external alarm box n installtion
TRANSCRIPT
-
8/11/2019 External Alarm Box n Installtion
1/34
Alcatel-Lucent GSM
External Alarm Box Installation
and Commissioning Manual
BSC & TC Document
Installation & Dismantling Manual
3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
2/34
Status RELEASED
Short title INS
All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel.
BLANK PAGE BREAK
2 / 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
3/34
Contents
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
1 Overview . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
1.1 Presentation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.1 Hardware Description . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 81.1.2 Cases . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.3 Options . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.4 Initial State. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.5 Final State . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.6 Restrictions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 91.1.7 Grouped Task Sequence . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
1.2 Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.2.1 Prerequisites. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 111.2.2 Site-Specific Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
1.3 Scheduling . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.4 Resources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12
1.4.1 Tools . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.4.2 Supplies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 121.4.3 Applicable Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
2 External Alarm Box Installation and Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.1 Before Going on Site . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162.2 Before You Start (On Arrival at the Site) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.2.1 Checks . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 162.2.2 Required Knowledge . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
2.3 EAB Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.3.1 Wall Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.3.2 Fix the EAB to the Wall . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 172.3.3 Connect Cables to EAB . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 18
2.4 EAB Commissioning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.4.1 Check the Power Supply and Power Up . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 212.4.2 Set EAB Parameters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 222.4.3 Declare the EAB at OMC-R . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
2.5 Finish Installation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
3BK 17422 3101 RJZZA Ed.08 3 / 34
-
8/11/2019 External Alarm Box n Installtion
4/34
Contents
4 / 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
5/34
Preface
Preface
Purpose This document describes how to install on site an External Alarm Box for A9130BSC/MFS Evolution of ALCATEL-LUCENT BSS.
Whats New In Edition 08Description improvement in the following sections:
Configure OMC-R IP Address on EAB(Section 2.4.2.10)
Connect the EAB to the A9130 BSC/MFS Evolution(Section 2.4.2.12)
Test the Connectivity(Section 2.4.2.14).
In Edition 07Description improvement in:
Prerequisites (Section 1.2.1)
Connect the EAB to the A9130 BSC/MFS Evolution(Section 2.4.2.12).
In Edition 06Description improvement in:
Installation Kits(Section 1.4.1.1)
Configure IP Addresses on EAB(Section 2.4.2.5).
In Edition 05Description update in:
Configure IP Addresses on EAB(Section 2.4.2.5)
Finish Installation (Section 2.5).The following sections were added:
Check if Wago BootP Software is Installed(Section 2.4.2.1)
Download Wago BootP Software(Section 2.4.2.2)
Modify EAB IP Address(Section 2.4.2.11).
3BK 17422 3101 RJZZA Ed.08 5 / 34
http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?- -
8/11/2019 External Alarm Box n Installtion
6/34
Preface
In Edition 04Description update in:
Connect the External Alarm Cables(Section 2.3.3.3)
Site-Specific Information (Section 1.2.2)
Configure Gateway Address on EAB(Section 2.4.2.8)
Restriction removal inDeclare the EAB at OMC-R (Section 2.4.3).
In Edition 03
Restriction introduction inDeclare the EAB at OMC-R (Section 2.4.3).
In Edition 02Description update in:
Configure OMC-R IP Address on EAB(Section 2.4.2.10)
Connect the EAB to the A9130 BSC/MFS Evolution(Section 2.4.2.12)
Test the Connectivity(Section 2.4.2.14).
SectionDeclare the EAB at OMC-R (Section 2.4.3) was added.
In Edition 01
First official release of document.
Audience This document is intended for:
Installers
Site administrators
Supervisors
Project managers
Field service technicians
Occasional users.
Assumed Knowledge You must have a basic understanding of the following:
Basic knowledge of Alcatel-Lucent BSS equipment
Experience of electrical mounting and cabling.
6 / 34 3BK 17422 3101 RJZZA Ed.08
http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?- -
8/11/2019 External Alarm Box n Installtion
7/34
1 Overview
1 Overview
This Overview gives information needed by project managers and foremen, forpresentation to the customer and for site planning.
