f uec - 6 oct 06 recent fnal collider operations ron moore fermilab – tevatron dept
TRANSCRIPT
UEC - 6 Oct 06
f Recent FNAL Collider Operations
Ron Moore
Fermilab – Tevatron Dept.
UEC - 6 Oct 06R. Moore - FNAL 2
f Hooray for record luminosities! How’d you do it?
• Notable achievements since the long shutdown ended
– Delivered lumi / week = 33.3 pb-1
– Delivered lumi from Aug 28-Sep 3 ≈ 119 pb-1
– Peak luminosity = 229 1030 cm-2 s-1 (store 4964 average, before D0 correction)
– Record # pbars at start HEP ≈ 2870 109
• Contents– Ingredients to record running
• Tevatron: efficiencies, luminosity lifetime
• Recycler: new working point smaller emittances
• Pbar Source: near record stacking rates
• Proton Source: near record beam intensity
• Reliability (and little luck)
– FY07 Plan
UEC - 6 Oct 06R. Moore - FNAL 3
f Where have we been? FY06 Outcome
Tevatron B1 Repairs/Start-up
Tevatron A4 Warm-up/
Repairs
FY06Shutdown
UEC - 6 Oct 06R. Moore - FNAL 4
f Run II Peak Luminosities
UEC - 6 Oct 06R. Moore - FNAL 5
f Luminosity Formula
• N = bunch intensity, f = collision frequency
• ε = transverse emittance (size), σz = bunch length
• H = “hour glass” factor (<1, accounts for beam size over finite bunch length)
Increasing the Luminosity
• Decrease β* (new 28 cm β* lattice in Sep 05)
• Increase Na and/or decrease εa from Recycler + electron cooling
• Increase Np
)()(2
**
z
ap
ap HNfN
L
UEC - 6 Oct 06R. Moore - FNAL 6
f Increasing Beam Intensities
Beam Intensities at Start of HEP
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
4000 4200 4400 4600 4800 5000
Store #
Pb
ar
Inte
ns
ity
[E
9]
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
11000
Pro
ton
Inte
ns
ity
[E
9]
Pbar
Proton
10000 E9 278 E9 / bunch 2700 E9 75 E9 / bunch
UEC - 6 Oct 06R. Moore - FNAL 7
f Reduced Tevatron Beam Loss @ 150 GeV
Bunched Beam Inefficiency @ 150 GeV
-5
0
5
10
15
20
25
30
4000 4200 4400 4600 4800 5000
Store #
Ine
ffic
ien
cy
[%
]
Pbar
Proton
UEC - 6 Oct 06R. Moore - FNAL 8
f Reduced Beam-Beam Effects @ 150 GeV
Proton Inefficiency @ 150 GeV
0
5
10
15
20
25
30
500 1000 1500 2000 2500 3000 3500
Pbar Intensity @ Injection [E9]
Pro
ton
Inef
ficie
ncy
[%
]
Dec 04 - Feb 06
Jun 06 -
• Protons suffered from higher pbar intensities
• New helix (separator voltages) increased separation, especially at worst crossing point
UEC - 6 Oct 06R. Moore - FNAL 9
f• Long-range beam-beam effects degrade luminosity lifetime + integral
– Nearest parasitic crossings (≈59 m from IPs) especially bad
• During shutdown, additional separators installed to increase separation– More separation reduced beam-beam effects
– ~20% increase @ upstream IP
– Not as much @ downstream IP
• Luminosity lifetime improved ~20% compared to pre-shutdown running– Increased integrated luminosity per store (for given store length)
Tevatron Luminosity Lifetimes
UEC - 6 Oct 06R. Moore - FNAL 10
f Better Lifetime More Delivered Luminosity
Normalized Lumi Integral / 24 hr vs Initial Luminosity
0
1000
2000
3000
4000
5000
6000
7000
8000
0 50 100 150 200 250
Initial Luminosity [1030 cm-2 s-1]
No
rmal
ized
Lu
mi
Inte
gra
l [n
b-1
per
24
hr]
Dec 04 - Feb 06
Jun 06 -
Based on luminosity lifetime fits and adjusting to 24 hour store duration
UEC - 6 Oct 06R. Moore - FNAL 11
f Comparing HEP Stores to Model
• Luminosity evolution during
HEP now agrees better to
model without beam-beam
effects
• Most pbars lost during HEP
are burned in luminosity
– That’s good!
