final ppt
TRANSCRIPT
NARMADA BACHAO ANDOLANGroup 5:
Roll No. 46 to 56
INTRODUCTION 1961: Inauguration of Narmada Valley development project
1978: Government seeks World Bank’s assistance
Creation of 30 dams, 135 medium dams and 3000 small dams providing
water to almost 40 million people over 6 million hectares of land and
hydroelectric power for the region
Sardar Sarovar Project (“SSP”):
Irrigate 1.8 million hectares of land in Gujarat and 73,000 hectares of land in
Rajasthan + provision of water to 8,000 villages and 135 urban centers
Costs:
-Displacement of ten of thousands of individuals and considerable
environmental damage
-Submerge 37,000 hectares of land in the three states
1985: World Bank agrees to finance SSP
THE RESPONSE…. Local opponents, environmental activists, and professionals from the
academic, scientific, and cultural worlds formed an NGO
Late 1980s: Formation of Narmada Bachao Andolan (“NBA”)
1991: Creation of a Bank commission to independently review the project
Review’s conclusion: “Unless a project can be carried out in accordance
with existing norms of human rights—norms espoused and endorsed by the
Bank and many borrower countries—the project ought not to proceed”
1993: Creation of the World Bank Inspection Panel
NARMADA TRIBUNAL NARMADA WATER DISPUTES TRIBUNAL
Formed : On 6 Oct 1969As per India’s Interstate Water Disputes Act of
1956Under Chairman Justice V. Ramaswami
To Resolve:Water Sharing dispute.Rehab & Resettlement for those affected by Dams
– Indigenous people (Adivasis)
Contains Mandated Clauses such as:Land for Land (e.g. Gujrat. 5 acres of irrigable
land.)
NARMADA TRIBUNAL (CONTD.)NARMADA WATER DISPUTES TRIBUNAL
Shortcomings:Compensation to Legal Land Owners only.Focused on Interstate disputes not on Affected
CommunitiesPolitical deals limits alternatives to achieve
Objectives.Lacked appeal process by Ordinary courtNot enough land available for Redistribution.Settlers return to homes already submerged!
World Bank’s Involvement in the Project
• World Bank Stepped in after Narmada Tribunal’s final order.
• Bank Staffers worked in close coordination with Indian Officials to reconfigure the criticalities of project.
• Ist stage Project Preparation – 1973-1985 –Bank Ignored shortcomings in the approval process
• Transnationalization by Bank at multiple level
Indicated International approvals by including foreign actors.
Internationalized resistance to project
Bank’s international policy provided standard to judge the project performance
CONFLICT BETWEEN WORLD BANK’S POLICY & ITS SUPPORT OF DAM Policies developed in respect to establishing
environmental & human rights guidelines. Requisites for Bank’s policies on involuntary
settlement: Finalize resettlement plans prior to the loan’s
approval Credit agreements with the Indian states required
resettlement plans that conform to these policies No plans produced even after 6 years of loan
approval; No deadlines enforced by World Bank
Ecological consequences of the Sardar Sarovar Project were not addressed.
1980General
Resettlement Policy
1982Resettlememt
policy adressing tribal community
members
1990Involuntary settlement
1991Resettlement of
indigenous population
NARMADA BACHAO ANDOLAN (NBA) BEGINS…
A social movement protesting against the
implementation of the Sardar Sarovar Project(SSP)
Chhatra Yuva Sangharsh Vahini - youth protest
group in Gujarat
Narmada Ghati Navnirman Samiti and
Dharangrastha Samiti merged to form NBA in 1989
Focussed on transparency and accountability
Government has ignored the stakeholders while
making their decision
NBA’S METHODS AND LEADERSHIP
Innovative strategies of resistance that operated simultaneously at the grassroots, national, and international level
Originally employed ‘‘Gandhian methods’’ and later announced a ‘‘noncooperation movement’’
Leadership of environmental champions like Medha Patkar – Visionary leader
NBA’s struggle against the Maheshwar Dam in MP- Narmada Shakti Dal
Social activist Baba Amte provided moral leadership - Cry O Beloved Narmada in 1989
DIRECT ACTIONS• Anti Dam NBA Rally by Baba Amte • At Harshud, involving 60,000
people
Sept 1989
• Massive NBA 5 day Dharna• Forced PM to reconsider the
projectMay 1990
• Dharna unto death, by Amte & Patkar
• NBA called off after 21daysJan 1991
• Readiness for Jal Samarpan in Manibeli
• Forced the govt. to review the project
Mid 1992
INTERNATIONAL INTERVENTIONS AND COALITION BUILDING
Multi-pronged strategy - Lori Udall, Environmental Defence Fund
Megha Patkar met with World Bank
Narmada International Action Committee—lobbied in several investing countries
International NGO ‘Friends of the Earth’ (Japanese branch) field visit - withdrawal of Japan’s Fund
June 1992 report by Human Rights Watch (at the time of The Earth Summit in Rio de Janeiro)
The Environmental Defence Fund and the Bank Information Centre(both U.S.-based NGOs) led the formation of the Narmada International Human Rights Panel
Support of forty-two environmental and human rights NGOs representing sixteen countries.
