facilities & operations committee - board of regents 2015... · project narrative - page 4...

61
Facilities & Operations Committee February 2015 February 12, 2015 10:00 a.m. - 12:00 p.m. West Committee Room, McNamara Alumni Center

Upload: phamthu

Post on 04-Jul-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Facilities & Operations Committee

February 2015

February 12, 2015

10:00 a.m. - 12:00 p.m.

West Committee Room, McNamara Alumni Center

Page 2: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Docket Item Summary - Page 3 Project Narrative - Page 4 Project Location Map - Page 7

1. Capital Budget Amendment: Design of Intercollegiate AthleticsAthletes Village (Twin Cities Campus) - Review/Action

Docket Item Summary - Page 15

2. Annual Update on Sustainability in Operations

Docket Item Summary - Page 35

3. Long-Range Planning: Balancing Stewardship, Focus, and Growth

a. Update on Facility Use Agreement at TCF Bank Stadium

b. Update on Combined Heat and Power Plant (Twin CitiesCampus)

Docket Item Summary - Page 58

Memorandum - TCF Bank Stadium - Page 59

4. Information Items

Presentation Slides - Page 8

Presentation Slides - Page 17

Presentation Slides - Page 37

Memorandum - CHP - Page 61

FAC - FEB 2015

Page 3: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

BOARD OF REGENTS

DOCKET ITEM SUMMARY

Facilities & Operations February 12, 2015

Agenda Item: Capital Budget Amendment: Athletes Village

Review X Review + Action Action Discussion

Presenters: Vice President Pamela Wheelock

Assistant Vice President Suzanne Smith

Athletics Director Norwood Teague

Purpose & Key Points

In accordance with Board of Regents Policy: Reservation and Delegation of Authority, review and

approve amendments to the FY 2015 Capital Budget for the following project:

• Athletes Village – Twin Cities Campus

The Capital Budget Amendment requested at this time is for design services. A future request for

approval to complete the project will be advanced upon an approved financing agreement.

The attached Project Data Sheet addresses the basis for request, project scope, cost estimate,

funding, schedule and include a site map for this project.

Background Information

This project is planned to meet the current and future needs of the University’s athletic programs.

It will construct a new 340,000 square foot Athletes Village on the east side of the Bierman and

Gibson-Nagurski buildings, on the University of Minnesota Twin Cities campus.

President’s Recommendation

The President recommends approval of an amendment to the FY2015 Capital Budget for the project

listed below and of the appropriate administrative officers proceeding with the design for this

project:

• Athletes Village – Twin Cities Campus

This is a report required by Board policy.

3 of 61

Page 4: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Athletes Village Twin Cities Campus

Project No. 01-000-15-1129

1. Basis for Request:

The Athletes Village program was initially outlined during an athletics facility needs assessment completed in 2013. The goal of the assessment was to understand how to provide student-athletes, administrators, and coaches with state of the art tools that allow everyone to share in the success of the Gopher athletic department. The study confirmed that facility deficiencies severely hamper possible success. The proposed Athletes Village will meet current and future needs of the University’s athletics programs and will advance a unified athletic department. Most importantly, the proposed Center for Excellence creates space and an environment not currently available to our student-athletes. This space focuses on the academic, nutritional, and leadership needs and desires of all our student athletes and creates an environment that values all aspects of the student-athlete experience. The norm for NCAA Division 1-A programs is for more dedicated practice facilities. This project will result in that for Gopher athletics. The aging facilities at Gibson-Nagurski lack the necessary area for all sports that compete for practice space. Dedicated practice space results in consistent schedules and routine for athletes and coaches and allows everyone to maximize time for their sport and studies. This is also seen as an essential need as our coaches compete with other institutions during the recruiting process.

2. Scope of Project:

The project, located on the Twin Cities campus, will construct a new 340,000 sf Athletes Village on the east side of the Bierman and Gibson-­‐Nagurski buildings. It is comprised of four buildings which include a Center for Excellence, Basketball Practice Facility, Indoor Football Practice Facility, and Football Performance Center. The Center for Excellence (67,000 sf) will serve as a hub and flagship facility for the entire Athletics department and all 720+ student-athletes. This facility will include an Academic Center comprised of a computer lab, classroom, study hall, group study, and tutoring areas; a Leadership Center comprised of a multipurpose room, career and graduate resource room, academic counseling space, conference and interview rooms; a Training Table comprised of a kitchen, servery, and dining hall; and an athletics compliance suite. The Basketball Practice Facility (67,000 sf) will provide separate facilities for both Men’s and Women’s basketball to train and practice. This will include separate courts, locker rooms, and coach and staff offices for both men’s and women’s basketball programs as well as a combined strength and conditioning area. The Indoor Football Practice Facility (110,000 sf) will allow the University’s football program to match and exceed the facilities at other Big Ten schools. This will include a full field overrun with 90’ clear height and a partial field for lineman work.

4 of 61

Page 5: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

The Football Performance Center (96,000 sf) will provide better support facilities for the football program. This will include locker rooms, players lounge, team meeting rooms, an equipment area and support space, dedicated strength and conditioning space, training, rehab and hydrotherapy rooms, support space, and coach and staff offices. Though not in the scope of this project, the construction of these facilities will ultimately free up substantial space within the current Bierman/Gibson-Nagurski footprint for renovation and re-purposing for use by numerous men’s and women’s teams. The impact will further the University’s long-term commitment to excellence for each of the Gopher teams.

