falcon spire contract management training for …...the splitting of nzs 3910:2003 was split into 3...
TRANSCRIPT
Construction ContractsNZS 3910 | NZS 3915 | NZS 3916 | NZS 3917
www.falcontraining.comIt’s good to know
Delivered byFalcon Training & Spire Consulting
1
Housekeeping1. Emergency procedures
2. Comfort breaks3. Refreshments:
Morning tea, Lunch, Afternoon tea
4. Wifi5. Mobile phones & laptops6. Online Feedback7. Access soft copy materials:
www.falcontraining.com/templates Access code: CMT17
2
Workshop Objectives Gain familiarity with the most widely used construction
contracts in New Zealand
Understand the characteristics, features, advantages and disadvantages of each series
Review the key aspects of Contract law
Managing contracts – day to day
Practical tips in adopting construction contracts
3
Agenda
4
Background &
Introduction
Background &
Introduction
NZS 3910‐15‐16 Series
NZS 3910‐15‐16 Series
NZS3604 StandardNZS3604 Standard
Managing Contracts
(NZ3910‐5‐6)
Managing Contracts
(NZ3910‐5‐6)
Summary and real life feedback
Summary and real life feedback
LunchLunch
Paul A. Rogers; M.Bldg.Sci, Dip.Env.Mgt, Dip.En.Mgt, M.IPENZ, F.FMANZ M.IoD is the founder and Managing Director of the New Zealand based management consultancy firm Spire Consulting Ltd. Paul specialises in strategic procurement and supply chain optimisation, asset and facilities management, and organisational performance improvement. Based in Christchurch, New Zealand, Paul consults to a wide variety of clients from Qatar to Queenstown in the local and central government sector, health, infrastructure, petro‐chem, utilities, manufacturing and commercial property environments.
Current Focus = Principal Procurement Advisor to Christchurch City Council for the Infrastructure Rebuild & Southern DHB Alliance.
Paul has previously been a visiting lecturer on the MSc Asset Management Programme at Hong Kong Poly University, and is a regular guest presenter at Canterbury University in the Commerce & Marketing dept.
Paul, has 35 years experience in asset & facilities management having worked for J.P.Morgan, Lloyds of London, Colliers Jardine and AMP Investments. Prior to forming Spire Consulting, Paul was National Manager – Facilities Management at Telecom New Zealand where he was responsible for the contract and performance management of New Zealand’s largest facilities management portfolio.
Contact: Email: [email protected]:+64 (27) 4400 867. www.spireconsulting.co.nz
5
About your Presenter
Now you…
Your Name & Role
Context of involvement in this Workshop
Top 3 aspects you are seeking to learn from this workshop today
Anything else to contribute to our session today – that we should know?
6
Construction Contracts –Background and Introduction
7
Background & IntroductionBackground & Introduction
NZS 3910‐15‐16 Series
NZS 3910‐15‐16 Series
NZS3604 StandardNZS3604 Standard
Managing Contracts
(NZ3910‐5‐6)
Managing Contracts
(NZ3910‐5‐6)
Summary and real life feedbackSummary and
real life feedback
In this section we’ll review:
Contract options and forms
The NZ3910-5-6 series vs NEC series
Characteristics, features, advantages and disadvantages of each series
Practical application and requirement to use the NZ 3910-5-6 series
Basic contract law
Fair and reasonable approaches to contracting
Practical tips in adopting construction contracts
8
Construction Contracts
9
NZ Construction Contracts: The 3910/5/6/7 (2013) Suite
Designed for New Zealand conditions by New Zealand Lawyers and
Engineers.
The splitting of NZS 3910:2003 was split into 3 separate contracts (10/16/17).
(3917 is a fixed term Contract for services including maintenance).
2013 standards easier to follow with tick-box type tables for Special
Conditions and include additional standard form documents (to save
parties developing their own).
10
NZ Construction Contracts: The 3910/5/6/7 (2013) Suite cont.
Among the substantive changes, the payment system has been simplified
and contains different time periods and there is greater certainty about
responsibility for arranging insurance and paying deductibles. The conditions
are also aligned with the Construction Contracts Act 2002 and 2015
Amendment.