3BK 17422 3101 RJZZA Ed.08 7 / 34
-
8/11/2019 External Alarm Box n Installtion
8/34
1 Overview
1.1 Presentation
1.1.1 Hardware Description
The External Alarm Box provides external alarm inputs adaptable to the
individual requirements. Typically can be used for main power supply, rectifiers,batteries, air conditioning, intrusion.
1.1.1.1 Module Configuration
The External Alarm Box includes:
A Programmable Field Bus controller Ethernet TCP/IP 10/100 Mbits/s
for Input/Output modules.
Six input modules with four channels for signal control from digital field
devices numbered from left to right side.
One module for bus termination of internal data circuit and correct data flow.
One power supply adaptor
Fused disconnect terminal block with LED.
C
D
A
B
2 4 V 0 V
+ +
ETHERNET
LINK
MS
NS
I/ O
USR
TxD/RxD
C
D
A
B
13 14
+ +
15 16
WAGO
750 432
+ +
01
C
D
A
B
13 14
+ +
15 16
WAGO
750 432
+ +
02
C
D
A
B
13 14
+ +
15 16
WAGO
750 432
+ +
03
C
D
A
B
13 14
+ +
15 16
WAGO
750 432
+ +
04
C
D
A
B
13 14
+ +
15 16
WAGO
750 432
+ +
05
C
D
A
B
13 14
+ +
15 16
WAGO
750 432
+ +
06
C
D
A
B
WAGO
750 600
EntreSortie
+ 0
+ + +
+
2
Figure 1: External Alarm Box (Front View)
8 / 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
9/34
1 Overview
1.1.1.2 Weight and Dimensions
The following tables gives the dimensions and weight of the EAB.
Width
Depth
Height
280 mm
180 mm
380 mm
Weight 2.5 kg
1.1.2 Cases
None.
1.1.3 Options
None.
1.1.4 Initial State
The External Alarm Box and installation kit are packed and delivered on site.
1.1.5 Final State
After finishing the installation and commissioning the EAB is ready to bedeclared ant the OMC-R.
The EAB will be ready for use after:
Declaration at OMC-R side
Assignment of an OMC-R device type.
1.1.6 Restrictions
None.
3BK 17422 3101 RJZZA Ed.08 9 / 34
-
8/11/2019 External Alarm Box n Installtion
10/34
1 Overview
1.1.7 Grouped Task Sequence
EAB Installation
Before You Start
Before Going On Site
EAB Commissioning
Finish Installation
10/ 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
11/34
1 Overview
1.2 Preparation
1.2.1 Prerequisites
The following prerequisites apply:
The site conforms to the "Safety rules" of General Wiring Handbook
The site is ready to receive the EAB, according to SPP 59
The A9130 BSC/MFS Evolution is already operational and able to route the
EAB messages towards the OMC-R.
1.2.2 Site-Specific Information
Site: The following specific information (input) is needed to complete thescenario:
Grounding plate location
Power supply cabinet location
Fuse breakers location into power box
2 wires or 3 wire power system (if applicable)
EAB precise location
Number of alarms to be connected
Wago Protocol Type
Wago Reverse
Alarm is active when the electrical status is open loop.Wago DirectAlarm is active when the electrical status is close loop.
Alarm cabling diagram
EAB IP Address, Subnet Mask and Gateway IP Address
OMC-R IP Address
OMC-R username and password for secure connection.
3BK 17422 3101 RJZZA Ed.08 11/ 34
-
8/11/2019 External Alarm Box n Installtion
12/34
1 Overview
1.3 Scheduling
Task Duration (mn)
1st person
Preliminary checks 30
EAB installation 30
EAB commissioning 20
Finishing installation 10
Total Time: 1h 30min
1.4 Resources
1.4.1 Tools
1.4.1.1 Installation Kits
The following table describe the necessary installation kits.
Installation kits Mnemo Reference Qty
External Alarm Box equipped JBXEAB 1AB 24048 0001 1
Ethernet cable ALETHC 3BW01805JA 1
1.4.1.2 Software Tools
None.
1.4.1.3 Hardware Tools
The following table is used to check, on base, the availability of the necessarytools.
See Tools catalogue for content checking.
Kit name Reference Calibration
Basic kit tools OUT 001 no
1.4.2 Supplies
None.