3. Master Plan or Precinct/District Plan:

The project is in compliance with the 2009 Twin Cities Campus Master Plan.

4. Environmental Issues:

Hazardous materials (contaminated soil and mercury) will be abated.

5. Cost Estimate:

Construction Cost $125,350,000 Non Construction Cost 24,650,000 Total Project Cost $150,000,000

6. Capital Funding:

Project funding is targeted to come from external fundraising supplemented by short term debt financing to the extent required to bridge timing differences between the actual receipt of donations and the construction timetable.

7. Capital Budget Approvals: This project was not included in the FY2015 Capital Budget as fundraising was in progress. The Capital Budget Amendment requested at this time, in the amount of $15,000,000, is for design services. A future request for approval to complete this project will be requested upon an approved financing agreement.

8. Annual Operating and Maintenance Cost and Source of Revenue: The operating cost of the new facilities is anticipated to be approximately $8.10/sf.

9. Time Schedule:

5 of 61

Page 6: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Proposed Completion of Design Proposed Start of Construction (Site) Proposed Completion of Construction

May 2016* October 2015* October 2017*

*Assumes an approved financing agreement is in place prior to the June 2015 Board of Regents approval of the Annual Capital Budget

10. Project Team

Architect: Construction Manager at Risk:

11. Recommendation:

BWBR Architects TBD

The above described project scope of work, cost, funding, and schedule is appropriate:

Richa.!tJ.f ~t and Chief Financial Officer

P ela Wheelock, Vice President for University Services

6 of 61

Page 7: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Athletics Village Twin Cities Campus

Site Location Map

     

North

Athletes Village

7 of 61

Page 8: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Athletes Village

Twin Cities Campus

Board of Regents Facilities and Operations Committee

February 12, 2015

8 of 61

Page 9: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Location Map – Athletes Village

2

Athletes Village

North 9 of 61

Page 10: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Project Rationale

3

• Existing facility deficiencies

• Limited options available for scheduling

practices in existing venues

• Critical for recruitment

• Provides state-of-the-art tools to student-

athletes, administrators, and coaches

• Create a hub for the entire Athletics

Department and 720 student-athletes10 of 61

Page 11: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Project Description

4

• 340,000 SF Athletes Village includes:

– Center for Excellence

– Basketball Practice Facility

– Indoor Football Practice Facility

– Football Performance Center

• Total Project Cost: $150,000,000

– Construction Cost $125,350,000

– Key assumptions

• Buildings are included in a single phase

• Construction is initiated in 2016

• Financing agreements are complete

and approved by CFO and President 11 of 61

Page 12: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Project Description - continued

5

• Capital Funding *

– Private Gifts $15,000,000

Total Approved Project Budget $15,000,000

*for Schematic Design

• Architect:

– BWBR Architects

• Project Delivery Method:

– Construction Manager at Risk

12 of 61

Page 13: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Building Exterior - Concept

6

Gibson

Nagurski

Football

Support

Indoor

Football

Practice

Center for

ExcellenceBasketball

Practice

Bierman13 of 61

Page 14: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

©2014 Regents of the University of Minnesota. All rights reserved.

The University of Minnesota is an equal opportunity educator and employer. 14 of 61

Page 15: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

BOARD  OF  REGENTS  DOCKET  ITEM  SUMMARY  

 

 Facilities  &  Operations        February  12,  2015        Agenda  Item:   Annual  Update  on  Sustainability  in  Operations               Review       Review  +  Action       Action       X   Discussion    

       Presenters:   Pamela  Wheelock,  Vice  President,  University  Services           Jacqueline  Johnson,  Chancellor,  Morris  Campus           Shane  Stennes,  Sustainability  Coordinator      Purpose  &  Key  Points    Board  of  Regents  Policy:  Sustainability  and  Energy  Efficiency  states,  “The  University  is  committed  to  incorporating  sustainability  into  its  teaching,  research,  and  outreach  and  the  operations  that  support  them.”  The  purpose  of  this  presentation  is  to  update  the  Board  on  operations  sustainability  activities  and  accomplishments,  and  to  inform  the  Regents  about  proposed  changes  in  sustainability  governance  and  organizational  structures  for  the  institution.    Efforts  that  advance  sustainability  in  the  institution’s  operations  are  widespread  and  at  all  scales  –  from  individual  actions,  to  initiatives  covering  a  whole  department  or  function,  to  system-­‐wide  programs  that  benefit  multiple  campuses  and  communities.  This  diversity  provides  a  unique  opportunity  to  model  a  variety  of  approaches  and  solutions  to  issues  associated  with  the  three  aspects  of  sustainability:  environmental,  economic,  and  social  justice.    Reflecting  on  the  breadth  of  this  activity  across  the  University’s  campuses,  the  following  themes  emerge:    

• Buildings  –  How  facilities  are  constructed  and  operated  today  significantly  affects  the  sustainability  of  the  institution,  immediately  and  for  decades  to  come  given  the  longevity  and  durability  of  the  built  environment.    Given  this,  the  University  is  committed  to  applying  sustainable  building  standards,  which  encourage  choices  for  healthy  indoor  air,  purchase  of  local  materials,  and  features  that  reduce  resource  consumption  and  life  cycle  impacts  for  the  building.    

• Energy  –  The  energy  resources  supporting  teaching,  research,  and  outreach  are  the  primary  contributor  to  the  carbon  footprint  for  most  of  our  campuses  and  sites.  Therefore,  how  we  create  the  power  that  supports  progress  and  discovery,  and  how  much  energy  we  consume,  is  a  core  component  to  operations  sustainability  efforts.  Over  the  last  year,  progress  continued  on  multi-­‐year  initiatives  to  use  cleaner  energy  sources  and  to  use  energy  more  efficiently.  

