City of New Orleans – Capital Improvement Program

Filmore North – Group A

Jan. 15, 2019

Page 2: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

1

Agenda

WelcomeLisbeth Pedroso & Yvonne Martin, Mayor’s Office of Neighborhood Engagement

Project OverviewDamian Kulas, Department of Public Works

What to Expect During ConstructionKim Tran , RoadworkNOLA

DiscussionLisbeth Pedroso, Mayor’s Office of Neighborhood Engagement

Page 3: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

2

Ground Rules

Presentation will precede public comment

Please limit questions to the project area

Please fill out a comment card to provide a

comment/ask a question

Please raise your hand and your comment card will be

collected by a staff member

There is a two-minute time limit on questions

A staff member will hold the microphone for you

You may not yield time to another speaker

Page 4: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

3

Capital Improvement Program Highlights

More than $2.2B worth of DPW / SWB work in the next 8 years

Most comprehensive infrastructure program our region has seen in a generation.

More than 200 individual projects - every neighborhood will feel a positive impact.

Multiple Funding Sources: FEMA-funded road / waterline work, FEMA-funded Hazard Mitigation Grant Program (HMGP) projects, HUD-funded National Disaster Resiliency Competition (NDRC) grant projects, SWB-funded Sewer System Evaluation and Rehabilitation Program (SSERP) (sewer consent decree) work and City-funded bond project work.

Work will create thousands of construction jobs across the city and maximize

economic opportunity for the City’s small and disadvantaged businesses.

Page 5: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

4

Filmore North Group A - Overview

Designer: Professional Engineering Consultants (PEC)

Corporation

Construction Contractor: Command Construction

Industries, LLC

Cost: Approximately $5.5M

Schedule: Construction will begin early Feb. 2019 and last

for approximately one year

Page 6: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

5

Scope of Work

Repaving the asphalt roadway from curb-to-curb in

some areas;

Patching the roadway with asphalt in some areas;

Repairing some damaged sidewalks and driveway

aprons;

Installing Americans with Disabilities Act-compliant curb

ramp at intersections; and

Replacing/repairing damaged underground water,

sewer and/or drainage lines.

Page 7: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

6

Project Limits – Filmore North Group A

Page 8: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

7

Typical Roadway Cross-Section

7

Southbound Northbound

26-feet wide

Drainage

Sewer Line

Water LineOther Underground Utility

Man Hole

Catch

BasinCatch Basin

NOT TO SCALE

Page 9: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

8

Waterline Replacements or Repairs

• Drainage line repairs

• Minimal water service

disruptions

• Notifications will be

sent to residents 48-

hours prior to any

work that may cause

water services

disruptions

Page 10: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

9

This project will begin with the

replacement of the waterlines on

the following streets: Madrid,

Burbank, Athis, Prentiss, Paris,

Charlotte, Bancroft, and

Pressburg.

Full road closures will occur on

Charlotte and Bancroft Drives for

full restoration.

Once the utility work is complete

the trench sites will be filled.

Paving work will follow.

Waterline Replacements or Repairs

Page 11: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

10

Patch Mill / Overlay

• Roadway will be re-

surfaced with asphalt

• Repairs may be made to

some damaged curbs,

sidewalks and driveway

aprons After

Before

Page 12: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

11

Patch Concrete

• Replacing one or multiple damaged concrete panels in

the roadway

• Repairs may be made to some damaged curbs, sidewalks

and driveway aprons

After

Before

Page 13: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

12

Incidental Road Repairs

• Roadway patches will be re-

surfaced with asphalt

• Repairs may be made to

some damaged curbs,

sidewalks and driveway

aprons

Before

After

Page 14: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

13

Non-Paving Incidentals

• Eligible damaged or missing

sidewalks will be removed and

replaced

• New sidewalks meet

Americans with Disabilities Act

requirements

Before

After

Page 15: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

14

Americans with Disabilities Act-Compliant Curb Ramps

Before

After

Curb ramps at sidewalk

corners ensure accessibility

for people who are visually

or physically impaired,

using wheelchairs or

strollers.

Page 16: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

15

Project Timeline*

Milestone Date

Construction Start Date Feb. 2019

Construction Completion Early 2020

* Please note that all schedules are subject to change and weather delays.

Page 17: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

16

What to Expect During Construction Traffic

One travel lane will be maintained, in each direction,

throughout construction on water line replacement

streets

Full road closures are necessary on Charlotte and

Bancroft drives during water line replacement work.

Limited parking available near trench site.

Crews will attempt to allow local access to driveways in

the evenings, depending on the location of the water

line replacement.

Page 18: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

17

What to Expect During Construction

Temporary construction impacts

• Additional construction equipment

• Limited parking availability

• Sounds

• Dust

Efforts to minimize construction impacts

• Construction signage placed around the sites.

• Any temporary closures will be communicated in advance.

• Any changes to garbage and US Postal services will be

communicated in advance.

• Residents will be informed throughout construction.

Regular work hours are Monday-Friday 7:00 a.m. to 5:30 p.m.

Permission for occasional weekend work may be granted, if required.

Road

Construction

Ahead

Page 19: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

18

Keeping You Informed Roadwork.nola.gov

Page 20: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

19

Stay Connected

504.658.ROAD (7623)Facebook.com/roadworkNOLA

@roadworkNOLA

@roadworkNOLA

We have joined NextDoor!

[email protected]

Monthly Newsletter Updates

Page 21: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

20

Contact Information

Kim Tran, Outreach Specialist

504-658-ROAD (7623)

[email protected]

Page 22: Filmore North Group A...2019/01/15  · Charlotte, Bancroft, and Pressburg. Full road closures will occur on Charlotte and Bancroft Drives for full restoration. Once the utility work

21

Questions / Discussion