Standards NZ says the 2013 contracts “reflect a fair risk allocation between
the parties, minimizing the degree of Special Conditions”
3915 – same as 3910 but no Engineer to the Contract11
Contracts –What to useExample
12
Getting to Contract – Conditions of Tendering
13
Getting to Contract – Conditions of Tendering
14
Construction Contract Choices Choices depend on your specific needs.
Let’s discuss your experiences with these forms ….
Build Design Build / Construct Maintain NZS 3910 (2013) NZS 3916 (2013) NZS 3915 (2005)
NEC. Engineering & Construction Contract (ECC)
NEC. Engineering & Construction Contract (ECC)
NEC Term Service Agreement (TSC)
FIDIC, JCT, ICE
15
NEC Suite
16
NEC Vs 3910/5/6 /7 high level comparison
NEC seen by the industry as a more collaborative agreement (the language is more ‘equitable’). The NEC Agreements have processes that force parties to communicate clearly and in a timely manner (Early Warning – Compensation Events etc.). No ‘Engineer to the Contract’ with NEC3910 slightly more litigious (focuses more on liabilities and risk allocation) NZS Suite far more prevalent in NZ. Widely known, understood and accepted by NZers. ‘Written by Kiwis, for Kiwis…’
17
NEC Vs 3910/5/6 /7 high level comparison
My Opinion:
18
“Both agreements work when both parties understand their roles
and contractual commitments. Collaboration is a behaviour and
attitude and no contract document can replicate the approach and
communication required to deliver project success.”
“Both agreements work when both parties understand their roles
and contractual commitments. Collaboration is a behaviour and
attitude and no contract document can replicate the approach and
communication required to deliver project success.”
19
Series Best applied
3910• All construction works.• Typically works over $50k (under $50K most organizations use a ‘Minor
Works Contract’ being a slim form of 3910
3915 • As above but where there is no Engineer to the Contract
3916 • All Design and Build requirements, where the Contractor undertakes the design + physical works delivery
3917 • Used for Maintenance Term Service Agreements
Fair & Reasonable Approach's to Contracting
Correct contractor entity entered (post RFP/RFT process)
Notification of acceptance of tender/award of Contract – best practice
Contract should be signed before works commence. At the very least, a formal Letter of Award is entered into.
Post tender correspondence – e.g. agreed correspondence re tags, minutes of pre-award meetings
20
Construction Contracts:
The NZS 3910-15-16 Series
21
Background & IntroductionBackground & Introduction
NZS 3910‐15‐16 Series
NZS 3910‐15‐16 Series
NZS3604 StandardNZS3604 Standard
Managing Contracts
(NZ3910‐5‐6)
Managing Contracts
(NZ3910‐5‐6)
Summary and real life feedbackSummary and
real life feedback
In this section we’ll review:
In depth review of each contract form
Examine the meaning and application of each form
Review the roles and responsibilities of the Engineer to Contract
/ Engineers Representative / Project Manager
Contract definitions and terms
22
Construction Contracts:
The NZS 3910-15-16 Series
23
Background & IntroductionBackground & Introduction
NZS 3910‐15‐16 Series
NZS 3910‐15‐16 Series
NZS3604 StandardNZS3604 Standard
Managing Contracts
(NZ3910‐5‐6)
Managing Contracts
(NZ3910‐5‐6)
Summary and real life feedbackSummary and
real life feedback
NZS 3910 -
2013 Update
24
10 Key Changes
NZS 3910 Overview: The 2013 Updates
251 of 10
NZS 3910 Overview
261 of 10
NZS 3910 Overview
272 of 10
NZS 3910 Overview
283 of 10
NZS 3910 Overview
294 of 10
NZS 3910 Overview
304 of 10
NZS 3910 Overview
315 of 10
NZS 3910 Overview
327 of 10
NZS 3910 Overview
338 of 10
NZS 3910 Overview
349 of 10
NZS 3910 Overview
359 of 10
NZS 3910 Overview
3610 of 10
NZS 3910 OverviewExample
37
NZS 3910 Overview
38
39
NZS 3910 Overview
40
NZS 3910 Overview
41
NZS 3910 Overview
42
NZS 3910 Overview
The NZS 3910 Series
The Pitfalls & Challenges : Key Considerations
43
CONDITIONS OF CONTRACT CONSIDERATIONS – SCHEDULE 11.2/10.2: Separable Portions – where part of the Contract Works are handed over separately2.1: What type of contract? • Lump Sum – as stated in Contract, subject to adjustments (e.g.