X   This  is  a  report  required  by  Board  policy.    

15 of 61

Page 16: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

• Food  –  University  research  and  instruction  are  deeply  involved  in  the  development  of  sustainable  food  systems.  Students,  faculty,  and  staff  are  taking  these  lessons  learned  from  the  classroom,  the  lab,  and  the  field  to  transform  and  make  more  sustainable  our  campus  food  systems.    

• Transportation  –  How  we  get  to  and  around  campus  impacts  a  number  of  sustainability  dimensions  including  carbon  footprint,  resource  consumption,  and  personal  wellness.  Efforts  to  make  our  transportation  systems  more  sustainable  advanced  during  the  last  year  with  an  increase  in  the  availability  and  utilization  of  sustainable  transportation  such  as  mass  transit  and  bicycle.  

 • Waste  –  What  we  do  with  products  at  the  end  of  their  useful  life  is  an  important  strategy  

for  resource  conservation  and  sustainability.  Diversion  of  waste  to  more  sustainable  disposal  options  was  increased  in  the  past  year  through  expanding  collection  of  organic  waste  and  enhancing  collection  efforts  during  student  move-­‐in/move-­‐out  times.  

 These  themes  are  aligned  with  the  guiding  principles  and  implementation  objectives  outlined  in  Board  of  Regents  Policy:  Sustainability  and  Energy  Efficiency.  The  presentation  will  provide  additional  information  to  the  Board  on  accomplishments  and  activities  in  the  aforementioned  areas.    Sustainability  Governance  and  Organization    Over  the  course  of  the  past  year,  sustainability  at  the  University  has  reached  an  important  reflection  point.  The  Systemwide  Sustainability  Committee  work  team  completed  a  project  to  examine  and  make  recommendations  for  advancing  sustainability  at  the  institution.  Simultaneously,  the  Twin  Cities  Sustainability  Committee  fulfilled  two  of  its  major  objectives  and  it  started  development  of  a  committee  workplan  for  the  future.  Organizationally,  the  University’s  Sustainability  Director  and  the  Director  of  the  Institute  on  the  Environment  both  departed  the  institution  for  other  opportunities.    The  convergence  of  these  activities  and  changes  represent  an  important  opportunity  for  the  institution  to  reflect  on  what  has  been  accomplished,  to  identify  our  future  goals,  and  to  determine  how  to  organize  to  best  advance  institutional  sustainability  objectives.  The  presenters  will  review  with  the  Regents  changes  to  the  sustainability  committee  structure.            Background  Information    The  University  regularly  publishes  a  report  on  its  sustainability  activities  at  http://italladdsup.umn.edu/goals    February  2014:  Annual  Report  on  Sustainability,  Energy  Management,  and  Utilities  to  the  Facilities  and  Operations  Committee    

16 of 61

Page 17: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Annual Report on Sustainability in Operations

Board of Regents Facilities and Operations Committee

February 12, 2015

17 of 61

Page 18: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Discussion Topics

• Importance of

sustainability to

University mission

• Future University

sustainability

interests

2

Research Plot at Cedar Creek

18 of 61

Page 19: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

What is Sustainability?

Social

EnvironmentalEconomic

3

19 of 61

Page 20: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Sustainability Commitment

4

• Leadership

• Modeling

• Energy

Efficiency

• Education and

Outreach

• Research

• Operational

Improvements

The University is committed to incorporating

sustainability into its teaching, research, and

outreach, and the operations that support

them.

Morris’ Green Prairie Residence Hall

20 of 61

Page 21: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Sustainability Highlights 2004-2014

5

Systemwide

Sustainability Committee

Appointed

Work Team

Considers Future

Regents Policy on

Sustainability and

Energy Efficiency

Adopted

Systemwide

Sustainability, Goals,

Outcomes, Measures

Report

Institute on the

Environment

Formed

Straight A’s on

SEI Report Card

Second Nature Climate

Leaders Award for

MorrisPresidents’ Climate

Commitment Signed

2008

2004

2006 2009

2010

2011

2012

AASHE STARS Ratings:

UMM Gold, UMTC Silver

2013

2014

21 of 61

Page 22: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Sustainability Aligned with the Strategic Plan

• Address Grand

Challenges

• Reciprocal

Engagement

• Reject Complacency

6

Northrop Memorial Auditorium

22 of 61

Page 23: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Moving Forward

• What are our goals?

• How do we advance

this work?

• What are achievable

timeframes?

• How do we organize

our efforts?Twin Cities’ Living Laboratory

23 of 61

Page 24: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Envisioning Sustainability at the U

24 of 61

Page 25: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

• Build on our

success

• Engage senior

leaders

• Align accountability

• Increase capacity

9

Future Structure Goals

Duluth’s Victus Farms

25 of 61

Page 26: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Sustainability Commitment in Operations

10

• Leadership

• Modeling

• Energy

Efficiency

• Education and

Outreach

• Research

• Operational

Improvements

The University is committed to incorporating

sustainability into its teaching, research, and

outreach and the operations that support

them.

Crookston’s Heritage Hall Rain Garden

Under Construction26 of 61

Page 27: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Energy

• Over $28 million in

cost avoidance

since 2008

• 60% of campus

electricity is

renewable at Morris

11

West Central Research and Outreach

Center Solar Thermal Array27 of 61

Page 28: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

12

How does combined heat and power work?

