Expo Operations & Maintenance Facility
Operations and Maintenance FacilityPre-Construction Meeting
July 10, 2013
Expo Operations & Maintenance Facility
Meeting Purpose and Format
Project Status Update
Introduction of Construction Contractor
Overview of Construction Process and Timeline
Next Steps
Meeting Agenda
Pre-Construction Meeting
Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility
Project Milestones
Design Kick-Off
Summer 2011
Final Design CompletedFall 2012
ConstructionContract Awarded
Spring 2013
Start of ConstructionSummer 2013
Project Completion
Fall 2014
Status Update
Expo Operations & Maintenance Facility
Site Plan
Design
Expo Operations & Maintenance Facility Design
View from Exposition Boulevard
Expo Operations & Maintenance Facility
View from Stewart Street at Exposition Boulevard
Design
Expo Operations & Maintenance Facility
View from Stewart Street Crossing
Design
Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility
KIEWIT BUILDING GROUP (Builder)
• Kiewit ranked 3rd largest contractor in the nation and one of the largest in the world (per Engineering News Record)
• In business since 1884…over 129 years of experience• A national leader in vertical building as well as heavy civil design-build
transportation projects• Builder of Gold Line Extension and other Metro projects, as well as the
Dorothy Chandler Pavilion and other significant LA County projects
MAINTENANCE DESIGN GROUP (Designer)• Maintenance Design Group (MDG), and its architectural partner RNL, have
assembled a multi-disciplined group of design and engineering professionals with expertise in transit maintenance facilities
Construction Contractor
Construction
Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility
Construction Timeline
MAJOR CONSTRUCTION ELEMENTS
Summer 2013• Demolition• Site Excavation
Fall 2013• Continue Site Excavation• Site Utilities• Building Structural Foundations
Winter 2014• Steel Erection• Building Exterior• Building Interior Rough-in
Spring 2014• Rail Yard and Track Work• Building Finishes and Equipment
Summer 2014• Continue Rail Yard and Track Work• Continue Building Finishes and Equipment• Site Paving and Landscaping
Fall 2014• Continue Site Paving and Landscaping• Substantial Completion
Construction
Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility
Limits of Activity: Majority of construction activities are contained onsite, with the exception of a
few utility tie-ins that will take place along Stewart Street and Centinela Avenue
Field Office:Contractor will utilize an existing building for an onsite field office
Site Access and Parking: Construction staff will access the site off of Stewart Street and exit onto
Centinela Avenue, and employees will park onsite
Haul Routes: Haul routes will use major thoroughfares (Centinela, Olympic, Stewart) as
opposed to residential streets
Construction Work Hours: 8 a.m. to 6 p.m., Monday to Friday9 a.m. to 5 p.m., Saturday (if necessary)
Construction Overview
Construction
Expo Operations & Maintenance Facility Mitigation Measures
Noise Mitigation –• Monitor existing ambient noise• Implement site specific noise control plans• Manage noise generating activities and minimize equipment noise• Implement mitigation measures if noise produced by construction activity exceeds allowable limits (i.e. sound blankets)• Respond to noise complaints or concerns
Temporary Construction Fencing – Installation of 8’ tall perimeter fencing that will securely delineate the construction work areas and provide noise attenuation
Construction Mitigation Plans
Perimeter Fencing with Noise Attenuation
Expo Operations & Maintenance Facility Mitigation Measures
Dust Control – Watering trucks will be used regularly to mitigate dust
Storm Water Protection – Filter fabric/controls will be installed around drain inlets to prevent runoff
Watering Truck for Dust Control
Construction Mitigation Plans (cont.)
Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility
Distribute construction notices to project adjacent communities as the work progresses:
• Post on project website BuildExpo.org• Post on project social media sites Facebook and Twitter• Email to database of stakeholders and elected officials• Distribute door-to-door to within a ¼ mile radius of the construction
work zone• Provide to key project stakeholders as appropriate (i.e.
homeowners associations, etc.) for further dissemination
Construction Outreach
Construction Noticing
Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility Construction Outreach
Tom BeatyKiewit Building Group Community Relations ManagerTel: 310-694-6069Email: [email protected]
A 24-hour hotline is also available for all construction inquiries and emergencies: (213) 922-EXPO (3976)
• Team will respond to all construction inquiries as soon as possible and no later than 48 hours
• All emergencies will be addressed immediately
Community relations staff is available to respond to construction related issues:
Community Relations
Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility Opportunities
Local Jobs Program
Expo Board approved a Project Labor Agreement as part of the contract, which includes a Construction Careers component
30% of construction work hours to be performed by Community Residents who live in zip codes within a 5-mile radius of the Phase 2 alignment
10% of these hours will be performed by Disadvantaged Workers, such as those suffering from chronic unemployment and/or receiving public assistance
Expo Operations & Maintenance FacilityExpo Operations & Maintenance Facility
Secure the construction site with perimeter fencing
Begin building demolition and site prep work
Provide regular updates to stakeholder groups throughout construction
Next Steps
Next Steps
Expo Operations & Maintenance Facility Contacts
Project Website: www.BuildExpo.org
Sign-up on our homepage to be added to the project database and receive notices via email.
Project Hotline: 213-922-EXPO (3976)
www.Facebook.com/ExpoLine
www.Twitter.com/ExpoLine
Social Media:Email: [email protected]
Next Steps