Planning and Acting in the Real World. Feng Zhiyong Tianjin University Fall 2008. OutLine. 12.1 Time. Schedules. and Resources 12.2 Hierarchical Task Network Planning 12.3 Planning and Acting in Nondeterministic Domains 12.4 Conditional Planning 12.5 Execution Monitoring and Replanning - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Feng Zhiyong Tianjin University Fall 2008

Feng ZhiyongTianjin University

Fall 2008

Planning and Acting in the Real World

Page 2: Feng Zhiyong Tianjin University Fall 2008

12.1 Time. Schedules. and Resources 12.2 Hierarchical Task Network Planning 12.3 Planning and Acting in

Nondeterministic Domains 12.4 Conditional Planning 12.5 Execution Monitoring and Replanning 12.6 Continuous Planning 12.7 MultiAgent Planning 12.8 Summary

Page 3: Feng Zhiyong Tianjin University Fall 2008

Planning so far does not specify how long an action takes, when an action occurs, except to say that is before or after another action◦ For example, in the cargo delivery domain, we

might like to know when the plane carrying some cargo will arrive, not just that it will arrive when it is done flying.

Job shop scheduling – time is essential critical path method (CPM)

◦ A partial order plan (with durations)◦ Critical path (or the weakest link)◦ Slack = LS (latest start) – ES (earliest start)◦ Schedule = plan + time (durations for actions)

Page 4: Feng Zhiyong Tianjin University Fall 2008
Page 5: Feng Zhiyong Tianjin University Fall 2008
Page 6: Feng Zhiyong Tianjin University Fall 2008

we augment our representation to include a field of the form RESOURCE: R(k), which means that k units of resource R are required by the action.

is both a prerequisite-the action cannot be performed if the resource is unavailable

When certain parts are not available, waiting time should be minimized

This make scheduling problems more complicatedby introducing additional interactions among actions.

resource constraints

Page 7: Feng Zhiyong Tianjin University Fall 2008
Page 8: Feng Zhiyong Tianjin University Fall 2008

cannot simultaneously add engine El to car C1 and engine E2 to car C2

Page 9: Feng Zhiyong Tianjin University Fall 2008

hierarchical decomposition◦ dealing with complexity◦ hierarchical methods can result in linear-time

instead of exponential-time planning algorithms. hierarchical task networks(HTNs)

◦ Plans are refined by applying action decompositions

◦ until only primitive actions remain in the plan.◦ partial-order planning →pure HTN planning.

Page 10: Feng Zhiyong Tianjin University Fall 2008
Page 11: Feng Zhiyong Tianjin University Fall 2008
Page 12: Feng Zhiyong Tianjin University Fall 2008
Page 13: Feng Zhiyong Tianjin University Fall 2008

First, the action a' is removed from P.

The next step is to hook up the ordering constraints for a' in the original plan to the steps in d'.

The final step is to hook up causal links. this approach might be too strict! Therefore, the

best solution is for each ordering constraint to record the reason for the constraint

Page 14: Feng Zhiyong Tianjin University Fall 2008

Pure HTN planning is undecidable, even though the underlying state space is finite!◦ We can rule out recursion, which very few domains require. In that case,

all HTN plans are of finite length and can be enumerated.

◦ We can bound the length of solutions we are about. Because the state space is finite, a plan that has more steps than there are states in the state space must include a loop that visits the same state twice. We would lose little by ruling out HTN solutions of this kind, and we would control the search.

◦ We can adopt the hybrid approach that combines POP and HTN planning. Partial-order planning by itself suffices to decide whether a plan exists, so the hybrid problem is clearly decidable

Page 15: Feng Zhiyong Tianjin University Fall 2008

A poor couple has only two prized possessions-he a gold watch and she her beautiful long hair. Each plans to buy a present to make the other happy. He decides to trade his watch to buy a silver comb for her hair, and she decides to sell her hair to get a gold chain for his watch.

In (b) the partial plan is inconsistent, because there is no way to order the "Give Comb" and "Give Chain" abstract steps without a conflict. (We assume that the "Give Comb" action has the precondition Hair, because if the wife doesn't have her long hair, the action won't have the intended effect of making her happy, and similarly for the "Give Chain" action.)

In (c) we decompose the “Give Comb” step with an “installment plan” method. In the first step of the decomposition, the husband takes possession of the comb and gives it to his wife, while agreeing to deliver the watch in payment at a later date. In the second step, the watch is handed over and the obligation is fulfilled. A similar method decomposes the “Give Chain” step. As long as both giving steps are ordered before the delivery steps, this decomposition solves the problem. (Note that it relies on the problem being defined so that the happiness of using the chain with the watch or the comb with the hair persists even after the possessions are surrendered.)

