJECT Project Performance 

  • 8/18/2019 Final STSM LondonUCL Report

    35/97

    Aspects of Performance Concerned with Doing the Project Right

    Original Targets and changes to targets Actual Achievements Against Targets

    Performancerelated to achieving

    specification

    7D=>C@A=Q @89 8

  • 8/18/2019 Final STSM LondonUCL Report

    36/97

    Aspects of Performance Concerned with Doing the Right Project

    Stakeholder orStakeholder Grouping

    Original Aims of ProjectInvolvement and Changes to these

    Aims

    Achievement of these Aims

    Described in PROJECT PROFILE

    SECTION 4 - PROJECT PERFORMANCE

    !6' ($, *) %2-7 0)&' 80'

    MEGAPROJECT Project Environment 

  • 8/18/2019 Final STSM LondonUCL Report

    37/97

    Legal and Regulatory Environment

    Legal and

    Regulatory ProjectEnvironment

    (regionally, nationally

    and Europe wide)

    5: 9:;:?9:@AB

  • 8/18/2019 Final STSM LondonUCL Report

    38/97

    Political Environment

    PoliticalProject

    Environment

    3>D@9 C9B9IJ>: LAC A B9:O@8F K=>I9CC B:C:CQ @89 9?9=O9:I9 >N C@=A@9OK?9:@ K>@9:JAB A:P I>?K9J:O AO9:PACT

    %: @89 F9A=C 9:5>?=@ @89 KA=@F L9= ;9=:?9:@ A::>D:I9C @8A@ /63. I>:C@=DI@9P AC A KDMB 689 /63. -DC9 >N />??>:CT

    !9MT 9::5 .>:P>: A:P />:J:9:@AB 3A MDK9=A@9 /63. N>BB>LI9CCT

    mA:T 9::=G5K=;9=:?9:@ A::>D:I9C @8A@ ./3 A=9 D:AMB9 @> =A I>:C@=DI@

    /63.T ./3 L>=R >: A =9C@=DI@D=N @89 V:A:I= @89 K=>H9I@TmD:T 9::; 689 &>;9=:?9:@ AII9K@C ./3bC =9C@=DI@D=K>CABC N>= @89 I>:C@=DIJ>:Q >K9=AJ>: A:P

    V:A:IN @89 /63.T $>6Q ./3Q A:P 3A

  • 8/18/2019 Final STSM LondonUCL Report

    39/97

    Economic Environment

    EconomicProject

    Environment

    The project’s reliance on private sector funding dates from its conception and was at the insistence of the Prime Ministerof the time (Margaret Thatcher). This situation (at least in its rhetoric) continued beyond 1997, despite the change ingovernment. LCR was responsible for financing its construction and operation, but the government agreed to provide

    GBP 1.7bn funding and development rights around Kings Cross and Stratford stations, and guaranteed LCR’s debt.However, LCR was unable to raise the GBP 0.8bn equity and GBP 3-4bn debt finance needed to build the Link.

    Escalating costs and reduced passenger forecasts were cited as reasons. The government refused to provide more grantfunding, but agreed a financial restructuring with LCR, involving the sale and leaseback of trains, in 1998. Revenue andpatronage have continued since to be below forecast. In 2010, the 30 year concession was sold to a Canadian pension

    plan for GBP 2.1 bn.

    SpecificEconomic

    Events

    impacting on

    the project

     /

    Financing

    and funding

    1987: The Channel Tunnel Act specifically said that no Government support would be forthcoming for the construction ofa new rail link.The fixed link was to be privately financed, owned and operated – no public subsidy could be given. But, under the

    Channel Tunnel act the public sector was legally obliged to:- procure, at its own expense, substantial (connecting) new and upgraded infrastructure works plus rolling stock

    for international passenger and freight services;-  set (jointly with SNCF) fixed tolls (subject to a guaranteed minimum) revenue to Eurotunnel for a given period

    in return for half the operating capacity (necessary for Eurotunnel to raise finance).

    1991: The BR & Eurorail joint venture had originally required £1,900 million of public sector money to be either committedor placed at risk during the early stages of construction. The Government felt that some of the risks could be better

    managed by the private sector and therefore decided that the project should proceed as part of the Private FinanceInitiative (PFI).1997: LCR approached the Department of Transport to obtain a relaxation of the contract – this effectively asked the

    Department to increase its financial risk in the project by £230 million.LCR's announcement that second stage financing could not be reached, the Department of Transport considered itsoptions and instructed its advisers to scrutinise the demand forecasts for Eurostar UK.

    1998: The Deputy Prime Minister announced the failure of LCR to raise funds to build the CTRL without a further sum of£1.2 billion from the Government. LCR would have to find the money some other way.

    1999: Re-financing completed with a successful bond issue (£2.65bn).

    SECTION 5 - PROJECT ENVIRONMENT

    MEGAPROJECT Project Key Events and Activities Timeline 

  • 8/18/2019 Final STSM LondonUCL Report

    40/97

    Events and activitiesrelating to project

    stakeholders

    Events and activitiesrelating to project

    management

    6%`7

    SECTION 6 - PROJECT TIMELINE

    2*12

    CONCEPTION:British Railways(BR) & French

    Railways (SNCF)work on

    combined rail

    scheme between2 capital cities

    BR proposed a

    new terminal. AnInterchange inSellindge (Kent)

    was alsoproposed by BR

    should Frenchtrains not be ableto penetrate

    further into UKwithout theconstruction of a

    new line.

    2*1)

    CONCEPTION:BR firstproposes link

    2*1X 2*1\2*YX

    INITIATION:British andFrench

    Governmentsagreed that a

    bored railtunnel underthe Channel

    would be a

    good

    investment.

    2*YY

    INITIATION:  An agreementwas signed

    for the privatesector to build

    and finance atunnel –Government-

    guaranteed

    loans would

    cover most ofthe cost.

    INITIATION: The UK andFrench

    governments,SNCF, BR and

    the British andFrench tunnelcompanies

    signed

    contracts,

    which ;laterresulted in aTreaty (1986)

    Major publicoppositionresulted, in light

    of fears about theimpact of faster

    and morefrequent trains.

    INITIATION:TheGovernment

    abandoned theChannel Tunnel

    idea anddecided toconcentrate

    (with France)

    which was an

    easier politicaloption.

    Events and activitiesrelating to project

    environment

    Events and activitiesrelating to project

    performance

    MEGAPROJECT Project Key Events and Activities Timeline 

    6%`7

  • 8/18/2019 Final STSM LondonUCL Report

    41/97

    Events and activitiesrelating to project

    stakeholders

    Events and activitiesrelating to project

    management

    6%`7

    SECTION 6 - PROJECT TIMELINE

    CONTEXT:UK andFrance sign

    ChannelTunnel Treaty

    2*[Y 2*[1

    CONTEXT:Channel Tunnelact rules out

    public funding forinternational

    services

    2*[2

    INITIATION:BR andSNCF

    reachedagreement to

    build atunnel.

    INITIATION: Secretary of Statefor Transport of

    both countriesannounce willing

    to give thenecessary politicalguarantees to

    facilitate fixed link

    (however withoutpublic financialsupport).

    2*[X

    The ChannelTunnelconcession was

    awarded to TransManche Link (later

    Eurotunnel).

    Constraintpoints forpassenger

    services at Ashford were to

    be remodelled

    and a newInternational

    Stationconstructed.

    INCEPTION: BR study of routeand terminal

    capacity.Four terminal

    options was

    defined: White City,King's Cross,

    London Bridge andStratford.

    INCEPTION: BR invitestenders for

     joint venturepartner.

    Eurorailselected

    2*[[ 2*[*

    Governmentestablished theprinciple of private

    sector involvement.

