Final Project Report
Document information
Project Title Consolidation of Operational Concept Definition and Validation
Project Number 05.02
Project Manager NATS
Deliverable Name Final Project Report
Deliverable ID D01
Edition 01.00.00
Template Version 03.00.04
Task contributors
NATS.
Abstract
Project 05.02 (P05.02) was a transversal project which ran throughout the course of the SESAR programme from 2010 to 2016. P05.02 had responsibility for consolidating the concept development across SESAR Work Package 5 – Terminal Manoeuvring Area (TMA), and for providing guidance for validation strategy. The report identifies the key deliverables - the Detailed Operational Description documents for TMA and Validation Strategies for TMA.
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
2 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
Authoring & Approval
Prepared By - Authors of the document.
Name & Company Position & Title Date
Richard Pugh / NATS P05.02 Manager (former) 09/12/2015
Siân Andrews / NATS P05.02 Manager 28/06/2016
Reviewed By - Reviewers internal to the project.
Name & Company Position & Title Date
Laurence Rognin/ ECTL P05.02 Project Member 11/07/2016
Mike Whitmarsh / NATS P05.02 Project Member 05/07/2016
Gilda Bruno / ENAV P05.02 Project Member 12/07/2016
Jorge Valle / INDRA P05.02 Project Member 12/07/2016
Reviewed By - Other SESAR projects, Airspace Users, staff association, military, Industrial Support, other organisations.
Name & Company Position & Title Date
John Godsell / NATS WP5 Lead 25/07/2016
Charlotte Chambelin / DSNA P04.02 Manager 18/07/2016
Alan Groskreutz / ENAIRE P06.02 Manager No response received
Etienne De Muelenaere / EUROCONTROL P07.02 Manager No response received
Steve Morton / EUROCONTROL P10.01.07 Manager 14/09/2016
Didier Delibes / AIRBUS P09.49 Manager 14/09/2016
Approved for submission to the SJU By - Representatives of the company involved in the project.
Name & Company Position & Title Date
Siân Andrews / NATS P05.02 Manager 25/07/2016
Bruno Favennec / EUROCONTROL P05.02 Project Member 26/07/2016
Gilda Bruno / ENAV P05.02 Project Member 25/07/2016
Jorge Valle / INDRA P05.02 Project Member 22/07/2016
Janet Firminger / LEONARDO P05.02 Member (former) 21/07/2016
Rejected By - Representatives of the company involved in the project.
Name & Company Position & Title Date
None
Rational for rejection
None.
Document History
Edition Date Status Author Justification
00.00.01 19/05/2015 Draft Richard Pugh New Document
00.00.02
09/12/2015 Revised Draft Richard Pugh Updated Template
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
3 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
00.00.03 28/06/2016 Revised Draft Siân Andrews Updated Template
00.01.00 26/07/2016 Final version Siân Andrews This version includes review comments and approvals.
00.01.01 22/09/2016 Final version Siân Andrews Updated in response to SJU assessment
01.00.00 27/09/2016 Final Version Siân Andrews Updated in response to SJU second assessment
Intellectual Property Rights (foreground)
This deliverable consists of SJU foreground.
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
4 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
Acronyms
Acronym Definition
2D 2 Dimensional
AMAN Arrival Manager
ASAS Airborne Separation Assistance System
ATM Air Traffic Management
CCO Continuous Climb Operations
CDO Continuous Descent Operations
CONOPS Concept of Operations Document
CTA Controlled Time of Arrival
CTO Controlled Time Over
CWP Controller Working Position
DOD Detailed Operational Description
DS Dataset
ENB Enabler
FATO Final Approach and Take Off area
GLS GNSS Landing System
GNSS Global Navigation Satellite System
ILS Instrument Landing System
LPV Localiser Performance with Vertical Guidance
OFA Operational Focus Area
OI Operational Improvement
P Project
PCP Pilot Common Project
R&D Research and Development
RBT/RMT Reference Business Trajectory/Reference Mission Trajectory
RNP Required Navigation Performance
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
5 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
SBT/SMT Shared Business Trajectory/Shared Mission Trajectory
SE System Engineering
SJU SESAR Joint Undertaking
TMA Terminal Manoeuvring Area
V&V Roadmap Verification and Validation Roadmap
VFR Visual Flight Rules
VALS Validation Strategy
WP Work Package
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
6 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
1 Project Overview
P05.02 was an operational project responsible for the Operational Concept of the TMA (Terminal Manoeuvring Area); ensuring the coherency and consistency of the various contributions of operational projects involved with TMA aspects and also those addressing other domains (En-Route, Airport and Network) and the overall concept. This objective was achieved through the delivery of the Detailed Operational Description (DOD) documents for the TMA.
