extension of time (eot) & related costs in construction - presentation slides
TRANSCRIPT
![Page 1: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/1.jpg)
Extension of Time (EOT) and Related Costs in Construction
© www.asia-masters.com
![Page 2: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/2.jpg)
• Time is of Essence• Delays are inevitable on construction projects• The only project to have completed on time is a Mosque.
Divine intervention (or God’s help) was understood to be the force behind the timely completion of this Mosque.
• Time and Money go hand-in-hand. When projects get late, additional costs are incurred.
• This makes it imperative to take control of project delays; timely and effectively.
© www.asia-masters.com
![Page 3: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/3.jpg)
• Majority of construction projects worldwide are administered by the FIDIC forms of contract.
• FIDIC recognises delay and related costs and has provisions related thereto. For example;
Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition) Clauses 44 & 53 (FIDIC 1987 Edition)
FIDIC
FIDIC
FIDIC
FIDIC
FIDIC
© www.asia-masters.com
![Page 4: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/4.jpg)
The FIDIC Provisions define the conditions where delay may be claimed as the basis for an Extension of Time (EOT). Some examples are;
Late provision of design or drawings
Unforeseeable Physical Conditions encountered on
Site
Inclement Weather
Variations instructed by the Engineer (Additional
Works etc.)
© www.asia-masters.com
![Page 5: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/5.jpg)
Meanwhile the principles of how delay and related costs should be calculated are not defined by FIDIC. This leads to issues; issues which are usually contentious due to various 'schools of thoughts' and varied interpretations existing worldwide.
Disputes are the usual outcome.
© www.asia-masters.com
![Page 6: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/6.jpg)
Contentious Issues in Delay Analysis
resulting in Disputes– Critical Path– Who owns the Float?– Concurrent (or Contractor) Delays and how these
effect Entitlement– EOT and its relation with Compensation for Delay– Which is the best Method of Delay Analysis?
» As-Planned Vs. As-Built Comparison» Impacted As-Planned» Collapsed As-Built / But-For» Time Slice / Sub-Networks / Time-Impact» Etc.
© www.asia-masters.com
![Page 7: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/7.jpg)
In order to eliminate disputes or facilitate settlement of disputes, there are now certain standards used worldwide. The leading standards are;
Society of Construction Law’s Delay and Disruption Protocol (SCL
Protocol)
AACE 29R-03 (Forensic Schedule Analysis)© www.asia-masters.com
![Page 8: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/8.jpg)
The SCL Protocol was finalized in October
2002 after several years of deliberations and
considerable debate and agreement between
experts from different backgrounds
© www.asia-masters.com
![Page 9: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/9.jpg)
The objective of the SCL Protocol was to bring
reasonableness and fairness into the delay assessment process and to eliminate
widespread manipulation of complex delay issues
© www.asia-masters.com
![Page 10: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/10.jpg)
The SCL Protocol tried to standardize the issues such that disputes would be
reduced or eliminated
© www.asia-masters.com
![Page 11: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/11.jpg)
It is recommended that;
should be adopted as a Standard and should be,
where possible, incorporated in the
Construction Contracts© www.asia-masters.com
![Page 12: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/12.jpg)
The SCL Protocol can be downloaded from:
www.eotprotocol.com
© www.asia-masters.com
![Page 13: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/13.jpg)
The remaining slides of this lecture will review and discuss the basic
Principles suggested and recommended by theSCL Protocol
© www.asia-masters.com
![Page 14: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/14.jpg)
Basic Principles suggested and
recommended bythe SCL Protocol
© www.asia-masters.com
![Page 15: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/15.jpg)
The Principles suggested by the SCL Protocol are simple.
Some of the key principles suggested by the Protocol are;
© www.asia-masters.com
![Page 16: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/16.jpg)
RULE NO. 1If there is an Employer’s delay, which is beyond the Contractor’s control, and if this delay impacts the
Completion Date of the Works, the Contractor should be entitled to receive an Extension of Time (EOT).
