fhlb affordable housing competition march 4, 2020 workshop ... · fhlb affordable housing...
TRANSCRIPT
FHLB Affordable Housing CompetitionMarch 4, 2020 Workshop Night
Cost, Design, and Impacts to the Total Project Budget
Jonathan Lavash
Jonathan Lavash Project Management, LLC
The Project Delivery Team: Owner, Architect, Contractor
FHLB Competition – March 7, 2018 Workshop Night - JLPM, LLC. 2
Triple Project Constraints: Scope, Budget, and Schedule
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 3
Project Delivery: Planning, Design, Construction
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 4
Project timeline
Planning- Site Selection- Highest and Best Use- Financial Planning- Regulatory Approvals
Design- Conceptual Design- Detailed Design- Construction Documents- Construction Administration
Construction- Subcontractor Procurement- Submittals and Purchasing- Production and Quality- Change Management
Changes to the Project: Influence and project cost
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 5
Value Management:Continuous Value Engineering Process
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 6
Typical Project Budget History Curve
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 7
Construction Costs and Total Project Budget
• Construction costs usually account for 70% to 80% of the total budget.
• Construction costs are part of the Hard Cost budget.
Total Project Budget
o Acquisition
o Hard Costs
o Soft Costs
o Owner’s Contingency
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 8
Development of the Total Project Budget
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 9
Hard Costs:
o Construction Estimate (From contractors, estimators, benchmarks, in-house resources)
o Owner furnished Items (Security and access systems, FFE)
Soft Costs:
o Architect’s proposal including consultants (or % of construction costs)
o Legal Feeso Accounting Feeso Owner’s Project
Managemento Clerk of the Works
o Financing Feeso Insuranceo Surveyingo Taxeso City Feeso Appraisalso Testing and Inspection
Owner’s contingency
• Contingency covers unknowns in the project:o Design development
o Economic development
o Scope development
o Unforeseen subsurface conditions
• Owners run contingency down during all stages:o Planning
o Design (Concept, Schematic, Development, Documents)
o Construction
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 10
Construction Costs:Masterformat of Construction Specification Institute
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 11
MASTERFORMAT 1995 EDITIONBefore November 2004, MasterFormat was composed of 16 Divisions:
Division 1 — General RequirementsDivision 2 — Site ConstructionDivision 3 — ConcreteDivision 4 — Masonry (Ex. Concrete block)Division 5 — Metals (Ex. Beams)Division 6 — Wood and PlasticsDivision 7 — Thermal and Moisture ProtectionDivision 8 — Doors and Windows
Division 9 — FinishesDivision 10 — SpecialtiesDivision 11 — EquipmentDivision 12 — FurnishingsDivision 13 — Special ConstructionDivision 14 — Conveying SystemsDivision 15 — Mechanical (Ex. Plumbing and HVAC)Division 16 — Electrical
Hard Cost Estimates: Actual Affordable Housing Example
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 12
Uses of Funds Analysis
Name
. Basis for estimates?
14,000 SF
DV Trade Item Amount % By Division $/SF
. 3 Concrete $129,816 5% 5% 3 $9.27
. 4 Masonry $8,002 0% 0% 4 $0.57
. 5 Metals $6,381 0% 0% 5 $0.46
. 6 Rough Carpentry $197,068 7% 9% 6 $14.08
. 6 Finish Carpentry $47,879 2% $3.42
. 7 Waterproofing $13,216 0% 7% 7 $0.94
. 7 Insulation $18,869 1% $1.35
. 7 Roofing $32,322 1% $2.31
. 7 Sheet Metal and Flashing $9,347 0% $0.67
. 7 Exterior Siding $116,237 4% $8.30
. 8 Doors $116,525 4% 6% 8 $8.32
. 8 Windows $55,836 2% $3.99
. 8 Glass $0 0% $0.00
. 9 Veneer Plaster $0 0% 11% 9 $0.00
. 9 Drywall $131,793 5% $9.41
. 9 Tile Work $73,297 3% $5.24
. 9 Acoustical $0 0% $0.00
. 9 Wood Flooring $0 0% $0.00
. 9 Resilient Flooring $44,601 2% $3.19
9 Carpet $0 0% $0.00
. 9 Paint & Decorating $51,844 2% $3.70
AM Fogarty Scheme A
Hard Cost Benchmarks:New York City Example
FHLB Competition - March 7, 2018 Workshop Night - JLPM, LLC. 13