fifth cw and high average power rf workshop - 2008

14
Fifth CW and High Average Power RF Workshop - 2008 25 - 28 March 2008, CERN - Geneva 25 - 28 March 2008, CERN - Geneva OPERATIONAL EXPERIENCE WITH THE SOLEIL 352 MHZ RF SYSTEMS P. Marchand

Upload: aulii

Post on 07-Jan-2016

50 views

Category:

Documents


0 download

DESCRIPTION

Fifth CW and High Average Power RF Workshop - 2008 25 - 28 March 2008, CERN - Geneva OPERATIONAL EXPERIENCE WITH THE SOLEIL 352 MHZ RF SYSTEMS. P. Marchand. Operational experience with the BO RF system. 5-cell copper cavity of the LEP type in the SOLEIL Booster. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Fifth CW and High Average Power               RF Workshop - 2008

Fifth CW and High Average Power RF Workshop - 2008

25 - 28 March 2008, CERN - Geneva25 - 28 March 2008, CERN - Geneva

OPERATIONAL EXPERIENCE WITHTHE SOLEIL 352 MHZ RF SYSTEMS

P. Marchand

Page 2: Fifth CW and High Average Power               RF Workshop - 2008

Operational experience with the BO RF systemOperational experience with the BO RF system

The BO RF plant was commissioned mid 2005.The BO RF plant was commissioned mid 2005.Up to date, after ~ Up to date, after ~ 9 59 500 running hours, only a single trip in operation, 00 running hours, only a single trip in operation, due to a human due to a human mistakemistake

The 35 kW solid state amplifier has proved to be very reliable :The 35 kW solid state amplifier has proved to be very reliable : - 4 (out of 147) modules had a failing - 4 (out of 147) modules had a failing bad soldering (3) + 1 filter bad soldering (3) + 1 filter (0 transistor failure !)(0 transistor failure !) - In any case, that did not affect at all the operating conditions and could be quickly- In any case, that did not affect at all the operating conditions and could be quickly repaired repaired during scheduled machine shutdowns.during scheduled machine shutdowns.

Don’t play with the equipment during the operation !Don’t play with the equipment during the operation !

5-cell copper cavity of the LEP type in the SOLEIL Booster

35 kW solid state amplifier and LLRF system in the Booster RF room

Page 3: Fifth CW and High Average Power               RF Workshop - 2008

As scheduled for SOLEIL - phase 1, with IAs scheduled for SOLEIL - phase 1, with Ibeambeam < 300 mA and a reduced number of insertion < 300 mA and a reduced number of insertion

devices, one half of the SR RF system was installed and commissioned, during summer 2006 devices, one half of the SR RF system was installed and commissioned, during summer 2006 (CM1, cryogenic plant, 2 amplifiers, (CM1, cryogenic plant, 2 amplifiers, control and LLRF systems).control and LLRF systems).

The goal of storing up to 300 mA of stable beam, using a single CM, was quickly achieved.The goal of storing up to 300 mA of stable beam, using a single CM, was quickly achieved.

At first, without the RF feedbackAt first, without the RF feedback, the cavity was slightly detuned in order to cope with the , the cavity was slightly detuned in order to cope with the Robinson instabilityRobinson instability, at the expense of ~ 10 kW extra reflected power., at the expense of ~ 10 kW extra reflected power.

Commissioning of theCommissioning of the SR RFSR RF

VVcav cav = 1 MV= 1 MV

: 0 : 0 67° 67°

unstable

stable

I beam [mA]

stable

unstable

VVcav cav = 1 MV= 1 MV

: 4 : 4 71° 71°

I beam [mA]

Later on, we have commissioned the RF feedbackLater on, we have commissioned the RF feedback, which enabled to store up to 300 mA , which enabled to store up to 300 mA stable beam without any tuning offset, hence saving ~ 10 kW of reflected power.stable beam without any tuning offset, hence saving ~ 10 kW of reflected power.

