field force operational data visualization - eprismartgrid.epri.com/doc/2012-11-01 - smart grid...
TRANSCRIPT
John J. Simmins, Ph.D.
Electric Power Research Institute
Smart Grid Information Sharing Call
November 27, 2012
Field Force Operational Data Visualization
What’s So Smart About It?
2 © 2012 Electric Power Research Institute, Inc. All rights reserved.
The self healing grid
Normal Configuration
3 © 2012 Electric Power Research Institute, Inc. All rights reserved.
A Fault Occurs
4 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Flow of Fault Current Triggers
Faulted Circuit Indicators (FCIs)
5 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Substation circuit breaker
trips a first time
6 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Substation circuit breaker recloses….
7 © 2012 Electric Power Research Institute, Inc. All rights reserved.
…and trips again (lockout)
8 © 2012 Electric Power Research Institute, Inc. All rights reserved.
FLISR identifies faulted section by
comparing FCIs
9 © 2012 Electric Power Research Institute, Inc. All rights reserved.
FLISR opens switches to isolate
the faulted feeder section
10 © 2012 Electric Power Research Institute, Inc. All rights reserved.
FLISR Triggers Upstream Restoration
11 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Downstream restoration of blinking section
Compare load with available capacity
12 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Downstream restoration of blinking section
Compare load with available capacity
Pre-fault load
= 1 MW
Available Capacity =
2 MW
13 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Capability exists, so…
Available Capacity =
2 MW
Pre-fault load
= 1 MW
14 © 2012 Electric Power Research Institute, Inc. All rights reserved.
FLISR closes switch to restore service
Via alternate supply line
15 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Now FLISR checks for capacity to
Transfer last downstream section
Available Capacity = 1.5
MW
Pre-fault load
= 2 MW
16 © 2012 Electric Power Research Institute, Inc. All rights reserved.
In this case capacity does not exist so
downstream section is not restored
Pre-fault load
= 2 MW
Available Capacity = 1.5
MW
17 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Options for the red substation….
Pre-fault load
= 2 MW
Available Capacity = 2.5
MW
18 © 2012 Electric Power Research Institute, Inc. All rights reserved.
These actions free enough capacity to
pick up last remaining section
19 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Only one problem….
20 © 2012 Electric Power Research Institute, Inc. All rights reserved.
So, how has this changed?
21 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Contents
• Introduction to Field Force
Visualization supplemental
project
• Data visualization in a
broader sense
• Data and visualization as a
commodity
22 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Goals of the FFDV Supplemental Project
• Identify gaps in standards
• Demonstrate the use of low
cost platforms
• Demonstrate the use of low
cost communication media
• Prove value of in field
integration
• Prove value for large scale
outages
• Identify multiplatform issues.
23 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Field Force Data Visualization
An integrated field force data
visualization and integration
tool for managing work and
maintaining any asset in the field.
Leveraging CIM, Augmented Reality and Context
Aware GIS
24 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Definition – Common Information Model (CIM)
• In our context, it is a
semantic model of the
electric utility industry that
may be leveraged to create
standard messaging
between back office
systems --- or in our case,
tablet or other hardware in
the field.
25 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Definitions – Augmented Reality
• Augmented reality (AR) is a
live, direct or indirect, view of
a physical, real-world
environment whose
elements are augmented by
computer-generated sensory
input such as sound, video,
graphics or GPS data.
• Not to be confused with
virtual reality – which
replaces a real world with a
simulated one.
Don Carlos
(Mexican)
102 Broad St.
26 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Definition – Context Aware GIS
• Using the dynamic context of
mobile device users, caused
by the mobility and constant
change in the environment,
to deliver information.
• Aware of the spatial
environment surrounding the
user.
• Aware of the role (limiting
access) of the user.
27 © 2012 Electric Power Research Institute, Inc. All rights reserved.
From “Dumb” to “Smart”
28 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Traditional Point-to-Point Integration
Characteristics
• Complex environment
• High integration costs
• High maintenance costs
• Message tracking – non-
existent
• Guaranteed delivery –
non-existent
• Frequent “broken”
interfaces.
There is no “leverage” of the information being exchanged
29 © 2012 Electric Power Research Institute, Inc. All rights reserved.
“Smart” Integration
Characteristics
• Enterprise semantic model
• Enterprise service bus
– Little or no custom code
– Lower integration cost
– Lower maintenance
costs
– Message tracking
– Guaranteed delivery
– Reliable.
Messages are agnostic of their origins
30 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Example: Typical Elements of a Work Request
• Work ID
• Location
• A bill of materials (BOM)
• An estimated time of
completion is calculated and
a start or completion time is
calculated.
• Crew type (based on skill
sets or roles)
• Detailed work tasks.
31 © 2012 Electric Power Research Institute, Inc. All rights reserved.
So, how does this all work?
32 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Field Force Data Visualization
The Issue:
• Access to real-time data in the field has not progressed
• Getting data to the field is too expensive
• Getting the data from the field is too cumbersome
• The applications don’t interop
• Data is not accurate
The Impact:
• Work is not efficient
• Decisions in the field suffer.
• Potentially dangerous situation.
Multiple applications in the field isn’t a great leap forward
33 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Field Force Data Visualization
EPRI Solution:
• Build on a light weight, inexpensive platform.
• Leverage augmented reality capabilities.