• Protons suffer more from
beam-beam effects
– Especially with smaller pbars
V. Lebedev
UEC - 6 Oct 06R. Moore - FNAL 12
f New Recycler Working Point
• During HEP shot-setup, Recycler “momentum-mines” 9 parcels that become the 9 pbar transfers (4 bunches/transfer) shot to the Tevatron
• Poor lifetime and high transverse emittance growth rate in that state
• New tune working point reduced emittance growth rate (mid-August) Brighter (smaller emittance) pbars delivered to Tevatron
Higher instantaneous luminosity for same number of pbars
(Smaller emittances also improves pbar and proton efficiencies in Tevatron)
• Currently limiting max Recycler pbar “stash” to 400 1010
• Increase as experience and pbar stacking rate allow
UEC - 6 Oct 06R. Moore - FNAL 13
f Pbar Stacking
0
5
10
15
20
25
7/1/2005 8/20/2005 10/9/2005 11/28/2005
1/17/2006 3/8/2006 4/27/2006 6/16/2006 8/5/2006 9/24/2006
Ave
rage
Sta
ckin
g R
ate
(E
10/h
r)
0
1000
2000
3000
4000
5000
Antip
roto
ns
x 101
0
Average Stacking rate
Pbars delivered•Started slowly after shutdown, partly due to Booster proton output
•Ramped up to record performance (20.5 mA / hr peak yesterday)
•Increasing stacking still most direct route to higher Tev luminosities
Ave
rag
e S
tack
ing
Rat
e [
101
0 m
A /
hr
]
Pba
rs D
eliv
ered
[1
010
]
UEC - 6 Oct 06R. Moore - FNAL 14
f Protons on Pbar TargetNow > 8 1012
protons / pulse on target
UEC - 6 Oct 06R. Moore - FNAL 15
f Reliability
Motherhood statement: You can’t integrate luminosity if you aren’t running…
Mother Nature statement: How’d you like Monday’s storm? I won that round…
5 store running averages
UEC - 6 Oct 06R. Moore - FNAL 16
f Where do we go from here? The FY07 Plan
8 week shutdown
~2x existing dataset
Ramp up to48 pb-1/ week
UEC - 6 Oct 06R. Moore - FNAL 17
f FY07 Plan for Peak Luminosity
UEC - 6 Oct 06R. Moore - FNAL 18
f Summary
• Record running thanks to performance and reliability of all machines
– More protons on pbar target (Linac / Booster / Main Injector)
– Near record pbar stacking rates (Debuncher / Accumulator)
– Smaller pbar emittances from Recycler
– More beam to HEP and improved luminosity lifetime in Tevatron
– Good reliability and luck to avoid (most of) Mother Nature’s wrath
• Current Tevatron Records
– Delivered luminosity / week = 33.3 pb-1
– Peak luminosity = 229 1030 cm-2 s-1
• FY07 plan
– Deliver ≈ 1800 pb-1 at up to 48 pb-1/ week
– Reach peak luminosity 3.2 1030 cm-2 s-1
– 8 week shutdown during summer
UEC - 6 Oct 06R. Moore - FNAL 19
f
Accelerator Highest Energy
Cockroft Walton 750 keV
Linac 400 Mev
Booster 8 GeV
Main injector 150 GeV
TEVATRON 980 GeV
NuMI (120 GeV)MiniBoone
(8 GeV)
P1 Line
A1 Line
UEC - 6 Oct 06R. Moore - FNAL 20
fCollider Run II Integrated Luminosity
0
5
10
15
20
25
30
35
5 20 35 50 65 80 95 110 125 140 155 170 185 200 215 230 245 260 275 290
Week #(Week 1 starts 03/05/01)
Wee
kly
In
teg
rate
d L
um
ino
sit
y (
pb
-1)
0
400
800
1200
1600
2000
Ru
n In
teg
rate
d L
um
ino
sity
(p
b-1
)
Weekly Integrated Luminosity Run Integrated Luminosity
UEC - 6 Oct 06R. Moore - FNAL 21
f FY07 Plan for Weekly Integrated Lumi
UEC - 6 Oct 06R. Moore - FNAL 22
f
0
1
2
3
4
5
6
7
8
9
10S
ep-0
3
Sep
-04
Sep
-05
Oct
-06
Oct
-07
Oct
-08
Oct
-09
Date
Inte
grat
ed L
umin
osity
(fb
-1) 30mA/hr
25mA/hr
20mA/hr
15mA/hr
Run II Luminosity Projections
Zero-Stack Pbar Stacking Rate Design
Now on this line