Facilities Project Management Monthly Report by Building Tuesday, June 05, 2018 153 Approved Project PROJECT TITLE PM Accountable Project Code Project Number: 1 Leavitt Lane Projects in Building 1 1 Leavitt Lane 123 renovation 3IN CONSTRUCTION FCR POLITANO, FRANK 5/30/18_ Work has been completed, customer has asked for a change. Design Firm: Contractor: External Contractor Name: Milestone 20160429 10 Pettee Brook Lane Projects in Building 1 10 Pettee Brook Lane Renovations to Space 3IN CONSTRUCTION FCR ROULEAU, RICHARD A 6/4/2018 Update: Construction is underway. Addressing submittals and RFIs. Substantial completion anticipated for mid to lateAugust. Furniture is being finalized and will be ordered soon. Design Firm: Manypenny Murphy Archite Contractor: External Contractor Name: Landlord 20170472 11 Brook Way Projects in Building 1 11 Brook Way Building Demolition 2.5IN PROCUREMENT FCR RINES, DANIEL M 52118: pcb testing came back negative, bids will be awarded 53018. Design Firm: Contractor: Contractor Name: 20160437 121 Technology Drive Projects in Building 3 121 Technology Drive Advanced Manufacturing Center 3IN CONSTRUCTION FCR BRICKETT, ALEXANDER J 5/30/18_Punchlist items in progress. Design Firm: JSA, Inc. Contractor: External Contractor Name: Careno Construction 20160301 121 Technology Drive Fit Up of Unassigned Suite 3.1SUBSTANTIAL COMPLETION FCR BRICKETT, ALEXANDER J 5/30/18_Update Please refer to ID 20160186 for updates. Design Firm: Contractor: External Contractor Name: Careno Construction 20180062 Tuesday, June 05, 2018 Page 1 of 28 University of New Hampshire Brenda Whitmore, Director Facilities Project Management

Upload: others

Post on 27-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

Facilities Project Management Monthly Report by Building

Tuesday, June 05, 2018 153Approved Project

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

1 Leavitt Lane Projects in Building 1

1 Leavitt Lane ‐ 123 renovation

3‐ IN CONSTRUCTION

FCRPOLITANO, FRANK

5/30/18_     Work has been completed, customer has asked for a change.

Design Firm: Contractor: External Contractor Name: Milestone

2016‐0429

10 Pettee Brook Lane Projects in Building 1

10 Pettee Brook Lane ‐ Renovations to Space

3‐ IN CONSTRUCTION

FCRROULEAU, RICHARD A

6/4/2018 Update: Construction is underway.  Addressing submittals and RFIs.  Substantial 

completion anticipated for mid to late‐August.  Furniture is being finalized and will be ordered 

soon.

Design Firm: Manypenny Murphy Archite Contractor: External Contractor Name: Landlord

2017‐0472

11 Brook Way Projects in Building 1

11 Brook Way ‐ Building Demolition

2.5‐ IN PROCUREMENT

FCRRINES, DANIEL M

5‐21‐18: pcb testing came back negative, bids will be awarded 5‐30‐18.

Design Firm: Contractor: Contractor Name:

2016‐0437

121 Technology Drive Projects in Building 3

121 Technology Drive ‐ Advanced Manufacturing Center

3‐ IN CONSTRUCTION

FCRBRICKETT, ALEXANDER J

5/30/18_Punchlist items in progress.

Design Firm: JSA, Inc. Contractor: External Contractor Name: Careno Construction

2016‐0301

121 Technology Drive ‐ Fit Up of Unassigned Suite

3.1‐ SUBSTANTIAL COMPLETION

FCRBRICKETT, ALEXANDER J

5/30/18_Update ‐ Please refer to ID 2016‐0186 for updates.

Design Firm: Contractor: External Contractor Name: Careno Construction

2018‐0062

Tuesday, June 05, 2018 Page 1 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 2: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

121 Technology Drive ‐ Interior Lease Space Renovations

3.1‐ SUBSTANTIAL COMPLETION

FCRBRICKETT, ALEXANDER J

5/30/18_Project is substantially complete. Punchlist and completion items ongoing.

Design Firm: Cowan‐Goudreau Contractor: External Contractor Name: Careno Construction

2016‐0186

5 Leavitt Lane Projects in Building 1

5 Leavitt Lane ‐ Library Storage Building Structure Investigation

1.1‐ PLAN/EST

RRRINES, DANIEL M

6‐5‐18 PM will reach out to customer, and Term Structural consultants

Design Firm: Contractor: Contractor Name:

2018‐0363

88 Commercial Street Projects in Building 1

88 Commercial Street ‐ Mechanical Tech Lab

3.1‐ SUBSTANTIAL COMPLETION

FCRROULEAU, RICHARD A

6/4/2018 Update:  Many tools and some larger pieces of equipment purchased and in place.  

Need to close out 1850 Associates purchase order to determine how much funding is available 

for additional tools and equipment.

Design Firm: John Jordan Contractor: External Contractor Name: 1850 PDRA Associates

2016‐0428

9 Madbury Road Projects in Building 1

9 Madbury Road ‐ Lease Space Office Fit Up

3‐ IN CONSTRUCTION

SIROULEAU, RICHARD A

6/4/2018 Update:  Construction is well underway.  Completion anticapate for late‐June or early‐

July.  Furniture has been ordered and expected in mid‐July.

Design Firm: Harriman Contractor: External Contractor Name: Milestone

2018‐0092

Adams Tower Projects in Building 1

Adams Tower ‐ Verizon Wireless Antenna Upgrade

1.1‐ PLAN/EST

FCRPOLITANO, FRANK

5/30/18_   We are coordinating work with Verizon for summer execution.

Design Firm: Contractor: External Contractor Name: Verizon

2018‐0310

Barton Hall & Cole Hall Projects in Building 1

Tuesday, June 05, 2018 Page 2 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 3: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Cole Hall ‐ HVAC HU‐3 EQ5389 Cat Walks and Accessibility Modifications

2.5‐ IN PROCUREMENT

RRHOUDE, DONALD A

5‐22‐18 This project went out to bid. Not happy with results. Still in discussion with the Bidder.

Design Firm: Oak Point Contractor: External Contractor Name: Milestone  E & C

2018‐0086

Building Interior Projects in Building 2

Thompson Hall ‐ Graduate Student Center

2‐ IN DESIGN

SIHECKLER, BARBARA K

5/25/2018: S. Thorne directing design. Goal is to implement by September

Design Firm: Contractor: External  Contractor Name:

2017‐0212

Campus ‐ UNH Fire Damper Study

3.1‐ SUBSTANTIAL COMPLETION

FCRHENRY, PAUL A

5‐22‐18     buildings Survey complete, for first 4 buildings.

