exw-p007-0201-mc-keo-rp-00209-scada pmcs control-r6.pdf

40
IA/12-13/D/003/ST Pre Contract Professional Consultancy Design Services for AI Rayyan Road & AI Bustan Street South (P007) AL RAYYAN ROAD Al Rayyan Road Junctions R6 Road Tunnel Tunnel SCADA PMCS Control Concept Prepared by: Doc. No.: EXW-P007-0201-MC-KEO-RP-00209 Rev. D02

Upload: joshua-evans

Post on 19-Dec-2015

24 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0201-MC-KEO-RP-00209 Page i

Rev. D02

Control Sheet

IA/12-13/D/003/ST

Pre Contract Professional Consultancy Design Services

for AI Rayyan Road & AI Bustan Street South (P007)

AL RAYYAN ROAD

Al Rayyan Road

Junctions R6 Road Tunnel

Tunnel SCADA PMCS Control Concept

Prepared by:

Doc. No.: EXW-P007-0201-MC-KEO-RP-00209

Rev. D02

Page 2: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf
Page 3: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0201-MC-KEO-RP-00209 Page iii

Rev. D02

TABLE OF CONTENTS

1.0 INTRODUCTION ...................................................................................................................................... 1

1.1 Document Purpose and Scope .................................................................................................................. 1

1.2 Related Documents .................................................................................................................................. 1

1.3 Related Drawings ..................................................................................................................................... 1

1.4 Codes and standards applicable .............................................................................................................. 4

1.5 List of Abbreviations ................................................................................................................................. 5

2.0 ASHGHAL’S RELEVANT OBJEVTIVES ............................................................................................................ 9

3.0 ELECTROMAGNETIC COMPATIBILITY (EMC) ...................................................................................... 9

3.1 Normative references .......................................................................................................................... 9

4.0 PMCS OVERVIEW .................................................................................................................................. 10

4.1 Introduction............................................................................................................................................ 10

4.2 System Architecture ............................................................................................................................... 11

4.3 SCADA Servers ........................................................................................................................................ 11

4.4 Supervisory Control PLC’s ....................................................................................................................... 12

4.5 Outstation PLC’s ..................................................................................................................................... 12

4.6 Dual configuration ................................................................................................................................. 12

4.7 SCADA Graphical User Interface (Operator Interface) ........................................................................... 13

4.8 TMC/TSS ................................................................................................................................................. 14

4.9 Engineering Terminal ............................................................................................................................. 14

4.10 Control & Monitoring Software............................................................................................................ 15

4.11 Control Network ................................................................................................................................... 15

4.12 Instrumentation Interface .................................................................................................................... 15

4.13 Cable Types .......................................................................................................................................... 16

4.14 Equipment Accommodation ................................................................................................................. 16

4.15 Power Supply Redundancy ................................................................................................................... 16

4.16 Capacity Sizing ..................................................................................................................................... 16

5.0 GENERAL MONITORING AND CONTROL SCHEME ..................................................................................... 16

5.1 Data Acquisition ..................................................................................................................................... 16

5.2 Alarm Monitoring ................................................................................................................................... 17

5.3 Control and Data Flows .......................................................................................................................... 18

5.4 Control Modes ........................................................................................................................................ 18

5.5 Running Hours and Plant Metrics .......................................................................................................... 19

5.6 Signal Conditioning ................................................................................................................................ 19

6.0 TUNNEL LIGHTING SYSTEM CONTROL SCHEME ........................................................................................ 20

6.1 Control Scheme Overview ...................................................................................................................... 20

6.2 General Lighting Control Scheme ........................................................................................................... 20

6.3 Automatic Control Mode ........................................................................................................................ 21

Page 4: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0201-MC-KEO-RP-00209 Page iv

Rev. D02

6.4 Manual Operator Override from TMC Control Mode ............................................................................. 21

6.5 Manual Operator Override from SCADA GUI Control Mode .................................................................. 22

6.6 Manual Operator Override from SCP Control Mode .............................................................................. 22

6.7 Manual Operator Override from LCP Control Mode .............................................................................. 23

6.8 Lamp Status Monitoring ........................................................................................................................ 23

6.9 Emergency Standby Generator Load Shedding ...................................................................................... 23

7.0 FIRE SAFETY SYSTEMS CONTROL SCHEME ................................................................................................ 23

7.1 Emergency/Electrical Distribution Panels Control Scheme .................................................................... 23

7.2 Smoke Detection System ........................................................................................................................ 24

7.3 Smoke Control Panels ............................................................................................................................. 24

8.0 COMMUNICATIONS SYSTEMS CONTROL SCHEME .................................................................................... 25

8.1 Control Scheme Overview ...................................................................................................................... 25

8.2 Emergency Roadside Telephones Control Scheme ................................................................................. 25

8.3 Public Automatic Branch Exchange Control Scheme .............................................................................. 25

8.4 Airwave and Emergency Services Radio Repeater Control Scheme ....................................................... 25

8.5 Public Address Control Scheme .............................................................................................................. 25

9.0 ELECTRICAL SUPPLY SYSTEMS CONTROL SCHEME .................................................................................... 26

9.1 Control Scheme Overview ...................................................................................................................... 26

9.2 MV System Control Scheme ................................................................................................................... 26

9.3 Transformer Control Scheme ................................................................................................................. 26

9.4 LV System Control Scheme ..................................................................................................................... 28

9.5 Emergency Standby Generator Control Scheme .................................................................................... 31

9.6 UPS Systems Control Scheme ................................................................................................................. 32

10.0 MISCELLANEOUS SYSTEMS CONTROL SCHEME ....................................................................................... 34

10.1 Control Scheme Overview .................................................................................................................... 34

11.0 INTERFACES ............................................................................................................................................ 34

11.1 TMC Interface ....................................................................................................................................... 34

11.2 Physical Locations of PMCS Plant Interfaces ........................................................................................ 34

11.3 Plant Interfaces .................................................................................................................................... 34

11.4 Ethernet TCP/IP Infrastructure ............................................................................................................. 35

Page 5: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 1 of 36

Rev. D02

1.0 INTRODUCTION

1.1 Document Purpose and Scope

This document describes the outline design for the Tunnel Plant Monitoring and Control System

(PMCS) that forms part of the Tunnel construction works.

This document provides the following information:

Overview of the PMCS

PMCS system architecture and topology

Description of plant interfaces

Description of external interfaces

Details of schemes for plant monitoring and control

1.2 Related Documents

Document Number Title

EXW-P007-0201-MC-KEO-RP-00209 Tunnel SCADA PMCS Control Concept (This Document)

EXW-P007-0201-MC-KEO-RP-00210 Tunnel TMC/TSS – SCADA/PMCS Control Interface

EXW-P007-0201-MC-KEO-RP-00211 Tunnel PMCS Smoke Control Panel Control Interface

EXW-P007-0201-MC-KEO-RP-00212 Tunnel PMCS Plant I/O Control Interface List

EXW-P007-0201-MC-KEO-RP-00213 Tunnel CCTV Camera Specification

EXW-P007-0201-MC-KEO-RP-00214 Mechanical, Electrical and Systems – General Specifications

EXW-P007-0201-MC-KEO-RP-00215 Tunnel Pumped Drainage Installations

EXW-P007-0201-MC-KEO-RP-00216 Tunnel Fire Safety Systems Specification

EXW-P007-0201-MC-KEO-RP-00217 Tunnel Panels

EXW-P007-0201-MC-KEO-RP-00218 Tunnel Cross Passage Doors

EXW-P007-0201-MC-KEO-RP-00219 Tunnel Way Finding Signs

EXW-P007-0201-MC-KEO-RP-00220 Tunnel Operational Control Concept

EXW-P007-0201-MC-KEO-RP-00221 Tunnel Ventilation Control Concept

EXW-P007-0201-MC-KEO-RP-00222 Junction R6 Road Tunnel – Detailed Design M&E Systems

EXW-P007-0201-MC-KEO-RP-00223 Contract 2 Underpasses – Detailed Design M&E Systems

EXW-P007-0201-MC-KEO-RP-00224 Not used

EXW-P007-0201-MC-KEO-RP-00225 Underpass Pumped Drainage installations

1.3 Related Drawings

Drawing No. Title

EXW-P007-0201-JF-KEO-DG-00100-001

RAYYAN ROAD KEY PLAN M&E LAYOUT (SHEET 1 OF 1)

EXW-P007-0201-MC-KEO-DG-00106-001

RAYYAN ROAD FIRE SAFETY TYPICAL PLAN & SECTIONS (SHEET 1 OF 2)

EXW-P007-0201-MC-KEO-DG-00106-002

RAYYAN ROAD FIRE SAFETY TYPICAL PLAN & SECTIONS (SHEET 2 OF 2)

EXW-P007-0201-MC-KEO-DG-00107-001

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 FIRE MAIN, HYDRANTS & VALVES LOCATION (SHEET 1 OF 8)

Page 6: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 2 of 36

Rev. D02

Drawing No. Title

EXW-P007-0201-MC-KEO-DG-00107-002

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 FIRE MAIN, HYDRANTS & VALVES LOCATION (SHEET 2 OF 8)

EXW-P007-0201-MC-KEO-DG-00107-003

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 FIRE MAIN, HYDRANTS & VALVES LOCATION (SHEET 3 OF 8)

EXW-P007-0201-MC-KEO-DG-00107-004

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 FIRE MAIN, HYDRANTS & VALVES LOCATION (SHEET 4 OF 8)

EXW-P007-0201-MC-KEO-DG-00107-005

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 FIRE MAIN, HYDRANTS & VALVES LOCATION (SHEET 5 OF 8)

EXW-P007-0201-MC-KEO-DG-00107-006

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 FIRE MAIN, HYDRANTS & VALVES LOCATION (SHEET 6 OF 8)

EXW-P007-0201-MC-KEO-DG-00107-007

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 FIRE MAIN, HYDRANTS & VALVES SECTION (SHEET 7 OF 8)

EXW-P007-0201-MC-KEO-DG-00107-008

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 FIRE MAIN, HYDRANTS & VALVES SECTION (SHEET 8 OF 8)

EXW-P007-0201-MC-KEO-DG-00201-001

RAYYAN ROAD JUNCTION 6 TUNNEL TU1 ILLUMINATED EMERGENCY WAY FINDING SIGN LOCATIONS (SHEET 1 OF 4)

EXW-P007-0201-MC-KEO-DG-00201-002

RAYYAN ROAD JUNCTION 6 TUNNEL TU1 ILLUMINATED EMERGENCY WAY FINDING SIGN LOCATIONS (SHEET 2 OF 4)

EXW-P007-0201-MC-KEO-DG-00201-003

RAYYAN ROAD JUNCTION 6 TUNNEL TU1 ILLUMINATED EMERGENCY WAY FINDING SIGN LOCATIONS (SHEET 3 OF 4)

