fes inhouse paint inspection guideline suppliers

30
FES – Painting & Inspection Guidelines CQ / FF / 003 dt 23. 01. 2012

Upload: achuthan-kannankutty

Post on 01-Jan-2016

109 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection Guidelines

CQ / FF / 003 dt 23. 01. 2012

Page 2: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 1 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Scope:

This document is a Guideline covering the usage of recommended paint , painting process

for FES, process parameters of FES painting, Quality criteria of painted FES Inspection,

repair methodology of the paint defects & quality certification before dispatch to Ashok

Leyland.

Objective:

i. To guide the FES painting Suppliers to ensure the quality of painting in both appearance

as well as in corrosion protection performance of the FES supplied to Ashok Leyland.

1.0 Guidelines:

FES painting Suppliers of Ashok Leyland shall adhere to the following guidelines in the

usage of recommended process, paint, consumables, Inspection of painted vehicle, repair of

paint defects, testing of various parameters for measuring the short term & long term

properties of paint , monitoring , recording & preservation of the quality records.

1.1 FES & its child parts shall be painted using only the recommended paint & process

mentioned in the Annexure A. Supplier shall ensure the surface coating quality of FES child

parts to meet Ashok Leyland Surface protection requirements standard ALS 268.03.

FES Liquid painting supplier shall maintain adequate records of monitoring the process

parameters mentioned in Annexure A.1

1.2 FES shall be classified into the appearance zone mentioned in Annexure B.1.

Inspection of the Painted FES shall be carried out based on the zone wise quality criteria

mentioned in the Annexure B.2.

Inspection of the Paint Defects on FES shall be done based on the frequency given in

Annexure B.3.

1.3 Possible issues with paint mixing & its root causes shall be understood by the FES

painting supplier based on the guidelines given in the Annexure C & appropriate remedy

shall be taken to ensure paint quality.

Page 3: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 2 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

1.4 Possible root causes of the Paint defects shall be understood by the FES painting

supplier based on the guidelines mentioned in the Annexure D & appropriate preventive &

corrective action shall be taken to avoid recurrence.

1.5 Identified paint defects shall be rectified based on the repair guidelines given in the

Annexure D.1.

1.6 PU Touch up of certain paint defects shall be done based on the guidelines given in the

Annexure D.2.

1.7 FES painting supplier shall incorporate the best process of PU Touch up by

understanding the Do’s & Don’ts of the PU painting process given in Annexure D.3

1.8 FES painting supplier shall use only the recommended Tools & consumable mentioned

in the Annexure E for paint mixing, painting , repair & Touch up.

1.9 FES painting supplier shall confirm the receipt paint quality by doing receipt inspection

for all the parameters mentioned in Annexure F & own the responsibility of the quality of

paint used for FES painting. The supplier shall equip himself with the adequate Lab facility

for testing.

2.0 FES Inspection & defect rectification shall be recorded in the FES Painting Inspection

card (Refer Annexure G) for every FES dispatched to Ashok Leyland.

The Inspection cards shall be retained & preserved for a minimum period of 2 years from the

date of dispatch to Ashok Leyland.

Page 4: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 3 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

FES Painting

Child parts

Paint raw material

Sheet Metal

Quality Approval

Repair

Inspection

SCOPE of Guideline

ALS 268.03

FES Painting Process:

OK

Not OK

OK

Page 5: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 4 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure A. Recommended Paint & process:

Part name Option 1 Option 2

Primer Top coat Primer Top coat

FES Skin Liquid Painting:

Primer (715633)

Liquid Painting:

Berger Body Bake

Enamel Golden

Brown (036432)

FOP & Side

grills

CED:

NIPA / APPG /

BASF

Liquid Painting:

QD Auto Enamel

S/G AL Black

(B31J26)

CED:

NIPA / APPG /

BASF

PP Powder Coating:

Akzo – JN195N /

JN103N /

Marpol - 99-01001 /

Jotun - 1027028 /

Berger – 312J26.

Bottom grill

CED:

NIPA / APPG /

BASF

Liquid Painting:

Berger Body Bake

Enamel Golden

Brown (036432)

Mud guard

Mud guard

Stay

Under body Liquid Painting:

Primer (715633)

Liquid Painting:

Berger Body Bake

Enamel Golden

Brown (036432)

Touch Up

PU paint:

B’Thane L/B UC

Golden Brown

(475432)

Thinner & additive used shall be based on the above Paint supplier recommendations.