Design Firm: Harriman Contractor: Contractor Name:

2017‐0205

Chase Ocean Engineering Lab Projects in Building 4

Chase Ocean Engineering Lab ‐ Tank Room Ceiling Restoration and Replacement of 

HV‐3

2.5‐ IN PROCUREMENT

RRGEUTHER, MARK E

05‐29‐2018: HV‐3 replacement scheduled to start the week of June 4.

Design Firm: HL Turner Contractor: External Contractor Name: Milestone

2017‐0153

Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe

2.5‐ IN PROCUREMENT

FCRHOUDE, DONALD A

5‐22‐18 This project has been estimated and the client has the FCR, we are waiting o funding.

Design Firm: Contractor: External Contractor Name: Yates Electric

2018‐0314

Chase Ocean Engineering Lab ‐ Tank Room Ventilation System

3.1‐ SUBSTANTIAL COMPLETION

SIGEUTHER, MARK E

05‐29‐2018:  Substantially Complete. Noise reduction scope complete.

Design Firm: HL Turner Contractor: External Contractor Name: Milestone

2016‐0147

Tuesday, June 05, 2018 Page 3 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 4: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Chase Ocean Engineering Lab ‐ Expansion

3.1‐ SUBSTANTIAL COMPLETION

FCRGEUTHER, MARK E

05‐29‐2018: Substantially Complete

Design Firm: HL Turner Contractor: FCT Contractor Name: Milestone Engineer & Construction

2015‐2755

Childhood Study & Development Center Projects in Building 1

Childhood Study & Development Center ‐ Roof Repair and Misc Repairs

2‐ IN DESIGN

RRPOLITANO, FRANK

5/30/18_  Drawings are due by Friday 6/1

Design Firm: SMRT Contractor: External Contractor Name:

2018‐0159

Combined Heat & Power Plant Projects in Building 1

Combined Heat & Power Plant ‐ Structural Floor Modifications

3.1‐ SUBSTANTIAL COMPLETION

FCRPOLITANO, FRANK

5/30/18_    Work is complete, I am looking for a new contractor, our term whom was under a P/O 

is not compliant. I have asked Careno to price this for us waiting on proposal.

Design Firm: Contractor: Contractor Name:

2017‐0189

Conant Hall Projects in Building 2

Conant Hall ‐ DDC Controls Installation

3.1‐ SUBSTANTIAL COMPLETION

RRHENRY, PAUL A

5‐22‐18  need to fiinish commissioning

Design Firm: Harriman Contractor: Contractor Name:

2018‐0192

Conant Hall ‐ Minor Interior Renovations

3.1‐ SUBSTANTIAL COMPLETION

SIHENRY, PAUL A

5‐22‐18 Building occupied  Working on punch List, and finishing MEP improvements

Design Firm: Mannypenny Murphy Contractor: External Contractor Name: Trumbell Nelson

2016‐0410

Dimond Library Projects in Building 3

Tuesday, June 05, 2018 Page 4 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 5: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Dimond Library ‐ Minor Renovation for Customer Service and Addison Areas

1.1‐ PLAN/EST

FCRHECKLER, BARBARA K

8/16/2017: Deferred pending approval from Dimond Deanʹs Office.

5/23/18=Barbarah Please reach out to the customer and work the plan to to proceed with this 

project.

Design Firm: Contractor: External Contractor Name:

2017‐0423

Dimond Library ‐ Interior Painting of Main Lobby

2.5‐ IN PROCUREMENT

RRBOIE, GREGG J

05/30 /18, APC will commence painting on June 11th.

.

Design Firm: Contractor: External Contractor Name: APC Services of New England

2018‐0307

Dimond Library – Room 221 Renovation

3‐ IN CONSTRUCTION

SIHECKLER, BARBARA K

5/25/2018:  Work started on 5/21 and on track to be complete by 8/1.

Design Firm: Contractor: Contractor Name:

2018‐0179

DPW Grounds & Roads Projects in Building 1

DPW Grounds & Roads ‐ Garage

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

5‐22‐18    poring slab on Thursday this week

Design Firm: Careno Contractor: External Contractor Name: Careno

2013‐1610

Elliott Alumni Center Projects in Building 1

Elliott Alumni Center ‐ HHW Conversion to Natural Gas Boiler

3‐ IN CONSTRUCTION

FCRPOLITANO, FRANK

5/30/18_     GSP has been awarded the major portion of the project and we are looking to start on 

6/6

Design Firm: SMRT Contractor: External Contractor Name: Granite State Plumbing

2017‐0443

Field House Projects in Building 3

Tuesday, June 05, 2018 Page 5 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 6: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Field House ‐ New Ski Locker Room/Team Area

2‐ IN DESIGN

FCRBRICKETT, ALEXANDER J

5/30/18__Working with design team for final space renderings.

Design Firm: Harriman Contractor: Contractor Name:

2017‐0251

Field House ‐ Womens Team Locker Room Upgrades ‐ Planning Only

2‐ IN DESIGN

SIHECKLER, BARBARA K

5/25/2018: Will schedule June meeting with Harriman.

Design Firm: Contractor: Contractor Name:

2018‐0198

Field House ‐ Steam to Domestic Hot Water System Replacement

3‐ IN CONSTRUCTION

RRPARSONS, STEPHANIE E

5/24/18: This project has been awarded to Northern Peabody.  Preconstruction meeting will be 

scheduled in the near future to work on project timeline and schedule coordination with athletics.

Design Firm: Harriman Contractor: External Contractor Name: Northern Peabody

2017‐0325

Gables Building A Projects in Building 1

Gables Buildings A, B & C ‐ Replace the EPDM roof tops

2.5‐ IN PROCUREMENT

FCRPOLITANO, FRANK

5/30/18_   Project  awarded to Viking Roofing will begin 6/4

Design Firm: ARM Contractor: External Contractor Name: Viking

2018‐0118

Gables Building B Projects in Building 1

Gables A,B,C ‐ Boiler Plant Replacement

2.5‐ IN PROCUREMENT

FCRPOLITANO, FRANK

5/30/18_  awarded to Charters Brothers and will begin 6/4

Design Firm: SMRT Contractor: External Contractor Name: Charters Brothers

2018‐0076

Gregg Hall Projects in Building 3

Tuesday, June 05, 2018 Page 6 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 7: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Gregg Hall ‐ Chiller Replacement

2.5‐ IN PROCUREMENT

RRPARSONS, STEPHANIE E

5/25/18: RFB request has been submitted to procurement.   Anticipate make ready work to occur 

July /August with chiller replacement to occur October / November after primary cooling season.

Design Firm: Harriman Contractor: External Contractor Name: TBD

2017‐0281

Gregg Hall ‐ Chiller Replacement ‐ Funding for Construction

2.5‐ IN PROCUREMENT

RRPARSONS, STEPHANIE E

5/25/18: Please refer to project 2017‐0281 for updates on construction.