Page 16: Feng Zhiyong Tianjin University Fall 2008

Classical planning◦ fully observable, static,and deterministic

Four planning methods for handling indeterminacy◦ Sensorless planning(described in Chapter 3)◦ Conditional planning

Also known as contingency planning◦ Execution monitoring and replanning◦ Continuous planning

Page 17: Feng Zhiyong Tianjin University Fall 2008

CP in fully observable environments (FOE) initial state : the robot in the right square of a clean world;

the environment is fully observable: AtR ∧CleanL∧CleanR. The goal state : the robot in the left square of a clean

world.◦ Vacuum world with actions Left, Right, and Suck◦ Disjunctive effects: ◦ if Left sometime fails◦ Conditional effects: Action(Suck, Precond: , Effect: (when AtL: CleanL)

^ (when AtR: CleanR)Action (Left, Precond: AtR, Effect: AtL v (AtL ^ when CleanL: !ClearnL)

◦ Conditional steps for creating conditional plans:if test then planA else planBe.g., if AtL ^ CleanL then Right else Suck

◦ The search tree for the vacuum world (Fig 12.9) State nodes (squares) and chance nodes (circles)

Page 18: Feng Zhiyong Tianjin University Fall 2008
Page 19: Feng Zhiyong Tianjin University Fall 2008
Page 20: Feng Zhiyong Tianjin University Fall 2008

Triple Murphy

Page 21: Feng Zhiyong Tianjin University Fall 2008

◦ Initial state is a state set – a belief state ◦ Determine “both squares are clean” with local dirt

sensing the vacuum agent is AtR and knows about R, how

about L? Dirt can sometimes be left behind when the agent

leaves a clean square◦ A graph representation (Figure 12.12, p438)◦ How different between in FOE and in POE

Which one is a special case of the other?

Page 22: Feng Zhiyong Tianjin University Fall 2008
Page 23: Feng Zhiyong Tianjin University Fall 2008

Sets of full state descriptions◦ { (AtR ⋀ CleanR ⋀ CleanL), (AtR ⋀ CleianR ⋀ ¬CleanL) }

Logical sentences that capture exactly the set of possible worlds in the belief state.◦ AtR ⋀ CleanR

Knowledge propositions describing the agent's knowledge

◦closed-world assumption - if a knowledge proposition does not appear in the list, it is assumed false.

Page 24: Feng Zhiyong Tianjin University Fall 2008

◦ automatic sensing◦ active sensing: percepts are obtained only

by executing specific sensory actions

◦ Action(Left, PRECOND: AtR, EFFECT: K(AtL) ⋀¬K (AtR) ⋀ when CleanR: ¬K(CleanR) ⋀ when CleanL: K ( CleanL) ⋀ When ¬ CleanL: K(¬ CleanL))

.

◦ Action(CheckDirt, EFFECT: when AtL⋀CleanL: K(CleanL) ⋀ when AtL ⋀ ¬CleanL: K (¬CleanL) ⋀ when AtR ⋀ CleanR: K(CleanR) ⋀ when AtR ⋀ ¬CleanR: K(¬CleanR))

Page 25: Feng Zhiyong Tianjin University Fall 2008

execution monitoring: checks its percepts to see whether everything is going according to plan.◦ action monitoring◦ plan monitoring

Replanning: knows what to do when something unexpected happens:◦ call a planner again to come up with a new plan

to reach the goal

Page 26: Feng Zhiyong Tianjin University Fall 2008
Page 27: Feng Zhiyong Tianjin University Fall 2008

before carrying out the next action of plan, the agent examines its percepts to see whether any preconditions of the plan have unexpectedly become unsatisfied. If they have, the agent will try to get back on track by replanning a sequence of actions that should take it back to some point in the whole-plan.

Return to the chair-table painting problem ◦ Plan: [Start; Open(BC); Paint(Table,Blue); Finish]

What if it missed a spot of green on the table? Loop is created by plan-execute-replan, or no explicit loop Failure is only detected after an action is performed

Page 28: Feng Zhiyong Tianjin University Fall 2008

Problem

Plan: If: the agent constructs a plan to solve the

painting problem by painting the chair and table red. only enough paint for the chair

Page 29: Feng Zhiyong Tianjin University Fall 2008
Page 30: Feng Zhiyong Tianjin University Fall 2008

Plan monitoring◦ Detect failure by checking the preconditions for

success of the entire remaining plan ◦ Useful when a goal is serendipitously achieved

While you’re painting the chair, someone comes painting the table with the same color

◦ Cut off execution of a doomed plan and don’t continue until the failure actually occurs While you’re painting the chair, someone comes painting

the table with a different color If one insists on checking every precondition, it

might never get around to actually doing anything

Page 31: Feng Zhiyong Tianjin University Fall 2008

Unpainted area will make the agent to repaint until the chair is fully painted.