[This will effectively result in an extended Time for Completion and will relieve the Contractor from
having to pay penalties for delay (or Delay Damages under FIDIC)]
© www.asia-masters.com
![Page 17: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/17.jpg)
RULE NO. 2For the case of recovery of delay (or prolongation) costs
incurred due to the Employer delays, the Contractor must be able to prove that there has been no other delay, which
is in his own control, and which is equally (or partly) contributing for delaying the Time for Completion.
This category of delay is called a ‘Concurrent’
(or Contractor’s) Delay [In order to win a Delay Costs Claim, the Contractor
must be able to prove that he has not been responsible for Concurrent Delays to the Time for
Completion]
© www.asia-masters.com
![Page 18: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/18.jpg)
RULE NO. 3
Where Contractor’s Delay to Completion occurs concurrently with Employer’s
Delay to Completion, the Contractor’s concurrent delay should NOT reduce
anyExtension of Time (EOT), which is due.
[Result of Rule No. 1 will not change and is irrespective of the result of Rule No. 2]
© www.asia-masters.com
![Page 19: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/19.jpg)
The foregoing Rules proposed by the SCL Protocol are meant to bring fairness and
reasonableness into the delay assessment process.
[The emphasis of the SCL Protocol is that no one Party should benefit from default of the
other Party]
© www.asia-masters.com
![Page 20: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/20.jpg)
The Illustrations demonstrating the principles of the SCL Protocol are contained in the
following Figures A to G
© www.asia-masters.com
![Page 21: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/21.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Path 1 Float = 3.5 Weeks
Path 2 Float = 5.5 Weeks
Path 2
Figure A - Accepted Contract Programme
Weeks
Path 1
Contract Start Date
Contract Completion Date
© www.asia-masters.com
![Page 22: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/22.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Excusable Delay
Path 1 Float = 1.0 Week
Path 2 Float = 5.5 Weeks
(a) 2.0 Weeks (a) 5.5 Weeks(b) 1.0 Weeks (b) 0 Weeks(c) 0 Weeks (c) 1.0 Weeks(d) 5.5 Weeks (d) 2.0 Weeks
(a) 2.0 Weeks (a) 0.1% of Contract Price(b) 1.0 Weeks (b) Direct Costs of Excusable Delay(c) 0 Weeks (c) NIL(d) 5.5 Weeks (d) (a) plus (b)
<=Date of Excusable Delay
Figure B - Delay Impact 1
Weeks
Path 1
Contract Start Date
Contract Completion Date
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Contract Completion Date
Impact on Path 1 = 2.0 Weeks
Path 2
Path 1
![Page 23: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/23.jpg)
Principles & Provisions of the SCL Protocol
relevant to Figure B
Core Principle No. 7 - Float as it relates to timeUnless there is express provision to the contrary in the contract, where there is remaining float in the programme at the time of an Employer Risk Event, an EOT should only be granted to the extent that the Employer Delay is predicted to reduce to below zero the total float on the activity paths affected by the Employer Delay.
Guidance Section 1.12.1 If as a result of an Employer Delay, the Contractor is prevented from completing the works by the Contractor’s planned completion date (being a date earlier than the contract completion date), the Contractor should in principle be entitled to be paid the costs directly caused by the Employer Delay, notwithstanding that there is no delay to the contract completion date (and therefore no entitlement to an EOT), provided also that at the time they enter into the contract, the Employer is aware of the Contractor’s intention to complete the works prior to the contract completion date, and that intention is realistic and achievable.
© www.asia-masters.com
![Page 24: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/24.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Excusable Delay
Float = -0.5 Week
(a) 0.5 Weeks (a) 5.5 Weeks(b) 3.5 Weeks (b) 0.5 Weeks(c) 0 Weeks (c) 3.5 Weeks(d) 5.5 Weeks (d) 0 Weeks
(a) 3.5 Weeks (a) 0.15% of Contract Price(b) 0.5 Weeks (b) Direct Costs of Excusable Delay(c) 0 Weeks (c) (a) plus (b)(d) 3.0 Weeks (d) NIL
Contract Completion Date
Impact on Path 1 = 3.5 Weeks
Path 2
Path 1
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
<=Date of Excusable Delay
Figure C - Delay Impact 2
Weeks
Path 1
Contract Start Date
Contract Completion Date
![Page 25: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/25.jpg)
Core Principle No. 4 - Procedure for granting extension of timeThe EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delayFor an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended.