P05.02 was also responsible for the coordination and consolidation of the TMA Concept validation, which was achieved through the delivery of Validation Strategy (VALS) documents for the TMA.
1.1 Project progress and contribution to the Master Plan
The principal objectives of the project have been to develop the Concept of Operation for TMA operations to ensure coherency and consistency with the higher-level SESAR Concept of Operations and with the detailed concepts being developed by operational projects for the TMA; and to support concept validation of TMA activities. As such, P05.02 has performed a role to ensure that the progress of concept development across TMA projects was consistent with the Air Traffic Management (ATM) Masterplan. Specific Objectives were to:
Develop and maintain the TMA concept to the necessary level of maturity required to support the validation activities.
Develop a consistent approach and set of high-level requirements for TMA Validation Activities.
Manage TMA concept updates through the Masterplan change control process; ensuring co-ordination took place with WP-B (Target concept projects) and other WPs as appropriate.
Initiate stakeholder engagement in respect of the TMA Concept and assist the SJU as necessary in any related Stakeholder buy-in activities.
Review the outputs from TMA projects to ensure consistency between projects and to ensure alignment with the SESAR programme required methodology and processes.
Act as the lead reviewer for ATM operational aspects related to the TMA in the SESAR Programme Release process (System Engineering Review process).
During 2015/2016 P05.02 took the lead in producing a Transition Validation Strategy for the SESAR 2020 programme, coordinating and consolidating inputs from the other equivalent projects covering the En Route, Airport and Network domains.
P05.02 also supported project B4.2 (Project responsible for developing the Concept of Operations) to define a Transition Concept of Operations for the SESAR2020 programme.
Throughout the SESAR programme P05.02 has had a formal role in the ATM Masterplan change control process as the lead reviewer for all proposed changes to the ATM Masterplan concerning TMA operations i.e. all change requests concerning Operational Improvements linked to TMA have been coordinated by P05.02. P05.02 also coordinated with the system federating project members to ensure the correct coverage of enablers against OIs. This included the updates for Dataset (DS) DS9, DS10, DS11, DS12, DS13, DS14, DS15 and DS16. P05.02 has been instrumental in developing the Masterplan update process and applying lessons learned.
P05.02 has worked together with the other equivalent projects which cover the En Route, Airport and Network domains, management projects in other ATM domain areas and with the SJU in order to develop improvements to the programme. We have participated in monthly coordination webexes with our counterpart projects and quarterly face-to-face meetings with B4.2, as well as providing expertise to other activities across the programme when required.
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
7 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
The TMA Operational Improvements (OIs) which were developed during the SESAR programme under the high level responsibility of the TMA Global Coordination and Management project were grouped into four Operational Focus Areas (OFAs). P05.02 contributed to the creation of Operational Focus Areas to coordinate the activities of operational projects, systems project and other projects around specific Operational Improvements. P05.02 had a role covering four OFAs and one Enabling project, and has had constant liaison and provided significant support and guidance to these OFAs and associated primary projects. The project has ensured P05.02 attendance at OFA meetings and was involved in the review of documents produced by primary projects/OFAs, in addition to those which have formed part of the formal Release process.