ψψ = = ψψoptopt (P (Prr min) min) beam lost at 230 mA beam lost at 230 mA ψψ = = ψψoptopt + 4° + 4° stable up to 300 mA stable up to 300 mA

Page 4: Fifth CW and High Average Power               RF Workshop - 2008

Commissioning of theCommissioning of the SR RFSR RF

0

25

50

75

100

125

150

175

0 50 100 150 200 250 300 350

P r [kW]

P i [kW]

10 kW

145 kW135 kW

No RF feedback, ψ = ψopt (Ib) + 4°

With RF feedback, ψ = ψopt (Ib)

Under these conditions, at cst VUnder these conditions, at cst Vcavcav = 1 MV, = 1 MV,

the tuning loop is continually active, the tuning loop is continually active, compensating for the reactive beam compensating for the reactive beam

loadingloadingeither partially (no RF feed-back) either partially (no RF feed-back)

or fully (with RF feed-back) or fully (with RF feed-back)

f (k

Hz)

f (kH

z)

00

22

44

66

88

Ψop

t (d

eg.)

67° 67°

4.2 kHz4.2 kHz

RF power required per cavity (Pi, Pr) vs Ibeam at cst voltage of 1 MV / cav

Frequency changes of ~ 4 kHz, Frequency changes of ~ 4 kHz, about 10 000 motor steps, about 10 000 motor steps,

required at each injection.required at each injection.

Page 5: Fifth CW and High Average Power               RF Workshop - 2008

0

25

50

75

100

125

150

175

200

0 50 100 150 200 250 300

Commissioning of theCommissioning of the SR RFSR RF

Ramping VRamping Vcavcav from 650 kV at 0-current, up to 1.4 MV at 300 mA, with fixed tuning angle, from 650 kV at 0-current, up to 1.4 MV at 300 mA, with fixed tuning angle,

ψψ = 60°, allows to maintain P= 60°, allows to maintain Prr < 50 kW and Pi ~ 145 kW (green plot). < 50 kW and Pi ~ 145 kW (green plot).

Vcav : 1.4 MV cst, = 60°

I beam [mA]

PR

F [

kW

]

Considering the difficulties encountered on Super-3HC at ELETTRA with a similar tuning Considering the difficulties encountered on Super-3HC at ELETTRA with a similar tuning system, which happened to get stuck after ~ 50 millions of motor steps, it was proposed to system, which happened to get stuck after ~ 50 millions of motor steps, it was proposed to operate at constant tuning during the injectionoperate at constant tuning during the injection, in order to use the tuners more sparingly., in order to use the tuners more sparingly.

Injecting at constant tuning Injecting at constant tuning requires a ramping of Vrequires a ramping of Vcav cav ;;

otherwise too large Potherwise too large Prr at low at low

current (red plot).current (red plot).

145 kW145 kW

Injection at constant tuningInjection at constant tuning

Energy and phase acceptance at low RF Energy and phase acceptance at low RF voltage ?voltage ?

Vcav : 1 1.4 MV, = 60°

VVcavcav : 0.65  : 0.65 1.4 MV, 1.4 MV, = 60° = 60°

Page 6: Fifth CW and High Average Power               RF Workshop - 2008

Commissioning of theCommissioning of the SR RFSR RF

At VAt VRFRF as low as 1.3 MV (650 kV / cav), E & as low as 1.3 MV (650 kV / cav), E & ΦΦ acceptance strongly reduced acceptance strongly reduced

VRF = 1.3 MVФs = 50°

- 3

+ 3 VRF = 2 MVФs = 30°

The experience demonstrated that it remains tolerable :The experience demonstrated that it remains tolerable : injection efficiency nearly injection efficiency nearly unaffected while keeping Vunaffected while keeping V sinsin Φ cstΦ cst : V(I : V(Ibb) and ) and Φ(V), Φ(V), numerically controlled via the PLCnumerically controlled via the PLC

Precise control of Φ(V) required for operating with the multibunch transverse feedbackPrecise control of Φ(V) required for operating with the multibunch transverse feedback