Principles & Provisions of the SCL Protocol
relevant to Figure C
© www.asia-masters.com
![Page 26: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/26.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Float = -0.5 Week
Excusable DelayImpact on Path 2 = 6.0 Weeks
(a) 0 Weeks (a) 5.5 Weeks(b) 6.0 Weeks (b) 0 Weeks(c) 0.5 Weeks (c) 6.0 Weeks(d) 5.5 Weeks (d) 0.5 Weeks
(a) 3.5 Weeks (a) (d) minus (c)(b) 0.5 Weeks (b) Direct Costs of Excusable DelayNIL(c) 6.0 Weeks (c) Direct Costs of Excusable Delay(d) 3.0 Weeks (d) 0.2% of Contract Price
<=Date of Excusable Delay
Figure D - Delay Impact 3
Weeks
Path 1
Contract Start Date
Contract Completion Date
Path 2
Path 1
Contract Completion Date
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
![Page 27: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/27.jpg)
Core Principle No. 4 - Procedure for granting extension of timeThe EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delayFor an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended.
Principles & Provisions of the SCL Protocol
relevant to Figure D
© www.asia-masters.com
![Page 28: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/28.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Contract Completion Date
Float = -1.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Excusable DelayImpact on Path 1 = 2.0 Weeks
Float = -3.5 Weeks
(a) 3.5 Weeks (a) 2.0 Weeks(b) 2.0 Weeks (b) 0 Weeks(c) 1.5 Weeks (c) 3.5 Weeks(d) 0 Weeks (d) 1.5 Weeks
(a) 3.5 Weeks (a) (c) plus (d)(b) 2.0 Weeks (b) Direct Costs of Excusable DelayNIL(c) 3.0 Weeks (c) Direct Costs of Excusable Delay(d) 0 Weeks (d) 0.1% of Contract Price
Figure E - Delay Impact 4
Weeks
Path 1
Contract Start Date
<=Date of Excusable Delay
Path 2
Path 1
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
![Page 29: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/29.jpg)
Guidance Section 1.2.11 …an EOT should be granted to the extent that the Employer Risk Event is predicted to prevent the works being completed by the then prevailing contract completion date. This process requires consideration of the available float…
Guidance Section 1.4.12…Where there has been Employer Delay, this may prevent the Employer charging the Contractor with LDs for failure to achieve a contract completion date…
Principles & Provisions of the SCL Protocol
relevant to Figure E
© www.asia-masters.com
![Page 30: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/30.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
<=Date of Excusable Delay
Contract Completion Date
Float = -1.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Impact on Path 1 = 2.0 Weeks Excusable Delay
Float = -3.5 Weeks
(a) 2.0 Weeks (a) 0 Weeks(b) 3.5 Weeks (b) 2.0 Weeks(c) 1.5 Weeks (c) 3.5 Weeks(d) 0 Weeks (d) 1.5 Weeks
(a) 3.5 Weeks (a) (c) plus (d)(b) 2.0 Weeks (b) Direct Costs of Excusable DelayNIL(c) 3.0 Weeks (c) Direct Costs of Excusable Delay(d) 0 Weeks (d) 0.1% of Contract Price
Figure F - Delay Impact 5
Weeks
Path 1
Contract Start Date
Path 2
Path 1
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
![Page 31: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/31.jpg)
Guidance Section 1.4.8Where an Employer Risk Event occurs after the contract completion date, in a situation where failure to complete by the contract completion date has been caused by Contractor Delays, the principle set out in Section 1.4.7 above should apply, except where the Employer Risk Event is a non-compensable Employer Risk Event. In such an event, no EOT (or compensation) should be due. Where an EOT is due after the contract completion date, the Employer Risk Event does not exonerate the Contractor for all its delays prior to the Employer Risk Event occurring. The effect of the Employer Risk Event should be assessed as described above and any EOT found due should simply be added to the contract completion date.