EXW-P007-0201-MC-KEO-DG-00201-004

RAYYAN ROAD JUNCTION 6 TUNNEL TU1 ILLUMINATED EMERGENCY WAY FINDING SIGN LOCATIONS (SHEET 4 OF 4)

EXW-P007-0201-MC-KEO-DG-00301-001

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 EDP, EP, CCP & TULDB LOCATIONS (SHEET 1 OF 7)

EXW-P007-0201-MC-KEO-DG-00301-002

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 EDP, EP, CCP & TULDB LOCATIONS (SHEET 2 OF 7)

EXW-P007-0201-MC-KEO-DG-00301-003

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 EDP, EP, CCP & TULDB LOCATIONS (SHEET 3 OF 7)

EXW-P007-0201-MC-KEO-DG-00301-004

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 EDP, EP, CCP & TULDB LOCATIONS (SHEET 4 OF 7)

EXW-P007-0201-MC-KEO-DG-00301-005

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 EDP, EP, CCP & TULDB LOCATIONS (SHEET 5 OF 7)

EXW-P007-0201-MC-KEO-DG-00301-006

RAYYAN ROAD JUNCTION R6 TUNNEL- TYPICAL SINGLE EMERGENCY PANEL ARRANGEMENT (WITHOUT HYDRANT) (SHEET 6 OF 7)

EXW-P007-0201-MC-KEO-DG-00301-007

RAYYAN ROAD JUNCTION R6 TUNNEL- TYPICAL INDIVIDUAL LIGHTING DISTRIBUTION PANEL (SHEET 7 OF 7)

EXW-P007-0201-MC-KEO-DG-00302-001

RAYYAN ROAD JUNCTION R6 TUNNEL-TU1 EDP, EP &CCP GROUP ARRANGEMENT (SHEET 1 OF 1)

EXW-P007-0201-MC-KEO-DG-00401-001

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 PA/VA SYSTEM LOCATIONS (SHEET 1 OF 6)

EXW-P007-0201-MC-KEO-DG-00401-002

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 PA/VA SYSTEM LOCATIONS (SHEET 2 OF 6)

EXW-P007-0201-MC-KEO-DG-00401-003

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 PA/VA SYSTEM LOCATIONS (SHEET 3 OF 6)

EXW-P007-0201-MC-KEO-DG-00401-004

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL PA/VA SYSTEM LOCATIONS (SHEET 4 OF 6)

EXW-P007-0201-MC-KEO-DG-00401-005

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL PA/VA SYSTEM LOCATIONS (SHEET 5 OF 6)

EXW-P007-0201-MC-KEO-DG-00401-006

AL RAYYAN ROAD JUNCTION R6 ROAD TUNNEL PA/VA CONFIGURATION (SHEET 6 OF 6)

Page 7: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 3 of 36

Rev. D02

Drawing No. Title EXW-P007-0201-MC-KEO-DG-00402-001

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 PA/VA SCHEMATIC SHEET (SHEET 1 OF 1)

EXW-P007-0201-MC-KEO-DG-00501-001

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 GENERAL FIRE DETECTION & WARNING (SHEET 1 OF 4)`

EXW-P007-0201-MC-KEO-DG-00501-002

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 GENERAL FIRE DETECTION & WARNING (SHEET 2 OF 4)`

EXW-P007-0201-MC-KEO-DG-00501-003

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 GENERAL FIRE DETECTION & WARNING (SHEET 3 OF 4)`

EXW-P007-0201-MC-KEO-DG-00501-004

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 GENERAL FIRE DETECTION & WARNING (SHEET 4 OF 4)`

EXW-P007-0201-MC-KEO-DG-00601-001

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 VENTILATION LAYOUT (SHEET 1 OF 4)

EXW-P007-0201-MC-KEO-DG-00601-002

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 VENTILATION LAYOUT (SHEET 2 OF 4)

EXW-P007-0201-MC-KEO-DG-00601-003

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 VENTILATION LAYOUT (SHEET 3 OF 4)

EXW-P007-0201-MC-KEO-DG-00601-004

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 VENTILATION LAYOUT (SHEET 4 OF 4)

EXW-P007-0201-MC-KEO-DG-00701-001

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 LANE CONTROL SIGNS LOCATION LAYOUT (SHEET 1 OF 4)

EXW-P007-0201-MC-KEO-DG-00701-002

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 LANE CONTROL SIGNS LOCATION LAYOUT (SHEET 2 OF 4)

EXW-P007-0201-MC-KEO-DG-00701-003

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 LANE CONTROL SIGNS LOCATION LAYOUT (SHEET 3 OF 4)

EXW-P007-0201-MC-KEO-DG-00701-004

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 LANE CONTROL SIGNS LOCATION LAYOUT (SHEET 4 OF 4)

EXW-P007-0201-MC-KEO-DG-00702-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL PMCS/SCADA COMMUNICATION NETWORK SHEET 1 OF 1

EXW-P007-0201-MC-KEO-DG-00800-001

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 CCTV CAMERA SCHEMATIC (SHEET 1 OF 1)

EXW-P007-0201-MC-KEO-DG-00801-001

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 CCTV CAMERA LAYOUT (SHEET 1 OF 5)

EXW-P007-0201-MC-KEO-DG-00801-002

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL CCTV CAMERA SCHEMATIC (SHEET 2 OF 5)

EXW-P007-0201-MC-KEO-DG-00801-003

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL CCTV CAMERA SCHEMATIC (SHEET 3 OF 5)

EXW-P007-0201-MC-KEO-DG-00801-004

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL CCTV CAMERA SCHEMATIC (SHEET 4 OF 5)

EXW-P007-0201-MC-KEO-DG-00801-005

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL CCTV CAMERA SCHEMATIC (SHEET 5 OF 5)

EXW-P007-0201-MC-KEO-DG-00802-001

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 VAID CAMERA LAYOUT (SHEET 1 OF 5)

EXW-P007-0201-MC-KEO-DG-00802-002

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL VAID SYSTEM SCHEMATIC (SHEET 2 OF 5)

EXW-P007-0201-MC-KEO-DG-00802-003

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL VAID CAMERA CONFIGURATION (SHEET 3 OF 5)

EXW-P007-0201-MC-KEO-DG-00802-004

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 VAID CAMERA LAYOUT (SHEET 4 OF 5)

EXW-P007-0201-MC-KEO-DG-00802-005

RAYYAN ROAD JUNCTION R6 TUNNEL TU1 VAID CAMERA CONFIGURATION (SHEET 5 OF 5)

EXW-P007-0201-MC-KEO- RAYYAN ROAD JUNCTION R6 TUNNEL TU1 VAID CAMERA SYSTEM SCHEMATIC

Page 8: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 4 of 36

Rev. D02

Drawing No. Title

DG-00803-001 (SHEET 1 OF 1)

EXW-P007-0201-MC-KEO-DG-00901-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL ERT NETWORK (SHEET 1 OF 1)

EXW-P007-0201-MC-KEO-DG-00902-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL LHD DTS SCHEMATIC (SHEET 1 OF 2)

EXW-P007-0201-MC-KEO-DG-00902-002

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL LEAKY FEEDER (SHEET 2 OF 2)

EXW-P007-0201-MC-KEO-DG-00903-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL FIRE SAFETY SYSTEMS (SHEET 1 OF 1)

EXW-P007-0201-MC-KEO-DG-00904-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL LANE CONTROL SIGN SYSTEM SCHEMATIC (SHEET 1 OF 2)

EXW-P007-0201-MC-KEO-DG-00904-002

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL DMS/LCS CONFIGURATION (SHEET 2 OF 2)

EXW-P007-0201-MC-KEO-DG-00905-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL IMPOUNDING SUMP VENTILATION SCHEMATIC (SHEET 1 OF 1)

EXW-P007-0201-MC-KEO-DG-00906-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL SCP GA PANEL LAYOUT (SHEET 1 OF 3)

EXW-P007-0201-MC-KEO-DG-00906-002

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL SCP GA PANEL LAYOUT (SHEET 2 OF 3)

EXW-P007-0201-MC-KEO-DG-00906-003

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL SCP GA PANEL LAYOUT (SHEET 3 OF 3)

EXW-P007-0201-MC-KEO-DG-00907-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL – TYPICAL SMOKE CONTROL PANEL LAYOUT (SHEET 1 OF 1)

EXW-P007-0201-MC-KEO-DG-00908-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL - CROSS PASSAGE DOORS (SHEET 1 OF 3)

EXW-P007-0201-MC-KEO-DG-00908-002

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL - TYPICAL CROSS CONNECTION DOORS (SHEET 2 OF 3)

EXW-P007-0201-MC-KEO-DG-00908-003

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL - DETAIL OF FIRE BRIGADE CONNECTORS (SHEET 3 OF 3)

EXW-P007-0201-MC-KEO-DG-00909-001

RAYYAN ROAD JUNCTION R6 ROAD TUNNEL - DETAIL OF FIRE BRIGADE CONNECTORS (SHEET 3 OF 3)

EXW-P007-0201-CD-KEO-DG-00212-005

Al RAYYAN ROAD JUNCTION R6 ROAD TUNNEL ATTENUATION TANK SECTIONAL DETAIL (SHEET 5 OF 6)

EXW-P007-0201-CD-KEO-DG-00212-006

Al RAYYAN ROAD JUNCTION R6 ROAD TUNNEL ATTENUATION TANK/PLANT ROOM INSTALLATION SCHEMATIC (SHEET 6 OF 6)

EXW-P007-0201-CD-KEO-DG-00208-001

Al RAYYAN ROAD UNDERPASS DRAINAGE CHANNEL DETAILS

1.4 Codes and standards applicable

Hierarchy of codes, standards and specifications

1. National legislation, codes and statutes

2. Regional legislation, codes and statutes

3. This document

4. UK Highways Agency BD78/99 and NFPA 502

5. UK Highways Agency Series 7000 specifications

6. PIARC Road Tunnel Manual

Page 9: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 5 of 36

Rev. D02

7. Ashghal ITS Specifications

8. Federal Highway Administration (System Engineering Handbook for ITS Systems)

9. QCS Specifications 2010

10. WIS Standards

1.5 List of Abbreviations

The abbreviations used in this Specification and the associated Plant Specifications have the

following meanings:

Abbreviation Meaning

ac Alternating Current

AC Air Changes

AFBMA Anti-Friction Bearing Manufacturer’s Association

AI Analogue Input

AIP Approval in Principle

AISI American Iron and Steel Institute

AO Analogue Output

ASTM American Society for Testing and Materials

ATEX ATmosphères EXplosives or Explosive Atmospheres

BS British Standard

BG Break Glass

CCD Charged Coupled Device

CCTV Closed Circuit Television

CD-R Compact Disc Recordable

CD Compact Disc

CDM Construction Design and Management (Regulations)