28 of 61

Page 29: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Buildings

• Sustainable design

in every project

• 7 Energy Star rated

and 11 LEED

certified buildings

13

LEED Silver Ianni Hall at Duluth

29 of 61

Page 30: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Waste

• 49% of waste

diverted in 2014

• Crookston diverted

~ 500 lbs. of

aluminum for the

nonprofit Cans for

Cancer14

Waste Station at Coffman Union

30 of 61

Page 31: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Food

• 10 tons of food

harvested systemwide

• 1,382 lbs. of food

recovered and donated

to Urban Ventures to

feed families in need

15

Harvest from Crookston’s Campus Garden

31 of 61

Page 32: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Transportation

• Bike commuter

program logged a

million miles

• 13 electric vehicle

charging stations on

Twin Cities Campus

16

Light Rail on the Twin Cities Campus

32 of 61

Page 33: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Discussion Topics

• Importance of

sustainability to

University mission

• Future University

sustainability

interests

17

One of Two Wind Turbines at Morris33 of 61

Page 34: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

©2014 Regents of the University of Minnesota. All rights reserved.

The University of Minnesota is an equal opportunity educator and employer.

ItAllAddsUpUMN UMNSustain It All Adds Up –U of M

34 of 61

Page 35: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

BOARD  OF  REGENTS  DOCKET  ITEM  SUMMARY  

 

 Facilities  &  Operations        February  12,  2015        Agenda  Item:   Long  Range  Planning:  Balancing  Stewardship,  Focus,  and  Growth               Review       Review  +  Action       Action       X   Discussion    

       Presenters:   Pamela  Wheelock,  Vice  President,  University  Services           Michael  Berthelsen,  Associate  Vice  President,  Facilities  Management    Purpose  &  Key  Points    University  of  Minnesota  Twin  Cities  Campus  Master  Plan  Guiding  Principle  #9  calls  for  optimizing  the  use  of  campus  land  and  facilities  and  applying  best  practices.    This  principle  further  requires  that:      

• Campus  facilities  must  be  used  efficiently  and  effectively  in  support  of  the  academic  mission.  • Assignment  of  space  should  encourage  interdisciplinary  use.  • Space  needs  are  met  first  in  ways  other  than  building  new  facilities.  • Space  is  flexible  and  adaptable  to  ensure  buildings  can  meet  academic  needs.    

 In  recent  years  University  Services  has  provided  the  Board  of  Regents  with  information  on  various  aspects  of  the  items  addressed  in  this  principle,  including  regular  presentations  on  the  Facilities  Condition  Assessment,  space  utilization,  campus  master  planning,  and  the  six-­‐year  capital  planning  process.      University  Services  has  continued  to  evolve  its  thinking  on  these  topics  in  response  to  changing  programmatic  needs,  external  forces,  resource  availability,  and  facility  condition.  The  evolution  of  this  thinking  is  a  Physical  Asset  Strategy  focused  around  individual  buildings,  collegiate  facility  portfolios,  and  institutional  strategies.  The  presentation  will  introduce  the  concept  of  the  multi-­‐level  Physical  Asset  Strategy  and  to  focus  on  the  first  goal,  A  Plan  for  Every  Building.      Historically,  the  University  has  approached  each  of  its  buildings  as  stand-­‐alone  asset  that  should  be  treated  equally.  With  insufficient  resources  to  adequately  maintain  the  inventory,  this  approach  has  led  to  the  current  practice  whereby  1)  the  University’s  limited  repair  and  replacement  and  HEAPR  funds  are  spread  thinly  across  the  campus  in  an  attempt  to  keep  ahead  of  the  worst  problems  while  2)  large  amounts  of  capital  are  spent  on  a  select  few  buildings  to  bring  very  obsolete  facilities  up  to  like-­‐new  condition  (e.g.,  Tate  Laboratory  of  Physics).  This  has  led  to  a  more  reactionary  renewal  strategy  and  a  slow  decline  in  the  condition  of  all  but  the  select  few  facilities  where  the  University  is  able  to  afford  a  whole  building  renovation.      The  revised  approach  being  put  forth  under  “A  Plan  for  Every  Building”  will  develop  a  more  specific  and  intentional  plan  for  each  building  with  the  goal  of  providing  colleges  with  a  better  sense  of  the  

  This  is  a  report  required  by  Board  policy.    