Pretreatment Chemicals used shall be only from Henkel / NIPA / Chemetall rai / APPG.

Shade detail:

Shade Parameter

Golden Brown L : 46.889; a: 18.407; b: 27.291; c:32.918; H: 55.979

Matt Black RAL 9005

Page 6: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 5 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure A.1 - Recommended process parameters – FES Liquid painting:

Process parameter

Process Value Inspection Frequency

Coating

weight

Dicationic

phosphating > 3.5 gsm

Once/ Shift Tricationic

phosphating > 2.5 gsm

Layer wise

DFT

Primer 30 Once / shift

Top coat 20 Refer Annexure B.2

Baking EMT Curing Time above 130c : 30 min Every Month

Compressed

dry air spec

Dew point + 10 deg C @ 6 bar as per ISO 8573-1

(Class 6)

Every Month Dust content

Less than 0.1 microns & 0.1 mg/m3

concentration as per ISO 8573-1

(Class 6)

Oil content Less than 0.01 mg/m3 as per ISO

8573-1 (Class 1)

Page 7: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 6 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure B – Quality criteria of painted FES:

B.1 Classification of FES into Appearance zones.

Classification Parts covered

Zone 1 False Panel, Corner Panel, Embellisher, Bottom grill, Side

grill (LH/RH), FOP.

Zone 2 Foot step, Wing end step (LH / RH).

Zone 3 Floor , Rear Facia & Mud guard (LH/ RH) , Under body &

all other parts.

Page 8: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 7 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure B.2 - Zone wise acceptance criteria of most common paint defects:

1. DFT:

Description Zone - 1 / 2 / 3 – 13 points (Refer Annexure G – DFT measurement locations)

Flat surfaces 50µ ~ 120

Within 5 cm from

Corners / Edges 40 ~ 100

2. Gloss:

Description Zone - 1 / 2 / 3

Flat surfaces Golden Brown - Min 90 @ 60, Black – 50 ~ 60@ 60

Within 5 cm from

Corners / Edges Not applicable

Description Zone - 1 / 2 / 3

MEK Solvent rub test No peel off or discoloration

3. Paint film Under bake:

Description Zone 1 Zone 2 Zone 3

Visible at a distance

of 2m from surface Zero

Visible only on close

observation Zero Max 3mm Max 5mm

4. Paint Sag / rundown:

Description Zone – 1 / 2 / 3

Visible Not acceptable

5. Paint crack / Touch mark:

Page 9: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 8 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

6. Paint Overspray:

7. Paint poor hiding:

8. Paint Crater / Pinhole (For every 100cm x 100 cm surface area):

Description Zone 1 Zone 2 Zone 3

Heavy roughness &

Color variation (Touch feel)

Not acceptable

Light roughness but

no color variation Not acceptable Not acceptable Acceptable

Description Zone 1 Zone 2 Zone 3

Primer is visible Not acceptable

Slight color

difference on close

observation

Not acceptable Acceptable

Size of defect Zone 1 Zone 2 Zone 3

Φ > 1mm Zero

Φ 0.5 ~ 1mm Zero Max 3 Max 5

Φ < 0.5mm Zero Max 5 Max 10

9. Dust / Contamination (For every 100cm x 100cm Surface area):

Size of defect Zone 1 Zone 2 Zone 3

Φ > 1mm Zero Max 5 Max 10

Φ 0.5 ~ 1mm Max 2 Max 10 Max 15

Φ < 0.5mm Max 5 Max 10 Max 15

Forms of Dust:

Lint; Sanding dust; Booth dust; Oven dust; paint dust; Contamination,etc.

Zone wise acceptance criteria of paint defects - Continued

Page 10: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 9 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

10. Orange Peel:

11. Color Mismatch:

Description Zone 1 Zone 2 Zone 3

Visible at a distance

of 2m from surface Not acceptable

Visible only on close

observation Not acceptable Acceptable

Description Zone 1 Zone 2 Zone 3

Visible at a distance

of 2m from surface Not acceptable Acceptable

Visible only on close

observation Not acceptable Acceptable

Instrumental Color

difference to std

panel

Delta E < 3.0 Delta E < 4.0

Instrumental Color

difference to adjacent

parts

Delta E < 1.0

12. Cross Hatch Adhesion:

Description Zone – 1 / 2 / 3

In a 10 x 10 square lattice of 2mm.