    Events and activitiesrelating to project

    environment

    Events and activitiesrelating to project

    performance

    MEGAPROJECT Project Key Events and Activities Timeline 

    6%`7

  • 8/18/2019 Final STSM LondonUCL Report

    42/97

    Events and activitiesrelating to project

    stakeholders

    Events and activitiesrelating to project

    management

    Events and activitiesrelating to project

    performance

    Events and activitiesrelating to project

    environment

    6%`7

    SECTION 6 - PROJECT TIMELINE

    2**_

    DELAY:BR’s jointventure with

    Euroraildisbanded

    2**2

    Evaluation ofroute options

    Governmentannounces

    constructionwill be jointventure under

    private finance

    initiative

    Publicconsultationon preferred

    route.Channel

    Tunnel RailLink bill inparliament

    2**X 2**\ 2**Y

    CONTEXT:Thamesgateway

    planningframework

    published

    CTRL bill gainsroyal assent.Environmental

    impact study.LCR

     Appointed asconcessionaire(./3 AIaD

  • 8/18/2019 Final STSM LondonUCL Report

    43/97

    Events and activitiesrelating to project

    stakeholders

    Events and activitiesrelating to project

    management

    Events and activitiesrelating to project

    performance

    Events and activitiesrelating to project

    environment

    6%`7

    SECTION 6 - PROJECT TIMELINE

    2**10*[

    DELAY:LCR unable toraise sufficient

    finance. Financialrestructuring

    agreed

    CONSTRUCTION:Construction ofstage 1 begins

    )__2

    The Deputy PrimeMinister signsagreement to

    secure completionof the CTRL.

    DELIVERY:Stage 1 opens

    )__Z )__1 )__*

    DELIVERY:Stage 2 opens

    DELIVERY:Impact study

    )_2_

    DELIVERY:Concessionsold to

    Canadianpension plan

    CONSTRUCTION:Construction ofstage 2 begins

    MEGAPROJECT Case StudyCase compiled by: ...............................

    ! )*+,- . 0 2.3

  • 8/18/2019 Final STSM LondonUCL Report

    44/97

    Basic Project Information

    Contact details: ...............................

    Project Title  !"#$%&' )*&+ ,-./012304.526 

    Location '#&78"+9$:#'#& ,;!#&978)7-6 

    Purpose *2?/.2@A52@B ?.@20C5.? BD2E F.@209#1.5C/@2 &/?G5.EH;.500945.3/. ./ID52@B 3/J/B5CK/2?)5L@B @D.C5.? BD2E 

    Scope TransnationalIntegrated with Trans-European Transport Network (TEN-T)

    Total Project Value MHNO42 9 ?122/B0P OHQ42R [email protected]/P OHSS42R 4.D3I/0P NHT42 (in 2010 USD)

    Project Status(i.e.. initiation, planning,

    construction, operation, dismantling)

    Planning start date: 1984Construction start date: 10/1993

    Operation start date: 07/2000

    Relevant PhysicalDimensions (e.g. height, width,volume, length) 

    F!F8) )#&>F=P UM+7"8*)P MV+7 R "!8'P SV+7 R W"*'>#P UHX+7 R F%&)P M+78"F*Y*;*8) *$)8&'P NHS+7V 

    SECTION 1 - BASIC PROJECT INFORMATION

    !"#$%&' )*+,- .&/0$&1 2.3

    MEGAPROJECT Case StudyCase compiled by: ...............................C d il

  • 8/18/2019 Final STSM LondonUCL Report

    45/97

    Basic Project Information

    Contact details: ...............................

    ContractualFramework(e.g. fixed price,cost-plus etc.)

    Y%&'*&>P NOOZ

  • 8/18/2019 Final STSM LondonUCL Report

    46/97

    Stakeholder

    Category Case-Study  Comments

    (e.g. maturity, previous experiences of

    stakeholders, skills, influence on project)

    I    n t    er  n al    

    Supply-Side  Client  Denmark and Sweden Governments /The Oresundbro Consortium (OC)

    Financiers  The Oresundbro Consortium

    Sponsors The Oresundbro Consortium, OC (AS Oresund,

    Denmark and Svedab AB, Sweden)

    Ownership was split equally between theSwedish and Danish states. was

    responsible for performing theenvironmental impact assessment (EIA),

    projecting, financing, negotiatingcontracts, constructing and operating the

    fixed link.

    Client’s

    Customers General public (passengers)

    Client’s Owners  Danish and Swedish Governments

    Other internal

    supply-side

    categories

    ( please specify) 

    Category  Case-Study

    SECTION 2 - PROJECT STAKEHOLDERS

    Stakeholder Case-Study  Comments

    MEGAPROJECT Internal Stakeholder Identification(Stakeholders with a direct legally sanctioned relationship with the project)

  • 8/18/2019 Final STSM LondonUCL Report

    47/97

    Category  (e.g. maturity, influence on project)I    n t    er  n a

    l    

    Demand

    Side ) Principal Contractor  Oresund Consortium (SPEs) was responsible for negotiations

    with the contractors

    First TierContractors 

    Consortia:The Öresund Tunnel Contractors, a consortium consisting of NCC AB (SE), Dumez-GTM SA (F), John Laing Ltd (UK), E. Pihl & Søn(DK), and Boskalis Westminster (NL) AndÖresund Marine Joint Venture, a consortium of Per Aarsleff A/S(DK), Ballast Nedam Dredging b.v. (NL) and Great Lakes Dredge &Dock Co (USA).

    were responsible for theconstruction of the artificial islandand dredging

     AndSundlink Contractors, a consortium of Skanska AB (SE), Højgaard &

    Schultz (DK), Monberg & Thorsen (DK), and Hochtief AG (Germany)

    Responsible for the construction ofthe bridges.

    Second Tier

    Consultants Consultant VBB VIAK Conducted investigations covering

    topics such as sedimentary and

    mapping of environmentally

    polluted areas

    Consultants COWI and VKI Provided investigations and impact

    analysis regarding marine fauna

    and flora.

    Professional

    Services Providers

    IVL, the Swedish Environmental Research InstituteSwedish national rail administration and Peab AB

    Consulting services

    Other internal

    supply-side

    categories 

    Category Case-Study

    SECTION 2 - PROJECT STAKEHOLDERS

    MEGAPROJECT Internal Stakeholder Identification(Stakeholders with a direct legally sanctioned relationship with the project)

  • 8/18/2019 Final STSM LondonUCL Report

    48/97

    I    n t    er  n al    

    78*& ;!&F"8;F$ 

    SECTION 2 - PROJECT STAKEHOLDERS

    MEGAPROJECT External Stakeholder Identification(Stakeholders with a direct interest in the project but with no legal contract)

  • 8/18/2019 Final STSM LondonUCL Report

    49/97

    Stakeholder

    Category Case-Study  Comments

    (e.g. maturity, previous

    experiences of

    stakeholders, skills,influence on project)

    E x t    er  n al    

    Public  RegulatoryAgencies 

    Swedish National Board for EnvironmentProtection (SNBEP)

    Local Government  The municipalities of Malmö and Copenhagen. Responsible forplanning tasks such

    as land acquisitions.

    NationalGovernment 

    Department of communications (DOC) and the Ministry of traffic (MOT) in theSwedish and Danish governments.

    Representatives and officials from the Swedish Road Administration (SRA), the

    Swedish Rail Administration (SRAIL), the Swedish State Railways (SSR) andtheir Danish counterparts (DSB)

    Denmark Parliament (responsible for juridical authority)

    responsible forbackground

    investigations andreports as well as

    negotiations belowminister level in the

    early stages of thepre-construction

    phase.

    Other internal

    supply-side

    categories ( please

    specify) 

    Category  Case-study 

    The WRC and the SNBEP were the two main juridicalauthorities for the SwedishEIA.

    SECTION 2 - PROJECT STAKEHOLDERS

    MEGAPROJECT External Stakeholder Identification(Stakeholders with a direct interest in the project but with no legal contract)

  • 8/18/2019 Final STSM LondonUCL Report

    50/97

    Stakeholder

    Category Case-Study  Comments

    e.g. maturity, previous

    experiences of

    stakeholders, skills,influence on project)

    E x t    er  n al    

    Private Local residents 

    Local Landowners 

    Environmentalists  Environmental Protection Act (EPA), the Natural Resources Act (NRA) and theWater Act (WA). Organized Groups.