35 of 61

Page 36: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

type  and  timing  of  reinvestment  that  they  can  reasonably  expect.  These  building-­‐specific  plans  will  allow  for  better  coordination  of  future  facility  and  programmatic  investments.  Accompanying  this  approach  in  a  subsequent  phase  will  be  an  increased  emphasis  on  helping  colleges  and  major  administrative  units  think  more  holistically  about  their  space  portfolio,  changing  programmatic  demands,  and  overall  facility  utilization.    Background  Information    The  2009  Twin  Cities  Master  Plan  identified  expansion  at  the  edges  of  the  East  Bank  campus.    Since  the  plan’s  adoption,  growth  has  been  achieved  in  one  of  the  primary  mission  activities  (research)  by  the  development  of  parcels  in  identified  areas.  The  Biomedical  Discovery  District  added  two  major  research  buildings  and  additions:  Cancer  Cardio  and  an  expansion  to  the  Center  for  Magnetic  Resonance  Research.  The  University  of  Minnesota  Health  clinics  are  under  construction  and  will  function  as  a  new  entry  to  the  east  side  of  the  East  Bank  of  the  Twin  Cities  campus.  The  Board  of  Regents  recently  approved  the  purchase  of  the  block  adjacent  to  the  clinics,  Block  31.  Foundation-­‐managed  land  at  the  intersection  of  Washington  and  Huron  Boulevard  offers  the  potential  for  coordinated  planning  in  support  of  the  evolution  of  the  campus.      Since  2000,  the  University  has  fully  renewed  11  buildings,  removed  23  buildings  from  its  inventory,  constructed  15  new  facilities,  and  improved  dozens  of  buildings  in  some  significant  way  through  the  use  of  HEAPR  funds.  The  2009  Twin  Cities  Campus  Utility  Master  Plan  established  a  roadmap  for  improving  electrical  distribution  infrastructure,  increasing  chilled  water  capacity,  and  upgrading  steam  generation  capabilities.  As  the  Facilities  and  Operations  Committee  heard  in  December  2014,  the  majority  of  initiatives  in  that  plan  have  been  completed  and  a  new  utility  master  plan  is  being  contemplated.        Robert  Bruininks  Hall,  completed  in  2009,  is  an  example  of  the  consolidated  effort  between  the  academic  and  operational  sides  of  the  University  working  to  understand  pedagogical  changes  and  improve  teaching  and  learning.  In  support  of  clinical  advancement,  University  of  Minnesota  Health  clinics  are  under  construction  on  the  East  Bank  and  a  comprehensive  academic  health  facility  study  is  underway.        Efforts  such  as  the  Smart  Labs  program  will  support  research  by  providing  more  cost-­‐effective  facilities.  Smart  Labs  is  an  emerging  design  approach  to  laboratory  facilities,  which  are  often  the  most  utility-­‐intensive  spaces  at  the  University.  Through  design  and  controls,  mechanical  systems  monitor  air  quality,  adjust  air  exchanges,  and  control  temperature  through  a  dynamic  system  that  responds  to  occupancy  and  demand.  The  potential  reduction  in  energy  use  is  50  percent  or  more.    The  Board  has  heard  updates  on  components  of  the  physical  asset  strategy  as  follows:    

• The  Facilities  Condition  Assessment  has  been  discussed  annually  with  the  committee  since  2003.    

• The  Board  reviews  and  adopts  a  six-­‐year  capital  plan  and  an  annual  capital  budget  each  year.  • An  annual  report  on  utilities  includes  components  of  the  University’s  infrastructure  needs  and  plans  to  address  them.  

• Presentations  with  a  focus  on  maximizing  the  University’s  physical  assets  were  given  throughout  FY  2013-­‐2014.  

36 of 61

Page 37: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Long-Range Planning:

Balancing Stewardship, Focus, and GrowthFacilities and Operations Committee

February 12, 2015

37 of 61

Page 38: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

University Services Strategic Plan

• Optimize the University’s physical assets– physical asset leadership

– functionality

– operating and lifecycle costs

– consistent campus experience

• Ensure a safe University– safe and secure places

– culture of shared responsibility

• Provide a memorable student experience– student-centric place

– meaningful connections

– quality, affordable services2

38 of 61

Page 39: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

2009 Master Plan Guiding Principles

3

Building Community

1. Cultivate a genuine sense of community

2. Strengthen connections to adjacent communities

Creating a Model Campus

3. Create a cohesive, memorable system of public spaces

4. Provide a compatible and distinctive built environment

5. Steward historic buildings and landscapes

6. Foster a safe, secure, and accessible campus environment

Integrating Local and Regional Systems

7. Preserve and enhance natural systems and features

8. Integrate transportation systems emphasizing pedestrians, bicycles, and transit

Using Resources Wisely

9. Optimize the use of campus land and facilities and apply best practices

10. Make the campus environmentally and operationally sustainable

11. Utilize the campus as a living laboratory to advance the University’s mission

39 of 61

Page 40: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Principle #9

• Campus facilities must be used efficiently and

effectively in support of the academic mission

• Assignment of space should encourage

interdisciplinary use

• Space needs are met first in ways other than building

new facilities

• Space is flexible and adaptable to ensure buildings

can meet academic needs

4

40 of 61

Page 41: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Space Goals

• Aligned: The University should provide the correct type, quality,

and quantity of space required for people and programs to

function effectively

• Sustainable: The University should have only as much space

as it can afford to operate, maintain, and support

• Managed: The University should provide tools and incentives

for maximizing the efficiency and effectiveness of its space

resources

5

41 of 61

Page 42: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

2009 Anticipated Growth

6

4

3

2

1

42 of 61

Page 43: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Stewardship

7

43 of 61

Page 44: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Focus

8

44 of 61

Page 45: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Growth

9

45 of 61

Page 46: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Physical Asset Strategy

10

46 of 61

Page 47: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

A Plan for Every Building

• Stewardship

– which buildings are we going to invest in?

• Focus

– which buildings will no longer be a priority?

• Growth

– which areas of the campus are targeted for expansion or

greater density?

11

47 of 61

Page 48: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Campus Condition

12

CampusTotal

GSF 1

Estimated

Replacement

Value 2

Projected

10-Year Needs

10 Year

Needs/Replacement

Value = (FCNI)

Twin Cities 22,787,527 $8,639,540,998 $ 2,837,671,283 0.33

Duluth 3,233,888 $968,930,667 $ 262,611,844 0.27

Morris 993,166 $359,732,192 $ 131,879,334 0.37

Crookston 674,626 $270,777,555 $ 56,161,631 0.21

ROCs 1,576,493 $240,513,943 $ 53,533,685 0.22

TOTALS 29,265,700 $10,479,495,355 $ 3,341,857,777 0.32

1Total Gross Square Feet (formally assessed square feet approximately 80% of total). Excludes Rochester Campus. Does not include parking ramp decks.