Design Firm: Harriman Contractor: External Contractor Name: TBD

2017‐0250

Gregg Hall ‐ Basement Flood Restoration

3‐ IN CONSTRUCTION

RR

Emergency Repair

BRICKETT, ALEXANDER J

5/30/18_Drywall work to be competed when pump station upgrades are installed. Work to be 

coordinated with John OʹRourke.

Design Firm: Contractor: External Contractor Name:

2018‐0132

Hamel Recreation Center Projects in Building 1

Hamel Recreation Center ‐ Expansion & Renovations

3‐ IN CONSTRUCTION

CPPARSONS, STEPHANIE E

5/25/18: AWF installation is 60% complete.  Sanding / striping and sanding will beging early 

June. This project is scheduled to be complete by 6/30.

Design Firm: HGA Contractor: FCT Contractor Name: Shawmut / Charters Brothers

2013‐1176

Hamilton Smith Hall Projects in Building 1

Hamilton Smith Hall ‐ Major Renovation Project

3.5‐ WARRANTY REPAIRS

SIROULEAU, RICHARD A

6/4/2018 Update:  Meeting with Skanska and subcontractors for warranty review on 6/11.  

Working with Milestone to do some small follow‐up work.  Bi‐directional amplifier per Town 

ordinance split off as separate project (2018‐0223).

Design Firm: DiMella Shaffer Associates Contractor: External Contractor Name: Skanska USA, Inc.

2012‐1851

Health & Wellness Building Projects in Building 2

Tuesday, June 05, 2018 Page 7 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 8: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Health & Wellness Building ‐ Physical Reorganization of Services

1.1‐ PLAN/EST

FCRHECKLER, BARBARA K

5/25/2018: Final estimate and schedule for additional work expected by 5/25. Work will be 

complete by 8/3.

Design Firm: Harriman A/E Contractor: Contractor Name:

2017‐0340

Health & Wellness Building ‐  Fire Alarm System Upgrade

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

5/25/18: Final acceptance testing and review with SFMO to occur after commencement.  Will 

schedule walk through with SFMO early June.

Design Firm: Contractor: External Contractor Name: Norris

2018‐0182

Holloway Commons Projects in Building 2

Holloway Commons ‐ Retro‐Commissioning Repairs

1.1‐ PLAN/EST

FCRBRICKETT, ALEXANDER J

5/30/2018 ‐ RFS has been contacted to establish scope of repairs needed.

Design Firm: Contractor: External Contractor Name:

2016‐0500

Holloway Commons ‐ Expansion Project

3.5‐ WARRANTY REPAIRS

CPROULEAU, RICHARD A

6/4/2018 Update: There remain just a few project items that need to be resolved.

Design Firm: Miller Dyer Spears Contractor: External Contractor Name: North Branch Construction

2014‐1657

Hood House Projects in Building 4

Hood House ‐ Side Portico Structure and Roof Replacement

3.1‐ SUBSTANTIAL COMPLETION

RRHENRY, PAUL A

5‐22‐18   Hood House Renovation, 98% complete.

Design Firm: Contractor: Contractor Name:

2014‐1705

Hood House ‐ Minor Renovation for Career and Professional Success Center

3.1‐ SUBSTANTIAL COMPLETION

SIHENRY, PAUL A

5‐22‐18     Project in punch list,  occupants in the building.

Design Firm: Mannypenny Murphy Contractor: External Contractor Name: Trumbell Nelson

2016‐0409

Tuesday, June 05, 2018 Page 8 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 9: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Hood House ‐ Supplemental MEP Repairs

3.1‐ SUBSTANTIAL COMPLETION

RRHENRY, PAUL A

5‐22‐18 99% complete, in puhch list

Design Firm: MpM Contractor: External  Contractor Name: Trumbull Nelson

2018‐0140

Hood House ‐ Rear Entrance Canopy and Stair Replacement

3.1‐ SUBSTANTIAL COMPLETION

RRHENRY, PAUL A

5‐22‐18  Hood House Renovation, 98 % complete.

Design Firm: Contractor: Contractor Name:

2013‐1775

Horton Social Science Center Projects in Building 2

Horton Social Science Center ‐ 3rd Floor Daiken Unit Recommissioning

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

5‐22‐18  Operations locked out the Heat, checking to see if we still want to Retro‐Commission the 

system.

Design Firm: Harriman / RFS Contractor: External Contractor Name: RFS / Harriman

2018‐0295

Horton Social Science Center ‐ 1st Floor Renovation ‐ Phase 2

3‐ IN CONSTRUCTION

SIHENRY, PAUL A

5‐22‐18   Started construction 5‐17

Design Firm: Harriman Contractor: External  Contractor Name: Milestone

2008‐0203

Huddleston Hall Projects in Building 2

Huddleston Hall ‐ Roof Replacement Design Only

2‐ IN DESIGN

RRHENRY, PAUL A

5‐22‐18 Harriman working with ARM to include the design. Starting roof investigation   2013‐

1155 Huddleston Egress project.

Design Firm: ARM Contractor: External Contractor Name: Harriman

2016‐0165

Huddleston Hall ‐ Design of Egress Modifications

2‐ IN DESIGN

RRHENRY, PAUL A

5‐22‐18  Harriman working on  MEP Systems evaluation Construction 2021.

Design Firm: Harriman Contractor: External Contractor Name: Harriman

2013‐1155

Tuesday, June 05, 2018 Page 9 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 10: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Jackson Lab Projects in Building 1

Jackson Lab ‐ Autoclave Replacement

2.5‐ IN PROCUREMENT

RRHOUDE, DONALD A

5‐22‐18  A PO has been provided to the contractor  for this work. Equipment has been ordered. I 

am waiting for an ETA on equipment to schedule a const start. Expected in June.

Design Firm: Contractor: FCT Contractor Name:

2017‐0377

James Hall Projects in Building 3

James Hall ‐ Heat Exchanger Replacement

2.5‐ IN PROCUREMENT

RR

Emergency Repair

PARSONS, STEPHANIE E

5/28/18: This project was awarded to Northern Peabody.  Preconstruction / schedule / 

coordination meeting will be scheduled in June to discuss possible interruption of service.

Design Firm: Harriman Associates Contractor: External Contractor Name: NPI

2017‐0393

James Hall ‐ HVAC Modifications Investigation and Design

3‐ IN CONSTRUCTION

RRPOLITANO, FRANK

5/30/18_  We have found a missing gasket which seperates the compartments of the AHU, we 

will schedule the repair after commencement. We are still investigating the fans as a potential 

cause as well.

Design Firm: Contractor: Contractor Name:

2018‐0270

James Hall ‐ AHU‐3 Failure Investigation and Repair

3‐ IN CONSTRUCTION

RR

Emergency Repair

BRICKETT, ALEXANDER J

5/30/18_ Repairs and room reconditioning in progress.

Design Firm: Contractor: Contractor Name:

2018‐0309

Kendall Hall Projects in Building 2

Kendall Hall ‐ Levels 3‐ 5 Repurposing CE and COLSA ‐ Design Only

1.1‐ PLAN/EST

SIPOLITANO, FRANK

5/30/18_   Update ‐ Working with Campus Planning to review scope required to allow this 

occupant to relocate to Kendall Hall in FY 18.