Variations) – see 2.2.1• Measure and Value: Contract Price = measured quantity at rates
in Schedule of Prices, subject to adjustments – see 2.3.1• Cost Reimbursable: Contract Price = Net Cost + percentages for
overheads and profit or Contract rates – see 2.4.1. Records required as for Dayworks. Certain costs not claimable – see 2.4.2
44
Key considerations before entering into the Contract: Price Model
Key considerations before entering into the Contract: Price Model
5.11.3/5.11.4: Licenses/Permits – resource consent, building consent. Principal usually obtains under NZS 3910 but can set out exceptions. What management plans are required?• Site-specific safety plan• Quality plan• Traffic management plan• Environmental compliance plan
Cross refer to P&G Specification or other scope/requirements in Contract
45
Key considerations before entering into the Contract: Price Model
6.1: Engineer to Contract• External Engineer etc. • Approved List?
8: Insurance• Who is insuring what?• Are there existing structures?• What is the risk of the project?• Are there any specific items of Plant that are critical to the
works?• Is PI insurance required?
46
Key considerations before entering into the Contract: Price Model
11.5/11.6: Warranties and Guarantees• Consider what you need and from whom?• Default position is the warranties in the Contract (Schedules 13, 17
and 18)
12: Payments• Advance payments? • Default timeframes selected – 12.2.8 (although for 12.5.9 not
selected)• If Advance payment will be made Contractor must provide an
Agreement for Off-site Materials in Schedule 14
47
3910 - On-Site Overheads / Preliminary & General
On-site Overheads are defined as “expenses or losses …. for the general overall running of the Contract Works”. See 3910 CoC, Clause 1.2 Definitions (Page 6).
On-site Overheads may be considered as direct site costs of the project that cannot effectively be priced within the scheduled items, i.e., site hoardings, insurances or site management
• The costs are not directly related to changes in quantity / activity
48
NZS 3910 – The Pricing Schedule Risks
Trade Breakdowns
• Requirement for true schedule of quantities / tender documents
Elemental Breakdowns
• Most appropriate for estimating purposes
Activity Based breakdowns
• Most prevalent in my experience
49
NZS 3910 – The Pricing Schedule Risks
Trade Breakdowns
• Requirement for true schedule of quantities / tender documents
Elemental Breakdowns
• Most appropriate for estimating purposes
Activity Based breakdowns
• Most prevalent in my experience
50
Official standard - most detailed, measured in accordance
with a standard method of measurement, i.e. NZS4202.
Trades might include concrete, formwork, reinforcement,
asphalting, blockwork, GIB lining, framing, etc.
A component such as a ground floor slab is measured into
trades of concrete (m3), Reinforcement (kg), powerfloat
(m2), etc.
Each item priced in its lowest form - variations can be easily
and effectively calculated.
NZS 3910 – The Pricing Schedule Risks
s
Elemental Breakdowns
• Most appropriate for estimating purposes
Activity Based breakdowns
• Most prevalent in my experience
51
Elements include foundations, structure, roofing, external
façade, internal divisions, etc.
Measurements can be high level such as a rate/m2 for
roofing or much more detailed into components - i.e.,
specific roof sheeting + underlay + insulation x m2
component rate. Different components are measured to
total to the overall element total.
A contractor could price the component, however variation
is more difficult to calculate as you wouldn’t know what the
make-up of the component is, i.e. if you changed the
insulation you would know the correct deduction to make
from the component rate
NZS 3910 – The Pricing Schedule Risks
g
Activity Based breakdowns
• Most prevalent in my experience
52
Activities could be measured simply as 1x bridge, Entry
roads or could also in include components, i.e., bridge
supports, bridge deck, bridge balustrade, etc.