12/ 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
13/34
1 Overview
1.4.3 Applicable Documents
The following table is used to check, at base, the availability of the necessarydocuments.
Document tittle Reference
Applicable Notification List(ITL-PRO) 3DF 00462 0004 AAAGA
Applicable Operation Instructions(IO) 3DF 00300 0004 UAZZA
General Wiring Handbook 3BK 17160 0001 RJZZA
Tools catalogue for Field Activity 3BK 20458 0001 RJZZA
Site premises inspection form (CEL) 8BL 00704 0015 DRBRA
Installation Manual Generic CCL 3BK 17200 0002 QZZZA
Specification for site preparation (SPP 59) 8BL 00704 0076 DRZZA
BSS Site Premises Inspection, Post Handover 8BL 00704 0016 DRBRA
BSS Configuration HandbookB9 Release 3BK 20901 AAAA PCZZA
BSS Configuration HandbookB10 Release 3BK 21201 AAAA PCZZA
3BK 17422 3101 RJZZA Ed.08 13/ 34
-
8/11/2019 External Alarm Box n Installtion
14/34
1 Overview
14/ 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
15/34
2 External Alarm Box Installation and Commissioning
2 External Alarm Box Installation and Commissioning
This Scenario presents all checks needed before beginning the scenario, andall detailed tasks to be performed on site.
3BK 17422 3101 RJZZA Ed.08 15/ 34
-
8/11/2019 External Alarm Box n Installtion
16/34
2 External Alarm Box Installation and Commissioning
2.1 Before Going on Site
Before going on site you must check that the following information and toolsare available:
AllPrerequisites (Section 1.2.1) are fulfilled
The customer has been informed of the:
Date and time
Site name and address
Purpose of the operation.
Personnel are available and ready for operation (refer to Scheduling
(Section 1.3)
Site-Specific Information (Section 1.2.2) is available and ready for operation
Hardware Tools(Section 1.4.1.3)are available and ready for operation
Installation Kits(Section 1.4.1.1)are available and ready for operation
Applicable Documents (Section 1.4.3)are available and ready for operation.
2.2 Before You Start (On Arrival at the Site)
2.2.1 Checks
Before you start, perform the following operations:
Check that all Prerequisites (Section 1.2.1)are fulfilled
Check applicable notifications and operating instructions (refer to the
Applicable Notifications Listand Applicable Operation Instructions List)
Check the availability of all necessary tools and supplies.
Refer to BSS Site Premises Inspection, Post Hand over and complete the
Premises Inspection form (CEL).
Check that the safety precautions have been taken in accordance with the
safety instructions described in theBSS Methods Handbook.
Check whichCases (Section 1.1.2) or Options (Section 1.1.3) apply
Complete the header field of the CCL. The CCL is completed as each
instruction is carried out.
2.2.2 Required Knowledge
You must be familiar with the following:
The safety rules and precautions given in the BSS Methods Handbook.
How to document faults and anomalies as described in the BSS Methods
Handbook.
16/ 34 3BK 17422 3101 RJZZA Ed.08
http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?- -
8/11/2019 External Alarm Box n Installtion
17/34
2 External Alarm Box Installation and Commissioning
2.3 EAB Installation
2.3.1 Wall Preparation
To prepare the wall:
1. Mount four mural foot pieces on the back side of EAB box.
2. Mark the drilling positions on the wall.
Note: Depending on site configuration following position can be used
20
20
254
20
20
20
20
3. Drill the holes.
2.3.2 Fix the EAB to the Wall
To fix the EAB:
1. Insert the expanding plugs in the holes.
2. Place the EAB box in position and fix it to the wall with provided screws.
3BK 17422 3101 RJZZA Ed.08 17/ 34
-
8/11/2019 External Alarm Box n Installtion
18/34
2 External Alarm Box Installation and Commissioning
2.3.3 Connect Cables to EAB
2.3.3.1 Connect the Ground and Power Cables
To connect the ground and power cables:
1. Connect the ground cable to the site grounding plate
2. Connect the ground cable to the ground terminal block
3. At site power distribution panel switch OFF the EAB power breaker
4. Connect the power cables to the power supply module as follows:
Connect the 0V DC to the left position on the EAB power supply
Connect the -48V DC to the right position on the EAB power supply as
shown in the figure below.