Is it different from the loop of repainting in conditional planning?

The difference lies in the time at which the computation is done and the information is available to the computation process◦ CP - anticipates uneven paint◦ RP - monitors during execution

Page 32: Feng Zhiyong Tianjin University Fall 2008

Continuous planning agent◦ execute some steps ready to be executed◦ refine the plan to resolve standard deficiencies◦ refine the plan with additional information◦ fix the plan according to unexpected changes

recover from execution errors remove steps that have been made

redundant Goal ->Partial Plan->Some actions-> Monitoring the

world -> New Goal

Page 33: Feng Zhiyong Tianjin University Fall 2008

Goal: On(C,D)^On(D,B) Action(Move(x,y),

Pre:Clear(x)^Clear(y)^On(x,z),Eff:On(x,y)^Clear(z)^!Clear(y)^!On(x,z))

Fig 12.15 – 12.21

Start is used as the label for the current state

Page 34: Feng Zhiyong Tianjin University Fall 2008

Steps in execution:◦ Ordering - Move(D,B), then Move(C,D)◦ Another agent did Move(D,B) - change the plan◦ Remove the redundant step◦ Make a mistake, so On(C,A)

Still one open condition◦ Planning one more time - Move(C,D)◦ Final state: start -> finish

Page 35: Feng Zhiyong Tianjin University Fall 2008
Page 36: Feng Zhiyong Tianjin University Fall 2008
Page 37: Feng Zhiyong Tianjin University Fall 2008
Page 38: Feng Zhiyong Tianjin University Fall 2008
Page 39: Feng Zhiyong Tianjin University Fall 2008

So far we have dealt with single-agent environments

multiagent planning◦ requires some form of coordination◦ possibly achieved by communication.

Page 40: Feng Zhiyong Tianjin University Fall 2008
Page 41: Feng Zhiyong Tianjin University Fall 2008

A solution to a multiagent planning problem is a joint plan consisting of actions for each agent

PLAN 1 :◦ A : [Go(A,[Right,Baseline]),Hit(A, Ball)]◦ B : [NoOp(B),NoOp(B)].

PLAN 2:◦ A : [Go(A, [Left, Net]), NoOp(A)]◦ B : [Go (B,[Right,baseline]),H it(23, Ball)]

If A chooses plan 2 and B chooses plan 1, then nobody will return the ball.◦ So the agents need a mechanism for coordination

Page 42: Feng Zhiyong Tianjin University Fall 2008

concentrates on the construction of correct joint plans, deferring the coordination issue for the time being

Based on partial-order planning the environment is no longer truly static

◦ Need synchronization For example, Plan 2 for the tennis problem

can be represented as this sequence of joint actlons:

Page 43: Feng Zhiyong Tianjin University Fall 2008

The simplest method:◦ adopt a convention

For example◦ the convention "stick to your side of the court"

would cause the doubles partners to select plan 2◦ the convention "one player always stays at the

net" would lead them to plan 1 can also use communication For example, a doubles tennis player could

shout "Mine!" or "Yours!" to indicate a preferred joint plan.

Page 44: Feng Zhiyong Tianjin University Fall 2008

Not all multiagent environments involve cooperative agents

Agents with conflicting utility functions are in competition with each other

One example:chess-playing. So an agent must◦ (a) recognize that there are other agents◦ (b) compute some of the other agent's possible plans◦ (c) compute how the other agent's plans interact with

its own plans◦ (d) decide on the best action in view of these

interactions

Page 45: Feng Zhiyong Tianjin University Fall 2008

Many actions consume resources Time is one of the most important resources Hierarchical task network (HTN) planning Standard planning algorithms assume

complete and correct information and deterministic,fully observable environments. Many domains violate this assumption.

Conditional plans allow the agent to sense the world during execution to decide what branch of the plan to follow.

Page 46: Feng Zhiyong Tianjin University Fall 2008

Execution monitoring detects violations of the preconditions for successful completion of the plan.

Replanning agent uses execution monitoring and splices in repairs as needed.

continuous planning agent creates new goals as it goes and reacts in real time.

Multiagent planning is necessary when there are other agents in the environment withwhich to cooperate, compete, or coordinate. Multibody planning constructs joint plans