2Limited portions of facility replacement value modeled pending completion of formal assessment and report. 48 of 61

Page 49: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

CriteriaRange

Condition (FCNI)

Renovation Cost ($ per GSF)

Operations & Maint. Costs

Energy Demand (kBTU)

Space Efficiency

Historical Value (NHRP Status)

Code/Access(Issue Extent)

Low / Good Excellent <$25 <95% <95% Best Listed or Eligible 4-Not Significant

Good $25-$74 3-Minor

Mid Fair $75-$124 95% to 110% 95% to 110% Avg Steward 2-Moderate

Poor $125-$199 1-Major

High / Poor Critical >$200 >110% >110% Worst None 0-Serious

Building by Building Renewal Planning

13

• Adaptability• Master Plan Fit• Image/Aesthetics• Usability• Program Impact• Displacement

STA

GE

1ST

AG

E 2

Catch-up / Keep-up

Sustain

Dispose or Replace49 of 61

Page 50: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Renewal Plan – RRC Outline (*DRAFT EXAMPLE*)

14

RRC / Renewal Category Building Name % of Bldg % of RRC FCNI 10 Year Needs Min_InvestmentAG EXPERIMENT STATION 0.29 $16,568,780 $874,019

1_Keep Up AG AND LANDSCAPE STORAGE 51% 3% 0.08 $21,550 $0ANIMAL WASTE TREATMENT CENTER 100% 12% 0.16 $463,163 $0PLANT GROWTH FACILITIES - EAST 78% 14% 0.12 $2,510,802 $0

2_Catch Up / Keep Up AGRONOMY AND PLANT GENETICS GREENHOUSE 78% 0.37 $2,260,334 $150,674PLANT GROWTH FACILITIES - WEST 0.34 $8,548,803 $260,964

3_Sustain AGRICULTURAL CHEMICAL STORAGE BUILDING 100% 6% 0.46 $724,639 $114,789FARM AND GROUNDS MAINTENANCE BUILDING 100% 7% 0.48 $2,039,489 $347,593

AHC SHARED UNITS 0.29 $34,036,575 $970,6211_Keep Up CANCER CARDIOVASCULAR RESEARCH BLDG 54% 20% 0.00 $1 $0

DWAN VARIETY CLUB CARDIO RESEARCH 51% 11% 0.18 $17,053,667 $0MINNESOTA MOLECULAR AND CELLULAR THERAPY 80% 3% 0.29 $6,191,810 $0VETERINARY ANIMAL FACILITY 100% 1% 0.28 $618,778 $0717 DELAWARE BUILDING [EST] 24% 7% 0.08 $6,606,298 $0

3_Sustain ANIMAL SHELTER [NO SURVEY] 100% 1% $0LARGE ANIMAL HOLDING 100% 5% 0.54 $2,282,301 $537,027

4_Dispose VETERINARY ISOLATION BUILDINGS 100% 1% 0.64 $1,283,721 $433,593

BIOLOGICAL SCIENCES, COL OF 0.39 $102,062,913 $19,452,4841_Keep Up ECOLOGY BUILDING 78% 14% 0.19 $9,581,976 $0

CARGILL BLDG-MICROBIAL & PLANT GENO 40% 5% 0.07 $2,378,554 $02_Catch Up / Keep Up BIOLOGICAL SCIENCE 82% 31% 0.48 $51,908,099 $9,138,364

GORTNER LABORATORY 92% 15% 0.61 $24,204,626 $7,321,860SNYDER HALL 77% 7% 0.53 $11,544,960 $2,633,354

4_Dispose BIOLOGICAL SCIENCE GREENHOUSE 97% 3% 0.45 $2,444,699 $358,906

CARLSON SCHOOL OF MANAGEMENT 0.04 $8,732,453 $01_Keep Up CARLSON SCHOOL OF MANAGEMENT 77% 81% 0.08 $8,619,584 $0

HANSON HALL, HERBERT M., JR. 43% 19% 0.00 $112,869 $050 of 61

Page 51: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Facility Renewal Initiatives

1. Building by Building Planning

– Develop a renewal plan for each building

– Align financial resources to renewal plan

2. Facility Improvement Strategy

– Shift renewal funding to more predictable source

3. HEAPR / R&R Planning

– Expand consultative process with Collegiate units

4. Six Year Plan

– Continue to refine current plan and priorities

15

51 of 61

Page 52: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Physical Asset Strategy

16

52 of 61

Page 53: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Discussion

17

53 of 61

Page 54: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

©2014 Regents of the University of Minnesota. All rights reserved.

The University of Minnesota is an equal opportunity educator and employer. 54 of 61

Page 55: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Stewardship, Focus, and Growth

19

55 of 61

Page 56: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

20

56 of 61

Page 57: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

2118

90

19

00

19

10

18

80

19

30

19

40

19

50

19

60

19

70

19

80

19

90

20

00

20

10

19

20

01

7

18

0 C

MR

R

43

9

27

3

19

6 T

CF

Ba

nk S

tad

ium

03

0

43

0

24

7

19

14

85

48

6

04

2 W

alte

r L

ibra

ry

03

2 J

ackso

nH

14

7 W

ea

ve

r-D

en

s

17

8 N

ils H

asse

lmo

Ha

ll

18

4

16

7

17

1

41

5

00

8

35

2

10

3

42

3

05

0 W

illia

ms A

ren

a

42

7

43

6

09

5

38

3 B

aile

yH

15

0

21

1 M

on

da

leH

15

6 C

ivil

En

g.