+ 0
+ + +
48 VDC0 VDC GND
Figure 2: GND and Power Cables Connection
5. Connect the power cables to the site distribution panel.
18/ 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
19/34
2 External Alarm Box Installation and Commissioning
2.3.3.2 Connect the Ethernet Cable
Connect the Ethernet cable between the PC and the EAB controller module:
1. Identify the Ethernet cable connecting position
Figure 3: Ethernet Connector Location
2. Connect the Ethernet cable to the controller module.
3. Connect the Ethernet cable to the PC.
3BK 17422 3101 RJZZA Ed.08 19/ 34
-
8/11/2019 External Alarm Box n Installtion
20/34
2 External Alarm Box Installation and Commissioning
2.3.3.3 Connect the External Alarm Cables
If WAGO REVERSE protocol (normal close loop) is used you mustconnect provided straps for all unused alarm ports.
To connect the external alarm cables to the alarm input modules:
1. Insert the screwdriver into the opening above the connection
2. Insert the wire into the opening
Figure 4: Wire Connection Principle
3. Remove the screwdriver.
After removing the operating tool, the conductor is safely clamped.
4. Perform the above steps for all alarms to be connected.
5. If WAGO REVERSE protocol (normal close loop) is used, connect providedstraps for all unused alarm ports.
The following table gives the alarm number allocation for all input modulesand for all ports on each module.
Input Module Input Number Alarm Number
13 & + 1
14 & + 2
15 & + 3
1
16 & + 4
13 & + 5
14 & + 6
15 & + 7
2
16 & + 8
20/ 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
21/34
2 External Alarm Box Installation and Commissioning
Input Module Input Number Alarm Number
13 & + 9
14 & + 10
15 & + 11
3
16 & + 12
13 & + 13
14 & + 14
15 & + 15
4
16 & + 16
13 & + 17
14 & + 18
15 & + 19
5
16 & + 20
13 & + 21
14 & + 22
15 & + 23
6
16 & + 24
2.4 EAB Commissioning
2.4.1 Check the Power Supply and Power Up
To check the power supply and powering up:
1. Using a multimeter check at site power supply the voltage and polarity.
2. Switch ON the power breaker for the EAB.
LED on power supply module is switched ON.
3BK 17422 3101 RJZZA Ed.08 21/ 34
-
8/11/2019 External Alarm Box n Installtion
22/34
2 External Alarm Box Installation and Commissioning
2.4.2 Set EAB Parameters
If on the EAB Programmable Field Controller you find a label with the defaultgeneric IP Address of the device continue with section Configure Local PC(Section 2.4.2.6).
The default generic IP address of EAB is 192.192.4.1 and the SubnetMask is 255.255.255.248.If on the EAB you do not find the label with default generic IP address continuewith next sectionCheck if Wago BootP Software is Installed(Section 2.4.2.1)
2.4.2.1 Check if Wago BootP Software is Installed
To check if Wago BootP Software is installed:
1. From the Windows desktop click on [ Start ] then click [ Control Panel ] .
The "Control Panel" window opens.
2. Double-click on the Add or Remove Programs.
The "Add or Remove Programs" window opens.
3. If the WAGO BootP Server software is on the "Currently installed programs:"list continue with sectionDisable Windows XP Firewall(Section 2.4.2.4).
4. If the WAGO BootP Server software is not on the "Currently installedprograms:" list continue with sectionDownload Wago BootP Software(Section 2.4.2.2).
2.4.2.2 Download Wago BootP Software
To download Wago BootP Software:
1. Launch Mozilla Internet Browser. In the address field typehttp://www.wago.comthen press [ Enter ].
The "Wago Innovative Connections " window opens.
2. Click on [ WAGO Global Site ] link then select from menu Service ->Downloadsin the"WAGO Kontakttechnik GmbH & Co. KG" window.
3. Click on ELECTRONICC
The new frame opens when you are asked to agree with Terms andConditions.