Design Firm: Contractor: External Contractor Name:

2017‐0186

Tuesday, June 05, 2018 Page 10 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 11: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Kendall Hall ‐ Upgrade the Nutrition Assessment & Teaching Labs

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

5/25/18:  Awaiting furniture delivery.

Design Firm: A Contractor: FCT Contractor Name:

2017‐0235

Leavitt Cntr Transportation Center Projects in Building 1

Leavitt Cntr Transportation Center ‐ Bus Maintenance Lift Replacements

2.5‐ IN PROCUREMENT

FCRHOUDE, DONALD A

5‐22‐18  Working with Steve, Dirk and Ray. I am meeting with the UNH Purchasing dept to put 

this out to bid. We had a funding glitch, I believe we have solved that issue. I am working with 

Purchasing to put this out to bid.

Design Firm: Contractor: External Contractor Name: Design build

2017‐0447

McConnell Hall Projects in Building 1

McConnell Hall ‐ Water Intrusion Investigation

1.1‐ PLAN/EST

FCRPOLITANO, FRANK

5/30/18_    We have funds left for the repairs and I will secure a term contractor for repairs when 

the weather warms up to allow for proper conditions on repairs.

Design Firm: Contractor: External Contractor Name:

2016‐0297

Memorial Union Building Projects in Building 6

Memorial Union Building ‐ Granite State Room Exterior Deck

3‐ IN CONSTRUCTION

BARROULEAU, RICHARD A

6/4/2018 Update:  Staging erection underway.  Some work may start soon; however, loud work 

cannot start until after freshmen orientation.

Design Firm: Hoyle Tanner Contractor: Contractor Name: Charters Bros.

2017‐0352

Memorial Union Building ‐ Bookstore Flood Restoration and Repairs

3‐ IN CONSTRUCTION

BAR

Emergency Repair

POLITANO, FRANK

5/30/18_    Immediate repairs are complete facilities to repair valve. Other work such as carpet 

and office work to be scheduled when the bookstore slows down.

Design Firm: Contractor: Contractor Name:

2018‐0229

Tuesday, June 05, 2018 Page 11 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 12: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Memorial Union Building ‐ Exterior Deck Recoating

3‐ IN CONSTRUCTION

BARROULEAU, RICHARD A

6/4/2018 Update: Work to commence soon.

Design Firm: Contractor: External Contractor Name: Charters Bros.

2017‐0139

Memorial Union Building ‐ Strafford Room Wood Flooring Repair

3‐ IN CONSTRUCTION

BARPOLITANO, FRANK

5/30/18_    Old floor has been removed, Sprague will begin new floor around 7/1. Some sub floor 

work will begin prior.

Design Firm: Contractor: External Contractor Name: Sprague

2018‐0299

Memorial Union Building ‐ Strafford Room Chillers and AHUʹs

3‐ IN CONSTRUCTION

BARPOLITANO, FRANK

5/30/18_   Demo has begun, new unit is scheduled to arrive 6/15

Design Firm: SMRT Contractor: External Contractor Name: Careno

2018‐0143

Memorial Union Building ‐ Granite Square Station Mail Boxes

3.5‐ WARRANTY REPAIRS

FCRPOLITANO, FRANK

5/30/18_  Warranty issues, working with Armstrong and contractor for resolution. Looking to 

begin mid June.

Design Firm: Contractor: FCT Contractor Name:

2015‐2517

Morrill Hall Projects in Building 1

Morrill Hall ‐ Rm 209 Replacement Light Fixtures

2.5‐ IN PROCUREMENT

FCRHOUDE, DONALD A

5‐03‐18 The customer has show interest in additional work. I have sent an updated FCR. The 

customer is trying to appropriate the additional funding.

Design Firm: Contractor: External Contractor Name: Yates

2017‐0304

Morse Hall Projects in Building 4

Morse Hall ‐ HVAC Evaluation and Feasibility Study

1.1‐ PLAN/EST

RRPOLITANO, FRANK

5/30/18_    I will be scheduling a meeting with RFS to review scope and ask for a proposal

Design Firm: Contractor: Contractor Name:

2017‐0317

Tuesday, June 05, 2018 Page 12 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 13: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Morse Hall ‐ Security Upgrades Including Card Readers and Video Cameras

1.1‐ PLAN/EST

FCRHOUDE, DONALD A

5‐22‐18 This project has been estimated and a proposal with several options was presented to the 

client. I am waiting on feedback. They are waiting to see if they get any SAARC funding.

Design Firm: Contractor: External Contractor Name: Yates, Burns

2018‐0322

Morse Hall ‐ Third Floor Tempid Water Loop

3.1‐ SUBSTANTIAL COMPLETION

RRBRICKETT, ALEXANDER J

5/30/18_Basix to install monitoring equipment week of 6/4.

Design Firm: Contractor: External Contractor Name: GSPH

2017‐0004

Morse Hall ‐ Rm 345 Renovations

3.1‐ SUBSTANTIAL COMPLETION

FCRHENRY, PAUL A

5‐22‐18     Contacted stakeholder, he would like to wait and expand the system. Working with 

EHS on details of new control panel to be located in the corridor.

Design Firm: Harriman Contractor: External Contractor Name: TBD

2015‐2384

Murkland Hall Projects in Building 1

Murkland Hall ‐ Exterior Painting

2.5‐ IN PROCUREMENT

RRBOIE, GREGG J

05/31/18, Met with Kevin Sousa on scheduling and will get back with info.

Design Firm: Contractor: Contractor Name:

2018‐0305

Nesmith Hall Projects in Building 7

Nesmith Hall ‐ Room Improvements G00CRA, G17‐G22, G24‐G26 (including G25B)

1.1‐ PLAN/EST

SIHECKLER, BARBARA K

5/25/2018: Project on track for Summer.

Design Firm: Contractor: External Contractor Name: milestone

2018‐0173

Nesmith Hall ‐ Upward Bound / Talent Search Relocation

2‐ IN DESIGN

SIHECKLER, BARBARA K

5/28/2018: Careno on board as GC; will provide details week of 5/28.

Design Firm: Contractor: External Contractor Name: Careno

2018‐0202

Tuesday, June 05, 2018 Page 13 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 14: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Nesmith Hall ‐ Phone‐a‐thon Fit Out

2.5‐ IN PROCUREMENT

SIBRICKETT, ALEXANDER J

5/30/18_Design completed. Work to begin week of 6/4.

Design Firm: Harriman Contractor: External Contractor Name:

2018‐0166

Nesmith Hall ‐ Bathroom Renovations

3‐ IN CONSTRUCTION

RRBRICKETT, ALEXANDER J

5/25/18_Construction in progress.