As part of the P05.02 role to ensure consistency and alignment with SESAR process requirements it has been the operational reviewer for System Engineering (SE) reviews, which were the yearly review processes run by the programme to determine and assess the maturity of the SESAR Solutions. P05.02 has supported the initial planning reviews (SE#1) and final maturity assessment (SE#3) reviews for all SESAR Releases for the OFAs under the responsibility of P05.02. As part of this, the project has reviewed all programme deliverables contributing to SESAR Solutions for the TMA.
The SESAR Solutions under responsibility of P05.02 Operational Focus Areas are listed below:
Optimised 2D-3D Routes
Enhanced Terminal Airspace for RNP-based Operations
Enhanced terminal operations with LPV procedures
Enhanced terminal operations with automatic RNP transition to ILS/GLS
Optimised Route Network using Advanced RNP
Point Merge in complex TMA
Continuous Descent Operations (CDO)
Enhanced Rotorcraft and GA operations in the TMA
Dynamic and Enhanced Routes and Airspace
ASAS Spacing
ASAS Spacing applications Remain behind and Merge behind
Ground-Based Separation in TMA
High Productivity Controller Team Organisation
Collaborative Control
Improved Performance in the Provision of Separation
Enhanced Arrival and Departure Management
Extended Arrival Management (AMAN) horizon
Controlled Time of Arrival (CTA) in Medium density/medium complexity environment
Arrival Management into Multiple Airports
AMAN and Point Merge
CWP for En-route & TMA
Each of the Solutions above is made up of one or more Operational Improvements. In the ATM Masterplan (Dataset 15) the Operational Improvements are also grouped by Steps based on the expected evolution of the overall ATM Concept of Operations. Step 1: Time Based Operations - this was the building block for the implementation of the SESAR concept.
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
8 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
Step 2: Trajectory Based Operations - this builds upon the time based operations using more accurate and complete data concerning the aircraft trajectories and increased sharing of this information. As the lead reviewer for ATM operational aspects related to the TMA domain in the SESAR yearly System Engineering Review process, P05.02 Operational experts contributed to the final assessment of V3 maturity of the proposed solutions and the associated Operational Improvements, evaluating readiness to enter the industrialisation phase, according to the European Operational Concept Validation Methodology (E-OCVM) as described in Figure 1.
Figure 1 E-OCVM Maturity Levels within SESAR
The SESAR Solutions and OIs under the responsibility of P05.02 (and addressed by primary projects) are listed in the following table, including the maturity level throughout the life of the project:
SESAR Solution OI Code OI Name Maturity at project start
Maturity at project end1
Enhanced Rotorcraft and GA operations in the TMA
AOM-0104 Enhanced Rotorcraft Operations at VFR FATOs with specific Point-in-Space RNP procedures using satellite augmentation
V2 V3
Optimised Route Network using Advanced RNP
AOM-0404 Optimised Route Network using Advanced RNP
V1 V3
Enhanced Terminal Airspace for RNP-based Operations
AOM-0603 Enhanced Terminal Airspace for RNP-based Operations
V1 V3
Enhanced terminal operations with automatic RNP transition to ILS/GLS
AOM-0605 Enhanced terminal operations with automatic RNP transition to ILS/GLS/LPV
V1 V3
Enhanced terminal operations with LPV procedures
AOM-0605 Enhanced terminal operations with automatic RNP transition to ILS/GLS/LPV
V1 V3
1 Where the maturity of an OI does not show progress between project start and project end, this is due to the fact that it is a successor OI which will be carried forward to SESAR 2020 and the maturity of the predecessor OI has been the focus in SESAR 1.