    Conservationists 

    Archaeologists   Municipality of Malmö Carry out extensivearchaeological

    investigationsOther External

    Private

    stakeholders

    (please specify) 

    Category  Case-study  was very active inlobbying for the fixed

    link.Chamber of Commerce and Industry of SouthernSweden

    Private regional actor

    The Swedish Meteorological and Hydrological Institute(SMHI) and the Danish Hydraulic Institute (DHI)

    were deeply involvedin hydrologicalinvestigations

    SECTION 2 - PROJECT STAKEHOLDERS

  • 8/18/2019 Final STSM LondonUCL Report

    51/97

    MEGAPROJECT External Stakeholder Attitude Analysis External

    StakeholderExternal Stakeholder’s Attitude to

    this ProjectExternal Stakeholder’s

    Influence on projectImpact ofProject onExternal

    Phase of Project ofGreatest Interest(initiation planning

  • 8/18/2019 Final STSM LondonUCL Report

    52/97

    SECTION 2 - PROJECT STAKEHOLDERS

    External

    Stakeholder

    (initiation, planning,construction, operation,

    dismantling)

    Danish policy  Not to allow a link across theOresund before one had been builtacross the Great Belt.

    Wider political issues influencedthe timing of the project.

    The controversy overenvironmental impacts delayedthe approval process in Sweden.

    Initiation/Planning

    Swedish NationalRailway Administration

    The fixed link across the Oresundwould not imply any strategicimprovement unless a promise of alink across the Fehmarn Belt wasalso discernable somewhere alongthe line.

    Initiation/Planning

    Department offinance (DOF)

     A principal issue was the pricingmechanisms for road and rail traffic.The Danes were adamant that thepricing mechanism for road trafficshould be based on the ferry taxes.

    Blocked many proposals andagreement texts.

    Initiation/Planning

    European Round

    Table ofIndustrialists (ERT)

    Comprising several important

    business representatives, arguedfor a fixed link in its ScanLinkproposal.

    Initiation/Planning

    The organisationStoppabron(stop the bridge)

    They were opposed to the link. Initiation/Planning

    MEGAPROJECT External Stakeholder Attitude Analysis 

    ExternalStakeholder

    External Stakeholder’s Attitude to this Project External Stakeholder’sInfluence on project

    Impact of Projecton ExternalS

    Phase of Projectof Greatest

  • 8/18/2019 Final STSM LondonUCL Report

    53/97

    SECTION 2 - PROJECT STAKEHOLDERS

    Stakeholder Interest

    The socialdemocratic

    leadership ofthe Swedishgovernment

    Were strong proponents of the combined road andrailway link between Copenhagen and Malmö, but

    there were deep rifts within the party and the issuecaused lots of controversy.

    During the 30th social democratic party congressheld in 1987 the issue was hotly contested. Manywithin the party were highly sceptical toward thealternative favoured by the leadership, a commonlypreferred alternative consisting of the railway tunnelbetween Copenhagen and Malmö.

    The referendumregarding the

    leadership!s proposalwas postponed and aninternal study groupresponsible for furtherinvestigations wasappointed.

    Initiation/Planning

    Danishsocialdemocrats

    Who, although not in government at the time, wereseen as crucial actors.

    Danish social democrats. The general opinionseemed to favour a railway tunnel, but the opinionwould however eventually swing in favour of thecombined road and railway link after intensepressure from the Swedish delegation.

    Unless the Danish socialdemocrats were positiveabout the project therewas no way for thegovernment in power tosecure support for theproposal in the Danishparliament.

    Initiation/Planning

    The

    Chamber ofCommerceand Industryof SouthernSweden

    which, together with its

    Danish counterpart, wasvery active in lobbyingfor the fixed link.

    Initiation/Planning

    MEGAPROJECT External Stakeholder Attitude Analysis 

    ExternalStakeholder

    ExternalStakeholder’s Attitude

    t thi P j t

    External Stakeholder’s Influence on project Impact of Projecton ExternalSt k h ld

    Phase of Projectof Greatest

    I t t

  • 8/18/2019 Final STSM LondonUCL Report

    54/97

    SECTION 2 - PROJECT STAKEHOLDERS

    to this Project Stakeholder Interest

    The Swedish

    National Boardfor EnvironmentProtection(SNBEP)

    In 1993, they rejected the application for

    permission to build and operate the fixed link(from OC) on the following grounds:•

     

    the project might harm the ecologicallysensitive Baltic Sea;

    •  it might also harm the immediatelysurrounding sea, which was an importantfishing area of national interest; and

    •  it was viewed as counter-productiveregarding strategies towards an

    environmentally adapted transport system.

    Initiation/Planning

    The municipalityof Malmö

    The municipal level hasa very strong position inthe Swedish planningsystem.

    Land use reservations for the link and connectinginfrastructure were made as early as themid-1950s.

  • 8/18/2019 Final STSM LondonUCL Report

    55/97

    Risk Management Processes  Present (describe below ) !Not Present !  No Information ! 

    HR Management Processes Present (describe below ) !Not Present !  No Information ! 

    Project Processes

  • 8/18/2019 Final STSM LondonUCL Report

    56/97

    Procurement Management Processes Present (describe below ) !Not Present !  No Information ! 

    Integration Management Processes Present (describe below ) !Not Present !  No Information ! 

    Scope Management Processes Present (describe below ) !Not Present !  No Information ! 

    Time Management Processes Present (describe below ) !Not Present !  No Information ! 

    Cost Management Processes Present (describe below ) !Not Present !  No Information ! 

    Quality management Processes Present (describe below ) !Not Present !  No Information ! 

    Communications ManagementProcesses

    Present (describe below ) !Not Present !  No Information ! 

    SECTION 3 - PROJECT MANAGEMENT

    !

    MEGAPROJECT Project Performance 

    Aspects of Performance Concerned with Doing the Project Right

  • 8/18/2019 Final STSM LondonUCL Report

    57/97

    Original Targets and changes to targets Actual Achievements AgainstTargets

    Performancerelating to time

    Construction start:Forecast: 1993

     Actual: 1995 

    Construction completion:

    Forecast: 2000 Actual: 2000 

    Months in planning: 112Months in construction: 81

    Project completed:

    #$ %&'()*+(

    SECTION 4 - PROJECT PERFORMANCE

    MEGAPROJECT Project Performance 

    Aspects of Performance Concerned with Doing the Project Right

  • 8/18/2019 Final STSM LondonUCL Report

    58/97

    Original Targets and changes to targets Actual AchievementsAgainst Targets

    Performancerelating to

    cost

    The main source of cost overrun is the connecting infrastructureon the Danish side, which was close to 70% higher than theestimates made in 1991, but the actual coast-to-coast link andthe connecting infrastructure on the Swedish side were alsosubject to substantial cost overruns.

    Costs predicted:

    1987: $#+ QHS42 ,#%" NHUM42 D2 VOOU C.DL/061991: $#+ NTHXVT42 ,#%" VHN42 D2 VOOU C.DL/061997: '++ NMHUT42 ,#%" VHSQ42 D2 VOOU C.DL/062000: #%" SHOQU42

    The escalating costs are attributed to maritime safety efforts,environmental protection and a third category simply labelled

    “other”. Maritime safety efforts account for around 42% of theescalation, while the other two categories account for 34% and24% respectively.