Design Firm: Cowan & Goudreau Contractor: External Contractor Name: Greenleaf Construction

2015‐2341

Nesmith Hall ‐ Bathroom Renovations DESIGN ONLY

3‐ IN CONSTRUCTION

RRBRICKETT, ALEXANDER J

5/30/18__See project 2015‐2341

Design Firm: Cowan & Goudreau Contractor: Contractor Name:

2018‐0096

Nesmith Hall ‐ Bathroom Improvements and ADA Accessibility Modifications

3‐ IN CONSTRUCTION

SIBRICKETT, ALEXANDER J

5/25/2018_See project 2015‐2341 for updates.

Design Firm: Cowan & Goudreau Contractor: External Contractor Name: Greenleaf Construction

2018‐0339

Nesmith Hall ‐ South Roof Replacement

3.1‐ SUBSTANTIAL COMPLETION

RRPOLITANO, FRANK

5/30/18_   P/O written looking to schedule ASAP

Design Firm: ARM Contractor: External Contractor Name: Viking

2010‐0433

New England Center Projects in Building 2

New England Center ‐ Adams Tower ‐ Separation of HHW and DHW Design Only

2‐ IN DESIGN

RRHENRY, PAUL A

5‐22‐18  Finalizing design in the next few months, project slated for Summer 2019

Design Firm: Harriman Contractor: External Contractor Name: TBD

2016‐0402

Tuesday, June 05, 2018 Page 14 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 15: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

New England Center ‐ Flood Damage Restoration and Repairs

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

HENRY, PAUL A

5‐22‐18  waiting for fin tube covers

Design Firm: Contractor: External Contractor Name: Milestione

2018‐0228

New Hampshire Hall Projects in Building 1

New Hampshire Hall ‐ Window Replacements and Exterior Painting

1.1‐ PLAN/EST

RRBOIE, GREGG J

05/30/2018, E‐Mailed Brian Gehris for status on window/paint quote.

Design Firm: Contractor: Contractor Name:

2018‐0306

Northwest Heat Plant Projects in Building 1

Northwest Heat Plant ‐ New Construction

3‐ IN CONSTRUCTION

FCRPARSONS, STEPHANIE E

5/25/18: Foundation is complete, undergroud utitlies at the building are ongoing.  Pipe in the 

shop at Putnam is ongoing to be complete by 6/18 when the violin program starts.

Design Firm: Wilson Engineering Contractor: External Contractor Name: Froling Energy

2018‐0002

Old Dairy Barn Projects in Building 1

Old Dairy Barn ‐ Demolition

3.1‐ SUBSTANTIAL COMPLETION

RRRINES, DANIEL M

5‐21‐18: Final coat of paint installed, waiting for loam, and seed, then final closeout.

Design Firm: Contractor: External Contractor Name: Milestone

2012‐1085

Outdoor Facility Projects in Building 2

Outdoor Facility ‐ New Soccer/Lacrosse Field

2.5‐ IN PROCUREMENT

FCRGEUTHER, MARK E

05‐29‐2018: Contract signed by contractor, and VPFA, hand delivered to USNH. Construction 

scheduled to start on or about August 1, 2018.

Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports

2017‐0285

Tuesday, June 05, 2018 Page 15 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 16: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Mooradian Field ‐ Subsurface Improvements and Turf Replacement

3.1‐ SUBSTANTIAL COMPLETION

RRGEUTHER, MARK E

05‐29‐2018: Substantially complete. Waiting on As‐Builts

Design Firm: Tighe & Bond Contractor: FCT Contractor Name: RAD Sports

2017‐0149

Outdoor Pool Projects in Building 1

Outdoor Pool ‐ Reconstruction of Outdoor Pool Facility

3.1‐ SUBSTANTIAL COMPLETION

CPPARSONS, STEPHANIE E

5/25/18  Preparing for project closeout.  Final items required for the project will be purchased 

and this project closed out by August 2018.

Design Firm: water technologies Contractor: External Contractor Name: Shawmut

2014‐2059

Parsons Hall Projects in Building 4

Parsons Hall ‐ Rms N104, N108 Classroom Renovation Iddles Lecture Halls Design 

Only

2‐ IN DESIGN

RRBRICKETT, ALEXANDER J

5/30/18_ Harriman has begun design work on new lecture halls.

Design Firm: Harriman Contractor: External Contractor Name:

2018‐0145

Parsons Hall ‐ Processed Chilled Water System Replacement

2‐ IN DESIGN

RRBRICKETT, ALEXANDER J

5/30/18_ Design work in progress.

Design Firm: Contractor: Contractor Name:

2018‐0048

Parsons Hall ‐ Rm S128 Ammonia Gas Control System

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

5/25/18: Awaiting Norris schedule to install FA module to supervise the ammonia system.

Design Firm: AirGas Contractor: External Contractor Name: AirGas

2017‐0431

Parsons Hall ‐ Rm S222 Minor Renovations

3.1‐ SUBSTANTIAL COMPLETION

FCRBRICKETT, ALEXANDER J

5/30/18_Work completed. Punchlist items in progress.

Design Firm: Harriman Contractor: External Contractor Name: Yates & GSPH

2018‐0058

Tuesday, June 05, 2018 Page 16 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 17: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Paul College Projects in Building 1

Paul College ‐ HVAC and Control Modifications from Original Construction

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

5/25/18. Further work may be required, will not have an assessment until cooling season.

Design Firm: RFS Contractor: External Contractor Name: TBD

2016‐0295

Paul Creative Arts Center Projects in Building 2

Paul Creative Arts Center ‐ Stair Egress Modifications

3.1‐ SUBSTANTIAL COMPLETION

RRPOLITANO, FRANK

5/30/18_    1st phase is complete, except some door hardware for egree doors. Scheduled to be 

delivered 6/4/18

Design Firm: Harriman Contractor: Contractor Name:

2017‐0232

Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation

3.5‐ WARRANTY REPAIRS

RRROULEAU, RICHARD A

6/4/2018 Update:  Water heater installation completed.  Equipment list submitted.  O&M 

manuals to be uploaded to Meridian shortly.  Domestic water booster pump design received and 

may be implemented as part of this project or possibly as a separate follow‐on project.

Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.

2018‐0249

Pettee Hall Projects in Building 2

Pettee Hall ‐ Rm G18 Mold Remediation and Investigation

3‐ IN CONSTRUCTION

RR

Emergency Repair

HECKLER, BARBARA K

5/252018: Project on track to be complete by 6/22.

Design Firm: Contractor: Contractor Name:

2018‐0251

Pettee Hall ‐ Slate Roof Repairs

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

ROULEAU, RICHARD A

6/4/2018 Update: Repairs completed pending final drone verification.

Design Firm: Contractor: External Contractor Name: Skyline Roofing

2018‐0098

Philbrook Hall Projects in Building 4

Tuesday, June 05, 2018 Page 17 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 18: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Philbrook Hall ‐ Boiler Forensic Investigation

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

5/25/18: Dye testing cannot begin until the refrigeration demo / floor cuts are complete.  RFP is 

being drafted for forensic analysis of the building infrastructure to determine cause of boiler 

failure.