The contractor interprets the specifications and drawings
provided and prices accordingly. Many possible
interpretations leads to large pricing differences and opens
the door to contractual claims.
It is very difficult to calculate variations from this method
NZS 3910 Overview: Programmes
Programme calibrates resources (and therefore costs)
Mutually Agreed Start Date and End Date. Working days calculated.
5.10.4: Is a Comprehensive Programme required?
• Simple programme always required
• Comprehensive may be required containing critical path analysis/key dates to be met by
Principal etc. (more complex works)
• 10/20 working days for providing simple vs comprehensive
• No payment until provided
53
NZS 3910 Overview: Liquated Damages
54
NZS 3910 Overview: Liquated Damages
Liquidated Damages
• Calculated from the period between the Due Date for
Completion up until the time of Practical Completion
• Principal not Engineer notifies deduction of liquidated damages
• Engineer has no authority to waive liquidated damages
55
NZS 3910 Overview: HSE
Schedule 19 – Form of Health & Safety Monthly Reporting
• Clause 5.7.15 of Schedule 1
• If other requirements for H&S reports these should be x-referenced in Schedule 1, cl 5.17.15
56
Role of the Key Parties - Engineer
WHO IS THE ENGINEER?
“Engineer” is defined in NZS 3910 as being a professional engineer, architect, surveyor or any other single natural person named in the Special Conditions of the Contract
The Engineer does not need to hold any particular qualifications. Such a requirement is at the Principal’s discretion
While in most cases the person named as the “Engineer” will frequently be a specialist and usually be registered as an Engineer - the law does not require the Engineer to be qualified or registered to operate in that role under NZS 3910
57
Role of the Key Parties – Engineer cont.
WHAT IS THE ENGINEER’S ROLE?
Engineer – 2 roles:
1. Expert adviser to Principal
2. Independent decision maker
Engineer is ultimately critical to the smooth delivery of the
project
58
Role of Key Parties – Engineer cont.
WHAT DOES BEING THE “EXPERT ADVISOR” TO AND “REPRESENTATIVE OF” MEAN?
The Engineer is the expert advisor to and the representative of the Principal when issuing directions and providing Payment Schedules
• E.g. ordering a Variation or giving directions as to how to carry out the Contract Works
• MUST act in the interest of the Principal
• MUST notify all of the Principal’s deductions when issuing a Payment Schedule even if they disagree with the Principal’s reasons
59
Role of key parties during the Contract –Engineer cont. DOES THE ENGINEER OWE A DUTY TO THE CONTACTOR?
No
There is no contract between the Engineer and the Contractor -Engineer owes obligations to the Principal under the consultancy agreement, not the Contractor
NZ Courts have held that the Engineer does not owe a duty of care to the Contractor
60
Role of Key Parties – Engineer cont.
IS THE ENGINEER INDEMNIFIED WHEN PERFORMING THE ROLE?
As an agent, the acts/omissions of the Engineer are treated as acts/omissions of the Principal
So long as the Engineer acts within the scope of his/her authority, he/she will be indemnified by the Principal against losses and liabilities in performing his/her duties
If the Engineer has apparent or ostensible authority to order additional work, and the Contractor makes a claim, the Principal must pay the Variation (the Engineer may then be liable to the Principal if they acted outside their powers)
61
Role of key parties – Engineer’s Representative
WHO IS THE ENGINEER’S REPRESENTATIVE?
Engineer may appoint Engineer’s Representative and
Engineer’s Representative assistants by giving written
notice to the Contractor
Normally a Principal's staff member but not always
62
Role of Key Parties – Engineer’s Representative cont.
WHAT IS THE ENGINEER’S REPRESENTATIVES ROLE?
Engineer’s Representative can exercise powers of Engineer except:
1. Review matter in dispute
2. Value Variations, issue Payment Schedules, issue completion certificates, EOTs, change Drawings and Specifications UNLESS Engineer expressly authorises
3. Other powers which the Engineer excludes
Any instructions or decisions of the Engineer’s Representative are deemed to be of the Engineer, and bind the parties
63
Role of Key Parties – Project Manager
WHO IS THE PROJECT MANAGER?