    Costs (in 2010 USD)Predicted cost: 2.96 bn

    Actual cost:

    Total: 4.10 bnTunnels: 0.9BN

    Marine: 0.33BNBridges: 1.5BN

    Project completed:

    SQZ ![#" W%'>#F

    SECTION 4 - PROJECT PERFORMANCE

    MEGAPROJECT Project Performance 

    Aspects of Performance Concerned with Doing the Project Right

    O i i l T t d h t t t A t l A hi t

  • 8/18/2019 Final STSM LondonUCL Report

    59/97

    Original Targets and changes to targets Actual AchievementsAgainst Targets

    Performancerelated toachieving

    specification

    FORECAST TRAFFIC

    (2007):

    Road: 15,732 VPDRail: 28,000 PPD

    ACTUAL TRAFFIC

    (2007): 

    Road: 18,432 VPDRail: 26,600 PPD

    SECTION 4 - PROJECT PERFORMANCE

    MEGAPROJECT Project Performance 

    Aspects of Performance Concerned with Doing the Project Right

    Original Targets and changes to targets Actual Achievements

  • 8/18/2019 Final STSM LondonUCL Report

    60/97

    Original Targets and changes to targets Actual AchievementsAgainst Targets

    Performancerelated toachieving

    specification

    (cont.)

    FORECAST TRAFFIC

    (2007):

    Road: 15,732 VPDRail: 28,000 PPD

    ACTUAL TRAFFIC

    (2007): 

    Road: 18,432 VPDRail: 26,600 PPD

    SECTION 4 - PROJECT PERFORMANCE

    Aspects of Performance Concerned with Doing the Right Project

    Stakeholder or Original Aims of Project Achievement of these Aims

  • 8/18/2019 Final STSM LondonUCL Report

    61/97

    Stakeholder orStakeholder Grouping

    Original Aims of ProjectInvolvement and Changes to these

    Aims

    Achievement of these Aims

    SECTION 4 - PROJECT PERFORMANCE

    !,- ./0 12 3456 728- 97-

    MEGAPROJECT Project Environment 

    Legal and Regulatory Environment

  • 8/18/2019 Final STSM LondonUCL Report

    62/97

    Legal andRegulatory

    ProjectEnvironment

    (regionally,nationally andEurope wide)

    The Oresund link was the first infrastructure project in Sweden entirely financed outside thestate budget. According to a paragraph in the budgetary law, infrastructure should normally be

    paid for by state grants using state revenue as the only source of funding.

    In Sweden the formal procedure implied that the project had to be tested against different legalframeworks in several juridical instances before gaining approval.Georg Andersson, then minister of communications, explained that the environmental inquirycould influence the shape and design of the fixed link, but not the actual building of it.

    In Denmark a special law is usually passed for large projects. This law, which is formulated by

    the responsible ministry (in this case the ministry of traffic), regulates the entire project andconsists of elements from the legislative framework which are deemed appropriate for theproject.

    The level of user fees for road traffic are regulated by the Oresund Consortium but according tothe 1991 agreement between the governments the price for crossing the link must be set usingthe price of the ferry route between Helsingborg and Elsinore as a point of departure.

    Specific Legal

    and Regulatoryevents

    impacting on

    the project

    1985: Denmark signed the EC directive regarding environmental impact assessments (EIA).1991: The preparations of the law concerning the fixed link a number of environmentalinvestigations were carried out which were presented in the report Miljö Öresund

    SECTION 5 - PROJECT ENVIRONMENT

    MEGAPROJECT Project Environment 

    Political Environment

  • 8/18/2019 Final STSM LondonUCL Report

    63/97

    PoliticalProject

    Environment

    Since the 1950s a great number of investigations and reports (more or less realistic and/orpolitically feasible) about the benefits of a fixed link across the Oresund were produced in both

    Sweden and Denmark. An agreement to build a fixed link was signed by the governments in1973, but the energy and economy crisis, as well as Denmark!s decision to join the EC andincreasing environmental awareness meant that the plans came to a halt.

    Since a fixed link across the Oresund had been a vision backed by the political establishmentin Malmö for a much longer time than in Copenhagen the matter of land acquisition differs quitesubstantially between the two municipalities. In Malmö land for the connecting infrastructurehad been reserved since the 1950s. In the 1956 general plan a zone was reserved for the

    connecting infrastructure (then thought of as a highway).

    SpecificPolitical

    Events

    impacting on

    the project

    1987-1991: The handling of the project was shifted towards the political sphere with theleading politicians in the Swedish and Danish social democratic parties as the main players(Both countries regarded the need to get approval for the project within the social democraticparties. Initially there was widespread resistance to the project amongst the social democratsin both countries.)

    1994: The OC handed over the revised plans and the government gave permission for theproject to proceed. The minister of environment stepped down from his post, but the centreparty remained in the government and thus a political crisis was averted. Elections were heldand the coalition lost power to the social democrats.

    SECTION 5 - PROJECT ENVIRONMENT

    MEGAPROJECT Project Environment 

    Economic Environment

    Economic The combined road and railway link was recommended by the OD on it was the best solution

  • 8/18/2019 Final STSM LondonUCL Report

    64/97

    Project

    Environment

    from an economic viewpoint given the evaluation of traffic volumes at the time.

    Despite the fact that it is common practice in Sweden to use socio-economic cost-benefit analysisas a basis for decisions regarding infrastructure investments, this was never the case for theOresund link. The analyses that were carried out focused on economic profitability, since this wasa prerequisite given the loan-based financing of the project. The funding structure based on userfees for road traffic as the main source of financing meant that the volume of road traffic and theprice level of user fees in relation to the construction cost became the ultimate criteria forappraisals.

    SpecificEconomic

    Events

    impacting on

    the project

    1985: Regarding financing it was agreed that the project had to be financed outside the statebudgets and to be profitable on business economic (rather than socio economic) terms.

    1989: A report was presented and two premises were guiding: the condition that no state budgetgrants should be used (business economic profitability); and that the structure of the link shouldnot affect the water flow in the Sound.

    1991: The agreement between the Swedish and Danish governments is signed. The chosen

    alternative of a combined road and railway link between Sweden is viewed as the best alternativefrom an economic perspective. The agreement also states that the connecting infrastructureshould be funded by revenues from the coast-to-coast section of the link.

    SECTION 5 - PROJECT ENVIRONMENT

    MEGAPROJECT Project Key Events and Activities Timeline 

    F*7#

    NQXT NQXa NQXU NQQONQUS NQXM NQQN

  • 8/18/2019 Final STSM LondonUCL Report

    65/97

    Events and activitiesrelating to project

    stakeholders

    Events and activitiesrelating to project

    management

    SECTION 6 - PROJECT TIMELINE

    CONCEPTION:Swedish-Danishgovernmentsagree to buildfixed link

    Events and activitiesrelating to project

    environment

    Events and activitiesrelating to project

    performance

    CONTEXT:European roundtable perceivedas lobbying forroad link

    INCEPTION:Oresunddelegation

    appointed

    CONCEPTION:DelegationproposesHelsingborg-HelsingørRailway Tunnel &Malmö-CopenhagenRoad Bridge.

    State fundingruled out

    CONTEX:Great beltbridge decisionbreaks Danishdomestic policyblock on otherfixed links

    CONCEPTION:Delegationrecommendscombined road/rail bridge butcontinues toconsider railtunnel option

    INCEPTION:Swedishparliamentsupportscombinedbridge option,Danish leadersfollow suit

    INCEPTION:Negotiationson fundingstructure

    INCEPTION:Twogovernmentssign bindingagreement.Constructionto start in1993 andfinish in 2000

    MEGAPROJECT Project Key Events and Activities Timeline 

    F*7#

    NQQM NQQTNQQV NQQS NQQUbX NQQQ VOOO

  • 8/18/2019 Final STSM LondonUCL Report

    66/97

    Events and activitiesrelating to project

    stakeholders

    Events and activitiesrelating to project

    management

    SECTION 6 - PROJECT TIMELINE

    INCEPTION:Redesignapproved bySwedishGovernment

    INCEPTION:OresundbroConsortiumformed,applies forplanningpermission

    Events and activitiesrelating to project

    environment

    Events and activitiesrelating to project

    performance

    CONSTRUCTION:Danish LandInfrastructure worksin preparation

    DELAY:Permissionrefused bySwedish NationalBoard, finallygranted by waterrights court butconditional onredesign

    CONSTRUCTION:Construction starts.OC contracts withthree consortia

    CONSTRUCTION: 1997: First tunnelsection in place

    1998: First bridge

    section in place

    DELIVERY:First cardrivesthroughtunnel

    DELIVERY:Handoverandinauguration

    The finished structuredid not affect thewater flow betweenthe North and BalticSeas – Zero impact“solution! 