THE WORLD BANK WITHDRAWS Morse Commission to re-examine the Project – June’91
to assess steps taken to resettle those who are affected
to assess the measures aimed at diminishing the project’s
environmental impact
Difficult situation for World Bank
Donor countries were unhappy with the developing image of the
Bank as a human rights violator
6 months to comply with certain environmental and rehabilitative
benchmarks.
The government of India announced cancelling the remaining $170
million Bank loan - what many regarded as an admission that the
government could not meet the new ‘‘benchmark
BROADER IMPACT OF NBA ON WORLD BANK
Forced WB to acknowledge Indian Govt.’s disregard for consequences.
NBA – An example before the world Social and Environmental impact of Bank projects Increasing awareness among middle class and rural
people An important ‘landmark’ in struggle for
‘accountability’ Independent commission to review bank funded projects Quasi-Independent panel to hear complaints about
violations Bank’s procedures opened for public, guidelines
rewritten and current projects re-examined. Environmental concerns – Into mainstream NGOs -Partners in development
THE WORLD BANK INSPECTION PANEL Setup in September 1993 acting as a
grievances redressal committee. To address the mismanagement and poor
governance, which galvanised World bank’s accountability failures.
Bank did not impose 78% of its negotiated loan conditions and one-third of the banks projects were unsatisfactory.
NGO’s and member countries who were sizeable lenders to bank raised criticisms.
Willi Wapenhans critiqued bank’s sweeping culture of approval.
THE WORLD BANK INSPECTION PANEL
Lack of independent oversight. Panel’s mandate was limited to examination
of the Bank’s compliance with its operational guidelines.
Less focus on the human right concerns. Narrow focus on procedural issues. 11 out of the 28 claims resulted in the positive
which includes:- Compensation for claimants Release of project information Improvement in resettlement packages for affected
people. Project suspension, cancellation or redesign Cessation of evictions.
NBA DEVELOPMENTS POST–BANK WITHDRAWAL
Developments After Bank’s Withdrawal
Withdrawal greatly reduced the international dimension
of the Narmada struggle.
NBA decided to pursue an additional avenue for change
—appeal to the Supreme Court of India.
Government’s continued construction raised the stakes
of the struggle for both sides - more and more villages
faced submergence, and the government’s commitment
to the Narmada Project deepened as the project
progressed
THE NBA AND THE SUPREME COURT NBA approached Supreme Court in 1994 The NBA’s lawyers began to push three novel legal
arguments: Project was an unconstitutional taking It violated the equal protection clause of the Indian
Constitution Government had infringed on their right to reside and
settle in any part of India.o In 1995 Supreme Court ordered a stay on further
construction but the courts orders were disregarded until the NBA march on Delhi in late 1995
o In 1999, Indian Supreme Court authorized construction to increase height of Dam to 85 meters
o Since, 2000 the construction happened uninterrupted under the surveillance of GRA ( Grievance Redressal Authorities) in each of the party states
THE PROJECT COMPLETION - ITS MERITS
Project got completed on December 31,2006
It is one of the largest water resources
project of India
Irrigation - 1.905 million Ha (1.8 million Ha. in
Gujarat benefitting 1 million farmers)
Drinking Water - 9633 villages and 131 towns
(29 million people)
THE PROJECT AND ITS DEMERITS
Unofficial estimate of around 320,000 people
got displaced
Their livelihood got deprived
Estimated Cost - Rs. 392.4 billion (8 billion
USD)
Thousands of acres of forest land destroyed
Acute water crisis in Saurashtra, Kutch and
North Gujarat even now
CONCLUSION
“NBA became symbolic of a global struggle for environmental and social justice, and a hope for people’s movements all over the world that are fighting for just, equitable,
and participatory development.”- NBA Partner