FERNALD CLEANUP PROGRESS BRIEFING. 6:30 p.m. 6:35 p.m. Waste Pits SEPTEMBER 2000 Opening Remarks Project Updates Remedial Action Project Gary Stegner Dave Lojek Soil & Disposal Facility Projects Decontamination & Dismantlement John Trygier Silos Project Nina Akgunduz Aquifer Restoration/Wastewater Project Rob Janke Waste Generator Services Randy Janke Rob Janke Question and Answer Session 8:30 p.m. Adjourn I .- Graphics # 6563.0A 9/00

Upload: others

Post on 27-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

FERNALD CLEANUP PROGRESS BRIEFING.

6:30 p.m.

6:35 p.m. Waste Pits

SEPTEMBER 2000

Opening Remarks

Project Updates Remedial Action Project

Gary Stegner

Dave Lojek

Soil & Disposal Facility Projects

Decontamination & Dismantlement John Trygier

Silos Project Nina Akgunduz Aquifer Restoration/Wastewater Project Rob Janke

Waste Generator Services Randy Janke

Rob Janke

Question and Answer Session

8:30 p.m. ’ Adjourn

I . -

Graphics # 6563.0A 9/00

Page 2: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

PROJECT NEWS WASTE PITS REMEDIAL ACTION

PROJECT Rail transportation

Waste pit excavation - 28 trains (167,000 tons) to Envirocare

- 30 percent of Pit 3; 20 percent of Pit 1 - Place an average of 800 cubic yards of

material into railcars daily Safety Awards - Fluor Corp. Tri Star Award (250,000

- IT Corp. Safety Award (over 1,000 days hours w/o lost time injuries)

w o lost time injuries)

Graphics # 6563.1A 9/00

Page 3: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

PROJECT NEWS SOIL & DISPOSAL FACILITY

PROJECT 120,000 implace cubic yards in On4ite Disposal Facility, end of July

- Cell 1, 98 percent complete; capping in 2001 - Cell 2, 51 percent complete

- Cell 3, 16 percent complete Resumed clay screening in the Borrow Area in July;

Issued RFP for capping of Cell 1 in July; contract to

Ongoing construction of the Enhanced Permanent

stockpiling for Cell 1 cap

be awarded in October

b Leachate Transmission System Graphics # 6563.2A 9/00

Page 4: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

PROJECT NEWS SOIL & DISPOSAL FACILITY

PROJECT Met with Ohio Department of Transportation and Hamilton County; discussed recent traffic study recommendations Excavated more than 600,000 bulk cubic yards from Southern Waste Units and surrounding areas; 165,000 bulk cubic yards this year; less than 12,000 cubic yards remain to complete excavation at the SWUs

percent ( 3 1 percent approved by EPA-7 percent pending) of site has been certified as meeting cleanup levels

Ongoing certification of soils; approximately 38

Graphics # 6563.2B 9/00

: L.

Page 5: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

ENHA PERMA E NSMISST S E

Photo taken August 2000 Crapliies # 6563.2C 9/00 I’lioto # 73YY-LI18H

Page 6: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

ENHANCED PERMANENT LEACHATE 1 _ - - TRANSMISSION SYSTEM . %'

Photo taltcn August 2000 Grupliics # 6563.21) 9/00 I'lioto # 7399-D166

Page 7: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

.. . . . . . . . . . . .. ,

BORROW E

v

(;r;tphics # 6563.211 9/00. Photo # 631Y-L)256X

Photo taken J d y 2000 t

Page 8: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

GEOPROBE SAMPLING

. . . ~ . . . .

,

+.

Photo takcn April 2000 Graphics # 6563.21' 9/00 Photo # 68461)93

Page 9: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

PROJECT NEWS DECONTAMINATION 6r

DISMANTLEMENT Plant 5 - Completed demolition of Building 4B - Continued equipment. removal in Building 5A

Plant 6 - Exterior transite removal of Building 70 I

- Continued removal of interior equipment and interior demolition of the Thorium Area

Nuclear Fuel Services Tanks (Building 2E) - Completed dismantlement and demolition of four tanks and the Pump

House Security Building (28A) and Industrial Relations Building (28B) - Completed demolition of Building 28N, Main Gate Guard Post

69 E\3 - Continued removal of asbestos contaminated material in 28A & B

- Began interior demolition of 28B

Graphics #I 6563.3A 9/00 -Q

w *.

Page 10: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

PROJECT NEWS SILOS PROJECT

Silos 1 & 2 Draft Revised Feasibility Study/ Proposed Plan Project Status

Signed Silos 1 & 2 Record of Decision Amendment (ROD) on July 13, 2000

Silos 1 & 2 RFP (draft) sent to DOE-HQ for review

Addressing comments on the draft RFP

I

Graphics # 6563.4A 9/00

Page 11: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

PROJECT NEWS AQUIFER RESTORATION/

- WASTEWATER PROJECT

Approved U.S. & OEPA ReHInjection Demonstration Test Report - Continued operations of existing injection wells - Consideration of additional wells

Remediation of the Great Miami Aquifer in Waste Storage and Plant 6 Areas Preliminary Design - Preparations underway to perform pump test on

southernmost plume in order to support preliminary design of Waste Pits Groundwater Remediation Module; due to EPAs in June 2001

Graphics # 6563.5A 9/00

Page 12: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

PROJECT NEWS AQUIFER RESTORATION/ WASTEWATER PROJECT

Conceptual Design Report Conclusions

Plant 6

- Original model plume not present

- No plume greater than 20 ppb exists

Waste Storage Area

- P

Graphics # 6563.58 9/00

~ ~ ~~

- Plume smaller than RIPS finding (55 acres versus 70 acres)

- Identified three distinct plumes

- Southern plume extends further east and has uranium concentration up to 566 parts-per-billion

Page 13: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

I Coiiceii tra tion

(PPb)

30

20

10

0

'I'he Operable Uiiit 5 ROD established a discharge limit of 20 ppb for total uraniuni (effective January 1998).

1/00 2/00 3/00 4/00 5/00 6/00 7/00 8/00 9/00 10/00 11/00 12/00

Sample Date (montldycar)

Page 14: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

.. , . . . . .. . .. . . _. . .. . . ,

POUNDS OF URANIUM DISCHARGED TO THE GREAT MIAMI RIVER

IN 2000 Weight (ponncb)

700

600 - 500 -e 400

300

200

100

Operable llnits 5 ROD established annual discharge limit of 600 pounds for total uranium $.

E3 Monthly Ll Cumulativc

1/00 2/00 3/00 4/00 5/00 6/00 7/00 8/00 9/00 10/00 11/00 12/00 0

. Sample Date (montldyear) Notc: Sum of monthly discharges niay not always agree with cuniulativc total hecaiise of rounding differences.

Graphics # 6563.51) 9/00

Page 15: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare
Page 16: FERNALD CLEANUP PROGRESS BRIEFING. SEPTEMBER 2000 · PROJECT NEWS WASTE PITS REMEDIAL ACTION PROJECT Rail transportation Waste pit excavation - 28 trains (167,000 tons) to Envirocare

PROJECT NEWS '

WASTE GENERATOR SERVICES,

Shipped low level waste Nevada Test Site

Shipped nuclear materials to Portsmouth, Ohio - Over 106,000 cubic feet, in FY 2000

- 3024 metric tons uranium (MTU) since June 1999 - Equates to 80 percent of 3,801 MTU to be- shipped

Began shipping Batch 9 (16,000 gallons of liquid mixed waste) to TSCA Incinerator in Oak Ridge

I Graphics # 6563.6A 9/00