CDROM Compact Disc Read Only Memory

CER Communications Equipment Room

CM Configuration Management

C of C Certificate of Conformity

CO Carbon Monoxide

COSHH Control of Substances Hazardous to Health

CPD Cross Passage Door

DB Distribution Board

DC Direct Current

DI Digital Input

DMRB Design Manual for Roads and Bridges

DP Distribution Panel

DO Digital Output

DOL Direct-on-line

DSEAR Dangerous Substances and Explosive Atmospheres Regulations UK (ATEX 137 implementation)

DTS Distributed Temperature sensing

DW Duct Work (Specification)

EC European Commission

EDP Emergency Distribution Point

ELV Extra Low Voltage

EMC Electromagnetic Compatibility

EMF Electromagnetic Fields

Page 10: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 6 of 36

Rev. D02

Abbreviation Meaning

EMI Electromagnetic Interference

EN European Standard

EP Emergency Point

EPDM Ethylene Propylene Diene Monomer

EPROM Erasable Programmable Read Only Memory

E2PROM Electrically Erasable Programmable Read Only Memory

EEPROM Electrically Erasable Programmable Read Only Memory

ERT Emergency Roadside Telephone

EX Explosion Proof rated

FAP Fire Alarm Panel

FAT Factory Acceptance Tests

FDS Functional Design Specification

FL Factory Link

FO Fibre Optic

FP Fire Protection

FRLS Fire Retardant Low Smoke

FS Fire Survivable

FSK Frequency Shift Key

FSC Forest Stewardship Council

GSM Global System for Mobiles

GUI Graphical User Interface

HA Highways Agency UK

HDLC High level Data Link Control

HEMP High Energy Magnetic Impulse

HH High-High

HMI Human Machine Interface

HVAC Heating/Ventilation/Air-Conditioning

HVCA Heating and Ventilating Contractor’s Association UK

HV High Voltage

Hz Hertz

IEC International Electrotechnical Commission

I/O Input/Output

IP Ingress Protection

IP Internet Protocol

IRT Incident Response Team i.e. Emergency Services

ISO International Standards Organisation

ITS Intelligent Transportation Systems

LCP Local Control Panel

LCS Lane Control Signs

LCS Lighting Control System

LEL Lower Explosive Level

LFS Low Fume and Smoke

LHD Linear Heat Detection

LL Low-Low

LPCB Loss Prevention Certification Board

LSOH Low Smoke Zero Halogen

LV Low Voltage, Voltage below 1000 Vac and above 50 Vac.

M&E Mechanical and Electrical

MCB Miniature Circuit Breaker

Page 11: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 7 of 36

Rev. D02

Abbreviation Meaning MCC Motor Control Centre

MCCB Moulded Case Circuit Breaker

MCHW Manual of Contract Documents for Highway Work in the UK

MES Mechanical - Electrical - Systems

MET Metrological/Environmental/Traffic

MMFO Multi-Mode Fibre Optic

MTBF Mean Time Between Failure

MTTR Mean Time to Repair

MUX Multiplexer

MV Medium Voltage, voltage above 1000 Vac but below HV

NAMAS National Measurement Accreditation Services

N/B Northbound

NEMA National Electrical Manufacturer’s Association

NER Neutral Earthing Resistor

NFPA National Fire Protection Association

NO Niitrogen Oxide

NPSH Net Positive Suction Head

NR Noise Reduction

NRV Non-Return Valve

NTCIP National Transportation Communications for ITS Protocol

ODVA Open DeviceNet Vendors Association

O&M Operations and Maintenance

OPC Open Process Control

PA Public Address

PABX Private Automatic Branch Exchange

PAVA Public Address Voice Alarm

PC Personal Computer

PEFC Programme for the Endorsement of Forest Certification

PIARC The World Road Association

PLC Programmable Logic Controller

PMCS Plant Monitoring and Control System

PN Pressure Normal

PQP Project Quality Plan

PROM Programmable Read Only Memory

PSU Power Supply Unit

PTZ Pan, Tilt and Zoom

PVC Polyvinyl Chloride

QA Quality Assurance

QC Quality Control

QCS Qatar Construction Standards

RAM Random Access Memory

RH Relative Humidity (as %)

RIO Remote Input / Output

RS232 Recognised Standard 232

RS422 Recognised Standard 422

RS485 Recognised Standard 485

RTD Resistance Temperature Detector

RTU Remote Terminal Unit

SAT Site Acceptance Tests

Page 12: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 8 of 36

Rev. D02

Abbreviation Meaning

S/B Southbound

SCADA Supervisory Control and Data Acquisition

SCP Smoke Control Panel

SDS Software Design Specifications

SFA Service Factor Amperes

SLV Safety Low Voltage

SMFO Single Mode Fibre Optic

STP Sheilded Twisted Pair

TCP/IP Transmission Control Protocol/Internet Protocol

TDSCG Tunnel Design and Safety Consultation Group

TERP Tunnel Emergency Response Plan

TFT Thin Film Transistor (Display Technology)

TM Tunnel Maintainer

TMC Traffic Management Centre/Tunnel Management Centre

TOA Tunnel Operating Authority

TR Technical Requirement

TSB Tunnel Service Building

TSS Tunnel Sub-System

UL Underwriters Laboratories

UPS Uninterruptible Power supply

USB Universal Serial Bus

USSG United States Standard Gage

UK United Kingdom

UKAS United Kingdom Accreditation Service

UTP Unsheilded Twisted Pair

V Volt(age)

Vac Volts ac

VAID Video Automatic Incident Detection

VCR Video Cassette Recorder

Vdc Volts dc

VDU Visual Display Unit

VESDA Very Early Smoke Detection Aspirator

VID Video Incident Detection

VIS Visibility

VMS Variable Message Sign

VSD Video Smoke Detection

VSD Variable Speed Detection

WIS Water Industry Specifications UK

XPLE Cross-linked Polyethylene

Page 13: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 9 of 36

Rev. D02

2.0 ASHGHAL’s RELEVANT OBJEVTIVES To meet the requirements of the UK HA DMRB BD78/99, the UK HA MCHW 5.7.2 and

Federal NFPA502 (IAN 020 Rev. A1) in respect to classification of tunnels and life safety

provisions.

Achieves environmental sustainability and whole life costs within the scheme budget

To provide a safe tunnel environment for road users, operators, maintenance staff, police

and the emergency services both during construction and in permanent conditions.

Reduces operational and maintenance risks

Meet The Road Tunnel Safety Regulations 2007 UK.

Safety of the work force and the road users

Deliver scheme as soon as possible

3.0 Electromagnetic compatibility (EMC)

3.1 Normative references

The following referenced documents are indispensable for the application of this document.

For dated references, only the edition cited applies. For undated references, the latest edition of the

referenced document (including any amendments) applies.

The applicable environment here is industrial.

Reference, Technical Committee, Title Subject

Normative references

IEC 60050-161, International Electrotechnical Vocabulary (IEV) – Chapter 161: Electromagnetic compatibility

IEC 61000-4-2, Electromagnetic compatibility (EMC) – Part 4: Testing and measurement techniques – Section 2: Electrostatic discharge immunity test

IEC 61000-4-3, Electromagnetic compatibility (EMC) – Part 4-3: Testing and measurement techniques – Radiated, radio-frequency, electromagnetic field immunity test

IEC 61000-4-4, Electromagnetic compatibility (EMC) – Part 4-4: Testing and measurement techniques – Electrical fast transient/burst immunity test

IEC 61000-4-5, Electromagnetic compatibility (EMC) – Part 4: Testing and measurement techniques – Section 5: Surge immunity test

IEC 61000-4-6, Electromagnetic compatibility (EMC) – Part 4-6: Testing and measurement techniques – Section 6: Immunity to conducted disturbances, induced by radio-frequency fields

IEC 61000-4-8, Electromagnetic compatibility (EMC) – Part 4: Testing and measurement techniques – Section 8: Power frequency magnetic field immunity test

IEC 61000-4-11, Electromagnetic compatibility (EMC) – Part 4-11: Testing and measurement techniques – Voltage dips, short interruptions and voltage variations immunity tests

CISPR 22, Information technology equipment – Radio disturbance characteristics – Limits and methods of measurement

Residential, commercial, light industrial environment

IEC 61000-6-3: Electromagnetic compatibility (EMC) - Part 6-3: Generic standards - Emission standard for residential, commercial and light-industrial environments

Emission

IEC 61000-6-1: Electromagnetic compatibility (EMC) - Part 6-1: Generic standards - Immunity for residential, commercial and light-industrial environments

Immunity

Industrial environment

Page 14: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 10 of 36

Rev. D02

IEC 61000-6-4: Electromagnetic compatibility (EMC) - Part 6-4: Generic standards - Emission standard for industrial environments

Emission

IEC 61000-6-2: Electromagnetic compatibility (EMC) - Part 6-2: Generic standards - Immunity for industrial environments

Immunity

Power station and substation environment

IEC 61000-6-5: Electromagnetic compatibility (EMC) - Part 6-5: Generic standards - Immunity for power station and substation environments

Immunity

Indoor equipment

IEC 61000-6-6: Electromagnetic compatibility (EMC) - Part 6-6: Generic standards - HEMP immunity for indoor equipment

HEMP immunity

4.0 PMCS Overview

4.1 Introduction

The PMCS will be formed as an autonomous monitoring and control system allowing all monitoring

and control operations to be performed locally to the tunnel.

The PMCS will be configured as a hierarchical distributed system, consisting of the following

monitoring and control layers:

Supervisory Control and Data Acquisition (SCADA) servers, incorporating the Graphical User

Interface (GUI)

Central supervisory control Programmable Logic Controllers (PLC’s)

Distributed outstation PLC’s associated with plant requiring local control functions, such as

those at local control panels

The provision of layered hierarchical monitoring and control will provide the following benefits:

Partitioning of monitoring and control capability to appropriate operating personnel

throughout the infrastructure

Reversionary monitoring and control capability in the event of incident

Ability to commission and maintain assets independently of the complete infrastructure

The SCADA Servers will be configured as a dual hot-standby pair.

The supervisory control PLC’s will be configured as a dual hot-standby pair.

Other PLC units will be configured in a dual hot-standby pair, where required, in order to provide a

highly reliable and available system, otherwise a singular unit will be employed connected to either

the A or B ring network.

SCADA Server, supervisory control PLC, PLC, and RIO units will be interconnected by a dual

redundant control network, in an A and B configuration.

The SCADA/PMCS will contain a separate logic programming emulating an interface window , named

the Tunnel Subsystem, which will interface with the TMC tunnel operator desk, for the remote

interface and control in respect to the traffic control aspect of the tunnel operation.