• Messaging using CIM to multiple systems.
• Two way communications to back office systems.
Value:
• Lower cost of field force automation.
• Puts accurate data where it needs to be.
• Correct inaccurate GIS data.
• Spurs CIM development.
34 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Field Force Data Visualization - Features
Asset Information
• Identify asset
• Maintenance history
• Create work request
• Call SOPs
One line circuit
diagram or geo-
schematic view
Crew location and
graphic circuit
representation
Links to other tools
Create work request
in the field
Status assigned work
in the field
Other Potential Features: QR, RFID, Bar Code, shape recognition
35 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Standards Leveraged by FFDV
Standard Title
IEC 61968-3 Network Operations
IEC 61968-4 Record and Asset Management
IEC 61968-6 Maintenance and Construction
IEC 61968-8 Customer Support
IEC 61968-9 Meter Reading and Control
IEC 61968-11 CIM Extensions for Distribution
IEC 61968-13 RDF Distribution model exchange
(CDPSM)
IEC 61968-14 MultiSpeak® Mappings and Profile
X12 511 Material Requisition
36 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Benefits
• Inexpensive to deploy
• Inexpensive to maintain
• Applications
– Asset maintenance manuals
– Damage assessment
– Asset information access
– Switching communications
– Work-order information flow
– Real-time system status
validation
– Visualizing faults in the field.
Field Work Becomes Easier and More Efficient
37 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Example: Damage Assessment
38 © 2012 Electric Power Research Institute, Inc. All rights reserved.
39 © 2012 Electric Power Research Institute, Inc. All rights reserved.
40 © 2012 Electric Power Research Institute, Inc. All rights reserved.
41 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications for Large Scale Outages
• Use “foreign” tablets in the
damaged service territory
• Provide tablets to
contractors
• Instantly recognize the
symbology of the host utility
• Share information as
necessary.
With technology and standards that apply across the
industry, you can:
42 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Augmented Reality View of Grid in Honolulu
GIS data contains
“z” dimension
Assets of interest
are marked
Conductors are
color coded
43 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Simulated Distribution Grid
Golf course secondary
44 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Details of Assets in the Field
GIS Aware List of
Options
• Schedule maintenance
• Retrieve manuals
• Edit asset location
• View locations details
45 © 2012 Electric Power Research Institute, Inc. All rights reserved.
List of Manuals Available for that Asset
GIS Aware List of Manuals
• Operations manual
• Maintenance manual
46 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Verification of Manual and Asset
Revision number
Last update
Visual verification
47 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Detailed Instructions
Detailed
instructions
Pictures or video
48 © 2012 Electric Power Research Institute, Inc. All rights reserved.
What About Security?
• Platform (iOS) Security
– Low level system calls not allowed
– App isolation – each app in its own “sandbox”
– Library randomization
– Encrypted drive
– Password protected
• Network Security
– SSL/TLS with X.509 certificates
• Application Security
– Encrypted data exchanges
– Strong log in
49 © 2012 Electric Power Research Institute, Inc. All rights reserved.
References:
• YouTube Video:
http://www.youtube.com/watch?v=amxE1BD21vc
• Program on Technology Innovation: Assessment of iPod
Touch® as a Sensor Platform for Application Across the
Electric Power Industry – 1024696
• Field Force Data Visualization: A Mobile Integrated Data
Access Platform – 1024304
• Field Force Data Visualization Software – 1023399
(available ~December 15, 2012).
50 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Implications
51 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Commoditization
• Commoditization occurs when consumers
can buy the same product or service from
different small or large businesses.
• Price is the only distinguishing factor in
commoditized products, because there is
no significant difference in quality or in
how consumers use these products.
• Companies usually cannot raise prices
because consumers can shop at
competitors offering the same or similar
products at lower prices.
• This process is enabled by standards or
de facto standards.
52 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Form 2S
3-Wire Self-Contained
Source: Handbook for
Electrical Metering, 9th Edition
Examples of Benefits of Commoditization
• C12.10 standard
– Mass production of meters
– Residential electrical meter ~ $20
• C12.18/C12.19 Optical port
• TX/RX Protocols
− Interoperable hardware: probes, hand held readers, etc.
53 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Typical Distribution Control Center a
Few Years Ago
• Distribution System was operated
manually with wall- mounted
switching diagrams
• Mostly paper driven processes
54 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Current Trend in Control Center
Design
• Increasing emphasis on “outside the fence” visualization
• Large mapboards disappearing from distribution control centers
• Use of stackable monitors for operator workstations – allows view of specific “area of responsibility”
55 © 2012 Electric Power Research Institute, Inc. All rights reserved.
What if we were to bring the same technology
inside the operations center?
• Geo-schematic view
• Geographic view
• Crew locations
• Fault locations
• Create a works order
• Assign to a crew
Lajja
Ajnnajd
Jdh
Aja
jf
Advantage: Display technology independent of back end systems
56 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Conclusions
• The combination of mobile technologies, standards
development and communications enables new ways to
access and view data.
• Integration – the ability to use data from multiple systems –
is available not only in the back office but in the field.
• Standardizing the symbology and visualization technology
has far reaching implications for mutual aid/large event
management.
• The same technologies – touch screens, standard symbols,
standard messages, etc. – can be leveraged inside the
operations center with likely gains in efficiency and quality
decisions.
57 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Questions
58 © 2012 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity