final 12 01 community mtg phase ii presentation

24
December 1, 2014 VTA’s BART Silicon Valley Extension BART Phase II Project Update

Upload: scvta

Post on 14-Jul-2015

1.780 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

Page 1: Final 12 01 community mtg  phase ii presentation

December 1, 2014

VTA’s BART Silicon Valley Extension

BART Phase II Project Update

Page 2: Final 12 01 community mtg  phase ii presentation

2

VTA’s BART Silicon Valley Alignment

Page 3: Final 12 01 community mtg  phase ii presentation

3

VTA’s BART Phase I – Berryessa Extension

• 10-mile extension under

construction

• Two Stations:

– Milpitas, near the Great Mall

– Berryessa, near the San Jose Flea

Market

• Forecast opening date is Fall 2017

• $2.3 billion total project cost

• Anticipated daily ridership for

Phase I: 23,000 opening day

(doubles in 15 years)

Page 4: Final 12 01 community mtg  phase ii presentation

4

Current Project Activities – Milpitas

Construction of Milpitas Station invert underway.

Page 5: Final 12 01 community mtg  phase ii presentation

5

Current Project Activities – San Jose

Completed Hostetter Road deck. Construction underway of BART trench at Hostetter Road in the City of San Jose.

Construction underway of wayside facilities (train control S44 and substation SHO) (east of the alignment)

Page 6: Final 12 01 community mtg  phase ii presentation

6

Current Project Activities – San Jose

Photo of a completed section of the Berryessa Aerial Guideway.

Page 7: Final 12 01 community mtg  phase ii presentation

• Phase II Total Project Cost in Year of Expenditure Dollars : $4.7 billion

– $163 million incurred to date

• Anticipated Daily Ridership for Phase II: 55,000

– 2035 forecast ridership

– based on 2012 model forecast

7

VTA’s BART Phase II Project

Page 8: Final 12 01 community mtg  phase ii presentation

8

Measure A Overview

• Measure A is a ½ cent retail sales tax in Santa Clara County

• Began collections in 2006 and will sunset in 2036

• Devoted to specified public transit capital improvement projects and operations

• VTA Board of Directors determined BART Silicon Valley a priority project in

December 2008

Page 9: Final 12 01 community mtg  phase ii presentation

$0

$2,000

$4,000

$6,000

$8,000

$10,000

$12,000

$14,000

$16,0002

00

6

20

08

20

10

20

12

20

14

20

16

20

18

20

20

20

22

20

24

20

26

20

28

20

30

20

32

20

34

20

36

$0

$2,000

$4,000

$6,000

$8,000

$10,000

$12,000

$14,000

$16,0002

00

6

20

08

20

10

20

12

20

14

20

16

20

18

20

20

20

22

20

24

20

26

20

28

20

30

20

32

20

34

20

36

$0

$2,000

$4,000

$6,000

$8,000

$10,000

$12,000

$14,000

$16,0002

00

6

20

08

20

10

20

12

20

14

20

16

20

18

20

20

20

22

20

24

20

26

20

28

20

30

20

32

20

34

20

36

$0

$2,000

$4,000

$6,000

$8,000

$10,000

$12,000

$14,000

$16,0002

00

6

20

08

20

10

20

12

20

14

20

16

20

18

20

20

20

22

20

24

20

26

20

28

20

30

20

32

20

34

20

36

$0

$2,000

$4,000

$6,000

$8,000

$10,000

$12,000

$14,000

$16,0002

00

6

20

08

20

10

20

12

20

14

20

16

20

18

20

20

20

22

20

24

20

26

20

28

20

30

20

32

20

34

20

36

9

Measure A Sales Tax Revenue –Cumulative Forecast Projections

Mil

lions

of

Yea

r-o

f-R

ecei

pt

Do

llar

s

2001: $14.3B

2005: $9.9B2007: $8.7B

2009: $6.6B2014: $7.4B

Page 10: Final 12 01 community mtg  phase ii presentation

OperatingCost of Debt

SVRT Phase 1

Other Projects

-

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

Uses

Measure A ½-Cent Sales Tax

Uses of Funds FY2006-FY2036

10

$1.5B

Mil

lio

ns

of

Yea

r-of-

Expen

dit

ure

Doll

ars

Incurred

Thru 6/14VTA’s BART Silicon Valley Extension Phase I

Page 11: Final 12 01 community mtg  phase ii presentation

OperatingCost of Debt

SVRT Phase 1

Other Projects

Operating

Cost of Debt

SVRT Phase 1

Other Projects

-

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

Uses

Measure A ½-Cent Sales Tax

Uses of Funds FY2006-FY2036

1111

Mil

lio

ns

of

Yea

r-of-

Expen

dit

ure

Doll

ars

Project

Commitments

$1.5B

$3.0B

Incurred

Thru 6/14

VTA’s BART Silicon Valley Extension Phase I

VTA’s BART Silicon Valley Extension Phase I

Page 12: Final 12 01 community mtg  phase ii presentation

OperatingCost of Debt

SVRT Phase 1

Other Projects

Operating

Cost of Debt

SVRT Phase 1

Other Projects

Future Projects/ Debt Cost

-

1,000

2,000

3,000

4,000

5,000

6,000

7,000

8,000

Uses

Measure A ½-Cent Sales Tax

Uses of Funds FY2006-FY2036

Remaining

Measure A

Funds

Available

Mil

lio

ns

of

Yea

r-of-

Expen

dit

ure

Doll

ars

Project

Commitments

Future Projects Cost of Debt

Future Projects Cost

12

$1.5B

$3.0B

$2.9B

$7.4BTOTAL

Incurred

Thru 6/14

VTA’s BART Silicon Valley Extension Phase I

VTA’s BART Silicon Valley Extension Phase I

Page 13: Final 12 01 community mtg  phase ii presentation

13

Measure A – Phase II Funding

• Measure A funds constrained

– $2.9 billion remaining for Measure A projects and financing

• Additional funding needed to build Phase II

• VTA will pursue federal funding from the Federal Transit Administration’s

(FTA) New Starts Program– New Starts rating for projects is based on two criteria: Project Justification (50%) and Local

Financial Commitment (50%)

• Other funding – Cap & Trade, Value Capture, etc.

Page 14: Final 12 01 community mtg  phase ii presentation

Phase II Capital Costs and Sources of Funds

14

* The 4-Station Alternative cost includes a full maintenance facility at Newhall.

** Analysis of Measure A revenue forecast is underway. The results from this analysis will determine the extent of Measure A revenue that may be available for projects and estimate the Shortfall $ for

SVRT Phase II.

1.1

1.0

1.1

2.6

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

4.0

4.5

5.0

4-Station Alternative(Alum Rock, Downtown, Diridon, Santa Clara)*

$4.7 billion

TCRP State Funds

Shortfall $ **

New Starts

Measure A **

.163

1.1

1.01.0

2.43

0.16

Page 15: Final 12 01 community mtg  phase ii presentation

15

Project History – Environmental Process

• 2004 – State clearance (CEQA) on Final Environmental Impact Report (EIR):

16-miles

• 2007 – CEQA clearance on Final Supplemental EIR (SEIR): 16-miles

• 2010 – Federal clearance (NEPA) on Final Environmental Impact Statement

(EIS): 10-miles

• 2011 – CEQA clearance on 2nd SEIR: 10-miles

• 2015 – Joint CEQA and NEPA document (SEIS/SEIR3): 6-miles

Page 16: Final 12 01 community mtg  phase ii presentation

Environmental Process

16

State (CEQA) and federal (NEPA) Environmental Process Timeline

Page 17: Final 12 01 community mtg  phase ii presentation

Environmental Process

17

• Notice of Preparation (NOP) – notification to state and other agencies of the

project including a description, the location, and potential environmental issues

• Scoping – an opportunity for members of the public and agencies to provide

input in the proposed project, purpose and need, the various environmental

topical areas related to the project, and the scope and content of the draft

environmental document

• Record of Decision (ROD) – federal environmental clearance

Page 18: Final 12 01 community mtg  phase ii presentation

NEPA/CEQA & New Starts (Federal

Funding Program) Milestone Schedule

18

Page 19: Final 12 01 community mtg  phase ii presentation

19

Future Community Engagement Activities

• Ongoing community outreach and engagement during

environmental process

• Environmental process kick-off (scoping meetings) – late

January/early February

• Focused Outreach Sessions – Spring 2015, some topics may

include:

– Economic and Community Benefits

– Funding

– Station Planning

– Transportation Connectivity

– Construction Methods

Page 20: Final 12 01 community mtg  phase ii presentation

END

20

Page 21: Final 12 01 community mtg  phase ii presentation

21

Page 22: Final 12 01 community mtg  phase ii presentation

END

22

Page 23: Final 12 01 community mtg  phase ii presentation

23

Page 24: Final 12 01 community mtg  phase ii presentation

24