Page 15: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 11 of 36

Rev. D02

4.2 System Architecture

The overall PMCS system architecture will be as shown in Figure 1.

Figure 1: PMCS Overall System Architecture

4.3 SCADA Servers

The SCADA Servers will perform overall management of the PMCS, including the following functions:

Provision and management of the Operator GUI

Datapoint storage and retrieval

The SCADA Servers will be configured as dual industrial-grade PCs operating in hot-standby mode.

NB Fan Starters,

Pollution Sensors

and VAID

TMC Authorized User TOA Authorized user

Manual Overrides and

Status Monitoring

Tunnel Subsystem

(TSS)

Dual PLC

Processors

Control

and Status

Dual

Redundant

Dual PLC

Processors

Dual

Redundant

NB Smoke

Control Panels

Dual

Redundant Dual

Redundant

SB Smoke

Control Panels

Control and

Status

Smoke Panel

Control Requests

and Plant Status

SB Fan Starters,

Pollution Sensors

and VAID

PMCS

Dual Redundant

SCADA Servers

Page 16: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 12 of 36

Rev. D02

4.4 Supervisory Control PLC’s

The supervisory control PLC’s performing overall management of the outstation PLC’s and RIO units

of the PMCS, including functions such as the following:

Overall system control

System moding

Interfacing with the GUI

Outstation PLC and RIO unit monitoring and control

Data acquisition management

System health monitoring

System alarm monitoring

Communications with Traffic Management Centre (TMC

The supervisory control PLC’s will be configured as dual industrial-grade PLC’s operating in hot-

standby mode.

4.5 Outstation PLC’s

Outstation PLC’s will be used where control functionality is required to be distributed within the

tunnel such as, for example, for the management of Smoke Control Panels (SCP’s).

Outstation PLC’s will be configured as dual industrial-grade PLC’s operating in hot-standby mode.

4.6 Dual configuration

Master-standby arbitration and selection of the supervisory control PLC’s will be achieved through

the use of external *with respect to the PLC’s+ hardware watchdog timing circuitry. Such a hardware-

based approach will provide much greater determinism of mutual exclusion of mastery.

Upon system start-up one of the supervisory control PLC pair, arbitrarily selected, shall automatically

be configured as the master, assuming control of the PMCS.

The master-standby state of the supervisory control PLC’s will be used to derive and determine the

master-standby configuration of other dual configuration units throughout the PMCS, thus removing

the need for additional master-standby arbitration hardware in each instance of dual configurations

throughout the system.

External hardware-based watchdogging will be used to monitor the supervisory control PLC’s for

failure, in which case mastery will be allocated the standby unit.

Software-based heartbeat watchdogging will be employed by the supervisory control PLC’s to

monitor the health of other dual configuration units throughout the PMCS, and allocation of mastery

performed accordingly.

The dual configuration scheme will transparently implement the following dual configuration

functions:

Replication of the processing context to the standby, including programs and data

Detection of faults and switchover

Page 17: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 13 of 36

Rev. D02

Disqualification of failed units

Re-qualification (i.e. re-synchronisation) of formerly failed units

Manual de-selection of the master

Heartbeat monitoring

4.7 SCADA Graphical User Interface (Operator Interface)

A SCADA operator interface (GUI) will be provided for use by Operators within each of the following

locations:

the Tunnel Services Building, (Master)

TOA Operator Interface at the TMC

Traffic Control Interface at the TMC

The Master SCADA GUI will be delivered by dual redundant servers and all SCADA GUI’s will provide

the following features and functions:

Operator access via password-protected login

System mimic display, including the following:

o Display of tunnel systems status in graphical format annotated with key system

parameter values

o Display of alarm conditions

o Display of tunnel system operational moding

Alarm management, including the following:

o Display of alarm conditions

o Alarm acknowledgements

o Alarm log viewing

Operator control actions, including the following:

o Setting of operational parameters for applicable tunnel systems

o Mode control of applicable tunnel systems

o Disqualification of sensors from participation in control mode demand calculation

algorithms

Data review and trending

PMCS system management, including the following:

o Logging of significant TPCMS events such as the following:

Operator login/logout

Significant Operator control actions

o Manual selection of dual configuration control processor changeover

o System start-up and shutdown [interlocked]

o Access to server operating system environment

The SCADA GUI will be presented on an Operator terminal featuring TFT-LCD monitor, keyboard, and

mouse/pointing device.

Page 18: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 14 of 36

Rev. D02

4.8 TMC/TSS

The Tunnel Subsystem (TSS) is an segregation of a partition of the control and monitoring logical

software system deployed within the SCADA/PMCS application servers/PLCs at the TSB that

facilitates the control and monitoring of carriageway and tunnel infrastructure through the TMC

Traffic system, providing functions such as the following:

The setting of signs

Control of tunnel lighting

Control of tunnel ventilation (0%- 50% and 100%, however we expect that only 50 and 100%

will be implemented)

PA message control, manual and automatic)

The TMC Traffic system acts as an integrated incident management tool that reacts to all relevant

situations by selecting the appropriate Tunnel Emergency Response Plan (TERP) from its database

and will display this to the Traffic Control Operator dealing with the tunnel incident for acceptance

and execution.

The TMC Tunnel System allows Traffic Control Operators to execute pre-defined response plans, as

well as allowing Operators to effect ad-hoc control actions in response to particular tunnel incidents

and situations.

4.9 Engineering Terminal

The PMCS will provide connectivity for an mobile engineering terminal for use by maintenance

personnel. The mobile engineering terminal may be connected to any suitable port on the PMCS

control network.

The engineering terminal will provide features and functions related to the commissioning and

maintenance of the system, including the following:

Monitoring and control of plant

Modification of the system control programs

Modification of system configuration parameters

Manual selection of dual configuration control processor changeover

Manual disqualification and re-qualification of dual configuration control processors

Fault diagnostic facilities

Logging and trending facilities

The engineering terminal will not normally be connected to the system, but will be capable of being

removed / inserted into the operational system.

The engineering terminal will consist of an industrial rough service Ultrabook with network interface

card hosting the engineering terminal software application.

Page 19: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 15 of 36

Rev. D02

4.10 Control & Monitoring Software

All PMCS control software will be developed using industry-standard software development

processes and methodologies.

PLC Control software will be developed in accordance with IEC 61131-3, Programmable controllers -

Part 3: Programming languages, 2003, in one of the following forms:

Ladder logic

Function block

Structured text

Instruction list

All Control and monitoring software will be developed in accordance with BS EN 61508 Safety

Integrity Level (SIL) 2 and a validation process shall be carried out confirming the criteria reached,

i.e. SIL2.

4.11 Control Network

The PMCS processing and I/O units will intercommunicate control and data via a dedicated dual

redundant Ethernet-based control network.

The PMCS control network will be formed of multi-mode fibre optic and copper segments, as

required.

The backbone of the PMCS control network linking central control units to outstation units will be

two fibre optic circuits, each arranged in a ring topology to form two independent ‘A’ and ‘B’ closed-

loop self-healing networks capable of continued operation in the event of a fibre-optic cable

disconnection or network switch failure.

The dual supervisory control PLC’s will each be provided with dual connections to both the ‘A’ and

‘B’ control networks, thereby providing resilience in the event of failure of one of the supervisory

control PLC’s.

Each PMCS outstation processing and I/O unit will be provided with a single connection to one of the

‘A’ or ‘B’ networks. At outstation locations where dual redundant processing and I/O units are

deployed, then each of these will be provide with a single connection to the ‘A’ and ‘B’ control

networks; one unit to the ‘A’ control network and one unit to the ‘B’ control network.

The dual SCADA Servers will each be provided with a single connection to the ‘A’ or ‘B’ control

networks; one to the ‘A’ control network and one to the ‘B’ control network.

The PMCS will use Ethernet-based Open Process Control (OPC) protocols for internal and external

communications.

4.12 Instrumentation Interface

The PMCS will provide connectivity to a range of instrumentation industry standards including the

following:

Page 20: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 16 of 36

Rev. D02

4-20mA current loop

Volt-free contacts

Serial protocols to include EIA-RS232, EIA-RS485 and USB connections

Generic Fieldbus and open/proprietary implementations thereof

Industrial Ethernet OVDA compliant implementation

4.13 Cable Types

Connections to plant will be implemented using the following cable types, as appropriate, and

dependent upon the specific requirements of the plant selected during detailed design stages:

Cat5e unshielded twisted pair (UTP) in accordance with TIA/EIA-568-B

Cat5e shielded twisted pair (STP) in accordance with TIA/EIA-568-B

Single-mode fibre-optic cable to (See ITS Specifications)

BS5308 Instrumentation Cable Part 1 Type 1

4.14 Equipment Accommodation

Remote Network switches and PLCs will be installed at the following locations:

Within the TSB within dedicated racks and remote positions (several locations)

Within 4 No. SCP’s outside each portal (Dual configuration)

Within 8 No. EDP’s within each bore (16 In total, single configuration interleaved)

In the midpoint sump plant room, (Dual Configuration)

4.15 Power Supply Redundancy

Dual configuration PMCS Server and PLC processing units will be fed through the UPS system and

parallel power supplies to ensure that failure of a single supply does not induce a common-mode

failure to redundant equipment.

4.16 Capacity Sizing

The PMCS will be capacity sized to accommodate the requirements of the outline design detailed

herein. Furthermore, allowances will be made for additional capacity, as follows:

I/O intrinsic average spare capacity: 10%

I/O spare capacity by addition of modules: 25%

I/O spare capacity by addition of subsystems: 50%

PLC Processor capacity by addition of spare capacity: 100%

SCADA Server disk/processing spare capacity: 200%

5.0 General Monitoring and Control Scheme

5.1 Data Acquisition

The PMCS performs logging of all data point values acquired or derived into a historical database.

Log entries will provide the following information:

Page 21: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 17 of 36

Rev. D02

Time stamp of entry

Date stamp of entry

Identity of the data point

Data point value with scaling

Data point transmission through the PMCS will be optimised with respect to update rates and data

push/pull configuration in order that:

Valid and current data is always available throughout the system

Data currency is always deterministic

Throughput on the transmission infrastructure is optimal

The transmission infrastructure can accommodate worst case data-burst situations,

particularly in non-normal scenarios.

The dual supervisory control PLC’s will independently gather all data from local sources regardless of

master-standby status. This approach will provide validation that each main supervisory control PLC

has an active communication link with the outstation devices, and will maintain data currency

allowing hot-swap to the standby in the event of failure of the master unit.

5.2 Alarm Monitoring

The PMCS will monitor all controlled plant for alarm conditions, including PMCS-internal fault

conditions.

The following alarm conditions will be monitored, as follows:

Alarm indications generated as a result of detection of conditions external to the PMCS. The

nature and extent of such alarms will be determined during subsequent design stages, but

are likely to include sensing of out-of-band parameters, i.e. physical measurements outside

their expected range.