4. Click on [ I agree ] to accept the Terms and Conditions agreement.
5. In the "ELECTRONICC Downloads" table chosse WAGO BootPServersoftware to download.
6. Save to disk BootPSer.zipin thedirectory.7. Unzip BootPSer.zip. in the :\WagoSoftwarefolder.
22/ 34 3BK 17422 3101 RJZZA Ed.08
Edited by Foxit ReaderCopyright(C) by Foxit Software Company,2005-2008For Evaluation Only.
http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?- -
8/11/2019 External Alarm Box n Installtion
23/34
2 External Alarm Box Installation and Commissioning
2.4.2.3 Install the Wago BootP Software
You must be logged on the PC as an administrator or a member of theAdministrators group in order to install the software.
To install Wago BootP Software:
1. Navigate in\WagoSoftwaredirectory.
2. Launch Setup.exe.
3. In the "Welcome" ("Willkommen") window click on [ Next ] ([ Weiter ]).
4. Enter the folder where WAGO BootP Server software will be installedc:\Program Files\WAGO Software\WAGO BootP Server\then click on[ Next ] ([ Weiter ]).
5. Choose Start Menu FolderWAGO Software\WAGO BootP Server thenclick on [ Next ] ([ Weiter ]).
6. Click on [ Finish ] ([ Beenden ]).
2.4.2.4 Disable Windows XP Firewall
During EAB installation the Windows XP firewall must be disable.If the firewall was enabled when you started the operation, be careful to set thefirewall back to enable at the end of the operation.You must to be logged on PC as an administrator or a member of Administratorsgroup in order to modify the firewall status.The following procedure must be performed only if the PC used for localterminal, is running Windows XP as operating system.
To disable XP Firewall
1. From the Windows desktop click on [ Start ] then click [ Run ]cmd
A DOS window opens.
2. In the DOS window enter the following commandnet stop SharedAccess
If the Firewall was started the following message is displayedThe Windows Firewall/Internet Connection Sharing
service was stopped successfully.
If the Firewall was not started the following message is displayed
The Windows Firewall/Internet Connection Sharing
service is not started
3. Close DOS window.
If on the PC there are other applications used for port scanning, virus protectionor spam blocking, disable these applications during the EAB installation.
3BK 17422 3101 RJZZA Ed.08 23/ 34
-
8/11/2019 External Alarm Box n Installtion
24/34
2 External Alarm Box Installation and Commissioning
2.4.2.5 Configure IP Addresses on EAB
1. From the Windows desktop, follow the menu path:
Start -> Programs -> Wago Software -> Wago BootP Server-> WagoBootP Server
2. In "Wago BootP Server" window click on [ Edit Bootptab ] to configure
BootP server.
Any line that begins with a # symbol is a comment, and will not be processed.
3. Edit the configuration parameters:
To configure BootP changes only the line in bold
The contents of this file looks like this:# bootptab.txt: database for bootp server#
# Blank lines and lines beginning with # are ignored.#.................................................................................................# Example of entry with no gatewayKeinProxy:ht=1:ha=0030DE000002:ip=10.1.254.202:# Example of entry with gateway# The gateway address must be inserted in hexadecimal# after the T3 parameterhamburg:ht=1:ha=0030DE000003:ip=10.1.254.203:T3=0A.01.FE.01:
In the line KeinProxy (Node Name) you need to modify:
On the left side of EAB Programmable Field Controller you find theunique MAC ID of the device.
Hardware address ha=0030DE000003 with the provided MAC
Address
Host IP address ip=10.1.254.202 with the default generic IP
Address: ip=192.192.4.1
At the end of line KeinProxy (Node Name) you need to add:
Default generic Subnet Mask IP Address: sm=255.255.255.248
: at the end of the line.
At the beginning of the line:
hamburg:ht=1:ha=0030DE000003:ip=10.1.254.203:T3=0A.01.FE.01:
type #
4. Click on File -> Saveand then close the file.
5. Switch OFF the power breaker for the EAB and wait for a couple of seconds.
6. Switch ON the power breaker for the EAB.
24/ 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
25/34
2 External Alarm Box Installation and Commissioning
To assign EAB IP address:
7. In "Wago BootP Server" window click on [ Start ] to configure BootP server.
If a messages sequence appears as shown in the figure below it means thatthe EAB Programmable Field Controller is configured with the provided IPaddress.