Design Firm: TBD Contractor: External Contractor Name: TBD

2018‐0162

Philbrook Hall ‐ Kitchen Modifications

2‐ IN DESIGN

FCRHENRY, PAUL A

5‐22‐18 Selected Charter Brothers as CMAR, will start Pre‐Construction Services to explor the 

site this summer

Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers

2017‐0399

Philbrook Hall ‐ Refrigeration Rack System

3‐ IN CONSTRUCTION

FCRHENRY, PAUL A

5‐22‐18   in construction

Design Firm: Harriman Assoc. Contractor: External Contractor Name: Charter Brothers

2015‐2492

Philbrook Hall ‐ Boiler Replacement

3‐ IN CONSTRUCTION

BARPARSONS, STEPHANIE E

5/25/18: Boiler is not being installed until 2018‐0162 forensic review is complete.

Design Firm: Harriman Contractor: External Contractor Name: Eckhardt Johnson

2018‐0149

Presidents House Projects in Building 1

Presidents House ‐ Major Site Repairs President Transition

2.5‐ IN PROCUREMENT

RRRINES, DANIEL M

4‐24‐18: Quotes have been obtained from contractors, working on final schedule and budgets. 

Work is set to begin on exterior work 5‐21‐18.

Design Firm: Contractor: External Contractor Name:  Bell and Flynn/ Chapman

2013‐1274

Presidentʹs House Projects in Building 1

Tuesday, June 05, 2018 Page 18 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 19: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Presidentʹs House ‐ Building Exterior and Interior Painting and Repairs

1.1‐ PLAN/EST

RRBRICKETT, ALEXANDER J

5/30/2018 Exterior work has begun. Interior work to begin 6/4.

Design Firm: Contractor: Contractor Name:

2013‐1032

Ritzman Hall Projects in Building 1

Ritzman Hall ‐ First Floor Reconfiguration

3.1‐ SUBSTANTIAL COMPLETION

FCRGEUTHER, MARK E

05‐29‐2018: Substantial Complete. New office chairs on order.

Design Firm: Contractor: External Contractor Name: Milestone

2018‐0292

Roads/Grounds Projects in Building 11

FY19 Sidewalk and Walkway Repairs

1.1‐ PLAN/EST

RRHENRY, PAUL A

5‐22‐18 Have estimates, working on POʹs

Design Firm: Contractor: External Contractor Name: T&S /  JTI

2017‐0027

FY19 Site Stair Repairs

1.1‐ PLAN/EST

RRHENRY, PAUL A

4‐30‐18 Working on estimates

Design Firm: Contractor: External Contractor Name: TBD

2017‐0026

FY19 Road Repairs and Crack Sealing

1.1‐ PLAN/EST

RRHENRY, PAUL A

5‐22‐18 Working on estimates, may not do this summer

Design Firm: Contractor: External Contractor Name: TBD

2017‐0024

Campus ‐ Huddleston Fairchild Hetzel Site Stairs Design

1.1‐ PLAN/EST

RRGEUTHER, MARK E

05‐29‐2018  Entering into an agreement with Hoyle‐Tanner for design.

Design Firm: Hoyle‐Tanner Contractor: External Contractor Name: TBD

2018‐0294

Tuesday, June 05, 2018 Page 19 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 20: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Campus ‐ Main Street South Sidewalk

2‐ IN DESIGN

SIRINES, DANIEL M

5‐21‐18: NTP obtained from NHDOT, CMA/USNH contract finalized, obtaining signatures.

Design Firm: CMA Engineering Contractor: Contractor Name:

2017‐0384

Memorial Union Building ‐ Driveway and Sidewalk ‐ Design Only

2‐ IN DESIGN

SIRINES, DANIEL M

5‐21‐18: meeting this week with, team to discuss drainage, and 60% plans from Hoyle Tanner.

Design Firm: Hoyle Tanner Contractor: Contractor Name:

2009‐0078

South Drive ‐ Design Advancement

2‐ IN DESIGN

SIHENRY, PAUL A

5‐22‐18   T&B recently estimated project at DD,  up dated estimate

Design Firm: Tighe & Bond Contractor: External Contractor Name:

2013‐1115

Campus Wayfinding ‐ Phase 2

2.5‐ IN PROCUREMENT

SIRINES, DANIEL M

5‐21‐18: sign copyʹs being finalized, installation expected in July/August.

Phase 1 punch list to begin 6‐11‐18

Design Firm: Contractor: External Contractor Name: Barlo Signs

2016‐0157

Campus ‐ South Drive ‐ Temporary Connection to Colovos Road

2.5‐ IN PROCUREMENT

SIGEUTHER, MARK E

05‐29‐2018‐Project on hold pending funding.

Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports

2018‐0267

Campus ‐ Wayfinding ‐ Phase 1

3.1‐ SUBSTANTIAL COMPLETION

SIKING, KATHLEEN M

4/27/18: Change order issued for punch list completion, to be completed in early summer.

Design Firm: Roll Barresi & Associates Contractor: FCT Contractor Name: Barlo Signs International

2017‐0211

Tuesday, June 05, 2018 Page 20 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 21: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Wildcat Stadium Parking Lot ‐Pay & Display Meter Installation & Pad

3.1‐ SUBSTANTIAL COMPLETION

FCRHOUDE, DONALD A

5‐22‐18  The project is 90% complete waiting for Bollard covers.

Design Firm: Contractor: External Contractor Name: T&S const

2018‐0150

Rudman Hall Projects in Building 15

Rudman Hall ‐ Conversion to DDC Controls

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

5/25/18 ‐see ID 2010‐0479 for updates.

Design Firm: Contractor: External Contractor Name: TBD

2015‐2336

Rudman Hall ‐ DDC Controls Backstop

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

5/25/18 ‐ see ID 2010‐0479 for updates

Design Firm: Contractor: Contractor Name:

2017‐0288

Rudman Hall ‐ Fire Alarm Replacement DESIGN

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

5/25/18 ‐ Design review ongoing, installation of fire alarm is scheduled for Summer 2019.

Design Firm: SFC Engineering Contractor: External Contractor Name: TBD

2013‐1149

Rudman Hall ‐ Laboratory Fume Hood Control System Replacement

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

5/25/18 ‐ Project is currently in preliminary design will need to coordinate this work closely with 

COLSA and Rudman occupants. Make ready work for AHU isolation is being scheduled for 

December 2018 with new HVAC control improvements to begin summer 2019.

Design Firm: SMRT, Inc. Contractor: External Contractor Name: TBD

2010‐0479

Rudman Hall ‐ Fire Alarm Replacement

1.1‐ PLAN/EST

RRPARSONS, STEPHANIE E

5/25/18 ‐ Please see  ID 2010‐0479 for updates.