Alarm indications generated as a result of detection of conditions internal to the PMCS. The

nature and extent of such alarms will be determined at subsequent design stages, but are

likely to include sensing of failure of control system processors, and the like.

Alarm indications will be filtered and stored by the PMCS.

Filtered alarm indications will be transmitted to the TAO/TMC for remote condition monitoring.

Two forms of alarm and fault monitoring mechanisms will be provided, as follows:

Active reporting by exception, whereby the plant and PMCS elements will signal alarm and

fault conditions detected

Polled monitoring by PMCS, whereby the active control elements of the control system will

intercommunicate periodically in order to determine the ‘health’, i.e. the correct operation,

of the control system itself.

Page 22: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 18 of 36

Rev. D02

Alarm indications will be ranked by importance/severity and displayed via the SCADA Tunnel

Operator Terminal (GUI) such that conditions are displayed in different modes according to the

condition severity and the operating privileges of any user logged on to the system.

Alarm indications will be recorded in a historical database for subsequent analysis. Log entries will

provide the following information:

Time stamp of entry

Date stamp of entry

Description of the alarm condition

5.3 Control and Data Flows

The dual supervisory control PLC's will receive control commands from the SCADA Servers and will

derive their own responses to these commands. The supervisory control PLC designated as master

will be configured to issue demand outputs to the tunnel plant. The standby supervisory control PLC

will be inhibited from issuing demand outputs.

The master and standby supervisory control PLC’s will replicate commands and data between them

in order that the processing context of both units remains synchronized, allowing hot-swap to the

standby in the event of failure of the master unit.

The SCADA Servers and TSS application will request data only from the supervisory control PLC that

is designated as master.

Dual configuration outstation PLC's will both transmit data to both supervisory control PLC’s.

Inputs from plant to dual PLC units will be read from PLC units and will be combined into a common

data set. In the case of data mismatch the worst-case plant condition will be reported.

Outputs to plant from dual RIO units will be configured so that either PLC device can operate the

plant by paralleling of outputs, thereby ensuring continued / fail-safe plant operation in the event of

failure of a single PLC unit.

5.4 Control Modes

The PMCS will provide a range of control modes to suit the operational requirements of the tunnel

environment.

The supervisory control PLC’s will accept requests for selection of control mode and will arbitrate

these requests in order to activate the highest priority control mode.

The following general control modes/sources will be provided ranked in increasing priority order:

Automatic

Automatic control mode is the default control mode and is always active, although possibly over-

ridden by a higher priority control mode. Automatic control mode demand is derived from plant

sensor levels and states, set-points, and control parameters. Automatic control mode demand will

Page 23: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 19 of 36

Rev. D02

always be derived and presented to Operators, regardless of the actual control mode active, thereby

providing the operator with visibility of the automatically calculated demand.

TMC Traffic Control operation through the TSS application

TOA Tunnel Operation control relates to operator control and demand selections from the

TMC Tunnel Operator interfaced via the TMC control stations and Network.

Engineering Terminal

Engineering Terminal control relates to operator control and demand selections from

engineering/maintenance terminals connected at any location on the PMCS network

infrastructure, and normally present at the TMC

SCADA GUI application

The SCADA GUI application is the primary source of system control moding', and is located

within the Tunnel Services Building (TSB).

Smoke Control Panels

These control mode selections will be requested from the SCP’s. Arbitration of control

requests will be performed in the event that both SCP's are accessed at the same time such

that only one Smoke Control Panel can issue commands at a time.

Local Plant Control

Local plant control will be affected by direct operation of individual items of plant and/or their

associated autonomous control systems via plant-local control panels. The PMCS will continue to

monitor locally controlled plant and generate control demands wile local plant control is active; in

order that seamless transition of control may be achieved once local plant control is relinquished.

Additional control modes specific to particular tunnel systems will be provides, as required, and

these are described herein within the sections detailing the control schemes for specific tunnel

systems.

5.5 Running Hours and Plant Metrics

The PMCS will acquire/derive and store data relating to the running time of plant, as well as other

metrics required to assist the effective and efficient plant maintenance. Data to be a

acquired/derived and stored includes the following:

Plant running time in hours

Plant duty cycle

Plant failure instances

Plant failure instance periods

The PMCS will provide the ability to reset metrics for individual items of plant.

5.6 Signal Conditioning

The PMCS will implement a scheme of signal conditioning and scaling that ensures that data is

transmitted, stored, and manipulated in a uniform and consistent manner.

Page 24: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 20 of 36

Rev. D02

Where required, digital inputs will be conditioned by pulse stretching in order that fast switching

signals are detected correctly

Where required, digital inputs will be conditioned by de-bouncing in order that switch selections and

the like are read correctly.

6.0 Tunnel Lighting System Control Scheme

6.1 Control Scheme Overview

The PMCS will provide a range of control modes to provide efficient and effective control of the

lighting system.

The PMCS will accept requests for selection of control mode and will arbitrate these requests in

order to activate the highest priority control mode.

Control modes that will be provided, ranked in increasing order of priority, are as follows:

Automatic

Manual Operator Override from TMC/TSS

Manual Operator Override from TOA/SCADA GUI

Manual Operator Override from SCP

Manual Operator Override from Lighting Control Panel (LCP)

Automatic control mode is the default control mode, and is always active, although possibly over-

ridden by a higher priority control mode

The manual operator override control modes provide an Incident Control sub-mode that allows

lighting level change demands to be actioned with reduced rate-of-change constraints, thus allowing

more rapid changes in lighting levels to be achieved.

Lighting control will be achieved via an autonomous Lighting Control System (LCS). A LCS will be

provided for each tunnel bore. Each LCS will be provided with a local LCP. The PMCS will interface

with the LCS, generating demands for lighting levels and monitoring LCS and lighting system status.

The Manual Operator Override from LCP, also known as Ancillary Local Manual Control, control

mode will be provided by the LCS

6.2 General Lighting Control Scheme

The LCS will control the tunnel lighting automatically based upon photometer sensor readings.

Two external photometers will be provided at the stopping distance from each tunnel bore entrance

portal, and the average reading of these will be used by the LCS to calculate a lighting level demand

for each tunnel bore.

The LCS will support seven stages of lighting, with stage 1 providing the lowest level of illumination

and stage 7 providing the highest level of illumination, this representing 100% of total possible

Page 25: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 21 of 36

Rev. D02

lighting system output. The LCS will convert photometer sensor readings into a demand for lighting

for stages 1 through to 7.

The LCS will integrate photometer sensor readings in order to filter fast rate of change

environmental effects upon the sensors, thus avoiding rapid and spurious lighting level changes.

The LCS will sequence through lighting stages with a set-point limit period between stage transitions

in order that gradual changes in lighting levels are achieved, with an associated reduction in peak

inrush currents. An Incident Control Mode will be provided by the LCS in which the limit period

between stage transitions is reduced so that more rapid changes in lighting level may be made.

The LCS will detect lamp failures and switch in additional units to compensate and maintain lighting

levels.

Threshold zone luminance will track the L20 luminance measured by the external photometers. The

threshold zone luminance will maintain 7% of the L20 value.

Transition zone luminance will track the threshold zone luminance and will vary along the length of

the zone following the reduction curve defined in BS5489-2.

Exit zone luminance will be as defined in BS5489-2.

Emergency lighting levels will be in accordance with BS5489-2 and BS EN 1838:1999, taken to be the

greater of the required level for stage 2 lighting or 15lux.

Lighting stages 1 through to 4 will be backed up by Emergency Standby Generator, with UPS support

for stage 1 and 2 lighting to cover the period of generator start-up. Failure of the Emergency Standby

Generator to provide a supply within 5 minutes of a demand will result in reversion to emergency

lighting levels, which will be maintained for at least 2 hours via the UPS.

6.3 Automatic Control Mode

In Automatic control mode the LCS will autonomously control the lighting levels within each tunnel

bore based upon external photometer sensor readings.

The automatically calculated lighting stage demand, and the currently active lighting stage for each

tunnel bore will be monitored by the PMCS, and this will be displayed on the SCADA GUI and

recorded by the SCADA Servers. This will give the Operator visibility of how the lighting control will

change when higher priority control modes are de-activated and lower priority control modes

become active.

6.4 Manual Operator Override from TMC Control Mode

The PMCS will accept Manual Operator Override from TMC control mode demands for each tunnel

bore. These demands will be for lighting stage 7 only.

The Manual Operator Override from TMC control mode will remain active until the PMCS receives a

control mode reset command from the TMC.

Page 26: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 22 of 36

Rev. D02

The SCADA GUI will provide a password-protected manual operator override control mode reset

function in case it is not possible for the TMC operator to issue a reset command due to TMC

communications link failures, and the like. The use of this function will be recorded by the SCADA

Servers for auditing purposes.

6.5 Manual Operator Override from SCADA GUI Control Mode

The PMCS will accept Manual Operator Override from SCADA GUI control mode demands for each

tunnel bore. These demands will be for lighting stages 1 through 7.

The PMCS will request the LCS to activate the lighting stage demanded by the operator. The LCS will

arbitrate the PMCS lighting stage demand, only selecting for activation demanded lighting stages

greater than the lighting stage demand calculated automatically by the LCS. Lighting stage demands

rejected by the LCS will be displayed by the SCADA GUI and recorded by the SCADA Servers.

The PMCS will provide an Incident Control Mode that will allow the PMCS to request the LCS to

activate the demanded lighting stage with reduced transition times between lighting stages in order

to allow more rapid variations in lighting levels to be achieved.

The Manual Operator Override from SCADA GUI control mode will remain active until the PMCS

receives a control mode reset command from the SCADA GUI.

6.6 Manual Operator Override from SCP Control Mode

The PMCS will accept Manual Operator Override from SCP control mode demands from for each

tunnel bore. These demands will be for lighting stages 1 through 7.

Four smoke control panels will be provided, situated at the portals, one per entrance and exit to

each tunnel bore.

Lighting control via the SCP’s will be arbitrated on a ‘first-come, first-served’ basis such that once an

SCP has been granted control for a tunnel bore the other SCP’s will be locked out from control of

that tunnel bore for the duration of the control selection being active.

SCP’s will provide the following lighting-related controls and indicators for each tunnel bore:

Request/relinquish local manual control selection control : 1 input latching toggle

Local manual control active indicator

Currently selected lighting stage indicator: 7 stage indication from stage 1 to stage 7

Requested lighting stage increment/decrement demand control: 2 input control with senses

of ‘increment’ and ‘decrement’

Incident control demand control: 2 input control with senses of ‘on’ and ‘off’

The PMCS will request the LCS to activate the lighting stage demanded by the Operator at the SCP.