Exfoliation along straight line & square

broken more than 50%.

Not acceptable

13. Sanding Mark:

Description Zone 1 Zone 2 Zone 3

Substrate

Sanding mark Not acceptable Acceptable

Polishing sanding

mark Not acceptable Not applicable

Zone wise acceptance criteria of paint defects - Continued

Page 11: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 10 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

14. Paint Wrinkling:

Description Zone 1 Zone 2 Zone 3

Visible at a distance

of 2m from surface Not acceptable

Visible only on close

observation

Description Zone 1 Zone 2 Zone 3

Visible at a distance

of 2m from surface Not acceptable Acceptable

Visible only on close

observation Not acceptable Acceptable

15. Paint Blistering:

Zone wise acceptance criteria of paint defects - Continued

Description Zone 1 Zone 2 Zone 3

Visible at a distance

of 2m from surface Not acceptable

Visible only on close

observation

16. White patches:

Other paint defects like Acid attack, Bird droppings, Bits, Bleaching, Bleeding,

Blooming , Blowing, Blushing, chalking, Fading, Fish eye, Water marks, etc. are

also not acceptable in any of the Zones & shall be rectified based on the paint

supplier recommendations.

Page 12: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 11 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure B.3 - Painted FES - Inspection Frequency :

S.No Check points Inspection Frequency by

FES supplier

1 DFT Every 4th FES.

2 Gloss Once / hr.

3 Paint Film under bake – Solvent rub Once / hr.

4 Paint Sag / Rundown

Every FES

5 Paint Crack / Touch mark

6 Paint Overspray

7 Paint poor hiding

8 Paint Crater / Pinhole

9 Dust / Contamination

10 Orange Peel

11 Color Mismatch

12 Cross Hatch adhesion Once / Shift

13 Sanding Mark

Every FES

13.1 Polishing Mark

14 Wrinkling

15 Blistering

16 White patches

Other Paint defects

Page 13: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 12 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure C - Most common paint mixing issues, possible root cause

& remedy:

Defect Possible root cause Remedy

1. Paint settling

Improper stirring

Paint shall be discarded

Long storage

High atmospheric temperature

Non compatible thinner, etc.

2. Gelling

Contaminated mixing tools

Paint shall be discarded

Non compatible thinner

Usage of Touch up paint more than Pot Life, etc.

3. Paint dissolution

Usage of Touch up paint more than Pot Life

Non compatible thinner

Usage of expired paint, etc.

4. Skin formation

Air entry into paint / hardener / thinner container Reject paint

High atmospheric temperature, etc.

5. Paint Air bubble

Improper paint mixing Ensure agitation

Non compatible thinner Modify thinner

Mixing of Compressed air direct in paint, etc. Stop practice

6. Paint dust / contamination

Improper filtration Re-filter & use

Improper agitation, etc.

Page 14: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 13 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure D : Most common Paint Defects & possible root causes:

Defect Possible root causes

1. Low DFT

Low viscosity

Booth air imbalance

Inadequate lighting, insufficient or cramped working space, inaccessibility of surfaces

Poor spraying technique, spray gun too far from surface, incorrect compressed air pressure, incorrect nozzle adjustment

Poor application Technique, etc.

2. Loss of Gloss - Haziness

High roughness of substrate

Inadequate or excessive dilution

Non- compatible thinner

Thin coating film

Slow evaporation of the solvent

Drying at High humidity (Above 90% RH)

Improper mixing

Solvent fumes or exhaust gases attacking the surface

Use of strong detergents or cleaners on a newly painted surface

Insufficient air circulation in booth, etc.

2.1. Touch up - Gloss variation

Improper Paint touch up without merging thinner

Localized polishing

Non compatible thinner, etc.

3. Paint under bake

Improper mixing of paint

Non compatible thinner

Low EMT, etc.

Page 15: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 14 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Defect Possible root causes

4. Running / Sagging

Incorrect viscosity of the paint

Air or surface temperature too low

Use of poor quality or incorrect thinner

Excess thickness of application, air pressure too low, fan width too narrow, spray gun too close to the surface or moving too slowly

Excessive dilution of the paint causing low viscosity

Painting over Smooth surface, etc.

5. Crack Poor paint mixing, Incompatible thinner, contaminated substrate, over baking, Expired paint life, etc.

6. Overspray

Booth air Imbalance

Non masking of the adjacent surface during Touch up

Compressed air pressure too high

Inadequate extraction or ventilation

Non removal of the Touch up overspray with thinner after baking, etc.