Constant tuning mode routinely used in operation ; easy switching from constant to Constant tuning mode routinely used in operation ; easy switching from constant to variable tuning mode (for run dedicated to machine R&D variable tuning mode (for run dedicated to machine R&D free control of V free control of VRFRF))

Injection at constant tuningInjection at constant tuning

+ 3

- 3

Page 7: Fifth CW and High Average Power               RF Workshop - 2008

Commissioning of theCommissioning of the SR RFSR RF

Injection at constant tuning – Robinson stabilityInjection at constant tuning – Robinson stability

0

50

100

150

200

250

300

350

400

450

500

0 50 100 150 200 250 300 350

I th [mA]

I b [mA]

VVcavcav : 0.65  : 0.65 1.4 MV, 1.4 MV, = 60° = 60°

unstable

I beam [mA]

Large stability margin even without RF feedbackLarge stability margin even without RF feedback

Page 8: Fifth CW and High Average Power               RF Workshop - 2008

Operational experience with the cryomodule (CM1)Operational experience with the cryomodule (CM1)

CM1 had been RF conditioned with full reflection CM1 had been RF conditioned with full reflection (I(Ibeambeam= 0) up to 200 kW= 0) up to 200 kW per coupler,per coupler, at CERNat CERN and then up to 80 kW, once installed in the SOLEIL SR (always kept under UHV).

Re-conditioning with beam went quite smoothlyRe-conditioning with beam went quite smoothly : a few coupler vacuum trips, at first when reaching P > 160 kW ; further conditioning likely would be required for operating at such power level ; however, with proper settings, P < 145 kW @ 300 mA with a single CM, which is more demanding than 500 mA with 2 CMs.

Not the least trip under nominal operating conditionsNot the least trip under nominal operating conditions

No evidence of HOM excitation : No evidence of HOM excitation : up to 300 mA, power dissipation in the HOM loads always negligible & residual beam phase oscillations < 0.1°

Taking care of using the cavity tuners sparinglyTaking care of using the cavity tuners sparingly cst tuning operation as much as possible+ additional diagnostic+ additional diagnostic rev counter for early detection of signs heralding a sticking

R&D for improved design - gear box

- transmission screw Test bench

Page 9: Fifth CW and High Average Power               RF Workshop - 2008

A few shutdowns caused by utility losses (water / electrical) fast restartfast restart

This was solved after bringing in slight This was solved after bringing in slight modifications on the cryogenic valve box modifications on the cryogenic valve box Pressure variations below Pressure variations below 2 mbar, 2 mbar, namely namely  0.1° in phase. 0.1° in phase. Not the least trip in operation.Not the least trip in operation.

Operational experience with the cryogenic plantOperational experience with the cryogenic plant

At the beginning of the commissioning, At the beginning of the commissioning, difficulties were encountered with LHe difficulties were encountered with LHe feeding and pressure instabilities inside feeding and pressure instabilities inside the cavity He tank, due to an unexpected the cavity He tank, due to an unexpected thermal load on the cryogenic valve box. thermal load on the cryogenic valve box.

Forthcoming upgradesForthcoming upgrades improve the autonomy

- Process modification take profit of the autonomy provided by the Dewar

- UPS extension to all the Cold-box components

- Cold-box dedicated water-cooling

Page 10: Fifth CW and High Average Power               RF Workshop - 2008

• The two 180 kW solid state amplifiers for CM1 The two 180 kW solid state amplifiers for CM1 have demonstrated good reliability in operation. have demonstrated good reliability in operation. After ~ 7 500 running hours, only 4 trips :

- 3 due to human mistakes (a fault in the interlock logic, a wrong manipulation, a cable pull out by accident) - 1 due to a failure on preamplifier module

• Although not perturbing for the operation,Although not perturbing for the operation, 56 (out of 1400) modules have suffered from 56 (out of 1400) modules have suffered from transistor failures in operation;transistor failures in operation; forfor 1010 ofof themthem itit waswas thethe result of a circulator result of a circulator load failingload failing solved by adding thermal grease solved by adding thermal grease