The LCS will arbitrate the PMCS lighting stage demand, only selecting for activation demanded

lighting stages greater than the lighting stage demand calculated automatically by the LCS. Lighting

stage demands rejected by the LCS will be displayed by the SCADA GUI and recorded by the SCADA

Servers.

Page 27: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 23 of 36

Rev. D02

The PMCS will provide an Incident Control Mode that will allow the PMCS to request the LCS to

activate the demanded lighting stage with reduced transition times between lighting stages in order

to allow more rapid variations in lighting levels to be achieved.

The Manual Operator Override from SCP control mode will remain active until the PMCS receives a

relinquish control command from the SCP.

6.7 Manual Operator Override from LCP Control Mode

The Manual Operator Override from LCP control mode will be provided by the LCS.

A local control panel will be provided, adjacent to the LCS at the TSB.

The Manual Operator Override from LCP control mode will remain active until relinquished at the

LCP.

6.8 Lamp Status Monitoring

The TPM&CS will continuously monitor the LCS for the status of the tunnel lamps, segmented into

tunnel zones. The following information will be displayed on the SCADA GUI and recorded by the

SCADA Servers for each tunnel zone:

One or more lamp/ballast failures present

One or more lamps in maintenance override

6.9 Emergency Standby Generator Load Shedding

The PMCS will inform the LCS that lighting stages in excess of stage 4 lighting cannot be exceeded

selected when the Emergency Standby Generator is active in the event of supply failure.

The PMCS will inform the LCS that lighting stages in excess of stage 2 lighting cannot be selected

when the Emergency Standby Generator has failed to become active on demand in the event of

supply failure, and lighting is therefore supported by UPS only.

7.0 Fire Safety Systems Control Scheme

7.1 Emergency/Electrical Distribution Panels Control Scheme

Emergency Panels (EP's) and Emergency Distribution Panels (EDP's) will be provided with limit

switches to allow the detection of the following conditions:

Fire extinguisher compartment door open/closed status

Fire extinguisher present/removed status

Emergency SOS telephone compartment door open/closed status

Fire hydrant compartment door open/closed status.

The PMCS will continuously monitor EP and EDP limit switch status this information will be displayed

on the SCADA GUI and recorded by the SCADA Servers.

Page 28: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 24 of 36

Rev. D02

7.2 Smoke Detection System

The Video Automatic Iincident Detection system for each tunnel bore will provide an array of

discrete signals to signal each of the detection events for each VAID zone. The following detection

events will be provided:

Slow vehicle

Stopped vehicle

Vehicle in wrong direction

Smoke detected

Object in carriageway (size to be determined)

Pedestrian/animal in carriageway

VAID detection events will be displayed on the SCADA GUI and recorded by the SCADA Servers.

The VAID systems for each tunnel bore will autonomously monitor and detect camera faults and will

signal these to the PMCS. VAID system camera faults will be displayed on the SCADA GUI and

recorded by the SCADA Servers.

The VAID smoke detection events for both tunnel bores will be displayed at each SCP.

The PMCS will allow the Operator to configure the VAID system for contra-flow working via the

SCADA GUI. The use of this function will be recorded by the SCADA Servers.

7.3 Smoke Control Panels

Four smoke control panels will be provided, situated at the portals, one per entrance and exit to

each tunnel bore.

SCP’s will provide the following control-related controls and indicators for each tunnel bore:

Ventilation fan status indication

Ventilation fan manual override control

Lighting system status indication

Lighting system manual override control

Firealarm status

SCP panel status

Manual broadcast of PA messages

SCP’s will provide a limit switch to sense the panel door open/close position. The PMCS will

continuously monitor the limit switches for status and this information will be displayed on the

SCADA GUI and recorded by the SCADA Servers.

Page 29: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 25 of 36

Rev. D02

8.0 Communications Systems Control Scheme

8.1 Control Scheme Overview

The PMCS will perform continuous monitoring of tunnel communications systems status and this

information will be displayed on the SCADA GUI and recorded by the SCADA Servers.

The status of the following communications systems will be monitored:

Emergency Roadside Telephones

Public Automatic Branch Exchange

Airwave and Emergency Services radio repeater system

Public Address system

The PMCS will provide supervisory control of the following systems:

Public Address system

8.2 Emergency Roadside Telephones Control Scheme

The open/closed status of each Emergency SOS telephone compartment door will be monitored.

8.3 Public Automatic Branch Exchange Control Scheme

The fault output of the PABX will be monitored for a failure status.

8.4 Airwave and Emergency Services Radio Repeater Control Scheme

The fault output of each component of the Radio Rebroadcast equipment will be monitored for a

failure status.

8.5 Public Address Control Scheme

The PMCS will allow the Operator to select from eight pre-defined announcements for broadcast

within each tunnel bore from either the SCADA GUI or the TMC.

The PMCS will demand the broadcast of the last pre-defined announcement selected from either the

SCADA GUI or the TMC, i.e. the SCADA GUI and the TMC will have equal priority in selecting pre-

defined announcements for broadcast.

The selected pre-defined announcement will continue to be broadcast until selected to stop at

either the SCADA GUI or the TMC, or until superseded by another pre-defined announcement.

The PMCS will monitor the Public Address system for confirmation that the commanded pre-defined

announcement is selected for broadcast by the Public Address system, and this information will be

displayed on the SCADA GUI and recorded by the SCADA Servers.

The PMCS will monitor the Public Address system form amplifier line load discrepancy status

information and this will be displayed on the SCADA GUI and recorded by the SCADA Servers.

Page 30: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 26 of 36

Rev. D02

9.0 Electrical Supply Systems Control Scheme

9.1 Control Scheme Overview

The PMCS will perform continuous monitoring of Electrical Supply systems status and this

information will be displayed on the SCADA GUI and recorded by the SCADA Servers.

The status of the following Electrical Supply systems will be monitored:

High Voltage (HV) system

Transformers

Low Voltage (LV) system

Emergency Standby Generators

UPS systems

Dual redundant power supplies (Equipment based)

9.2 MV System Control Scheme

Two HV supplies with appropriate redundancy will be supplied to meet the needs of the tunnel.

The PMCS will perform continuous monitoring of HV system status and this information will be

displayed on the SCADA GUI and recorded by the SCADA Servers. The following status information

will be monitored:

Bus status

ACB status

Description Type Direction Sense/Units Format

TSB VCB 'A' Incomer Status DIG I Failed/Normal +24vdc

TSB VCB 'B' Incomer Status DIG I Failed/Normal +24vdc

TSB VCB 'A' Bus Status DIG I Failed/Normal +24vdc

TSB VCB 'A' Bus Status DIG I Failed/Normal +24vdc

TSB VCB Bus Coupler Status DIG I Failed/Normal +24vdc

TSB VCB 'B' Bus Status DIG I Failed/Normal +24vdc

TSB VCB 'B' Bus Status DIG I Failed/Normal +24vdc

9.3 Transformer Control Scheme

Four transformers will be installed onthis project as follows:

The load capacity of new transformers for the tunnel and underpass will be determined based upon

the detailed design of lighting, ventilation, drainage, communications and tunnel control systems.

Transformers will be provided in a duty/duty/duty/stand-by arrangement with each duty

transformer capable of supplying 1/3 of the total tunnel load. In the event of a single transformer

failure the stand-by transformer will operate to ensure that the electrical power supply to the tunnel

Page 31: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 27 of 36

Rev. D02

continues with full functionality. The transformers will be located within separate enclosures at the

TSB. Low maintenance transformers will be utilised.

Each transformer will be fitted with at least two temperature-sensing devices fitted within pockets in

each phase winding to provide Over Temperature protection. The transformers will have Restricted

Earth Fault protection, as well as conventional Overcurrent, and Earth fault protection.

An estimate of the required loads based on the equipment being provided at part of the tunnel and

underpass design (excluding ITS loads) indicates the following capacities for the new equipment:

Transformer A - 1600 kVA (Duty)

Transformer B - 1600 kVA (Duty)

Transformer C - 1600 kVA (Duty)

Transformer D - 1600 kVA (Standby)