8. Click on [ Stop ] then click on [ Exit ]
If the firewall was enabled when you started the operation, be careful toset the firewall back to enable.
3BK 17422 3101 RJZZA Ed.08 25/ 34
-
8/11/2019 External Alarm Box n Installtion
26/34
2 External Alarm Box Installation and Commissioning
2.4.2.6 Configure Local PC
On the local PC you must set the network interface IP address to be in thesame network address range as the default generic IP address for EAB.Be careful to set the PC IP Address and subnetmask back at the end ofthe commissioning.
To set the network interface IP address:
1. If not already done, connect the PC to the EAB Ethernet Interface usingthe Ethernet cable.
The Ethernet Interface is located on EAB Programmable Field Bus controller.
2. Start the PC and login as local Administrator.
3. Select the following menu path:
Start -> Setting -> Network Connections
The "Network Connections" window is displayed.
4. Select Local Area Connection.
The "Local Area Connection" window is displayed.
5. Right-click on [ Properties ] and select Internet Protocol (TCP/IP) in the list.
The "Properties" window is open.
6. Click on [ Properties ].
The "Properties" window is displayed.
7. Select Use the following IP address frame.
8. Type the PC IP address in the IP address field.
The PC IP Address is 192.192.4.2
9. Type the mask in the Subnetmask fieldThe Subnetmask is 255.255.255.248
10. Click on [ OK ] in the "Internet Protocol (TCP/IP)" window.
11. Click on [ OK ] in the "Local Area Connection" window.
2.4.2.7 Set Date and Time on EAB
To set date and time on EAB:
1. Launch Mozilla Internet Browser. In the address field type the default genericEAB IP address then press [ Enter ].
A "Status information" window is displayed.
2. In the left frame of this window click on Clock
3. A "Prompt" window is opened. Type:
User name
admin
and Passwordwago
Click on [ OK ]
4. The new frame Configuration of the internal clock is displayed
5. To set time on EAB:
In the field Time on device type current time inhh:mm:ssformat.
6. Click on [ SUBMIT ] to save new time on EAB.
26/ 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
27/34
2 External Alarm Box Installation and Commissioning
7. To set date on EAB:
In the field Date on device type date in dd.mm.yyyyformat
8. Click on [ SUBMIT ] to save new date on EAB.
2.4.2.8 Configure Gateway Address on EAB
To configure gateway address on EAB:
1. Launch Mozilla Internet Browser. In the address field type the default genericEAB IP address then press [ Enter ].
A "Status information" window is displayed.
2. In the left frame of this window click on TCP/IP
If a password dialog box is open, you must enter the user name and thepassword.
3. The new frame TCP/IP configuration is displayed.
4. In the field Gateway type the provided gateway.
In case of BSC, active OMCP IP address
In case of MFS, Router Interface IP address.
5. Click on [ SUBMIT ] to save new gateway on EAB.
2.4.2.9 Check EAB Port Configuration
To check port configuration on EAB:
1. Launch Mozilla Internet Browser. In the address field type the default genericEAB IP address then press [ Enter ].
A Status information is displayed2. In the left frame of this window click on Port
If a password dialog box is open, you must enter the user name and thepassword.
3. The new frame Port configuration is displayed.
4. Enable SNMP protocol corresponding to ports 161 and 162, if the case.
5. Disable BootP protocol corresponding to port 68, if the case.
6. Click on [ SUBMIT ] to save changes on EAB.
3BK 17422 3101 RJZZA Ed.08 27/ 34
-
8/11/2019 External Alarm Box n Installtion
28/34
2 External Alarm Box Installation and Commissioning
2.4.2.10 Configure OMC-R IP Address on EAB
To configure the OMC-R IP address on EAB:
1. Launch Mozilla Internet Browser. In the address field type the default genericEAB IP address then press [ Enter ].
The "Status information" window is displayed as below
2. In the left frame of this window click on Snmp . A "Prompt" window isopened. Type:
User name
admin
and Passwordwago
Click on [ OK ]
28/ 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
29/34
2 External Alarm Box Installation and Commissioning
3. The new frame SNMP Configuration is displayed.
The displayed frame: Current SNMP Configuration is similar with thefigure below.
