extension of a strategic environmental ......extension of a strategic environmental assessment to...
TRANSCRIPT
Contents
EXTENSION OF A STRATEGIC ENVIRONMENTAL ASSESSMENT TO FACILITATE THE EFFICIENT AND EFFECTIVE IMPLEMENTATION OF WIND AND SOLAR PHOTOVOLTAIC ENERGY DEVELOPMENT IN SOUTH AFRICA
Expert Reference Group and Project Steering Committee
Meeting
25 July 2017
Presented by: Abulele Adams (CSIR)
Tel: 021 888 2408 - Email: [email protected]
2
Presentation outline
• Wind and Solar SEA (Phase 2)
– Introduction • Updated project team and roles
• Multi Author teams
• Timeline and methodology
• Consultation
– Technical Considerations
– Environmental Considerations
– Socio economic Considerations
– Way Forward
3
Project Team and roles
DEA • Dee Fischer, Project
Director • Simon Moganetsi, Project
Coordinator
CSIR • Lydia Cape, Project
Leader • Abulele Adams,
Project Manager
Multi-authors Specialists team
Other key stakeholders eg. Mining, CAA, Defense, Heritage, etc.
SANBI
SEA process development
and implementation
Sensitivity mapping and
specialist studies
• Fahiema Daniels • Kedibone Lamula • Moore Malatji
CSIR: Built Environment
• Mawande Ngidi • Elsona Van Huyssteen
Conservation Working Group
Consultation and experts’ inputs
Industry Working Group
ERG PSC Public
4
Multi-authors specialists team
5
Strategic Issues for consideration
Bats
Birds
Ecology & conservation
• Terrestrial fauna & flora
• Freshwater
Socioeconomic
Heritage and Visual
• Palaeontology
• Archaeology
• Landscape and Flicker
Land Use & Built Environment
• Agriculture
• Mining
• SKA
• CAA
• Radar
• Noise
6
Timeline and methodology: delineation of first
draft focus areas
June-August 2017
7
Timeline and methodology: delineation of second
draft focus areas and multi-authors studies
15 August – 15 September (TBC)
September 2017 (TBC) October 2017 –
February 2018 (TBC)
8
Timeline and methodology: delineation of third
draft focus areas and consultation on REDZs
March 2018 (TBC) April-May 2018 (TBC) June 2018 (TBC)
9
Consultation
• Quarterly working group meetings with industry and
conservation organisations
• Quarterly meetings with ERG and PSC members
• Sector specific meetings with key stakeholders
• Two 30 days review & comments period for the public
and all stakeholders
• Online project website continuously updated and
accessible during the duration of the SEA
10
Technical Considerations
See separate presentation pdf attached
Presentation by Abulele Adams (CSIR) [email protected]
Mapping team: Lydia Cape, Abulele Adams, and Fahiema Daniels
with inputs from the Energy Centre of the CSIR
11
Environmental Considerations
See separate presentation pdf attached
Presentation by Kedibone Lamula (SANBI) [email protected]
Mapping team: Fahiema Daniels, Kedibone Lamula, Moore Malatji, Tsamaelo Malebu, Lydia Cape, and Abulele Adams
12
Socio economic Considerations
See separate presentation pdf attached
Presentation by: Mawande Ngidi (CSIR) [email protected]
Project Team: Mawande Ngidi, Elsona van Huyssteen,
Gerbrand Mans, Dave McKelly, and Sibu Makhanya
13
Way Forward
• ERG and PSC members are invited to provide inputs on :
Additional strategic issues for consideration;
References for the multi-authors specialists team;
Criteria/data to be used for the Technical Considerations;
Criteria/data to be used for the Environmental Considerations;
Criteria/data to be used for the Socio economic Considerations; and
SEA process methodology and consultation.
Please send your inputs to the SEA project manager: Abulele Adams, Tel: (021) 888 2408, Fax: (021) 888 2473
Emali: [email protected]
Project website: http://redzs.csir.co.za
Project email: [email protected]
Please send your inputs to the SEA project manager: Abulele Adams
Tel: (021) 888 2408 Fax: (021) 888 2473
Email: [email protected]
Thank you for your participation to this second ERG/PSC meeting on 25th July 2017