Description Type Direction Sense/Units Format

Tx1 'A' Operating Temp DIG I Normal/High +24vdc

Tx1 'A' Operating Temperature DIG I Normal/High +24vdc

Tx1 'A' Primary Feeder Brkr Control DIG I Normal/LocalO/R +24vdc

Tx1 'A' Primary feeder Brkr Control DIG I Normal/LocalO/R +24vdc

Tx1 'A' Primary Feeder Brkr Posn DIG I /Open +24vdc

Tx1 'A' Primary Feeder Brkr Posn DIG I /Closed +24vdc

Tx1 'A' Primary feeder Brkr Posn DIG I -/Open +24vdc

Tx1 'A' Primary feeder Brkr Posn DIG I -/Closed +24vdc

Tx1 'A' Primary Feeder Brkr Service DIG I Avail/OutServ +24vdc

Tx1 'A' Primary feeder Brkr Service DIG I Avail/OutServ +24vdc

Tx1 'A' Primary Feeder Brkr Status DIG I Normal/Tripped +24vdc

Tx 1'A' Primary feeder Brkr Status DIG I Normal/Tripped +24vdc

Tx1 'A' Secondary Power Status DIG I Failed/Normal +24vdc

Tx1 'A' Secondary Power Status DIG I Failed/Normal +24vdc

Tx2 'A' Operating Temp DIG I Normal/High +24vdc

Tx2 'A' Operating Temperature DIG I Normal/High +24vdc

Tx2 'A' Primary Feeder Brkr Control DIG I Normal/LocalO/R +24vdc

Tx2 'A' Primary feeder Brkr Control DIG I Normal/LocalO/R +24vdc

Tx2 'A' Primary Feeder Brkr Posn DIG I /Open +24vdc

Tx2 'A' Primary Feeder Brkr Posn DIG I /Closed +24vdc

Tx2 'A' Primary feeder Brkr Posn DIG I -/Open +24vdc

Tx2 'A' Primary feeder Brkr Posn DIG I -/Closed +24vdc

Tx2 'A' Primary Feeder Brkr Service DIG I Avail/OutServ +24vdc

Tx2 'A' Primary feeder Brkr Service DIG I Avail/OutServ +24vdc

Page 32: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 28 of 36

Rev. D02

Tx2 'A' Primary Feeder Brkr Status DIG I Normal/Tripped +24vdc

Tx2 'A' Primary feeder Brkr Status DIG I Normal/Tripped +24vdc

Tx2 'A' Secondary Power Status DIG I Failed/Normal +24vdc

Tx2 'A' Secondary Power Status DIG I Failed/Normal +24vdc

Tx3 'B' Operating Temp DIG I Normal/High +24vdc

Tx3 'B' Operating Temperature DIG I Normal/High +24vdc

Tx3 'B' Primary Feeder Brkr Control DIG I Normal/LocalO/R +24vdc

Tx3 'B' Primary feeder Brkr Control DIG I Normal/LocalO/R +24vdc

Tx3 'B' Primary Feeder Brkr Posn DIG I /Open +24vdc

Tx3 'B' Primary Feeder Brkr Posn DIG I /Closed +24vdc

Tx3 'B' Primary feeder Brkr Posn DIG I -/Open +24vdc

Tx3 'B' Primary feeder Brkr Posn DIG I -/Closed +24vdc

Tx3 'B' Primary Feeder Brkr Service DIG I Avail/OutServ +24vdc

Tx3 'B' Primary feeder Brkr Service DIG I Avail/OutServ +24vdc

Tx3 'B' Primary Feeder Brkr Status DIG I Normal/Tripped +24vdc

Tx3 'B' Primary feeder Brkr Status DIG I Normal/Tripped +24vdc

Tx3 'B' Secondary Power Status DIG I Failed/Normal +24vdc

Tx3 'B' Secondary Power Status DIG I Failed/Normal +24vdc

Tx4 'B' Operating Temp DIG I Normal/High +24vdc

Tx4 'B' Operating Temperature DIG I Normal/High +24vdc

Tx4 'B' Primary Feeder Brkr Control DIG I Normal/Local O/R

+24vdc

Tx4 'B' Primary feeder Brkr Control DIG I Normal/Local O/R

+24vdc

Tx4 'B' Primary Feeder Brkr Posn DIG I /Open +24vdc

Tx4 'B' Primary Feeder Brkr Posn DIG I /Closed +24vdc

Tx4 'B' Primary feeder Brkr Posn DIG I -/Open +24vdc

Tx4 'B' Primary feeder Brkr Posn DIG I -/Closed +24vdc

Tx4 'B' Primary Feeder Brkr Service DIG I Avail/OutServ +24vdc

Tx4 'B' Primary feeder Brkr Service DIG I Avail/OutServ +24vdc

Tx4 'B' Primary Feeder Brkr Status DIG I Normal/Tripped +24vdc

Tx4 'B' Primary feeder Brkr Status DIG I Normal/Tripped +24vdc

Tx4 'B' Secondary Power Status DIG I Failed/Normal +24vdc

Tx4 'B' Secondary Power Status DIG I Failed/Normal +24vdc

9.4 LV System Control Scheme

Description Type Direction Sense/Units Format

LV Bus Energised/De-energised DIG I De-Engsd/Engisdd

+24vdc

LV Closing Supply Battery Condtn DIG I Normal/Low +24vdc

Page 33: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 29 of 36

Rev. D02

LV Closing supply Battery Condtn DIG I Normal/Low +24vdc

LV Bus Energised/De-energised DIG I De-Engsd/Engisdd

+24vdc

LV Closing Supply Battery Condtn DIG I Normal/Low +24vdc

LV Closing supply Battery Condtn DIG I Normal/Low +24vdc

LV Closing Supply Charger Status DIG I Normal/Fault +24vdc

LV Closing supply charger Status DIG I Normal/Fault +24vdc

LV Switchroom Air Extract Status DIG I Normal/Failed +24vdc

LV Switchroom Air Supply Status DIG I Normal/Failed +24vdc

LV Tripping Supply Battery Condtn DIG I Normal/Low +24vdc

LV Tripping supply Battery Condtn DIG I Normal/Low +24vdc

LV Tripping Supply Charger Status DIG I Normal/Fault +24vdc

LV Tripping supply charger Status DIG I Normal/Fault +24vdc

Bus Section ACB Local Override DIG I Normal/LocalO/R +24vdc

Bus Section ACB Position DIG I -/Open +24vdc

Bus Section ACB Position DIG I -/Closed +24vdc

Bus Section ACB Service DIG I Avail/OutServ +24vdc

ACB 'A' Incomer 1 Control DIG I Normal/LocalO/R +24vdc

ACB 'A' Incomer 2 Control DIG I Normal/LocalO/R +24vdc

ACB 'A' Incomer 1 Energy Reading ANA I kWh 4-20mA

ACB 'A' Incomer 2 Energy Reading ANA I kWh 4-20mA

ACB 'A' Incomer 1 Position DIG I -/Open +24vdc

ACB 'A' Incomer 1 Position DIG I -/Closed +24vdc

ACB 'A' Incomer 2 Position DIG I -/Open +24vdc

ACB 'A' Incomer 2 Position DIG I -/Closed +24vdc

ACB 'A' Incomer 1 Service DIG I Avail/OutServ +24vdc

ACB 'A' Incomer 2 Service DIG I Avail/OutServ +24vdc

ACB 'A' Incomer 1 Trip Status DIG I Normal/Tripped +24vdc

ACB 'A' Incomer 2 Trip Status DIG I Normal/Tripped +24vdc

ACB 'B' Incomer 1 Control DIG I Normal/LocalO/R +24vdc

ACB 'B' Incomer 2 Control DIG I Normal/LocalO/R +24vdc

ACB 'B' Incomer 1 Energy Reading ANA I kWh 4-20mA

ACB 'B' Incomer 2 Energy Reading ANA I kWh 4-20mA

ACB 'B' Incomer 1 Position DIG I -/Open +24vdc

ACB 'B' Incomer 1 Position DIG I -/Closed +24vdc

ACB 'B' Incomer 2 Position DIG I -/Open +24vdc

ACB 'B' Incomer 2 Position DIG I -/Closed +24vdc

ACB 'B' Incomer 1 Service DIG I Avail/OutServ +24vdc

Page 34: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 30 of 36

Rev. D02

ACB 'B' Incomer 2 Service DIG I Avail/OutServ +24vdc

ACB 'B' Incomer 1 Trip Status DIG I Normal/Tripped +24vdc

ACB 'B' Incomer 2 Trip Status DIG I Normal/Tripped +24vdc

Bus 'A' Power Status DIG I Failed/Normal +24vdc

Bus 'B' Power Status DIG I Failed/Normal +24vdc

Bore A Restricted Earth Status DIG I - +24vdc

Bore A Supply Power Reading ANA I kWh 4-20mA

Bore A TxA 1 Power Monitoring ANA I kWh 4-20mA

Bore A TxA 2 Power Monitoring ANA I kWh 4-20mA

Bore A TxB 3 Power Monitoring ANA I kWh 4-20mA

Bore A TxB 4 Power Monitoring ANA I kWh 4-20mA

Bore A UPS A Power Monitoring ANA I kWh 4-20mA

Bore A UPS B Power Monitoring ANA I kWh 4-20mA

Bore B Restricted Earth Status DIG I - +24vdc

Bore B Supply Power Reading ANA I kWh 4-20mA

Bore B TxA 1 Power Monitoring ANA I kWh 4-20mA

Bore B TxA 2 Power Monitoring ANA I kWh 4-20mA

Bore B TxB 3 Power Monitoring ANA I kWh 4-20mA

Bore B TxB 4 Power Monitoring ANA I kWh 4-20mA

Bore B UPS A Power Monitoring ANA I kWh 4-20mA

Bore B UPS B Power Monitoring ANA I kWh 4-20mA

Bus 'A' Power Factor Corrector Stage 1 DIG I Off/On +24vdc

Bus 'A' Power Factor Corrector Stage 1 DIG I On/Off +24vdc

Bus 'A' Power Factor Corrector Stage 2 DIG I Off/On +24vdc

Bus 'A' Power Factor Corrector Stage 2 DIG I On/Off +24vdc

Bus 'A' Power Factor Corrector Stage 3 DIG I Off/On +24vdc

Bus 'A' Power Factor Corrector Stage 3 DIG I On/Off +24vdc

Bus 'A' Power Factor Corrector Stage 4 DIG I Off/On +24vdc

Bus 'A' Power Factor Corrector Stage 4 DIG I On/Off +24vdc

Bus 'A' Power Factor Corrector Stage 5 DIG I Off/On +24vdc

Bus 'A' Power Factor Corrector Stage 5 DIG I On/Off +24vdc

Bus 'A' Power Factor Corrector Stage 6 DIG I Off/On +24vdc

Bus 'A' Power Factor Corrector Stage 6 DIG I On/Off +24vdc

Bus 'A' Power Factor Corrector Status DIG I Normal/Fault +24vdc

Bus 'B' Power Factor Corrector Stage 1 DIG I Off/On +24vdc

Bus 'B' Power Factor Corrector Stage 1 DIG I On/Off +24vdc

Page 35: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 31 of 36

Rev. D02

Bus 'B' Power Factor Corrector Stage 2 DIG I Off/On +24vdc

Bus 'B' Power Factor Corrector Stage 2 DIG I On/Off +24vdc

Bus 'B' Power Factor Corrector Stage 3 DIG I Off/On +24vdc

Bus 'B' Power Factor Corrector Stage 3 DIG I On/Off +24vdc

Bus 'B' Power Factor Corrector Stage 4 DIG I Off/On +24vdc

Bus 'B' Power Factor Corrector Stage 4 DIG I On/Off +24vdc

Bus 'B' Power Factor Corrector Stage 5 DIG I Off/On +24vdc

Bus 'B' Power Factor Corrector Stage 5 DIG I On/Off +24vdc

Bus 'B' Power Factor Corrector Stage 6 DIG I Off/On +24vdc

Bus 'B' Power Factor Corrector Stage 6 DIG I On/Off +24vdc

Bus 'B' Power Factor Corrector Status DIG I Normal/Fault +24vdc

9.5 Emergency Standby Generator Control Scheme

Description Type Direction Sense/Units Format

Diesel A Alternator ACB Posn DIG I Open/Closed +24vdc

Diesel A Alternator Output Status DIG I Normal/Failed +24vdc

Diesel A Engine Fuel Tank Level DIG I Normal/Low +24vdc

Diesel A Engine Control DIG I Auto/Manual +24vdc

Diesel A Engine Fire Alarm DIG I Normal/Alarm +24vdc

Diesel A Engine Oil Pressure DIG I Normal/Low +24vdc

Diesel A Engine Speed DIG I Normal/High +24vdc

Diesel A Engine Start Status DIG I Normal/Failed +24vdc

Diesel A Engine Starter Battery DIG I Normal/Failed +24vdc

Diesel A Engine Temperature DIG I Normal/High +24vdc

Diesel A Engine Trip Status DIG I Healthy/Tripped +24vdc