7. Poor hiding

Thin Top coat film

Inadequate lighting, insufficient or cramped working space, inaccessibility of surfaces

Poor Spraying Technique

Top coat not stirred before use, etc.

8. Pin Hole

Fast evaporating solvent

Poor flash off before drying

High baking temperature

Air Bubbles in the paint mixing

Immediate exposure to high temperature, etc.

Most common paint defects & Possible root causes: Continued

Page 16: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 15 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Defect Possible root causes

8.1. Crater

Contamination (Oil/grease/ water,etc) of the substrate not removed before painting

Contaminated mixing tools or equipment

Silicone in the environment or on the surface of the substrate

Moisture / Oil / dust in the compressed dry air or booth air supply, etc.

9. Dust / Contamination

Poor cleaning of the substrate

Cloth, booth & Oven Contamination

Improper / No filtration of the paint

Poor agitation of the paint, etc.

10. Orange peel

Paint incorrectly mixed, wrong viscosity, poor quality or incorrect thinner

Poor spraying technique, spray gun too far from surface, incorrect compressed air pressure, incorrect nozzle adjustment

Poor atomization of the paint

Low or High paint film thickness

Incorrect ambient or surface temperature

Long or very short flash off time between coats, etc.

11. Color Mismatch

Improper mixing of the Top coat

Low DFT of the Top coat

Poor PU Touch up

Usage of NC based paint, yellowing epoxy & alkyd based paints for Touch up - Yellowing

Usage of unapproved paints, Over baking of paint, etc.

Most common paint defects & Possible root causes: Continued

Page 17: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 16 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Defect Possible root causes

12. Adhesion failure

Contamination (Oil/grease/ water, etc.) of the substrate not removed before painting

Poor phosphating of the CR sheet (Improper substrate preparation)

Non compatibility between primer & Top coat

Non compatible thinner

Paint film under bake or over bake

Painting over smooth surface without sanding, etc.

13. Sanding Mark

Deep / Coarse sanding of the substrate

Wrong sanding disc & method

Low coating thickness, etc.

13.1 Polishing Mark

Polishing over Uncured paint surface

Excessive pressure applied in polishing

Coarse polishing paste

Polishing immediately on the hot surface from oven

Worn out Polishing head, etc.

14. Wrinkling

Painting over unset primer before flash off

No compatibility between primer & top coat

Excessive film thickness

Non compatible thinner

Prolonged drying time

Immediate exposure to high temperature, etc.

Most common paint defects & Possible root causes: Continued

Page 18: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 17 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Defect Possible root causes

15. Blistering

Painting on a hot surface

Paining on contaminated surface

Non compatible thinner

Exposure to rain or moisture before paint curing

Moisture migration thru paint surface, etc

16. White patches

Moisture entrapment before painting

Exposure to moisture or contamination before paint curing

Non compatible thinner

Water contamination of paint , etc

Most common paint defects & Possible root causes: Continued

Page 19: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 18 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure D.1 : Guideline for rectification of most common Paint defects.

Defect Condition

Repair Methodology D

ry

san

di

ng

Wet

Sa

nd

ing

Air

Blo

w

Cle

anin

g

PU

To

uch

u

p

Mer

gin

g Th

inn

er

Ho

t ai

r b

low

/ IR

h

eat

Polis

hin

g

Bat

ch

chan

ge

Rep

ain

tin

g

Reb

akin

g

Scu

ff

Orb

ital

1.Low DFT

Full Body

Part

2.Gloss

Full Body haziness

Under curing

Touch up Paint

Poor Touch up

3. Paint Under bake

4.1 Sag

4.2 Run down

5. Crack / Touch Mark

6. Over spray

Body paint

Touch up

7. Poor Hiding

Page 20: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 19 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Defect

Possible general root Cause

Repair Methodology D

ry

San

din

g

Wet

Sa

nd

ing

Air

Blo

w

Cle

anin

g

PU

To

uch

up

Mer

gin

g Th

inn

er

Ho

t ai

r b

low

/ IR

h

eat

Polis

hin

g

Bat

ch

chan

ge

Rep

ain

tin

g

Re

bak

ing

Scu

ff

Orb

ital

8. Crater / pinhole

9. Dust

9.1 Contamination

10. Orange Peel

11. Color Mismatch

Body Paint

Body paint Under curing

Paint

Touch up Under curing

12. Adhesion Failure

Substrate / Poor PT

Etch prim

er

Under baking

Over baking

Etch prim

er

Guideline for rectification of most common Paint defects - Continued

Page 21: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 20 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Defect