  • 8/18/2019 Final STSM LondonUCL Report

    67/97

  • 8/18/2019 Final STSM LondonUCL Report

    68/97

  • 8/18/2019 Final STSM LondonUCL Report

    69/97

  • 8/18/2019 Final STSM LondonUCL Report

    70/97

    !"#$%&%'( *+,%('(- .,(/( %0 #12 341%56/(0(1& *+&7/ #0 8%(4(10 #19 :/((1;(#+(< =,#& #/( &,( 86>0 ;/(0(1& %1 3?>:* @#0( 8&"9%(0<

    A>:>BC-

    B3   !" $% &'" ()*%*&"

    D>8   !" $% ()*%*&"

    UNITED KINGDOM DENMARK-SWEDEN GERMANY FRANCE NETHERLANDS

    CHANNEL TUNNEL RAIL LINK The Oresund Link Motorway A20 TGV Mediterranean BENELUXLIJN (Metro line)

     YES YES NO NO NO

    No mentioning of Siemens in OMEGA reports.But, Siemens is stated as supplier of signaling

    No mentioning of Siemens in OMEGA reports.But, Siemens is stated as a supplier of some

    No mentioning of Siemens in OMEGAreports. Plus, I didn't find any reference of

    No mentioning of Siemens in OMEGA reports. Plus, Ididn't find any reference of Siemens on Internet

    No mentioning of Siemens in OMEGA reports. There issome information on Internet: The signalling is

    3?>:* @(1&/( @#0( 8&"9%(0

  • 8/18/2019 Final STSM LondonUCL Report

    71/97

    , pp g g

    and train control systems on the website:

    , pp

    equipment.

    p , y

    Siemens on Internet regarding this project.

    y

    regarding this project.

    g g

    supplied by Alstom. All lines have been constructedbefore the Beneluxlijn are supplied by Siemens.

    http://www.railway-technology.com/projects/chunnel/ Siemens trains was meant to go on services fromFrankfurt to southern France via the new LGV Rhin-

    Rhône, and subsequently within Germany and onother international services to France, Belgium,Switzerland and the Netherlands. No mentioning of

    Siemens in TGV Mediterranee line.

    http://retmetro.nl/cms/index.php?option=com_content&view=article&id

    =260&Itemid=62

    http://www.railway-technology.com/features/feature-top-ten-fastest-

    trains-in-the-world/

     YES YES YES NO  YES

    No mentioning of any existing environmentalgroup activities in OMEGA reports. However, in

    the book: Environmental Protest in WesternEurope, Oxford University Press 2007, page 48, it

    is said: 1988.-1989, the number of Greenpeacesupporters increased almost two times and in1992. the protests were more organized.

    No mentioning of Greenpeace in OMEGA reports.On Internet we found the follow: International

    groups such as Birdlife International andGreenpeace & Transport & Environment have also

    looked into the issue of the Oresund link.Environmental groups, who worried thatconstruction of the link would disturb the flow of

    water and ecosystem of the Baltic Sea, still worryabout increased auto emissions. "We activelycampaigned against the bridge for three years

    until the final decisions were made by thegovernments," says Mats Abrahansson, aspokesman for Greenpeace.

    It is mentioning in OMEGA Centre reports."Many environmental agencies, such as

    BUND and Greenpeace, as well as smallerlocally organised agencies, criticized the A

    20. The strongest point of criticism is theroute option chosen in Schleswig-Holstein".

    No mentioning of Greenpeace in OMEGA reports.Plus, I didn't find any reference of Greenpeace on

    Internet regarding this project.

    No mentioning that any organization opposed theproject in Omega reports. It is written there public

    consultation was conducted. During the design andconstruction phase, intensive external project

    management was carried out. From previousexperience, the project team understood theimportance of good communication.

    http://books.google.rs/books?id=8ybVHakcYQkC&pg=PA48&lpg=PA48&dq=greenp

    eace+protests+channel+tunnel+rail+link&source=bl&ots=dZqzILv8go&sig=d8Pct-

    K3LLXG3uMIn4jS14cO9Cg&hl=en&sa=X&ei=yckNU_HUD4KM7AbAtoHgBA&ved=

    0CC8Q6AEwAg#v=onepage&q=greenpeace%20protests%2

    http://gurukul.ucc.american.edu/ted/oresund.htm

    There is some information on the Internet:

    http://www.csmonitor.com/1997/0410/041097.intl.intl.3.html/(pag

    e)/2

    http://sepp.xylou.de/a/DgA/23093a69/fr%C3%BChen_20._Harkenblec

    k_.html

    OMEGA report: A wide array of different

    organisations opposed to the link were organisedunder the umbrella organisation Stoppabron (stopthe bridge). The organisation comprised of over 30

    individual organisations ranging fromenvironmental NGOs to the labour.

     YES YES YES YES NO

    CONCESSIONAIRE: LONDON &CONTINENTAL RAILWAYS (LCR) composedby Arup, Bechtel, Halcrow and Systra

    The Oresundbro Consortium, OC (AS Oresund,Denmark and Svedab AB, Sweden)

    Federal Road Agency (DEGES) SNCF (Société Nationale des Chemins de ferFrançais; "French National Railway Company")

    Two public sector organisations were responsible forconstruction: Gemeentewerken for the rail track, andRijkswaterstaat for the tunnel section.

    Act of Aceleration of Transport

    Infrastruture Planning (VerkPBG)

    SNCF, as a public rail agency formed special entity for

    project management on this project, was responsiblefor the project and the future operator of the high

    speed line.

    RFF (Réseau Ferré de France)

     As owner of the rail network, RFF is responsible fordevelopment and maintenance as well as usage

    charges and timetable management.

    The SNCF operates the country's national railservices. Its functions include operation of railwayservices for passengers and freight, and maintenance

    and signalling of rail infrastructure owned by RFF.

    Siemens

    Greenpeace

    SPEs(Graham Winch's

    definitions)

    !"#$%&%'( *+,%('(- .,(/( %0 #12 341%56/(0(1& *+&7/ #0 8%(4(10 #19 :/((1;(#+(< =,#& #/( &,( 86>0 ;/(0(1& %1 3?>:* @#0( 8&"9%(0<

    A>:>BC-

    B3   !" $% &'" ()*%*&"

    D>8   !" $% ()*%*&"

    NETHERLANDS NETHERLANDS GREECE GERMANY GERMANY

    HSL ZUIDRANDSTADRAIL, THE HAGUE-

    ROTTERDAMAthens Metro (Sepolia - Dafni &

    Monastiraki - Ethniki Amyna)New ICE Cologne– Rhine/Main line Tiergarten Tunnel - Berlin

     YES NO  YES YES YES

    No mentioning of Siemens in OMEGA reports.Plus, I didn't find any reference of Siemens on

    The OMEGA material mentioned that Siemens are mentioning in OMEGA reports :"Equipment technology works, including

    Siemens are mentioning in OMEGA reports:Siemens was one of the contractors working on

    3?>:* @(1&/( @#0( 8&"9%(0

    Siemens are mentioning in OMEGA reports: The trackand signaling systems were developed by Infraspeed

  • 8/18/2019 Final STSM LondonUCL Report

    72/97

    Internet regarding this project. catenaries, signalling equipment,telecommunications, switching stations, powersupply and electric engineering, were carried

    out by a group headed by Siemens PLC (nowSiemens Transportation Systems)".

    road tunnel.