Design Firm: SFC Contractor: External Contractor Name: TBD

2015‐2352

Tuesday, June 05, 2018 Page 21 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 22: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Rudman Hall ‐ Level G Instruction Lab Support Expansion

1.1‐ PLAN/EST

SIPARSONS, STEPHANIE E

5/25/18: Working on design to enclose portion of the loading dock area to expand the lab support 

facility.

Design Firm: TBD Contractor: External Contractor Name: TBD

2017‐0418

Rudman Hall ‐ Rm 148 Replacement Environmental Room Humidifier

1.1‐ PLAN/EST

RRBOIE, GREGG J

05/30/18, Contacted Harris Environmental systems(problem with PO) for replacement 

Humidifier.

Design Firm: Contractor: External Contractor Name: Harris Environmental Systems Inc.

2018‐0354

Rudman Hall ‐ Vivarium Upgrades Phase 2 DESIGN ONLY

2‐ IN DESIGN

SIPOLITANO, FRANK

5/30/18_   Design in process review drawings due by 6/15

Design Firm: Harriman Contractor: Contractor Name:

2017‐0214

Rudman Hall ‐ ARO Autoclave Replacement

2.5‐ IN PROCUREMENT

RRBRICKETT, ALEXANDER J

5/30/18_Design documentation received.Obtaining quotes for work from contractors.

Design Firm: Contractor: Contractor Name:

2016‐0148

Rudman Hall ‐ Steam Domestic Hot Water Exchanger

3‐ IN CONSTRUCTION

RRPOLITANO, FRANK

5/30/18_   Work is underway, old unit is removed new one is being installed , scheduled to be 

completed 6/8

Design Firm: Contractor: External Contractor Name: GSP

2017‐0366

Rudman Hall ‐ Water Booster Pump  Replacement

3‐ IN CONSTRUCTION

RRPOLITANO, FRANK

5/30/18_   P/O is written work will be a Summer project

Design Firm: Contractor: External Contractor Name: GSP

2017‐0367

Tuesday, June 05, 2018 Page 22 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 23: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Rudman Hall ‐ G Level Flood Restoration and Repair

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

BRICKETT, ALEXANDER J

5/30/18_All affected areas have been repaired. Equipment replacement in progress.

Design Firm: Contractor: Contractor Name:

2018‐0230

Rudman Hall ‐ Dishwasher Fire/ Sprinkler Flood Restoration

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

KING, KATHLEEN M

4/27/18: Restoration is complete, project is also labeling fire sprinkler valves and considering 

modifying ventilation of space behind washer.

Design Firm: Contractor: Contractor Name:

2018‐0252

Rudman Hall ‐ Rm G51 Flood Restoration

3.1‐ SUBSTANTIAL COMPLETION

RR

Emergency Repair

BRICKETT, ALEXANDER J

5/30/18_ Ceiling tiles completed. Old refrigerator to be removed when contents are moved.

Design Firm: Contractor: FCT Contractor Name: Sprague

2017‐0293

Rudman Hall ‐ Steam Back Pressure Turbine

3.1‐ SUBSTANTIAL COMPLETION

FCRPARSONS, STEPHANIE E

5/25/18: All control interface is complete.  Steam turbine will start 5/25/18.  This will be final 

report on this project.

Design Firm: Waldron Engineering Contractor: External Contractor Name: Ewing Controls / TVC

2016‐0162

Service Building Projects in Building 3

Service Building ‐ Dispatch Center Keltron System

3‐ IN CONSTRUCTION

FCRPARSONS, STEPHANIE E

5/25/18: Gregg Hall ʹnodeʹ will be populated  May 2018.  This will remove 6 accounts from 

Service Building.  Upon completion, the team will assess the next node to popluate, Paul College 

or PMS.

Design Firm: Contractor: External Contractor Name: Norris / UNH Telecom

2016‐0123

Service Building ‐ Replacement and Installation of Isolation valves

3‐ IN CONSTRUCTION

RRPARSONS, STEPHANIE E

5/25/18 ‐ Please see project ID 2009‐0064 for updates and budget.

Design Firm: N/A Contractor: External Contractor Name: TBD

2013‐1465

Tuesday, June 05, 2018 Page 23 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 24: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Service Building ‐ Fire Alarm Replacement and Building System Upgrades

3‐ IN CONSTRUCTION

RRPARSONS, STEPHANIE E

5/25/18 Heating line replacement and isolation valve installation has started.  Fire alarm is 

substantially complete.  One final walk through will be conducted with SFC / DFD or SFMO and 

UNH. Date / time to be determined.

Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers

2009‐0064

Spaulding Hall Projects in Building 1

Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative

2‐ IN DESIGN

CPROULEAU, RICHARD A

6/4/2018 Update: CM has been selected.  Notice to be made tomorrow.  Design direction is to 

design the full addition and, if state funds are not forthcoming, do less in the existing building.

Design Firm: Ellenzweig Contractor: External Contractor Name: TBD

2016‐0278

Stoke Hall Projects in Building 3

Stoke Hall ‐ Registrarʹs Office Minor Renovation

2‐ IN DESIGN

SIHECKLER, BARBARA K

5/25/2018: Will meet with RO in June.

Design Firm: Contractor: Contractor Name:

2018‐0175

Stoke Hall ‐ Business Service Center Exterior Wall Repairs

3‐ IN CONSTRUCTION

RRBRICKETT, ALEXANDER J

5/30/18_ Construction in progress.

Design Firm: Contractor: Contractor Name:

2018‐0213

Stoke Hall ‐ Elevator upgrade

3‐ IN CONSTRUCTION

FCRROULEAU, RICHARD A

6/4/2018: Work is in progress and is to be complete prior to the fall semester.

Design Firm: Elevator Consulting Assoc. Contractor: External Contractor Name: Careno Construction

2018‐0117

Thompson Hall Projects in Building 3

Tuesday, June 05, 2018 Page 24 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 25: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Thompson Hall ‐ Retaining Wall Replacement and Walkway

2.5‐ IN PROCUREMENT

RRHENRY, PAUL A

5‐22‐18  Project out to bid second time

Design Firm: Harriman Contractor: External Contractor Name: TBD

2016‐0065

Thompson Hall ‐ Moisture Repair and Window Repair

3‐ IN CONSTRUCTION

RRPOLITANO, FRANK

5/30/18_    FCT to paint 3 remaining windows

Design Firm: Contractor: FCT Contractor Name:

2017‐0164

Thompson Hall ‐ Card Access and Security Camera Cable Pathways

3‐ IN CONSTRUCTION

FCRHOUDE, DONALD A

5‐22‐18  This project is funded and the contractor has started. I have checked and the contractor 

has made good progress.