43

2

18

1 R

idd

er

Are

na

00

1

09

3

00

3

00

6

04

0

32

2

05

7

12

1

15

2

43

7

14

0

37

1

43

4

02

8 S

an

ford

H

00

2

02

1

02

2 F

olw

ellH

33

5

12

7

36

43

65

37

3

42

9

Year Built

Gro

ss

Sq

ua

re F

ee

t (G

SF

)

Bldg FCNI Total Bldgs Bldg SqFeet

Excellent

Good

Fair

Below Avg

Poor

0.00-0.10 40 5,085,653

0.11-0.20 24 2,774,852

0.21-0.30 27 2,854,064

0.51-0.60

41 3,971,4540.31-0.50

28 2,589,284

31 3,720,293

1,000,000

500,000

0

NOTE: Excludes parking ramps, utilities buildings and warehouse facilities

100,000

50,000 GSF

20

71

39

Bie

rma

n1

42

Mo

os H

ea

lth

Scie

nce

s T

ow

er,

Ma

lco

m4

12

Ru

tta

n

39

0

20

4 W

ilso

n L

ibra

ry2

05

38

63

88

38

5

41

03

96

12

2 K

oth

offH

10

93

76

10

7

11

5

12

0

20

8 M

idd

leb

roo

kH

38

73

89

39

34

11

Bio

log

ica

l S

cie

nce

s

11

3

GSF By Year Built and FCNITwin Cities

09

9

09

8

15

4

16

1

17

3

17

7

37

9

Gross

Square Ft

(GSF)

01

1

01

9

02

0 E

llio

ttH

32

6

03

5 S

mith

H3

34

03

13

38

McN

ea

lH

03

73

42

04

4

05

2 P

ion

ee

rH0

51

05

80

56

06

3 C

om

sto

ckH

06

03

57

06

20

61

26

62

65

Me

ch

En

gin

ee

rin

g

37

23

74

38

1 11

1 D

ieh

lH1

05

Te

rrito

ria

l1

10

Fro

ntie

rH1

12

Ra

pso

nH

20

1 H

elle

r

12

5

39

4

06

4 C

offm

an

Un

ion

13

41

93

71

7 D

ela

wa

re

41

32

09

Ra

rig

41

4

14

3 D

wa

n

41

61

51

Co

mo

Stu

de

nt C

o-O

p H

ou

sin

g1

44

Ph

illip

s-W

an

ge

nste

en

Bu

ildin

g4

19

42

6

16

5 E

lectr

ica

l E

ng

ine

erin

g

21

6 H

HH

Ce

nte

r

15

92

15

16

92

18

WB

OB

19

2

43

81

74

Lio

ns

17

21

76

Ma

riu

cci

24

9 C

SO

M2

20

An

de

rse

n L

ibra

ry1

82

McN

am

ara

18

9 Y

ud

of

18

6 M

CB

36

92

41

24

2

25

01

97

WM

BB

00

5

1,500,000

Updated:

September 2014

29

9 S

TS

S

18

7

19

0

19

8

39

7

20

20

12

9 1

7th A

ve

Re

sid

en

ce

Ha

ll

05

3 N

ort

hro

p

15

3 C

an

ce

r &

Ca

rdio

Re

se

arc

h1

55

Ph

ysic

s &

Na

no

04

1

04

9 T

ate

La

b0

46

35

0

06

73

70

06

90

68

Ce

nte

nn

ialH

Above 0.61

191 20,995,600

Critical

20

2 S

ocia

l S

ci

20

3 B

leg

en

07

0 B

oyn

ton

38

2

07

4 M

ayo

Bu

ildin

g &

Ad

ditio

ns

07

32

68

07

12

67

06

6 A

mu

nd

so

nH

42

0

57 of 61

Page 58: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

BOARD OF REGENTS

DOCKET ITEM SUMMARY

Facilities & Operations February 12, 2015

Agenda Item: Information Items

X Review Review + Action Action Discussion

Presenters: Pamela Wheelock, Vice President, University Services

Purpose & Key Points

To update the committee regarding the following information items:

A. Update on TCF Bank Stadium Facility Use Agreement

B. Update on Combined Heat and Power Plant Permitting

Background Information

Information items are intended to provide the Board of Regents with information needed to

perform their oversight responsibilities.

This is a report required by Board policy.

58 of 61

Page 59: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Update on TCF Bank Stadium Facility Use Agreement

University of Minnesota

February 2015

All of the planning that went into hosting the Minnesota Vikings at TCF Bank Stadium paid off with a

smooth and successful first season. Vikings events followed the game day operations plan established

and refined over the first five years of Gopher game day operations.

The most significant challenge for the season was the single weekend with back-to-back Gopher-Vikings

games. Issues with workload, storage for two games worth of supplies, equipment, food and beverage,

as well as general event coordination were raised by multiple operating units as something to be

avoided in the future if possible.