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
9 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
Continuous Descent Operations (CDO)
AOM-0702-A
Continuous Descent Operations (CDO) V2 V3
Dynamic and Enhanced Routes and Airspace
AOM-0702-B
Advanced Continuous Descent Operations
V1 V1
AOM-0705-A2
Continuous Climb Operations (CCO)
AOM-0705-B
Advanced Continuous Climb Operations
AOM-0806 Dynamic Management of Terminal Airspace Routes and Transition
Improved Performance in the Provision of separation
CM-0206 Conflict Detection and Resolution in the TMA using trajectory data
V0 V1
CM-0208-A Automated Ground Based Flight Conformance Monitoring in the TMA in Step 1
CM-0606 Separation Management in the TMA using Pre-defined Routes with 2D RNP Specifications
Advanced Separation Management
CM-0208-B Automated Ground Based Flight Conformance and Intent Monitoring in the TMA
V1 V1
CM-0408 Enhanced Conflict Detection and Resolution in the TMA
CM-0608 Separation Management in the TMA using RBTs with 2D RNP Specifications
High Productivity Controller Team Organisation CM-0304
Sector Team Operations Adapted to New Responsibilities in the TMA, 1 Planning to several Tactical Controllers team structure
V1 Partial V2
Collaborative Control
CM-0305
Sector Team Operations Adapted to New Responsibilities and Operating Procedures involving reduced Coordination in the TMA
V1 V1/Partial V2
Controlled Time of Arrival (CTA) in Medium density/medium complexity environment
TS-0103 Controlled Time of Arrival (CTA) in medium density/complexity environment
V1 V3
ASAS Spacing applications Remain behind and Merge behind
TS-0105-A ASAS Spacing – target direct to merge point (Speed/simple geometry)
V1 V3 not achieved
Airborne Spacing Flight Deck Interval Management
TS-0108 ASAS Spacing – target not direct to a merge point (Speed and Lateral/more complex geometry)
V1 V1
Extended Arrival Management with overlapping AMAN operations and
TS-0109 Controlled Time of Arrival (CTA) in high density/complexity environment
V1 V1
2 AOM-0705-A has been deleted in DS16 and the progress made will be captured in AOM-0705-B, which is considered to encompass AOM-0705-A.
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
10 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
interaction with DCB and CTA TS-0305-B
Arrival Management Extended to En Route Airspace - overlapping AMAN operations
V1 Partial V2
Use of Arrival and Departure Management Information for Traffic Optimisation within the TMA
TS-0302-A Departure Management Information from Multiple Airports
V1
Partial V2
TS-0302-B Departure Management from Multiple Airports
TS-0307 Integrated Arrival Departure Management for traffic optimisation within the TMA Airspace
Arrival Management into Multiple Airports
TS-0303 Arrival Management into Multiple Airports V2 V3
Extended Arrival Management (AMAN horizon)
TS-0305-A Arrival Management Extended to En Route Airspace - single TMA
V2 V3
1.2 Project achievements
Detailed Operational Descriptions
Project 5.02 has delivered a series of Detailed Operational Description Documents (DODs) in two separate threads:
Step 1 DOD (Time Based Operations)
Step 2 DOD (Trajectory Based Operations)
For each thread the DOD has been iteratively developed to maintain consistency with the ATM Masterplan and alignment with the SESAR Concept of Operations. It has been updated also to reflect the outcomes and recommendations from validation activities within the TMA domain. The DODs have therefore been used as both an input to primary project and as a consolidation of primary project results3.
P05.02 contributed to the Transition Concept of Operations for the SESAR 2020 programme, which was delivered by project B4.2 (Project responsible for developing the Concept of Operations).
Validation Strategies
Project 5.02 has also delivered a series of Validation Strategy (VALS) documents.
Validation Strategy for Step 1
Validation Strategy for Step 2
Transition Validation Strategy for SESAR 2020
These VALS documents establish high-level validation objectives to be validated by primary operational projects.
P05.02 developed the process for capturing Integrated Validation needs. This approach to Integrated Validation was followed by all the equivalent projects across the ATM domains. P05.02 has supported projects with organising major Integrated Validation exercises through review of plans, provision of high level scenario descriptions and providing a lessons learned paper. Such exercises have been particularly challenging to manage - the approach developed provides a basis for future European collaborative validation exercises.
European ATM Architecture (EATMA)
Modelling Activities: For each Operational Focus Area under the responsibility of P05.02, the project has coordinated the development of operational process models, which now form part of the
3 The latest versions of the DODs were produced in Q2 2015; therefore no exercise results after June 2015 have been incorporated into the final version of the DODs.