- Upgrading of the 350 MHz design (investigation of other suitable transistors) Collaboration with ESRF (~ 50 towers of 50 kW)- Other freq. : 300 W module @ 500 MHz 476 MHz (2 x 40 kW for LNLS) 90 x 15 kW @ 1.3 GHz 4th generation LS (ARC-EN-CIEL)

R&DR&D

• Failure rate < 3.5 % / year pessimistic, as it includes part of the infant mortality, lack of grease, damages by accident on amplifier 1 expectedexpected failurefailure rate ~ 1%rate ~ 1%

longer running periods are required to find out the actual MTBF

• 100 available spare modules turn over : 50 usable in house while 50 under repair

Operational experience with the RF power amplifiersOperational experience with the RF power amplifiers

Page 11: Fifth CW and High Average Power               RF Workshop - 2008

Operational experience with the LLRFOperational experience with the LLRF

Without RF feedback : ± 0.5 % in amplitude and 0.15° in phaseWith RF feedback : ± 0.1 % in amplitude and 0.05° in phase

Frequency tuning loop

Phase loop

Amplitude loop

Direct RF feedback

Voltage control

PID

PID

Drive3dB 3dB Coupler

RF SWITCH

190 kW AMPLIFIER

CA

VIT

Y

-

G

Direct RF Feedback

352.2 MHZ

+

Phase control

Tuning control

PID

3dB

3dB

Tuner

Recently, a few trips due to wrong PRecently, a few trips due to wrong Prr interlocks on fast hardwired system interlocks on fast hardwired system

Solved by compromising speed & sensitivity to interferenceSolved by compromising speed & sensitivity to interference

Page 12: Fifth CW and High Average Power               RF Workshop - 2008

Drive

RF SWITCH

190 kW AMPLIFIER

CAVITY

MODULATORI Q

PLCPLC

PLCPLC

C-PCI

352.202 MHz

HERONSYSTEM

342.202 MHz

10 MHz

AD8345

AD8138

AD831

PLL

ADC

DAC DAC

FPGA

RS232

ADC

LP FILTER LP FILTER

Fast digital LLRFFast digital LLRF

First measured performance : 0.1 % in amplitude and 0.1° in phase to be completed in forthcoming runs

Page 13: Fifth CW and High Average Power               RF Workshop - 2008

• Up to date, the BO and half of the SR RF systems have been commissioned

• The technological choices, sc cavities and high power solid state amplifiers, both designed in house, were quite challenging

• The first operational experience is fully satisfactory :The first operational experience is fully satisfactory : after ~ 9 500 running hours in the BO and 7 500 in the SR, only a few trips in operation due to minor incidents

CMCM : Improve the frequency tuning system : Improve the frequency tuning system

AmplifiersAmplifiers : MTBF of transistors (?) : MTBF of transistors (?)

• Several laboratories are about to adopt the solid state technology “à la SOLEIL” @ 352 MHz : CEA and ESRF @ 500 MHz : LNL-Legnaro, LNLS-Brazil, SLS-PSI, NSLS II-Brookhaven (?) Collaborations under discussion R&D is going on at SOLEIL L - Band

• The 2nd half of the SR RF system, which is under fabrication, should be implemented in May 2008 nominal performance (4.4 MV and 500 mA)

Summary & conclusionsSummary & conclusions

Page 14: Fifth CW and High Average Power               RF Workshop - 2008

AcknowledgementAcknowledgement

SOLEIL, CEA, CERN, ESRF, LURE

SOLEIL RF & LINAC GROUP

Patrick MARCHAND

Robert LOPES

Fernand RIBEIRO Ti RUAN

Helder A. DIAS Jocelyn LABELLE

Massamba DIOP

Cyril MONNOT Moussa EL AJJOURI

Marc LOUVETRajesh SREEDHARANJean-Pierre POLLINA Nicolas GUILLOTIN

Jean-Pierre BAETE Julien SALVIA