Appointed by Principal to “represent” it as Principal during the Project
Need to undertake key duties such as:1. Reviewing requests for Variations
2. Reviewing provisional Payment Schedules received from Engineer and certifying deductions if required
3. Dispute Resolution
64
The Payment
Process -
example
65
Dispute Resolution Process
66
Dispute
Resolution
Process
67
Construction Contracts:
The NZS 3910-15-16 Series
68
Background & IntroductionBackground & Introduction
NZS 3910‐15‐16 Series
NZS 3910‐15‐16 Series
NZS3604 StandardNZS3604 Standard
Managing Contracts
(NZ3910‐5‐6)
Managing Contracts
(NZ3910‐5‐6)
Summary and real life feedbackSummary and
real life feedback
NZS 3916
69
NZS 3916 Overview
70
NZS 3916
Overview
71
+ 17: Deed of Novation
72
NZS 3916
Overview
NZS 3916 Overview
73
NZS 3916 Overview
74
NZS 3916 Overview
75
NZS 3917 (‘Conditions of contract for building and civil engineering. – Fixed term’) Overview
76
NZS 3917 Overview
77
Construction Contracts:
The NZS 3604 Standard
78
Background & IntroductionBackground & Introduction
NZS 3910‐15‐16 Series
NZS 3910‐15‐16 Series
NZS3604 StandardNZS3604 Standard
Managing Contracts
(NZ3910‐5‐6)
Managing Contracts
(NZ3910‐5‐6)
Summary and real life feedbackSummary and
real life feedback
In this section we’ll review:
Review use and application of the standard
Address issues and challenges experienced with this
standard
79
NZS3604 Standard Overview
80
81
NZS3604
Standard
Overview
NZS3604 Standard Overview
82
NZS3604
Standard
Overview
83
Construction Contracts:
Managing Contracts
84
Background & IntroductionBackground & Introduction
NZS 3910‐15‐16 Series
NZS 3910‐15‐16 Series
NZS3604 StandardNZS3604 Standard
Managing Contracts
(NZ3910‐5‐6)
Managing Contracts
(NZ3910‐5‐6)
Summary and real life feedbackSummary and
real life feedback
In this section we’ll review: Day to day management of the contracts
Top 5 daily aspects Project Managers need to consider when managing
contracts
Contract and project reporting options and considerations
Contract communications
Change management and variation control
Programme Management
Project Control Group Management
85
Day to Day Contract Management
86
Day to Day Contract Management: Informal Monitoring and Works delivery tracking
87
88
Day to Day Contract Management: Relationship Spectrum
89
Day to Day Contract Management
90
Day to Day management
91
Site Visits – Site Safety Checks – Project Status Reporting
Work through example sheets
92
Reporting Practices – Project Control –Communications -Payments
93
Construction Contracts:
Real time feedback
94
Background & IntroductionBackground & Introduction
NZS 3910‐15‐16 Series
NZS 3910‐15‐16 Series
NZS3604 StandardNZS3604 Standard
Managing Contracts
(NZ3910‐5‐6)
Managing Contracts
(NZ3910‐5‐6)
Summary and real life feedbackSummary and
real life feedback
In this section we’ll review: Your feedback:
• “All attendees to email their ‘Top 5 challenges’ with these
contracts through to the facilitator a week before the workshop.
The facilitator will collate and spend the last 80 - 90mins working
through the biggest constraints and issues raised.”
95
Feedback on the top 5 challenges
Based on dedicated feedback from the client on their
key issues and challenges with 3910 – 16 + NZS3604.
96
Summary / Wrap-up
Around the Table:
List the key ‘takeaways’
Practical learnings you can bring back and implement
into the workplace tomorrow
97
Action required
1. Now: Online Feedback – to be completed in classroom
www.surveymonkey.com/r/FalconTraining
2. Later: Access soft copies of the materials at:www.falcontraining.com/templates
Access code: CMT17
98
Thank You Falcon Training
www.falcontraining.com
Spire Consulting
www.spireconsulting.co.nz
99www.falcontraining.comIt’s good to know