Principles & Provisions of the SCL Protocol
relevant to Figure F
© www.asia-masters.com
![Page 32: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/32.jpg)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
<=Date of Excusable Delay
Contract Completion Date
Float = -1.5 Weeks
Path 2 Float = 2.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Float = -1.5 Weeks
Excusable Delay = 3.5 Weeks
(a) 2.5 Weeks (a) 0 Weeks(b) 3.5 Weeks (b) 2.5 Weeks(c) 1.0 Weeks (c) 3.5 Weeks(d) 1.5 Weeks (d) 1.5 Weeks
(a) 0 Weeks (a) (b) plus (d)(b) 2.0 Weeks (b) Direct Costs of Excusable Delay(c) 3.0 Weeks (c) NIL(d) 3.5 Weeks (d) 0.2% of Contract Price
Path 1
Path 2
(3) Compensation for Delay to Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Figure G - Delay Impact 6
Weeks
Path 1
Contract Start Date
Path 2
![Page 33: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/33.jpg)
Guidance Section 1.4.1Where Contractor Delay to Completion occurs concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due.
Guidance Section 1.4.7Where Employer Risk Events and Contractor Risk Events occur sequentially but have concurrent effects, here again any Contractor Delay should not reduce the amount of EOT due to the Contractor as a result of the Employer Delay.
Concurrency (Appendix A – Definations and Glossary)True concurrent delay is the occurrence of two or more delay events at the same time, one an Employer Risk Event, the other a Contractor Risk Event and the effects of which are felt at the same time. The term ‘concurrent delay’ is often used to describe the situation where two or more delay events arise at different times, but the effects of them are felt (in whole or in part) at the same time. To avoid confusion, this is more correctly termed the ‘concurrent effect’ of sequential delay events.
Principles & Provisions of the SCL Protocol
relevant to Figure G – Slide 1/2
© www.asia-masters.com
![Page 34: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/34.jpg)
Core Principle No. 9 - Concurrent delay – its effect on entitlement to extension of timeWhere Contractor Delay to Completion occurs or has effect concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due.
Core Principle No. 14 - Link between extension of time and compensationEntitlement to an EOT does not automatically lead to entitlement to compensation (and vice versa).
Core Principle No. 10 - Concurrent delay – its effect on entitlement to compensation for prolongationIf the Contractor incurs additional costs that are caused both by Employer Delay and concurrent Contractor Delay, then the Contractor should only recover compensation to the extent it is able to separately identify the additional costs caused by the Employer Delay from those caused by the Contractor Delay. If it would have incurred the additional costs in any event as a result of Contractor Delays, the Contractor will not be entitled to recover those additional costs.
Principles & Provisions of the SCL Protocol
relevant to Figure G – Slide 2/2
© www.asia-masters.com
![Page 35: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/35.jpg)
Guidance Section 3.2.13Although the programme should be the primary tool for guiding the CA in his determination of EOT, it should be used in conjunction with the contemporary evidence to ensure that the resulting EOT is fair and reasonable. It will also be necessary for the parties to apply common sense and experience to the process to ensure that all relevant factors are taken into account, and that any anomalous results generated by the programme analysis are managed properly.
Key Guideline, Suggestion and Advice of the SCL Protocol
© www.asia-masters.com
![Page 36: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/36.jpg)
Figure No. Question 1 Question 2 Question 3 Question 4B (c) (b) (a) (b)C (a) (b) (d) (b)D (c) (d) (d) (c)E (b) (a) (d) (c)F (a) (b) (d) (c)G (c) (a) (a) (b)
Correct Responses for Figures B to G
© www.asia-masters.com
![Page 37: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/37.jpg)
Congratulations we have come to the
end of the Lecture.You are now a Qualified and
Certified Delay Claims Analyst and
Expert.
© www.asia-masters.com
![Page 38: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/38.jpg)
FIDIC and Construction Solutionsthank you for your attendance and
contribution.
We wish you all Good Luck.
© www.asia-masters.com
![Page 39: Extension of Time (EOT) & Related Costs in Construction - Presentation Slides](https://reader030.vdocuments.site/reader030/viewer/2022032613/587067961a28ab48378b5421/html5/thumbnails/39.jpg)
THANK YOU!
© www.asia-masters.com