4. To assign OMC-R IP address where EAB is sending SNMP traps:
In the field First SNMP Agent type the first OMC-R IP address.
If is the case, in the field Second SNMP Agent type the second OMC-R
IP address, otherwise leave it empty.
In case of OMC-R X Large or XX Large configuration, enter the IP address ofthe Master Station.
5. Click on [ SUBMIT ] and then click on [ RESET ] to save the currentsettings to the EAB.
2.4.2.11 Modify EAB IP Address
To modify IP address on EAB:
1. Launch Mozilla Internet Browser. In the address field type the default genericEAB IP address then press [ Enter ].
A "Status information" window is displayed.
2. In the left frame of this window click on TCP/IP
If a password dialog box is open, you must enter the user name and the
password.
3. The new frame TCP/IP configuration is displayed.
4. In the field IP-Address type the provided EAB IP address.
5. In the fieldSubnet Mask type the provided subnet mask address.
6. In the field Gateway type the provided gateway.
In case of BSC, active OMCP IP address
In case of MFS, Router Interface IP address.
7. Click on [ SUBMIT ] to save new values on EAB.
3BK 17422 3101 RJZZA Ed.08 29/ 34
-
8/11/2019 External Alarm Box n Installtion
30/34
2 External Alarm Box Installation and Commissioning
8. Switch OFF the power breaker for the EAB and wait for a couple of seconds.
9. Switch ON the power breaker for the EAB.
The EAB Programmable Field Controller is configured with the provided IPaddress.
2.4.2.12 Connect the EAB to the A9130 BSC/MFS Evolution
To connect the EAB to the A9130 BSC/MFS Evolution:
1. Identify the Ethernet cable used for EAB connection
2. Connect the Ethernet cable:
In case of BSC, from the EAB to the JAXSSW1 port ETH 5 in
corresponding ATCA shelf as shown in the Figure 5
OMCR
BSC
Evolution
EAB
IP
Network
IP
Cisco
Router*
ETH 5SSW1
BSC Site
Figure 5: EAB Connection at BSC Site
* The Cisco Router is localized at BSC site or in case of MLPPPconnection at TC/MSC site.
In case of MFS, from the EAB to the Router/Switchs corresponding
ETH port as shown in the Figure 6
OMCRMFS
Evolution
EAB
IP
Network
IP
Cisco
Router
MFS Site
Figure 6: EAB Connection at MFS Site
30/ 34 3BK 17422 3101 RJZZA Ed.08
-
8/11/2019 External Alarm Box n Installtion
31/34
2 External Alarm Box Installation and Commissioning
2.4.2.13 Check EAB LED Status
The following table describes the status of the LEDs, when EAB is operatingcorrectly.
LED Status
Link Green
MS (Module Status) Green
NS (Node Status) Green or flashing green
TxD/RxD Flashing green
I/O Green
Table 1: Normal Operation Status
2.4.2.14 Test the Connectivity
To test the connectivity between BSC/MFS Evolution and EAB:
1. Connect the Ethernet cable from the Local PC to the JAXSSW1 port ETH 8in corresponding ATCA shelf.
2. Open a Telnet session on the active OMCP boardtelnet 172.17.y.x
where:
In case of MFS:
x is 3 for OMCP1
x is 4 for OMCP2
In case of BSC:
x is 30 for OMCP1
x is 40 for OMCP2
y is 3 for Shelf 3
y is 4 for Shelf 4
telnet 172.17.y.x
3. Type:
Username:root
Password:
alcatel
3BK 17422 3101 RJZZA Ed.08 31/ 34
-
8/11/2019 External Alarm Box n Installtion
32/34
-
8/11/2019 External Alarm Box n Installtion
33/34
2 External Alarm Box Installation and Commissioning
2.5 Finish Installation
To finish the installation:
1. Fit the labels to the EAB.
2. Write on the reserved area of the label the new IP address, if is the case.
3. Fix the cover.
4. Clear away packaging.
5. Clean the site. Do not put packages into the customer bin.
Figure 7: Clean the Site