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
11 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
European ATM Architecture (EATMA). This has ensured that each of the concepts developed within the TMA domain was defined in EATMA using a consistent approach. The process models are included in the Detailed Operational Description Deliverables but are formally maintained within EATMA (online portal). The operational process models were subsequently used as the basis of system modelling via sequence diagrams in the Technical Architecture Description document.
Contribution to the PCP
P05.02 has contributed to the PCP (Pilot Common Project) through supporting the following solutions to reach V3 maturity:
Enhanced Terminal Airspace for RNP-based Operations
Enhanced terminal operations with LPV procedures
Enhanced terminal operations with automatic RNP transition to ILS/GLS
Arrival Management Extended to En Route Airspace - single TMA
1.3 Project Deliverables The following table presents the relevant deliverables that have been produced by the project.
Reference Title Description
D84 Step 1 DOD Report - Fifth update This document is the WP5 TMA Step 1 Detailed Operational Description. It details and refines the TMA Operational Concept focusing on Step 1 'Time Based Operations'. It is aligned with Integrated Roadmap Dataset 13. 'Time Based Operations' is a building block for the implementation of the SESAR concept and is focused on flight efficiency, predictability and environment.
M319 DOD Step 2 Iteration 3 This document is the WP5 TMA Step 2 Detailed Operational Description. It details and refines the TMA Operational Concept focusing on Step 2 'Trajectory Based Operations'. It is aligned with Integrated Roadmap Dataset 13. 'Trajectory Based Operations' are focused on safety, flight efficiency, predictability, environmental sustainability, cost effectiveness and capacity. This is a milestone version of the document and forms the final detailed operational concept for TMA to step 2, which provided input to the SESAR 2020 Transition Conops.
D85 TMA Validation Strategy for Concept Step 1 - update 2014
The document guides WP5 OFA coordinators and primary projects in their validation activities, ensuring that all processes are kept in line with the overarching SESAR WP methodology and concept. It provides a detailed description of what should be conducted in terms of validation activities to prove fitness for purpose of Step 1 TMA concept elements. The TMA concept elements were mapped to OFA and OIs in order to determine the TMA validation requirements for Step 1, and are aligned with Integrated Roadmap Dataset 13. The comparison between the validation strategy and the projects validation activities enables inconsistencies
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
12 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
to be detected, both in terms of gaps and overlaps.
M323 TMA Validation Strategy for Concept Step 2 - update 2014
The document guides WP5 Primary Projects and potentially System Projects in their Step 2 validation activities, ensuring that all processes are kept in line with the overarching SESAR WP methodology and concept. It provides a detailed description of what should be conducted in terms of validation activities to prove fitness for purpose of Step 2 TMA concept elements. It was based on a top-down approach completed with some bottom-up information based on inputs as known at the end of October 2014 (e.g. ATM Master Plan, Release Strategy, V&V Roadmap, OFA material). This is a milestone version of the document and forms the final Validation Strategy for TMA to step 2, which provided input to the SESAR 2020 Transition Validation Strategy. It is aligned with Integrated Roadmap Dataset 13.
D109 Transition Validation Strategy for SESAR 2020
This document has been produced together with the equivalent projects covering the En Route, Airport and Network domains to describe why and how each SESAR 2020 Solution needs to be validated. It is structured around SESAR 2020 key features and documents the validation objectives and scenarios for each SESAR 2020 Solution and is aligned with Integrated Roadmap Dataset 15.
1.4 Contribution to Standardisation
P05.02 has not directly contributed to any standardisation activity (e.g. in EUROCONTROL, EUROCAE, ICAO groups) because these activities were the responsibility of lower level Research and Development projects. P05.02 members did however contribute actively in the discussion of different topics along the SESAR programme. E.g. The transition from SBT/SMT to RBT/RMT, the trajectory management concept, use of multiple CTOs, etc. The result of the discussions generated around those topics was used to provide a common and agreed perspective on the concepts behind those topics. It allowed the DODs of all ATM domains and the B4.2 CONOPS to be aligned and coherent among them.