Noteworthy items from the first season include:

• Construction - The University and Minnesota Vikings worked collaboratively to complete all

required and requested improvements to TCF Bank Stadium within the agreed upon schedule

and under the agreed upon budget. This included installation of the hydronic field heating

system and new artificial turf, erection and removal of temporary bleacher seating (that will be

reinstalled prior to the 2015 season), loge box heating, storage space, and the winterization of

restrooms and elevator lobbies as warranted.

• Parking and Transportation – The parking and transportation plan followed that for Gopher

events. Staff did note that it took longer to clear the streets after Vikings games than Gopher

games. This was attributed to higher attendance, more conflicts at LRT intersections, and a

different transportation mode split for the two events. On average the University parked about

7,700 cars per Vikings game, with about 2,500 having pre-purchased season parking passes.

Parking averaged about 6,700 cars on the east bank and 1,000 cars in St. Paul. The METRO

Green Line was incredibly popular causing long lines and delays. It was estimated that about

11,250 people arrived via the METRO per game. There was an average of 27 charter buses per

game. There were no significant tailgating issues. Parking and Transportation will continue to

work with the City of Minneapolis on improving the operation of the Huron Boulevard

intersection as well as an emerging issue at Malcom Avenue SE where Surly brewery traffic

crosses the University Transitway. Managing the numerous passenger transportation services,

including taxis, limousines, Uber, Lyft, and charter shuttle buses remains an on-going challenge.

• Safety and Security – There were no significant safety or security issues during the season. On a

per game basis, police calls were comparable to past Gopher seasons. University Emergency

Medical Services had approximately 100 patient contacts throughout the season and arranged

transport to local hospitals in 20 cases. Entry into the stadium was slowed due to NFL security

policies and later arriving crowds. The Washington game and the associated protest more than

59 of 61

Page 60: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

doubled the workload for public safety personnel for that one day and placed a significant

burden on staff leading up to and planning for the event. In the end about 4,000 persons were

able to peacefully protest with minimal disruption to the game.

• Stadium Operations - Facilities-related service calls during Vikings events were comparable to

Gopher events with approximately 20 calls per game. Issues were relatively minor and included

the usual items such as flooded toilets, broken cup holders, icy concrete, blown circuit breakers,

and television channel and volume problems. Painting the end zone letters purple for the

Vikings and back to gold for the Gophers was a challenge later in the season due to weather, but

otherwise stadium conversion went well. Vikings games (both inside the stadium and tailgating)

generated a total of 394,000 pounds of trash, of which 79% was recycled. Vikings games

generated about 15 percent more trash per capita that Gopher games, but had a higher

recycling recovery rate. At two games, the University achieved recycling recovery rates of 90%

and 89%, exceeding the 85% peak of Gopher games. Vikings games as a whole generated about

50% more trash inside the stadium, and 50% less trash outside in the tailgate lots, than Gopher

games.

• Community and Neighborhood – There were no significant or enduring game day issues in the

community. A couple of game day related noise complaints were received from the St. Anthony

Park neighborhood in St. Paul. Likewise, the increase in noise from media helicopters and

airplane flyovers over the stadium generated comments from the community. Additional steps

were put in place to improve communication with the community. Early in the season there

were some complaints about excess trash off-campus, but these were resolved through

operational changes as the season progressed.

• Food and Beverage – Numerous additional points of sale for both food and beverage, including

hawkers, were added for Vikings events. These were adjusted throughout the season in

response to lessons learned. Continued refinements are expected at Gate A which saw

disappointing sales and foot traffic. During pre-season there were long lines for ATM’s and, in

general, the concession stands with credit card readers did better than cash only stands.

Additional internet jacks and credit card readers were added to the majority of stands by the

start of the regular season. The increased points of sale in concessions and portables were well

received and assisted in increasing per capita revenues. UMPD conducted alcohol compliance

checks at four Vikings games. Aramark passed 66 of 68 compliance checks, a 97% success rate.

In both cases of failed checks, the employee was terminated immediately.

• Finance - The University developed a consolidated bill through University Services for all

University managed services including game day operations, construction, and parking. The

Vikings are current on all 26 invoices issued by the University for the expenses agreed to in the

Facility Use Agreement.

60 of 61

Page 61: Facilities & Operations Committee - Board of Regents 2015... · Project Narrative - Page 4 Project ... Design of Intercollegiate Athletics Athletes Village (Twin Cities Campus) -

Twin Cities Campus University Services

Office of the Vice President

317 Morrill Hall 100 Church Street Southeast

Minneapolis, MN 55455

Office: 612-624-3557

Fax: 612-626-2278

TO: Board of Regents Facilities and Operations Committee

FROM: Pamela Wheelock, Vice President, University Services

DATE: February 2, 2015

RE: Combined Heat and Power Plant Update

This memo is intended to provide a brief update on the status of the Combined Heat and Power (CHP)

project on the Twin Cities campus.

On January 27, 2015 the Minnesota Pollution Control Agency (MPCA) Citizens Board reviewed the CHP

permit application and environmental assessment worksheet, and gave the MPCA Commissioner

approval to issue the air permit. The Commissioner wrote on January 29, 2015 indicating that he had

signed the documents necessary for the permit to be issued.

The approval of this permit enables Capital Planning and Project Management to move ahead with the

commencement of construction. We anticipate the plant to be operational in December 2016. The

Guaranteed Maximum Price negotiated with the construction manager at risk has been approved and it is

within the amended budget approved by the Regents at their December 2014 meeting. We continue to

evaluate whether the amended budget is sufficient to address the costs of electrical distribution, or if

additional funds will need to be requested through the annual capital budget process (as indicated at the

December 2014 meeting.)

61 of 61