Feeder Maintenance Program
The purpose of the Cooperative is to providesafe, reliable, low-cost energy services infiscally responsible partnership with its 238,000 Member-owners.
PEC MISSION STATEMENT
14,748 Miles of overhead line
2,233 Miles of URD
How can we provide
The Question?
Safe
Reliable
Low Cost Energy
Tracking and Reporting
Outage Reduction Plan
Maintenance Program
Training
Review of Operations ProceduresResources
Feeders were ranked by SAIFI, SAIDI,and quantity of interruptions
Creating a Maintenance Program
Set up a scope of work
Contracted with Utility Support System (USS) to perform inspections (6 one-person crews)
Inspection Process
Poles
Hardware
Inventory Facilities
Minor ConstructionInspect guy wireInstall wildlife protectionRepair pole grounds
Construction Process
Major ConstructionCrossarms Insulator ReplacementCutoutLightning ArrestorGuy WireLight Tree TrimmingGround RodsPole change outs
Total Outages
Feeder Maintenance Results
2005
2006
2007
5,916
5,332
7,078
2008
2009
2010
4,473
5,424
3,331
OT Hours105,480
107,044
155,785
112,110
100,754
78,907
Overtime Savings $3,011,776
2005
1.21
Feeder Maintenance Results
2010
0.75
SAIDI
OutagesCauses 2005
Lighting 2318
Animals 1135
Transformers 412
Trees 436
Total Outages 5916
2010 Reduced
1487 36%
531 53%
211 49%
217 50%
3331 44%
In 2007 our tree outages were at 8% because of this several of our Districts took an aggressive approach to tree trimming.
Tree Trimming
Tree Trimming was Excluded from Scope of Services
PEC developing a 5yr Comprehensive Cycle Plan
In 2010 our tree outages were 6.6%
Feeder Maintenance Cost
Inspection and Minor construction $ 4,863,991
Major Construction
$ 3,011,776 Overtime Savings
Tree Trimming $33,342,393
$ 5,161,661
$8,673,609
Average Cost Per Year
Average Cost Per Member
Per Year $36.44
Per Month $ 3.04