1.5 Project Conclusion and Recommendations
Conclusion
P05.02 has successfully completed its project objectives and has made a significant contribution to the success of the programme, primarily through the production and maintenance of the DOD and VALS documents for the TMA. These key documents provided requirements and objectives that were used to ensure the consistency and alignment of the work of the operational projects, which were managing validations. The role of P05.02 within the SESAR programme has been the primary mechanism for ensuring the consistency of TMA concept development:
Across projects within the TMA domain
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
13 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
With the overall SESAR Concept of Operations and other operational WPs
With SESAR programme process and requirements
P05.02 has highlighted the importance of using the Integrated Roadmap to ensure consistency between the high level top-down concept and the detailed primary project bottom-up developments.
Recommendations
The final deliverables from P05.02 should provide the starting point for TMA research activities to be conducted in the SESAR 2020 programme. These address both the envisaged scope of R&D activities related to the TMA (Contribution to the SESAR 2020 Transition CONOPS), and the initial Transition Validation Strategy for SESAR 2020.
These documents have been produced taking into consideration the outputs from the Release 1 to 4 Review processes and expected assumptions from the Release 5 review (which was conducted after the production of the Transition documents). Therefore it is recommended that the SESAR 2020 programme also considers the output and recommendations from the Release 5 Review, which describe the final maturity achieved for the concepts within the TMA domain and are the basis for continuing research into these and related concepts.
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
14 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
2 References
[1] SESAR Programme Management Plan, Edition 03.00.01
[2] European ATM Master Plan
[3] Multilateral Framework Agreement (“MFA”) signed between the SJU, EUROCONTROL and its 15 selected members on August 11, 2009, amended on 14 June 2010, 19 October 2010 and 2 July 2012
[4] B4.2, Transition ConOps SESAR 2020 - Consolidated deliverable with contribution from Operational Federating Projects, D106, 01.01.00, 30/06/16
[5] P05.02, Step 1 DOD Report available - First Release Milestone, D100, 00.00.01, 31/01/11
[6] P05.02, Step 1 DOD Report - Second Release Milestone, D101, 00.01.00, 13/10/11
[7] P05.02, Step 1 DOD Report - Fifth update, D84, 00.01.01, 30/04/15
[8] P05.02, Initial WP Time Based Validation Strategy Report available, D51, 00.00.05, 10/12/12
[9] P05.02, TMA Validation Strategy for Concept Step 1 - update 2014, D85, 00.00.04, 14/07/15
[10] P05.02, Early Technical Assessment for Ground System Impact (Initial Draft), D64
[11] P05.02, Transition Validation Strategy for SESAR 2020, D109, 01.00.00, 30/06/16
[12] P05.02, DOD Step 2 Iteration 3, M319, 00.01.01, 09/06/15
[13] P05.02, TMA Validation Strategy for Concept Step 2 - update 2014, M323, 00.00.03, 14/07/15
[14] B04.02 SESAR Concept of Operations Step 1 Final Edition, D124, 02.02.00, 30/07/2015
[15] B04.02 SESAR Concept of Operations Step 2 edition 2014, D105, 01.01.00, 21/12/2014
[16] E-OCVM - European Operational Concept Validation Methodology, version 3.0, February 2010
[17] P10.01.07, Technical Architecture Description - Cycle 2015, D120, 00.01.00, 03/02/16
[18] B.01, Integrated Roadmap - DS15 Release Note, D83, 00.01.00, 02/12/15
Project Number 05.02 Edition 01.00.00 D01- Final Project Report
15 of 15
©SESAR JOINT UNDERTAKING, 2015. Created by NATS;for the SESAR Joint Undertaking within the frame of the SESAR Programme co-financed by the EU and EUROCONTROL. Reprint with approval of publisher and the source properly acknowledged
-END OF DOCUMENT-