Possible general root Cause

Repair Methodology D

ry

San

din

g

Wet

San

din

g

Air

Blo

w

Cle

anin

g

PU

To

uch

up

Mer

gin

g Th

inn

er

Ho

t ai

r b

low

/ IR

hea

t

Polis

hin

g

Bat

ch c

han

ge

Rep

ain

tin

g

Re

bak

ing

Scu

ff

Orb

ital

13. Sanding Mark

Substrate

Polishing

14. Wrinkling

Local

Full body Option

15. Blisters

16. White patches

Refer Annexure D.2 for Guideline on PU Touch up.

Guideline for rectification of most common Paint defects - Continued

Page 22: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 21 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

C.1 Paint Touch up – Process :

Step Process Purpose Photo

1 Substrate cleaning

Clean the dust, contamination, water, grease / oil or any other contamination – Clean dry cloth

2 Sanding To remove the contamination & prepare the substrate for paint adhesion.

3 Air Blow Remove the dust generated by sanding operation

4 Cleaning To remove the sticky dust particles using Tack rag.

5 Paint Touch up Defect rectification

6 Merging thinner application (Optional)

To merge the wet PU film with the Body paint

7 Drying Cure the paint film with Dryer

8 Wet Sanding To prepare the paint film smooth for polishing

9 Polishing To level out the gloss of the Touched up surface similar to non painted surface

Annexure D.2 - Guideline for PU Paint Touch Up:

Page 23: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 22 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Description Do’s Don’ts

Painting Location Inside paint Touch up booth

In open yard or under shed without exhaust

Surface preparation

Water contamination

Clean the surface with air blow, Dry cloth, followed by IPA & dry cloth.

Without cleaning & paint over water contamination

Dust/ contamination

Clean the surface with air blow, dry cloth & paint

Without cleaning & paint over dust/ contamination

Grease / Oil contamination

Clean with a separate dry clear cloth

Without cleaning & paint over grease /oil

Sanding for better adhesion

Usage of appropriate sand paper as per defect

Usage of inappropriate sand paper

Cleaning cloth

Usage of dry, clean & white cloth

Usage of waste cloth

Separate cloths for Dry wipe, water & grease

Usage of same cloth for all types of cleaning

IPA dispensing Thru Solvent dispenser Direct from container

Logo / Emblem & other plastic components Masking & no overspray Painting over the surface

Air Compressor line, reservoir & filter element

Drain the water collected every shift

No draining of the collected water

Paint Mixing

Paint storage In ventilated storage room

Open yard or non-ventilated room

Location Inside booth or paint kitchen

In open yard or shed

Paint Mixing – Paint, Hardener & Thinner

As per paint supplier recommendation

As per operator decision

Paint Mixing container

Closed Container Open container

Annexure D.3: PU Paint Touch Up – Do’s & Don’ts:

Page 24: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 23 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Description Do’s Don’ts

Paint Mixing

Paint storage container

With agitator No agitator

Paint filtration Thru Filter material Thru cloth

Paint viscosity measurement

Check with Ford Cup B4 No checking

Paint storage after mixing

Maximum 4 hours More than 4 hours

Paint mixing record Maintain time log for every lot of paint mix up

No monitoring of paint mixing time

Paint application

Spray gun Conventional gun with 0.8mm/ 0.9mm Nozzle

Conventional gun with 1.2 mm Nozzle

Condition of Spray gun

No paint leakage from gun

Paint Leakage from gun

Spray gun air pressure

4 ~ 5 bar More than 5 bar

Spray gun distance from surface

25 ~ 35cm Spray from long or short distance

Paint overspray Clean with Solvent No cleaning

Painted vehicle exposure to open atmosphere

After baking & polishing After painting without baking

De masking Removal of the masks after painting

No removal of mask & send to dispatch

Safety of workers Wear PPE Not wearing PPE

PU Paint Touch Up – Do’s & Don’ts : Continued

Page 25: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 24 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure E - Recommended Tools & Consumables for painting

& repair of paint defects:

Operation Tools & Consumable

Paint Mixing Ford Cup B4

Measuring jar & scale

Dry Scuff Sanding P 600 grit sandpaper – Cut / round

Round Sanding pad

Dry Orbital Sanding P 400 grit sandpaper - round

Orbital sander

Air Blow Air gun

Dry sanding – Wiping Tack rag

White, Clean & Lint free cloth

Wet Sanding P 2000 grit sandpaper

Sanding block

Wet sanding - Wiping White, Clean & Lint free cloth

Paint Spray gun

Booth Conventional / HVLP / Electrostatic gun with 1.2mm Nozzle

Touch up Conventional / HVLP gun with 0.8 mm/ 0.9mm Nozzle

Touch up paint Drying Hot air Blower / Infra Red Lamp

Polishing

2500 rpm Polishing Tool

Polishing pad with 3” / 5” / 12’’ wool

Paste Glaze (3M)

* Required facility for FES painting, repair & Touch up process shall be captured in the

process & facility audit of Ashok Leyland – CQ Team.

Page 26: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 25 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure F – Inspection parameters for every Paint batch (Primer / Topcoat):

Parameter Criteria Remarks

Solvent rub test (30% Toluene

& 70% Iso Octane)

No discoloration & surface alterations –

20 Double rubs

Self

Inspection by

FES Painting

supplier

Pencil hardness min HB

Cross cut adhesion

In a 10 x 10 square lattice of 2mm.

- No exfoliation along a straight line.

- No square broken up to 50% of the

area.

Scratch hardness Min 3000g

Impact resistance (ball dia – ½”,

Weight – 500g

Height – 50 cm)

No film crack & exfoliation.

Visual color difference Same as reference panel

Gloss @ 60 Refer Annexure B.2

Gloss o

meter or

Paint Test

certificate

Acid resistance (0.1n H2So4

soln.) – 20±2ºc / 8h

No surface defect on the film after

washing with DM water

Paint

manufacturer

Test

certificate

Alkali resistance (0.1n NaOH

soln.) – 20±2ºc / 8h

No surface defect on the film after

washing with DM water

Erichsen cupping No cracks up to 5mm indentation.

Resistance to UV light

alternating with humidity (200

hrs.) - Irradiance: 0.47 w/m2/nm

- Chalking & film cracking not

allowed.

- Gloss variation 15%

- No color variations are allowed.

Resistance to humidity

(500hrs @ 40±2°c – 95% ~

100% RH)

No film removal and blistering are

allowed. Min 80% of adhesion should be

retained

Water resistance

(40ºc / 240hrs)

No surface defect on the film. shall pass

adhesion at 2mm square

Corrosion resistance

(300 hrs. for CR Panel /

components) As per ASTM

B117 – Min 500 hrs. for CED

coated components

Edge masked and damage free

component, the following are not

allowed:

- Corrosion focuses on weld

junctions and surfaces in general

- Blistering.

Under pellicular corrosion ≤2mm

Submit

samples on

Line

condition &

get it tested

from Paint

manufacturer

Please refer Surface protection requirements standard ALS 268.03 for testing Methods.

Page 27: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 26 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

1 3 2

4 5

13

12

8

7

11

Annexure F.1 - DFT Inspection Template:

9

10

6

Page 28: FES Inhouse Paint Inspection Guideline Suppliers

FES – Painting & Inspection

guidelines

Page 27 of 28

REF: CQ / FF / 003

DATE: 23.01.2012

Annexure G - FES Inspection Card:

Page 29: FES Inhouse Paint Inspection Guideline Suppliers

1, Sardar Patel Road, Guindy, Chennai – 600 032.

Page 30: FES Inhouse Paint Inspection Guideline Suppliers

VISION

To be among Global Top 10 in Trucks & Top 5 in buses.

QUALITY POLICY

Ashok Leyland is committed to achieve customer satisfaction, by anticipating

and delivering superior value to the customers in relation to their own business,

through the products and services offered by the Company and comply with

statutory requirements.

Towards this, the Quality Policy of Ashok Leyland is to make continual

improvements in the processes that constitute the quality management system,

to make them more robust and to enhance their effectiveness and efficiency in

achieving stated objectives, leading to:

• Superior products manufactured as also services offered by the Company.

• Maximum use of employee potential to contribute to quality and

environment, by progressive up gradation of their knowledge and skills as

appropriate to their functions.

• Seamless involvement from vendors and dealers in the mission of the

Company to address customers’ changing needs and protection of the

environment.

Managing Director January, 2007

1, Sardar Patel Road, Guindy, Chennai – 600 032.