    Electromechanical WorksSIEMENS  AKTIENGESELLSHAFT BERLIN-MUENCHEN

    are one of the members of the consortiumOLYMPIC METRO (the contractor of theproject).

     YES NO  YES ? NO

    No mentioning of Greenpeace in OMEGAreports. Plus, I didn't find any reference of

    Greenpeace on Internet regarding this project.

    No mentioning of Greenpeace in OMEGAreports. However, on internet we found a report

    of Greenpeace which say: "A new metro linehas been built, gas-fuelled buses have been

    introduced (Athens has now the largest gas-fuelled bus fleet in Europe), and some 3 billion ! have been spent in public transport (extension

    of metro, introduction of tramway and suburbanrail, modernisation of bus and trolley fleets,tripling of bus-only lanes)".

    No mentioning of Greenpeace in OMEGAreports. However, on Internet, Greenpeace are

    conected to the project.

    No mentioning of Greenpeace in OMEGAreports. Plus, I didn't find any reference of

    Greenpeace on Internet regarding this project.

    http://www.publications.parliament.uk/pa/cm201012/cmselect

    /cmtran/writev/rail/m94.htm

    NO NO  YES ? ?

    Attiko Metro SA, a government-ownedcompany, was set up in 1991 to act as clientand project manager.

    Siemens

    Greenpeace

    SPEs(Graham Winch's

    definitions)

    (a consortium of Fluor Infrastructure, SiemensNederland, Koninklijke BAM Groep, Innisfree andHSBC Infrastructure), under a DBFM contract.

    Not Greenpeace but others: "Influential in thedebate, but not so much for the end result, was the co-

    operation between several interest groups fromdifferent backgrounds. This broad coalition, as it was

    called in the media, consisted of Stichting Natuur enMilieu, an environmental group, the ANWB, a union forusers of transport with wheels, LTO Nederland, an

    organization for agri- and horticultural entrepreneursand employers, the Chambers of Commerce of theregion of The Hague, and the WWF. This coalition

    started a strong lobby campaign in favor of the linkingof infrastructure along existing tracks and with a stopin The Hague."

    It seems there was not an SPE formed, but there arestrong elements of it: The transport ministry remained initiator, client and main financier throughout

    the project, and owns the line. The project teamworked under its supervision and included employees

    of its implementation agency, Rijkswaterstaat, andexternal consultants.

    Management of the project was shared betweenthe two regional governments, their transportoperators, and the local governments

    concerned, and a project management teamrepresenting the various organisations was set

    up to co-ordinate construction. The regionaltransport provider, RET, was responsible forconstruction of the Rotterdam sections, and the

    city of The Hague for the sections under itsownership (as the transport provider, HTM, hadbeen privatised).

    GFR (DB AG from 1992) acted ascommissioning client and project manager, andDE Consult was responsible for design. The

    Federal Railways Agency, established in 1994,took over supervisory and approval roles.

     Although the inter-agency planning team wasresponsible for co- ordinating the project as awhole, the city government oversaw the

    construction of the road tunnel and DB AG therail connection and stations. There was no main

    contractor, with separate contracts let forspecific parts of the project.

  • 8/18/2019 Final STSM LondonUCL Report

    73/97

    STSM Report 

    5.6. 

    Quantitative analysis comments for UK  Channel Tunnel Rail Link  and Oresund Bridge 

  • 8/18/2019 Final STSM LondonUCL Report

    74/97

    1.  PROJECT TITLE: CHANNEL TUNNEL RAIL LINK, LONDON‐KENT, UK 

    RESPONSE (DEPENDANT) 

    VARIABLE is  PROJECT 

    PERFORMANCE 

    CHANNEL 

    TUNNEL 

    RAIL LINK, 

    LONDON‐

    KENT, UK 

    Comments 

    Project  Phase  In operation 

    Planned  Completion date   2003 It is said actual completion was 48 months later than planned. And actual completion was 2007. 

     Actual  

    Completion 

    date   2007 

    It 

    is 

    operation 

    start 

    date 

    Planned  Budget    6.4bn  2010 prices 

     Actial  Budget    9.63bn 2010 prices 

    CTRL OVERBUDGT  1 

    DELAY during the construction phase 

    Delay during the planning phase  1  The planning phase was also prolonged and lasted 264 months. 

    A1 

    2.1 

    Stakeholders ‐

    Project has a foreign EPC 

    company 

    STSM Report 

    Internal 

    Siemens is involved as a 

    contractor in the project

    No mentioning of  Siemens in Omega material. But, Siemens is stated as supplier of  signaling and train control systems for the CTRL on the web site: 

  • 8/18/2019 Final STSM LondonUCL Report

    75/97

    A2 

    contractor in the project http://www.railway‐technology.com/projects/chunnel/ Also, some of  the trains are bought from Siemens. 

    A3 

    THE CLIENT IS ALSO THE EPC OR 

    MAIN CONTRACTOR 

    A4 

    The EPC has a clear goal ??? 

    Instead of  EPC, a Concessionaire is present here (London and Continental Railways  – LCR). The contract model is BOT. Therefore, a new attribute is proposed: BOT (yes  ‐1, no  – 0). Regarding the "Clear goal" attribute, no information in Omega material, no information on LCR's website. 

    The 

    project 

    is 

    mono 

    Cultural 

    (SEE 

    BELOW) 

    A5 

    A) CLIENT AND EPC HAVE THE 

    SAME NATIONALITY (N/A IF 

    THEY ARE THE SAME) 

    Client and Concessionaire are the same nationality. Those are top two levels when the project is delivered as BOT, such as this one. The third level would consist of  design and construction companies. They were 

    international. 

    A6 

    B) CLIENT AND EPC AND ALL THE 

    IMPORTANT FIRST TIER 

    CONTRACTOR 

    HAVE 

    THE 

    SAME 

    NATIONALITY 

    A7 

    More than 50% share of  the 

    client is under goverment 

    control (EVEN IF FOREIGN 

    GOVERNMENT) 

    A8 

    An experienced project director 

    is present 

    N/A  No data in Omega Material, nor on web. 

    A9 

    2.2 

    Stakeholders ‐

    External 

    ALREADY EXISTING 

    ENVIRONMENTAL GROUP (SUCH 

    AS GREENPEACE) HAVE 

    OBJECTED TO THE PROJECT 

    No mentioning

     of 

     any

     existing

     environmental

     group

     activities

     in

     Omega

     Centre material. However, in the book: Environmental Protest in Western Europe, Oxford University Press 2007, page 48, it is said: 1988.‐1989, the number of  Greenpeace supporters increased almost two times and in 1992. the protests were more organized. 

    STSM Report 

    THERE WAS PUBLIC 

    ACCEPTABILTY TO THE PROJECT 

    AT NATIONAL LEVEL (NO 

    1974. Major public opposition in light of  fears about the impact of  faster and more frequent trains. 

  • 8/18/2019 Final STSM LondonUCL Report

    76/97

    A10  PROTEST) 

    A11 

    THERE WAS PUBLIC ACCEPTABILTY TO THE PROJECT 

    AT LOCAL LEVEL (NO PROTEST) 

    A12 

    Environmental activists and 

    regulators have been engaged 

    ex‐ante, not ex post (N/A never 

    engaged or don't know) 

    Comprehensive Environmental Statement was prepared and then, as authorisation was obtained through the Parliamentary process that resulted in the CTRL Act, a series of  ‘environmental standards’ were agreed. Also: The RLCI was set up as an independent charity to support local communities, landowners and organisations to realise their ideas for environmental enhancement along the CTRL route. The 

    Initiative received initial funding of  £2m from the CTRL developers. 

    And also: 

    "Local authorities affected by the CTRL route and station options development process were variously consulted throughout the project preparation period. Their prime focus was on avoiding and mitigating potential environmental impacts within their areas." 

    A13 

    LOCAL LEVEL PROTESTS 

    OCCURED DURING 

    CONSTRUCTION OR 

    COMMISSIONING NOT DURING 

    PLANNING (N/A IF NO PROTEST 

    AT ALL) 

    5.1 Project 

    Environment ‐

    Legal 

    The project has a strong 

    regulation system as evidenced 

    by: 

    B1 

    a) The authority stopped the project or similar projects in 

    0  Not sure if  the Government can be considered as the authority here. If  yes, then it is 1, because: 

  • 8/18/2019 Final STSM LondonUCL Report

    77/97

    STSM Report 

    Institute of  Economic Affairs, 2007, Chapter 6 The Channel Tunnel (1985‐1994‐2007), pages 131‐132) D R Myddelton notes that the d i i t d ith th Ch l T l ( d b i ti th

  • 8/18/2019 Final STSM LondonUCL Report

    78/97

    decision to proceed with the Channel Tunnel (and by association the CTRL) spanned several different governments in the UK, as follows: “In the twelve years 1964‐75 the party in power in the UK changed three times and there were six different ministers of  transport. Given BR’s lukewarm attitude towards the Tunnel, so much chopping and changing can hardly have helped. But the project itself  was not party‐political. Douglas‐Home’s Conservative government started it, Wilson’s (first) Labour government signed an agreement ‘in principle’, and Heath’s Conservative government signed legal contracts and the Treaty. Finally 

    Wilson’s (second) Labour government cancelled the first high quality rail 

    link to London, then the 

    Tunnel itself. 

    In the early 1980s Mrs Thatcher expressed interest in a fixed link between England and France, which she had supported as a member of  the Heath government. The French were keen, in order to regenerate the Nord‐Pas de Calais region. At first she and Francois Mitterand, the French President, preferred a road to a rail link (as had Heath): he wanted a bridge while she favoured a drive‐through tunnel. But she ruled out any government finance, and doubted whether 

    a private enterprise tunnel would pay.” Not sure what should be the values for this attribute and values for 

    attributes b, c, d. 

    B7 

    b) Support of  the local government NO CENTRAL 

    STSM Report 

    GOVERNMENT 

    C) SUPPORT BY BOTH  0 

  • 8/18/2019 Final STSM LondonUCL Report

    79/97

    B8 

    LOCAL 

    AND 

    CENTRAL 

    B9 

    D) NOT SUPPORTED BY EITHER LOCAL AND CENTRAL 

    C1 

    3. Project 

    Manangement 

    THE MEGAPROJECT IS 

    COMPOSED OF MORE THAN 1 

    IDENTICAL INDEPENDENT UNIT 

    (E.G. WIND TURBINES TO MAKE 

    A FARM, 2 NUCLEAR PLANTS IN 

    THE SITE,

     10

     LARGE

     ASHIPS

     ETC…) 

    C2 

    Heavy usage of  planning by 

    milestones 

    N/A  No data. Omega centre did not go into details about PM aspects. 

    C3 

    Heavy usage of  Formal project 

    management tool and technique 

    N/A  No data. Omega centre did not go into details about PM aspects. 

    C4 Usage of  performance metrics 

    N/A  No data. Only some about environmental planning. Omega centre did 

    not go into details about PM aspects. 

    C5 

    LUMP SUM

     ‐Turn

     key

     contract

     

    between Client and EPC (main 

    contractor) 

    (N/A IF CLIENT AND EPC ARE THE 

    SAME) 

    C6 

    There was a formal litigation 

    procedure (e.g. international 

    chamber of  commerce) during 

    the contract

     between

     Client

     and

     

    EPC (IF THEY ARE DIFFERENT ‐ IF 

    THE SAME OR PROJECT STILL IN 

    PLANNING STAGE THEN N/A) 

    C7 

    Project has a well developed 

    FEED 

    ??? 

    STSM Report 

    Modular project  ‐ consider only 

    the related sentences below ‐

    D1

    a) The project is modular  ‐dependent modules

  • 8/18/2019 Final STSM LondonUCL Report

    80/97

    7. Technology 

    D1  dependent modules 

    D2 

    b) The project is modular  ‐

    independent modules 1 

    The project was split into 2 independent sections (see below), but inside the sections, modules were dependent (such as tracks and stations). "The 1998 restructuring split the construction of  the Link into two sections: Section 1 (the southern part, from the Channel Tunnel to near Ebbsfleet on the outskirts of  London) and Section 2 (the northern part, from near Ebbsfleet to St. Pancras). For contractual purposes the construction of  the sections were undertaken in separate LCR subsidiaries: Section 1 by Union Railways (South) Ltd and Section 2 by Union Railways (North) Ltd." 

    D3 

    FOAK WIDE DEFINTION: FOAK 

    AT LEAST IN THE COUNTRY (e.g. 

    the first EPR reactors in the 

    country) OR FOR THE EPC OR 

    UNIQUE (LIKE THE MOSE IN 

    VENICE) 

    Britain’s first high‐speed railway 

    D4 

    FOAK STRONG, NARROW 

    DEFINITION: FOAK EVER (first 

    EPR ‐OL3)

     or

     unique

     Project

     (like

     

    Venezia mose) 

    It is not the first high speed rail ever, but it could be considered as the first high speed rail trough the channel under the sea, connecting two countries. It depends how we define the attribute. It has the following 

    elements of  strong FOAK: In 1994, the American Society of  Civil Engineers elected the tunnel as one of  the seven modern Wonders of  the World (wikipedia). St Pancras International Station is the largest of  its kind in Europe and is expected to handle some 50 million passengers per year (omega material). 

    It is aslo said: "In 2007, it will take  just 7 minutes to get from St Pancras to Stratford 

    STSM Report 

    International station, which is a platform for creating Stratford City  ‐ the largest single mixed‐use urban regeneration project in Europe.

  • 8/18/2019 Final STSM LondonUCL Report

    81/97

    in Europe. 

    The upgraded transport infrastructure was instrumental in London winning the bid to host the Olympic Games." 

    E1 

    Not classificad 

    OFFSHORE PROJECT 0 

    E2 

    Financial Support from the 

    European Union 

    E3 

    Financial Support from the 

    national governament

     

    F1 

    RESPONSE 

    (DEPENDA

    NT) 

    VARIABLE is 

    EXTERNAL 

    PRIVATE 

    STAKEHOLD

    ER 

    ACCEPTABILITY 

    Previous national similar project 

    was ON TIME AND BUDGET (N/A 

    FOR foak) 

    N/A 

    F2 

    Unemployment  in the area 

    above national average 

    0? 

    I suppose the unemployment rate in London was not higher than national average, but I could not find exact figures. There are also following doubts about this attribute: When it is about the line infrastructure projects, there could be differences in unemployment rate between areas through which the 

    infrastructure goes. In case of  CTRL, it is said that 

    Economic development and employment opportunities were some of  the 

    main arguments for the project. 

    "The Channel Tunnel Rail Link presents the opportunity to provide high speed services for commuters into London, with significantly reduced  journey times. This will attract new business and employment opportunities and open up access from Kent for employment opportunities in Stratford, the Lower Lea and Docklands, and opportunities for reverse commuting." 

    STSM Report 

    It is probable that unemployment rate was different in London than in South‐eastern part of  England, where the line goes. However, more  jobs in relation to this project are probably offered in and around London. Even in the city there could be areas with different unemployment rate. 

  • 8/18/2019 Final STSM LondonUCL Report

    82/97

    y p y

    For example, it is also said for area around Ashton: "Local economic performance has lagged behind a rising rate of  housing development despite a generous supply of  employment land." 

    And unemployment rate can change over time also. That is interesting for this case, because the project was developed in a very long period of  

    time. About the project, it is written: "CTRL project workforce totaled some 8,000 persons (max) When completed, CTRL will have consumed some 50 million man‐hours." 

    F3 

    THE MAJORITY OF THE 

    NATIONAL POPULATION

     TRUST

     THE NATIONAL AUTHORITY 

    N/A 

    No data about the trust to authorities in Omega material. It is already mentioned about protests and that even the Government itself  stopped the project. On wikipedia, it is said that much more support to the project in early 

    phases (1987) was given in France, with its long tradition of  infrastructure investment. In contrast to the situation in UK, the project garnered widespread approval. In April 1987 the French National Assembly gave unanimous support (http://en.wikipedia.org/wiki/Channel_Tunnel). 

    F4 

    The Compensation of  local 

    community above  0,1% of  the 

    total budget

     

    It is 0, if  the following can be considered as the compensation for local community: The RLCI was set up as an independent charity to support local communities, landowners and organizations to realize their ideas for environmental enhancement along the CTRL route. The Initiative received initial funding of  £2m from the CTRL developers. 

    F5 

    The density of  population of  the 

    province is below the national 

    average 

    0 Both London and region of  South East have the population density above the national average. 

    STSM Report 

    G1  EXTRA LINES 

    AVAILABLE 

    The project is nuclear 0 

    G2 SPE 

  • 8/18/2019 Final STSM LondonUCL Report

    83/97

    NEW ATTRIBUTE PROPOSED: 

    1. 

    BOT: 1 (yes), 0 (no) 

    IMPORTANT COMMENTS ON EXISTING ATTRIBUTES DEFINITION: 

    1. 

    Regarding INTERNAL STAKEHOLDERS attributes: Instead of  levels: 

     

    Client 

     

    EPC 

      First Tier Contractors 

    More general level names are proposed, which would be adequate also for BOT model: 

      The first level (Client) 

      The second level (EPC or Concessionaire, depends on the contract model) 

      First Tier Contractors (contractors, or design and construction companies, depends on the contract model) 

    2. 

    Regarding the attributes: support of  the central/local Government: 

     

    What if  the attitude changed over time, as in this project ? (Kent Community Council at one point refused all the proposed 

    routes alternatives. How to consider this ? Is this no support from local government ? And the central Government also gave up 

    from project at one point.)  – Giorgio answered it should be considered as no support from local Government. 

    NO DATA IN OMEGA MATERIAL ABOUT: 

     

    Project Management 

     

    National trust to the authorities 

      Some aspects of  stakeholders, both internal and external (such as Siemens and Greenpeace) 

    STSM Report 

  • 8/18/2019 Final STSM LondonUCL Report

    84/97

  • 8/18/2019 Final STSM LondonUCL Report

    85/97

    STSM Report 

    It was not foreign, but it was international consortium. The two governments signed an agreement in 1991, committing them 

    both to form state‐owned stock companies. The companies would 

  • 8/18/2019 Final STSM LondonUCL Report

    86/97

    A1 

    2.1 

    Stakeholders ‐

    Internal 

    Project has a foreign EPC 

    company 

    form a consortium responsible for the financing, design, construction and operation of  the link, with loans raised on the international finance market, repaid by revenues from user fees and guaranteed by the two states. The Oresundbro Consortium (AS Oresund, Denmark and Svedab AB, Sweden) signed contracts with three consortia: Oresund Tunnel Contractors; Oresund Marine Joint Venture, for construction of  the artificial island and dredging; and Sundlink Contractors, for bridges. Consortium ownership was split equally between the Swedish and Danish states. 

    A2 

    Siemens is involved as a 

    contractor in the project 

    No mentioning of  Siemens in Omega material.  But, Siemens is stated as a supplier (not a Contractor) of  some equipment (file:///C:/Users/user/Downloads/342_acee490f4574a9f696014a385

    5e32709.pdf) on the Web. 

    A3 

    THE CLIENT IS ALSO THE EPC OR 

    MAIN CONTRACTOR 

    A4 

    The EPC has a clear goal 1? 

    No data about this in Omega material. The EPC is the Consortium, which is an SPE. However, on the web, it is written that the company's main purpose is to run an efficient and safe link between Denmark and Sweden and to create a sustainable business. (http://uk.oresundsbron.com/page/1103) 

    The project is mono Cultural 

    (SEE BELOW) 

    A5 

    A) 

    CLIENT 

    AND 

    EPC 

    HAVE 

    THE 

    SAME NATIONALITY (N/A IF 

    THEY ARE THE SAME) 

    N/A 

    A6 

    B) CLIENT AND EPC AND ALL 

    THE IMPORTANT FIRST TIER 

    CONTRACTOR HAVE THE SAME 

    NATIONALITY 

    The OC was responsible for negotiations with the contractors. After negotiations held from July to November 1995, deals were signed with three consortia. The Öresund Tunnel Contractors, a consortium consisting of  NCC AB (SE), Dumez‐GTM SA (F), John Laing Ltd (UK), E. 

  • 8/18/2019 Final STSM LondonUCL Report

    87/97

    STSM Report 

    completion. Even though other issues such as the impact on traffic volumes and land use initially were seen as important, the main issue has been the question of  how the structure would affect the water flow between the Baltic and the North Sea. 

    N d t b t l l t t i O t i l b t th i t

  • 8/18/2019 Final STSM LondonUCL Report

    88/97

    A11 

    THERE WAS PUBLIC 

    ACCEPTABILTY TO THE PROJECT 

    AT LOCAL LEVEL (NO PROTEST) 

    No data about local protests in Omega material, but the impact on the nearby ecologically sensitive island of  Saltholm was also a matter of  concern. It was deemed that the construction work would cause serious disturbance to 24 nesting bird populations. The existing seal population of  the island was deemed to be in danger of  being permanently removed from the area. on the web (http://gurukul.ucc.american.edu/ted/oresund.htm) it is 

    written: 

    After the Water Court gave its approval,the Swedish Environmental Minister, Olof  Johanssen, opposed this project so strongly that he resigned his position. (13) Even with the approval of  the Water Court, Johanssen felt that the delicate balance of  the Baltic Sea would be upset. (14) He was concerned about the possible effects of  the bridge on the wild birds inhabiting an island in the sound  and the effects of  a decrease in water flow on the fish and  other living 

    organisms in the sea.  Environmental groups in  Sweden felt the same way. Most environmentalists and biologists in Sweden are still opposed to building the crossing.  As recently as July and September of  1996, these groups have staged protests against this project, still feeling that water flows and species within the Oresund Sound will be disturbed. 

    A12 

    Environmental activists and 

    regulators have

     been

     engaged

     

    ex‐ante, not ex post (N/A never 

    engaged or don't know) 

    The project remained controversial in Sweden, particularly as the 

    environmental impact assessment took place only after the agreement to build the link was signed. 

    A13 

    LOCAL LEVEL PROTESTS 

    OCCURED DURING 

    CONSTRUCTION OR 

    0 Environmentalist groups from both Denmark and Sweden have opposed this project from the beginning. (http://gurukul.ucc.american.edu/ted/oresund.htm) 

    STSM Report 

    COMMISSIONING NOT DURING 

    PLANNING (N/A IF NO PROTEST 

    AT ALL) 

    The project has a strong 

  • 8/18/2019 Final STSM LondonUCL Report

    89/97

    5.1 Project 

    Environment ‐

    Legal 

    regulation system as evidenced 

    by: 

    B1 

    a) The authority stopped the project or similar projects in the same country 

    The Swedish National Board for Environmental Protection refused planning permission, but its competence was questioned and the government referred to the Water Rights Court instead. The WRC 

    granted permission, on condition that the project had no impact on water flow: this necessitated a redesign and further approvals. 

    This 

    became 

    known 

    as 

    „the 

    zero 

    impact 

    solution‟

    and 

    as 

    result 

    the 

    OC had to adjust the construction plans and submit these to the WRC again. 

    B2 

    b) The authority fined the EPC (main contractor) or one of  the internal stakeholders in the project 

    No information that this occurred. 

    B3 

    c) ACTIONS FROM THE AUTHORITY POSTPONED THE 

    FINAL COMPLETION OF THE 

    PROJECT 

    It is 1, although I am not sure about the difference between this 

    attribute and

     the

     one

     before

     the

     previous

     (a).

     

    The Swedish National Board for Environmental Protection refuse