Design Firm: Contractor: External Contractor Name: Yates

2018‐0246

Tirrell Light Horse Stable Projects in Building 1

Tirrell Light Horse Stable ‐ Replace 39 stall lighting fixtures with new LED fixtures

3‐ IN CONSTRUCTION

FCRHOUDE, DONALD A

5‐22‐18 This project was reviewed and we found it was a good for the new FCT division. Jeff 

mcGrath has acceptet the project, John Dube is ordering material.

Design Firm: Contractor: FCT Contractor Name:

2018‐0334

Utility Distribution Projects in Building 12

Utility Distribution ‐ HHW Line Replacement Service Building to Zais Hall

1.1‐ PLAN/EST

RRRINES, DANIEL M

5‐21‐18 Meeting with Leo and team next week to discuss, Obtaining prcing and schedules from 

RH White, and Charter Bros.

Design Firm: Contractor: Contractor Name:

2017‐0354

Utility Distribution ‐ Library Way Tunnel Design

1.1‐ PLAN/EST

RRKING, KATHLEEN M

4/27/18: PM is waiting on final direction from asset management and utilities

Design Firm: Contractor: Contractor Name:

2017‐0005

Tuesday, June 05, 2018 Page 25 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 26: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Utility Distribution ‐ College Brook Culvert Repair

2‐ IN DESIGN

RRHENRY, PAUL A

5‐22‐18  Exposted site, have to remove electrical duct bank to do work, working with Energy to 

incluce some High Voltage work to take atvanatve of moving the switches above ground, 

meeting next week.

Design Firm: Tighe & Bond Contractor: External Contractor Name: TBD

2018‐0100

UNH Utility Master Plan

2‐ IN DESIGN

SIKING, KATHLEEN M

4/27/18: Final comments returned to consultants and final report due May 11, followed by 

presentations by consultants.

Design Firm: RMF Contractor: Contractor Name:

2017‐0169

Utility Distribution ‐ Edgewood Water Tank ‐ Decomissio

2.5‐ IN PROCUREMENT

FCRBRICKETT, ALEXANDER J

5/30/18_PO for demolition issued to Charter Bros. Work to occur 8/1/18.

Design Firm: Contractor: External Contractor Name: Charter Brothers

2010‐0729

Utility Distribution ‐ Waterworks Road Water Main Repair

2.5‐ IN PROCUREMENT

FCRHENRY, PAUL A

5‐22‐18     T&B submitted an After the Fact Wetlands Permit to cover the emergency repair.

Design Firm: Tighe & Bond Contractor: External Contractor Name: Tighe & Bond

2018‐0250

Utility Distribution ‐ Reconfigure and Relocation of Colovos SSL0109 and SSL0486

2.5‐ IN PROCUREMENT

RRGEUTHER, MARK E

05‐29‐2018 Plans have been finalized. Waiting for price and schedule from Term Contractor.

Design Firm: Tighe & Bond Contractor: External Contractor Name: T&S Construction

2018‐0183

Utility Distribution ‐ Horton to PCAC HHW Line Replacements and Pit Repairs

3‐ IN CONSTRUCTION

RRROULEAU, RICHARD A

6/4/2018 Update: Construction is well underway.  Pipe should start going in this week.  

Unforeseen/hidden conditions and structural issues with existing vaults are being addressed.

Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.

2017‐0094

Tuesday, June 05, 2018 Page 26 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 27: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Utility Distribution ‐ HV ‐ Circuit 11 Hamilton Smith to Memorial Union Phase II

3‐ IN CONSTRUCTION

SIHOUDE, DONALD A

5‐22‐18  The contractor has a PO. Site preparation is taking place this week and excavation 

should start soon.

Design Firm: Contractor: External Contractor Name:

2018‐0067

Utility Distribution ‐ Main Street Tunnel Corrective Repair and Design

3‐ IN CONSTRUCTION

RRRINES, DANIEL M

5‐21‐18: RH White mobilized, concrete repair underway this week. Exterior tunnel work to be 

completed the week of 5‐28‐6‐11.

Design Firm: Simpson Gumpertz & Heger Contractor: External Contractor Name: R.H. White Construction

2018‐0155

Utility Distribution ‐ HHW and Sewer Line Replacement College Road to Kendall and 

Nesmith

3‐ IN CONSTRUCTION

RRGEUTHER, MARK E

05‐29‐2018: Work underway. Waterline not as anticipated. Working on alternate plan.

Design Firm: Harriman/Tighe & Bond Contractor: External Contractor Name: Waterline Industries

2017‐0093

Utility Distribution ‐ Gables Distribution Line Replacements

3.1‐ SUBSTANTIAL COMPLETION

RRKING, KATHLEEN M

4/27/18: Project is substantially complete, waiting on final invoicing.

Design Firm: Harriman Contractor: External Contractor Name: RH White

2017‐0348

Water Treatment Plant Projects in Building 1

Water Treatment Plant ‐ New Construction

3‐ IN CONSTRUCTION

SIGEUTHER, MARK E

05‐29‐2018: Concrete tank work ongoing. Site work on going. Masonry gearing up for mock up 

wall.

Design Firm: Woodard & Curran Contractor: External Contractor Name: Waterline Industries

2008‐0038

Whittemore Center ‐ Arena Projects in Building 3

Tuesday, June 05, 2018 Page 27 of 28University of New Hampshire

Brenda Whitmore, Director Facilities Project Management

Page 28: Facilities Project Management Monthly Report Building · Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe 2.5‐ IN PROCUREMENT HOUDE, DONALD A FCR 5‐22‐18 This

PROJECT TITLEPM 

AccountableProject 

Code

Project 

Number:

Whittemore Center ‐ Arena ‐ Ice System Engineering Evaluation

1.1‐ PLAN/EST

RRBRICKETT, ALEXANDER J

5/30/18_Meeting on 3/2 indicated that ice system needs replacement. Initial design phase in 

progress.

Design Firm: Stevens Engineering Contractor: Contractor Name:

2018‐0235

Whittemore Center ‐ Arena ‐ Engineering Evaluation for Exterior Concrete and Interior 

Mechanical Room Slab

1.1‐ PLAN/EST

RRRINES, DANIEL M

5‐21‐18: PM coordinating with SGH to begin investigations.

Design Firm: SGH Contractor: Contractor Name:

2017‐0394

Whittemore Center ‐ Arena ‐ Concessions Stand Electrical Work

3‐ IN CONSTRUCTION

FCRBRICKETT, ALEXANDER J

5/30/18_Yates has finished electrical work. Telecom work in progress.

Design Firm: Contractor: External Contractor Name: Yates

2018‐0157

Woodside ABC Projects in Building 1

Woodsides Complex ‐ Boiler Replacements and Modifications

3‐ IN CONSTRUCTION

FCRPOLITANO, FRANK

5/30/18_    Work has begun, all existing boilers have been removed, concrete pads are being 

poured 5/30‐6/4. New boiler install begins 6/4

Design Firm: SMRT Contractor: External Contractor Name: Careno

2017‐0408

Tuesday, June 05, 2018 Page 28 of 28University of New Hampshire