DO Fuse Condition Diesel A DIG I Failed/Normal +24vdc

Diesel A Engine Fire Alarm fuel dump DIG O Normal/Dump Relay

Diesel A Engine Fire Alarm fuel top-up DIG O Normal/Fill Relay

Diesel B Alternator ACB Posn DIG I Open/Closed +24vdc

Diesel B Alternator Output Status DIG I Normal/Failed +24vdc

Diesel B Engine Fuel Tank Level DIG I Normal/Low +24vdc

Diesel B Engine Control DIG I Auto/Manual +24vdc

Diesel B Engine Fire Alarm DIG I Normal/Alarm +24vdc

Diesel B Engine Oil Pressure DIG I Normal/Low +24vdc

Diesel B Engine Speed DIG I Normal/High +24vdc

Diesel B Engine Start Status DIG I Normal/Failed +24vdc

Diesel B Engine Starter Battery DIG I Normal/Failed +24vdc

Diesel B Engine Temperature DIG I Normal/High +24vdc

Diesel B Engine Trip Status DIG I Healthy/Tripped +24vdc

Page 36: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 32 of 36

Rev. D02

DO Fuse Condition Diesel B DIG I Failed/Normal +24vdc

Diesel B Engine Fire Alarm fuel dump DIG O Normal/Dump Relay

Diesel A Engine Fire Alarm fuel top-up DIG O Normal/Fill Relay

9.6 UPS Systems Control Scheme

Description Type Direction Sense/Units Format

UPS 'A' Battery Voltage DIG I Normal/Low +24vdc

UPS 'A' Battery Voltage DIG I Normal/Low +24vdc

UPS 'A' General Condition DIG I Normal/Fault +24vdc

UPS 'A' General Condition DIG I Normal/Fault +24vdc

UPS 'A' Inverter Status DIG I Normal/Fault +24vdc

UPS 'A' Inverter Status DIG I Normal/Fault +24vdc

UPS 'A' Output Power Status DIG I Normal/Failed +24vdc

UPS 'A' Output Power Status DIG I Normal/Failed +24vdc

UPS 'A' Rectifier Status DIG I Normal/Fault +24vdc

UPS 'A' Rectifier Status DIG I Normal/Fault +24vdc

UPS 'A' System Bypass DIG I Normal/Bypassed +24vdc

UPS 'A' System Bypass DIG I Normal/Bypassed +24vdc

UPS 'B' Battery Voltage DIG I Normal/Low +24vdc

UPS 'B' Battery Voltage DIG I Normal/Low +24vdc

UPS 'B' General Condition DIG I Normal/Fault +24vdc

UPS 'B' General Condition DIG I Normal/Fault +24vdc

UPS 'B' Inverter Status DIG I Normal/Fault +24vdc

UPS 'B' Inverter Status DIG I Normal/Fault +24vdc

UPS 'B' Output Power Status DIG I Normal/Failed +24vdc

UPS 'B' Output Power Status DIG I Normal/Failed +24vdc

UPS 'B' Rectifier Status DIG I Normal/Fault +24vdc

UPS 'B' Rectifier Status DIG I Normal/Fault +24vdc

UPS 'B' System Bypass DIG I Normal/Bypassed +24vdc

UPS 'B' System Bypass DIG I Normal/Bypassed +24vdc

UPS A Incomer MCCB (A) Control DIG I Normal/LocalO/R +24vdc

UPS A incomer MCCB (B) Control DIG I Normal/LocalO/R +24vdc

UPS A Incomer MCCB (A) Posn DIG I -/Open +24vdc

UPS A Incomer MCCB (A) Posn DIG I -/Closed +24vdc

UPS A incomer MCCB (B) Posn DIG I -/Open +24vdc

UPS A incomer MCCB (B) Posn DIG I -/Closed +24vdc

UPS A Incomer MCCB (A) Service DIG I Avail/OutServ +24vdc

UPS A incomer MCCB (B) Service DIG I Avail/OutServ +24vdc

UPS A Incomer MCCB (A) Status DIG I Normal/Tripped +24vdc

Page 37: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 33 of 36

Rev. D02

UPS A incomer MCCB (B) Status DIG I Normal/Tripped +24vdc

UPS B Incomer MCCB (A) Control DIG I Normal/LocalO/R +24vdc

UPS B incomer MCCB (B) Control DIG I Normal/LocalO/R +24vdc

UPS B Incomer MCCB (A) Posn DIG I -/Open +24vdc

UPS B Incomer MCCB (A) Posn DIG I -/Closed +24vdc

UPS B incomer MCCB (B) Posn DIG I -/Open +24vdc

UPS B incomer MCCB (B) Posn DIG I -/Closed +24vdc

UPS B Incomer MCCB (A) Service DIG I Avail/OutServ +24vdc

UPS B incomer MCCB (B) Service DIG I Avail/OutServ +24vdc

UPS B Incomer MCCB (A) Status DIG I Normal/Tripped +24vdc

UPS B incomer MCCB (B) Status DIG I Normal/Tripped +24vdc

TSB-UPS A LV Feeder A Brkr Control O/R DIG I Normal/LocalO/R +24vdc

TSB-UPS A LV Feeder A Brkr Posn DIG I -/Open +24vdc

TSB-UPS A LV Feeder A Brkr Posn DIG I -/Closed +24vdc

TSB-UPS A LV Feeder A Brkr Service DIG I Avail/OutServ +24vdc

TSB-UPS A LV Feeder A Brkr Trip Status DIG I Normal/Tripped +24vdc

TSB-UPS A LV Feeder A Energy Reading ANA I kWh 4-20mA

TSB-UPS A LV Feeder B Brkr Control O/R DIG I Normal/LocalO/R +24vdc

TSB-UPS A LV Feeder B Brkr Posn DIG I -/Open +24vdc

TSB-UPS A LV Feeder B Brkr Posn DIG I -/Closed +24vdc

TSB-UPS A LV Feeder B Brkr Service DIG I Avail/OutServ +24vdc

TSB-UPS A LV Feeder B Brkr Trip Status DIG I Normal/Tripped +24vdc

TSB-UPS A LV Feeder B Energy Reading ANA I kWh 4-20mA

TSB-UPS B LV Feeder A Brkr Control O/R DIG I Normal/LocalO/R +24vdc

TSB-UPS B LV Feeder A Brkr Posn DIG I -/Open +24vdc

TSB-UPS B LV Feeder A Brkr Posn DIG I -/Closed +24vdc

TSB-UPS B LV Feeder A Brkr Service DIG I Avail/OutServ +24vdc

TSB-UPS B LV Feeder A Brkr Trip Status DIG I Normal/Tripped +24vdc

TSB-UPS B LV Feeder A Energy Reading ANA I kWh 4-20mA

TSB-UPS B LV Feeder B Brkr Control O/R DIG I Normal/LocalO/R +24vdc

TSB-UPS B LV Feeder B Brkr Posn DIG I -/Open +24vdc

TSB-UPS B LV Feeder B Brkr Posn DIG I -/Closed +24vdc

TSB-UPS B LV Feeder B Brkr Service DIG I Avail/OutServ +24vdc

TSB-UPS B LV Feeder B Brkr Trip Status DIG I Normal/Tripped +24vdc

TSB-UPS B LV Feeder B Energy Reading ANA I kWh 4-20mA

Page 38: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 34 of 36

Rev. D02

10.0 Miscellaneous Systems Control Scheme

10.1 Control Scheme Overview

The PMCS will perform continuous monitoring of miscellaneous tunnel systems status and this

information will be displayed on the SCADA GUI and recorded by the SCADA Servers.

The status of the following miscellaneous systems will be monitored:

TSB intruder alarm

o Setting status

o Alarm status

11.0 Interfaces

11.1 TMC Interface

The interface with the TMC is defined in the document “Tunnel TMC/TSS – SCADA/PMCS Control

Interface” (document reference EXW-P007-0201-MC-KEO-RP-00210).

11.2 Physical Locations of PMCS Plant Interfaces

The PMCS will provide plant interfaces, i.e. PLCs or RIO units, at following locations:

Tunnel Services Building

SCP 1 to 4

EDPs N/B 1 to 8 and S/B 1 to 8.

Plant signals from plant marshalled at EPs will be cabling to the nearest [via containment route]

adjacent point-of-presence of a PMCS PLC/RIO unit. This will be an adjacent EDP or one of the

Ventilation Building switch rooms.

11.3 Plant Interfaces

The PMCS will interface to plant at the following locations:

Plant Location

MV/LV panels TSB

UPSs TSB

Transformers and Emergency Standby Generators TSB

Tunnel Ventilation System Through the EP, EDPs

Air Quality Monitoring System (Tunnel deployed Equipment) Through the tunnel panels

Tunnel Cross Passage Doors/Inter-bore Doors Through the tunnel panels

Tunnel Field equipment EP, EDPs, SCPs and Pump Plant room

Tunnel Lighting system including Photometers and Through the Lighting Control System

Page 39: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 35 of 36

Rev. D02

photocells (LCS) in the TSB

Video Automatic Incident Detection System (VAID) TSB

N/B Public Address system (PA) TSB

S/B Public Address System (PA) TSB

Linear Heat Detection (x2) LHD DTS TSB

Leaky Feeder System (x2) Equipment status TSB

CCTV System Equipment status TSB

Traffic Management System (TMS) Equipment status TSB

Network Communication system devices equipment status monitoring.

Within the TSB and distributed throughout the tunnel and plant rooms.

TSB Building Services Control System (BMS) and other building specific system requiring interface with the PMCS/SCADA

TSB

Weather stations (x2) including environmental monitoring Through the tunnel panels

Tunnel Flood Detection System (x1) Through the tunnel panels

11.4 Ethernet TCP/IP Infrastructure

Separate N/B and S/B networks will be formed initially to allow separate refurbishment works for

both tunnel bores. These separate networks will then be linked to form the dual PMCS network.

The N/B and S/B networks will each be formed using a single mode fibre optic (SMFO) ring network.

Ethernet network switches will be located at points where it is necessary for Internet Protocol

enabled equipment to access the network.

Network switches will support the physical single mode fibre optic (SMFO) ring topology, giving each

switch two possible communication paths to any other switch on the network.

Network switches will provide copper CAT5e ports for connection equipment via patch leads.

The N/B bore network switches will be provided at the following locations:

SCP 1 and 2

EDPs 1 to 8

TSB

Sump plant room

The W/B bore network switches will be provided at the following locations:

SCP 3 and 4

EDP 1 to 8

Page 40: EXW-P007-0201-MC-KEO-RP-00209-scada pmcs control-R6.pdf

Tunnel SCADA PMCS Control Concept

Specification

Doc. No. EXW-P007-0000-MC-KEO-RP-00209 Page 36 of 36

Rev. D02

TSB

The provision of switches at each location, other than EDP’s, will be dual redundant so that access to

the network at each location can be maintained in the event of a switch failing.

Network switches will provide the following configurable services as a minimum:

Packet prioritisation for data whose quality of content requires it to be continuously

streamed (such as audio and video).

Efficient routing of unicast and multicast packets between relevant equipment only. Global

broadcasts should be limited only to information that is required by all connected systems.